KR101177889B1 - Measuring the vertical management of high-rise buildings - Google Patents

Measuring the vertical management of high-rise buildings Download PDF

Info

Publication number
KR101177889B1
KR101177889B1 KR1020110079906A KR20110079906A KR101177889B1 KR 101177889 B1 KR101177889 B1 KR 101177889B1 KR 1020110079906 A KR1020110079906 A KR 1020110079906A KR 20110079906 A KR20110079906 A KR 20110079906A KR 101177889 B1 KR101177889 B1 KR 101177889B1
Authority
KR
South Korea
Prior art keywords
surveying
point
floor
vertical
gps
Prior art date
Application number
KR1020110079906A
Other languages
Korean (ko)
Inventor
김개준
Original Assignee
(주)만경기술공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)만경기술공사 filed Critical (주)만경기술공사
Priority to KR1020110079906A priority Critical patent/KR101177889B1/en
Application granted granted Critical
Publication of KR101177889B1 publication Critical patent/KR101177889B1/en

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B11/00Measuring arrangements characterised by the use of optical techniques
    • G01B11/16Measuring arrangements characterised by the use of optical techniques for measuring the deformation in a solid, e.g. optical strain gauge
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C9/00Measuring inclination, e.g. by clinometers, by levels
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01SRADIO DIRECTION-FINDING; RADIO NAVIGATION; DETERMINING DISTANCE OR VELOCITY BY USE OF RADIO WAVES; LOCATING OR PRESENCE-DETECTING BY USE OF THE REFLECTION OR RERADIATION OF RADIO WAVES; ANALOGOUS ARRANGEMENTS USING OTHER WAVES
    • G01S19/00Satellite radio beacon positioning systems; Determining position, velocity or attitude using signals transmitted by such systems
    • G01S19/01Satellite radio beacon positioning systems transmitting time-stamped messages, e.g. GPS [Global Positioning System], GLONASS [Global Orbiting Navigation Satellite System] or GALILEO
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

PURPOSE: A method for measuring and managing the perpendicularity of skyscrapers is provided to prevent error generating factors in advance by using a proper measuring device based on properties of concrete and enable to suggest criteria for a numerical correction. CONSTITUTION: A method for measuring and managing the perpendicularity of skyscrapers(300) is as follows. An initial reference point(400) and a benchmark are measured. A grid line of a lowest story and a position of an outer line are measured. A setting position of an ACS(Auto Climbing System) foam is confirmed. Slab bench marks of each story are measured. The perpendicularity of a peripheral part is measured. The perpendicularity of super upper stories using a GPS is measured. The perpendicularity of a core and columns are measured. Altitude bench marks of each story are measured. The column shortening inspection is measured. The settlement extent of a front basement of the lowest story is measured.

Description

초고층 건물 수직도 측량관리 {Measuring the vertical management of high-rise buildings}{Measuring the vertical management of high-rise buildings}

본 발명은 초고층 건물 신축에 있어 내부 및 외벽 수평,수직도측량 방법으로 GPS, 연직기, 토탈스테이션 등 최첨단 측량장비를 이용하여 건물의 적정수직도를 종합적으로 관리하기 위한 방법에 관한 것이다. The present invention relates to a method for comprehensively managing the proper verticality of a building using cutting-edge surveying equipment such as GPS, vertical machine, total station, etc. in the construction of a high-rise building.

건물의 초고층화는 건축기술의 급격하게 발전 과 토지효율성,고급주택의 많은 수요 등으로 신축 하고있다.High-rise buildings are being built due to the rapid development of construction technology, land efficiency, and high demand for luxury housing.

또한 경쟁하듯이 국가별로 랜드마크 개념으로 초고층 건물을 서로 앞다투어 짖고있는게 현실이다.In addition, the reality is that the skyscrapers are barking in front of each other as a landmark concept, as in competition.

상기 초고층 건물에는 매우많은 신기술이 적용된다. Many new technologies are applied to the skyscrapers.

하지만 수직도 측량분야는 아직도 종전방식(다림추 및 줄자)을 고수하고 있다. 초고층 수직도 측량관리는 건물의 중심 기준선 확정 및 후속공정(커튼월,엘리베이터,인테리어 시공 등)에 매우 중요하다.
However, the vertical surveying field still adheres to conventional methods (ironing weights and tape measure). High-rise vertical surveying management is very important for determining the center baseline of the building and for subsequent processes (curtain wall, elevator, interior construction, etc.).

초고층 건물의 수직도측량 관리에 있어 가장 큰 문제점은 The biggest problem in the vertical survey management of tall buildings

연직기 사용의 불안전 : 연직기의 수평물반을 정밀하게 맞추고 작업하더라도 측량기계 특성상 한쪽으로 치우치거나 거리가 멀수록 레이져 불빚이 퍼져보인 다거나 하는 현상이 발생한다.Insecureness of the use of the vertical machine: Even when the horizontal plane of the vertical machine is precisely adjusted, the phenomenon of the laser bulge spreads as one side of the surveying machine or the distance increases.

또한 연직기는 토탈스테이션과 달리 측량기기 성능검사를 실시하지 않아 기계 오차가 발생하여도 감지 할수없어 지속적으로 작업하여 일정부분으로 오차가 누적될시건물 수직도에 치명적인 오차가 발생될수 있다.
In addition, unlike the total station, the vertical station does not perform the performance test of the surveying equipment, so even if a mechanical error occurs, it cannot be detected.

컬럼쇼트닝(Column shortening)에 의한 수축 : 부재 자체의 수직중량에 의해서 기둥이 부등축소 하는 현상을 말한다. Shrinkage due to column shortening: A phenomenon in which the column is inevitably shrunk due to the vertical weight of the member itself.

컬럼 쇼트닝에서 문제가 되는것은 배치된 기둥부재들이 모두 동일한 량이 축소되는것이 아니라 기둥마다 축소량이 다른 부등축소현상이 생기기때문에 단순히"300m 건물을 지으면서 전체적으로 50cm축소된다"라고 보고 건물을 300.5m로 구조체를 형성할 수 없다는 점이다.The problem with column shortening is that not all of the arranged column members are reduced in the same amount, but the shrinkage is different for each column, so it is reduced to 50cm overall while building a 300m building. It cannot be formed.

무시하고 작업할 시 슬라브 처짐 현상(크랙발생) 커튼 월 시공불량 준공 후 수축으로 인한 창문파손현상 등 매우 큰 위험으로 다가온다.When neglected, the slab deflection phenomenon (cracking) The curtain wall construction failure is very dangerous, such as window breakage due to shrinkage after completion of construction.

그러므로 기준수준점(TBM)에서 부터 칼럼쇼트닝 부재축소량을 측량하여 매 층마다 측량한 내용을 현장에 즉시 보정하여 시공하여야 하지만 현장여건상 여러 가지 이유(측량방법론 등)로 중요성을 인지하지 못하고 있다.
Therefore, from the reference level (TBM), the reduction of column shortening members must be measured, and the surveyed contents for each floor must be immediately corrected and constructed.

스틸 테이프(steel tape) 온도에 의한 오차: 골조공사에 사용되는 스틸테이프는 온도보정, 장력보정, 처짐 보정을 전혀 실시하지않고 현장에서 먹 반장 판단에 의해 거리가 결정된다.Steel tape temperature error: The steel tape used in the frame construction is determined by the length of the board in the field without any temperature correction, tension correction, and deflection correction.

거리오차 중 가장 큰 오차는 온도에 의한 오차로,The biggest error among the distance errors is due to temperature.

Ct=a*L(t-to) 여기서, Ct: 온도보정량 L: 관측길이 a: 선팽창계수 Ct = a * L (t-to) where Ct: temperature correction L: observation length a: linear expansion coefficient

t: 측정시 온도 to:표준온도(15℃)                         t: Temperature at measurement to: Standard temperature (15 ℃)

영상 35℃에서 거리 50m를 측정시 온도보정은 11.5mm를 빼야하고,When measuring 50m distance at 35 ℃, the temperature compensation should be subtracted from 11.5mm.

영하 5℃에서는 11.5mm를 더해야된다.At minus 5 ℃, 11.5mm should be added.

거리오차가 1층에서 5mm발생 되었다고 가정한다면 상부 층으로 올라갈수록 오차량은 더욱 커져 골조공사에 막대한 피해 및 내/외부 마감 품질 확보에 문제점이 발생 될 것이다.Assuming that the distance error is 5mm from the first floor, the higher the error, the greater the amount of error, which will cause enormous damage to the frame construction and problems of securing internal and external finishing quality.

콘크리트 건조 수축: 건조수축이란 경화된 콘크리트가 온도변화와 상대습도의 차이로 콘크리트 내 공극에 남아있는 공극 수의 증발로 발생하는 것을 말한다.Drying shrinkage of concrete: Drying shrinkage refers to the hardening of concrete caused by the evaporation of the number of voids remaining in the pores of the concrete due to differences in temperature and relative humidity.

- 소성수축(plastic shrinkage) : 경화 전 수분증발과 수분손실에 의해 발생 -Plastic shrinkage: caused by moisture evaporation and water loss before curing

- 자기수축(chemical shrinkage) : 수화반응에 의한 수분감소로 발생. -Chemical shrinkage: It is caused by water loss due to hydration reaction.

- 건조수축(drying shrinkage) : 온도변화와 상대습도의 차이에 의한 공극 수의 수분증발로 발생 Drying shrinkage: Occurs due to moisture evaporation of the pore water due to temperature changes and differences in relative humidity.

- 탄산수축(carbinate shrinkage) : 대기중의 탄산가스와 경화시멘트 풀의 중성화 반응으로 생성된 물의 증발로 발생 된다. -Carbate shrinkage: Generated by the evaporation of water produced by neutralization of carbon dioxide gas and hardening cement pool in the atmosphere.

콘크리트 건조수축은 온도가 높을수록 수축량이 많아지는 게 특징이다.Concrete dry shrinkage is characterized by a higher shrinkage at higher temperatures.

300M이상 초고층 건물의 건조수축 변형량Dry shrinkage of high-rise buildings over 300M

- 슬라브 형상 :40m * 20m *t250mm  -Slab shape: 40m * 20m * t250mm

가정조건: 습윤양생 기간7일, 공기의 상대습도55%, 슬럼프치18㎝, 잔골재율46%Home condition: 7 days of wet curing, relative humidity of air 55%, slump 18㎝, fine aggregate 46%

공기량3%, 단위시멘트량400kgf/㎡, 타설후 60일경과           3% of air, 400kgf / m2 of cement, 60 days after pouring

건조수축변형량 계산결과 : 40m에서 1.223㎝ , 20m에서 0.6114cm 수평 수축량이 발생하였다.Results of calculation of dry shrinkage strain: 1.223cm at 40m and 0.6114cm horizontal shrinkage at 20m.

측량장비의 노후화 및 원시적 측량방법: 골조공사에 사용되는 측량장비는 트랜싯, 다림 추, 스틸 테이프 등 매우 열 약하고 노후화되어있다.Aging and primitive surveying methods: Surveying equipment used in framing works is very fragile and obsolete, such as transits, iron weights and steel tape.

다림 추를 이용한 1개층 단위의 기준 먹 이설 방법은 바람의 영향 및 개인적 착오로 인하여 많은 오차량을 포함한다. 현장에서 사용중인 트랜싯의 경우 5초독, 10초독 측량장비가 대부분이다.The standard feeding method of one floor unit using the iron weight includes a large amount of error due to the influence of wind and personal error. For transits in the field, 5 and 10 reading instruments are most common.

콘크리트 슬라브 길이 : 50m * 50m SLAB에서 10초 오차가 발생하면,Concrete slab length: 50m * 50m If 10 seconds error occurs in SLAB,

tan 0°0′10″* 50m = 2.4mm 오차가 발생하며 4개의 꼭짓점을 경유하여 폐합할 시 9.6mm 오차가 발생할 수도 있다.tan 0 ° 0′10 ″ * 50m = 2.4mm error occurs and 9.6mm error may occur when closing via 4 vertices.

콘크리트 분활 타설로 인한 오차: 현장여건상 빠른 공정 Cycle 및 1일 콘크리트 타설양의 한계 등 여러 가지 이유에서 2회 ~ 4회로 나누어 분활 타설을 하고 있는 게 현재 현장의 실정이다.Error due to concrete smashing: Currently, the site is split crushing twice or four times for various reasons such as fast process cycle and limit of concrete pouring per day.

일정 순서대로 분활 타설하게 되면 콘크리트의 건조수축 순서가 정해져 콘크리트가 한쪽 방향으로 계속 치우치거나 또는 나선형처럼 구조물이 뒤틀림 현상이 나타난다.
When the concrete is poured in a certain order, the order of drying shrinkage of the concrete is determined so that the concrete continues to deviate in one direction or the structure is warped like a spiral.

본 발명은 위와 같은 문제점을 해소하기 위해 창출된 것으로서 초고층건물 신축에 있어 원활한 공사가 이루어질 수 있도록 고 정밀 측정방법으로 최첨단 장비(연직기,토탈스테이션,GPS VRS System)를 이용하여 설계위치 확정, 정확한 시공, 콘크리트 오차발생 요인 등을 사전에 예방, 보완하여 적정(건교부시방서; 고층:층당±6mm 전체±25mm이내) 수직도 유지관리하여 품질 향상을 도모하는데 그 목적이 있다.The present invention was created in order to solve the above problems, and the design position is determined by using high-tech equipment (vertical machine, total station, GPS VRS System) with high precision measurement method to achieve smooth construction in the construction of high-rise buildings. It aims to improve quality by preventing and supplementing construction and concrete error occurrence factors in advance and maintaining proper verticality (building section specification: high floor: within ± 6mm per floor within ± 25mm).

또한, 초고층 수직도 측량 관리 Work Flow를 작성하여 방법론을 제시하고 체계적으로 종합 관리하여 각종 Check결과를 신속, 정확한 결과를 제공하여 품질향상 하는데 목적이 있다.
In addition, it aims to improve the quality by providing a quick and accurate result of various check results by presenting the methodology by systematically managing the ultra-high vertical surveying management workflow.

즉, 본 발명은 상술한 바와 같은 목적을 달성하기 위하여, 현장투입 시점부터 골조공사 준공까지의 초고층 수직도 측량관리의 총체적인 흐름 과 아이템별 중점 관리사항 및 세부적 방법론을 제시하는 게 특징으로 한다.
That is, the present invention is characterized by presenting the overall flow of the super vertical vertical surveying management from the point of time input to the completion of the frame construction, the key management matters for each item, and the detailed methodology in order to achieve the above object.

본 발명은 초고층건물 신축에 있어 종합적 수직도 측량 관리로서 체계적인 Work Flow 및 최첨단 장비를 사용하여 작업 방법론을 제시함으로써 정확한 설계위치 확정, 건물 수직도 불안전으로 인한 공사비 절감 및 골조공사와 후속공정 (마감)의 고 정밀 품질시공을 가능하게 할 수 있다.The present invention is a comprehensive vertical surveying management in the construction of high-rise buildings by presenting a work methodology using systematic work flow and state-of-the-art equipment. High precision quality construction can be enabled.

또한, 콘크리트 성질 및 적절한 측량 장비의 사용으로 오차 발생요인을 사전에 예방하고 오차발생시 수치적 수정 보완의 기준을 제시해 준다.
In addition, the use of concrete properties and the use of appropriate surveying equipment prevents the occurrence of errors in advance and suggests a standard for complementing numerical corrections when errors occur.

도 1 은 본 고안에 따른 실시 예를 보인 기준점 및 수준점 평면도.
도 2 은 본 고안에 따른 실시 예를 보인 기준라인 이설방법 사시도.
도 3 은 본 고안에 따른 실시 예를 보인 도 2 부분 상세도.
도 4 은 본 고안에 따른 실시 예를 보인 외부 기준점에서 외벽 모서리 검측하는 방법 사시도.
도 5 은 본 고안에 따른 실시 예를 보인 허리 먹 이설 작업절차 측 단면도.
도 6 은 본 고안에 따른 실시 예를 보인 허리 먹 이설 후 현장 표시하는 방법 측 단면도.
도 7 은 본 고안에 따른 실시 예를 보인 최하층 레벨 측량 방법으로 측 단면도.
도 8 은 본 고안에 따른 실시 예가 적용된 층별 전체 수직도 측량 검측 위치 평면도.
1 is a reference point and level point plan view showing an embodiment according to the present invention.
Figure 2 is a perspective view of the method of moving the reference line showing an embodiment according to the present invention.
Figure 3 is a partial detailed view of Figure 2 showing an embodiment according to the present invention.
Figure 4 is a perspective view of the outer wall edge detection method from the external reference point showing an embodiment according to the present invention.
Figure 5 is a side cross-sectional view showing the embodiment according to the present invention.
Figure 6 is a cross-sectional view showing the method after the site of the present invention showing the embodiment according to the present invention.
Figure 7 is a side cross-sectional view of the lowest level surveying method showing an embodiment according to the present invention.
Figure 8 is a floor-to-floor verticality measurement detection position plan to which the embodiment according to the present invention is applied.

기준점 및 수준점(TBM)측량관리 : Reference and Level Point (TBM) Survey Management:

실시시점: 현장투입 즉시 시행하며 1개월 단위로 재확인하여야 한다.Implementation Point: Immediately after on-site injection, it should be reconfirmed on a monthly basis.

사용장비: GPS, Total Station, LevelEquipment: GPS, Total Station, Level

측량방법: 1)현장 내/외부 지반이 견고하고 침하 또는 변위가 없는 곳을 선점 2)지적 도근점 및 국가 수준점을 이용하여 폐합트래버스 측량 3)저층부 4개소, 고층부 4개소 (최소 8개소 이상) 관리하고 1개월 주기로 체크하여 변위 여부를 파악하여 오차 발생시 망실 또는 신설하여야 한다.Surveying method: 1) Preempt the place where the internal and external ground is firm and there is no settlement or displacement. 2) Closed traverse survey using the intelligent approach point and the national level point. 3) Management of 4 lower floors and 4 higher floors And check it every month to find out whether it is displaced or not.

중점관리사항: 기준망 조정시 폐합트래버스를 하여 오차를 최소화하여야 한다.Critical Control Points: Minimize errors by using closed traverse when adjusting the reference network.

기대효과: 기준점 체계 확립으로 인접 공구와의 상호관계 및 골조공사 구조물 정확한 설계위치 확정으로 고품질 정밀시공이 가능하다.
Expected effect: High quality precision construction is possible by establishing the reference point system and establishing the exact design position of the interworking structure and the structure of adjacent structures.

최하층 그리드라인 및 외곽선 위치 측량 : Lowermost gridline and outline position survey:

실시시점: 전면기초(Mat Foundation) 콘크리트 타설 전후Implementation Point: Before and after Mat Foundation concrete casting

사용장비: Total StationEquipment: Total Station

측량방법: 1)확정된 기준점에서 Total Station을 이용하여 지하층 기준이 되는 그리드 라인을 측량 2)설치된 점에 Total Station을 세워 정사각형으로 기준먹을 설치하고, 각각의 기준먹 거리는 30m 이상으로 골조팀이 사용할수 있도록 4점 이상 설치 3)설치된 점에서부터 건물 외곽선 각 모서리를 측량하여 설계위치에 건물이 정확히 셋팅 되었는지 확인Surveying method: 1) Survey the grid line that is the basement level by using Total Station at the determined reference point. 2) Set up the total station at the installed point and install the standard feed in a square. Each reference distance is 30m or more. 4 points or more to be installed 3) Check that the building is correctly set at the design location by surveying each corner of the building outline from the installed point.

중점관리사항: 지상에서 지하로 측량하는 것은 많은 오차를 포함하며 연직선 오차는 소거 불가능하다. 그러므로 정반위 측량을 하여 오차를 최소화하여야 한다. Critical Control Points: Surveying from ground level to ground level contains a number of errors and vertical error cannot be eliminated. Therefore, specular surveys should be performed to minimize errors.

또한, 좌표측량 후 크로스 체크 개념으로 대각검측 및 치수를 확인하여야 한다.In addition, the diagonal check and dimensions should be confirmed by the concept of cross check after coordinate surveying.

기대효과: 구조물의 정확한 설계위치 확정으로 고품질 정밀시공이 가능하다.
Expected Effect: High-quality precision construction is possible by confirming the exact design position of the structure.

ACS(Automatic Climbing System)폼 셋팅 위치 확인 : Locate the ACS (Automatic Climbing System) Form Settings:

실시시점: 초기(지상1층 ~ 3층사이)에서 골조 준공시까지When to start: From the beginning (between 1st and 3rd floor) to the completion of the frame

사용장비: GPS, Total StationEquipment: GPS, Total Station

측량방법: 1)ACS폼 각 모서리마다 나사못으로 표시 2)확정된 기준점에서 GPS, Total Station을 이용하여 ACS폼 모서리마다 하단 및 상단 수평 위치를 확인 3)설계기준과 비교분석하여 ACS폼 셋팅하는것이 바람직하다.Surveying method: 1) A screw is displayed at each corner of the ACS form. 2) At the determined reference point, the GPS and Total Station are used to check the horizontal position of the lower and upper corners of the ACS form. desirable.

중점관리사항: ACS폼 각 모서리마다 나사못으로 표시해두어 골조팀에서 수정시 기준이 되어야 하며 초기 ACS폼 셋팅 후 장기 사용으로 인해 오차량이 발생함으로 10개층 간격으로 재확인하여 수정보완 하여야 한다.Critical Control Points: Each corner of the ACS foam should be marked with screws to be a guideline for modification by the framing team. After initial ACS foam setting, errors will occur due to long-term use.

기대효과: 구조물의 정확한 설계위치 확정 및 건물 외곽 수직도를 정밀하게 하여 후속공정(커튼 월)에 있어 고품질 정밀시공이 가능하다.
Expected Effect: High-quality precision construction is possible in the subsequent process (curtain wall) by precisely positioning the design of the structure and precisely the verticality of the exterior of the building.

각층 슬라브(SLAB) 기준 먹 체크 : Check the ink on each floor slab:

실시시점: 콘크리트 타설 후 매 층마다Implementation Point: Every floor after concrete pouring

사용장비: 연직기, Total StationEquipment: Vertical Machine, Total Station

측량방법: 1)콘크리트 타설 후 매 층마다 골조 기준먹 오픈슬리브를 통하여 연직기를 이용 2)기준 층 기준라인에서 상부층으로 기준먹 확인 3)골조 기준먹과 연직기 측량값의 차이를 파악 4)오차발생시 즉시 보정 및 수정하는 것이 바람직하다.Surveying method: 1) Using the vertical knitting machine through the frame open standard sleeve for each floor after concrete casting 2) Checking the standard feed from the reference layer reference line to the upper layer 3) Identifying the difference between the frame standard eating and the vertical knitting machine 4) Error It is desirable to correct and correct it immediately when it occurs.

중점관리사항: 연직기 사용시 기준 층에서 상부 층으로 오픈슬리브를 통하여 시준시 각도는0°, 90°, 180°, 270°총4회를 시준하여 평균값을 취해야만 이설오차를 소거할 수 있다.IMPORTANT IMPORTANT: When using a vertical loom, the collimation angle from the reference layer to the upper layer through the open sleeve should be averaged four times at 0 °, 90 °, 180 °, and 270 ° to eliminate the relocation error.

골조 오픈슬리브 설치에 있어 Core부 4개소, 외주부 4개소 이상 오픈 슬래브를 설치하며, 설치조건은 각도는90°거리는 길수록 좋으며, 설계도서를 면밀히 검토하여 추후 장애물 발생 위치는 피하는 게 바람직하다. In the installation of framed open sleeves, open cores should be installed at 4 cores and at least 4 outer periphery. The longer the angle is, the longer the angle is, and the better the design documents should be reviewed.

기준먹이설 전 기준층 기준먹을 Total Station을 이용하여 각도 및 거리를 확인하여 콘크리트 수축으로 인한 오차 발생 유무를 사전점검하고 작업을 실시해야되며, 연직기를 이용하여 상부층으로 이설후 상부층의 이설된 기준먹을 Total Station을 이용하여 각도와 거리를 필히 확인하여 이설시 오차가 발생하였는지 확인하여야 한다.Before the standard feeding, the reference floor reference eating Total station is used to check the angle and distance to check for errors due to the shrinkage of concrete, and to carry out work. Check the angle and distance by using the station to see if an error occurred during relocation.

또한, 기준층 기준라인이 셋팅되었으면 기준층에서 부터 먹박스를 통하여 다이렉트(Direct)로 15개층 이상 측설하여야 하며, 기준층은 건조수축이 콘크리트 타설 10일 경과후 15개층 간격으로 이설 하는 것이 바람직하다.In addition, when the reference layer reference line is set, more than 15 layers should be staked directly from the reference layer through the mux box, and the reference layer is preferably relocated at intervals of 15 layers after 10 days of concrete shrinkage.

기대효과: 저층 기준먹을 상부층으로 이설 함으로 저층과 동일한 기준라인 사용으로 초고층 건물의 적정 수직도를 유지하여 구조물 안정성 및 고품질 정밀시공이 가능하다.Expected Effect: By relocating the lower floor standard to the upper floor, it is possible to maintain the proper verticality of the skyscraper by using the same reference line as the lower floor.

외주부 수직도 관리 : Outer Perimeter Vertical Control:

실시시점: 콘크리트 타설 후 매 층마다Implementation Point: Every floor after concrete pouring

사용장비: GPS, Total Station, 줄자Equipment: GPS, Total Station, Tape Measure

측량방법: 1)슬라브 기준먹 체크 후 시행 2)기준라인에서 부터 슬라브 끝 선까지 줄자를 이용하여 거리를 체크하여 건물외곽 모서리 위치 확인하여야 한다.Surveying method: 1) Check after slab reference. 2) Check the distance from the reference line to the end of the slab using a tape measure.

3)외부기준점에서 3개층 간격으로 Total Station 또는 GPS를 이용하여 슬라브 끝선을 재확인 4)크로스 체크 하여 오차량 분석하여 수정보완 하는게 바람직하다.3) Reconfirm the slab end line by using Total Station or GPS at three floor intervals from the external reference point.

중점관리사항: 외부에서 좌표 측량시 건물 외벽과 나란한 지점에 Total Station을 설치하여 측벽 라인을 확인하고 매번 같은 지점에서 측량하여야 오차발생을 최소화 할수있다.Critical Control Points: When coordinate surveying from the outside, install a total station on the side of the building's exterior wall to check the side wall line and survey at the same point every time to minimize the occurrence of errors.

기대효과: 구조물의 정확한 설계위치 확정 및 건물 외곽 수직도를 정밀하게 하여 후속공정(커튼월)에 있어 고품질 정밀시공이 가능하다.
Expected Effect: High-quality precision construction is possible in the subsequent process (curtain wall) by accurately determining the design position of the structure and precisely the verticality of the exterior of the building.

GPS(Global Positioning System)를 이용한 초고층 수직도 측량 : Tall vertical survey using Global Positioning System (GPS):

실시시점: 콘크리트 타설 후 3개 층마다Implementation Point: Every 3 floors after concrete pouring

사용장비: VRS GPS (SOKKIA - GSR2700 ISX 권장)Equipment: VRS GPS (SOKKIA-GSR2700 ISX recommended)

GPS 측량의 이해: VRS(Virtual Reference Station) 방식은 새로운 실시간 GPS 측량법으로서, 기지국 GPS를 설치하지않고 이동국 GPS만을 이용하여 VRS서비스센타에서 제공하는 위치보정데이타를 휴대전화로 수신함으로써 RTK 또는 DGPS 측량을 수행할 수 있는 최첨단 기법이다.Understanding GPS Surveying: VRS (Virtual Reference Station) is a new real-time GPS surveying method that allows RTK or DGPS surveys to be performed by receiving the mobile phone's position correction data provided by the VRS service center without using base station GPS. State-of-the-art techniques that can be performed.

VRS 측위의 정도: 1) 정밀측위 : ㎝ 단위의 RTK - VRS 서비스Accuracy of VRS Positioning: 1) Precision Positioning: RTK-VRS Service in cm

2) 일반측위 : 미터 단위이하 DGPS - VRS 서비스                 2) General location: DGPS-VRS service below metric unit

3) 정지측위 : 10㎜이내 후처리 방식으로 정지측량 VRS서비스                 3) Stopping location: Stop surveying VRS service with post-processing method within 10㎜

측량방법: 1)현장내 기준점을 이용하여 GPS기준 망조정을 한다. 2)GPS좌표와 현장기준점 간의 오차가 발생함으로 GPS좌표를 현장좌표로 변환한다. 3)변환된 좌표는 GPS수신기에 저장되고 항상 변환된 시스템으로 작업시 거의 동일한 결과를 얻는다. 4)변환좌표가 확정되면 GPS수신기를 가지고 내/외부 기준점 체크 포인트로 이동한다. 5)초당 1점정도 측위가능 하므로 약 30분정도 체크후 측정된 좌표를 프로그램 [SPECTRUM SURVEY]을 이용하여 프로그램화 하여 평균값을 취득한다. 6)GPS 확정된 좌표와 연직기 측정값과의 결과 값 비교 분석하여 수정보완 하는 것이 바람직하다.Surveying method: 1) Adjust the GPS reference network using the site reference point. 2) The GPS coordinates are converted to field coordinates because an error occurs between the GPS coordinates and the field reference point. 3) The converted coordinates are stored in the GPS receiver and always get almost the same result when working with the converted system. 4) Once the converted coordinate is confirmed, move to the internal / external reference point check point with GPS receiver. 5) Since it is possible to position one point per second, check about 30 minutes and program the measured coordinates using the program [SPECTRUM SURVEY] to obtain the average value. 6) It is preferable to perform numerical analysis by comparing and analyzing the result value between the GPS coordinates and the measured value of the weaving machine.

중점관리사항: GPS측량은 매우많은 오차(위성시계, 계도, 대기권전파지연, 안테나 구심, 전파다중경로, 위성배치상태 등)를 포함한다. 그러므로 1점측설시 필히 30분이상 측위하고 2시간 간격으로 2회 더 측위하여 평균값을 취해야 한다.Critical Control Points: GPS surveys involve a large number of errors (satellite clocks, genealogies, atmospheric propagation delays, antenna centers, radio wave multipaths, satellite positioning, etc.). Therefore, one-stake out of the place must be measured for more than 30 minutes and twice more at 2 hour intervals.

연직기를 골조 준공시까지 진행하고 크로스체크 개념으로 GPS로 확인하여 15MM이상 오차발생시 저층에서 연직기를 이용하여 현장 기준라인 고층부로 재확인 하는게 바람직하다.It is advisable to proceed to the completion of framing machine and check it with GPS as a cross check concept and reconfirm it to the high floor part of the site reference line by using the weaving machine at the lower floor when an error occurs over 15MM.

기대효과: 연직기 측량 결과값과 GPS측량 결과값을 상호 분석, 수정, 보완 함으로서 초고층 건물 적정 수직도를 유지하여 구조물 안정성 및 고품질 정밀시공이 가능하다.
Expected Effect: By analyzing, modifying and supplementing the vertical survey results and GPS survey results, it is possible to maintain structural stability and high-quality precision construction by maintaining proper verticality of skyscrapers.

Core 및 기둥(Column) 수직도 체크 : Core and column verticality check:

실시시점: 콘크리트 타설 후 매층마다Implementation Point: Every floor after concrete pouring

사용장비: GPS, Total Station, 줄자Equipment: GPS, Total Station, Tape Measure

측량방법: 1)매층마다 Core 기준라인에서 부터 기둥먹까지 각도 및 거리를 확인, 2)Core외벽 수직도를 체크 하여야 하며 Core벽면에 Core끝선으로 부터 20㎝이동시켜 수직 먹선을 설치하여야 한다. 3)Core내부 Elevator Pit의 수직도를 확인하기 위해서는 Core기준라인에서 부터 Elevator Pit 4각모서리를 광파기로 체크하는게 바람직하다.Surveying method: 1) Check the angle and distance from the core reference line to the pillar eater for each floor, 2) Check the verticality of the core outer wall, and install vertical black wires by moving 20cm from the core end line on the core wall. 3) In order to check the verticality of the elevator pit inside the core, it is desirable to check the elevator pit square corner from the core reference line with a light drill.

중점관리사항: Elevator Pit 수직도는 골조 준공이전에 Elevator 일부(약 중간층까지)설치 되므로 매층마다 필히 거리 및 각도를 확인하여 즉시 수정하여야 하며, 수정시 Elevator Pit폼 특성상 1개층에서 30mm 이상의 오차는 수정불가능 함으로 층당5㎜씩 여러층에 걸쳐서 수정하여야 한다.Main point of care: Elevator Pit verticality is installed part of elevator (up to about middle floor) before construction of frame, so make sure to check distance and angle every floor immediately and correct any errors more than 30mm in one floor due to the characteristics of elevator pit form. Impossible to correct over several layers, 5 mm per layer.

기대효과: Elevator Pit의 정확한 설계위치 확정으로 초고층건물의 고속Elevator 시공에 있어 적정 수직도를 유지하여 Elevator의 안정성 및 정밀시공이 가능하다.
Expected Effect: It is possible to maintain elevator's stability and precise construction by maintaining proper verticality in high-speed elevator construction of high-rise buildings by determining the exact design position of elevator pit.

각층 허리먹 체크 :Waist check on each floor:

실시시점: 콘크리트 타설 후 매층마다Implementation Point: Every floor after concrete pouring

사용장비: Lever, 줄자Equipment: Lever, Tape Measure

측량방법: 1)현장내 수준점에서 부터 건물 최하층까지 수준측량하여 바닥 슬라브에서 1M 상부 지점(Core벽면)에 2점이상 허리먹선을 설치하여 한다. 2)최하층에 신설된 허리먹을 이용하여 상부층으로 이설하여 허리먹선을 표시한다. 각층마다 동일한 방법으로 측량하여 허리먹선 설치하여야 한다.Surveying method: 1) Level survey from the level point of the site to the lowest floor of the building and install two or more waistline at the 1M upper point (Core wall surface) of the floor slab. 2) Relocate to the upper layer by using the newly installed waistband on the lower floor and mark the waistband. Each floor should be surveyed and installed in the same way.

중점관리사항: 10개층 간격으로 수준점(TBM)에서 허리먹선을 직접 확인하여 컬럼 쇼트닝(Column shortening)발생량을 상부층으로 보정하여 작업하는게 바람직하다.Critical Control Points: It is advisable to check the waist line directly at the level (TBM) in 10-layer intervals to correct the column shortening incidence to the upper layer.

또한 Core선행 작업시 외주부 Slab콘크리트 타설일정보다 허리먹을 Core벽면에 선시공되어야 외주부 기준레벨로 사용 가능하다.In addition, it is possible to use it as the reference level of the outer circumference only when it is installed on the wall of the core where the outer lap of the slab concrete is placed on the back of the core.

기대효과: 매층 허리먹을 설치함으로서 층고 및 세대 마감선를 확정하여 후속공정(인테리어)의 기준이되어 설계 및 고품질 정밀시공이 가능하다.
Expected effect: By installing floor-floor waistband, it is possible to design floors and household finish lines, and to design and high-quality precision construction as a standard for subsequent process (interior).

컬럼쇼트닝(Column shortening) 검사 측량 : Column shortening inspection survey:

실시시점: 최초 신설후 월1회 측량When to start: Survey once a month after initial establishment

사용장비: Lever, 줄자Equipment: Lever, Tape Measure

측량방법: 1)하중의 증가 및 시간 경과에 따른 변형률이 많은 층을 선정한다. Survey method: 1) Select a layer with a high strain rate and a strain over time.

2)슬라브 바닥에서 1M상부지점 Core5점, 컬럼 10점을 선정하여 칼금 표시한다. 3)외부 수준점(TBM)을 이용하여 최초 신설후 1개월 단위로 상대 처짐 변위를 관찰 하여 설계값과 비교 검토하는게 바람직하다.2) At the bottom of the slab, select 5M core points and 10 column points at the top of the slab. 3) It is desirable to observe the relative deflection displacement in units of 1 month after the initial construction using the external level point (TBM) and compare it with the design value.

중점관리사항: 레벨 과 스틸테이프 만을 이용한 직접 수준측량을 실시하여야 한다. Total Station을 이용한 광파기 측량은 해서는 아니된다. Total Station의 연직선 오차로 인해 정확한 레벨성과를 얻지못한다. Critical Control Points: Direct leveling should be carried out using only levels and steel tape. Optical surveys should not be performed using Total Station. Due to vertical line error of Total Station, accurate level performance is not obtained.

기대효과: 컬럼쇼트닝(Column shortening)을 확인하여 초고층 건물의 수직수축에 대해 파악하고 상부층 및 슬라브 골조시공에 있어 보정하여 작업하므로 전체 층고및 건물준공후 수축에 대하여도 보정하여 정밀시공이 가능하다.
Expected Effect: By checking the column shortening, the vertical contraction of high-rise buildings is identified and corrected in the construction of upper and slab frames.

최하층 기초MAT 침하 체크 : Bottom MAT Settlement Check:

실시시점: 최초 신설후 월1회 측량When to start: Survey once a month after initial establishment

사용장비: Lever, 줄자Equipment: Lever, Tape Measure

측량방법: 1)현장내 수준점에서 부터 건물 최하층 기초MAT까지 직접 수준측량하여 주동부 바닥에 동별4점이상 침하핀을 설치하여야 한다. 2)1개월 단위로 최초 신설한 방법과 동일하게 측량하여 침하 변위를 관찰 하여 설계값과 비교 검토하는게 바람직하다.Surveying method: 1) Four-point sinking pins should be installed on the base of the main eastern part by leveling directly from the site level point to the base MAT of the lowest floor of the building. 2) It is desirable to survey the settlement displacement and compare it with the design value in the same way as the newly established method on a monthly basis.

중점관리사항: 레벨 과 스틸테이프 만을 이용한 직접 수준측량을 실시하여야 한다. Total Station을 이용한 광파기 측량은 해서는 아니된다. Total Station의 연직선 오차로 인해 정확한 레벨성과를 얻지못한다. Critical Control Points: Direct leveling should be carried out using only levels and steel tape. Optical surveys should not be performed using Total Station. Due to vertical line error of Total Station, accurate level performance is not obtained.

또한 지하층 바닥마감으로 인한 침하핀이 망실될수 있으므로 침하핀 설치시 바닥에서 20㎝상부로 돌출시켜 신설하여야 된다.In addition, the sinking pins may be lost due to the basement floor finishing, so when installing the sinking pins, they should be protruded 20cm above the floor.

기대효과: 최하층 기초MAT 침하핀을 설치하여 하중이 증가함에 따른 건물의 침하 및 부등침하 여부를 파악하여 초고층 건물의 안정성을 확인하는게 바람직하다.
Expected Effect: It is desirable to check the stability of high-rise buildings by installing the lowest base MAT settlement pins to determine whether the building is subsided and unevenly settled as the load increases.

S : 슬라브(SLAB)
T : 타워크레인(TOWER-CRANE)
E : 건물 모서리(Edge)
C : 코아(Core)벽면
100 : 연직기(Laser Plummet) 110 : 광파기(Total Station) 120:레벨(Lever) 130 :스틸 테이프(Steel tape) 140 : 표척(스타프) 150 : 정밀타켓
200 : 부지경계
300 : 초고층 건물 310 : 지하 기초MAT 320 : 침하핀
400 : 기준점
500 : 허리먹선
600 : 시준선 610 : 기준먹선
700 : 골조먹박스(Open sleeve)
800 : 건물 내부기준점 검측 위치 810 : 건물 외벽 모서리 검측 위치 820 : 엘리베이터(Elevator Pit) 검측 위치
S: Slab
T: Tower Crane (TOWER-CRANE)
E: Edge of building
C: Core Wall
100: laser plummet 110: total station 120: level 130: steel tape 140: stippling 150: precision target
200: site boundary
300: high-rise building 310: underground foundation MAT 320: subsidence pin
400: reference point
500: waistline
600: collimation line 610: reference
700: skeleton sleeve box (Open sleeve)
800: Location of internal reference point detection 810: Location of outer wall edge detection 820: Location of elevator pit detection

Claims (11)

초고층 건물의 수직도 측량관리에 있어서;
최초 기준점 및 수준점 측량관리 하는 제1단계;
최하층 그리드라인 및 외곽선 위치 측량관리 하는 제2단계;
ACS(Automatic Climbing System)폼 셋팅 위치확인 하는 제3단계
각층 슬라브(SLAB) 기준먹 측량관리 하는 제4단계;
외주부 수직도 측량관리 하는 제5단계;
GPS(Global Positioning System)를 이용한 초고층 수직도 측량관리 하는 제6단계;
Core 및 기둥(Column) 수직도 측량관리 하는 제7단계;
각층 허리먹 측량관리 하는 제8단계;
컬럼쇼트닝(Column shortening) 검사 측량관리 하는 제9단계;
최하층의 전면기초(Mat Foundation) 침하량을 측량관리 하는 제10단계;
총체적인 흐름 과 아이템별 중점 관리사항 및 세부적 방법론 제시를 특징으로 하는 초고층 수직도 측량관리.
In the vertical surveying management of tall buildings;
A first step of managing initial reference point and level point surveying;
A second step of measuring the lowest gridline and outline position surveying;
3rd step to confirm ACS (Automatic Climbing System) form setting position
A fourth step of managing each layer slab reference mud;
A fifth step of managing the outer circumference verticality measurement;
A sixth step of managing high-rise verticality surveying using a global positioning system (GPS);
A seventh step of measuring core and column verticality measurement;
An eighth step of managing each waist waist measurement;
A ninth step of managing a column shortening inspection;
A tenth step of surveying and managing a bottom foundation settlement of Mat Foundation;
High-rise vertical surveying management, characterized by overall flow, itemized control points and detailed methodology.
제1항에 있어서;
상기 제1단계는,
지적도근점을 이용하여 기준점 측량시 폐합트래버스 망조정을 하여 오차량을 최소화하는 단계;
저층부4점 고층부4점 이상 신설하여 관리하고, 1개월 주기로 체크하여 변위여부 파악하는단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 건물 수직도 측량관리.
The method of claim 1, further comprising:
In the first step,
Minimizing an error amount by adjusting a closed traverse network when surveying a reference point using an cadastral point;
Establishing and managing four or more low-rise portions and four or more high-rise portions, and checking displacements every month for 1 month;
Skyscraper building vertical surveying management, characterized in that consisting of.
제1항에 있어서;
상기 제2단계는,
Total Station을 세워 정사각형으로 기준먹을 설치하고, 각각의 기준먹 거리는 30m 이상으로 골조팀이 사용할수 있도록 4점이상 설치하는 단계;
설치된 점에서 부터 건물 외곽선 각 모서리을 측량하여 설계위치에 건물이 정확히 확인하는 단계
연직선오차는 소거 불가능하므로 정반위 측량을 하여 오차를 최소화 하는 단계;
좌표측량 후 크로스 체크 개념으로 대각검측 및 치수를 확인하는 단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
The second step comprises:
Establish a total station to install the standard food in the square, each standard food distance is installed more than four points so that the skeleton team can use more than 30m;
Survey the corners of the building outline from the installed point to verify the building accurately at the design location
Since the vertical line error is impossible to erase, minimizing the error by performing a specular measurement;
Confirming diagonal detection and dimensions with a cross check concept after coordinate surveying;
Ultra-high rise vertical surveying, characterized in that consisting of.
제1항에 있어서;
상기 제3단계는,
ACS폼 각 모서리 마다 나사못으로 표시하는 단계;
확정된 기준점에서 GPS, Total Station을 이용하여 ACS폼 모서리 마다 하단 및 상단 수평 위치를 확인하는 단계;
설계기준과 비교분석하여 ACS폼 수정보완 후 셋팅하는 단계;
ACS폼 셋팅 후 장기 사용으로 인해 오차량이 발생됨으로 10개층 간격으로 재 확인하여 수정보완 하는 단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
In the third step,
Marking screws at each corner of the ACS foam;
Checking the bottom and top horizontal positions of each corner of the ACS foam using GPS and Total Station at the determined reference point;
Comparing and comparing the design criteria with the ACS form number setting;
After the ACS foam setting, the error amount is generated due to long-term use, and reconfirming the information at 10-layer intervals;
Ultra-high rise vertical surveying, characterized in that consisting of.
제1항에 있어서;
상기 제4단계는,
골조 오픈슬리브 설치에 있어 Core부 4개소, 외주부 4개소 이상 오픈 슬리브를 설치 하는 단계;
기준먹이설 전 기준층 기준먹을 Total Station을 이용하여 각도 및 거리를 확인하는 단계;
골조 기준먹 오픈슬리브를 통하여 연직기를 이용하여 기준층 기준라인에서 상부층으로 골조 기준먹 확인 하는 단계;
시준시 각도는0°, 90°, 180°, 270°총4회를 시준하여 평균값을 취하여 이설오차를 소거하는 단계;
연직기를 이용하여 상부층으로 이설후 상부층의 이설된 기준먹을 Total Station을 이용하여 각도와 거리를 확인하는 단계;
골조 기준먹과 연직기 측량값이 차이를 파악 하여 오차발생시 즉시 보정 및 수정하는 하는 단계;
기준층에서 부터 먹박스를 통하여 다이렉트(Direct)로 15개층 이상 측설하는 단계;
기준층은 건조수축이 콘크리트 타설 10일 경과후 15개층 간격으로 이설 하는단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
In the fourth step,
Installing four open cores and four open outer peripheries in a framed open sleeve;
Confirming the angle and distance by using the total station to eat the reference layer before the reference feeding;
Checking the skeleton reference mud from the reference layer reference line to the upper layer using the weaving machine through the skeleton reference mud open sleeve;
Collimating the collimation angle of 0 °, 90 °, 180 °, and 270 ° four times, taking an average value to eliminate the relocation error;
Checking the angle and distance by using a total station that is moved to the upper layer by using a weaving machine and then moved by the reference layer of the upper layer;
Grasping the difference between the frame reference mud and the weaving machine measurement value and immediately correcting and correcting the error;
Stake out at least 15 floors from the reference layer through a mux box directly;
The reference layer is a dry shrinkage step of moving to 15 layers after 10 days of concrete pouring;
Ultra-high rise vertical surveying, characterized in that consisting of.
제1항에 있어서;
상기 제5단계는,
상기 제4단계 시행 후 시행하는 단계;
기준라인에서 부터 슬라브 끝선까지 Total Station 및 줄자를 이용하여 각도 및 거리를 체크하여 건물외곽 모서리 위치 확인하는 단계;
외부기준점에서 3개층 간격으로 Total Station 또는 GPS를 이용하여 슬라브 끝선을 재 확인 하는 단계;
외부에서 좌표 측량시 건물 외벽과 나란한 지점에 Total Station을 설치하여 측벽 라인을 확인하고 매번 같은 지점에서 측량하여야 오차발생을 최소화 하는 단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
In the fifth step,
Executing after the fourth step;
Checking an angle and a distance from a reference line to a slab end line using a total station and a tape measure to determine a location of a corner of a building;
Reconfirming the slab end line using Total Station or GPS at three floor intervals from an external reference point;
Installing a total station at a point parallel to the outer wall of the building to check the side wall line and surveying the same point every time to minimize the occurrence of errors when coordinate surveying from the outside;
Ultra-high rise vertical surveying, characterized in that consisting of.
제1항에 있어서;
상기 제6단계는,
상기 제1단계 시행 후 시행하는 단계;
GPS좌표와 현장기준점 간의 오차가 발생함으로 GPS기준 망조정을 하여 GPS좌표를 현장 기준좌표로 변환하는 단계;
변환좌표가 확정되면 GPS수신기를 가지고 건물내부의 기준점 체크 포인트로 이동하는 단계;
1점측설시 필히 30분이상 측위하고 2시간 간격으로 2회 더 측위하여 측정된 좌표를 프로그램 [SPECTRUM SURVEY]을 이용하여 프로그램화 하여 평균값을 취득하는 단계;
GPS 확정된 좌표와 연직기 측정값과의 결과값 비교 분석하여 수정보완 하는 단계;
상기 제4단계를 골조 준공시까지 진행하고 크로스체크 개념으로 GPS로 확인하여 15MM이상 오차발생시 제4단계를 재 확인 하는단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
The sixth step,
Executing after the first step;
Converting the GPS coordinates into the field reference coordinates by adjusting the GPS reference network as an error occurs between the GPS coordinates and the field reference points;
Moving to a reference point check point in the building with a GPS receiver when the converted coordinate is confirmed;
Programing the measured coordinates using the program [SPECTRUM SURVEY] by positioning more than 30 minutes and positioning two more times at a time interval of 1 point when staked out;
Comparing and analyzing the result value between the GPS-determined coordinates and the weaving machine measurements;
Proceeding to the fourth step until the completion of the frame and confirming the fourth step in case of an error of 15 mm or more by checking with a GPS as a cross check concept;
Ultra-high rise vertical surveying, characterized in that consisting of.
제1항에 있어서;
상기 제7단계는,
상기 제4단계 시행 후 시행하는 단계;
Total Station을 이용하여 Core 기준라인에서 부터 기둥먹선까지 각도 및 거리를 확인하는 단계;
Core벽면에 Core끝선으로 부터 20㎝이동시켜 수직 먹선을 설치하는 단계;
Core기준라인에서 부터 Elevator Pit 4각모서리를 Total Station으로 체크하는 단계;
오차발생 수정시 Elevator Pit폼 특성상 1개층에서 30mm 이상의 오차는 수정불가능 함으로 층당5㎜씩 여러층에 걸쳐서 수정하는 단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
The seventh step,
Executing after the fourth step;
Confirming the angle and distance from the core reference line to the pillar line using Total Station;
Installing vertical vertical lines on the core wall by moving 20 cm from the core end line;
Checking the elevator pit square corner from the core reference line to the total station;
When the error is corrected, the error of more than 30mm in one layer due to the characteristics of the elevator Pit form is impossible to correct the step of correcting over several layers by 5mm per floor;
Ultra-high rise vertical surveying, characterized in that consisting of.
제1항에 있어서;
상기 제8단계는,
상기 제1단계 시행 후 시행하는 단계;
건물 최하층까지 수준측량하여 바닥 슬라브에서 1M 상부 지점(Core벽면)에 2점이상 허리먹선을 설치하는 단계;
최하층에 신설된 허리먹을 이용하여 상부층으로 이설하여 허리먹선을 표시하는 단계;
10개층 간격으로 수준점(TBM)에서 허리먹선을 직접 확인하여 컬럼 쇼트닝(Column shortening)발생량을 상부층으로 보정하여 작업하는 단계;
Core선행 작업시 외주부 Slab콘크리트 타설일정보다 허리먹을 Core벽면에 선시공하는 단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
The eighth step,
Executing after the first step;
Leveling up to the lowest floor of the building and installing two-point waistline at the 1M upper point (Core wall surface) on the floor slab;
Displaying the waist line by relocating to the upper layer by using the waist layer newly formed at the bottom layer;
Checking the waist line directly at the level (TBM) at intervals of 10 layers and correcting the amount of column shortening to the upper layer;
Preliminary work on the core wall surface of the outer periphery Slab concrete placing work information during the core leading work;
Ultra-high rise vertical surveying, characterized in that consisting of.
제1항에 있어서;
상기 제9단계는,
상기 제1단계 시행 후 시행하는 단계;
상기 건물의 최하층부터 최상층 중에서, 건물 구조해석하여 하중의 증가 및 시간 경과에 따른 변형률이 가장 큰 층을 선정하는 단계;
슬라브 바닥에서 1M상부지점 Core5점, 컬럼 10점을 선정하여 칼금 표시하는 단계;
외부 수준점에서 부터 레벨 과 스틸테이프 만을 이용한 직접 수준측량을 실시하는 단계;
최초 신설후 1개월 단위로 상대 축소 변위를 관찰 하여 설계값과 비교 검토하는 단계;
초고층 건물의 수직수축에 대해 파악하고 상부층 및 슬라브 골조시공에 있어 보정하여 작업하는 단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
The ninth step,
Executing after the first step;
Selecting, from the lowest floor to the uppermost floor of the building, a building structure analysis to select a floor having the largest increase in load and strain over time;
Selecting a 1M upper point Core5 point and a column 10 point at the bottom of the slab to display a sword;
Performing a direct leveling using only the level and steel tape from an external level point;
Observing relative shrinkage displacements in units of one month after initial construction and comparing them with design values;
Identifying the vertical contraction of the skyscraper and correcting and working in the construction of the upper floor and the slab;
Ultra-high rise vertical surveying, characterized in that consisting of.
제1항에 있어서;
상기 제10단계는,
상기 제1단계 시행 후 시행하는 단계;
수준점에서 부터 건물 최하층 기초MAT까지 레벨 과 스틸테이프 만을 이용한 직접 수준측량을 하는 단계;
주동부 바닥마감으로 인한 침하핀이 망실될수 있으므로 침하핀 설치시 바닥에서 20㎝상부로 돌출시켜 동별4점이상 침하핀을 설치하는 단계;
1개월 단위로 최초 신설한 방법과 동일하게 측량하여 침하 및 부등침하 변위를 관찰 하여 설계값과 비교 검토하는 단계;
를 포함하여 이루어지는 것을 특징으로하는 초고층 수직도 측량관리.
The method of claim 1, further comprising:
The tenth step,
Executing after the first step;
Performing direct level surveying using only the level and steel tape from the level point to the base MAT of the lowest floor of the building;
Since the sinking pins may be lost due to the bottom of the main eastern part, installing the sinking pins by protruding from the bottom 20 cm above the bottom when installing the sinking pins;
In the same way as the newly established method on a monthly basis, the step of observing settlement and unequal displacement, and comparing with the design value;
Ultra-high rise vertical surveying, characterized in that consisting of.
KR1020110079906A 2011-08-11 2011-08-11 Measuring the vertical management of high-rise buildings KR101177889B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110079906A KR101177889B1 (en) 2011-08-11 2011-08-11 Measuring the vertical management of high-rise buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110079906A KR101177889B1 (en) 2011-08-11 2011-08-11 Measuring the vertical management of high-rise buildings

Publications (1)

Publication Number Publication Date
KR101177889B1 true KR101177889B1 (en) 2012-08-29

Family

ID=46887963

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110079906A KR101177889B1 (en) 2011-08-11 2011-08-11 Measuring the vertical management of high-rise buildings

Country Status (1)

Country Link
KR (1) KR101177889B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101751991B1 (en) 2017-03-21 2017-06-30 테이즈엔지니어링(주) High-rise management surveying method
KR101879804B1 (en) * 2018-02-20 2018-07-18 한진정보통신(주) System for managing verticality of high-rise buildings using gnss/inclinometer
CN109443324A (en) * 2018-09-21 2019-03-08 中国五冶集团有限公司 A kind of construction site construction survey method
KR102359081B1 (en) * 2021-05-13 2022-02-08 기하토목기술(주) Method of perpendicularity supervising survey
KR102530428B1 (en) 2022-12-23 2023-05-09 테이즈엔지니어링(주) Level point verticality relocation survey method and survey apparatus therefor

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100796033B1 (en) 2006-04-05 2008-01-21 (주)성풍건설 The measurement method for perpendicular point making use of raise climber
KR100928662B1 (en) 2007-08-22 2009-11-26 이양재 A multipurpose instrument
KR101021057B1 (en) 2008-11-10 2011-03-15 김유경 Apparatus and Method for Measuring Vertical Straightness
KR101033230B1 (en) 2010-03-31 2011-05-06 주식회사 대한지오매틱스 Horizontal and vertical device for level measurement

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100796033B1 (en) 2006-04-05 2008-01-21 (주)성풍건설 The measurement method for perpendicular point making use of raise climber
KR100928662B1 (en) 2007-08-22 2009-11-26 이양재 A multipurpose instrument
KR101021057B1 (en) 2008-11-10 2011-03-15 김유경 Apparatus and Method for Measuring Vertical Straightness
KR101033230B1 (en) 2010-03-31 2011-05-06 주식회사 대한지오매틱스 Horizontal and vertical device for level measurement

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101751991B1 (en) 2017-03-21 2017-06-30 테이즈엔지니어링(주) High-rise management surveying method
KR101879804B1 (en) * 2018-02-20 2018-07-18 한진정보통신(주) System for managing verticality of high-rise buildings using gnss/inclinometer
CN109443324A (en) * 2018-09-21 2019-03-08 中国五冶集团有限公司 A kind of construction site construction survey method
KR102359081B1 (en) * 2021-05-13 2022-02-08 기하토목기술(주) Method of perpendicularity supervising survey
KR102530428B1 (en) 2022-12-23 2023-05-09 테이즈엔지니어링(주) Level point verticality relocation survey method and survey apparatus therefor

Similar Documents

Publication Publication Date Title
KR101177889B1 (en) Measuring the vertical management of high-rise buildings
CN106320707B (en) A kind of full projection line-putting method
Abdelrazaq Validating the structural behavior and response of Burj Khalifa: Synopsis of the full scale structural health monitoring programs
CN102080960B (en) Super-high-rise building verticality measuring and controlling method based on GPS (Global Positioning System)
CN104034319B (en) A kind of skyscraper measures control point projection positioning auxiliary device and using method thereof
CN111609833B (en) Settlement observation method for high-rise building
CN102094532A (en) Method for measuring and controlling size of building construction horizontal member
CN106223623A (en) Steel construction box arched roof truss installation method
CN111999148B (en) Method for quickly constructing original rock crustal stress test standard part with saturated stress
Mrówczyńska et al. Indicating vertical deviation of historical buildings using geodetic methods-case study of brick and wood tower in Nowe Miasteczko
KR101234372B1 (en) Method of Perpendicularity Supervising Survey using Totalstation
KR100602832B1 (en) Amentment method of differential shortenint of vertical member in reinforced-concrete structures
Cardoso et al. Tabique walls typologies and building details in the Alto Douro Wine Region
KR100929144B1 (en) System for managing position and obtaining shape information of building structure using gnss
KR102359081B1 (en) Method of perpendicularity supervising survey
Hayes et al. Core Wall Survey Control System for High Rise Buildings.
CN207779390U (en) Tile paved surface absolute altitude and levelness measuring device
CN102995899A (en) Measurement control method for sizes of building construction vertical members
RU2011120865A (en) METHOD FOR CONSTRUCTION AND ANALYSIS OF STRESSED-DEFORMED CONDITION OF BUILDINGS, STRUCTURES AND OTHER EXTENDED VERTICAL OBJECTS ON UNEQUALLY COMPRESSIBLE SOILS
RU2267745C1 (en) Coordinate post-construction survey method
Kim et al. Key technologies for super tall building construction: Lotte world tower
Katz Statistical Variations of Rebar Placement and Its Effect on Service Life
CN103452315A (en) Construction method of high-precision heterogenic thin-walled concrete hole body structure
KR101580993B1 (en) Gang form having horizontal level measurement function of construction site
Uranjek et al. Seismic strengthening of churches as a part of earthquake renewal in the Posočje region, Slovenia

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150821

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160822

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20170816

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180822

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190822

Year of fee payment: 8