JP3861017B2 - Column beam joint construction method - Google Patents

Column beam joint construction method Download PDF

Info

Publication number
JP3861017B2
JP3861017B2 JP2002068810A JP2002068810A JP3861017B2 JP 3861017 B2 JP3861017 B2 JP 3861017B2 JP 2002068810 A JP2002068810 A JP 2002068810A JP 2002068810 A JP2002068810 A JP 2002068810A JP 3861017 B2 JP3861017 B2 JP 3861017B2
Authority
JP
Japan
Prior art keywords
column
main
reinforcing bar
bars
precast concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002068810A
Other languages
Japanese (ja)
Other versions
JP2003268885A (en
Inventor
由美子 澤田
光陽 岩本
眞司 山岡
成美 松岡
唯治 仲地
Original Assignee
株式会社間組
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社間組 filed Critical 株式会社間組
Priority to JP2002068810A priority Critical patent/JP3861017B2/en
Publication of JP2003268885A publication Critical patent/JP2003268885A/en
Application granted granted Critical
Publication of JP3861017B2 publication Critical patent/JP3861017B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Description

【0001】
【発明が属する技術分野】
本発明は、プレキャストコンクリート部材による梁と、現場打ちコンクリートによる柱とを含む柱梁接合部の施工方法に関する。
【0002】
【従来の技術】
プレキャストコンクリート柱部材とプレキャストコンクリート梁部材とを用いて柱梁架構を構築する工法は従来から知られており、例えば、特開2000−336747号公報には、プレキャストコンクリート部材による柱梁接合部の施工方法が記載されている。この公報に記載された施工方法では、図6の立面図に示したように、下階側の柱部材1Aの上端にブラケット3を固定し、このブラケット3に取り付けた高さ調整材4の上に対向配置で梁部材2A,2Bを載せて支持しながら、梁主筋同士の接続作業を実施する。このとき、上階と下階の柱部材1A,1Bの主筋同士は、梁部材2A,2Bの下端主筋より下方位置で互いに接続するようになっており、上階側の柱部材1Bを落とし込むまでの間は、接合部に柱主筋が存在しない状態が作られるため、この接合部において梁主筋同士を接続したり、せん断補強筋の配筋作業を行うものである。
【0003】
【発明が解決しようとする課題】
しかしながら、上記従来の施工方法において、柱梁接合部でせん断補強筋の配筋作業や主筋の接続作業を行う場合には、ブラケット3や高さ調整材4の隙間を通して作業員が下方から手を入れて実施するか、あるいは梁部材2A,2Bの上から作業員が手を入れて実施する必要があるため、充分に作業性を向上させることができないという欠点がある。
【0004】
この欠点を解消するためには、柱梁接合部に充分な隙間を作るべく、下階側の柱部材1Aを短くして、そのコンクリート上端面を低くすることが考えられるが、この場合、柱梁接合部における型枠作業が増加し、現場打ちコンクリート量も増加するため、施工の効率化というプレキャスト化の趣旨に反するものになってしまうという新たな欠点が生じる。
【0005】
本発明は上記のような問題点を解決するためになされたものであり、その課題は、柱梁接合部における柱や梁の主筋同士の接続、せん断補強筋の配筋などの作業を効率的に行うことができる柱梁接合部の施工方法を提供することにある。
【0006】
【課題を解決するための手段】
本発明によれば、下端主筋及びあばら筋下部がコンクリート中に埋設され、下端主筋の両端部がコンクリートの端面から突出して製作されたプレキャストコンクリートの梁部材と、主筋及び帯筋を備えた柱用鉄筋組立体とを用いて柱梁接合部を構築する方法であって、下階側の前記柱用鉄筋組立体の上端に上下に移動可能な状態で所定数の帯筋を配置する工程と、該柱用鉄筋組立体の上方で前記梁部材を対向させて支保工で支持しながら、梁部材の上端主筋どうしと下端主筋どうしとをそれぞれ接続する工程と、前記両工程の後に上階側の柱用鉄筋組立体の主筋の下端部を下階側の柱用鉄筋組立体の上に落し込む工程と、前記上下動可能な状態の所定数の帯筋を上方に動かして前記梁部材の下端主筋よりも下方に作業空間を形成し、該作業空間において上下双方の柱主筋を互いに接続する工程とを含むことを特徴とする柱梁接合部の施工方法が提供される。
【0007】
本発明では、鉄筋組立体を用いて現場打ちコンクリートで柱を構築するようにしたので、この鉄筋組立体の上端では帯筋を主筋周りに環装し上下に移動可能な状態にしておくことが可能になり、必要に応じて帯筋を上下に移動することで、梁部材の下面と柱用鉄筋組立体の上端との間には充分な隙間を作り出すことができる。また本発明では、梁部材を支保工で支持するようにしたので、上記従来の施工法のようなブラケットや高さ調整部材などは設ける必要もなく、したがって、柱梁接合部には充分な作業スペースが確保できて、せん断補強筋の配筋や主筋の接続などの作業を効率的に行うことが可能である。
なお、本発明は、上記従来の施工方法のように柱を構築するためにプレキャストコンクリート部材を使用せず、鉄筋組立体、型枠および現場打ちコンクリートなどにより構築するものであるが、柱梁接合部における良好な作業性と、柱部材としてプレキャストコンクリート部材を使わないことによる材料コストの低減により、上記従来の施工方法と比べても、工期とコストの両面において遜色ないものである。
【0008】
本発明において、プレキャストコンクリート梁部材の配設予定位置を示す目印を下方の床スラブ上にあらかじめ設け、支保工には前記床スラブ上の目印に対応する目印をあらかじめ設けると共に前記プレキャストコンクリート梁部材を載置する際の配置を規定するガイド部材を設け、前記両目印を用いて前記支保工を位置決めした後に、該支保工の上に前記プレキャストコンクリート梁部材を載置して柱梁接合部方向に移動させる工程を含むように構成しても良い。
【0009】
【実施例】
以下、添付図面を参照して本発明の好適な実施形態を説明する。
【0010】
図1は本発明の柱梁接合部の施工方法における一工程を示す簡略図である。
本発明の施工方法は、図1に示すように、梁はプレキャストコンクリート部材10A,10B,10C、柱は鉄筋組立体20A,20Bを用いて柱梁接合部を構築するものである。すなわち、プレキャストコンクリートの梁部材10A,10B,10Cは、下端主筋12及びあばら筋下部13がコンクリート中に埋設され、下端主筋12の両端部がコンクリートの端面から突出して製作されたものであり、一方、柱用鉄筋組立体20A,20Bは、主筋21の上下端部を除いた外周に帯筋23が巻かれて固定されたものである。
【0011】
図1において、柱用鉄筋組立体20Aは、床スラブ41上に突出した部分のみが図示されているが、その下端部は既に下階側の柱に接続されて現場打ちコンクリート内に埋設されている。
床スラブ41上には、プレキャストコンクリート梁部材10A,10B,10Cの配設予定位置を示す目印として、あらかじめ墨出しを行う一方で、この床スラブ41上の目印に対応するように支保工33にもあらかじめ目印を設けておく。また支保工33は、プレキャストコンクリート梁部材10A,10B,10Cを載置する際の配置を規定するガイド部材34を備えたものを使用する。
最初に、床スラブ41上の目印に合せながら支保工33自体を位置決めし、次いで、クレーン等の揚重機を用いてガイド部材34に合わせながらプレキャストコンクリート梁部材10A10B,10Cを支保工33の上に吊り降ろし、その上端主筋11と下端主筋12の端部,が柱梁接合部の所定位置に配置されるように横方向に移動させる。そして、対向配置の上端主筋11どうしと、下端主筋12どうしとをカップラーやナットなどの結合部材15により結合する。
このとき、柱梁接合部には、プレキャストコンクリート梁部材10A,10B,10Cの上端主筋11と下端主筋12以外の部材は配置されておらず、しかも、柱用鉄筋組立体20A,20Bの主筋21,24の接合部は梁部材10A,10B,10Cの下面よりも下方に配置されるため、柱梁接合部に充分な作業スペースを確保することができる。したがって、上端主筋11、下端主筋12それぞれの結合作業は上方及び下方のいずれ側からも容易に行うことが可能になる。
なお、理解を容易にするため、図1から図4においては図示を省略したが、それぞれの接合部では必要に応じて、これらのプレキャストコンクリート梁部材10A,10B,10Cに直交する方向からも、上記と同様な工程で適宜梁部材を配設し、対向配置の主筋どうしを接合する。
【0012】
上記プレキャストコンクリート梁部材10A,10B,10Cの配設・結合工程の前後いずれか、あるいは同時に帯筋22の配設工程を行う。すなわち、柱用鉄筋組立体20Aの周りに複数のジャッキ31を配置し、柱用鉄筋組立体20Aの上端の帯筋23が設けられていない部分に支持部材32を設け、この支持部材32を下方からジャッキ31で支持し、複数の帯筋22を柱用鉄筋組立体20Aの主筋上端21から環装して支持部材32で支持するように配置する。これにより、他の鉄筋に接触しない限りにおいて、複数の帯筋22は上下動可能に配設されており、ジャッキ31を伸張すれば複数の帯筋22は上方へ移動させることができて、逆に、ジャッキ31を収縮すれば複数の帯筋22は下方へ移動させることができる。
【0013】
以上のプレキャストコンクリート梁部材の配設・結合工程と、帯筋の配設工程とが終了したら、上階側の柱用鉄筋組立体20Bをクレーン等の揚重機により柱梁接合部に吊り降ろし、上階側の柱用鉄筋組立体20Bの主筋24下端部を、下階側の柱用鉄筋組立体20Aの主筋21上端部に対向するように配置する。
ここで、上階側の柱用鉄筋組立体20Bの主筋24下端部には、図5に示したような被覆部材25をあらかじめ嵌めておく。この被覆部材25は、合成樹脂などの滑りの良い材料から形成されたものであり、下端25aは尖った形状に形成され、主筋24の螺子山に螺合するような係合部25bを備えている。したがって、上階側の柱用鉄筋組立体20Bを柱梁接合部に吊り降ろすときに、主筋24の下端部が他の鉄筋に接触したとしても、被覆部材25が摺動するため、上階側の柱用鉄筋組立体20Bはつかえることなく所定位置まで導かれる。
【0014】
上階側の柱用鉄筋組立体20Bを吊った状態で支持しながら、図3に示したように、ジャッキ31を伸張して複数の帯筋22を上方へ移動させる。これにより、支持部材32の下方、かつ下階側の柱用鉄筋組立体20Aの上端には、柱主筋21のみが存在するだけで帯筋22が無いスペースが生じる。このスペースを利用して作業を行い、上階側の柱用鉄筋組立体20Bの主筋24下端部と、下階側の柱用鉄筋組立体20Aの主筋21上端部とをカップラーやナットなどの結合部材26により接合する。
【0015】
柱主筋21,24の接合作業が終了したら、ジャッキ31と支持部材32を撤去し、帯筋22を柱用鉄筋組立体20A,20Bの主筋21,24の周りにワイヤー等により固定すると共に、柱梁接合部には他の帯筋やあばら筋などの補強筋を設ける。そして、図示はしないが、下階側の柱用鉄筋組立体20Aの周りや柱梁接合部に型枠を建て込んで、柱、梁及び柱梁接合部にコンクリートを打設し、この現場打ちコンクリートが硬化した後に型枠を脱型すれば、柱梁接合部の施工が終了する。
【0016】
【発明の効果】
本発明では、柱を鉄筋組立体と現場打ちコンクリートにより構築し、梁はプレキャストコンクリート部材を使用して柱梁接合部を構成し、鉄筋組立体の上端では帯筋を上下に移動可能な状態で主筋周りに環装し、必要に応じて帯筋を上下に移動することで、梁部材の下面と柱用鉄筋組立体の上端との間に充分な隙間を作り出し、この隙間を作業スペースとして柱主筋の接合作業を行うようにしたので、従来の施工法、すなわち、柱梁の両方をプレキャストコンクリート部材により構築する施工法と比較すると、主筋の接続やせん断補強筋の配筋などの作業を格段に効率良く行うことが可能になった。
【図面の簡単な説明】
【図1】本発明の柱梁接合部の施工方法における一工程を示す簡略図である。
【図2】図1の工程に続く工程を示す簡略図である。
【図3】図2の工程に続く工程を示す簡略図である。
【図4】図3の工程に続く工程を示す簡略図である。
【図5】柱用鉄筋組立体の主筋下端に嵌めた被覆部材の側面図である。
【図6】従来例を示す立面図である。
【符号の説明】
10A,10B,10C プレキャストコンクリートの梁部材
11 上端主筋
12 下端主筋
13 あばら筋
20A,20B 柱用鉄筋組立体
21,24 柱主筋
22 帯筋(移動可能な状態で配置した帯筋)
23 帯筋
[0001]
[Technical field to which the invention belongs]
The present invention relates to a method for constructing a column beam joint including a beam made of a precast concrete member and a column made of cast-in-place concrete.
[0002]
[Prior art]
A construction method for constructing a column beam frame using a precast concrete column member and a precast concrete beam member has been conventionally known. For example, Japanese Patent Laid-Open No. 2000-336747 discloses construction of a column beam joint portion using a precast concrete member. A method is described. In the construction method described in this publication, as shown in the elevation view of FIG. 6, the bracket 3 is fixed to the upper end of the column member 1A on the lower floor side, and the height adjusting member 4 attached to the bracket 3 is fixed. While the beam members 2A and 2B are placed and supported on the upper side, the beam main bars are connected to each other. At this time, the main bars of the upper and lower column members 1A and 1B are connected to each other at a position lower than the lower main bars of the beam members 2A and 2B until the upper column member 1B is dropped. During this period, a state where the column main bars do not exist in the joint portion is created. Therefore, the beam main bars are connected to each other at this joint portion, or the reinforcing bar reinforcement work is performed.
[0003]
[Problems to be solved by the invention]
However, in the above-described conventional construction method, when performing the reinforcement work of the shear reinforcement bars or the connection work of the main reinforcements at the beam-column joints, the worker manually moves from below through the gap between the bracket 3 and the height adjustment material 4. However, there is a drawback that the workability cannot be improved sufficiently because it is necessary to put the hand into the work from above the beam members 2A and 2B.
[0004]
In order to eliminate this drawback, it is conceivable to shorten the column member 1A on the lower floor side and lower the concrete upper end surface in order to make a sufficient gap in the beam-column joint. Formwork work at the beam joint increases and the amount of on-site concrete increases, resulting in a new drawback that goes against the purpose of precasting, which is the efficiency of construction.
[0005]
The present invention has been made in order to solve the above-mentioned problems, and the task is to efficiently perform operations such as connection between the main bars of the columns and beams at the beam-column joint, and arrangement of the shear reinforcement bars. It is in providing the construction method of the beam-column joint which can be performed to.
[0006]
[Means for Solving the Problems]
According to the present invention, a beam member of a precast concrete in which the lower end main bar and the lower part of the lower bar are embedded in the concrete and both ends of the lower main bar protrude from the end surface of the concrete, and the column including the main bar and the band bar. A method of constructing a column beam joint using a reinforcing bar assembly, the step of disposing a predetermined number of bars in a state of being vertically movable at the upper end of the column reinforcing bar assembly on the lower floor side; A process of connecting the upper and lower main bars of the beam member to each other on the upper floor side after both the processes, while supporting the beam members facing each other above the column reinforcing bar assembly and supporting them. A step of dropping a lower end portion of the main reinforcing bar of the column reinforcing bar assembly onto the column reinforcing bar assembly on the lower floor side, and moving a predetermined number of the reinforcing bars in a vertically movable state upward to move the lower end of the beam member A work space is formed below the main bar, and the work space is Construction method of Column Joints characterized by comprising a step of connecting together the pillar main reinforcement of the upper and lower both are provided in.
[0007]
In the present invention, since the column is constructed with the cast-in-place concrete using the reinforcing bar assembly, it is possible to wrap the strip around the main bar at the upper end of the reinforcing bar assembly so that it can move up and down. It becomes possible, and a sufficient gap can be created between the lower surface of the beam member and the upper end of the column rebar assembly by moving the band up and down as necessary. Further, in the present invention, since the beam member is supported by the support work, it is not necessary to provide a bracket or a height adjusting member as in the conventional construction method described above. Space can be secured, and work such as shear reinforcement reinforcement connection and main reinforcement connection can be performed efficiently.
The present invention does not use a precast concrete member for constructing a column as in the conventional construction method described above, but is constructed by a reinforcing bar assembly, formwork, cast-in-place concrete, etc. Due to the good workability in the part and the reduction of material cost by not using the precast concrete member as the column member, both the construction period and the cost are comparable as compared with the conventional construction method.
[0008]
In the present invention, a mark indicating the pre-positioned position of the precast concrete beam member is provided in advance on the lower floor slab, and a mark corresponding to the mark on the floor slab is provided in advance in the support work and the precast concrete beam member is provided in advance. After providing a guide member that regulates the arrangement when placing, and positioning the support using the marks, the precast concrete beam member is placed on the support in the direction of the column beam joint. You may comprise so that the process to move may be included.
[0009]
【Example】
DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, preferred embodiments of the invention will be described with reference to the accompanying drawings.
[0010]
FIG. 1 is a simplified diagram showing one step in the method of constructing a column beam joint of the present invention.
As shown in FIG. 1, the construction method of the present invention is to construct a beam-column joint using precast concrete members 10A, 10B, 10C for the beams and reinforcing bar assemblies 20A, 20B for the columns. That is, the beam members 10A, 10B, and 10C of precast concrete are manufactured by embedding the lower end main reinforcement 12 and the rib lower part 13 in the concrete and projecting both ends of the lower end main reinforcement 12 from the end surface of the concrete. The column reinforcing bars assemblies 20A and 20B are formed by winding the band 23 around the outer periphery excluding the upper and lower ends of the main reinforcing bar 21 and fixing it.
[0011]
In FIG. 1, only the portion of the column reinforcing bar assembly 20 </ b> A protruding on the floor slab 41 is illustrated, but the lower end portion thereof is already connected to the column on the lower floor side and embedded in the cast-in-place concrete. Yes.
On the floor slab 41, ink marks are preliminarily printed as marks indicating the pre-positioned positions of the precast concrete beam members 10A, 10B, 10C, while the support works 33 are arranged so as to correspond to the marks on the floor slab 41. Also have a mark in advance. Further, the support 33 is provided with a guide member 34 that defines the arrangement when the precast concrete beam members 10A, 10B, and 10C are placed.
First, the support work 33 itself is positioned while being aligned with the mark on the floor slab 41, and then the precast concrete beam members 10A10B and 10C are placed on the support work 33 while being adjusted to the guide member 34 using a lifting machine such as a crane. It is suspended and moved in the lateral direction so that the ends of the upper main bar 11 and the lower main bar 12 are arranged at predetermined positions of the beam-column joint. Then, the upper main bars 11 and the lower main bars 12 that are opposed to each other are coupled to each other by a coupling member 15 such as a coupler or a nut.
At this time, members other than the upper main bar 11 and the lower main bar 12 of the precast concrete beam members 10A, 10B, and 10C are not arranged at the column beam joint, and the main bar 21 of the column reinforcing bar assemblies 20A and 20B. , 24 are arranged below the lower surfaces of the beam members 10A, 10B, 10C, so that a sufficient working space can be secured in the column beam joint. Therefore, it is possible to easily perform the joining operation of the upper main bar 11 and the lower main bar 12 from either the upper side or the lower side.
In addition, although illustration was abbreviate | omitted in FIGS. 1-4 for easy understanding, also from the direction orthogonal to these precast concrete beam members 10A, 10B, and 10C as needed in each junction part, A beam member is appropriately disposed in the same process as described above, and the main bars facing each other are joined to each other.
[0012]
The pre-cast concrete beam members 10A, 10B, 10C are arranged before or after the arrangement / bonding step or simultaneously with the arrangement step of the band 22. That is, a plurality of jacks 31 are arranged around the column reinforcing bar assembly 20A, a support member 32 is provided in a portion where the upper end of the column reinforcing bar assembly 20A is not provided, and the support member 32 is moved downward. Are supported by a jack 31, and are arranged so as to be supported from the upper end 21 of the main reinforcement of the column reinforcing bar assembly 20A and supported by a support member 32. Thus, as long as it does not come into contact with other reinforcing bars, the plurality of rebars 22 are arranged so as to be movable up and down, and if the jack 31 is extended, the plurality of rebars 22 can be moved upward, In addition, if the jack 31 is contracted, the plurality of straps 22 can be moved downward.
[0013]
When the above-described precast concrete beam member arrangement / bonding step and the reinforcing bar arrangement step are finished, the upper-level column reinforcing bar assembly 20B is suspended from the beam-to-column joint by a lifting machine such as a crane, The lower bar lower end portion of the upper bar reinforcing bar assembly 20B is arranged so as to face the upper end of the main bar 21 of the lower bar reinforcing bar assembly 20A.
Here, a covering member 25 as shown in FIG. 5 is fitted in advance to the lower end portion of the main reinforcing bar 24 of the column reinforcing bar assembly 20B on the upper floor side. The covering member 25 is formed of a material having good sliding property such as a synthetic resin, and the lower end 25a is formed in a sharp shape, and includes an engaging portion 25b that engages with a thread of the main muscle 24. Yes. Accordingly, when the lower-layer column reinforcing bar assembly 20B is suspended from the beam-column joint, the covering member 25 slides even if the lower end of the main reinforcing bar 24 comes into contact with other reinforcing bars. The column reinforcing bar assembly 20B is guided to a predetermined position without being grasped.
[0014]
As shown in FIG. 3, the jack 31 is extended to move the plurality of reinforcing bars 22 upward while supporting the column reinforcing bar assembly 20 </ b> B on the upper floor side in a suspended state. As a result, there is a space in which only the column main reinforcement 21 exists and no band 22 exists at the upper end of the column reinforcing bar assembly 20A on the lower floor side below the support member 32. The work is performed using this space, and the lower end of the main bar 24 of the upper column side reinforcing bar assembly 20B and the upper end of the main bar 21 of the lower column side reinforcing bar assembly 20A are coupled with a coupler or a nut. The members 26 are joined.
[0015]
When the joining work of the column main bars 21 and 24 is finished, the jack 31 and the support member 32 are removed, and the band 22 is fixed around the main bars 21 and 24 of the column reinforcing bar assemblies 20A and 20B with wires or the like. Reinforcing bars such as other strips and stirrups are provided at the beam joint. Although not shown in the drawing, a formwork is built around the column reinforcing bar assembly 20A on the lower floor side or in the column beam joint, and concrete is placed in the column, beam, and column beam joint. If the mold is removed after the concrete has hardened, the construction of the beam-column joint is completed.
[0016]
【The invention's effect】
In the present invention, the column is constructed with a reinforcing bar assembly and cast-in-place concrete, the beam uses a precast concrete member to form a column beam joint, and at the upper end of the reinforcing bar assembly, the strip can be moved up and down. Enclose around the main bars and move the straps up and down as necessary to create a sufficient gap between the lower surface of the beam member and the upper end of the column rebar assembly. Since the main bars are joined, compared to the conventional construction method, that is, the construction method in which both column beams are constructed with precast concrete members, the work of connecting the main bars and the reinforcement of the shear reinforcement bars is markedly different. Can be performed efficiently.
[Brief description of the drawings]
FIG. 1 is a simplified diagram showing one step in a method for constructing a beam-column joint of the present invention.
FIG. 2 is a simplified diagram showing a step that follows the step of FIG.
3 is a simplified diagram showing a step that follows the step of FIG. 2. FIG.
4 is a simplified diagram showing a step that follows the step of FIG. 3. FIG.
FIG. 5 is a side view of the covering member fitted to the lower end of the main reinforcing bar of the column reinforcing bar assembly.
FIG. 6 is an elevational view showing a conventional example.
[Explanation of symbols]
10A, 10B, 10C Beam member 11 of precast concrete Upper main bar 12 Lower main bar 13 Stirrup bars 20A, 20B Reinforcing bar assemblies 21, 24 Column main bars 22 Band bars (band bars arranged in a movable state)
23 Belt muscle

Claims (3)

下端主筋及びあばら筋下部がコンクリート中に埋設され、下端主筋の両端部がコンクリートの端面から突出して製作されたプレキャストコンクリートの梁部材と、主筋及び帯筋を備えた柱用鉄筋組立体とを用いて柱梁接合部を構築する方法であって、下階側の前記柱用鉄筋組立体の上端に上下に移動可能な状態で所定数の帯筋を配置する工程と、該柱用鉄筋組立体の上方で前記梁部材を対向させて支保工で支持しながら、梁部材の上端主筋どうしと下端主筋どうしとをそれぞれ接続する工程と、前記両工程の後に上階側の柱用鉄筋組立体の主筋の下端部を下階側の柱用鉄筋組立体の上に落し込む工程と、前記上下動可能な状態の所定数の帯筋を上方に動かして前記梁部材の下端主筋よりも下方に作業空間を形成し、該作業空間において上下双方の柱主筋を互いに接続する工程とを含むことを特徴とする柱梁接合部の施工方法。Using a precast concrete beam member made by embedding the bottom main bar and the lower part of the lower bar in the concrete, with both ends of the lower main bar protruding from the end surface of the concrete, and a column rebar assembly with the main bar and strip A method of constructing a beam-to-column joint by disposing a predetermined number of bars in a state of being vertically movable at the upper end of the column reinforcing bar assembly on the lower floor side, and the column reinforcing bar assembly The upper and lower main bars of the beam member are connected to each other while the beam members are opposed to each other and supported by a supporting work, and the upper-stage column reinforcing bar assembly is connected after both the steps. The process of dropping the lower end of the main bar onto the lower column side bar rebar assembly, and moving the predetermined number of bars in the up and down movable state upward to work below the lower main bar of the beam member Forming a space, and Construction method of Column Joints characterized by comprising a step of connecting the pillar main reinforcement together. プレキャストコンクリート梁部材の配設予定位置を示す目印を下方の床スラブ上にあらかじめ設け、支保工には前記床スラブ上の目印に対応する目印をあらかじめ設けると共に前記プレキャストコンクリート梁部材を載置する際の配置を規定するガイド部材を設け、前記両目印を用いて前記支保工を位置決めした後に、該支保工の上に前記プレキャストコンクリート梁部材を載置して柱梁接合部方向に移動させる工程を含むことを特徴とする請求項1記載の柱梁接合部の施工方法。When the precast concrete beam member is preliminarily provided with a mark on the lower floor slab, a mark corresponding to the mark on the floor slab is preliminarily provided and the precast concrete beam member is placed. A step of providing a guide member for prescribing the arrangement, positioning the supporting work using the both marks, and placing the precast concrete beam member on the supporting work and moving it in the direction of the column beam joint portion. The method of constructing a beam-column joint according to claim 1, comprising: 前記柱用鉄筋組立体の主筋の下端部には、下階側の柱用鉄筋組立体の上に落し込む際に他の鉄筋に接触してつかえることを防止するための被覆部材を設けることを特徴とする請求項1または2に記載の柱梁接合部の施工方法。A covering member is provided at the lower end portion of the main reinforcing bar of the column reinforcing bar assembly to prevent it from coming into contact with other reinforcing bars when dropped onto the column reinforcing bar assembly on the lower floor side. The construction method of the beam-column joint part according to claim 1 or 2, characterized by the above-mentioned.
JP2002068810A 2002-03-13 2002-03-13 Column beam joint construction method Expired - Lifetime JP3861017B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002068810A JP3861017B2 (en) 2002-03-13 2002-03-13 Column beam joint construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002068810A JP3861017B2 (en) 2002-03-13 2002-03-13 Column beam joint construction method

Publications (2)

Publication Number Publication Date
JP2003268885A JP2003268885A (en) 2003-09-25
JP3861017B2 true JP3861017B2 (en) 2006-12-20

Family

ID=29199820

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002068810A Expired - Lifetime JP3861017B2 (en) 2002-03-13 2002-03-13 Column beam joint construction method

Country Status (1)

Country Link
JP (1) JP3861017B2 (en)

Also Published As

Publication number Publication date
JP2003268885A (en) 2003-09-25

Similar Documents

Publication Publication Date Title
KR101809687B1 (en) Joining Members of Steel Concrete Column and Steel Beam and Construction Method Thereof
JP5937898B2 (en) Construction method of box girder bridge
KR20100121866A (en) Pc slave for building having reinforcement structure as a set
JP2016098504A (en) Construction method for reinforced concrete structure, and reinforced concrete structure
EP2657423B1 (en) A concrete slab
KR101211332B1 (en) Connecting Structure between Pre-Stressed Concrete Girder and Precast Panel
KR101129275B1 (en) Method for manufacturing half pc(precast concrete) slab
JP3861017B2 (en) Column beam joint construction method
CN210597881U (en) Formwork-supporting-free decorative frame column and frame column beam system
JP4565331B2 (en) Floor structure
KR100403989B1 (en) Bridge slab construction method and precast concrete plate applied therein
KR20130081756A (en) Method for manufacturing half pc(precasting concrete) slab
JP2000273946A (en) Method for constructing reinforced concrete structure
CN111778856A (en) Construction method of main tower steel bar
JP7145717B2 (en) building construction method
KR20080020727A (en) Costruction die for steel reinforcing
CN211973976U (en) Vertical joint bar structure of cavity shear wall and connection structure thereof
KR960001240B1 (en) Half precast concrete slab
KR102409371B1 (en) Rib-type PC slab having welded wire mesh with upper end hook and method for manufacturing and construction of the rib-type PC slab
JP5973295B2 (en) Column head construction method
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
JP5461492B2 (en) Construction method of reinforced concrete frame structure
KR101827678B1 (en) Construction method of drainage structure
JP7281431B2 (en) Precast concrete member manufacturing method and precast concrete member
JP2700852B2 (en) Construction method of building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041228

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060905

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060925

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120929

Year of fee payment: 6