KR101535863B1 - Up-Down Combination Type Pile Connecting Apparatus and Pile Construction Method Using the Same - Google Patents

Up-Down Combination Type Pile Connecting Apparatus and Pile Construction Method Using the Same Download PDF

Info

Publication number
KR101535863B1
KR101535863B1 KR1020140160403A KR20140160403A KR101535863B1 KR 101535863 B1 KR101535863 B1 KR 101535863B1 KR 1020140160403 A KR1020140160403 A KR 1020140160403A KR 20140160403 A KR20140160403 A KR 20140160403A KR 101535863 B1 KR101535863 B1 KR 101535863B1
Authority
KR
South Korea
Prior art keywords
fastening
pile
joint
hole
bolt
Prior art date
Application number
KR1020140160403A
Other languages
Korean (ko)
Inventor
최승선
Original Assignee
주식회사 비엠앤텍
최승선
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=53793047&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=KR101535863(B1) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by 주식회사 비엠앤텍, 최승선 filed Critical 주식회사 비엠앤텍
Priority to KR1020140160403A priority Critical patent/KR101535863B1/en
Application granted granted Critical
Publication of KR101535863B1 publication Critical patent/KR101535863B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A post connecting apparatus for vertically mounting a post according to the present invention comprises: an upper plate unit connected to one end of a first connection post and provided with a plurality of first mounting holes formed along a circumference thereof for mounting on the first connection post; a lower plate unit connected to one end of a second connection post, provided with a plurality of second mounting holes formed along a circumference thereof for mounting on the second connection post, and wherein the second mounting holes are not aligned with the first mounting holes; and a connection unit disposed between the upper plate unit and the lower plate unit. And, a post installation method using the same according to the present invention uses a post connecting apparatus comprising: an upper plate unit connected to one end of a first connection post and provided with a plurality of first mounting holes formed along a circumference thereof for mounting on the first connection post; a lower plate unit connected to one end of a second connection post, provided with a plurality of second mounting holes formed along a circumference thereof for mounting on the second connection post, and wherein the second mounting holes are not aligned with the first mounting holes; a connection unit disposed between the upper plate unit and the lower plate unit, opened in an outer diameter direction, and provided with second bolt insertion holes connected to the second mounting holes and formed thereon; and protective caps inserted into the second bolt insertion holes to protect heads of mounting bolts mounted into the second mounting holes. The post installation method using the post connecting apparatus comprises: a step of inserting the mounting bolts or steel bars of the first connection post into the first mounting holes to mount the upper plate unit on the first connection post; a step of inserting the mounting bolts into the second mounting holes to mount the lower plate unit on the second connection post; and a step of inserting the protective caps into the second bolt insertion holes.

Description

상하 체결형 말뚝 이음장치 및 이를 이용한 말뚝 시공방법{Up-Down Combination Type Pile Connecting Apparatus and Pile Construction Method Using the Same}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates generally to pile joining, and more particularly,

본 발명은 말뚝 간을 서로 연결시키는 말뚝 이음장치에 관한 것으로서, 보다 상세하게는 상판부 및 하판부의 체결홀이 서로 어긋난 위치에 형성된 상하 체결형 말뚝 이음장치에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a pile joining device for connecting piles to each other, and more particularly, to a vertically coupled pile joining device formed at a position where coupling holes of an upper plate and a lower plate are displaced from each other.

일반적으로 지반의 상부에 소정의 상재 구조물을 설치하기 위해서는 그 지반이 상재구조물의 하중에 대한 충분한 지지력이 확보되어야 한다. 지반 조건이나 상재구조물의 하중 조건에 대응하여 충분한 지지력이 확보되지 않은 지반을 연약지반이라 한다.Generally, in order to install a predetermined upper structure on the upper part of the ground, a sufficient supporting force for the load of the upper structure must be secured. The ground where the sufficient supporting force is not secured in response to the ground condition or the load condition of the superstructure is called soft ground.

연약지반은 상재 구조물의 안정성과 침하 문제에 대한 대책이 상재 구조물 설치 이전에 마련되어야 하며, 이러한 사전 대책 중에 가장 보편적으로 사용되고 있는 방법으로서, 향후 예측되는 상재 구조물의 하중을 지지층에 균등하고 안전하게 도달시키고자 선시공하는 말뚝공법이 있다.In soft ground, the stability and settlement problem of the superego structure should be prepared prior to installation of the superego structure, and the most widely used method is to equally and safely reach the supposed supposed supine structure load There is a pile construction method.

이와 같은 말뚝공법은 미리 공장에서 생산된 기성의 콘크리트 말뚝을 디젤해머, 유압해머 등으로 타격하여 시공하거나 지반을 천공한 후 매입 시공하는 방법을 말한다.Such a pile method refers to a method of constructing concrete piles produced by a factory in advance by hitting them with a diesel hammer or a hydraulic hammer or by drilling the ground and then installing the piles.

말뚝공법 수행 시에는 구조물에 가해지는 하중조건과 내진설계 여부, 기타 충격응력 등을 고려하여 사용하는 말뚝을 선정하게 되는데, 현재 건축현장에서 는 고강도 콘크리트 말뚝이 보편적으로 사용되고 있으며, 한국 산업규격(KS)에 따르면, 원심력을 응용하여 제조된 콘크리트의 압축 강도가 78.5N/㎟(800㎏f/㎠) 이상의 프리텐션 방식에 의한 고강도 콘크리트 말뚝(이하, “콘크리트 말뚝”이라 함)이라 규정하고 있다.In the case of the pile construction method, the pile is selected considering the load condition applied to the structure, the seismic design, and other impact stresses. In the present construction site, high strength concrete pile is widely used, (Hereinafter referred to as " concrete pile ") of a pre-tensioned concrete having a compressive strength of 78.5 N / mm 2 (800 kgf / cm 2) or more in the concrete produced by applying centrifugal force.

그리고 콘크리트 말뚝은 제조, 운반상의 제약으로 인하여 길이는 5~15m로 규정되어 있으나 실제 시공되는 현장의 지반조건에 따라 16m 이상의 깊이로 시공되는 경우도 비일비재한 상황이다.The length of concrete piles is 5 ~ 15m due to the manufacturing and transportation constraints. However, depending on the ground conditions of the actual construction site, the construction of concrete piles with a depth of 16m or more is also inevitable.

이와 같이 시공되는 길이가 16m 이상인 경우 콘크리트 말뚝을 2본 이상 연결하여 시공하게 되는데 현재까지 가장 많이 사용되는 이음방법은 도 1에 도시된 바와 같이, 제1이음말뚝(1) 및 제2이음말뚝(2)의 단부에 용접홈(5)이 가공된 철판(3, 4)을 각각 부착하여 말뚝을 생산하고, 현장에서 상하 말뚝을 서로 맞대어 용접 이음하는 방법이다.As shown in FIG. 1, the first joint pile (1) and the second joint pile (1) are formed by connecting two or more concrete piles when the length of the concrete pile is 16 m or longer. 2 are attached to the end portions of the steel plates 3 and 4 with welding grooves 5 formed thereon to produce piles and the upper and lower piles are welded to each other in the field.

다만, 이와 같은 용접이음 방법은 기후의 영향을 쉽게 받고, 용접 부위의 검사가 필요하며, 안전사고의 위험도 상존하는 등 그 문제점이 많아 근래 무용접 이음의 필요성이 대두되고 있는 실정이다.However, such a welding joint method is problematic in that it is easily influenced by climate, inspection of a welded portion is required, and there is a risk of a safety accident.

따라서 이와 같은 문제점들을 해결하기 위한 방법이 요구된다.Therefore, a method for solving such problems is required.

한국등록특허 제10-0646258호Korean Patent No. 10-0646258 한국등록특허 제10-0835778호Korean Patent No. 10-0835778 한국등록실용신안 제20-0298683호Korean Registered Utility Model No. 20-0298683 일본공개특허 제2000-328556호Japanese Patent Application Laid-Open No. 2000-328556

본 발명은 상술한 종래 기술의 문제점을 해결하기 위하여 안출된 발명으로서, 연결부가 구조적으로 안정하고, 비용면에서 경제적인 말뚝 이음장치를 제공하기 위함이다.SUMMARY OF THE INVENTION It is an object of the present invention to solve the above-mentioned problems of the prior art and to provide a pile joint device having a connecting part structurally stable and economical in terms of cost.

또한 용접을 수행하지 않고도 말뚝을 연결시킬 수 있는 말뚝 이음장치를 제공하기 위함이다.And to provide a pile joint device capable of connecting a pile without performing welding.

그리고 기존의 무용접이음 방법 보다 시공성 및 경제성이 확보된 방법을 제공하기 위함이다.And a method of securing workability and economical efficiency compared with a conventional weldless welding method.

또한 기성말뚝에 후 부착하여 말뚝을 연결할 수 있는 장치를 제공하기 위함이다.The present invention also provides a device capable of connecting a pile after it is attached to an existing pile.

본 발명의 과제들은 이상에서 언급한 과제들로 제한되지 않으며, 언급되지 않은 또 다른 과제들은 아래의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.The problems of the present invention are not limited to the above-mentioned problems, and other problems not mentioned can be clearly understood by those skilled in the art from the following description.

상기한 목적을 달성하기 위한 본 발명의 상하 체결형 말뚝 이음장치는, 제1이음말뚝의 일단에 연결되며, 상기 제1이음말뚝과의 체결을 위한 복수의 제1체결홀이 둘레를 따라 형성된 상판부, 제2이음말뚝의 일단에 연결되며, 상기 제2이음말뚝과의 체결을 위한 복수의 제2체결홀이 둘레를 따라 형성되되, 상기 제2체결홀은 상기 제1체결홀과 어긋난 위치에 형성된 하판부 및 상기 상판부와 상기 하판부 사이에 구비되는 연결부를 포함한다.In order to accomplish the above object, the present invention provides a pile joint device of a vertically-coupled type, comprising: a first joint pile connected to one end of a first joint pile and having a plurality of first fastening holes for fastening with the first joint pile, A plurality of second coupling holes for coupling with the second coupling peg are formed along the periphery, and the second coupling holes are formed at positions displaced from the first coupling holes And a connection part provided between the upper plate part and the lower plate part.

그리고 상기 제1체결홀은, 상기 제1체결홀에 삽입되어 상기 제1이음말뚝의 강봉너트에 체결되는 체결볼트에 대응되도록 형성될 수 있다.The first fastening hole may be formed to correspond to a fastening bolt inserted into the first fastening hole and fastened to a steel rod nut of the first joint pile.

또한 상기 하판부 및 상기 연결부를 관통하여 상기 제1체결홀에 연통되는 제1볼트삽입홀이 더 형성될 수 있다.And a first bolt insertion hole passing through the lower plate portion and the connection portion and communicating with the first fastening hole may be further formed.

그리고 상기 제1체결홀은, 상기 제1이음말뚝의 강봉에 대응되도록 형성되어, 상기 제1이음말뚝의 강봉이 삽입 및 고정되도록 형성될 수 있다.The first joint hole may be formed to correspond to the steel bar of the first joint pile, and may be formed to insert and fix the steel rod of the first joint pile.

또한 상기 제1체결홀은, 상기 강봉의 머리보다 큰 직경을 가지는 강봉삽입부와, 상기 강봉의 머리보다 큰 직경을 가지되, 상기 강봉의 머리가 정착될 수 있도록 형성된 강봉고정부를 포함할 수 있다.The first fastening hole may include a steel bar insertion portion having a larger diameter than the head of the steel bar and a steel bead portion having a diameter larger than that of the steel bar and formed so that the head of the steel bar can be fixed have.

그리고 상기 제2체결홀은, 상기 제2체결홀에 삽입되어 상기 제2이음말뚝의 강봉너트에 체결되는 체결볼트에 대응되도록 형성될 수 있다.The second fastening hole may be formed to correspond to a fastening bolt inserted into the second fastening hole and fastened to the steel rod nut of the second joint.

또한 상기 연결부의 외경 방향으로 개구되고, 상기 제2체결홀에 연통되는 제2볼트삽입홀이 더 형성될 수 있다.Further, a second bolt insertion hole may be formed in the outer circumferential direction of the connection portion and communicated with the second connection hole.

그리고 상기 상판부에는, 상기 제2체결홀에 대응되는 위치를 가지는 제3볼트삽입홀이 더 형성될 수 있다.The upper plate portion may further include a third bolt insertion hole having a position corresponding to the second fastening hole.

또한 상기 제2볼트삽입홀 및 상기 제3볼트삽입홀은 서로 연결되어 개구된 형상을 가질 수 있다.Further, the second bolt insertion hole and the third bolt insertion hole may be connected to each other and have an open shape.

그리고 상기 제2볼트삽입홀에 삽입되어 상기 제2체결홀에 체결된 체결볼트의 머리부를 보호하는 보호캡을 더 포함할 수 있다.And a protection cap inserted in the second bolt insertion hole to protect the head of the fastening bolt fastened to the second fastening hole.

또한 상기 보호캡의 외측은 상기 연결부 외경의 곡률에 대응되는 곡률로 형성될 수 있다.The outer side of the protective cap may be formed with a curvature corresponding to a curvature of the outer diameter of the connection portion.

그리고 상기 보호캡에는 상기 체결볼트의 머리부가 수용되는 수용홈이 형성될 수 있다.The protection cap may be formed with a receiving groove for receiving the head of the fastening bolt.

또한 상기 복수의 제2체결홀에 체결되는 체결볼트 중 일부 제2체결홀에 체결되는 체결볼트는 서로 결합 가능하도록 분리된 머리부 및 나사부를 포함하는 형태로 형성될 수 있다.Further, the fastening bolts fastened to the second fastening holes of the fastening bolts fastened to the plurality of second fastening holes may be formed to include the separated head and threaded portions so as to be able to be engaged with each other.

이때 상기 복수의 제2체결홀 중 일부 제2체결홀에는 가이드핀이 결합되고, 상기 가이드핀이 결합되는 제2체결홀은 상기 가이드핀을 제거하기 위한 인출홈을 더 포함할 수 있다.At this time, a guide pin may be coupled to a part of the second fastening holes of the plurality of second fastening holes, and a second fastening hole to which the guide pin is coupled may further include a lead-out groove for removing the guide pin.

그리고 상기 제1이음말뚝은 강관 콘크리트말뚝 형태로 형성되며, 상기 상판부의 둘레에는 상기 강관이 안착되는 안착홈이 형성될 수 있다.The first joint pile is formed in the form of a steel pipe concrete pile, and a seating groove on which the steel pipe is seated may be formed around the upper plate.

또한 상기한 목적을 달성하기 위한 본 발명의 상하 체결형 말뚝 이음장치의 다른 형태는, 강관말뚝 형태로 형성되는 제1이음말뚝의 일단에 연결되며, 둘레에는 상기 강관이 안착되는 안착홈이 형성된 상판부, 제2이음말뚝의 일단에 연결되며, 상기 제2이음말뚝의 강봉너트에 체결되는 체결볼트에 대응되는 복수의 제2체결홀이 둘레를 따라 형성된 하판부 및 상기 상판부와 상기 하판부 사이에 구비되는 연결부를 포함한다.According to another aspect of the present invention, there is provided a pile joint device of a vertically-coupled type, comprising: a first joint pile formed in the form of a steel pipe pile and connected to one end of the first joint pile; A lower plate portion connected to one end of the second joint pile and having a plurality of second fastening holes corresponding to the fastening bolts fastened to the steel rod nuts of the second joint pegs along the periphery thereof and a lower plate portion provided between the upper plate portion and the lower plate portion. .

그리고 상기 연결부의 외경 방향으로 개구되고, 상기 제2체결홀에 연통되는 제2볼트삽입홀이 더 형성될 수 있다.And a second bolt insertion hole opened in the outer diameter direction of the connection portion and communicating with the second fastening hole may be further formed.

또한 본 발명의 상하 체결형 말뚝 이음장치를 이용한 말뚝 시공방법은, 제1이음말뚝의 일단에 연결되며, 상기 제1이음말뚝과의 체결을 위한 복수의 제1체결홀이 둘레를 따라 형성된 상판부와, 제2이음말뚝의 일단에 연결되며, 상기 제2이음말뚝과의 체결을 위한 복수의 제2체결홀이 둘레를 따라 형성되되, 상기 제2체결홀은 상기 제1체결홀과 어긋난 위치에 형성된 하판부와, 상기 상판부와 상기 하판부 사이에 구비되며, 외경 방향으로 개구되고, 상기 제2체결홀에 연통되는 제2볼트삽입홀이 형성된 연결부와, 상기 제2볼트삽입홀에 삽입되어 상기 제2체결홀에 체결된 체결볼트의 머리부를 보호하는 보호캡을 포함하는 말뚝 이음장치를 이용한 말뚝 시공방법에 있어서, 상기 제1체결홀에, 체결볼트 또는 상기 제1이음말뚝의 강봉을 삽입하여 상기 상판부와 상기 제1이음말뚝을 체결하는 단계, 상기 제2체결홀에, 체결볼트를 삽입하여 상기 하판부와 상기 제2이음말뚝을 체결하는 단계 및 상기 보호캡을 상기 제2볼트삽입홀에 삽입하는 단계를 포함한다.In addition, the method of constructing a pile using the vertically-coupled pile joint device of the present invention is characterized in that a pile installation method is used in which a plurality of first fastening holes for fastening with the first joint pile are formed along a periphery, A plurality of second coupling holes for coupling with the second coupling peg are formed along the periphery, and the second coupling holes are formed at positions displaced from the first coupling holes A connecting portion provided between the upper plate portion and the lower plate portion and having a second bolt insertion hole formed in the outer circumferential direction and communicating with the second fastening hole and a second bolt insertion hole formed in the second bolt insertion hole, And a protective cap for protecting a head portion of a fastening bolt fastened to the second fastening hole, the method comprising: inserting a fastening bolt or a steel rod of the first jointed pile into the first fastening hole, Top Inserting the first joint pile, inserting a fastening bolt into the second fastening hole to fasten the lower plate and the second joint pile, and inserting the protection cap into the second bolt insertion hole .

그리고 상기 상판부에는 상기 제2체결홀에 대응되는 위치를 가지는 제3볼트삽입홀이 더 형성되고, 상기 연결부의 높이는 상기 체결볼트의 높이보다 낮게 형성되며, 상기 상판부와 상기 제1이음말뚝을 체결하는 단계 이전에는, 상기 제3볼트삽입홀을 통해 상기 체결볼트를 상기 제2체결홀에 삽입하는 단계가 더 포함될 수 있다.The upper plate portion is further provided with a third bolt insertion hole having a position corresponding to the second fastening hole. The height of the connection portion is lower than the height of the fastening bolt, and the upper plate portion and the first joint pile are fastened The step of inserting the fastening bolt into the second fastening hole through the third bolt insertion hole may be further included before the step.

또한 상기 복수의 제2체결홀 중 일부 제2체결홀에 체결되는 상기 체결볼트는 서로 결합 가능하도록 분리된 머리부 및 나사부를 포함하는 형태로 형성되며, 상기 하판부와 상기 제2이음말뚝을 체결하는 단계 이전에는, 상기 제2이음말뚝에 구비된 강봉너트 중 일부에 상기 나사부를 결합하는 단계가 더 포함될 수 있다.The fastening bolts fastened to a part of the second fastening holes of the plurality of second fastening holes are formed in a shape including a head and a screw part which are separated so as to be able to be engaged with each other, and the lower plate part and the second joint peg The step of joining the threaded portion to a part of the steel bar nuts provided in the second joint pile may be further included.

그리고 상기 복수의 제2체결홀 중 일부 제2체결홀에는 봉 형태의 가이드핀이 결합되며, 상기 하판부와 상기 제2이음말뚝을 체결하는 단계 이전에는, 상기 제2이음말뚝에 구비된 강봉너트 중 일부에 상기 가이드핀을 결합하는 단계가 더 포함되며, 상기 하판부와 상기 제2이음말뚝을 체결하는 단계 이후에는, 상기 가이드핀을 상기 제2체결홀로부터 제거하는 단계가 더 포함될 수 있다.A plurality of second fastening holes may be formed on the first joint pile, and a rod-shaped guide pin may be coupled to the second fastening hole of the plurality of second fastening holes. Before the step of fastening the lower plate and the second joint pile, The method may further include a step of coupling the guide pin to a part of the lower joint part, and after the step of fastening the lower joint part and the second joint pile, removing the guide pin from the second fastening hole.

상기한 과제를 해결하기 위한 본 발명의 상하 체결형 말뚝 이음장치는 다음과 같은 효과가 있다.The above and other objects and features of the present invention will become more apparent from the following detailed description when taken in conjunction with the accompanying drawings, in which: FIG.

첫째, 서로 어긋나게 배열된 제1체결홀 및 제2체결홀에 의해 말뚝의 이음부가 구조적으로 안정하다는 장점이 있다.First, there is an advantage that the joint of the pile is structurally stable by the first fastening holes and the second fastening holes which are arranged to be shifted from each other.

둘째, 연결부의 높이를 최소화할 수 있어 재료의 절감을 실현할 수 있는 장점이 있다.Second, since the height of the connecting portion can be minimized, the material can be reduced.

셋째, 용접을 수행할 필요가 없어, 시공 비용을 절감할 수 있으며, 환경의 제약을 받지 않는 장점이 있다.Third, there is no need to perform welding, and the construction cost can be reduced, and there is an advantage that it is not restricted by the environment.

넷째, 작업 난이도가 낮아 숙련된 작업자가 필요하지 않은 장점이 있다.Fourth, there is a merit that the skill level is low and skilled workers are not needed.

다섯째, 종래 기성 말뚝에도 사용이 가능하다는 장점이 있다.Fifth, there is an advantage that it can be used for a conventional pile.

여섯째, 다양한 종류의 말뚝에 호환이 가능하므로 범용성이 뛰어나다는 장점이 있다.Sixth, because it is compatible with various kinds of piles, there is an advantage that it is excellent in versatility.

일곱째, 기존 무용접 이음 방법에 비하여 시공성 및 경제성이 우수하다는 장점이 있다.Seventh, there is an advantage that the workability and economical efficiency are superior to the conventional weldless welding method.

본 발명의 효과들은 이상에서 언급한 효과들로 제한되지 않으며, 언급되지 않은 또 다른 효과들은 청구범위의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.The effects of the present invention are not limited to the effects mentioned above, and other effects not mentioned can be clearly understood by those skilled in the art from the description of the claims.

도 1은 종래 용접 방식으로 말뚝을 연결한 모습을 나타낸 단면도;
도 2는 본 발명의 제1실시예에 따른 말뚝 이음장치에 있어서, 각 구성 간의 연결 구조를 나타낸 분해사시도;
도 3은 본 발명의 제1실시예에 따른 말뚝 이음장치의 모습을 확대한 모습을 나타낸 사시도;
도 4는 본 발명의 제1실시예에 따른 말뚝 이음장치를 보다 자세히 나타낸 평면도, 단면도 및 저면도;
도 5는 본 발명의 제1실시예에 따른 말뚝 이음장치로 제1이음말뚝 및 제2이음말뚝을 서로 연결한 모습을 나타낸 단면도;
도 6은 본 발명의 제2실시예에 따른 말뚝 이음장치의 모습을 확대한 모습을 나타낸 사시도;
도 7은 본 발명의 제2실시예에 따른 말뚝 이음장치를 보다 자세히 나타낸 평면도, 단면도 및 저면도;
도 8은 본 발명의 제2실시예에 따른 말뚝 이음장치로 제1이음말뚝 및 제2이음말뚝을 서로 연결한 모습을 나타낸 단면도;
도 9는 본 발명의 제3실시예에 따른 말뚝 이음장치의 모습을 확대한 모습을 나타낸 사시도;
도 10은 본 발명의 제4실시예에 따른 말뚝 이음장치의 모습을 확대한 모습을 나타낸 사시도;
도 11은 본 발명의 제4실시예에 따른 말뚝 이음장치를 보다 자세히 나타낸 평면도, 단면도 및 저면도;
도 12는 본 발명의 제4실시예에 따른 말뚝 이음장치로 제1이음말뚝 및 제2이음말뚝을 서로 연결한 모습을 나타낸 단면도;
도 13은 본 발명의 제5실시예에 따른 말뚝 이음장치의 모습을 확대한 모습을 나타낸 사시도;
도 14는 본 발명의 제5실시예에 따른 말뚝 이음장치로 제1이음말뚝 및 제2이음말뚝을 서로 연결한 모습을 나타낸 단면도;
도 15는 본 발명의 제6실시예에 따른 말뚝 이음장치의 모습을 확대한 모습을 나타낸 사시도;
도 16은 본 발명의 제6실시예에 따른 말뚝 이음장치로 제1이음말뚝 및 제2이음말뚝을 서로 연결한 모습을 나타낸 단면도;
도 17은 본 발명의 제1실시예에 따른 말뚝 이음장치를 이용하여 제1이음말뚝 및 제2이음말뚝을 연결하는 과정을 나타낸 단면도;
도 18은 본 발명의 제2실시예에 따른 말뚝 이음장치를 이용하여 제1이음말뚝 및 제2이음말뚝을 연결하는 과정을 나타낸 단면도; 및
도 19은 본 발명의 제2실시예에 따른 말뚝 이음장치를 이용하여 제1이음말뚝 및 제2이음말뚝을 연결하는 과정을 다른 단면에서 나타낸 단면도이다.
1 is a cross-sectional view showing a state where a pile is connected by a conventional welding method;
FIG. 2 is an exploded perspective view showing a connection structure between respective components in the pile joint device according to the first embodiment of the present invention; FIG.
FIG. 3 is a perspective view showing an enlarged view of a pile joint device according to a first embodiment of the present invention; FIG.
FIG. 4 is a plan view, a cross-sectional view and a bottom view of the pile-connecting device according to the first embodiment of the present invention.
5 is a cross-sectional view showing a first joint pile and a second joint pile connected to each other by a pile joint device according to a first embodiment of the present invention;
6 is a perspective view showing an enlarged view of a pile joint device according to a second embodiment of the present invention;
FIG. 7 is a plan view, a cross-sectional view and a bottom view showing a pile-connecting device according to a second embodiment of the present invention in more detail; FIG.
FIG. 8 is a sectional view showing a first joint pile and a second joint pile connected to each other by a pile joint device according to a second embodiment of the present invention; FIG.
FIG. 9 is a perspective view showing an enlarged view of a pile joint device according to a third embodiment of the present invention; FIG.
FIG. 10 is a perspective view showing an enlarged view of a pile joint device according to a fourth embodiment of the present invention; FIG.
11 is a plan view, a cross-sectional view and a bottom view of the pile-connecting device according to the fourth embodiment of the present invention.
12 is a cross-sectional view illustrating a first joint pile and a second joint pile connected to each other by a pile joint device according to a fourth embodiment of the present invention;
FIG. 13 is a perspective view showing an enlarged view of a pile joint device according to a fifth embodiment of the present invention; FIG.
FIG. 14 is a sectional view showing a first joint pile and a second joint pile connected to each other by a pile joint device according to a fifth embodiment of the present invention; FIG.
FIG. 15 is a perspective view showing an enlarged view of a pile joint device according to a sixth embodiment of the present invention; FIG.
16 is a cross-sectional view showing a first joint pile and a second joint pile connected to each other by a pile joint device according to a sixth embodiment of the present invention;
17 is a sectional view showing a process of connecting a first joint pile and a second joint pile using the pile joint device according to the first embodiment of the present invention;
18 is a sectional view showing a process of connecting a first joint pile and a second joint pile using a pile joint device according to a second embodiment of the present invention; And
19 is a cross-sectional view showing another cross-section of a process of connecting a first joint pile and a second joint pile using the pile joint device according to the second embodiment of the present invention.

이하 본 발명의 목적이 구체적으로 실현될 수 있는 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 설명한다. 본 실시예를 설명함에 있어서, 동일 구성에 대해서는 동일 명칭 및 동일 부호가 사용되며 이에 따른 부가적인 설명은 생략하기로 한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings. In describing the present embodiment, the same designations and the same reference numerals are used for the same components, and further description thereof will be omitted.

도 2는 본 발명의 제1실시예에 따른 말뚝 이음장치(100)에 있어서, 각 구성 간의 연결 구조를 나타낸 분해사시도이며, 도 3은 본 발명의 제1실시예에 따른 말뚝 이음장치(100)의 모습을 확대한 모습을 나타낸 사시도이다. 그리고 도 4는 본 발명의 제1실시예에 따른 말뚝 이음장치(100)를 보다 자세히 나타낸 평면도, 단면도 및 저면도이다.FIG. 2 is an exploded perspective view showing a connection structure between respective components in the pile joint 100 according to the first embodiment of the present invention. FIG. 3 is a perspective view of the pile joint 100 according to the first embodiment of the present invention. Of the present invention. And FIG. 4 is a plan view, a cross-sectional view, and a bottom view of the pile-joining apparatus 100 according to the first embodiment of the present invention.

도 2 내지 도 4에 도시된 바와 같이, 제1이음말뚝(10) 및 제2이음말뚝(20)은 말뚝 이음장치(100)에 의해 서로 연결되며, 상기 말뚝 이음장치(100)는 상판부(110)와, 하판부(120)와, 연결부(130)를 포함한다.2 to 4, the first joint pile 10 and the second joint pile 20 are connected to each other by a pile joining device 100, and the pile joining device 100 is connected to the upper plate 110 A lower plate portion 120, and a connecting portion 130.

상기 상판부(110)는 제1이음말뚝(10)의 일단에 연결되며, 상기 제1이음말뚝(10)과의 체결을 위한 복수의 제1체결홀(112)이 둘레를 따라 형성된다.The upper plate 110 is connected to one end of the first joint pile 10 and a plurality of first fastening holes 112 for fastening the first joint pile 10 to the first joint pile 10 are formed along the periphery.

그리고 상기 하판부(120)는 제2이음말뚝(20)의 일단에 연결되며, 상기 제2이음말뚝(20)과의 체결을 위한 복수의 제2체결홀(122)이 둘레를 따라 형성된다. 이때 상기 제2체결홀(122)은 상기 제1체결홀(112)과 서로 어긋난 위치에 형성된다. 즉 상기 제1체결홀(112) 및 상기 제2체결홀(122)은 서로 둘레를 따라 교대로 형성된다.The lower plate portion 120 is connected to one end of the second joint pile 20 and a plurality of second fastening holes 122 for fastening with the second joint pile 20 are formed along the circumference. At this time, the second fastening holes 122 are formed at positions displaced from the first fastening holes 112. That is, the first fastening hole 112 and the second fastening hole 122 are alternately formed along the circumference.

또한 상기 연결부(130)는 상기 상판부(110)와 상기 하판부(120) 사이에 구비되며, 소정의 높이를 가질 수 있다.The connection part 130 is provided between the upper plate part 110 and the lower plate part 120 and may have a predetermined height.

여기서 본 실시예의 경우, 상기 제1이음말뚝(10) 및 상기 제2이음말뚝(20)은 모두 콘크리트 말뚝 형태로 형성되며, 내부에 강봉 및 강봉너트가 구비된 형태를 가진다. 따라서 상기 제1체결홀(112) 및 상기 제2체결홀(122)은, 서로 대응되는 말뚝의 강봉 및 강봉너트의 개수와 동일하게 형성될 수 있다.Here, in the present embodiment, the first joint pile 10 and the second joint pile 20 are all formed as concrete piles and have a steel bar and a steel bar nut provided therein. Therefore, the first fastening hole 112 and the second fastening hole 122 may be formed to have the same number of steel rods and steel rod nuts as the piles corresponding to each other.

보다 구체적으로 본 실시예에서 상기 제1체결홀(112) 및 상기 제2체결홀(122)은, 상기 제1체결홀(112) 및 상기 제2체결홀(122)을 관통하는 형태로 각 말뚝(10, 20)의 강봉너트에 체결되는 체결볼트(160)에 대응되도록 형성된다. 즉 상기 상판부(110) 및 상기 하판부(120)는 상기 체결볼트(160)에 의해 각각 상기 제1이음말뚝(10) 및 상기 제2이음말뚝(20)에 체결될 수 있다.More specifically, in this embodiment, the first fastening hole 112 and the second fastening hole 122 are formed so as to penetrate through the first fastening hole 112 and the second fastening hole 122, And the fastening bolts 160 fastened to the steel bar nuts of the fasteners 10 and 20. That is, the upper plate 110 and the lower plate 120 can be fastened to the first joint pile 10 and the second joint pile 20 by the fastening bolts 160, respectively.

또한 본 실시예의 경우, 상기 제1체결홀(112)에 체결볼트(160)를 삽입할 수 있도록 상기 하판부(120) 및 상기 연결부(130)를 관통하여 상기 제1체결홀(112)에 연통되는 제1볼트삽입홀(114)과, 상기 제2체결홀(122)에 체결볼트(160)를 삽입할 수 있도록 상기 연결부(130)의 외경 방향으로 개구되고, 상기 제2체결홀(122)에 연통되는 제2볼트삽입홀(124)이 형성된다.Also, in this embodiment, the fastening bolt 160 may be inserted into the first fastening hole 112, and may be communicated with the first fastening hole 112 through the lower plate 120 and the connecting portion 130, The first bolt insertion hole 114 and the second bolt insertion hole 114 are formed in the outer circumferential direction of the connection portion 130 so that the fastening bolt 160 can be inserted into the second fastening hole 122, A second bolt insertion hole 124 is formed.

이에 따라 상기 제1체결홀(112)에 결합되는 체결볼트(160)는 제1볼트삽입홀(114)을 통해, 상기 제2체결홀(122)에 결합되는 체결볼트(160)는 제2볼트삽입홀(124)을 통해 삽입되어 체결될 수 있다.The fastening bolt 160 coupled to the first fastening hole 112 is connected to the fastening bolt 160 coupled to the second fastening hole 122 through the first bolt insertion hole 114, Can be inserted and fastened through the insertion hole (124).

한편 본 실시예는 상기 제2볼트삽입홀(124)에 삽입되어 상기 제2체결홀(122)에 체결된 체결볼트(160)의 머리부를 보호하는 보호캡(150)을 더 포함한다. 상기 보호캡(150)은 상기 제2볼트삽입홀(124)의 개수만큼 구비되어 각 제2볼트삽입홀(124)마다 삽입될 수 있으며, 흙 등의 이물질이 침입하는 것을 방지하여 체결볼트(160)의 머리부가 토양과 접촉함에 따라 부식되는 것을 방지하는 목적으로 사용된다.The present embodiment further includes a protection cap 150 inserted into the second bolt insertion hole 124 to protect the head of the fastening bolt 160 fastened to the second fastening hole 122. The protective cap 150 is provided in the number corresponding to the number of the second bolt insertion holes 124 and can be inserted in each of the second bolt insertion holes 124 to prevent foreign substances such as soil from entering the fastening bolt 160 Is used for the purpose of preventing corrosion as the head portion comes into contact with the soil.

그리고 본 실시예에서 상기 보호캡(150)은 상부가 막힌 형태를 가지며, 상기 체결볼트(160)의 머리부가 수용되는 수용홈(152)이 형성된다. 또한 상기 보호캡(150)의 외측은, 상기 연결부(130) 외경의 곡률에 대응되는 곡률로 형성되도록 하여, 저항을 줄이고 시공성을 향상시킬 수 있다.In this embodiment, the protective cap 150 has a closed top shape and a receiving groove 152 for receiving the head of the fastening bolt 160 is formed. Further, the outer side of the protective cap 150 may be formed with a curvature corresponding to the curvature of the outer diameter of the connection part 130, thereby reducing the resistance and improving the workability.

도 5는 본 발명의 제1실시예에 따른 말뚝 이음장치(100)로 제1이음말뚝(10) 및 제2이음말뚝(20)을 서로 연결한 모습을 나타낸 단면도이다.5 is a cross-sectional view showing a first joint pile 10 and a second joint pile 20 connected to each other by a pile joint 100 according to a first embodiment of the present invention.

도 5에 도시된 바와 같이, 상기 말뚝 이음장치(100)는 제1이음말뚝(10) 및 제2이음말뚝(20)의 사이에 구비되며, 체결볼트(160)가 각각 제1이음말뚝(10)의 강봉(12)을 고정시키는 강봉너트(14)와, 제2이음말뚝(20)의 강봉(22)을 고정시키는 강봉너트(24)에 결합된다. 이에 따라 상기 제1이음말뚝(10) 및 상기 제2이음말뚝(20)은 안정적으로 연결된 상태를 유지할 수 있다.5, the pile joint device 100 is provided between the first joint pile 10 and the second joint pile 20, and the fastening bolts 160 are respectively connected to the first joint pile 10 A steel rod nut 14 for fixing the steel rod 12 of the second joint 20 and a steel rod nut 24 for fixing the steel rod 22 of the second joint 20. Accordingly, the first joint pile 10 and the second joint pile 20 can be stably connected.

이하에서는 본 발명의 다른 실시예들에 대해 설명하도록 한다.Hereinafter, other embodiments of the present invention will be described.

도 6은 본 발명의 제2실시예에 따른 말뚝 이음장치(200)의 모습을 확대한 모습을 나타낸 사시도이며, 도 7은 본 발명의 제2실시예에 따른 말뚝 이음장치(200)를 보다 자세히 나타낸 평면도, 단면도 및 저면도이다.FIG. 6 is a perspective view showing an enlarged view of a pile joint device 200 according to a second embodiment of the present invention, and FIG. 7 is a perspective view showing a pile joint device 200 according to a second embodiment of the present invention in more detail Sectional view and a bottom view, respectively.

도 6 및 도 7에 도시된 바와 같이, 본 발명의 제2실시예에 따른 말뚝 이음장치(200)는 전술한 제1실시예와 전체적으로 동일한 형상을 가지도록 형성된다. 즉 상판부(210), 하판부(220), 연결부(230), 제1체결홀(212), 제2체결홀(222), 제1볼트삽입홀(214), 제2볼트삽입홀(224) 및 보호캡(250)이 모두 동일하게 형성되나, 본 실시예의 경우 제3볼트삽입홀(226)이 더 형성된다는 점이 다르다.6 and 7, the pile-connecting device 200 according to the second embodiment of the present invention is formed to have the same overall shape as the first embodiment described above. A first bolt insertion hole 214, a second bolt insertion hole 224, and a second bolt insertion hole 214. The first bolt insertion hole 214 and the second bolt insertion hole 224 are formed in the upper plate portion 210, the lower plate portion 220, the connection portion 230, And the protective cap 250 are all formed identically, but in this embodiment, the third bolt insertion hole 226 is further formed.

상기 제3볼트삽입홀(226)은 상기 상판부(210) 측에 형성되며, 특히 상기 제2체결홀(222)에 대응되는 위치마다 형성된다. 즉 상기 제3볼트삽입홀(226)은 각 제1체결홀(212) 사이에 형성되며, 상기 제2체결홀(222)과 동심축을 가지도록 형성된다.The third bolt insertion hole 226 is formed on the side of the upper plate 210, particularly at each position corresponding to the second fastening hole 222. That is, the third bolt insertion hole 226 is formed between the first fastening holes 212 and has a concentric axis with the second fastening holes 222.

이에 따라, 하판부(220)를 제2이음말뚝(20)에 결합할 경우, 상기 체결볼트(260)의 높이가 상기 제2볼트삽입홀(224)의 높이보다 높다고 하더라도 상기 체결볼트(260)를 제3볼트삽입홀(226)로 삽입할 수 있게 된다. 이와 같은 경우에는 말뚝 이음장치(200)의 전체 높이를 보다 낮게 하여 제조 비용을 절감하고, 연결 안정성을 보다 향상시킬 수 있다.Accordingly, even if the height of the fastening bolt 260 is higher than the height of the second bolt insertion hole 224 when the lower plate 220 is coupled to the second joint pile 20, The third bolt insertion hole 226 can be inserted. In such a case, the total height of the pile joint device 200 may be reduced to reduce the manufacturing cost and improve the connection stability.

한편 본 실시예의 경우, 도 7의 B-B단면과 같이 제2체결홀(222) 중 일부는 인출홈(223)을 더 포함하며, 이에 대해서는 후술하도록 한다.Meanwhile, in the case of this embodiment, as shown in section B-B of FIG. 7, a part of the second fastening holes 222 further includes a lead-out groove 223, which will be described later.

도 8은 본 발명의 제2실시예에 따른 말뚝 이음장치(200)로 제1이음말뚝(10) 및 제2이음말뚝(20)을 서로 연결한 모습을 나타낸 단면도이다.8 is a cross-sectional view illustrating a first joint pile 10 and a second joint pile 20 connected to each other by a pile joint 200 according to a second embodiment of the present invention.

도 8에 도시된 바와 같이, 상기 말뚝 이음장치(200)는 제1이음말뚝(10) 및 제2이음말뚝(20)의 사이에 구비되며, 체결볼트(260)가 각각 제1이음말뚝(10)의 강봉(12)을 고정시키는 강봉너트(14)와, 제2이음말뚝(20)의 강봉(22)을 고정시키는 강봉너트(24)에 결합된다.8, the pile joint device 200 is provided between the first joint pile 10 and the second joint pile 20, and the fastening bolts 260 are respectively connected to the first joint pile 10 A steel rod nut 14 for fixing the steel rod 12 of the second joint 20 and a steel rod nut 24 for fixing the steel rod 22 of the second joint 20.

이때 제1이음말뚝(10)과 말뚝 이음장치(200)를 먼저 결합시키는 경우에는 전술한 제3볼트삽입홀(226, 도 6 참조)이 제1이음말뚝(10)에 의해 차폐되므로, 제2이음말뚝(20)과의 결합을 위한 체결볼트(260)는 미리 제2체결홀(222, 도 6 참조)에 삽입시켜 놓는 것이 바람직하다.In this case, when the first joint pile 10 and the pile coupling 200 are first coupled, the third bolt insertion hole 226 (see FIG. 6) described above is shielded by the first joint pile 10, It is preferable that the fastening bolts 260 for coupling with the joint pile 20 are inserted into the second fastening holes 222 (see FIG. 6) in advance.

도 9는 본 발명의 제3실시예에 따른 말뚝 이음장치(300)의 모습을 확대한 모습을 나타낸 사시도이다.9 is a perspective view showing an enlarged view of a pile joint device 300 according to a third embodiment of the present invention.

도 9에 도시된 본 발명의 제3실시예의 경우, 상판부(310), 하판부(320), 연결부(330), 제1체결홀(312), 제2체결홀(322), 제1볼트삽입홀(314), 제2볼트삽입홀(324)이 전술한 제1실시예 및 제2실시예와 모두 동일하게 형성된다. 다만, 본 실시예의 경우 제2실시예에서의 제2볼트삽입홀 및 제3볼트삽입홀이 서로 연결되어 개구된 형상을 가진다는 점이 다르다.9, the upper plate portion 310, the lower plate portion 320, the connecting portion 330, the first fastening hole 312, the second fastening hole 322, the first bolt insertion portion 322, The hole 314 and the second bolt insertion hole 324 are formed in the same manner as the first and second embodiments described above. However, the second embodiment differs from the second embodiment in that the second bolt insertion hole and the third bolt insertion hole are connected to each other and have an opening shape.

이와 같은 경우 말뚝 이음장치(300)의 중량을 최소화할 수 있으며, 또한 이때 보호캡은 상판부(310) 및 연결부(330)를 합친 높이에 대응되는 높이를 가질 수 있을 것이다.In this case, the weight of the pile joint device 300 can be minimized, and at this time, the protective cap may have a height corresponding to the combined height of the top plate portion 310 and the connection portion 330.

도 10은 본 발명의 제4실시예에 따른 말뚝 이음장치(400)의 모습을 확대한 모습을 나타낸 사시도이며, 도 11은 본 발명의 제4실시예에 따른 말뚝 이음장치(400)를 보다 자세히 나타낸 평면도, 단면도 및 저면도이다. 그리고 도 12는 본 발명의 제4실시예에 따른 말뚝 이음장치(400)로 제1이음말뚝(30) 및 제2이음말뚝(20)을 서로 연결한 모습을 나타낸 단면도이다.FIG. 10 is a perspective view showing an enlarged view of a pile joint device 400 according to a fourth embodiment of the present invention, and FIG. 11 is a perspective view showing a pile joint device 400 according to a fourth embodiment of the present invention in more detail Sectional view and a bottom view, respectively. 12 is a cross-sectional view showing a first joint pile 30 and a second joint pile 20 connected to each other by a pile joint 400 according to a fourth embodiment of the present invention.

도 10 내지 도 12에 도시된 본 발명의 제4실시예에 따른 말뚝 이음장치(400)는, 전술한 제1실시예와 상판부(410), 하판부(420), 연결부(430), 제2체결홀(422), 제2볼트삽입홀(424) 및 보호캡(450)이 모두 동일하게 형성된다.The pile joint 400 according to the fourth embodiment of the present invention shown in Figs. 10 to 12 is different from the pile joint 400 according to the first embodiment in that the upper plate 410, the lower plate 420, the connecting portion 430, The fastening hole 422, the second bolt insertion hole 424, and the protection cap 450 are all formed identically.

다만, 본 실시예의 말뚝 이음장치(400)는 제1이음말뚝과 일체로 성형되는 말뚝 이음장치(400)로서, 상판부(410)에 형성된 제1체결홀(412)의 형태가 다르게 형성된다.However, the pile joint device 400 of the present embodiment is formed integrally with the first joint pile, and the shape of the first joint hole 412 formed in the upper plate portion 410 is different.

구체적으로, 본 실시예에서 상기 제1체결홀(412)은 상기 제1이음말뚝(30)의 강봉(32)에 대응되도록 형성되어, 상기 제1이음말뚝(30)의 강봉(32)이 삽입 및 고정되도록 형성된다. 이를 위해 상기 제1체결홀(412)은, 상기 강봉(32)의 머리보다 큰 직경을 가지는 강봉삽입부(412a)와, 상기 강봉(32)의 머리보다 큰 직경을 가지되, 상기 강봉(32)의 머리가 정착될 수 있도록 형성된 강봉고정부(412b)를 포함한다.Specifically, in the present embodiment, the first joint hole 412 is formed to correspond to the steel rod 32 of the first joint pile 30, and the steel rod 32 of the first joint pile 30 is inserted And fixed. The first fastening hole 412 has a steel rod insertion portion 412a having a larger diameter than the head of the steel rod 32 and a steel rod insertion portion 412b having a diameter larger than that of the steel rod 32, And a head 412b formed to be able to fix the head of the head 412b.

이에 따라 말뚝 제조 시 상기 강봉(32)을 강봉삽입부(412a)에 삽입한 뒤 강봉고정부(412b)로 이동시켜 말뚝 이음장치(400)가 말뚝에 일체로 고정되도록 할 수 있다. 즉 도 12에 도시된 바와 같이, 말뚝 이음장치(400)는 제1이음말뚝(30)의 강봉(32)이 제1체결홀(412)에 삽입되어 일체로 형성됨을 확인할 수 있다.Accordingly, when the pile is manufactured, the steel rods 32 are inserted into the steel rod insertion portion 412a, and then moved to the steel sump forming portion 412b so that the pile joining device 400 can be integrally fixed to the pile. That is, as shown in FIG. 12, it can be seen that the steel rod 32 of the first joint pile 30 is inserted into the first fastening hole 412 and formed integrally with the pile joint device 400.

도 13은 본 발명의 제5실시예에 따른 말뚝 이음장치(500)의 모습을 확대한 모습을 나타낸 사시도이며, 도 14는 본 발명의 제5실시예에 따른 말뚝 이음장치(500)로 제1이음말뚝(40) 및 제2이음말뚝(20)을 서로 연결한 모습을 나타낸 단면도이다.FIG. 13 is a perspective view showing an enlarged view of a pile joint device 500 according to a fifth embodiment of the present invention, FIG. 14 is a pile joint device 500 according to a fifth embodiment of the present invention, Sectional view showing a state in which the joint pile 40 and the second joint pile 20 are connected to each other.

도 13 및 도 14에 도시된 본 발명의 제5실시예에 따른 말뚝 이음장치(500)는, 전술한 제4실시예와 상판부(510), 하판부(520), 연결부(530), 제1체결홀(512), 제2체결홀(522), 제2볼트삽입홀(524) 및 보호캡(550)이 모두 동일하게 형성된다.The pile joint device 500 according to the fifth embodiment of the present invention shown in Figs. 13 and 14 is similar to the pile joint device 500 of the fourth embodiment except that the upper plate portion 510, the lower plate portion 520, the connecting portion 530, The fastening hole 512, the second fastening hole 522, the second bolt insertion hole 524, and the protection cap 550 are all formed identically.

다만, 본 실시예의 말뚝 이음장치(500)는 제1이음말뚝(40)이 강관(40a)과 콘크리트(40b)가 복합된 강관 콘크리트 말뚝인 경우에 사용되는 것으로, 상기 상판부(510)의 둘레에 상기 강관(40a)이 안착되는 안착홈(515)이 형성된다는 점이 다르다.The pile joint device 500 of the present embodiment is used when the first joint pile 40 is a steel pipe concrete pile in which a steel pipe 40a and a concrete 40b are combined. And a seat groove 515 in which the steel pipe 40a is seated is formed.

즉 본 실시예의 경우, 도 14와 같이 강관(40a)이 안착홈(515)에 안정적으로 안착된 상태로 제1이음말뚝(40) 및 제2이음말뚝(20)이 서로 연결될 수 있다.That is, in this embodiment, the first joint pile 40 and the second joint pile 20 can be connected to each other in a state where the steel pipe 40a is stably installed in the seating groove 515 as shown in Fig.

도 15는 본 발명의 제6실시예에 따른 말뚝 이음장치(600)의 모습을 확대한 모습을 나타낸 사시도이며, 도 16은 본 발명의 제6실시예에 따른 말뚝 이음장치(600)로 제1이음말뚝(50) 및 제2이음말뚝(20)을 서로 연결한 모습을 나타낸 단면도이다.FIG. 15 is a perspective view showing an enlarged view of a pile joining apparatus 600 according to a sixth embodiment of the present invention. FIG. 16 is a pile joining apparatus 600 according to a sixth embodiment of the present invention, Sectional view showing a joint pile 50 and a second joint pile 20 connected to each other.

도 15 및 도 16에 도시된 바와 같이, 본 발명의 제6실시예에 따른 말뚝 이음장치(600)의 경우, 전술한 제5실시예와 상판부(610), 하판부(620), 연결부(630), 제2체결홀(622), 제2볼트삽입홀(624) 및 보호캡(650)이 모두 동일하게 형성된다. 다만 본 실시예에 따른 말뚝 이음장치(600)는 제1이음말뚝(50)이 강관말뚝 형태일 경우 사용되는 것으로서, 제1체결홀이 생략된 형태를 가진다.As shown in FIGS. 15 and 16, in the pile driving apparatus 600 according to the sixth embodiment of the present invention, the upper plate 610, the lower plate 620, the connecting portion 630 The second fastening hole 622, the second bolt insertion hole 624, and the protection cap 650 are formed in the same manner. However, the pile joint device 600 according to the present embodiment is used when the first joint pile 50 is in the form of a steel pipe pile, and the first joint hole is omitted.

즉 제1이음말뚝(50)이 강관말뚝인 경우 콘크리트 부분과 체결하기 위한 구성이 구비될 필요가 없으므로, 이와 같이 제1체결홀이 생략된 형태로 형성되는 것이다. 이때 상기 상판부(610)에는 상기 제1이음말뚝(50)이 안착되는 안착홈(515)이 형성되는 것은 전술한 제5실시예와 같다.That is, when the first joint pile 50 is a steel pipe pile, it is not necessary to provide a structure for fastening to the concrete portion. Thus, the first fastening hole is omitted. At this time, the upper plate portion 610 is formed with a seating groove 515 in which the first joint pile 50 is seated, as in the fifth embodiment described above.

이상으로, 본 발명의 각 실시예에 대해 설명하였다. 이하에서는, 본 발명에 따른 말뚝 이음장치를 이용하여 말뚝을 시공하는 과정에 대해 설명하도록 하며, 대표적으로 제1실시예 및 제2실시예를 선택하였다.In the foregoing, each embodiment of the present invention has been described. Hereinafter, a process of constructing a pile using a pile joining apparatus according to the present invention will be described, and the first and second embodiments are selected as representatives.

도 17은 본 발명의 제1실시예에 따른 말뚝 이음장치(100)를 이용하여 제1이음말뚝(10) 및 제2이음말뚝(20)을 연결하는 과정을 나타낸 단면도이다.17 is a sectional view showing a process of connecting the first joint pile 10 and the second joint pile 20 using the pile joint 100 according to the first embodiment of the present invention.

도 17에 도시된 바와 같이, 본 발명의 제1실시예에 따른 말뚝 이음장치(100)를 이용하여 제1이음말뚝(10) 및 제2이음말뚝(20)을 연결하는 과정은, 먼저 (a) 및 (b)와 같이, 제1체결홀(112)에 체결볼트(160)를 삽입하여 상판부와 제1이음말뚝(10)을 체결하게 된다.17, the process of connecting the first joint pile 10 and the second joint pile 20 using the pile joint 100 according to the first embodiment of the present invention includes the steps of (a The fastening bolt 160 is inserted into the first fastening hole 112 to fasten the first joint pile 10 to the upper plate.

이후 (b) 및 (c)와 같이, 제2체결홀(122)에 체결볼트(160)를 삽입하여 하판부와 제2이음말뚝(20)을 체결하게 된다. 이에 따라 상기 제1이음말뚝(10) 및 상기 제2이음말뚝(20)은 서로 안정적으로 연결될 수 있다.The fastening bolt 160 is inserted into the second fastening hole 122 to fasten the lower plate and the second joint pile 20 as shown in FIGS. Accordingly, the first joint pile (10) and the second joint pile (20) can be stably connected to each other.

이후 (c) 및 (d)와 같이, 보호캡(150)을 제2볼트삽입홀(124)에 삽입하게 되며, 이에 따라 제2이음말뚝(20)에 체결된 체결볼트(160)는 보호캡(150)에 의해 외부에 노출되지 않게 된다. 이상으로 말뚝의 시공이 완료된다.The protective cap 150 is inserted into the second bolt insertion hole 124 and the fastening bolt 160 fastened to the second joint pile 20 is inserted into the second bolt insertion hole 124 as shown in (c) and (d) (Not shown). Thus, the construction of the pile is completed.

한편 본 실시예의 경우 제1이음말뚝(10)과 말뚝 이음장치(100)가 체결볼트(160)에 의해 체결되는 것으로 하였으나, 상기 말뚝 이음장치(100)가 제1이음말뚝(10)의 강봉(12)에 의해 일체로 제조되는 형태 역시 상기와 같은 순서가 적용될 수 있음은 물론이다.In the present embodiment, the first joint pile 10 and the pile joint 100 are fastened by the fastening bolts 160. However, when the pile joint device 100 is fastened to the steel rods 10 of the first joint pile 10 12 may be manufactured in the same manner as described above.

도 18은 본 발명의 제2실시예에 따른 말뚝 이음장치(200)를 이용하여 제1이음말뚝(10) 및 제2이음말뚝(20)을 연결하는 과정을 나타낸 단면도이다.18 is a cross-sectional view illustrating a process of connecting the first joint pile 10 and the second joint pile 20 using the pile joint apparatus 200 according to the second embodiment of the present invention.

도 18에 도시된 제2실시예에 따른 말뚝 이음장치(200)의 시공 과정 역시, 전술한 제1실시예의 시공 과정과 동일하다.The construction process of the pile joint device 200 according to the second embodiment shown in FIG. 18 is also the same as the construction process of the first embodiment.

다만, 전술한 바와 같이 본 실시예의 경우 제3볼트삽입홀(226)이 더 형성되므로 상기 제2볼트삽입홀(224)의 높이는 체결볼트(260)의 높이보다 낮게 형성될 수 있으며, 이와 같은 경우 체결볼트(260)를 제2볼트삽입홀(224)로 삽입할 수 없게 된다.However, since the third bolt insertion hole 226 is further formed in the present embodiment, the height of the second bolt insertion hole 224 may be lower than the height of the bolt 260. In this case, The fastening bolt 260 can not be inserted into the second bolt insertion hole 224.

따라서 본 실시예에 따른 시공 과정은, (b) 및 (c)와 같이 상기 말뚝 이음장치(200)의 상판부와 상기 제1이음말뚝(10)을 체결하는 단계 이전에, (a)와 같이 상기 제3볼트삽입홀(226)을 통해 상기 체결볼트(260)를 상기 제2체결홀(222)에 미리 삽입하는 단계가 더 포함될 수 있다.Therefore, according to the present embodiment, as shown in (b) and (c), before the step of fastening the upper joint part of the pile joint device 200 and the first joint pile 10, The step of inserting the fastening bolt 260 into the second fastening hole 222 through the third bolt insertion hole 226 may be further included.

이와 같이 하는 이유는 상기 말뚝 이음장치(200)의 상판부와 상기 제1이음말뚝(10)이 서로 체결된 이후에는, 제3볼트삽입홀(226)이 차폐되기 때문이다.This is because the third bolt insertion hole 226 is shielded after the upper joint part of the pile joint device 200 and the first joint pile 10 are fastened to each other.

그리고 이후 시공 과정은, 전술한 제1실시예의 시공 과정과 동일하게 수행된다.Then, the construction process is performed in the same manner as the construction process of the first embodiment.

도 19은 본 발명의 제2실시예에 따른 말뚝 이음장치(200)를 이용하여 제1이음말뚝(10) 및 제2이음말뚝(20)을 연결하는 과정을 다른 단면에서 나타낸 단면도이다.FIG. 19 is a sectional view showing another cross-section of a process of connecting a first joint pile 10 and a second joint pile 20 using a pile joint device 200 according to a second embodiment of the present invention.

도 19는 도 18과 동일한 시공 과정을 나타내는 것이나, 도 18은 도 7을 기준으로 A-A단면을 나타낸 반면, 도 19는 B-B단면을 나타낸 것이다. 이는 제2실시예의 경우 제2체결홀(222) 중 일부에는 일반적인 체결볼트(260, 도 18 참조)와 다른 형태의 체결볼트(270)가 적용되기 때문이다.FIG. 19 shows the same construction as FIG. 18, but FIG. 18 shows a cross section taken along the line A-A in FIG. 7, and FIG. 19 shows a cross section taken along the line B-B. This is because, in the case of the second embodiment, a part of the second fastening holes 222 is applied with a fastening bolt 260 (see FIG. 18) and another fastening bolt 270.

구체적으로 B-B단면의 제2체결홀(222)에 체결되는 체결볼트(270)는, 서로 결합 가능하도록 분리된 머리부(270a) 및 나사부(270b)를 포함하는 형태로 형성된다.Specifically, the fastening bolt 270 fastened to the second fastening hole 222 of the B-B cross section is formed to include a head 270a and a threaded portion 270b which are separated so as to be mutually engageable.

이와 같은 다른 형태의 체결볼트(270)를 사용하는 이유는, 제1이음말뚝(10)과 말뚝 이음장치(200)를 상호 결합한 이후, 제2이음말뚝(20)의 강봉너트(24)와 제2체결홀(222)의 위치를 정확하고 용이하게 맞추기 위해서이다.The reason for using the other type of fastening bolts 270 is that after the first joint pile 10 and the pile joint device 200 are coupled to each other, the steel rod nut 24 of the second joint pile 20, So that the position of the two fastening holes 222 can be precisely and easily adjusted.

즉 (c)에 나타난 바와 같이, 체결볼트(270)의 나사부(270b)를 제2이음말뚝(20)의 강봉너트(24)에 먼저 체결한 뒤, 돌출된 나사부(270b)에 제2체결홀(222)을 맞추어 삽입하도록 하는 방법으로 용이하게 제2이음말뚝(20)의 강봉너트(24)와 제2체결홀(222)의 위치를 맞출 수 있다. 이후 (c) 및 (d)와 같이 체결볼트(270)의 머리부(270a)를 제2볼트삽입홀(224)로 삽입하여, 나사부(270b)와 결합함으로써 제2이음말뚝(20)과 말뚝 이음장치(200)의 결합을 완료할 수 있다.The threaded portion 270b of the fastening bolt 270 is first fastened to the steel rod nut 24 of the second jointed pile 20 and then the fastening bolt 270 is fastened to the projected threaded portion 270b as shown in (c) It is possible to align the positions of the steel bar nuts 24 and the second fastening holes 222 of the second joint pile 20 with each other by inserting the fastening bolts 222 in alignment with each other. The head portion 270a of the fastening bolt 270 is inserted into the second bolt insertion hole 224 and the fastening bolt 270 is coupled with the screw portion 270b as shown in FIGS. The coupling of the coupling device 200 can be completed.

한편 전술한 바와 같이, 다른 형태의 체결볼트(270)가 삽입되는 제2체결홀(222)에는 인출홈(223, 도 7 참조)이 형성될 수 있다. 이는 나사부(270b)를 이용하여 제1이음말뚝(10) 및 제2이음말뚝(20)을 접합한 이후 인출하고, 일반적인 체결볼트(260)를 사용하는 경우에 이용되는 것으로서, 나사부(270b)의 인출을 용이하게 하기 위하여 형성되는 것이다.Meanwhile, as described above, the second fastening hole 222 into which the other fastening bolts 270 are inserted may be formed with the lead-out groove 223 (see FIG. 7). This is used when the first joint pile 10 and the second joint pile 20 are joined by using the screw portion 270b and then pulled out and a general fastening bolt 260 is used. It is formed to facilitate withdrawal.

그리고 인출홈(223)의 또다른 목적은, 체결볼트(270)을 사용하는 대신 나사부가 형성되지 않은 봉 형태의 가이드핀(미도시)을 사용하여 제1이음말뚝(10) 및 제2이음말뚝(20)을 접합한 후, 상기 가이드핀을 용이하게 인출하고 일반적인 체결볼트(260)를 제2체결홀(222)에 용이하게 삽입하기 위한 것이다. 이때 상기 인출홈(223)에 의해 상기 제2볼트삽입홀(224)의 높이가 체결볼트(260)의 높이보다 낮아도 볼트를 삽입할 수 있게 된다.Another purpose of the lead groove 223 is to form a first joint pile 10 and a second joint pile 30 by using a rod-shaped guide pin (not shown) The guide pin is easily drawn out and the general fastening bolt 260 is easily inserted into the second fastening hole 222 after the fastening bolt 260 is fastened. At this time, even if the height of the second bolt insertion hole 224 is lower than the height of the fastening bolt 260 by the lead groove 223, the bolt can be inserted.

또한 상기 인출홈은 경사지게 형성되어, 일반적인 체결볼트(260)를 제2볼트삽입홀(224)로 삽입하는 경우 그 경사면에 의해 삽입이 용이하도록 할 수도 있다.In addition, when the general fastening bolt 260 is inserted into the second bolt insertion hole 224, it may be easily inserted by the inclined surface.

추가적으로, 상기 나사부(270b)에는 나사부(270b)의 결합 시 회전을 용이하게 하기 위해, 렌치가 걸리도록 하는 렌치홈 또는 핀이 삽입되는 핀홀 등이 형성될 수 있다.
In addition, the screw portion 270b may be formed with a wrench groove or a pin hole into which the wrench 270 is inserted to facilitate rotation when the screw portion 270b is engaged.

이상과 같이 본 발명에 따른 바람직한 실시예를 살펴보았으며, 앞서 설명된 실시예 이외에도 본 발명이 그 취지나 범주에서 벗어남이 없이 다른 특정 형태로 구체화될 수 있다는 사실은 해당 기술에 통상의 지식을 가진 이들에게는 자명한 것이다. 그러므로, 상술된 실시예는 제한적인 것이 아니라 예시적인 것으로 여겨져야 하고, 이에 따라 본 발명은 상술한 설명에 한정되지 않고 첨부된 청구항의 범주 및 그 동등 범위 내에서 변경될 수도 있다.It will be apparent to those skilled in the art that the present invention can be embodied in other specific forms without departing from the spirit or scope of the invention as defined in the appended claims. It is obvious to them. Therefore, the above-described embodiments are to be considered as illustrative rather than restrictive, and the present invention is not limited to the above description, but may be modified within the scope of the appended claims and equivalents thereof.

10: 제1이음말뚝 12: 강봉
14: 강봉너트 20: 제2이음말뚝
22: 강봉 24: 강봉너트
100: 말뚝 이음장치 110: 상판부
112: 제1체결홀 114: 제1볼트삽입홀
120: 하판부 122: 제2체결홀
124: 제2볼트삽입홀 130: 연결부
150: 보호캡 152: 수용홈
160: 체결볼트
10: First joint pile 12: Steel bar
14: Steel rod nut 20: Second joint stake
22: Steel rod 24: Steel rod nut
100: pile joining device 110: upper plate
112: first fastening hole 114: first bolt insertion hole
120: lower plate portion 122: second fastening hole
124: second bolt insertion hole 130:
150: protective cap 152: receiving groove
160: fastening bolt

Claims (21)

제1이음말뚝의 일단에 연결되며, 상기 제1이음말뚝과의 체결을 위한 복수의 제1체결홀이 둘레를 따라 형성된 상판부;
제2이음말뚝의 일단에 연결되며, 상기 제2이음말뚝과의 체결을 위한 복수의 제2체결홀이 둘레를 따라 형성되되, 상기 제2체결홀은 상기 제1체결홀과 어긋난 위치에 형성된 하판부;
상기 상판부와 상기 하판부 사이에 구비되는 연결부;
상기 제1체결홀의 하측으로 상기 하판부 및 상기 연결부를 관통하여 상기 제1체결홀에 연통되며, 상기 제1이음말뚝의 일단과 체결되는 체결볼트가 통과되어 상기 체결볼트의 머리가 수용되는 제1볼트삽입홀; 및
상기 연결부의 외경 방향으로 개구되고, 상기 제2체결홀에 연통되는 제2볼트삽입홀;
을 포함하는 말뚝 이음장치.
A top joint part connected to one end of the first joint pile and having a plurality of first fastening holes for fastening with the first joint pile;
A plurality of second coupling holes for coupling with the second coupling pile are formed along the periphery of the second coupling pile, and the second coupling holes are connected to one end of the second coupling pile, part;
A connection portion provided between the upper plate portion and the lower plate portion;
A first joint piercing through the lower plate portion and the connecting portion to the lower side of the first fastening hole and communicating with the first fastening hole so that the fastening bolt fastened to one end of the first joint pile is passed, Bolt insertion hole; And
A second bolt insertion hole opened in an outer diameter direction of the connection portion and communicating with the second connection hole;
And a pile coupling device.
제1항에 있어서,
상기 제1체결홀은,
상기 제1체결홀에 삽입되어 상기 제1이음말뚝의 강봉너트에 체결되는 체결볼트에 대응되도록 형성된 말뚝 이음장치.
The method according to claim 1,
Wherein the first fastening hole
And the pivot shaft is inserted into the first fastening hole to correspond to the fastening bolt fastened to the steel rod nut of the first joint pile.
삭제delete 삭제delete 삭제delete 제1항에 있어서,
상기 제2체결홀은,
상기 제2체결홀에 삽입되어 상기 제2이음말뚝의 강봉너트에 체결되는 체결볼트에 대응되도록 형성된 말뚝 이음장치.
The method according to claim 1,
The second fastening hole
And the second bolt is inserted into the second bolt hole to correspond to a fastening bolt fastened to a steel bar nut of the second joint pile.
삭제delete 제1항에 있어서,
상기 상판부에는,
상기 제2체결홀에 대응되는 위치를 가지는 제3볼트삽입홀이 더 형성된 말뚝 이음장치.
The method according to claim 1,
In the upper plate portion,
And a third bolt insertion hole having a position corresponding to the second fastening hole.
제8항에 있어서,
상기 제2볼트삽입홀 및 상기 제3볼트삽입홀은 서로 연결되어 개구된 형상을 가지는 말뚝 이음장치.
9. The method of claim 8,
And the second bolt insertion hole and the third bolt insertion hole are connected to each other to have an opening shape.
제1항에 있어서,
상기 제2볼트삽입홀에 삽입되어 상기 제2체결홀에 체결된 체결볼트의 머리부를 보호하는 보호캡을 더 포함하는 말뚝 이음장치.
The method according to claim 1,
And a protective cap inserted in the second bolt insertion hole to protect a head portion of a fastening bolt fastened to the second fastening hole.
제10항에 있어서,
상기 보호캡의 외측은 상기 연결부 외경의 곡률에 대응되는 곡률로 형성된 말뚝 이음장치.
11. The method of claim 10,
And the outer side of the protective cap has a curvature corresponding to a curvature of the outer diameter of the connecting portion.
제10항에 있어서,
상기 보호캡에는 상기 체결볼트의 머리부가 수용되는 수용홈이 형성된 말뚝 이음장치.
11. The method of claim 10,
Wherein the protection cap has a receiving groove for receiving a head of the fastening bolt.
제6항에 있어서,
상기 복수의 제2체결홀에 체결되는 체결볼트 중 일부 제2체결홀에 체결되는 체결볼트는 서로 결합 가능하도록 분리된 머리부 및 나사부를 포함하는 형태로 형성된 말뚝 이음장치.
The method according to claim 6,
Wherein the fastening bolts fastened to a part of the second fastening holes of the fastening bolts fastened to the plurality of second fastening holes include a head portion and a screw portion which are separated from each other to be able to be engaged with each other.
제6항에 있어서,
상기 복수의 제2체결홀 중 일부 제2체결홀에는 가이드핀이 결합되고, 상기 가이드핀이 결합되는 제2체결홀은 상기 가이드핀을 제거하기 위한 인출홈을 더 포함하는 말뚝 이음장치.
The method according to claim 6,
Wherein a guide pin is coupled to a part of the second fastening holes of the plurality of second fastening holes and a second fastening hole to which the guide pin is coupled further includes a lead groove for removing the guide pin.
삭제delete 삭제delete 삭제delete 제1이음말뚝의 일단에 연결되며, 상기 제1이음말뚝과의 체결을 위한 복수의 제1체결홀이 둘레를 따라 형성된 상판부와, 제2이음말뚝의 일단에 연결되며, 상기 제2이음말뚝과의 체결을 위한 복수의 제2체결홀이 둘레를 따라 형성되되, 상기 제2체결홀은 상기 제1체결홀과 어긋난 위치에 형성된 하판부와, 상기 상판부와 상기 하판부 사이에 구비되는 연결부와, 상기 제1체결홀의 하측으로 상기 하판부 및 상기 연결부를 관통하여 상기 제1체결홀에 연통되며, 상기 제1이음말뚝의 일단과 체결되는 체결볼트가 통과되어 상기 체결볼트의 머리가 수용되는 제1볼트삽입홀과, 상기 연결부의 외경 방향으로 개구되고, 상기 제2체결홀에 연통되는 제2볼트삽입홀을 포함하는 말뚝 이음장치를 이용한 말뚝 시공방법에 있어서,
상기 제1볼트삽입홀을 통해 상기 제1체결홀에 체결볼트를 삽입하여 상기 상판부와 상기 제1이음말뚝을 체결하는 단계; 및
상기 제2볼트삽입홀을 통해 상기 제2체결홀에 체결볼트를 삽입하여 상기 하판부와 상기 제2이음말뚝을 체결하는 단계;
를 포함하는 말뚝 시공방법.
A first joint pile connected to one end of the first joint pile and having a plurality of first fastening holes for fastening the first joint pile to the first joint pile, the first joint pile being connected to one end of the second joint pile, Wherein the second fastening holes are formed at positions displaced from the first fastening holes, a connecting portion provided between the upper plate and the lower plate, A first joint piercing through the lower plate portion and the connecting portion to the lower side of the first fastening hole and communicating with the first fastening hole so that the fastening bolt fastened to one end of the first joint pile is passed, And a second bolt insertion hole which is opened in an outer diameter direction of the connection portion and communicates with the second fastening hole, the method comprising:
Inserting a fastening bolt into the first fastening hole through the first bolt insertion hole to fasten the upper joint part and the first joint pile; And
Inserting a fastening bolt into the second fastening hole through the second bolt insertion hole to fasten the lower plate and the second joint pile;
And the pile construction method.
제18항에 있어서,
상기 상판부에는 상기 제2체결홀에 대응되는 위치를 가지는 제3볼트삽입홀이 더 형성되고, 상기 연결부의 높이는 상기 체결볼트의 높이보다 낮게 형성되며,
상기 상판부와 상기 제1이음말뚝을 체결하는 단계 이전에는,
상기 제3볼트삽입홀을 통해 상기 체결볼트를 상기 제2체결홀에 삽입하는 단계가 더 포함되는 말뚝 시공방법.
19. The method of claim 18,
The upper plate portion is further provided with a third bolt insertion hole having a position corresponding to the second fastening hole, the height of the connection portion is lower than the height of the fastening bolt,
Before the step of fastening the upper joint part and the first joint pile,
And inserting the fastening bolt through the third bolt insertion hole into the second fastening hole.
제18항에 있어서,
상기 복수의 제2체결홀 중 일부 제2체결홀에 체결되는 상기 체결볼트는 서로 결합 가능하도록 분리된 머리부 및 나사부를 포함하는 형태로 형성되며,
상기 하판부와 상기 제2이음말뚝을 체결하는 단계 이전에는,
상기 제2이음말뚝에 구비된 강봉너트 중 일부에 상기 나사부를 결합하는 단계가 더 포함되는 말뚝 시공방법.
19. The method of claim 18,
The fastening bolts fastened to a part of the second fastening holes of the plurality of second fastening holes are formed in a shape including a separated head and a threaded portion so as to be able to be engaged with each other,
Before the step of fastening the lower joint part and the second joint pile,
And joining the threaded portion to a portion of the steel bar nut provided on the second joint pile.
제18항에 있어서,
상기 복수의 제2체결홀 중 일부 제2체결홀에는 봉 형태의 가이드핀이 결합되며,
상기 하판부와 상기 제2이음말뚝을 체결하는 단계 이전에는,
상기 제2이음말뚝에 구비된 강봉너트 중 일부에 상기 가이드핀을 결합하는 단계가 더 포함되며,
상기 하판부와 상기 제2이음말뚝을 체결하는 단계 이후에는,
상기 가이드핀을 상기 제2체결홀로부터 제거하는 단계가 더 포함되는 말뚝 시공방법.
19. The method of claim 18,
Wherein a rod-shaped guide pin is coupled to a part of the second fastening holes of the plurality of second fastening holes,
Before the step of fastening the lower joint part and the second joint pile,
Further comprising coupling the guide pin to a part of the steel bar nut provided on the second joint pile,
After the step of fastening the lower joint part and the second joint pile,
And removing the guide pin from the second fastening hole.
KR1020140160403A 2014-11-17 2014-11-17 Up-Down Combination Type Pile Connecting Apparatus and Pile Construction Method Using the Same KR101535863B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140160403A KR101535863B1 (en) 2014-11-17 2014-11-17 Up-Down Combination Type Pile Connecting Apparatus and Pile Construction Method Using the Same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140160403A KR101535863B1 (en) 2014-11-17 2014-11-17 Up-Down Combination Type Pile Connecting Apparatus and Pile Construction Method Using the Same

Publications (1)

Publication Number Publication Date
KR101535863B1 true KR101535863B1 (en) 2015-07-13

Family

ID=53793047

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140160403A KR101535863B1 (en) 2014-11-17 2014-11-17 Up-Down Combination Type Pile Connecting Apparatus and Pile Construction Method Using the Same

Country Status (1)

Country Link
KR (1) KR101535863B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190085734A (en) 2018-01-11 2019-07-19 이광영 Joining device of file
KR20190120576A (en) 2018-04-16 2019-10-24 박인수 Connecting device for PHC pile with improve workability and assembling method of PHC pile using it
KR20190127507A (en) 2018-05-03 2019-11-13 백기원 lifting device for PHC pile and piling method of PHC pile using the same
KR102128820B1 (en) 2019-04-01 2020-07-01 김기웅 Coupling apparatus for non-welding of pile
KR102170104B1 (en) 2019-06-26 2020-10-27 김기웅 Coupling apparatus for non-welding of pile
KR20210128169A (en) 2020-04-16 2021-10-26 이광영 Joining device of file
KR102340773B1 (en) * 2020-11-12 2021-12-17 주식회사 택한 Connector of PHC piles and connection method of PHC pile using the same

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100870859B1 (en) * 2008-03-26 2008-11-27 이호경 The coupling structure of pretentioned spun high strength concrete piles
KR20140122460A (en) * 2013-04-10 2014-10-20 (주)스마텍엔지니어링 Connecting Structure and Method of PHC Piles

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100870859B1 (en) * 2008-03-26 2008-11-27 이호경 The coupling structure of pretentioned spun high strength concrete piles
KR20140122460A (en) * 2013-04-10 2014-10-20 (주)스마텍엔지니어링 Connecting Structure and Method of PHC Piles

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20190085734A (en) 2018-01-11 2019-07-19 이광영 Joining device of file
KR20190120576A (en) 2018-04-16 2019-10-24 박인수 Connecting device for PHC pile with improve workability and assembling method of PHC pile using it
KR102065504B1 (en) 2018-04-16 2020-01-13 박인수 Connecting device for PHC pile with improve workability and assembling method of PHC pile using it
KR20190127507A (en) 2018-05-03 2019-11-13 백기원 lifting device for PHC pile and piling method of PHC pile using the same
KR102128820B1 (en) 2019-04-01 2020-07-01 김기웅 Coupling apparatus for non-welding of pile
KR102170104B1 (en) 2019-06-26 2020-10-27 김기웅 Coupling apparatus for non-welding of pile
KR20210128169A (en) 2020-04-16 2021-10-26 이광영 Joining device of file
KR102340773B1 (en) * 2020-11-12 2021-12-17 주식회사 택한 Connector of PHC piles and connection method of PHC pile using the same

Similar Documents

Publication Publication Date Title
KR101535863B1 (en) Up-Down Combination Type Pile Connecting Apparatus and Pile Construction Method Using the Same
US9127421B2 (en) Bollards
KR101945369B1 (en) Connecting device for PHC pile and manufacturing method thereof
JP5156845B2 (en) Cable-type road protection fence
CN102400463B (en) Ground-grabbing device
JP4936232B2 (en) Protective bodies such as avalanches and rockfalls
JP5718861B2 (en) Construction method of pile-type pier
JP4753426B2 (en) Steel pipe joints
JP4741386B2 (en) Joining method and structure of wood structure materials
KR101448145B1 (en) Column Integrated Footing
KR101855458B1 (en) Composite pile
KR20180007292A (en) Connecting device for PHC pile
JP2016108742A (en) Post unit
JP4310812B1 (en) Protective fence reinforcement method
KR101192633B1 (en) Coupling apparatus of pile
JP3146282U (en) Protective fence
KR200426656Y1 (en) Head reinforced apparatus for steel pipe
KR101252027B1 (en) Coupling apparatus of pile
KR20140131648A (en) Coupling apparatus of pile using coupler integrated pc nut
KR101894235B1 (en) Bearing Power Reinforcement Structure for Support of Guard Rail
KR20140096872A (en) Serial connection apparatus of pile
JP6541473B2 (en) Legal frame movement prevention method and system
KR101601876B1 (en) Composite Pile Connecting Apparatus and Composite Pile Construction Method Using the Same
JP2014020017A (en) Pile head structure and construction method for the same
JP2012241392A (en) Existing foundation reinforcement method and existing foundation reinforcement structure

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
J206 Request for trial to confirm the scope of a patent right
J301 Trial decision

Free format text: TRIAL NUMBER: 2017100000300; TRIAL DECISION FOR CONFIRMATION OF THE SCOPE OF RIGHT_AFFIRMATIVE REQUESTED 20170203

Effective date: 20171031

J204 Invalidation trial for patent
J301 Trial decision

Free format text: TRIAL NUMBER: 2018100000241; TRIAL DECISION FOR INVALIDATION REQUESTED 20180124

Effective date: 20180521

J121 Written withdrawal of request for trial
FPAY Annual fee payment

Payment date: 20180702

Year of fee payment: 4

J122 Written withdrawal of action (patent court)
J121 Written withdrawal of request for trial
J122 Written withdrawal of action (patent court)
FPAY Annual fee payment

Payment date: 20190706

Year of fee payment: 5