KR101317753B1 - The bridge construction technique for which a construction cable was used - Google Patents

The bridge construction technique for which a construction cable was used Download PDF

Info

Publication number
KR101317753B1
KR101317753B1 KR1020120024332A KR20120024332A KR101317753B1 KR 101317753 B1 KR101317753 B1 KR 101317753B1 KR 1020120024332 A KR1020120024332 A KR 1020120024332A KR 20120024332 A KR20120024332 A KR 20120024332A KR 101317753 B1 KR101317753 B1 KR 101317753B1
Authority
KR
South Korea
Prior art keywords
cable
coupled
steel formwork
vertical
longitudinal direction
Prior art date
Application number
KR1020120024332A
Other languages
Korean (ko)
Other versions
KR20130103028A (en
Inventor
김철수
Original Assignee
주식회사 동호
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 동호 filed Critical 주식회사 동호
Priority to KR1020120024332A priority Critical patent/KR101317753B1/en
Publication of KR20130103028A publication Critical patent/KR20130103028A/en
Application granted granted Critical
Publication of KR101317753B1 publication Critical patent/KR101317753B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명에 따른 케이블을 이용한 콘크리트 가설 교량은, 양측 지반에 각각 설치되며, 상단에 제1케이블 설치부 및 제2케이블 설치부가 각각 형성되는 한 쌍의 교대와, 상기 제1케이블 설치부에 양단이 각각 결합되는 1차 케이블과, 상기 1차 케이블에 의해 지지되도록 교대들의 상단에 종 방향 양단이 각각 설치되고, 하단에는 종 방향을 따라 다수의 수직재 결합홀이 상하로 관통 형성되는 강재 거푸집과, 상기 수직재 결합홀에 상단이 결합되며, 상기 강재 거푸집의 종 방향을 따라 배치되는 다수의 수직재와, 상기 강재 거푸집에 설치되어 상기 수직재들의 상단에 지지되며, 종 방향 양단에 제3케이블 설치부가 각각 형성되는 상부 슬라브와, 상기 제2케이블 설치부들에 양단이 각각 결합되어, 상기 수직재들의 하단을 탄성 지지하는 2차 케이블 및, 상기 강재 거푸집과 상기 1차 케이블 및 상기 2차 케이블 철거 후, 양단이 상기 제3케이블 설치부에 각각 결합되어, 상기 수직재들의 하단을 탄성 지지하는 3차 케이블을 포함한다.Concrete temporary bridge using a cable according to the present invention is installed on both sides of the ground, a pair of alterations each having a first cable installation portion and a second cable installation portion is formed at the upper end, both ends of the first cable installation portion The primary cable is coupled to each other, and both ends in the longitudinal direction are respectively installed at the upper end of the shift so as to be supported by the primary cable, the lower end of the steel formwork is formed with a plurality of vertical material coupling holes are formed in the vertical direction; The upper end is coupled to the vertical coupling hole, a plurality of vertical members disposed along the longitudinal direction of the steel formwork, and are installed on the steel formwork and supported on the upper ends of the vertical members, respectively, the third cable installation portion is formed at both ends in the longitudinal direction, respectively. Both ends of the upper slab and the second cable installation portions are respectively coupled to the secondary cable to elastically support the lower ends of the vertical members, and the steel After removing the formwork, the primary cable and the secondary cable, both ends are respectively coupled to the third cable installation portion, and includes a tertiary cable that elastically supports the lower ends of the vertical members.

Description

케이블을 이용한 콘크리트 가설 교량{THE BRIDGE CONSTRUCTION TECHNIQUE FOR WHICH A CONSTRUCTION CABLE WAS USED}Concrete bridge with cable {THE BRIDGE CONSTRUCTION TECHNIQUE FOR WHICH A CONSTRUCTION CABLE WAS USED}

본 발명은 케이블을 이용한 콘크리트 가설 교량에 관한 것으로, 보다 상세하게는 철근 조립 및 콘크리트 타설이 어려운 지형에서도 용이하게 교량의 상판을 시공할 수 있는 케이블을 이용한 콘크리트 가설 교량에 관한 것이다.
The present invention relates to a concrete temporary bridge using a cable, and more particularly to a concrete temporary bridge using a cable that can be easily installed in the top plate of the bridge even in the terrain difficult to reinforce assembling and concrete placing.

일반적으로, 교량이란 하천, 호수, 해협, 만(灣), 운하, 저지 또는 다른 교통로나 구축물(構築物) 위를 건너갈 수 있도록 건설되는 고가구조물이다.In general, bridges are elevated structures that can be constructed to cross rivers, lakes, straits, bays, canals, lowlands, or other traffic or structures.

이러한, 교량은 강, 하천 등의 지반에 고정되는 교대 및 교각과, 상기 교대 및 교각에 지지되어 차량이나 사람 등이 소통할 수 있도록 하는 상판 등으로 구성된다.The bridge is composed of shifts and bridges fixed to the ground of rivers, rivers, and the like, and a top plate supported by the shifts and bridges to allow vehicles or people to communicate.

그러나 종래의 교량은, 수심이 깊거나 경사가 급한 지형 등에서는 상판 시공을 위찬 철근 조립 및 콘크리트 타설 과정이 어려운 문제점이 있었다.
However, in the conventional bridges, rebar assembly and concrete placing process for the construction of the top plate is difficult in the depth of the deep or steep terrain.

본 발명과 관련된 문헌으로는 대한민국 공개특허 제10-2010-0025163호(2010년 03월 09일)이 있으며, 상기 문헌에는 유지관리가 용이한 PSC 거더교 시공방법 및 이에 사용되는 교대 벽체구조가 개시되어 있다.
Documents related to the present invention include Korean Patent Application Publication No. 10-2010-0025163 (March 09, 2010), which discloses a PSC girder bridge construction method and an alternate wall structure used therein for easy maintenance. have.

본 발명의 목적은 상부 슬라브가 설치되는 강재 거푸집의 하단에 교각의 역할을 하는 수직재들을 설치하고, 수직재들의 하단을 지지 케이블로 탄성 지지함으로써, 철근 조립 및 콘크리트 타설이 어려운 지형에서도 용이하게 교량의 상판을 시공할 수 있는 케이블을 이용한 콘크리트 가설 교량을 제공하는데 있다.
An object of the present invention is to install the vertical members that act as a pier to the bottom of the steel formwork on which the upper slab is installed, and by elastically supporting the bottom of the vertical members with a support cable, the top plate of the bridge easily in the terrain difficult to reinforce assembling and concrete casting To provide a concrete bridge bridge using a cable that can be constructed.

본 발명은 양측 지반에 각각 설치되며, 상단에 제1케이블 설치부 및 제2케이블 설치부가 각각 형성되는 한 쌍의 교대와, 상기 제1케이블 설치부에 양단이 각각 결합되는 1차 케이블과, 상기 1차 케이블에 의해 지지되도록 교대들의 상단에 종 방향 양단이 각각 설치되고, 하단에는 종 방향을 따라 다수의 수직재 결합홀이 상하로 관통 형성되는 강재 거푸집과, 상기 수직재 결합홀에 상단이 결합되며, 상기 강재 거푸집의 종 방향을 따라 배치되는 다수의 수직재와, 상기 강재 거푸집에 설치되어 상기 수직재들의 상단에 지지되며, 종 방향 양단에 제3케이블 설치부ㄱ 각각 형성되는 상부 슬라브와, 상기 제2케이블 설치부들에 양단이 각각 결합되어, 상기 수직재들의 하단을 탄성 지지하는 2차 케이블 및, 상기 강재 거푸집과 상기 1차 케이블 및 상기 2차 케이블 철거 후, 양단이 상기 제3케이블 설치부에 각각 결합되어, 상기 수직재들의 하단을 탄성 지지하는 3차 케이블을 포함하는 것을 특징으로 한다.The present invention is installed on both sides of the ground, respectively, a pair of alternations each having a first cable installation portion and a second cable installation portion is formed on the top, the primary cable is coupled to both ends of the first cable installation portion, respectively, Both ends of the longitudinal direction are respectively installed at the upper end of the shifts to be supported by the primary cable, the lower end is a steel formwork formed with a plurality of vertical member coupling holes penetrating up and down along the longitudinal direction, the upper end is coupled to the vertical member coupling holes, A plurality of vertical members disposed along the longitudinal direction of the steel formwork, upper slabs installed on the steel formwork and supported at the upper ends of the vertical members, respectively having third cable installation portions a at both ends in the longitudinal direction, and the second cable Both ends are respectively coupled to the installation portions, the secondary cable for elastically supporting the lower ends of the vertical members, the steel formwork and the primary cable and the secondary cable After the removal of the block, both ends are respectively coupled to the third cable installation, characterized in that it comprises a tertiary cable for elastically supporting the lower ends of the vertical members.

여기서, 상기 강재 거푸집은 횡 방향으로 각각 분할 가능하도록 바닥 면에 종 방향을 따라 제1절개부 및, 상기 제1절개부를 연결하기 위한 제1연결부재가 결합되는 것이 바람직하다.Here, the steel formwork is preferably coupled to the first cutout portion along the longitudinal direction and the first connection member for connecting the first cutout portion to the bottom surface so as to be respectively divided in the transverse direction.

또한, 상기 제1연결부재는 상기 제1절개부의 상단 및 하단에 각각 결합되며, 상하로 다수의 제1체결홀이 형성되는 한 쌍의 제1연결판 및, 상기 제1체결홀들을 통해 삽입되어, 상기 강재 거푸집에 관통 경합되는 다수의 제1체결부재가 구비되는 것이 바람직하다.In addition, the first connection member is coupled to each of the upper end and the lower end of the first cutout, a pair of first connecting plate and a plurality of first fastening holes are formed up and down, and are inserted through the first fastening holes It is preferable that a plurality of first fastening members are provided through the steel formwork.

또한, 상기 수직재들의 하단에는 상기 1차 케이블이 측방으로 관통 결합되는 제1관통홀 및, 상기 제1관통홀의 하방에 형성되어, 상기 2차 케이블이 측방으로 관통 결합 되는 제2관통홀이 형성되는 것이 바람직하다.In addition, the lower end of the vertical member is formed with a first through-hole through which the primary cable is laterally coupled, and a second through-hole formed below the first through-hole, the second cable is coupled through the side It is preferable.

또한, 상기 수직재들의 상단은 상기 수직재 결합홀을 통해 상기 슬라브 설치홈 내에 돌출 위치되어, 상기 상부 슬라브와 일체로 결합되는 것이 바람직하다.In addition, the upper end of the vertical member is projected in the slab installation groove through the vertical member coupling hole, it is preferable to be integrally coupled to the upper slab.

또한, 상기 수직재들의 상단 테두리 부위에는 상하로 길이를 가지며, 하단이 상기 슬라브 설치홈의 바닥 면을 지지하는 다수의 가지지대가 더 구비되는 것이 바람직하다.In addition, the upper edge portion of the vertical member has a length up and down, the lower end is preferably further provided with a plurality of branches supporting the bottom surface of the slab installation groove.

또한, 상기 강재 거푸집의 횡 방향 양단에는 횡 방향으로 각각 분할이 가능하도록 종 방향을 따라 제2절개부가 형성되며, 상기 강재 거푸집의 종 방향을 따라 길이를 갖는 한 쌍의 작업발판이 더 설치되며, 상기 작업발판의 상단 및 하단에는 상기 제2절개부를 연결하기 위한 제2연결부재가 결합되는 것이 바람직하다.In addition, at both ends of the steel formwork in the transverse direction, the second cutout is formed along the longitudinal direction so as to be divided in the transverse direction, respectively, a pair of working scaffold having a length along the longitudinal direction of the steel formwork is further installed, It is preferable that a second connection member for connecting the second cutout is coupled to the top and bottom of the working scaffold.

또한, 상기 제2연결부재는 상기 제2절개부의 상단 및 하단에 각각 결합되며, 상하로 다수의 제1체결홀이 형성되는 한 쌍의 제2연결판 및, 상기 제1체결홀들을 통해 삽입되어, 상기 강재 거푸집에 관통결합되는 다수의 제1체결부재가 구비되는 것이 바람직하다.In addition, the second connection member is coupled to the upper and lower ends of the second cutout, respectively, a pair of second connecting plate and a plurality of first fastening holes are formed up and down and are inserted through the first fastening holes It is preferable that a plurality of first fastening members are penetrated to the steel formwork.

또한, 상기 제2절개부에는 상기 작업발판의 종 방향을 따라 보 삽입홀이 더 형성되며, 상기 보 삽입홀 내에는 상기 작업발판을 지지하기 위한 가로 보가 삽입되는 것이 바람직하다.
In addition, the second cutting portion is further formed with a beam insertion hole along the longitudinal direction of the working scaffold, it is preferable that a horizontal beam for supporting the working scaffold is inserted in the beam insertion hole.

본 발명은 강재 거푸집의 하단을 지지하는 수직재들을 설치하고, 수직재들의 하단이 지지 케이블에 의해 탄성 지지되도록 한 것으로, 철근 조립 및 콘크리트 타설이 어려운 지형에서도 용이하게 교량의 상판을 시공할 수 있는 효과를 갖는다.
The present invention is to install the vertical members supporting the lower end of the steel formwork, and the lower end of the vertical members to be elastically supported by a support cable, it is easy to construct the top plate of the bridge even in the terrain difficult to reinforce assembling and concrete casting Have

도 1은 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량을 가설한 상태를 보여주기 위한 측면도이다.
도 2는 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량의 설치를 완료한 상태를 보여주기 위한 측면도이다.
도 3은 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량에서 수직재와 2차 케이블 및 3차 케이블의 설치상태를 보여주기 위한 요부 단면도이다.
도 4는 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량에서 강재 거푸집을 보여주기 위한 단면도이다.
도 5는 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량에서 강재 거푸집의 작업발판을 보여주기 위한 도면이다.
1 is a side view for showing a state of installing a concrete temporary bridge using a cable according to the present invention.
Figure 2 is a side view for showing a state of completing the installation of a concrete temporary bridge using a cable according to the present invention.
Figure 3 is a cross-sectional view of the main part to show the installation state of the vertical member and the secondary cable and the tertiary cable in the concrete temporary bridge using the cable according to the present invention.
Figure 4 is a cross-sectional view for showing the steel formwork in the concrete temporary bridge using the cable according to the present invention.
5 is a view for showing the working scaffolding of the steel formwork in the concrete temporary bridge using the cable according to the present invention.

이하, 첨부된 도면을 참조하면서 본 발명에 따른 바람직한 실시 예를 상세히 설명하기로 한다.
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명의 이점 및 특징, 그리고 그것을 달성하는 방법은 첨부된 도면과 함께 상세하게 후술되어 있는 실시예들을 참조하면 명확해질 것이다.BRIEF DESCRIPTION OF THE DRAWINGS The advantages and features of the present invention and the manner of achieving it will become apparent with reference to the embodiments described in detail below with reference to the accompanying drawings.

그러나 본 발명은 이하에 개시되는 실시예들에 의해 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 것이며, 단지 본 실시예들은 본 발명의 개시가 완전하도록 하며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이며, 본 발명은 청구항의 범주에 의해 정의될 뿐이다.The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art. To fully disclose the scope of the invention to those skilled in the art, and the invention is only defined by the scope of the claims.

또한, 본 발명을 설명함에 있어 관련된 공지 기술 등이 본 발명의 요지를 흐리게 할 수 있다고 판단되는 경우 그에 관한 자세한 설명은 생략하기로 한다.
In the following description, well-known functions or constructions are not described in detail since they would obscure the invention in unnecessary detail.

도 1은 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량을 가설한 상태를 보여주기 위한 측면도이고, 도 2는 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량의 설치를 완료한 상태를 보여주기 위한 측면도이다.1 is a side view for showing the state of the concrete construction bridge using the cable according to the present invention, Figure 2 is a side view for showing a state of completing the installation of the concrete temporary bridge using the cable according to the present invention.

그리고, 도 3은 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량에서 수직재와 2차 케이블 및 3차 케이블의 설치상태를 보여주기 위한 요부 단면도이다.And, Figure 3 is a cross-sectional view of the main part for showing the installation state of the vertical member and the secondary cable and the tertiary cable in the concrete temporary bridge using the cable according to the present invention.

또한, 도 4는 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량에서 강재 거푸집을 보여주기 위한 단면도이며, 도 5는 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량에서 강재 거푸집의 작업발판을 보여주기 위한 도면이다.
In addition, Figure 4 is a cross-sectional view for showing the steel formwork in a concrete temporary bridge using a cable according to the invention, Figure 5 is a view for showing the working scaffolding of steel formwork in a concrete temporary bridge using a cable according to the present invention. .

도 1 내지 도 5에 도시한 바와 같이, 본 발명에 따른 케이블을 이용한 콘크리트 가설 교량은 한 쌍의 교대(100)와, 1차 케이블(200)과, 강재 거푸집(300)과, 다수의 수직재(400)와, 상부 슬라브(500)와, 2차 케이블(600) 및, 3차 케이블(700)을 포함한다.1 to 5, the concrete temporary bridge using the cable according to the present invention is a pair of alternating 100, the primary cable 200, steel formwork 300, a plurality of vertical materials ( 400, upper slab 500, secondary cable 600, and tertiary cable 700.

먼저, 상기 한 쌍의 교대(100)는 강, 하천(10) 등의 양측 지반에 각각 설치된다.First, the pair of shifts 100 are installed on both grounds, such as rivers and rivers 10, respectively.

그리고, 상기 교대(100)들의 상단에는 후술 될 1차 케이블(200)을 설치하기 위한 제1케이블 설치부(110)와, 후술 될 2차 케이블(600)을 설치하기 위한 제2케이블 설치부(120)가 각각 형성된다.The first cable installation unit 110 for installing the primary cable 200 to be described later, and the second cable installation unit for installing the secondary cable 600 to be described later (above the shifts 100) 120 is formed respectively.

상기 제1케이블 설치부(110)와 상기 제2케이블 설치부(120)는, 교대(100)들의 양측 면에 각각 형성될 수 있다.The first cable installation unit 110 and the second cable installation unit 120 may be formed on both side surfaces of the alternations 100, respectively.

여기서, 상기 제1케이블 설치부(110)와 제2케이블 설치부(120)에는 후술 될 1차 케이블(200) 및 2차 케이블(600)의 양단을 결합시키기 위한 결합구(미도시)가 설치될 수 있다.Here, the first cable installation unit 110 and the second cable installation unit 120 is provided with a coupling (not shown) for coupling both ends of the primary cable 200 and the secondary cable 600 which will be described later Can be.

상기 결합구는, 상기 1차 하부케이블(200)의 결합 및 분리 가능하도록 개폐 가능한 구조를 가질 수 있다.The coupler may have a structure that can be opened and closed to enable coupling and detachment of the primary lower cable 200.

1차 케이블(200)은, 양단을 1차 긴장시켜 교대(100)들의 상단에 형성된 제1케이블 설치부(110)에 고정한다. 여기서, 상기 1차 케이블(200)은 일정 강도를 갖는 금속 빔으로 제작될 수 있으며, The primary cable 200 is fixed to the first cable installation unit 110 formed on the upper end of the primary tension by the both ends of the primary tension (100). Here, the primary cable 200 may be made of a metal beam having a certain strength,

이때, 상기 1차 케이블(200)은 상기 제1케이블 설치부(110)에 양단이 고정된 상태에서 교대(100)들의 상단에서 수평으로 일직선을 이룰 수 있다.At this time, the primary cable 200 may form a straight line horizontally at the upper end of the shift 100 in a state where both ends are fixed to the first cable installation unit 110.

도 4와 도 5에 더 상세히 도시한 바와 같이, 강재 거푸집(300)은 1차 케이블(200)에 의해 지지되도록 교대(100)들의 상단에 종 방향 양단이 각각 설치된다.As shown in more detail in Figures 4 and 5, the steel formwork 300 is installed at both ends in the longitudinal direction at the top of the alternating 100 to be supported by the primary cable 200, respectively.

여기서, 상기 강재 거푸집(300)의 상단에는 종 방향을 따라 슬라브 설치홈(310)이 오목하게 형성된다.Here, the slab installation groove 310 is formed in the upper end of the steel formwork 300 along the longitudinal direction.

그리고, 상기 강재 거푸집(300)의 하단에는 종 방향을 따라 다수의 수직재 결합홀(320)이 상하로 관통 형성된다.In addition, a plurality of vertical material coupling holes 320 penetrate upward and downward along a longitudinal direction at a lower end of the steel formwork 300.

또한, 상기 강재 거푸집(300)은 횡 방향으로 각각 분할 가능하도록 슬라브 설치홈(310)의 바닥 면에는 종 방향을 따라 제1절개부(311)가 형성될 수 있다.In addition, the steel formwork 300 may be formed on the bottom surface of the slab installation groove 310 in the longitudinal direction so that the first cutout portion 311 along the longitudinal direction.

이와 더불어, 상기 슬라브 설치홈(310)의 상단 및 하단에는, 상기 제1절개부(311)를 연결하기 위한 제1연결부재(330)가 결합될 수 있다.In addition, a first connection member 330 for connecting the first cutout 311 may be coupled to an upper end and a lower end of the slab installation groove 310.

상기 제1연결부재(330)는, 제1절개부(311)의 상단 및 하단에 각각 결합되며, 상하로 다수의 제1체결홀이 형성되는 한 쌍의 제1연결판(331) 및, 상기 제1체결홀들을 통해 삽입되어 강재 거푸집(300)에 관통 결합되는 다수의 제1체결부재(332)가 구비될 수 있다.The first connection member 330 is coupled to the upper and lower ends of the first cutout portion 311, and a pair of first connection plates 331 having a plurality of first fastening holes formed up and down, and the A plurality of first fastening members 332 inserted into the first fastening holes and coupled to the steel formwork 300 may be provided.

상기 강재 거푸집(300)의 횡 방향 양단에는, 횡 방향으로 각각 분할 가능하도록 종 방향을 따라 제2절개부(351)가 형성되는 한 쌍의 작업발판(350)이 더 설치될 수 있다.At both ends of the steel formwork 300 in a lateral direction, a pair of working scaffolds 350 having a second cutout portion 351 formed along the longitudinal direction may be further installed to be split in the lateral direction.

상기 한 쌍의 작업발판(350)은, 강재 거푸집(300)의 종 방향을 따라 길이를 갖도록 설치될 수 있다.The pair of working scaffolding 350 may be installed to have a length along the longitudinal direction of the steel formwork 300.

그리고, 상기 작업발판(350)의 상단 및 하단에는 제2절개부(351)를 연결하기 위한 제2연결부재(360)가 결합될 수 있다.In addition, a second connection member 360 for connecting the second cutout 351 may be coupled to the upper and lower ends of the working scaffold 350.

상기 제2연결부재(360)는, 제2절개부(351)의 상단 및 하단에 각각 결합되며, 상하로 다수의 제2체결홀이 형성되는 한 쌍의 제2연결판(361) 및, 상기 제2체결홀들을 통해 삽입되어 강재 거푸집(300)에 관통 결합되는 다수의 제2체결부재(362)가 구비될 수 있다.The second connection member 360 is coupled to the upper and lower ends of the second cutout 351, respectively, and a pair of second connection plates 361 having a plurality of second fastening holes formed up and down, and the A plurality of second fastening members 362 may be provided to be inserted through the second fastening holes and coupled to the steel formwork 300.

여기서, 상기 제2절개부(351)에는 작업발판(350)의 종 방향을 따라 보 삽입홀(352)이 더 형성될 수 있다.Here, the beam insertion hole 352 may be further formed in the second cutout 351 along the longitudinal direction of the working footing 350.

또한, 상기 보 삽입홀(352) 내에는 작업발판(350)의 종 방향을 지지하여 강도를 보강하기 위한 가로보(370)가 삽입될 수 있다.In addition, a horizontal beam 370 may be inserted into the beam insertion hole 352 to reinforce strength by supporting the longitudinal direction of the working footing 350.

상기 가로보(370)는, 일정 강도를 갖는 금속 빔으로 제작될 수 있으며, 작업발판(350)의 강도를 보강하기 위한 용도로 사용된다.The cross beam 370 may be made of a metal beam having a certain strength, and is used for reinforcing the strength of the working scaffold 350.

즉, 상기 작업발판(350)은 제2연결부재(360)에 의해 용이하게 결합 및 분리시킬 수 있고, 이를 통해 가로보(370)를 용이하게 설치할 수 있다.That is, the working footing 350 can be easily coupled and separated by the second connection member 360, through which the horizontal beam 370 can be easily installed.

아울러, 강재 거푸집(300)의 슬라브 설치홈(310) 내에는 후술 될 상부 슬라브(500)의 콘크리트(520)가 양생 된 후, 용이하게 분리될 수 있도록 분리재(미도시)가 도포될 수 있다.In addition, after the concrete 520 of the upper slab 500 to be described later is cured in the slab installation groove 310 of the steel formwork 300, a separating material (not shown) may be applied to be easily separated. .

상기 분리재는, 폴리테트라플루오르에치렌(PTFE: Polytetrafluoroethylene) 등을 사용할 수 있다.As the separator, polytetrafluoroethylene (PTFE) may be used.

뿐만 아니라, 강재 거푸집(300)의 폭 방향 양단에는 종 방향을 따라 가이드홈이 형성된 레일(380)이 설치될 수 있다.In addition, rails 380 having guide grooves formed along the longitudinal direction may be installed at both ends of the steel formwork 300 in the width direction.

상기 레일(380)에는, 수동 또는 구동 모터의 구동력에 의해 이동할 수 있도록 작업차(미도시)가 슬라이드 이동가능하게 설치될 수 있다.Work rails (not shown) may be installed on the rails 380 so as to be movable by a driving force of a manual or driving motor.

도 3에 더 상세히 도시한 바와 같이, 다수의 수직재(400)는 상하로 길이를 갖도록 형성될 수 있으며, 금속 빔 또는 철근 콘크리트 등을 이용해 제작할 수 있다.As shown in more detail in FIG. 3, the plurality of vertical members 400 may be formed to have a length up and down, and may be manufactured using a metal beam or reinforced concrete.

이와 같은 상기 수직재(400)들은, 전술한 수직재 결합홀(320)에 상단이 관통 결합된 상태로 강재 거푸집(300)의 종 방향을 따라 다수로 배치될 수 있다.Such vertical members 400 may be disposed along the longitudinal direction of the steel formwork 300 in a state where the upper end is penetrated through the vertical member coupling hole 320 described above.

여기서, 상기 수직재(400)들의 하단에는 후술 될 2차 케이블(600)이 측방으로 관통 결합되어 후술 될 2차 케이블(600)이 측방으로 관통 결합되는 제1관통홀(420) 및, 상기 제1관통홀(420)의 상방에 형성되어, 후술 될 3차 케이블(700)이 측방으로 관통 결합되는 제2관통홀(430)이 형성된다.Here, a first through-hole 420 through which the secondary cable 600 to be described later penetrates laterally through the lower side of the vertical member 400 is coupled to the secondary cable 600 to be described later, and the first The second through hole 430 is formed above the through hole 420 to allow the tertiary cable 700 to be laterally coupled to the third hole 700.

그리고, 상기 수직재(400)들의 상단은 수직재 결합홀(320)을 통해 슬라브 설치홈(310) 내에 돌출 위치되어, 후술 될 상부 슬라브(500)와 일체로 결합되는 것이 바람직하다.In addition, the upper ends of the vertical members 400 protrude and are positioned in the slab installation groove 310 through the vertical member coupling holes 320, and are integrally coupled to the upper slab 500 to be described later.

또한, 상기 수직재(400)들의 상단 테두리 부위에는 상하로 길이를 가지며, 하단이 상기 슬라브 설치홈(310)의 바닥 면을 지지하는 다수의 가지지대(410)가 더 구비될 수 있다.In addition, the upper edge portion of the vertical member 400 has a length up and down, the lower end may be further provided with a plurality of branch zones 410 for supporting the bottom surface of the slab installation groove (310).

상기 가지지대(410)는, 수직재(400)들의 상단이 일정 높이를 유지할 수 있도록 지지하는 역할을 한다.The branch support 410 serves to support the upper ends of the vertical members 400 to maintain a predetermined height.

상부 슬라브(500)는, 강재 거푸집(300)의 슬라브 설치홈(310) 내에 설치되어 교량의 상판을 형성한다.The upper slab 500 is installed in the slab installation groove 310 of the steel formwork 300 to form a top plate of the bridge.

이러한, 상기 상부 슬라브(500)는 수직재(400)들의 상단에 지지되며, 상기 제2케이블 설치부(120)는 상부 슬라브(500)의 양측에 각각 형성될 수 있다.This, the upper slab 500 is supported on the top of the vertical member 400, the second cable installation portion 120 may be formed on both sides of the upper slab 500, respectively.

즉, 후술 될 3차 하부케이블(600)의 양단이 상기 제2케이블 설치부(120)에 각각 결합될 수 있다.That is, both ends of the third lower cable 600 to be described later may be coupled to the second cable installation unit 120, respectively.

여기서, 상기 상부 슬라브(500)는 슬라브 설치홈(310) 내에 철근(510)을 조립하고, 상기 조립된 철근(510)에 콘크리트(520)를 타설한 후, 일정 시간 양생하는 과정을 통해 설치할 수 있다.Here, the upper slab 500 can be installed through the process of assembling the reinforcing bars 510 in the slab installation grooves 310, and after pouring concrete 520 to the assembled reinforcing bars 510, curing for a predetermined time. have.

상기 철근(510)은, 수직재(400)들의 상단을 하방에서 지지하는 형태로 결속될 수 있다.The reinforcing bar 510 may be bound in a form of supporting the upper ends of the vertical members 400 from below.

그리고, 상기 상부 슬라브(500)는 전술한 강재 거푸집(300) 철거 시 교대(100)들의 상단에 종 방향 양단이 각각 거치된 상태로 설치된다. In addition, the upper slab 500 is installed in the state in which both ends in the longitudinal direction are mounted on the upper end of the shift 100 when the steel formwork 300 described above.

여기서, 상기 상부 슬라브(500)의 종 방향 양단과 교대(100)들의 상단 사이에는 별도의 지지부재(미도시)를 설치할 수 있다.Here, a separate support member (not shown) may be installed between the longitudinal ends of the upper slab 500 and the upper ends of the shifts 100.

여기서, 상기 제2케이블 설치부(120)에는 별도의 결합구(미도시)가 설치될 수 있는데, 미도시한 상기 결합구는 상기 2차 하부케이블(600)의 결합 및 분리가 가능하도록 개폐 가능한 구조를 가질 수 있다.Here, a separate coupler (not shown) may be installed in the second cable installation unit 120. The coupler, which is not shown, may be opened and closed to allow the second lower cable 600 to be coupled and separated. It can have

2차 케이블(600)은, 제2케이블 설치부(120)들에 양단이 각각 결합되어, 상기 수직재(400)들의 하단을 탄성 지지한다.Both ends of the secondary cable 600 are respectively coupled to the second cable installation parts 120 to elastically support lower ends of the vertical members 400.

2차 케이블(600)은, 금속 와이어를 이용해 제작할 수 있으며, 수직재(400)들의 하단에 형성된 제1관통홀(420)에 관통 결합시킨다.The secondary cable 600 may be manufactured using a metal wire and may be coupled to the first through hole 420 formed at the lower ends of the vertical members 400.

그리고, 상기 2차 케이블(600)의 종 방향 양단을 제2케이블 설치부(120)들에 각각 결합시킨다.And, both ends of the longitudinal direction of the secondary cable 600 is coupled to the second cable installation portion 120, respectively.

이때, 상기 2차 케이블(600)의 종 방향 양단은 제2케이블 설치부(120) 내에 삽입된 상태에서 별도의 체결부재(미도시)에 의해 결합될 수 있다.In this case, both ends of the longitudinal direction of the secondary cable 600 may be coupled by separate fastening members (not shown) in the state inserted into the second cable installation unit 120.

즉, 상기 2차 케이블(600)이 수직재(400)들을 상방으로 탄성 지지하게 되므로, 수직재(400)들은 안정적으로 가설될 수 있으며, 상부 슬라브(500)의 설치를 완료한 후에 상기 2차 하부케이블을 철거할 수 있다.That is, since the secondary cable 600 elastically supports the vertical members 400 upwards, the vertical members 400 may be stably installed, and after the installation of the upper slab 500 is completed, the secondary lower cables Can be demolished.

3차 케이블(700)은, 강재 거푸집(300)과 1차 케이블(200) 및 상기 2차 케이블(600) 철거 후, 양단이 상기 제3케이블 설치부(530)에 각각 결합되어, 수직재(400)들의 하단을 탄성 지지한다.The tertiary cable 700, after dismantling the steel formwork 300, the primary cable 200 and the secondary cable 600, both ends are respectively coupled to the third cable installation portion 530, the vertical member 400 Elastic support of the bottom of the).

3차 케이블(700)은, 전술한 2차 케이블(600)과 동일하게 금속 와이어를 이용해 제작할 수 있으며, 수직재(400)들의 하단에 형성된 제2관통홀(430)에 관통 결합시킨다.The tertiary cable 700 may be manufactured using a metal wire in the same manner as the above-described secondary cable 600, and is coupled to the second through hole 430 formed at the lower ends of the vertical members 400.

그리고, 상기 3차 케이블(700)의 양단은 상부 슬라브 설치 과정이 진행되는 동안 교대들의 후방에 임시로 고정된다.And, both ends of the tertiary cable 700 is temporarily fixed to the rear of the shift during the upper slab installation process.

이후, 강재 거푸집(300)과 1차 케이블(200) 및 2차 케이블(600) 철거 후, 3차 케이블(700)의 양단은 제3케이블 설치부(530)에 각각 고정된다.Subsequently, after dismantling the steel formwork 300, the primary cable 200, and the secondary cable 600, both ends of the tertiary cable 700 are fixed to the third cable installation unit 530, respectively.

이때, 상기 3차 케이블(700)의 종 방향 양단은 별도의 체결부재(미도시)에 의해 제3케이블 설치부(530)에 결합될 수 있다.At this time, both ends of the longitudinal direction of the tertiary cable 700 may be coupled to the third cable installation unit 530 by a separate fastening member (not shown).

즉, 상기 3차 케이블(700)이 수직재(400)들을 상방으로 탄성 지지하게 되며, 3차 케이블(700)은 전술한 2차 케이블(600)과 달리 지지대들을 지지하는 영구적인 구조물로 사용한다.That is, the tertiary cable 700 elastically supports the vertical members 400 upwards, and the tertiary cable 700 is used as a permanent structure for supporting the supports, unlike the secondary cable 600 described above.

결과적으로, 본 발명은 상부 슬라브(500)가 설치되는 강재 거푸집(300)의 하단에 1차 하부케이블(500)에 의해 지지되는 수직재(400)를 설치함으로써, 철근 조립 및 콘크리트 타설이 어려운 지형에서도 용이하게 교량의 상판을 시공할 수 있다.As a result, the present invention by installing the vertical member 400 supported by the primary lower cable 500 at the bottom of the steel formwork 300, the upper slab 500 is installed, even in the terrain difficult to reinforce assembling and concrete casting The top plate of the bridge can be easily constructed.

지금까지 본 발명의 케이블을 이용한 콘크리트 가설 교량에 관한 구체적인 실시예에 관하여 설명하였으나, 본 발명의 범위에서 벗어나지 않는 한도 내에서는 여러 가지 실시 변형이 가능함은 자명하다.Although specific embodiments of the concrete temporary bridge using the cable of the present invention have been described so far, it is obvious that various embodiments can be modified without departing from the scope of the present invention.

그러므로 본 발명의 범위에는 설명된 실시예에 국한되어 전해져서는 안 되며, 후술하는 특허청구범위뿐만 아니라 이 특허청구범위와 균등한 것들에 의해 정해져야 한다.Therefore, the scope of the present invention should not be limited to the above-described embodiments, but should be determined by the scope of the appended claims and equivalents thereof.

즉, 전술된 실시예는 모든 면에서 예시적인 것이며, 한정적인 것이 아닌 것으로 이해되어야 하며, 본 발명의 범위는 상세한 설명보다는 후술될 특허청구범위에 의하여 나타내어지며, 그 특허청구범위의 의미 및 범위 그리고 그 등가 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.
It is to be understood that the foregoing embodiments are illustrative and not restrictive in all respects and that the scope of the present invention is indicated by the appended claims rather than the foregoing description, It is intended that all changes and modifications derived from the equivalent concept be included within the scope of the present invention.

100: 교대 110: 제1케이블 설치부
120: 제2케이블 설치부 200: 1차 케이블
300: 강재 거푸집 310: 슬라브 설치홈
311: 제1절개부 320: 수직재 결합홀
330: 제1연결부재 331: 제1연결판
332: 제1체결부재 350: 작업발판
351: 제2절개부 352: 보 삽입홀
360: 제2연결부재 361: 제2연결판
362: 제2체결부재 370: 가로보
380: 레일 400: 수직재
410: 가지지대 420: 제1관통홀
430: 제2관통홀 500: 상부 슬라브
510: 철근 520: 콘크리트
530: 제3케이블 설치부 600: 2차 케이블
700: 3차 케이블
100: alternate 110: first cable mounting portion
120: second cable installation portion 200: primary cable
300: steel formwork 310: slab mounting groove
311: first cutout 320: vertical member coupling hole
330: first connecting member 331: first connecting plate
332: first fastening member 350: working scaffold
351: second incision 352: beam insertion hole
360: second connecting member 361: second connecting plate
362: second fastening member 370: cross beam
380: rail 400: vertical
410: branch zone 420: first through hole
430: second through hole 500: upper slab
510: rebar 520: concrete
530: third cable installation portion 600: secondary cable
700: tertiary cable

Claims (9)

양측 지반에 각각 설치되며, 상단에 제1케이블 설치부 및 제2케이블 설치부가 각각 형성되는 한 쌍의 교대;
상기 제1케이블 설치부에 양단이 각각 결합되는 1차 케이블;
상기 1차 케이블에 의해 지지되도록 교대들의 상단에 종 방향 양단이 각각 설치되고, 하단에는 종 방향을 따라 적어도 두 개 이상의 수직재 결합홀이 상하로 관통 형성되는 강재 거푸집;
상기 수직재 결합홀에 상단이 결합되며, 상기 강재 거푸집의 종 방향을 따라 배치되는 적어도 두 개 이상의 수직재;
상기 강재 거푸집에 설치되어 상기 수직재들의 상단에 지지되며, 종 방향 양단에 제3케이블 설치부가 각각 형성되는 상부 슬라브;
상기 제2케이블 설치부들에 양단이 각각 결합되어, 상기 수직재들의 하단을 탄성 지지하는 2차 케이블; 및
상기 강재 거푸집과 상기 1차 케이블 및 상기 2차 케이블 철거 후, 양단이 상기 제3케이블 설치부에 각각 결합되어, 상기 수직재들의 하단을 탄성 지지하는 3차 케이블;을 포함하는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
A pair of shifts, each of which is installed on both sides of the ground, each of which has a first cable installation part and a second cable installation part formed on an upper end thereof;
A primary cable having both ends coupled to the first cable installation unit;
Longitudinal both ends are respectively installed at the upper end of the shift to be supported by the primary cable, the lower end of the steel formwork at least two vertical material coupling holes are formed in the vertical direction;
An upper end coupled to the vertical member coupling hole and at least two vertical members disposed along a longitudinal direction of the steel formwork;
An upper slab installed on the steel formwork and supported at upper ends of the vertical members, and having third cable installation portions formed at both ends in a longitudinal direction thereof;
A second cable coupled to both ends of the second cable installation parts to elastically support lower ends of the vertical members; And
After the steel formwork and the primary cable and the secondary cable dismantling, both ends are respectively coupled to the third cable installation portion, the tertiary cable for elastically supporting the lower end of the vertical member; cable comprising a Used concrete temporary bridge.
제1항에 있어서,
상기 강재 거푸집은,
횡 방향으로 각각 분할 가능하도록 바닥 면에 종 방향을 따라 제1절개부 및,
상기 제1절개부를 연결하기 위한 제1연결부재가 결합되는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
The method of claim 1,
The steel formwork,
A first incision along the longitudinal direction on the bottom surface such that the respective divisions in the transverse direction are possible;
Concrete temporary bridge using a cable, characterized in that the first connection member for connecting the first cutout is coupled.
제2항에 있어서,
상기 제1연결부재는,
상기 제1절개부의 상단 및 하단에 각각 결합되며, 상하로 적어도 두 개 이상의 제1체결홀이 형성되는 한 쌍의 제1연결판; 및
상기 제1체결홀들을 통해 삽입되어, 상기 강재 거푸집에 관통 경합되는 적어도 두 개 이상의 제1체결부재;가 구비되는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
3. The method of claim 2,
The first connection member,
A pair of first connection plates which are respectively coupled to the upper end and the lower end of the first cutout and have at least two first fastening holes formed up and down; And
At least two first fastening members inserted through the first fastening holes and penetrated by the steel formwork; and a concrete temporary bridge using a cable.
제1항에 있어서,
상기 수직재들의 하단에는,
상기 1차 케이블이 측방으로 관통 결합되는 제1관통홀; 및
상기 제1관통홀의 하방에 형성되어, 상기 2차 케이블이 측방으로 관통 결합 되는 제2관통홀;이 형성되는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
The method of claim 1,
At the bottom of the vertical members,
A first through hole through which the primary cable is laterally coupled; And
It is formed below the first through-hole, the second through-hole through which the secondary cable is coupled to the side; Concrete temporary bridge using a cable, characterized in that formed.
제1항에 있어서,
상기 수직재들의 상단은,
상기 수직재 결합홀을 통해 상기 슬라브 설치홈 내에 돌출 위치되어, 상기 상부 슬라브와 일체로 결합되는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
The method of claim 1,
The upper end of the vertical members,
Provisionally positioned in the slab installation groove through the vertical material coupling hole, concrete temporary bridge using a cable, characterized in that coupled to the upper slab integrally.
제5항에 있어서,
상기 수직재들의 상단 테두리 부위에는,
상하로 길이를 가지며, 하단이 상기 슬라브 설치홈의 바닥 면을 지지하는 적어도 두 개 이상의 가지지대가 더 구비되는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
The method of claim 5,
In the upper edge portion of the vertical member,
The concrete temporary bridge using a cable having a length up and down, the lower end is further provided with at least two branches supporting the bottom surface of the slab installation groove.
제1항에 있어서,
상기 강재 거푸집의 횡 방향 양단에는,
횡 방향으로 각각 분할이 가능하도록 종 방향을 따라 제2절개부가 형성되며, 상기 강재 거푸집의 종 방향을 따라 길이를 갖는 한 쌍의 작업발판이 더 설치되며,
상기 작업발판의 상단 및 하단에는,
상기 제2절개부를 연결하기 위한 제2연결부재가 결합되는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
The method of claim 1,
At both ends of the steel formwork in the transverse direction,
A second incision is formed along the longitudinal direction so as to be divided in the transverse direction, and a pair of working scaffold having a length along the longitudinal direction of the steel formwork is further installed,
At the top and bottom of the working scaffold,
Concrete temporary bridge using a cable, characterized in that the second connecting member for connecting the second cutout is coupled.
제7항에 있어서,
상기 제2연결부재는,
상기 제2절개부의 상단 및 하단에 각각 결합되며, 상하로 적어도 두 개 이상의 제1체결홀이 형성되는 한 쌍의 제2연결판; 및
상기 제1체결홀들을 통해 삽입되어, 상기 강재 거푸집에 관통결합되는 적어도 두 개 이상의 제1체결부재;가 구비되는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
The method of claim 7, wherein
The second connection member,
A pair of second connecting plates which are respectively coupled to the upper and lower ends of the second cutout and have at least two first fastening holes formed up and down; And
At least two first fastening members inserted through the first fastening holes and penetratingly coupled to the steel formwork, the concrete temporary bridge using a cable provided therewith.
제7항에 있어서,
상기 제2절개부에는,
상기 작업발판의 종 방향을 따라 보 삽입홀이 더 형성되며,
상기 보 삽입홀 내에는,
상기 작업발판을 지지하기 위한 가로 보가 삽입되는 것을 특징으로 하는 케이블을 이용한 콘크리트 가설 교량.
The method of claim 7, wherein
In the second incision,
A beam insertion hole is further formed along the longitudinal direction of the working scaffold,
In the beam insertion hole,
Concrete temporary bridge using a cable, characterized in that the horizontal beam is inserted for supporting the working scaffold.
KR1020120024332A 2012-03-09 2012-03-09 The bridge construction technique for which a construction cable was used KR101317753B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120024332A KR101317753B1 (en) 2012-03-09 2012-03-09 The bridge construction technique for which a construction cable was used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120024332A KR101317753B1 (en) 2012-03-09 2012-03-09 The bridge construction technique for which a construction cable was used

Publications (2)

Publication Number Publication Date
KR20130103028A KR20130103028A (en) 2013-09-23
KR101317753B1 true KR101317753B1 (en) 2013-10-11

Family

ID=49452528

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120024332A KR101317753B1 (en) 2012-03-09 2012-03-09 The bridge construction technique for which a construction cable was used

Country Status (1)

Country Link
KR (1) KR101317753B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002356813A (en) 2001-05-30 2002-12-13 Miyoshi Koji Kk Movable scaffolding device and construction method thereof
JP3678719B2 (en) 2002-08-28 2005-08-03 オリエンタル建設株式会社 End separation type upper suspension type suspension floor slab bridge
JP2008248529A (en) 2007-03-29 2008-10-16 Oriental Shiraishi Corp Straight road-type suspended floor slab bridge and its construction method
JP4558609B2 (en) 2005-08-30 2010-10-06 オリエンタル白石株式会社 Extrusion construction method of bridge

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002356813A (en) 2001-05-30 2002-12-13 Miyoshi Koji Kk Movable scaffolding device and construction method thereof
JP3678719B2 (en) 2002-08-28 2005-08-03 オリエンタル建設株式会社 End separation type upper suspension type suspension floor slab bridge
JP4558609B2 (en) 2005-08-30 2010-10-06 オリエンタル白石株式会社 Extrusion construction method of bridge
JP2008248529A (en) 2007-03-29 2008-10-16 Oriental Shiraishi Corp Straight road-type suspended floor slab bridge and its construction method

Also Published As

Publication number Publication date
KR20130103028A (en) 2013-09-23

Similar Documents

Publication Publication Date Title
KR101699888B1 (en) Cantilever part of bridge and method thereof
JP5847483B2 (en) Bridge wall railing method
KR101203980B1 (en) upper structure of bridge
KR101203978B1 (en) upper structure of bridge
KR101090400B1 (en) Construction method of road for extending breadth of road on slope face
KR102061224B1 (en) Sectionally devided precast box culverts and the construction method thereof
JP2012082622A (en) Construction method of bridge floor slab and joint structure of precast floor slab
JP5367297B2 (en) Bridge with precast cross girder and precast girder and its construction method
KR102040363B1 (en) Slab joint construction method for bridges
KR102014418B1 (en) Beam bridge having beam support block and its construction method
KR101256774B1 (en) Constrcution method of end cross beam for integrating continuity of supporting portion and preventing falling down of psc girder
KR101317753B1 (en) The bridge construction technique for which a construction cable was used
KR101287739B1 (en) Sheet pile combined modular bridge abutment and construction method of the same
KR102220544B1 (en) Bridge expansion joints with the improved installation and method thereof
KR101824963B1 (en) Hybrid composite girder and construction method therewith
JP6889010B2 (en) Bridge construction method
JP4477467B2 (en) Bridge structure and its replacement method
KR101229000B1 (en) Expansion joint for bridges, and its production and installation methods
KR102261661B1 (en) Polyurea drain plate and method for constructing expansion joint
KR20200072986A (en) Pseudo jointless bridge construction made of steel plate girder with overhanged end widen and extended flange composed of concrete block
CN211776455U (en) Movable rail encloses fender
KR101803177B1 (en) Concrete panel mounted with front/side finishing materials by connecting elements
JP5967698B2 (en) Drainage groove forming member of viaduct expressway and construction method of viaduct expressway using the drainage groove forming member
KR101267626B1 (en) The bridge construction technique for which a construction cable was used
JP4071981B2 (en) Construction method of large section box culvert

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee