KR101703820B1 - Manufacturing method of concrete-filled box girder using the type channel the concrete-filled box girder for the bridge by the same - Google Patents

Manufacturing method of concrete-filled box girder using the type channel the concrete-filled box girder for the bridge by the same Download PDF

Info

Publication number
KR101703820B1
KR101703820B1 KR1020160104029A KR20160104029A KR101703820B1 KR 101703820 B1 KR101703820 B1 KR 101703820B1 KR 1020160104029 A KR1020160104029 A KR 1020160104029A KR 20160104029 A KR20160104029 A KR 20160104029A KR 101703820 B1 KR101703820 B1 KR 101703820B1
Authority
KR
South Korea
Prior art keywords
concrete
channel
channels
pair
camber
Prior art date
Application number
KR1020160104029A
Other languages
Korean (ko)
Inventor
이경표
Original Assignee
이경표
(주) 이레기술개발
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이경표, (주) 이레기술개발 filed Critical 이경표
Priority to KR1020160104029A priority Critical patent/KR101703820B1/en
Application granted granted Critical
Publication of KR101703820B1 publication Critical patent/KR101703820B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a method of manufacturing a rectangular steel pipe girder, which has introduced pre-stress and has a closed rectangular cross-sectional area to enable a concrete material to be deposited therein; and a rectangular steel pipe girder for a bridge manufactured by the same. The rectangular steel pipe girder is sequentially manufactured comprising: (a) a step of preparing a C-shaped channel which has a bottom side, a pair of lateral sides bent from both sides of the bottom side, and ribs horizontally bent from the end portions of the lateral sides; (b) a step of installing a plurality of separation walls inside the C-shaped channel; (c) a step of forming the shape of a camber as both end portions or a center are sagged by weight of the concrete material by heating the C-shaped channel, and then depositing the concrete material inside the C-shaped channel; (d) a step of cooling the C-shaped channel to maintain the camber formed by sagging; and (e) a step of integrating a joining plate to a pair of the C-shaped channels by arranging two concrete sides to face each other and to be symmetrical while the joining plate is interposed between the C-shaped channel with the camber, and then welding the C-shaped channels and the joining plate while weight is imposed on an open portion.

Description

ㄷ채널을 이용한 콘크리트 충진 박스거더의 제작방법 및 이에 의해 제작된 교량용 콘크리트 충진 박스거더{MANUFACTURING METHOD OF CONCRETE-FILLED BOX GIRDER USING THE ㄷTYPE CHANNEL THE CONCRETE-FILLED BOX GIRDER FOR THE BRIDGE BY THE SAME}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of manufacturing a concrete box box girder using a c-channel, and a concrete box filler box girder constructed by the method.

본 발명은 교량의 상부구조를 이루는 거더에 관한 것으로서, 보다 구체적으로는 ㄷ채널을 이용하여 프리스트레스가 도입되고, 그 내부에 콘크리트가 타설될 수 있도록 폐쇄된 사각단면을 가지는 콘크리트 충진 박스거더의 제작방법 및 이에 의해 제작된 교량용 콘크리트 충진 박스거더에 관한 것이다.The present invention relates to a girder forming an upper structure of a bridge, and more particularly, to a method of manufacturing a concrete filled box girder having a rectangular cross section closed so that a prestress is introduced by using a channel, And a concrete fill box girder for a bridge manufactured by the method.

일반적으로 프리스트레스트 거더교라 함은 고강도 콘크리트 거더에 강연선을 삽입하고 이를 이용하여 긴장력을 도입시킨 거더를 상판콘크리트와 일체화시켜 형성되는 합성단면으로 작용하는 하중에 저항하는 형식의 교량을 말한다.In general, the term "prestressed girder bridge" refers to a type of bridge resisting load acting on a composite section formed by inserting a stranded wire into a high-strength concrete girder and incorporating a tensile force-induced girder with a top plate concrete.

그런데 최근 들어 건설부재들의 재질적인 특성과 함께 각 부재들의 형상적인 특징을 유기적으로 결합시켜 부재의 거동에 효율적으로 대응할 수 있는 다양한 복합구조가 개발되고 있으며, 그 중 대표적인 것으로 콘크리트 충진 강관(Concrete Filled Steel Tube, CFT)구조가 있다.Recently, a variety of composite structures capable of efficiently responding to the behavior of the members by organically combining the structural characteristics of the members together with the structural characteristics of the construction members have been developed. Typical examples thereof include a concrete filled steel pipe Tube, CFT) structure.

상기의 CFT구조는 강관의 내부에 콘크리트를 충진시킨 것으로서, 상기 콘크리트는 강관의 급격한 국부좌굴 변형을 억제하고, 상기 강관은 콘크리트를 구속시켜 허용압축응력을 초과하는 응력에 의해 갑작스럽게 터져나가는 것을 방지하여, 부재로 하여금 매우 높은 내력 및 내화성을 가지게 할 뿐 아니라, 탁원한 변형성능, 소음 및 진동억제 효과를 가지고 있다.The above-mentioned CFT structure is filled with concrete in a steel pipe. The concrete suppresses abrupt local buckling deformation of the steel pipe, and the steel pipe prevents concrete from being suddenly discharged due to stress exceeding the allowable compressive stress. So that the member has not only high strength and fire resistance but also excellent deformation performance, noise and vibration suppression effect.

따라서 CFT구조의 상기한 작용효과를 이용함과 더불어 프리스트레스를 도입시킴으로써 부재의 경량화 및 장스팬화를 도모하기 위한 시도가 지속적으로 이루어지고 있으며, 그 예의 하나로 등록특허공보 등록번호 10-1136926호의 프리스트레스 콘크리트 충진강관 합성보라는 명칭의 휨부재가 제안된 바 있다.Therefore, attempts have been made to reduce the weight and long span of members by introducing a prestress along with utilizing the above-mentioned action effect of the CFT structure. One example of this is the prestressed concrete filling of Registration No. 10-1136926 A member having a name of a steel tube composite structure has been proposed.

상기의 프리스트레스 콘크리트 충진강관 합성보는, 도 1에 도시된 바와 같이, 상부면에 콘크리트 충진구멍(111)이 형성된 박스형 강관(110); 상기 박스형 강관(110)의 양 마구리에 덧대어 설치된 엔드플레이트(120); 상기 박스형 강관(110)의 길이방향 중간에서 박스형 강관(110)의 너비방향으로 관통하게 설치된 관통지지봉(130); 상기 박스형 강관(110) 내부에서 박스형 강관(110)의 길이방향을 따라 관통지지봉(130) 아래 또는 위를 지나도록 배치되어 긴장 설치되되, 긴장으로 상기 관통지지봉(130)에서 절곡된 채 관통지지봉에 지지되면서 양단부가 상기 엔드플레이트(120)에 정착 설치된 제1강연선(141); 및, 상기 박스형 강관(110)의 콘크리트 충진구멍(111)을 통해 충진되어 제1강연선(141)을 매설시키는 충진콘크리트(150);로 이루어져 있다.As shown in FIG. 1, the composite of the prestressed concrete filled steel pipe includes a box-shaped steel pipe 110 having a concrete filling hole 111 formed on the upper surface thereof; An end plate 120 attached to both ends of the box-shaped steel pipe 110; A penetration support rod 130 installed to penetrate the box-shaped steel pipe 110 in the width direction of the box-shaped steel pipe 110 in the longitudinal direction of the box-shaped steel pipe 110; Shaped steel pipe 110 in the longitudinal direction of the box-shaped steel pipe 110 so as to pass under or over the penetrating support bar 130. The tension pipe 130 is bent in the through- A first strand 141 which is supported on both ends of the end plate 120 and is fixed to the end plate 120; And a filled concrete 150 filled through a concrete filling hole 111 of the box-shaped steel pipe 110 to fill the first strand 141.

그런데 앞서 설명한 CFT 구조의 콘크리트 구속효과는 강관 내부에 콘크리트가 밀실하게 충진되는 것을 전제로 하여 발휘되는 것인 바, 강관에 대한 콘크리트의 밀실충진 정도는 CFT 구조의 핵심이라고 할 수 있으나, 강관의 폐쇄된 단면 형상으로 인하여 콘크리트의 밀실한 충진이 그다지 용이하지 않다.However, the concrete confinement effect of the CFT structure described above is exerted on the assumption that the concrete is filled tightly in the steel pipe, and the degree of filling of the concrete with respect to the steel pipe is the core of the CFT structure. However, Due to the cross-sectional shape, the filling of the concrete is not easy.

따라서 일반적으로는 상기한 프리스트레스 콘크리트 충진강관 합성보에서 보여지는 바와 같이, 콘크리트를 충진시키기 위한 콘크리트 충진구멍(111)의 박스형 강관(110)에 다수 개 구비시켜 이를 통해 콘크리트를 충진시키고 있으나, 이는 강관의 단면손실과 함께 콘크리트 폐쇄면적을 감소시켜 그 기능을 저하시키게 하는 문제점이 있다.In general, as shown in the composite sheet of the prestressed concrete-filled steel pipe, a plurality of concrete-filled steel pipes 110 are filled with concrete through the concrete filling holes 111 for filling the concrete. There is a problem in that the function of the concrete is reduced due to the reduction of the area of the closed concrete with the cross-sectional loss.

또 CFT 강관구조에 대하여 상기한 종래기술에서와 같이 강선을 삽입하여 이를 긴장하는 방식의 프리스트레스 도입은 CFT구조의 형성과는 별도의 작업을 필요로 하는 것이어서, 작업의 공정 수를 증가시킬 뿐 아니라 강선의 배치 및 긴장작업의 번거로움으로 인하여 부재수 증가 및 공기가 늘어나게 되는 문제점이 있다.In addition, the introduction of the prestress in a manner of inserting and tightening the steel wire with respect to the CFT steel pipe structure as described above requires a separate work from the formation of the CFT structure, There is a problem that the number of members increases and the air increases.

KRKR 10-113692610-1136926 B1B1

본 발명은 종래기술의 상기한 문제점을 해결하기 위한 것으로서, 강관에 단면결손을 발생시키지 않으면서 필요한 부분에 대한 밀실한 콘크리트의 충진이 확실하게 이루어지고, 거더의 제작과정 중에 자연스럽게 프리스트레스가 도입되게 함으로써 프리스트레스 도입을 위한 별도의 부재 및 공정을 필요로 하지 아니하여 경제적이면서 제작시간을 단축시킬 수 있는 콘크리트 충진 박스거더의 제작방법와 이에 의해 제작된 교량용 사각강관거더를 제공함에 그 목적이 있다.Disclosure of the Invention The present invention has been made to solve the above problems of the prior art, and it is an object of the present invention to provide a steel pipe which can reliably fill tight concrete with a necessary portion without causing a short- It is an object of the present invention to provide a method for manufacturing a concrete filled box girder which is economical and can shorten a manufacturing time without requiring separate members and processes for introducing a prestress, and a rectangular steel girder for a bridge manufactured by the method.

상기한 과제를 해결하기 위한 본 발명의 가장 바람직한 실시예에 의하면, a) 바닥면과, 상기 바닥면의 양측에서 수직으로 절곡된 한 쌍의 측면 및, 상기 측면의 단부에서 수평으로 절곡된 리브가 형성된 ㄷ채널을 준비하는 단계; b) 상기 ㄷ채널의 내측에 다수 개의 격벽을 설치하는 단계; c) 상기 ㄷ채널을 가열한 후 내측에 콘크리트를 타설함으로써 상기 콘크리트의 자중에 의한 처짐이 ㄷ채널의 양단부 또는 중앙부에 발생되어 캠버의 형상이 형성되도록 하는 단계; d) 상기 처짐에 의해 형성된 캠버가 유지되도록 ㄷ채널을 냉각시키는 단계; e) 캠버가 형성된 한 쌍의 ㄷ채널이 연결판을 사이에 두고 콘크리트면이 서로 마주보도록 대칭으로 배치시킨 후, 벌려진 부분에 하중을 가한 상태에서 용접함으로써 한 쌍의 ㄷ채널과 연결판을 일체화시키는 단계;가 순차로 이루어지는 것을 특징으로 하는 ㄷ채널을 이용한 콘크리트 충진 박스거더의 제작방법이 제공된다.According to a most preferred embodiment of the present invention for solving the above-mentioned problems, there is provided a method of manufacturing a semiconductor device, comprising the steps of: a) forming a bottom surface, a pair of side surfaces bent at both sides of the bottom surface, Preparing a channel; b) providing a plurality of partitions on the inner side of the channel; c) heating the c-channel to pour concrete into the inside of the c-channel so that deflection due to the weight of the concrete is generated at both ends or a central portion of the c-channel to form a shape of the camber; d) cooling the channel to maintain the camber formed by the deflection; e) A pair of channels formed with a camber is disposed symmetrically with the concrete planes facing each other with the connecting plate therebetween, and then a pair of the channels and the connecting plate are integrated by welding while the load is applied to the expanded portion The method comprising the steps of: (a) providing a box-type concrete box girder having a plurality of channels;

이때, 상기 c)단계는 ㄷ채널을 가열한 상태에서 그 내측에 콘크리트를 타설하되, 캠버의 형상을 유도하기 위하여 중앙부에 1점지지를 형성시킬 수도 있고 양 단부에 2점지지를 형성시킬 수도 있으며, 이러한 지지점을 ㄷ채널의 가열 전에 형성시킬 수도 있고 콘크리트가 타설된 후에 형성시킬 수도 있다.At this time, in the step c), the concrete is poured into the inside of the c-channel while heating the c-channel, and a one-point support may be formed at the center part to induce the shape of the camber, , This support point may be formed before the heating of the c-channel, or may be formed after the concrete is poured.

또 상기 콘크리트는 ㄷ채널의 전 구간에 대하여 타설할 수도 있고 단면의 보강구간에 대하여만 타설할 수도 있다.Also, the concrete may be laid over the whole section of the c-channel, or may be laid only against the reinforcing section of the section.

본 발명은 ㄷ채널에 대한 충진상태를 육안으로 확인하면서 콘크리트를 타설할 수 있기 때문에 밀실한 콘크리트의 충진과 함께 강관에 대한 단면결손을 발생시키기 않기 때문에 고품질의 CFT구조를 가진 콘크리트 충진 박스거더를 기대할 수 있게 한다.Since the concrete can be poured while visually checking the filling state for the c channel, the concrete filling box girder having a high-quality CFT structure can be expected I will.

또한 본 발명은 열처리를 이용함으로써 콘크리트의 자중만으로도 ㄷ채널에 캠버를 용이하게 형성시킬 수 있을 뿐 아니라, 지지점의 형성 위치 및 그 높이를 조절함으로써 다양한 방향에 대한 프리스트레스의 도입을 가능하게 하여 하중의 크기 및 종류에 적절하게 대응할 수 있게 한다Further, by using the heat treatment, the present invention can easily form the camber on the C-channel only by using the self-weight of the concrete, and it is possible to introduce the prestress into various directions by adjusting the position and height of the support point, And the type of the material

도 1은 종래기술에 의한 프리스트레스 콘크리트 충진강관 합성보의 사시도 및 단면도이다.
도 2는 본 발명의 일 실시예의 제작방법에 의해 제작된 콘크리트 충진 박스거더의 사시도이다.
도 3은 상기 콘크리트 충진 박스거더에 관한 각 실시예에 단면도이다.
도 4는 상기 콘크리트 충진 박스거더를 제작하는 과정에 대하여 각 단계별로 도시한 개략 사시도이다.
도 5 내지 10은 ㄷ채널에 대하여 캠버의 형상을 유도하기 위한 방법의 다양한 실시예를 도시한 개략 사시도이다.
도 11, 12는 본 발명의 콘크리트 충진 박스거더가 제작되는 과정 중에 프리스트레스가 도입되는 과정의 각 실시예를 도시한 개략 사시도이다.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view and a cross-sectional view of a composite structure of a prestressed concrete-filled steel pipe according to the prior art.
2 is a perspective view of a concrete filling box girder fabricated by a manufacturing method of an embodiment of the present invention.
3 is a cross-sectional view of each concrete filling box girder.
FIG. 4 is a schematic perspective view illustrating the concrete filling box girder according to each step.
5 to 10 are schematic perspective views showing various embodiments of a method for deriving a shape of a camber with respect to a channel.
FIGS. 11 and 12 are schematic perspective views showing respective embodiments of a process of introducing a prestress during the process of manufacturing a concrete-filled box girder of the present invention.

이하에서는 본 발명의 실시 예를 첨부된 도면을 참조하여 상세히 설명한다. 그러나 본 발명을 설명함에 있어 공지의 구성을 구체적으로 설명함으로 인하여 본 발명의 기술적 사상을 흐리게 하거나 불명료하게 하는 경우에는 위 공지의 구성에 관한 설명을 생략하기로 한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. However, in order to obscure or obscure the technical idea of the present invention due to the detailed description of the known structure in describing the present invention, the description of the structure of the above known structure will be omitted.

도 2는 본 발명의 일 실시예의 제작방법에 의해 제작된 콘크리트 충진 박스거더의 사시도이고, 도 3은 상기 콘크리트 충진 박스거더에 관한 각 실시예에 단면을 도 2에 대응하여 도시한 것이다.FIG. 2 is a perspective view of a concrete filling box girder manufactured by the manufacturing method of one embodiment of the present invention, and FIG. 3 is a sectional view corresponding to FIG. 2 of each embodiment of the concrete filling box girder.

본 발명에 의한 콘크리트 충진 박스거더(이하 '본 발명의 거더'라 함)는, 콘크리트(30)가 충진되는 사각 강관에 단면결손을 발생시키지 않으면서 육안에 의한 콘크리트(30)의 밀실한 충진상태를 확인할 수 있어 고품질의 CFT구조를 가지게 할 뿐 아니라, 열처리와 자중을 이용하여 프리스트레스가 도입될 수 있게 한다.The concrete filling box girder according to the present invention (hereinafter, referred to as 'the girder of the present invention') is a concrete filled box girder according to the present invention in which the concrete 30 is filled in a tight filling state So that not only a high-quality CFT structure can be obtained but also a prestress can be introduced by heat treatment and self weight.

이러한 본 발명의 거더는, 연결판(40)을 사이에 두고 콘크리트(30)가 충진된 한 쌍의 ㄷ채널(10)이 대칭으로 용접 부착되어 일체화된 구조를 가진다.The girder according to the present invention has a structure in which a pair of c-channels 10 filled with concrete 30 with a connecting plate 40 therebetween are integrally welded symmetrically.

상기 연결판(40)은, 상기와 같이 한 쌍의 ㄷ채널(10)을 일체화시키는 연결부재로써의 기능을 할 뿐 아니라, ㄷ채널(10)의 개방면을 폐쇄시켜 ㄷ채널(10) 내의 콘크리트(30)를 구속시키고, 더 나아가 일체화되지 못한 두 ㄷ채널(10)의 콘크리트(30)면에 대한 보강기능을 한다.The connecting plate 40 functions not only as a connecting member for integrating the pair of the channels 10 as described above but also to open and close the openings of the channels 10, (30), and further reinforces the two channels (10), which are not integrated, with respect to the concrete (30) surface.

이때 상기 한 쌍의 ㄷ채널(10)은 도 3의 (a)에서와 같이 상하부에 위치한 ㄷ채널(10)의 모두를 전 구간에 대하여 콘크리트(30)가 충진되는 구조를 가질 수도 있고, 도 3의 (b)에서와 같이 어느 하나는 전 구간에 대하여 콘크리트(30)가 충진되고, 나머지 하나에는 양 단부 또는 중앙부의 보강구간에 대하여만 충진되게 하는 것으로, 예컨대 하부에 위치한 ㄷ채널(10)에 대하여는 전 구간에 콘크리트(30)를 충진시키고, 상부에 위치한 ㄷ채널(10)에 대하여는 보강구간, 즉 라멘구조에서 양 단부에 발생하는 부모멘트 구간에 대하여만 콘크리트(30)를 충진시키거나 단순거치구조에서 중앙부에 발생하는 정모멘트 구간에 대하여만 콘크리트(30)를 충진시킬 수 있으며, 도 3의 c)에서와 같이 상하부에 위치한 ㄷ채널(10)의 모두를 양단부 또는 중앙부의 에 대하여만 콘크리트(30)가 충진되게 할 수도 있다.3 (a), the pair of the channels 10 may have a structure in which all of the upper and lower channels 10 are filled with the concrete 30 over the entire section, As shown in (b) of FIG. 1, one of them is filled with the concrete 30 over the entire section, and the other one is filled only with the reinforcing sections at both ends or the center. For example, The concrete 30 is filled in the entire section and the concrete 30 is filled only in the reinforcement section, that is, the section of the moment occurring at both ends in the frame structure, or the simple installation It is possible to fill the concrete 30 only with respect to the section of the moment that occurs in the center portion of the structure, and all of the upper and lower channels 10, as shown in FIG. 3C, (30) to be filled.

도 4는 이러한 본 발명의 거더를 제작하는 과정에 대하여 각 단계별로 도시한 것으로서, a) ㄷ채널(10)의 준비단계; b) 격벽(20)의 설치단계; c) ㄷ채널(10)의 가열, 콘크리트(30) 타설 및, 지지점(0) 형성단계; d) ㄷ채널(10)의 냉각단계; e) ㄷ채널(10)의 일체화 단계;가 순차로 이루어지는 것으로 구성된다. 이하에서 각 단계에 관하여 구체적으로 설명한다.FIG. 4 is a cross-sectional view of the process for fabricating the girder according to the present invention, including the steps of: a) preparing the channel 10; b) installing the partition 20; c) heating the c channel 10, pouring the concrete 30, and forming a fulcrum 0; d) cooling of the channel (10); e) an integration step of the channel 10; Each step will be described in detail below.

a) ㄷ채널a) channel (10)의(10) 준비단계{도 4의 (a)}; Preparation step {Fig. 4 (a)};

바닥면(11)과, 상기 바닥면(11)의 양측에서 수직으로 절곡된 한 쌍의 측면(12) 및, 상기 측면(12)의 단부에서 수평으로 절곡된 리브(13)가 형성된 ㄷ채널(10)을 준비한다.(11), a pair of side walls (12) bent at both sides of the bottom surface (11), and ribs (13) bent horizontally at the ends of the side walls 10) is prepared.

상기 ㄷ채널(10)은 소정의 두께를 가지는 강판을 절곡하여 구성되는 것으로서, 본 발명의 거더는 이러한 ㄷ채널(10)의 한 쌍이 연결판(40)에 일체화는 것인 바, 적어도 2개의 ㄷ채널(10)과 함께 연결판(40)을 준비한다.The c channel 10 is formed by bending a steel plate having a predetermined thickness. In the girder of the present invention, a pair of the c channels 10 are integrated with the connecting plate 40, The connecting plate 40 is prepared together with the channel 10.

b) 격벽(20)의 설치단계{도 4의 (b)};b) the step of installing the partition 20 (Fig. 4 (b)};

ㄷ채널(10)의 내측에 다수 개의 격벽(20)을 설치한다.And a plurality of partition walls 20 are provided on the inner side of the channel 10.

상기 격벽(20)은 제작되어진 본 발명의 거더에 작용하는 수직하중에 대한 전단응력을 향상시키고, 비틀림에 대한 저항능력을 향상시킬 뿐 아니라, 도 3의 (b)(c)에 도시된 바와 같이 보강구간의 일부에 대하여만 콘크리트(30)를 충진시킬 때 이에 대한 거푸집의 기능을 함으로써 콘크리트(30) 충진의 시공성을 향상시킨다.The partition wall 20 improves the shear stress with respect to the vertical load acting on the manufactured girder of the present invention and improves the resistance against torsion. In addition, as shown in FIGS. 3B and 3C, When the concrete 30 is filled only with respect to a part of the reinforcing section, the workability of filling the concrete 30 is improved by functioning as a mold for the concrete 30.

c) ㄷ채널c) channel (10)의(10) 가열, 콘크리트(30) 타설 및, 지지점(0) 형성단계{도 4의 (c)}; Heating, pouring concrete 30, and forming a fulcrum 0 (Fig. 4 (c));

본 단계는 열처리와 자중 및 지지점(0) 형성을 이용하여 콘크리트(30)가 충진된 ㄷ채널(10)에 대하여 캠버(△)의 형상으로 변형을 유도하는 단계이다.This step is a step of inducing deformation to the shape of the camber (?) With respect to the c-channel (10) filled with the concrete (30) by using heat treatment, self weight and formation of the supporting point (0).

먼저 전기에너지를 이용한 고주파 열처리 등의 방법을 이용하여 ㄷ채널(10)을 가열함으로써 상기 ㄷ채널(10)의 소성변형이 용이하게 이루어질 수 있게 한다.The first channel 10 is heated by using a method such as high frequency heat treatment using electrical energy so that the plastic deformation of the channel 10 can be easily performed.

이와 같이 가열된 된 상태에서 도 3의 (a) 내지 (c)에 도시된 것처럼 ㄷ채널(10)의 내측에 콘크리트(30)를 타설하여 상기 콘크리트(30)의 자중에 의해 ㄷ채널(10)의 양 단부 또는 중앙부에 처짐이 발생되도록 함으로써, 상기 ㄷ채널(10)은 캠버(△)의 형상으로 변형된다.3 (a) to 3 (c), the concrete 30 is placed inside the c-channel 10, and the c-channel 10 is pushed by the weight of the concrete 30, So that the channel 10 is deformed into the shape of a camber (DELTA).

도 5 내지 10은 본 단계를 위한 세부공정의 각 실시예를 도시한 것이다.Figures 5 to 10 illustrate each embodiment of the detailed process for this step.

도 5에 도시된 제1실시예는, ⅰ) 작업베드(B) 위에 ㄷ채널(10)을 거치시키는 단계, ⅱ) ㄷ채널(10)을 가열하는 단계, ⅲ) ㄷ채널(10)의 내측에 콘크리트(30)를 타설하는 단계, ⅳ) 콘크리트(30)가 타설된 ㄷ채널(10)의 중앙부만을 상승시킨 1점지지를 형성시키는 단계가 순차로 진행된다.The first embodiment shown in Fig. 5 comprises the steps of: i) mounting the channel 10 on the working bed B, ii) heating the channel 10, iii) , And iv) forming a one-point support by lifting only the central portion of the c-channel (10) in which the concrete (30) is placed.

도 6에 도시된 제2실시예는, ⅰ) 작업베드(B) 위에 ㄷ채널(10)을 거치시키는 단계; ⅱ) ㄷ채널(10)을 가열하는 단계; ⅲ) ㄷ채널(10)의 중앙부만을 상승시킨 1점지지를 형성시키는 단계; ⅳ) ㄷ채널(10)의 내측에 콘크리트(30)를 타설하는 단계;가 순차로 진행된다.The second embodiment shown in Fig. 6 comprises the steps of: i) mounting a C-channel 10 on a work bed B; Ii) heating the channel (10); Iii) forming a one-point support with only the central portion of the channel 10 elevated; Iv) placing the concrete 30 inside the channel 10, and so on.

도 7에 도시된 제3실시예는, ⅰ) 작업베드(B) 위에 ㄷ채널(10)을 거치시키는 단계, ⅱ) ㄷ채널(10)의 중앙부만을 상승시킨 1점지지를 형성시키는 단계; ⅲ) ㄷ채널(10)을 가열하는 단계; ⅳ) ㄷ채널(10)의 내측에 콘크리트(30)를 타설하는 단계;가 순차로 진행된다.The third embodiment shown in Fig. 7 comprises the steps of: i) mounting a C-channel 10 on a work bed B; ii) forming a one-point support with only the center of the C-channel 10 elevated; Iii) heating the channel (10); Iv) placing the concrete 30 inside the channel 10, and so on.

상기한 제1 내지 3실시예는 ㄷ채널(10)의 개방면, 즉 콘크리트(30)의 노출면(D)이 볼록한 외면을 형성하게 된다. 이에 반하여 다음의 제4 내지 6실시예는 ㄷ채널(10)의 바닥면(11)이 볼록한 외면을 형성하게 된다.In the first to third embodiments, the open surface of the channel 10, that is, the exposed surface D of the concrete 30, forms a convex outer surface. On the contrary, in the following fourth to sixth embodiments, the bottom surface 11 of the channel 10 forms a convex outer surface.

도 8에 도시된 제4실시예는, ⅰ) 작업베드(B) 위에 ㄷ채널(10)을 거치시키는 단계; ⅱ) ㄷ채널(10)을 가열하는 단계; ⅲ) ㄷ채널(10)의 내측에 콘크리트(30)를 타설하는 단계; ⅳ) 콘크리트(30)가 타설된 ㄷ채널(10)의 양 단부를 상승시킨 2점지지를 형성시키는 단계;가 순차로 진행된다.The fourth embodiment shown in Fig. 8 comprises the steps of: i) mounting a C-channel 10 on a work bed B; Ii) heating the channel (10); Iii) casting concrete 30 on the inside of the channel 10; Iv) forming a two-point support by raising both ends of the c-channel 10 in which the concrete 30 is installed;

도 9에 도시된 제5실시예는, ⅰ) 작업베드(B) 위에 ㄷ채널(10)을 거치시키는 단계; ⅱ) ㄷ채널(10)을 가열하는 단계; ⅲ) ㄷ채널(10)의 양 단부를 상승시킨 2점지지를 형성시키는 단계; ⅳ) ㄷ채널(10)의 내측에 콘크리트(30)를 타설하는 단계;가 순차로 진행된다.The fifth embodiment shown in Fig. 9 comprises: i) mounting a C-channel 10 on a work bed B; Ii) heating the channel (10); Iii) forming a two-point support with both ends of the channel 10 raised; Iv) placing the concrete 30 inside the channel 10, and so on.

도 10에 도시된 제6실시예는, ⅰ) 작업베드(B) 위에 ㄷ채널(10)을 거치시키는 단계, ⅱ) ㄷ채널(10)의 양 단부를 상승시킨 2점지지를 형성시키는 단계; ⅲ) ㄷ채널(10)을 가열하는 단계; ⅳ) ㄷ채널(10)의 내측에 콘크리트(30)를 타설하는 단계;가 순차로 진행된다.The sixth embodiment shown in Fig. 10 comprises the steps of: i) mounting a c-channel 10 on a working bed B, ii) forming a two-point support with raised both ends of the c-channel 10; Iii) heating the channel (10); Iv) placing the concrete 30 inside the channel 10, and so on.

d) ㄷ채널d) channel (10)의(10) 냉각단계{도 4의 (d)}; Cooling step {Fig. 4 (d)};

열에 의해 소성변형된 ㄷ채널(10)은 하중이 작용하는 방향에 따라 원상회복되거나 요구되지 아니한 방향으로의 변형이 발생할 수 있는 바, 본 단계는 c) 단계에 의해 처짐이 발생됨으로써 중앙부가 볼록하게 또는 오목하게 형성된 캠버(△)가 작업과정 중에 다시 소성변형으로 복원되지 않고 그 형상을 유지하여, 향후 작용되는 하중에 대하여는 탄성변형을 가질 수 있도록 가열되었던 ㄷ채널(10)을 냉각시킨다.The channel (10) plastically deformed by heat may be restored to the original state or deformed in an undesired direction depending on the direction in which the load is applied. In this step, since the deflection is generated by the step c) Or the recessed camber (?) Is not restored to the plastic deformation again during the working process, but keeps its shape and cools the heated c-channel (10) so as to have elastic deformation with respect to the load to be applied.

e) ㄷ채널e) channel (10)의(10) 일체화 단계{도 4의 (e)}; Integration step (FIG. 4 (e));

내부에 콘크리트(30)가 충진된 상태로 캠버(△)가 형성된 ㄷ채널(10)이 완성되면, 이러한 ㄷ채널(10)의 한 쌍을 연결판(40)의 양측에 용접으로 일체화시킴으로써 프리스트레스가 도입된 본 발명의 거더가 제작된다.When the c channel 10 formed with the concrete 30 filled therein is completed, a pair of the c channels 10 is welded to both sides of the connection plate 40, The girder of the present invention is manufactured.

즉 도 11, 12에 도시된 바와 같이, 한 쌍의 ㄷ채널(10)이 각 콘트리트 노출면(D)이 서로 마주보도록 연결판(40)을 사이에 두고 대칭으로 배치시키게 되면, ㄷ채널(10)의 양단부 또는 중앙부가 벌려지게 되는 바, 상기와 같이 벌려진 부분에 하중을 가하여 각 ㄷ채널(10)과 연결판(40)이 함께 일직선이 되도록 한 상태에서 이들 각 부재들 사이를 용접으로 일체화시키고 가하고 있던 상기 하중을 제거함으로써 거더에 프리스트레스가 도입되도록 한다.As shown in FIGS. 11 and 12, when a pair of the channels 10 are symmetrically arranged with the connecting plate 40 interposed therebetween so that the respective concrete exposure surfaces D face each other, A load is applied to the open portion so that the respective channels 10 and the connecting plate 40 are aligned with each other, and these members are welded together by welding The load is removed so that the prestress is introduced into the girder.

이를 보다 구체적으로 설명하면, 도 11에 도시된 일 실시예에서는 본 단계에서 연결판(40)을 사이에 둔 한 쌍의 ㄷ채널(10)을 각 중앙부가 연결판(40)에 대칭이 되도록 배치하고, 이에 의해 벌려진 양 단부에 하중을 가하여 이들 각 부재들을 일체화시킴으로써 프리스트레스가 도입된 본 발명의 거더가 제작 완성된다. 이렇게 하여 제작된 본 발명의 거더는 연속교에서 구조적으로 매우 유리하게 작용된다.11, in this embodiment, a pair of the channels 10 having the connecting plate 40 interposed therebetween is arranged so that each center portion is symmetrical with respect to the connecting plate 40 And a load is applied to both ends of the wedge so as to integrate these members so that a girder according to the present invention in which a prestress is introduced is completed. The girder of the present invention manufactured in this way functions structurally very advantageously in the continuous bridge.

이러한 도 11의 실시예는 c)단계에서의 ㄷ채널(10)의 캠버(△)형성을 위한 각 실시예 중 제1 내지 3실시예가 이에 유효하게 적용된다.The embodiment of FIG. 11 is effectively applied to the first to third embodiments of each embodiment for forming the camber (DELTA) of the c-channel 10 in the step c).

또 도 12에 도시된 타 실시예에서는 본 단계에서 연결판(40)을 사이에 둔 한 쌍의 ㄷ채널(10)을 각 양단부가 연결판(40)에 대칭이 되도록 배치하고, 이에 의해 벌려진 중앙부에 하중을 가하여 이들 각 부재들을 일체화시킴으로써 프리스트레스가 도입된 본 발명의 거더가 제작 완성된다. 이렇게 하여 제작된 본 발명의 거더는 단순교에서 구조적으로 매우 유리하게 작용된다.In the other embodiment shown in FIG. 12, a pair of the channels 10 having the connecting plate 40 interposed therebetween is disposed so that the opposite ends thereof are symmetrical with respect to the connecting plate 40, So that the girders of the present invention having the prestress introduced therein can be manufactured. The girder of the present invention manufactured in this way is structurally very advantageous in a simple bridge.

이러한 도 12의 실시예는 c)단계에서의 ㄷ채널(10)의 캠버(△)형성을 위한 각 실시예 중 제4 내지 6실시예가 이에 유효하게 적용된다.The embodiment of FIG. 12 is effectively applied to the fourth to sixth embodiments of each embodiment for forming the camber (DELTA) of the c-channel 10 in the step c).

이와 같이 본 발명의 거더는 연결판(40)을 중심으로 캠버(△)가 형성된 한 쌍의 ㄷ채널(10)에 탄성변형을 줌으로써 프리스트레스가 도입되도록 하는 것이나, 상기 한 쌍의 ㄷ채널(10) 각각에 대하여 캠버(△)의 정도를 달리하게 함으로써 교량의 상부하중의 크기에 적절하게 대응할 수 있게 한다.As described above, the girder of the present invention has a structure in which the prestress is introduced by elastically deforming a pair of the channels 10 formed with the camber (?) Around the connecting plate 40, By varying the degree of camber (DELTA) with respect to each of them, it is possible to appropriately cope with the size of the upper load of the bridge.

이상에서 본 발명은 구체적인 실시 예를 참조하여 상세히 설명하였으나, 상기 실시 예는 본 발명을 이해하기 쉽도록 하기 위한 예시에 불과한 것이므로, 이 분야에서 통상의 지식을 가진 자라면 본 발명의 기술적 사상의 범위 내에서 이를 다양하게 변형하여 실시할 수 있을 것임은 자명한 것이다. 따라서 그러한 변형 예들은 청구범위에 기재된 바에 의해 본 발명의 권리범위에 속한다고 할 것이다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the scope of the invention is not limited to the disclosed embodiments, but, on the contrary, It is obvious that it will be possible to carry out various modifications thereof. It is therefore intended that such modifications are within the scope of the invention as set forth in the claims.

10; ㄷ채널 11; 바닥면
12; 측면 13; 리브
20; 격벽 30; 콘크리트
40; 연결판
10; Channel 11; Bottom surface
12; Side 13; live
20; A partition wall 30; concrete
40; Connecting plate

Claims (13)

교량용 거더를 제작함에 있어서,
a) 바닥면(11)과, 상기 바닥면(11)의 양측에서 수직으로 절곡된 한 쌍의 측면(12) 및, 상기 측면(12)의 단부에서 수평으로 절곡된 리브(13)가 형성된 2개의 ㄷ채널(10)과; 상기 2개의 ㄷ채널(10)을 일체화시키기 위한 연결판(40)을 준비하는 단계;
b) 상기 ㄷ채널(10)의 내측에 다수 개의 격벽(20)을 설치하는 단계;
c) 작업베드(B) 위에 상기의 격벽(20)이 설치된 ㄷ채널(10)을 거치시킨 상태에서 상기 ㄷ채널(10)을 가열한 후, 상기 가열된 ㄷ채널(10)의 중앙부만을 상승시킨 1점지지를 형성시키고, 상기 ㄷ채널(10)의 내측에 콘크리트(30)를 타설하여 ㄷ채널(10)의 양단부에 처짐이 발생되어 캠버(△)의 형상이 형성되도록 하는 단계;
d) 상기 처짐에 의해 형성된 캠버(△)가 유지되도록 ㄷ채널(10)을 냉각시키는 단계;
e) 연결판(40)을 사이에 두고 각 콘크리트 노출면(D)이 서로 마주보면서 각 중앙부가 상기 연결판(40)에 접하도록 캠버(△)가 형성된 한 쌍의 ㄷ채널(10)을 대칭으로 배치시킨 후, 벌어진 상기 ㄷ채널(10)의 양 단부에 하중을 가한 상태에서 한 쌍의 ㄷ채널(10)과 연결판(40)을 용접으로 일체화시키는 단계;가 순차로 이루어지는 것을 특징으로 하는 ㄷ채널을 이용한 콘크리트 충진 박스거더의 제작방법.
In making the girder for bridges,
a) a bottom surface 11, a pair of side surfaces 12 bent at both sides of the bottom surface 11, and ribs 13 horizontally bent at the end of the side surface 12, Channels (10); Preparing a connection plate (40) for integrating the two channels (10);
b) installing a plurality of partitions (20) inside the channel (10);
c) heating the c-channel (10) in a state where the c-channel (10) provided with the partition (20) is mounted on the working bed (B) and then raising only the central portion of the heated c- Forming a one point support and placing concrete 30 on the inside of the C channel 10 so that deflection occurs at both ends of the C channel 10 to form the shape of the camber?
d) cooling the c-channel (10) so that the camber (?) formed by the deflection is retained;
e) A pair of c-channels (10) formed with a camber (?) so that each of the concrete exposed surfaces (D) face each other with the connecting plate (40) And a step of integrating a pair of the channels 10 and the connecting plate 40 by welding in a state where a load is applied to both ends of the opened channel 10, A Method of Making Concrete Filled Box Girders Using.
삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 제1항에 있어서, 상기 e)단계에서 연결판(40)을 사이에 두고 일체화되는 한 쌍의 ㄷ채널(10)은 모두 c) 단계에서의 콘크리트(30) 타설시 ㄷ채널(10)의 전 구간에 대하여 콘크리트(30)가 타설되는 것을 특징으로 하는 ㄷ채널을 이용한 콘크리트 충진 박스거더의 제작방법.The method as claimed in claim 1, wherein a pair of the channels (10) integrated with the connecting plate (40) in the step (e) And the concrete 30 is poured into the section of the concrete filling box girder. 제1항에 있어서, 상기 e)단계에서 연결판(40)을 사이에 두고 일체화되는 한 쌍의 ㄷ채널(10) 중, 어느 하나는 c)단계에서의 콘크리트(30) 타설시 전 구간에 대하여 콘크리트(30)가 타설되고, 나머지 하나에는 양 단부 또는 중앙부의 보강구간에 대하여만 콘크리트(30)가 타설되는 것을 특징으로 하는 ㄷ채널을 이용한 콘크리트 충진 박스거더의 제작방법.The method as claimed in claim 1, wherein, in step (e), any one of the pair of the channels (10) integrated with the connecting plate (40) The concrete 30 is laid and the other one of the concrete 30 is laid only on the reinforcing sections of both ends or the center part. 제1항에 있어서, 상기 e)단계에서 연결판(40)을 사이에 두고 일체화되는 한 쌍의 ㄷ채널(10)은 모두 c) 단계에서의 콘크리트(30) 타설시 ㄷ채널(10)의 양 단부 또는 중앙부의 보강구간에 대하여만 콘크리트(30)가 타설되는 것을 특징으로 하는 ㄷ채널을 이용한 콘크리트 충진 박스거더의 제작방법.The method as claimed in claim 1, wherein the pair of the channels (10) integrated with the connecting plate (40) in the step (e) And the concrete 30 is installed only in the reinforcing section of the end portion or the center portion of the concrete filling box girder. 삭제delete 삭제delete 제1항의 제작방법에 의해 제작된 교량용 콘크리트 충진 박스거더.A concrete box filler box girder constructed by the method of claim 1.
KR1020160104029A 2016-08-17 2016-08-17 Manufacturing method of concrete-filled box girder using the type channel the concrete-filled box girder for the bridge by the same KR101703820B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160104029A KR101703820B1 (en) 2016-08-17 2016-08-17 Manufacturing method of concrete-filled box girder using the type channel the concrete-filled box girder for the bridge by the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160104029A KR101703820B1 (en) 2016-08-17 2016-08-17 Manufacturing method of concrete-filled box girder using the type channel the concrete-filled box girder for the bridge by the same

Publications (1)

Publication Number Publication Date
KR101703820B1 true KR101703820B1 (en) 2017-02-08

Family

ID=58155331

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160104029A KR101703820B1 (en) 2016-08-17 2016-08-17 Manufacturing method of concrete-filled box girder using the type channel the concrete-filled box girder for the bridge by the same

Country Status (1)

Country Link
KR (1) KR101703820B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107663833A (en) * 2017-10-26 2018-02-06 北京科技大学 A kind of the water cooling constructing device and temprature control method of box beam closure section concrete
CN108396653A (en) * 2018-03-01 2018-08-14 成都佰人佰思科技有限公司 A kind of steel structural bridge beam construction method
CN111794112A (en) * 2020-07-21 2020-10-20 重庆交通大学 Pier concrete hydration heat sink
CN111794113A (en) * 2020-07-21 2020-10-20 重庆交通大学 Device for controlling hydration heat of mass concrete of bridge pier in water bridge and using method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080108880A (en) * 2007-06-11 2008-12-16 이창남 Trench forme method for the steel concrete column
KR101104297B1 (en) * 2011-03-28 2012-01-11 주식회사 도화엔지니어링 Preflex girder making method and bridge construction method using the same
KR101136926B1 (en) 2009-11-04 2012-04-20 류승일 Composite beam by prestressed concrete filled tube
KR20120136071A (en) * 2011-06-08 2012-12-18 주식회사 액트파트너 Composite beam with partially filled concrete

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080108880A (en) * 2007-06-11 2008-12-16 이창남 Trench forme method for the steel concrete column
KR101136926B1 (en) 2009-11-04 2012-04-20 류승일 Composite beam by prestressed concrete filled tube
KR101104297B1 (en) * 2011-03-28 2012-01-11 주식회사 도화엔지니어링 Preflex girder making method and bridge construction method using the same
KR20120136071A (en) * 2011-06-08 2012-12-18 주식회사 액트파트너 Composite beam with partially filled concrete

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107663833A (en) * 2017-10-26 2018-02-06 北京科技大学 A kind of the water cooling constructing device and temprature control method of box beam closure section concrete
CN108396653A (en) * 2018-03-01 2018-08-14 成都佰人佰思科技有限公司 A kind of steel structural bridge beam construction method
CN111794112A (en) * 2020-07-21 2020-10-20 重庆交通大学 Pier concrete hydration heat sink
CN111794113A (en) * 2020-07-21 2020-10-20 重庆交通大学 Device for controlling hydration heat of mass concrete of bridge pier in water bridge and using method
CN111794112B (en) * 2020-07-21 2021-12-07 重庆交通大学 Pier concrete hydration heat sink

Similar Documents

Publication Publication Date Title
KR101703820B1 (en) Manufacturing method of concrete-filled box girder using the type channel the concrete-filled box girder for the bridge by the same
KR100547619B1 (en) Prestressing tendon layouts for prestressed steel composite girder
KR100536489B1 (en) Manufacturing method for prestressed steel composite girder and prestressed steel composite girder thereby
US4493177A (en) Composite, pre-stressed structural member and method of forming same
KR100541965B1 (en) Manufacturing apparatus for steel composite girder whose self weight is loaded on steel girder and manufacturing method thereof
US7047704B1 (en) Method for designing and fabricating multi-step tension prestressed girder
KR100947306B1 (en) Composite bridge structure with concrete shear connector and construction method of the same
KR101545936B1 (en) Precast wall structure construction
KR101108788B1 (en) Method of manufacturing multi stage prestressed composite beam which composes precast concrete panel and steel girder and correction device used therein
KR101677668B1 (en) Formed steel beam having bolt connection with lattice reinforcement and composite beam using the same
KR101768056B1 (en) Manufacturing method of prestressed concrete girder for bridge and constructing method of bridge using same
KR101527752B1 (en) Construction method of prestressed composite girder bridge
KR101251118B1 (en) A manufacturing method of a composite steel box girder using prestressed concrete for a positive moment area of a bridge
KR100937252B1 (en) Prestressed steel composite beam and a manufacturing method thereof
KR101847544B1 (en) Precast concrete slab having shear reinforcement function
KR100693871B1 (en) Optimized end reinforcing structure of prestressed steel composite beam and construction method by using the same
KR101994089B1 (en) Precast Concrete Slab With Pullout-Shear Resistance Elements Of Mesh Rib And Manufacturing Method Thereof
KR100546719B1 (en) Prestressed steel composite girder
KR101698807B1 (en) Manufacturing method of the psc girder using the corrugated steel plate and the psc girder manufactured thereby
KR101687159B1 (en) Manufacturing method of prestressed cft unit column and the unit column thereby
KR102278450B1 (en) Truss hybrid beam with wide Precast concrete lower flange
KR101797960B1 (en) Formed steel beam having neutral axis lifting elements and composite beam using the same
KR101796600B1 (en) Box-Section Composite Girder Using One Pairs of Module Member and Its Construction Method
KR101300490B1 (en) Hollow girder having upper flange of different materials, and method for constructing bridge using for the same
KR20100108927A (en) The method of manufacturing for manufactured girder of composition style p.s.c form that have half section slab and the method of constructing for bridge by using the upper method