KR101129275B1 - Method for manufacturing half pc(precast concrete) slab - Google Patents

Method for manufacturing half pc(precast concrete) slab Download PDF

Info

Publication number
KR101129275B1
KR101129275B1 KR1020110107836A KR20110107836A KR101129275B1 KR 101129275 B1 KR101129275 B1 KR 101129275B1 KR 1020110107836 A KR1020110107836 A KR 1020110107836A KR 20110107836 A KR20110107836 A KR 20110107836A KR 101129275 B1 KR101129275 B1 KR 101129275B1
Authority
KR
South Korea
Prior art keywords
slab
concrete
reinforcing member
formwork
manufacturing
Prior art date
Application number
KR1020110107836A
Other languages
Korean (ko)
Inventor
이진섭
이정현
강태성
전재홍
Original Assignee
삼표건설 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼표건설 주식회사 filed Critical 삼표건설 주식회사
Priority to KR1020110107836A priority Critical patent/KR101129275B1/en
Application granted granted Critical
Publication of KR101129275B1 publication Critical patent/KR101129275B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/26Producing shaped prefabricated articles from the material by slip-casting, i.e. by casting a suspension or dispersion of the material in a liquid-absorbent or porous mould, the liquid being allowed to soak into or pass through the walls of the mould; Moulds therefor ; specially for manufacturing articles starting from a ceramic slip; Moulds therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/065Light-weight girders, e.g. with precast parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Dispersion Chemistry (AREA)
  • Manufacturing & Machinery (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Abstract

PURPOSE: A half PC slab manufacturing method is provided to automatically manufacture half PC slabs with shear bond strength secured by integrated reinforcing members. CONSTITUTION: A half PC slab manufacturing method comprises the steps of: setting reinforcing members(120) in the longitudinal direction of a half PC slab(100) within a form in order to reinforce the shear strength of the half PC slab, placing concrete in a form with a concrete placing device(300) from above the form so that the horizontally bent upper portions of the reinforcing members are exposed on the concrete placed in the form, and straightening the bent upper portions of the reinforcing members to protrude from the top of the half PC slab body formed out of the concrete.

Description

하프 PC 슬래브의 제조방법{Method for manufacturing half PC(precast concrete) slab}Method for manufacturing half PC slab {Method for manufacturing half PC (precast concrete) slab}

본 발명은 하프 PC 슬래브의 제조방법에 관한 것으로서, 보다 상세하게는 보강부재가 돌출된 형태로 제조되는 하프 PC 슬래브의 제조방법에 관한 것이다.The present invention relates to a method for manufacturing a half PC slab, and more particularly to a method for manufacturing a half PC slab is produced in the form of a protruding reinforcing member.

슬래브는 건설, 토목 분야 등에서 철근콘크리트구조의 바닥을 말한다.Slab refers to the floor of reinforced concrete structures in construction and civil engineering.

이러한 슬래브는 다음과 같이 방법들로 시공하고 있다.Such slabs are constructed in the following ways.

첫째, 슬래브 전체를 현장에서 콘크리트 타설 작업에 의해 시공하는 현장타설공법이 있다.First, there is an on-site casting method in which the entire slab is constructed by concrete pouring work on site.

둘째, 슬래브를 공장 등에서 미리 프리캐스트 패널(precast panel)로 분할 제작한 후, 현장으로 이송하여 설치하는 프리캐스트공법이 있다.Second, there is a precast method of dividing the slab into precast panels in a factory or the like, and then transporting and installing the slab to a site.

셋째, 슬래브의 두께 방향을 따라 슬래브의 일부를 프리캐스트 패널로 시공하고. 그 나머지를 현장콘크리트 타설에 의해 시공하는 하프 프리캐스트 공법(half precast method)이 있다. 이하, 설명의 편의를 위해 하프 프리캐스트 공법에서 프리캐스트 패널로 이루어지는 슬래브의 일부를 하프 PC 슬래브라 하며, 현장 콘크르트 타설에 의해 시공되는 슬래브의 나머지 부분을 현장 타설 슬래브라 한다. Third, construct a part of the slab with a precast panel along the thickness direction of the slab. There is a half precast method in which the rest is constructed by on-site concrete casting. Hereinafter, for convenience of description, a part of the slab made of the precast panel in the half precast method is a half PC slab, and the remaining part of the slab constructed by site concrete placing is cast in place.

이 중 하프 프리캐스트 공법의 경우, 도 1 및 도 2에 도시된 바와 같이 하프 PC 슬래브(2)와 현장 타설 슬래브 간 결합력을 높이기 위해, 하프 PC 슬래브(2)에 현장 타설 슬래브의 콘크리트 타설 작업시 콘크리트가 타설될 수 있도록 홈 또는 홀 구조의 전단 키(shear key)(2b)가 복수 형성될 수 있다. 도 1 및 도 2에 도시된 하프 PC 슬래브(2)는 하프 PC 슬래브(2)의 길이방향(화살표 L)을 따라 관통된 코어(core)(2a)를 갖는 할로우 코어(hollow core) 구조이다.In the case of the half precast method, as shown in Figs. 1 and 2, in order to increase the coupling force between the half PC slab (2) and the in-site casting slab, when the concrete pouring work of the in-site casting slab to the half PC slab (2) A plurality of shear keys 2b having a groove or hole structure may be formed so that concrete can be poured. The half PC slab 2 shown in FIGS. 1 and 2 is a hollow core structure having a core 2a pierced along the longitudinal direction (arrow L) of the half PC slab 2.

이러한 하프 PC 슬래브(2)는 제작 및 운송, 인양 등이 가능한 소정 단위로 제조된 후, 현장에서 하프 PC 슬래브(2)이 폭방향(화살표 W) 및 길이방향(화살표 L)을 따라 상호 연접되도록 설치될 수 있다.The half PC slab 2 is manufactured in a predetermined unit that can be manufactured, transported and lifted, and then the half PC slab 2 is connected to each other along the width direction (arrow W) and the length direction (arrow L) in the field. Can be installed.

그러나, 종래 기술에 따른 하프 프리캐스트 공법은, 하프 PC 슬래브(2)의 전단키(2b)만으로는 충분한 수평전단력을 확보하기 어렵고, 하프 PC 슬래브(2)의 전단키(2b)를 형성하기 위해 하프 PC 슬래브(2) 제작을 위한 거푸집의 구조가 복잡하여 거푸집의 설계가 용이하지 않다는 문제점이 지적되고 있다. 더욱이, 상기 하프 프리캐스트 공법은 자동화 공법으로 수행되기 어려운 단점이 있다.However, the half precast method according to the prior art is difficult to secure sufficient horizontal shear force only by the shear key 2b of the half PC slab 2, and the half PC slab is formed to form the shear key 2b of the half PC slab 2. (2) It is pointed out that the design of the formwork is not easy due to the complicated structure of the formwork for fabrication. Moreover, the half precast method has a disadvantage in that it is difficult to be performed by the automated method.

대한민국 등록특허 10-0644139(중공 구조를 갖는 하프 슬래브 및 그 제작방법)Republic of Korea Patent Registration 10-0644139 (Half slab having a hollow structure and its manufacturing method)

본 발명은, 일체로 매립된 보강부재에 의해 현장 타설 슬래브와의 전단 결합력을 확보할 수 있도록 함과 아울러 하프 PC 슬래브를 자동 생산 방식으로 제조하기 위한 하프 PC 슬래브의 제조방법을 제공하는 것을 목적으로 한다.An object of the present invention is to provide a method for manufacturing a half PC slab for producing a half PC slab by an automatic production method while also ensuring a shear bonding force with a site-pouring slab by an integrally embedded reinforcing member. do.

본 발명은, 하프 PC 슬래브의 제조방법에 있어서, 바닥 또는 프레임 위에 하프 PC 슬래브의 전단력 보강을 위하여 상기 하프 PC 슬래브의 길이방향을 따라 보강부재들을 설치하되, 상기 보강부재는 하부로부터 상부로 연장되며 상부 부분이 수평 방향으로 절곡된 상태로 설치되는 보강부재 설치단계와, 상기 프레임 또는 상기 하프 PC 슬래브의 거푸집 폼이 구비된 콘크리트 타설장치를 상기 길이방향을 따라 직선 이동시켜 상기 콘크리트 타설장치의 거푸집 폼에 의해 상기 보강부재가 위치된 하프 PC 슬래브의 콘크리트 타설영역을 형성하면서 상기 타설영역의 상측에서 상기 타설영역에 콘크리트를 타설하되, 상기 보강부재의 절곡된 상부 부분이 상기 타설된 콘크리트의 상면 상에 노출되도록 하는 콘크리트 타설 단계와, 상기 콘크리트 타설로부터 소정 시간이 흐른 후, 상기 보강부재의 절곡된 상부 부분을 펴서 상기 하프 PC 슬래브의 콘크리트로 이루어진 본체부의 상부로 돌출시키는 보강부재 펼침단계를 포함하는 하프 PC 슬래브의 제조방법을 제공한다.According to the present invention, in the method of manufacturing a half PC slab, reinforcing members are installed along a longitudinal direction of the half PC slab to reinforce the shear force of the half PC slab on the floor or the frame, and the reinforcing member extends from the bottom to the top. Forming form of the concrete pouring apparatus by linearly moving the reinforcement member installation step of the upper portion is installed in the horizontal direction and the concrete pouring apparatus provided with the form foam of the frame or the half PC slab along the longitudinal direction By placing concrete in the pour area on the upper side of the pour area while forming the concrete pour area of the half PC slab where the reinforcing member is located, wherein the bent upper portion of the stiffened member is placed on the top surface of the poured concrete. Concrete pouring step to expose, and predetermined from the concrete pouring After a period of time, it provides a method of manufacturing a half PC slab comprising the step of unfolding the reinforcing member to extend the bent upper portion of the reinforcing member to protrude to the top of the body portion made of the concrete of the half PC slab.

본 발명에 있어서, 상기 콘크리트 타설장치는, 상기 콘크리트 타설장치 또는 상기 프레임이 직선 이동할 때, 상기 타설된 콘크리트의 상면에 밀착될 수 있도록 이루어진 타설 콘크리트 밀착부를 포함할 수 있다.In the present invention, the concrete placing device, when the concrete placing device or the frame moves linearly, may include a pour concrete contact portion made to be in close contact with the upper surface of the pour concrete.

또한, 본 발명의 다른 측면에 따르면, 본 발명은, 하프 PC 슬래브의 제조방법에 있어서, 하프 PC 슬래브용 거푸집 내에 상기 하프 PC 슬래브의 전단력 보강을 위하여 보강부재를 설치하되, 상기 보강부재는 상기 거푸집 내에서 하부로부터 상부로 연장되며 상부 부분이 수평 방향으로 절곡된 상태로 설치되는 보강부재 설치단계와, 상기 거푸집 또는 콘크리트 타설장치를 상기 거푸집의 길이방향을 따라 직선 이동시키면서 상기 콘크리트 타설장치에 의해 상기 거푸집의 상측에서 상기 거푸집 내에 콘크리트를 타설하되, 상기 보강부재의 절곡된 상부 부분이 상기 거푸집에 타설된 콘크리트의 상면 상에 노출되도록 하는 콘크리트 타설 단계와, 상기 콘크리트 타설로부터 소정 시간이 흐른 후, 상기 보강부재의 절곡된 상부 부분을 펴서 상기 하프 PC 슬래브의 콘크리트로 이루어진 본체부의 상부로 돌출시키는 보강부재 펼침단계를 포함하는 하프 PC 슬래브의 제조방법을 제공한다.In addition, according to another aspect of the present invention, in the manufacturing method of the half PC slab, the reinforcing member is installed in the formwork for the half PC slab for reinforcing the shear force of the half PC slab, the reinforcing member is the formwork The reinforcing member installation step of extending from the bottom to the top in the upper portion is bent in a horizontal direction and installed by the concrete pouring device while linearly moving the formwork or concrete pouring device along the longitudinal direction of the formwork Pouring concrete into the formwork at the upper side of the formwork, wherein the bent upper portion of the reinforcing member is exposed to the upper surface of the concrete poured into the formwork; Straightening the bent upper part of the reinforcing member said half PC slab It provides a process for the preparation of the half PC slab containing reinforcing members unfolding step of projecting to the upper body portion made of a concrete.

본 발명에 있어서, 상기 콘크리트 타설장치는, 상기 콘크리트 타설장치 또는 상기 거푸집이 직선 이동할 때, 상기 타설된 콘크리트의 상면에 밀착될 수 있도록 이루어진 타설 콘크리트 밀착부를 포함할 수 있다.In the present invention, the concrete placing device, when the concrete placing device or the formwork moves linearly, may include a pour concrete contact portion made to be in close contact with the upper surface of the poured concrete.

상기 콘크리트 타설장치는 상기 거푸집의 길이방향을 따라 전진함과 아울러 전후방향 및 상하방향 중 적어도 하나의 방향으로 진동하면서 상기 거푸집 내에 콘크리트를 타설토록 이루어질 수 있다.The concrete pouring device may be made to pour concrete in the formwork while advancing along the longitudinal direction of the formwork and vibrating in at least one of front and rear and up and down directions.

또한, 본 발명의 또 다른 측면에 따르면, 본 발명은, 하프 PC 슬래브의 제조방법에 있어서, 프레임 상에 설치된 상기 하프 PC 슬래브용 거푸집 내에 상기 하프 PC 슬래브의 전단력 보강을 위하여 보강부재를 설치하되, 상기 보강부재는 상기 거푸집 내에서 하부로부터 상부로 연장되며 상부 부분이 수평 방향으로 절곡된 상태로 설치되는 보강부재 설치단계와, 콘크리트 타설장치에 의해 상기 거푸집의 상측에서 상기 거푸집 내에 콘크리트를 타설하되 상기 보강부재의 절곡된 상부 부분이 상기 거푸집에 타설된 콘크리트의 상면 상에 노출되도록 함과 아울러, 상기 거푸집을 진동시키는 상기 콘크리트 타설 단계와, 상기 콘크리트 타설로부터 소정 시간이 흐른 후, 상기 보강부재의 절곡된 상부 부분을 펴서 상기 하프 PC 슬래브의 콘크리트로 이루어진 본체부의 상부로 돌출시키는 보강부재 펼침단계를 포함하는 하프 PC 슬래브의 제조방법을 제공한다.In addition, according to another aspect of the present invention, in the manufacturing method of the half PC slab, the reinforcing member is installed in the form for the half PC slab installed on the frame to reinforce the shear force of the half PC slab, The reinforcing member extends from the bottom to the upper side within the formwork, and the reinforcing member installation step of installing the upper portion is bent in a horizontal direction, and the concrete is poured into the formwork in the form on the upper side of the formwork by the concrete pouring device The concrete placing step of causing the bent upper portion of the reinforcing member to be exposed on the upper surface of the concrete poured in the formwork, and vibrating the formwork, and after a predetermined time has passed from the concrete placing, bending of the reinforcing member Main body made of concrete of the half PC slab It provides a method for producing a half PC slab comprising a step of expanding the reinforcing member to protrude to the upper portion of the part.

상기 하프 PC 슬래브의 본체부는 평판부 및, 상기 하프 PC 슬래브의 길이방향을 따라 길게 상기 평판부에 수직 돌출 형성된 리브를 포함할 수 있다.The main body portion of the half PC slab may include a flat plate and ribs protruding perpendicularly to the flat plate along the longitudinal direction of the half PC slab.

상기 하프 PC 슬래브의 본체부는 상기 하프 PC 슬래브의 길이방향을 따라 관통된 코어를 갖도록 형성될 수 있다.The main body portion of the half PC slab may be formed to have a penetrated core along the longitudinal direction of the half PC slab.

상기 보강부재는 상기 거푸집에 타설된 콘크리트의 상면 상에 노출되는 상부 부분이 고리 형상을 갖도록 이루어질 수 있다.The reinforcing member may be formed so that the upper portion exposed on the upper surface of the concrete poured in the formwork has a ring shape.

상기 보강부재는 상기 고리 형상을 갖도록 상기 하프 PC 슬래브의 폭방향 또는 길이방향을 따라 '∩'으로 절곡된 형상의 본체부를 포함할 수 있다.The reinforcing member may include a body portion bent in a '으로' along the width direction or the longitudinal direction of the half PC slab to have the annular shape.

상기 보강부재는 상기 하프 PC 슬래브의 길이방향을 따라 상호 이격 설치되는 복수의 본체부를 포함할 수 있다.The reinforcing member may include a plurality of main body parts spaced apart from each other along the longitudinal direction of the half PC slab.

상기 보강부재는 상기 거푸집에 타설된 콘크리트에 매립되며 상기 하프 PC 슬래브의 폭방향을 따라 상기 보강부재의 본체부로부터 돌출되도록 상기 보강부재의 본체부와 일체로 형성되는 절곡부를 더 포함할 수 있다.The reinforcing member may further include a bent portion embedded in the concrete poured in the formwork and integrally formed with the main body portion of the reinforcing member to protrude from the main body portion of the reinforcing member along the width direction of the half PC slab.

상기 보강부재는 상기 하프 PC 슬래브의 길이방향을 따라 상호 이격 설치되는 복수의 본체부 및, 상기 거푸집에 타설된 콘크리트에 매립될 수 있도록 형성되며 상기 본체부와 본체부 사이에 형성되어 일체로 연결하는 복수의 연결부를 포함할 수 있다.The reinforcing member is formed to be embedded in a plurality of body parts spaced apart from each other along the longitudinal direction of the half PC slab, and to be embedded in the concrete poured in the formwork and formed between the body portion and the body portion to connect integrally It may include a plurality of connections.

상기 보강부재는 상기 복수의 본체부 및 복수의 연결부가 하나의 라인으로 상호 연속적으로 연결되도록 이루어질 수 있다.The reinforcing member may be configured such that the plurality of body parts and the plurality of connecting parts are continuously connected to each other in one line.

본 발명에 따른 하프 PC 슬래브의 제조방법은 하프 PC 슬래브의 콘크리트로 이루어진 본체부의 상측으로 보강부재의 상부 부분이 돌출되도록 하프 PC 슬래브를 제조할 수 있기 때문에, 보강부재에 의해 하프 PC 슬래브와 현장 타설 슬래브 간 전단 결합력이 향상될 수 있는 이점을 가질 수 있다.Since the manufacturing method of the half PC slab according to the present invention can produce the half PC slab so that the upper part of the reinforcing member protrudes to the upper side of the main body portion made of concrete of the half PC slab, in situ casting with the half PC slab by the reinforcing member It may have an advantage that the shear bonding force between slabs can be improved.

또한, 본 발명에 따른 하프 PC 슬래브의 제조방법은 상술한 바와 같이 보강부재가 종래의 홈 또는 홀 구조의 전단 키를 대신함에 따라, 하프 PC 슬래브의 거푸집의 구조가 보다 간소해질 수 있어 하프 PC 슬래브의 설계 및 제작이 보다 용이해질 수 있는 이점을 가질 수 있다.In addition, in the method of manufacturing a half PC slab according to the present invention, as the reinforcing member replaces the shear key of the conventional groove or hole structure as described above, the formwork of the half PC slab can be more simplified, the half PC slab It can have the advantage that the design and fabrication of the can be easier.

또한, 본 발명에 따른 하프 PC 슬래브의 제조방법은 하프 PC 슬래브의 제조시 보강부재의 상부 부분이 수평방향으로 절곡된 상태로 보강부재를 거푸집 내에 설치하며, 거푸집 내에 타설된 콘크리트가 어느 정도 강도를 갖도록 굳고 난 후 보강부재의 상부 부분을 수직방향으로 펼침에 따라, 보강부재에 의한 간섭없이 콘크리트 타설장치에 의해 하프 PC 슬래브의 자동 생산이 이루어질 수 있어, 기계화, 자동화 생산에 따른 인건비 감소, 생산시간 감소, 품질의 일정화(즉, 고품질화)의 이점을 가질 수 있다.In addition, the manufacturing method of the half PC slab according to the present invention, when manufacturing the half PC slab, the reinforcing member is installed in the formwork with the upper portion of the reinforcing member bent in the horizontal direction, the concrete poured in the formwork to a certain degree of strength As the upper part of the reinforcing member is unfolded in the vertical direction after being hardened to have it, automatic production of the half PC slab can be made by the concrete pouring device without interference by the reinforcing member, thereby reducing the labor cost due to mechanization and automated production, and production time. It may have the advantage of reduction, constant quality (ie, high quality).

도 1은 종래 기술에 따른 하프 PC 슬래브의 현장 설치 예를 도시한 도면.
도 2는 종래 기술에 따른 하프 PC 슬래브의 일부 사시도.
도 3은 본 발명의 제1실시 예에 따른 하프 PC 슬래브의 일부 사시도.
도 4는 도 3의 A-A방향에 따른 단면도.
도 5는 도 3의 종단면도.
도 6은 본 발명의 제2실시 예에 따른 하프 PC 슬래브의 종단면도.
도 7은 도 6의 횡단면도.
도 8은 도 6에 적용된 보강부재의 사시도.
도 9는 본 발명의 제3실시 예에 따른 하프 PC 슬래브의 종단면도.
도 10은 도 9의 횡단면도.
도 11은 본 발명의 제4실시 예에 따른 하프 PC 슬래브의 종단면도.
도 12a 내지 도 12e는 본 발명의 제1실시 예에 따른 하프 PC 슬래브의 자동 생산을 위한 제조방법을 순서대로 도시한 도면.
도 13은 도 12에 도시된 자동 생산을 위한 설비의 평면도.
도 14는 도 12에 도시된 자동 생산을 위한 설비의 정면도.
도 15는 본 발명의 하프 PC 슬래브의 다른 실시 예에 따른 자동 생산을 위한 설비의 정면도.
도 16은 본 발명의 하프 PC 슬래브의 또 다른 실시 예에 따른 자동 생산을 위한 설비의 측면도.
도 17은 도 16의 정면도.
도 18은 도 16의 사시도.
1 is a view showing an on-site installation example of a half PC slab according to the prior art.
2 is a partial perspective view of a half PC slab according to the prior art.
3 is a partial perspective view of a half PC slab according to the first embodiment of the present invention.
4 is a cross-sectional view taken along the AA direction of FIG. 3.
5 is a longitudinal cross-sectional view of FIG.
6 is a longitudinal sectional view of a half PC slab according to a second embodiment of the present invention;
7 is a cross-sectional view of FIG. 6.
8 is a perspective view of the reinforcing member applied to FIG.
9 is a longitudinal sectional view of a half PC slab according to a third embodiment of the present invention.
10 is a cross sectional view of FIG. 9;
11 is a longitudinal sectional view of a half PC slab according to a fourth embodiment of the present invention.
12A to 12E are diagrams sequentially showing a manufacturing method for the automatic production of the half PC slab according to the first embodiment of the present invention.
FIG. 13 is a plan view of a plant for automated production shown in FIG. 12;
FIG. 14 is a front view of the installation for the automatic production shown in FIG. 12.
15 is a front view of a facility for automatic production according to another embodiment of a half PC slab of the present invention.
16 is a side view of a facility for automatic production according to another embodiment of a half PC slab of the present invention.
17 is a front view of FIG. 16.
18 is a perspective view of FIG. 16.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

다만, 본 발명을 설명함에 있어서, 공지된 기능 혹은 구성에 대해 구체적인 설명이 본 발명의 요지를 흩트리지 않도록 하기 위하여 생략하기로 한다. In the following description of the present invention, a detailed description of known functions and configurations will be omitted so as not to obscure the gist of the present invention.

도 3 내지 도 11을 참조하면, 본 발명의 일 실시예에 따른 하프 PC 슬래브(100)는 프리캐스트 공법에 의해 제조되는 프리캐스트 부재로, 거푸집에 타설되는 콘크리트로 이루어진 본체부(110) 및, 하프 PC 슬래브(100)와 현장 타설 슬래브의 결합시 전단력 보강을 위해 본체부(110)의 상측으로 돌출되도록 본체부(110)에 일체로 설치되는 보강부재(120)를 포함할 수 있다.3 to 11, the half PC slab 100 according to an embodiment of the present invention is a precast member manufactured by a precast method, the body portion 110 made of concrete cast in formwork, The half PC slab 100 may include a reinforcing member 120 integrally installed in the main body 110 so as to protrude upward of the main body 110 for reinforcement of shear force when the in situ slab is combined.

하프 PC 슬래브(100)의 본체부(110)는 요구되는 하프 PC 슬래브(100)의 구조에 따라 다양한 형상으로 형성될 수 있다. The main body 110 of the half PC slab 100 may be formed in various shapes according to the structure of the half PC slab 100 required.

바람직하게는 도 3 및 도 4에 도시된 바와 같이, 하프 PC 슬래브(100)는 본체부(110)가 평판부(112) 및 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 길게 평판부(112)에 수직 돌출 형성된 리브(rib)(114)를 포함하는 리브드 하프 PC 슬래브(ribbed half PC slab)로 이루어질 수 있다. 리브(114)는 하나의 하프 PC 슬래브(100)마다 하나만 형성될 수도 있고, 도시된 바와 같이 하프 PC 슬래브(100)의 폭방향(화살표 W)을 따라 상호 이격된 상태로 복수 형성될 수 있다.Preferably, as shown in FIGS. 3 and 4, the half PC slab 100 has a main body 110 that is flat along the longitudinal direction (arrow L) of the flat plate 112 and the half PC slab 100. It may be made of a ribbed half PC slab comprising ribs 114 protruding perpendicularly to the portion 112. Only one rib 114 may be formed for each half PC slab 100, and as illustrated, a plurality of ribs 114 may be formed to be spaced apart from each other along the width direction (arrow W) of the half PC slab 100.

또한, 도 7 및 도 10에 도시된 바와 같이, 하프 PC 슬래브(100)는 본체부(110)가 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 관통된 코어를 갖도록 형성된 할로우 코어 구조로 이루어질 수 있다. 코어는 하나의 하프 PC 슬래브(100)마다 하나만 형성될 수도 있고, 도시된 바와 같이 하프 PC 슬래브(100)의 폭방향(화살표 W)을 따라 상호 이격된 상태로 복수 형성될 수 있다.In addition, as shown in FIGS. 7 and 10, the half PC slab 100 has a hollow core structure in which the main body 110 has a core penetrated along the longitudinal direction (arrow L) of the half PC slab 100. It may be made of. Only one core may be formed for each half PC slab 100, or as shown in the figure, a plurality of cores may be formed to be spaced apart from each other along the width direction (arrow W) of the half PC slab 100.

보강부재(120)는 하프 PC 슬래브(100)와 현장 타설 슬래브의 전단 결합력을 높일 수 있는 소재라면 어떠한 것이든 무방하며, 예컨대 원형철근, 바, 와이어 로프, 강선 등으로 이루어질 수 있다.The reinforcing member 120 may be any material as long as it can increase the shear coupling force between the half PC slab 100 and the in-situ slab. For example, the reinforcing member 120 may be formed of a circular rebar, bar, wire rope, steel wire, or the like.

보강부재(120)는 하프 PC 슬래브(100)의 본체부(110) 제작시 하프 PC 슬래브(100)의 본체부(110)에 인서트(insert)되어 일체화되는 것으로, 하프 PC 슬래브(100)의 본체부(110)에 매립되도록 설치되는 매립 부분(122) 및, 하프 PC 슬래브(100)의 제조시 거푸집 내에서 상기의 매립 부분(122)과 일체로 이루어지며 하부로부터 상부로 연장되어 하프 PC 슬래브(100)의 본체부(110)의 상측으로 돌출되는 상부 부분(124)으로 이루어질 수 있다.The reinforcing member 120 is inserted into and integrated into the main body 110 of the half PC slab 100 when the main body 110 of the half PC slab 100 is manufactured. The main body of the half PC slab 100 is integrated. The buried portion 122 is installed to be embedded in the portion 110, and in the form of the half PC slab 100 is made integrally with the buried portion 122 in the formwork and extends from the bottom to the top half slab ( It may be made of an upper portion 124 protruding upward of the body portion 110 of the 100.

보강부재(120)의 상부 부분(124)은 특히 도시된 바와 같이 고리 형상을 갖도록 이루어질 수 있으며, 이에 따라 향후 하프 PC 슬래브(100)의 현장 설치시 하프 PC 슬래브(100)의 양중을 위한 고리로 사용하거나 현장 타설 슬래브의 현장 타설 작업시 현장 타설 슬래브의 철근 고정용 스페이서(spacer)로 사용되는 등 다양한 용도로 사용될 수 있다는 측면에서 유리할 수 있다.The upper portion 124 of the reinforcing member 120 may be made to have a ring shape, in particular as shown, so as a ring for the lifting of the half PC slab 100 in the future installation of the half PC slab 100 It may be advantageous in that it can be used for various purposes, such as used as a spacer for fixing the reinforcing bar of the site pour slab in the field pour operation of the site pour slab.

이와 같이 보강부재(120)의 상부 부분(124)이 고리 형상을 갖도록, 보강부재(120)는 하프 PC 슬래브(100)의 폭방향(화살표 W)(도 3 내지 도 8 참조) 또는 길이방향(화살표 L)(도 9 내지 도 11 참조)을 따라 '∩'으로 절곡된 형상의 본체부를 포함하도록 이루어질 수 있다. 즉, 보강부재(120)의 본체부는 보강부재(120)의 매립 부분(124) 중 연결부(123) 또는 절곡부(123')을 제외한 부분(121) 및 보강부재(120)의 상부 부분으로 이루어질 수 있다.As such, the reinforcing member 120 has a width direction (arrow W) (see FIGS. 3 to 8) or a lengthwise direction of the half PC slab 100 such that the upper portion 124 of the reinforcing member 120 has an annular shape. It may be made to include a body portion of the shape bent in '∩' along the arrow L) (see FIGS. 9 to 11). That is, the main body of the reinforcing member 120 is composed of a portion 121 of the buried portion 124 of the reinforcing member 120 except for the connecting portion 123 or the bent portion 123 'and the upper portion of the reinforcing member 120. Can be.

이러한 보강부재(120)는 하프 PC 슬래브(100)가 길이방향(화살표 L)으로 길도록 형성됨에 따라, 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 상호 이격 설치되는 복수의 본체부를 포함하도록 이루어질 수 있다. 아울러, 도 3 내지 도 5 및, 도 11에 도시된 바와 같이, 하나의 보강부재(120)를 이루는 복수의 본체부는 구조적으로 상호 분리된 상태로 설치될 수 있다. 이때, 도 3 내지 도 5에 도시된 바와 같이 본체부의 매립 부분(121)이 상하방향으로 수직한 일자형으로만 형성될 수도 있다. 또는 도 11에 도시된 바와 같이, 보강부재(120)는 상술한 바와 같이 본체부의 매립 부분(121)이 일자형으로 형성됨과 아울러, 거푸집에 타설된 콘크리트에 매립되며 하프 PC 슬래브(100)의 폭방향(화살표 W)을 따라 보강부재(120)의 본체부의 매립 부분(121)로부터 돌출되도록 보강부재(120)의 본체부의 매립 부분(121)과 일체로 형성되는 절곡부(123')를 더 포함할 수 있다. 보강부재(120)의 절곡부(123')는 도시된 바와 같이 보강부재(120)의 본체부의 매립 부분(121)의 하단으로부터 연장 형성될 수 있으며, 이에 따라 보강부재(120)가 하나의 라인으로 연결된 구조를 취할 수 있어, 하나의 라인을 벤딩(bending)하는 작업에 의해 용이하게 형성될 수 있다.As the reinforcing member 120 is formed such that the half PC slab 100 is long in the longitudinal direction (arrow L), a plurality of main body parts spaced apart from each other along the longitudinal direction (arrow L) of the half PC slab 100 is installed. It may be made to include. In addition, as shown in FIGS. 3 to 5 and 11, a plurality of body parts forming one reinforcing member 120 may be installed in a structurally separated state. In this case, as shown in FIGS. 3 to 5, the buried portion 121 of the main body may be formed only in a straight shape vertically in the vertical direction. Alternatively, as shown in FIG. 11, the reinforcing member 120 has a straight portion 121 of the main body portion formed as described above, and is embedded in concrete poured in formwork and is in the width direction of the half PC slab 100. Further comprising a bent portion 123 ′ integrally formed with the buried portion 121 of the main body portion of the reinforcing member 120 to protrude from the buried portion 121 of the main body portion of the reinforcing member 120 along the arrow (W). Can be. The bent portion 123 ′ of the reinforcement member 120 may be formed to extend from the lower end of the buried portion 121 of the main body portion of the reinforcement member 120, and thus the reinforcement member 120 may be formed in one line. The structure may be connected to each other, and may be easily formed by an operation of bending one line.

또는 도 6 내지 도 10에 도시된 바와 같이, 보강부재(120)는 구조적으로 상호 본체부의 매립 부분(121)과 본체부의 매립 부분(121) 사이에 거푸집에 타설된 콘크리트에 매립될 수 있도록 형성되는 연결부(123)를 통해 복수의 본체부가 일체화된 구조를 취할 수 있다. 이때, 보강부재(120)는 복수의 본체부 및 복수의 연결부가 하나의 라인으로 상호 연속적으로 연결되도록, 연결부(123)가 본체부의 매립 부분(121)의 하단으로부터 연장되도록 형성될 수 있다.6 to 10, the reinforcing member 120 is structurally formed to be embedded in the concrete placed in the formwork between the buried portion 121 and the buried portion 121 of the body portion mutually A plurality of body parts may be integrated through the connection part 123. At this time, the reinforcing member 120 may be formed such that the connecting portion 123 extends from the lower end of the buried portion 121 of the main body portion such that the plurality of main body portions and the plurality of connecting portions are continuously connected to each other in one line.

한편, 본 발명에 따른 하프 PC 슬래브(100)의 보강을 위해, 하프 PC 슬래브(100)의 본체부(110)에는 보강부재(120)보다 하측에 메쉬(mesh)(130), 보강철근(140) 등이 더 매립되도록 설치될 수 있다.On the other hand, for the reinforcement of the half PC slab 100 according to the present invention, the main body 110 of the half PC slab 100, the mesh (130), the reinforcement 140 in the lower side than the reinforcing member 120 ) May be installed to be further embedded.

상술한 바와 같은 본 발명에 따른 하프 PC 슬래브(100)는 도 12 내지 도 14에 도시된 바와 같이 다음과 같은 제조 방법에 의해 자동 생산 방식으로 제조될 수 있다. 참고로, 도 12 내지 도 14에 도시된 보강부재(120)는 도 3 내지 도 5에 도시된 바 제1실시 예에 따른 보강부재(120a)로 한정하여 도시한 것이다.As described above, the half PC slab 100 according to the present invention may be manufactured by an automatic production method by the following manufacturing method as shown in FIGS. 12 to 14. For reference, the reinforcing member 120 illustrated in FIGS. 12 to 14 is illustrated as being limited to the reinforcing member 120a according to the first embodiment as illustrated in FIGS. 3 to 5.

하프 PC 슬래브(100)의 제조를 위한 거푸집(200)은 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 연속적으로 자동 생산이 가능토록, 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 길게 제작될 수 있다. 즉, 하나의 거푸집(200)은 복수의 하프 PC 슬래브(100)를 길이방향(화살표 L)을 따라 연달아 설치한 것과 같은 길이를 갖도록 제작하여, 하나의 거푸집(200)에서 제조된 복수의 하프 PC 슬래브(100)를 잘라서 사용토록 할 수 있다.The formwork 200 for the production of the half PC slab 100 can be continuously produced automatically along the longitudinal direction (arrow L) of the half PC slab 100, the longitudinal direction of the half PC slab 100 (arrow L) It can be made long along). That is, one formwork 200 is manufactured so as to have the same length as a plurality of half PC slab 100 in succession along the longitudinal direction (arrow L), a plurality of half PCs manufactured in one formwork 200 The slab 100 can be cut and used.

이와 같이 거푸집(100)을 거푸집 지지를 위한 프레임 또는 바닥 등의 베이스(B)에 설치하여 준비되면, 먼저 도 12a에 도시된 바와 같이, 본 발명에 따른 하프 PC 슬래브(100)가 메쉬(130), 보강철근(140) 등을 포함하는 경우, 설치된 거푸집(200) 내에 메쉬(130), 보강철근(140) 등을 삽입하여 거치시킨다. 도 12a는 메쉬(130), 보강철근(140)를 거푸집(200) 내에 설치하고 있는 상태를 보여준다.When the formwork 100 is installed and prepared in the base B such as a frame or a bottom for supporting the formwork, as shown in FIG. 12A, the half PC slab 100 according to the present invention is mesh 130. In the case of including the reinforcing reinforcing bars 140, the mesh 130, the reinforcing bar 140, and the like are inserted into the formwork 200 installed thereon. 12A shows a state in which the mesh 130 and the reinforcing bar 140 are installed in the formwork 200.

다음, 도 12b, 12c에 도시된 바와 같이, 거푸집(200) 내에 보강부재(120)를 설치한다. 도 12b는 거푸집(200) 내에 보강부재(120)를 설치하는 상태를 보여주고, 도 12c는 거푸집(200) 내에 보강부재(120)가 설치 완료된 상태를 보여준다. 보강부재(120)는 그 상부 부분(124)이 보강부재(120)의 매립 부분(122)으로부터 상하방향에 대한 수평 방향으로 절곡된 상태로 제작되어 거푸집 내(200)에 설치되는 것을 특징으로 할 수 있다. Next, as shown in FIGS. 12B and 12C, the reinforcing member 120 is installed in the formwork 200. 12B shows a state in which the reinforcing member 120 is installed in the formwork 200, and FIG. 12C shows a state in which the reinforcing member 120 is installed in the formwork 200. Reinforcement member 120 is characterized in that the upper portion 124 is bent in the horizontal direction with respect to the vertical direction from the buried portion 122 of the reinforcement member 120 is installed in the formwork 200 Can be.

이러한, 보강부재(120)는 거푸집(200) 내에 선 거치된 메쉬(130), 보강철근(140) 등의 위에 용접, 결속선 등에 의해 고정될 수 있다. Such a reinforcing member 120 may be fixed by welding, a binding line, or the like on the mesh 130 pre-mounted in the formwork 200, the reinforcing bar 140, or the like.

다음, 도 12d에 도시된 바와 같이, 거푸집(200) 내에 콘크리트를 타설할 수 있는 콘크리트 타설장치(300)에 의해 거푸집(200)의 상측에서 거푸집(200) 내에 콘크리트를 타설한다. 다만, 보강부재(120)의 매립 부분(122)만 거푸집(200) 내에 타설되는 콘크리트에 매립되고 보강부재(120)의 수평 방향으로 절곡된 상부 부분(124)이 거푸집(200)에 타설된 콘크리트의 상면 상에 노출될 수 있도록, 콘크리트의 타설이 이루어지는 것이 바람직하다. 즉, 콘크리트 타설은 도시된 바와 같이 거푸집(200)에 타설된 콘크리트의 상면이 보강부재(120)의 절곡된 상부 부분(124) 아래에 닿도록 소정 높이, 즉 콘크리트 타설 제한 높이(H)까지 이루어질 수 있으며, 도시하지 않았지만 거푸집(200)에 타설된 콘크리트의 상면이 보강부재(120)의 절곡된 상부 부분(124)의 윗면을 넘지 않도록 콘크리트의 타설이 이루어질 수 있다.Next, as shown in FIG. 12d, the concrete is poured into the formwork 200 at the upper side of the formwork 200 by the concrete placing device 300 capable of placing concrete in the formwork 200. However, only the buried portion 122 of the reinforcing member 120 is embedded in the concrete poured in the formwork 200 and the upper portion 124 bent in the horizontal direction of the reinforcing member 120 is cast concrete in the formwork 200. In order to be exposed on the upper surface of the concrete, it is desirable to make the casting. That is, the concrete pouring is made up to a predetermined height, that is, the concrete placing limit height (H) so that the upper surface of the concrete poured in the formwork 200 to reach below the bent upper portion 124 of the reinforcing member 120 as shown Although not shown, concrete pouring may be performed so that the upper surface of the concrete poured into the formwork 200 does not exceed the upper surface of the bent upper portion 124 of the reinforcing member 120.

또한, 상술한 바와 같이 거푸집(200)이 상당히 길게 형성됨에 따라, 콘크리트 타설은 거푸집(200) 또는 콘크리트 타설장치(300)가 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 이동되면서 이루어질 수 있으며, 이에 따라 콘크리트 타설장치(300)를 거푸집(200)의 길이에 대응하여 길게 형성하지 않아도 되므로 보다 유리할 수 있다. 예컨대, 도시된 바와 같이, 거푸집(200)의 양 옆으로 콘크리트 타설장치(300)의 직선 이동을 안내하는 레일(330)이 설치될 수 있으며, 콘크리트 타설장치(300)는 레일(330)을 따라 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 직선 이동 가능토록 콘크리트 타설을 위한 호퍼(hopper)(312)가 설치된 본체부(310)에 바퀴(314)가 구비될 수 있다.In addition, as the formwork 200 is formed to be quite long as described above, the concrete placing is made while the formwork 200 or the concrete placing device 300 moves along the longitudinal direction (arrow L) of the half PC slab 100. In this case, the concrete placing apparatus 300 may be more advantageous because it does not have to be formed long corresponding to the length of the formwork 200. For example, as shown, the rail 330 may be installed to guide the linear movement of the concrete placing apparatus 300 to both sides of the formwork 200, the concrete pouring apparatus 300 is along the rail 330 Wheels 314 may be provided in the main body 310 in which a hopper 312 for placing concrete is installed so as to be linearly movable along the longitudinal direction (arrow L) of the half PC slab 100.

이와 아울러, 콘크리트 타설장치(300)는 거푸집(200) 내에 타설된 콘크리트를 다질 수 있도록, 콘크리트 타설장치(300) 또는 거푸집(200)이 이동할 때 거푸집(200) 내에 타설된 콘크리트의 상면에 밀착될 수 있도록 이루어진 타설 콘크리트 밀착부(320)를 더 포함할 수 있다. 타설 콘크리트 밀착부(320)는 바닥면이 상기한 콘크리트 타설 제한 높이(H)와 동일 선 상에서 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 직선 이동 가능토록, 콘크리트 타설장치(300)의 본체부(310)의 후방에 결합된 플레이트(plate)로 이루어질 수 있다. 이때, 보강부재(120)가 철근이나 강선 등으로 이루어짐에 따라 보강부재(120)의 절곡된 상부 부분(124)이 거푸집(120)에 타설된 콘크리트 상면으로부터 돌출된 두께를 무시할 수 있을 정도이기 때문에, 타설 콘크리트 밀착부(320)가 보강부재(120)의 절곡된 상부 부분(124)에 의해 방해받지 않고 거푸집(200) 내에 타설된 콘크리트의 상면에 밀착되면서 직선 이동될 수 있다. 하지만, 본 발명은 이에 한정되지 않고, 상기 보강부재(120)의 절곡된 상부 부분(124)이 상기 타설된 콘크리트 상면에 노출된 상태로 파묻혀서, 상기 상부 부분(124)과 상기 타설된 콘크리트 상면이 수평면을 이룰 수도 있다.In addition, the concrete pouring device 300 is to be in close contact with the upper surface of the concrete poured in the formwork 200 when the concrete placing device 300 or the formwork 200 to move the compacted concrete in the formwork (200) It may further include a pour concrete contact portion 320 made to be. The pour concrete contact portion 320 is a concrete pour device 300 so that the bottom surface can be moved linearly along the longitudinal direction (arrow L) of the half PC slab 100 on the same line as the above-described concrete placing limit height (H). It may be made of a plate (plate) coupled to the rear of the body portion 310 of the. At this time, as the reinforcing member 120 is made of reinforcing bars or steel wires, the bent upper portion 124 of the reinforcing member 120 is so large that the thickness projected from the upper surface of the concrete cast on the formwork 120 can be ignored. The pouring concrete contact portion 320 may be linearly moved while being in close contact with the upper surface of the concrete poured in the formwork 200 without being disturbed by the bent upper portion 124 of the reinforcing member 120. However, the present invention is not limited thereto, and the bent upper portion 124 of the reinforcing member 120 is buried in the exposed state of the poured concrete, so that the upper portion 124 and the poured concrete upper surface. This horizontal plane may be achieved.

또한, 타설 콘크리트 밀착부(320)는 진동기나 유압실린더 등에 의해 상하 방향으로 진동하도록 콘크리트 타설장치(300)의 본체부(310)에 설치되어, 상하방향으로 진동하면서 거푸집(200) 내에 타설된 콘크리트의 상면을 반복적으로 다지도록 이루어질 수 있다. In addition, the pour concrete contact portion 320 is installed on the main body 310 of the concrete placing device 300 to vibrate in the vertical direction by vibrator or hydraulic cylinder, etc., the concrete poured in the form 200 while vibrating in the vertical direction It can be made to repeatedly compact the upper surface of.

한편, 콘크리트 타설장치(300)는 거푸집(200)의 길이방향(화살표 L)을 따라 전진함과 아울러 전후방향 및 상하방향으로 진동하면서 거푸집(200) 내에 콘크리트를 타설토록 작동될 수 있으며, 이에 따라 거푸집(200) 내에 타설된 콘크리트의 다짐이 보다 견고하게 이루어질 수 있다. 콘크리트 타설장치(300)의 전후방향 진동을 위해, 콘크리트 타설장치(300) 자체가 레일(30)을 따라 전후 미동될 수도 있고, 진동기 등에 의해 타설 콘크리트 밀착부(320)만 전후방향으로 진동토록 설치될 수 있다. 여기서, 전후방향 진동을 위한 진동기 등은 많은 기술분야에서 많이 알려진 기술사항이며, 본 발명은 공지된 진동기에 의한 실시가 가능하므로, 진동기에 대한 보다 구체적인 설명은 생략한다.On the other hand, the concrete pouring device 300 can be operated to pour concrete in the formwork 200 while advancing along the longitudinal direction (arrow L) of the formwork 200 and vibrating in the front and rear and up and down directions, thereby Compaction of the concrete poured in the formwork 200 may be made more robust. For the front and rear direction vibration of the concrete placing apparatus 300, the concrete placing apparatus 300 itself may be moved back and forth along the rail 30, and only the concrete placing portion in contact with the concrete 320 is vibrated in the front and rear direction by a vibrator or the like. Can be. Here, the vibrator for the front and rear direction vibration is a technology known in many technical fields, the present invention can be carried out by a known vibrator, a detailed description of the vibrator is omitted.

다음, 도 12e에 도시된 바와 같이, 거푸집(200) 내에 타설된 콘크리트가 완전히 양생되기 전에 콘크리트 타설로부터 소정 시간이 흐른 후, 보강부재(300)의 절곡된 상부 부분(124)을 상측으로 수직하도록 펴서 하프 PC 슬래브(100)의 콘크리트로 이루어진 본체부의 상부로 돌출시킨다. 즉, 타설된 콘크리트가 완전히 굳어서 보강부재(120)의 절곡된 상부 부분(124)이 타설된 콘크리트의 상면에 붙어버리기 전에, 보강부재(120)의 절곡된 상부 부분(124)을 용이하게 펼칠 수 있다. 하지만, 본 발명은 이에 한정되지 않고, 상기 상부 부분(124)이 상기 콘크리트의 상면과 다소 간격이 존재한다면, 상기 타설된 콘크리트가 완전히 굳은 후에 상기 상부 부분(124)을 펼칠 수도 있다.Next, as shown in FIG. 12E, after a predetermined time has passed from the concrete pouring before the concrete poured in the formwork 200 is completely cured, the bent upper portion 124 of the reinforcing member 300 is vertically upward. Unfold and protrude to the top of the body portion made of concrete of the half PC slab 100. That is, before the cast concrete is completely hardened and the bent upper portion 124 of the reinforcing member 120 adheres to the upper surface of the poured concrete, the bent upper portion 124 of the reinforcing member 120 can be easily unfolded. have. However, the present invention is not limited thereto, and if the upper portion 124 is somewhat spaced from the upper surface of the concrete, the upper portion 124 may be unfolded after the poured concrete is completely hardened.

보강부재(120)의 상부 부분(124)을 펼친 후, 거푸집(200) 내에 타설된 콘크리트가 완전히 굳을 수 있도록 소정 시간이 더 흐르면, 본 발명에 따른 하프 PC 슬래브(100)가 제조될 수 있다.
After unfolding the upper portion 124 of the reinforcing member 120, if the predetermined time further flows to completely solidify the concrete poured in the formwork 200, the half PC slab 100 according to the present invention can be manufactured.

한편, 다른 실시 예로, 본 발명에 따른 하프 PC 슬래브(100)는 도 15에 도시된 바와 같이 다음과 같은 제조 방법에 의해 자동 생산 방식으로 제조될 수 있다.Meanwhile, in another embodiment, the half PC slab 100 according to the present invention may be manufactured by an automatic production method by the following manufacturing method as shown in FIG. 15.

도 12 내지 도 14를 참조하여 상술한 본 발명의 일 실시 예에 따른 하프 PC 슬래브(100)의 제조방법과 마찬가지로 프레임(210) 상에 설치된 거푸집(200) 내에 보강부재(120) 등을 설치한 후, 다음과 같이 콘크리트의 타설이 이루어질 수 있다.Like the manufacturing method of the half PC slab 100 according to an embodiment of the present invention described above with reference to FIGS. 12 to 14 in which the reinforcing member 120 or the like is installed in the formwork 200 installed on the frame 210. After that, the pouring of concrete can be made as follows.

즉, 콘크리트 타설장치(300)에 의해 거푸집(200)의 상측에서 거푸집(200) 내에 콘크리트를 타설하되 보강부재(120)의 절곡된 상부 부분이 거푸집(200)에 타설된 콘크리트의 상면 상에 노출되도록 함과 아울러, 프레임(210) 상의 거푸집(200)을 진동시키는 것을 특징으로 할 수 있으며, 이에 따라 거푸집(200) 내에 콘크리트가 균일하게 타설됨과 아울러 다져질 수 있다.That is, the concrete is poured into the formwork 200 from the upper side of the formwork 200 by the concrete pouring device 300, the bent upper portion of the reinforcing member 120 is exposed on the upper surface of the concrete poured into the formwork 200 In addition, it may be characterized by vibrating the formwork 200 on the frame 210, and thus can be compacted and concrete is poured in the formwork 200.

거푸집(200)의 진동은 다음과 같이 여러 가지로 실시될 수 있다.Vibration of the formwork 200 may be carried out in various ways as follows.

첫째, '화살표 A'로 도시된 바와 같이, 진동기 등에 의해 프레임(210)을 프레임 가이드용 레일(220)을 하프 PC 슬래브(100)의 길이방향 또는 폭방향을 따라 미동 가능토록 설치하여, 거푸집(200)이 프레임(210)과 함께 진동되도록 할 수 있다. 이 경우, 거푸집(200)은 프레임(210)에 의해 미동 가능한 용량으로 형성되며, 자동 생산을 위해 거푸집이 순차적으로 프레임 위에 안착, 분리되는 것이 반복 실시될 수 있다. First, as shown by the "arrow A", the frame 210 by vibrator or the like to install the frame guide rail 220 so as to be able to move along the longitudinal direction or the width direction of the half PC slab 100, formwork ( 200 may be vibrated with the frame 210. In this case, the formwork 200 is formed with a microcapacity capacity by the frame 210, and the formwork may be repeatedly mounted and separated on the frame sequentially for automatic production.

둘째, 콘크리트 타설장치(300)는 '화살표 B'로 도시된 바와 같이, 거푸집(200)에 타설된 콘크리트의 상측에서 거푸집(200)에 타설된 콘크리트를 상하방향으로 진동시키는 타설 콘크리트 진동부(340)를 포함할 수 있다. 타설 콘크리트 진동부(340)는 예컨대, 거푸집(200)에 타설된 콘크리트의 상측에서 거푸집(200)에 타설된 콘크리트의 상면에 밀착될 수 있도록 이루어진 진동판(342) 및, 진동판(342)을 상하방향으로 진동시킬 수 있도록 유압 실린더 기구 등에 의해 이루어진 진동판 구동부(344)를 포함할 수 있다. 이때, 도시된 바와 같이 콘크리트 타설장치(300)는 거푸집(200)의 상측에 고정되고, 거푸집(200)이 길이방향을 따라 직선 이동될 수 있다. 또는 도시하지 않았지만, 콘크리트 타설장치(300)는 거푸집(200)을 따라 직선 이동하면서 거푸집(200)을 진동시킬 수 있다.Second, the concrete pouring device 300 is pour concrete vibrating unit 340 to vibrate the concrete placed in the formwork 200 in the vertical direction from the upper side of the concrete placed in the formwork 200, 340 ) May be included. The pouring concrete vibrating unit 340, for example, the vibration plate 342 and the vibration plate 342 made to be in close contact with the upper surface of the concrete poured in the formwork 200 on the upper side of the concrete placed in the formwork 200, It may include a diaphragm drive unit 344 made by a hydraulic cylinder mechanism or the like to vibrate. At this time, as shown, the concrete placing apparatus 300 is fixed to the upper side of the formwork 200, the formwork 200 may be linearly moved along the longitudinal direction. Alternatively, although not shown, the concrete placing apparatus 300 may vibrate the formwork 200 while linearly moving along the formwork 200.

이외에도 거푸집(200)을 진동시킬 수 있다면 어떠한 것이든 적용될 수 있다.
In addition, any one can be applied if the formwork 200 can be vibrated.

또 다른 실시 예로, 본 발명에 따른 하프 PC 슬래브(100)는 도 16 내지 도 18에 도시된 바와 같이 다음과 같은 제조 방법에 의해 자동 생산 방식으로 제조될 수 있다.In another embodiment, the half PC slab 100 according to the present invention may be manufactured in an automatic production method by the following manufacturing method as shown in FIGS. 16 to 18.

즉, 도 3 내지 도 11을 참조하여 설명한 본 발명의 일 실시 예와 비교해보면, 하프 PC 슬래브(100)의 제조 현장의 바닥(B) 또는 프레임 위에 거푸집이 설치되는 대신 콘크리트 타설장치(300)에 하프 PC 슬래브(100)의 콘크리트 타설영역(C)을 형성하기 위한 거푸집 폼(350)이 일체로 구비된 것을 특징으로 할 수 있다. That is, compared to the embodiment of the present invention described with reference to Figures 3 to 11, instead of the formwork is installed on the floor (B) or the frame of the manufacturing site of the half PC slab 100 to the concrete pouring device 300 The formwork foam 350 for forming the concrete pouring area C of the half PC slab 100 may be integrally provided.

따라서, 건물 바닥 또는 바닥 패널로만 이루어진 프레임 위에 도 3 내지 도 11을 참조하여 설명한 본 발명의 일 실시 예와 동일하게 보강부재(120)들을 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 설치하고, 이와 같이 설치된 보강부재(120)들이 콘크리트 타설장치(300)의 거푸집 폼(350)에 의해 형성된 타설영역(C)에 위치되도록 콘크리트 타설장치(300) 또는 프레임을 길이방향(화살표 L)을 따라 직선 이동시키면, 도 3 내지 도 11을 참조하여 설명한 본 발명의 일 실시 예의 거푸집에 대응하는 가설작업이 이루어질 수 있다.Accordingly, the reinforcing members 120 are placed along the longitudinal direction (arrow L) of the half PC slab 100 in the same manner as the embodiment of the present invention described with reference to FIGS. And the reinforcing members 120 installed in this way are disposed in the concrete pouring apparatus 300 or the frame in the longitudinal direction (arrow L) such that the reinforcing members 120 are positioned in the pouring region C formed by the formwork foam 350 of the concrete pouring apparatus 300. If the linear movement along, the temporary work corresponding to the formwork of the embodiment of the present invention described with reference to Figures 3 to 11 can be made.

이후, 이렇게 가설된 타설영역(C)에 도 3 내지 도 11을 참조하여 설명한 본 발명의 일 실시 예와 동일하게 콘크리트를 타설하고, 보강부재(120)의 절곡된 상부 부분을 펼치면, 하프 PC 슬래브(100)가 제조될 수 있다.Subsequently, when the concrete is poured in the same place as the embodiment of the present invention described with reference to FIGS. 3 to 11, and the folded upper portion of the reinforcing member 120 is unfolded, the half PC slab is placed. 100 can be manufactured.

한편, 콘크리트 타설장치(300)의 거푸집 폼(350)은 하프 PC 슬래브(100)의 형상 등에 따라 구성될 수 있으며, 예컨대 도시된 바와 같이 기본적으로 하프 PC 슬래브(100)의 폭방향(화살표 W)을 따라 양쪽 측벽을 포함할 수 있으며, 하프 PC 슬래브(100)의 길이방향(화살표 L)을 따라 전/후 측벽 중 어느 하나 또는 양쪽을 더 포함할 수 있다. 콘크리트 타설장치(300)의 거푸집 폼(350)은 항상 위치 고정될 수도 있고, 하프 PC 슬래브(100)의 길이방향(화살표 L)이나 상하방향을 따라 이동 가능토록 설치될 수도 있다.On the other hand, the formwork foam 350 of the concrete pouring apparatus 300 may be configured according to the shape of the half PC slab 100, etc., for example, as shown in the width direction of the half PC slab 100 (arrow W) It may include both sidewalls, and may further include any one or both of the front and rear sidewalls along the longitudinal direction (arrow L) of the half PC slab 100. The formwork foam 350 of the concrete placing apparatus 300 may always be fixed in position, and may be installed to be movable along the longitudinal direction (arrow L) or the vertical direction of the half PC slab 100.

이상에서는 본 발명의 바람직한 실시예를 예시적으로 설명하였으나, 본 발명의 범위는 이와 같은 특정 실시예에만 한정되는 것은 아니며, 특허청구범위에 기재된 범주 내에서 적절하게 변경 가능한 것이다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the invention.

100; 하프 PC 슬래브 120; 보강부재
122; 매립 부분 124; 상부 부분
200; 거푸집 210; 프레임
300; 콘크리트 타설장치 312: 호퍼
320: 타설 콘크리트 밀착부 340; 타설 콘크리트 진동부
100; Half PC slab 120; Reinforcement member
122; Buried portion 124; Upper part
200; Formwork 210; frame
300; Concrete Pourer 312: Hopper
320: pour concrete contact portion 340; Pour concrete vibrator

Claims (15)

하프 PC 슬래브의 제조방법에 있어서,
바닥 또는 프레임 위에 하프 PC 슬래브의 전단력 보강을 위하여 상기 하프 PC 슬래브의 길이방향을 따라 보강부재들을 설치하되, 상기 보강부재는 하부로부터 상부로 연장되며 상부 부분이 수평 방향으로 절곡된 상태로 설치되는 보강부재 설치단계;
상기 프레임 또는 상기 하프 PC 슬래브의 거푸집 폼이 구비된 콘크리트 타설장치를 상기 길이방향을 따라 직선 이동시켜 상기 콘크리트 타설장치의 거푸집 폼에 의해 상기 보강부재가 위치된 하프 PC 슬래브의 콘크리트 타설영역을 형성하면서 상기 타설영역의 상측에서 상기 타설영역에 콘크리트를 타설하여, 상기 보강부재의 절곡된 상부 부분이 상기 타설된 콘크리트의 상면 상에 노출되도록 하되, 상기 절곡된 상부 부분이 상기 타설된 콘크리트의 상면에 밀착되거나 상기 타설된 콘크리트의 상면에 노출된 상태로 파묻히게 하는 콘크리트 타설 단계;
상기 콘크리트 타설로부터 소정 시간이 흐른 후, 상기 보강부재의 절곡된 상부 부분을 펴서 상기 하프 PC 슬래브의 콘크리트로 이루어진 본체부의 상부로 돌출시키는 보강부재 펼침단계를 포함하는 하프 PC 슬래브의 제조방법.
In the manufacturing method of the half PC slab,
Reinforcement members are installed along the longitudinal direction of the half PC slab to reinforce the shear force of the half PC slab on the floor or the frame, wherein the reinforcement member extends from the lower portion to the upper portion and is installed with the upper portion bent in the horizontal direction. Member installation step;
While the concrete placing device with the form foam of the frame or the half PC slab is moved linearly along the longitudinal direction to form the concrete placing area of the half PC slab where the reinforcing member is positioned by the form foam of the concrete placing device. Placing concrete in the pour area from the upper side of the pour area, so that the bent upper portion of the reinforcing member is exposed on the top surface of the poured concrete, wherein the bent upper portion is in close contact with the top surface of the poured concrete Or burying the concrete to be buried in an exposed state on the upper surface of the poured concrete;
After the predetermined time has passed from the concrete casting, the method of manufacturing a half PC slab comprising the step of unfolding the reinforcing member to extend the bent upper portion of the reinforcing member to protrude to the top of the body portion made of concrete of the half PC slab.
청구항 1에 있어서,
상기 콘크리트 타설장치는 상기 콘크리트 타설장치 또는 상기 프레임이 직선 이동할 때, 상기 타설된 콘크리트의 상면에 밀착될 수 있도록 이루어진 타설 콘크리트 밀착부를 포함하는 하프 PC 슬래브의 제조방법.
The method according to claim 1,
The concrete pouring device is a method of manufacturing a half PC slab comprising a pour concrete contact portion made to be in close contact with the upper surface of the pour concrete when the concrete pour device or the frame moves linearly.
하프 PC 슬래브의 제조방법에 있어서,
하프 PC 슬래브용 거푸집 내에 상기 하프 PC 슬래브의 전단력 보강을 위하여 보강부재를 설치하되, 상기 보강부재는 상기 거푸집 내에서 하부로부터 상부로 연장되며 상부 부분이 수평 방향으로 절곡된 상태로 설치되는 보강부재 설치단계;
상기 거푸집 또는 콘크리트 타설장치를 상기 거푸집의 길이방향을 따라 직선 이동시키면서 상기 콘크리트 타설장치에 의해 상기 거푸집의 상측에서 상기 거푸집 내에 콘크리트를 타설하여, 상기 보강부재의 절곡된 상부 부분이 상기 거푸집에 타설된 콘크리트의 상면 상에 노출되도록 하되, 상기 절곡된 상부 부분이 상기 타설된 콘크리트의 상면에 밀착되거나 상기 타설된 콘크리트의 상면에 노출된 상태로 파묻히게 하는 콘크리트 타설 단계;
상기 콘크리트 타설로부터 소정 시간이 흐른 후, 상기 보강부재의 절곡된 상부 부분을 펴서 상기 하프 PC 슬래브의 콘크리트로 이루어진 본체부의 상부로 돌출시키는 보강부재 펼침단계를 포함하는 하프 PC 슬래브의 제조방법.
In the manufacturing method of the half PC slab,
A reinforcing member is installed in the formwork for the half PC slab to reinforce the shear force of the half PC slab, wherein the reinforcing member extends from the bottom to the top in the formwork, and the reinforcing member is installed with the upper portion bent in the horizontal direction. step;
The concrete is poured into the formwork at the upper side of the formwork by the concrete placing apparatus while linearly moving the formwork or concrete placing apparatus along the longitudinal direction of the formwork, and the bent upper part of the reinforcing member is cast on the formwork. A concrete placing step of exposing on a top surface of concrete, wherein the bent upper portion adheres to the top surface of the poured concrete or is buried in an exposed state of the top surface of the poured concrete;
After the predetermined time has passed from the concrete casting, the method of manufacturing a half PC slab comprising the step of unfolding the reinforcing member to extend the bent upper portion of the reinforcing member to protrude to the top of the body portion made of concrete of the half PC slab.
청구항 3에 있어서,
상기 콘크리트 타설장치는 상기 콘크리트 타설장치 또는 상기 거푸집이 직선 이동할 때, 상기 타설된 콘크리트의 상면에 밀착될 수 있도록 이루어진 타설 콘크리트 밀착부를 포함하는 하프 PC 슬래브의 제조방법.
The method according to claim 3,
The concrete pouring device is a method of manufacturing a half PC slab comprising a pour concrete contact portion made to be in close contact with the upper surface of the pour concrete when the concrete pour device or the formwork moves linearly.
청구항 2 또는 청구항 4에 있어서,
상기 타설 콘크리트 밀착부는 상하 방향으로 진동하면서 상기 타설된 콘크리트의 상면을 반복적으로 다지는 하프 PC 슬래브의 제조방법.
The method according to claim 2 or 4,
The method of manufacturing a half-PC slab repeatedly compacting the upper surface of the poured concrete while vibrating in the vertical concrete contact portion.
청구항 1 내지 청구항 4 중 어느 한 항에 있어서,
상기 콘크리트 타설장치는 상기 길이방향을 따라 전진함과 아울러, 전후방향 및 상하방향 중 적어도 하나의 방향으로 진동하면서 상기 콘크리트를 타설토록 이루어진 하프 PC 슬래브의 제조방법.
The method according to any one of claims 1 to 4,
The concrete pouring device is a method of manufacturing a half PC slab made to pour the concrete while advancing along the longitudinal direction, vibrating in at least one of the front and rear and up and down directions.
하프 PC 슬래브의 제조방법에 있어서,
프레임 상에 설치된 상기 하프 PC 슬래브용 거푸집 내에 상기 하프 PC 슬래브의 전단력 보강을 위하여 보강부재를 설치하되, 상기 보강부재는 상기 거푸집 내에서 하부로부터 상부로 연장되며 상부 부분이 수평 방향으로 절곡된 상태로 설치되는 보강부재 설치단계;
콘크리트 타설장치에 의해 상기 거푸집의 상측에서 상기 거푸집 내에 콘크리트를 타설하여 상기 보강부재의 절곡된 상부 부분이 상기 거푸집에 타설된 콘크리트의 상면 상에 노출되도록 하되, 상기 절곡된 상부 부분이 상기 타설된 콘크리트의 상면에 밀착되거나 상기 타설된 콘크리트의 상면에 노출된 상태로 파묻히게 함과 동시에, 상기 거푸집을 진동시키는 콘크리트 타설 단계;
상기 콘크리트 타설로부터 소정 시간이 흐른 후, 상기 보강부재의 절곡된 상부 부분을 펴서 상기 하프 PC 슬래브의 콘크리트로 이루어진 본체부의 상부로 돌출시키는 보강부재 펼침단계를 포함하는 하프 PC 슬래브의 제조방법.
In the manufacturing method of the half PC slab,
A reinforcing member is installed in the formwork for the half PC slab on the frame to reinforce the shear force of the half PC slab, wherein the reinforcing member extends from the bottom to the top in the formwork, and the upper portion is bent in the horizontal direction. Reinforcing member installation step that is installed;
Placing concrete in the formwork from the upper side of the formwork by the concrete pouring device so that the bent upper portion of the reinforcing member is exposed on the upper surface of the concrete poured in the formwork, wherein the bent upper portion is A concrete pouring step of allowing the formwork to vibrate while being buried in close contact with the top surface of the poured concrete or in an exposed state;
After the predetermined time has passed from the concrete casting, the method of manufacturing a half PC slab comprising the step of unfolding the reinforcing member to extend the bent upper portion of the reinforcing member to protrude to the top of the body portion made of concrete of the half PC slab.
청구항 1 내지 청구항 4, 청구항 7 중 어느 한 항에 있어서,
상기 하프 PC 슬래브의 본체부는 평판부 및, 상기 하프 PC 슬래브의 길이방향을 따라 길게 상기 평판부에 수직 돌출 형성된 리브를 포함하는 하프 PC 슬래브의 제조방법.
The method according to any one of claims 1 to 4 and 7,
The body part of the half PC slab manufacturing method of the half PC slab comprising a flat plate, and ribs protruding perpendicularly to the flat plate in the longitudinal direction of the half PC slab.
청구항 1 내지 청구항 4, 청구항 7 중 어느 한 항에 있어서,
상기 하프 PC 슬래브의 본체부는 상기 하프 PC 슬래브의 길이방향을 따라 관통된 코어를 갖도록 형성된 하프 PC 슬래브의 제조방법.
The method according to any one of claims 1 to 4 and 7,
The body part of the half PC slab manufacturing method of the half PC slab formed to have a core penetrated along the longitudinal direction of the half PC slab.
청구항 1 내지 청구항 4, 청구항 7 중 어느 한 항에 있어서,
상기 보강부재는 상기 거푸집에 타설된 콘크리트의 상면 상에 노출되는 상부 부분이 고리 형상을 갖도록 이루어진 하프 PC 슬래브의 제조방법.
The method according to any one of claims 1 to 4 and 7,
The reinforcing member is a manufacturing method of the half PC slab made so that the upper portion exposed on the upper surface of the concrete poured in the form has a ring shape.
청구항 10에 있어서,
상기 보강부재는 상기 고리 형상을 갖도록 상기 하프 PC 슬래브의 폭방향 또는 길이방향을 따라 '∩'으로 절곡된 형상의 본체부를 포함하는 하프 PC 슬래브의 제조방법.
The method according to claim 10,
The reinforcing member is a half PC slab manufacturing method including a main body portion of the shape bent in the '∩' along the width direction or the longitudinal direction of the half PC slab to have the annular shape.
청구항 10에 있어서,
상기 보강부재는 상기 하프 PC 슬래브의 길이방향을 따라 상호 이격 설치되는 복수의 본체부를 포함하는 하프 PC 슬래브의 제조방법.
The method according to claim 10,
The reinforcing member is a half PC slab manufacturing method comprising a plurality of main body parts spaced apart from each other along the longitudinal direction of the half PC slab.
청구항 12에 있어서,
상기 보강부재는 상기 거푸집에 타설된 콘크리트에 매립되며 상기 하프 PC 슬래브의 폭방향을 따라 상기 보강부재의 본체부로부터 돌출되도록 상기 보강부재의 본체부와 일체로 형성되는 절곡부를 더 포함하는 하프 PC 슬래브의 제조방법.
The method of claim 12,
The reinforcing member further includes a bent part that is embedded in the concrete poured in the formwork and is formed integrally with the main body portion of the reinforcing member so as to protrude from the main body portion of the reinforcing member along the width direction of the half PC slab. Manufacturing method.
청구항 10에 있어서,
상기 보강부재는 상기 하프 PC 슬래브의 길이방향을 따라 상호 이격 설치되는 복수의 본체부 및, 상기 거푸집에 타설된 콘크리트에 매립될 수 있도록 형성되며 상기 본체부와 본체부 사이에 형성되어 일체로 연결하는 복수의 연결부를 포함하는 하프 PC 슬래브의 제조방법.
The method according to claim 10,
The reinforcing member is formed to be embedded in a plurality of body parts spaced apart from each other along the longitudinal direction of the half PC slab, and to be embedded in the concrete poured in the formwork and formed between the body portion and the body portion to connect integrally A method of manufacturing a half PC slab comprising a plurality of connections.
청구항 14에 있어서,
상기 보강부재는 상기 복수의 본체부 및 복수의 연결부가 하나의 라인으로 상호 연속적으로 연결되도록 이루어진 하프 PC 슬래브의 제조방법.
The method according to claim 14,
The reinforcing member is a method of manufacturing a half PC slab is formed so that the plurality of the main body portion and the plurality of connecting portions are continuously connected to each other in one line.
KR1020110107836A 2011-10-21 2011-10-21 Method for manufacturing half pc(precast concrete) slab KR101129275B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110107836A KR101129275B1 (en) 2011-10-21 2011-10-21 Method for manufacturing half pc(precast concrete) slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110107836A KR101129275B1 (en) 2011-10-21 2011-10-21 Method for manufacturing half pc(precast concrete) slab

Publications (1)

Publication Number Publication Date
KR101129275B1 true KR101129275B1 (en) 2012-03-26

Family

ID=46142657

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110107836A KR101129275B1 (en) 2011-10-21 2011-10-21 Method for manufacturing half pc(precast concrete) slab

Country Status (1)

Country Link
KR (1) KR101129275B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101675507B1 (en) * 2016-02-24 2016-11-14 주식회사 하이드로코리아 Buoyant body for marine buoyancy structure and the fabricating method therefor
KR101675487B1 (en) * 2016-02-24 2016-11-14 주식회사 하이드로코리아 Buoyant body construction method for marine buoyancy structure
KR102163959B1 (en) * 2020-02-06 2020-10-12 김종옥 H-beam precast concrete composite slab system with built-in section steel
KR102294467B1 (en) * 2021-07-15 2021-08-26 (주) 효성 Shear Connector for Coastal Structure and Coastal Structures using the Shear Connector

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0552023U (en) * 1991-12-13 1993-07-09 小野田エー・エル・シー株式会社 Mounting bracket for concrete panel
KR100495337B1 (en) 1996-12-04 2005-09-30 파텍 콘크리트 디벨럽먼트 오와이 Method and apparatus for casting concrete products
KR100666610B1 (en) 2005-06-08 2007-01-12 노영곤 Half slab having hollow membrance and the production method
KR20090050520A (en) * 2007-11-16 2009-05-20 (주)콘솔베르 Libbed half pc slab and manufacturing method of the same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0552023U (en) * 1991-12-13 1993-07-09 小野田エー・エル・シー株式会社 Mounting bracket for concrete panel
KR100495337B1 (en) 1996-12-04 2005-09-30 파텍 콘크리트 디벨럽먼트 오와이 Method and apparatus for casting concrete products
KR100666610B1 (en) 2005-06-08 2007-01-12 노영곤 Half slab having hollow membrance and the production method
KR20090050520A (en) * 2007-11-16 2009-05-20 (주)콘솔베르 Libbed half pc slab and manufacturing method of the same

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101675507B1 (en) * 2016-02-24 2016-11-14 주식회사 하이드로코리아 Buoyant body for marine buoyancy structure and the fabricating method therefor
KR101675487B1 (en) * 2016-02-24 2016-11-14 주식회사 하이드로코리아 Buoyant body construction method for marine buoyancy structure
KR102163959B1 (en) * 2020-02-06 2020-10-12 김종옥 H-beam precast concrete composite slab system with built-in section steel
KR102294467B1 (en) * 2021-07-15 2021-08-26 (주) 효성 Shear Connector for Coastal Structure and Coastal Structures using the Shear Connector

Similar Documents

Publication Publication Date Title
KR101556545B1 (en) Method for constructing using a double wall Precast Concrete
KR101379305B1 (en) Wall structure manufacturing method using precast front wall panel and precast back wall panel
KR101129275B1 (en) Method for manufacturing half pc(precast concrete) slab
KR20190042193A (en) Method for constructing wall structure using precast double wall
JP7134070B2 (en) Construction method of top slab of underground structure
KR101336034B1 (en) Method for manufacturing half PC(precasting concrete) slab
KR102059435B1 (en) Precast slab beam and rahmen structure construction method therewith
JP2000273939A (en) Culvert construction method
KR101748781B1 (en) Precast wall structure construction method
KR101880813B1 (en) A sandwitch pc pannel structure and construction method of structure using thereof
JP7081744B2 (en) Foundation beam structure and foundation beam construction method
JP2016079695A (en) Beam construction method, and precast plate for beam
JP5750246B2 (en) Composite beam, building, and composite beam construction method
JP5749620B2 (en) Seismic isolation method for existing buildings
JP2008014047A (en) Beam-column connection portion structure and method of constructing the same
KR102195671B1 (en) Construction method of concrete column using flexible sheet concrete form
KR101482523B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
JP5574338B2 (en) Site precast method for foundation beam
JP6418870B2 (en) How to build an elevator pit
JP2019218684A (en) Manufacturing method of culvert
JP7311456B2 (en) Construction method of underground structure
KR101827678B1 (en) Construction method of drainage structure
JP2020517844A (en) On-site cast top type pile foundation and its construction method
JP4319775B2 (en) Seismic reinforcement wall and its manufacturing method
JP3861017B2 (en) Column beam joint construction method

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150305

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160204

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee