KR101119195B1 - Method for excavating submarine surface and constructing submarine vertical waterway - Google Patents

Method for excavating submarine surface and constructing submarine vertical waterway Download PDF

Info

Publication number
KR101119195B1
KR101119195B1 KR1020110122939A KR20110122939A KR101119195B1 KR 101119195 B1 KR101119195 B1 KR 101119195B1 KR 1020110122939 A KR1020110122939 A KR 1020110122939A KR 20110122939 A KR20110122939 A KR 20110122939A KR 101119195 B1 KR101119195 B1 KR 101119195B1
Authority
KR
South Korea
Prior art keywords
casing
excavation
construction method
inner casing
vertical sphere
Prior art date
Application number
KR1020110122939A
Other languages
Korean (ko)
Inventor
박호성
박정환
정재진
황진석
송재면
장현귀
Original Assignee
삼보이엔씨 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼보이엔씨 주식회사 filed Critical 삼보이엔씨 주식회사
Priority to KR1020110122939A priority Critical patent/KR101119195B1/en
Application granted granted Critical
Publication of KR101119195B1 publication Critical patent/KR101119195B1/en
Priority to PCT/KR2012/009704 priority patent/WO2013077595A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/12Underwater drilling
    • E21B7/136Underwater drilling from non-buoyant support
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/12Underwater drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/02Supports for the drilling machine, e.g. derricks or masts specially adapted for underwater drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

PURPOSE: A sea floor excavation and construction method is provided to prevent the subsidence of a casing due to excessive excavating load by connecting a support to the casing. CONSTITUTION: A sea floor excavation and construction method is as follows. A jack-up barge(10) is fixed to arrange a casing in a dredging side. A guide frame is established in one side of the jack-up barge. The casing is up pulled to arrange the casing on the dredging side using the guide frame. The underwater concreting is poured in the circumference of the casing. A subsidence preventive support supporting the upper side of 'the underwater concreting placed in the outer circumference of casing is established. The excavator is inserted into casing and the dredging side is out dug perpendicularly.

Description

해저 굴착 및 수직구 시공 방법{METHOD FOR EXCAVATING SUBMARINE SURFACE AND CONSTRUCTING SUBMARINE VERTICAL WATERWAY}Submarine excavation and vertical sphere construction method {METHOD FOR EXCAVATING SUBMARINE SURFACE AND CONSTRUCTING SUBMARINE VERTICAL WATERWAY}

본 발명은 해저 굴착 및 수직구 시공 방법에 관한 것으로서, 보다 상세하게는 산업시설용 냉각수의 심층 취수와 배수를 행하기 위해 해저를 굴착하고 수직구를 시공하는 방법에 관한 것이다.The present invention relates to a seabed excavation and vertical sphere construction method, and more particularly to a method for excavating the seabed and to construct a vertical sphere to perform deep intake and drainage of cooling water for industrial facilities.

일반적으로 산업시설은 공업용수를 많이 필요로 하며, 산업시설 중 특히 발전시설은 충분한 수자원의 확보를 위해 통상 임해지역에 건설된다.In general, industrial facilities require a lot of industrial water, and in particular, power generation facilities are usually constructed in coastal areas to secure sufficient water resources.

상기 발전시설의 일례로서 원자력 발전시설은, 우라늄의 핵분열 시 발생되는 열을 이용하여 증기 발생기의 물을 증기로 만들고, 그 증기의 힘으로 터빈을 가동시켜 전기를 발생시키기 위한 발전시설이다.As an example of the power generation facility, the nuclear power generation facility is a power generation facility for generating electricity by using steam generated by nuclear fission of uranium to make water in a steam generator and operating a turbine by the steam power.

상기 터빈의 가동에 이용되는 증기는 복수기에서 냉각되어 물로 만들어져 다시 증기발생기로 보내진다. 이때 사용되는 냉각수는 해수로서, 증기를 충분히 냉각시키고 난 후 온배수가 되어 해저 수직구를 통해 배출된다.The steam used to operate the turbine is cooled in the condenser, made of water, and sent back to the steam generator. At this time, the cooling water used is sea water, and after the steam is sufficiently cooled, the cooling water is discharged through the vertical hole of the sea bed.

그런데 온배수를 심층에서 배출하는 이유는 온배수가 해저면을 통해 방출되면 해수의 온도가 비교적 낮은 심층해수와 혼합되어 희석되기 때문에 표층해수의 온도 상승을 줄여 해양의 생태계 파괴를 최소화할 수 있기 때문이다.However, the reason why the warm drainage is discharged from the deep is that when the warm drainage is discharged through the sea floor, the temperature of the seawater is mixed with the deep seawater, which is relatively low.

이와 같이 심층 취/배수 시설은 원자력 발전소 외에 화력발전소나 제철소 및 일반 산업시설 등에 주로 적용되며, 등록특허공보 제10-0929482호에는 이러한 심층 취/배수를 위한 해상수직구 시공 방법이 개시되어 있다.As such, the deep intake / drainage facility is mainly applied to a thermal power plant, a steel mill, and a general industrial facility in addition to a nuclear power plant, and Patent Publication No. 10-0929482 discloses a method for constructing a marine vertical ball for deep intake / drainage.

그런데 이러한 시공 방법을 통하더라도, RCD(Reverse Circulation Drill) 공법과 같은 굴착 공법을 이용하여 해저면을 굴착하기 위해 설치된 케이싱이 굴착 작업이 진행되는 동안 점차 침하되는 문제점이 발생되고 있다.However, even through such a construction method, there is a problem that the casing installed to excavate the sea floor using an excavation method such as reverse circulation drill (RCD) method gradually sinks during the excavation work.

그리고 큰 규모의 해저 수직구를 시공하기 위해 큰 직경으로 해저면을 굴착할 때, 이러한 큰 직경의 해저면을 한번에 굴착하게 되면 굴착기에 과부하가 발생되어 굴착기 고장의 원인이 되는 문제가 있었다.And when excavating the seabed surface with a large diameter in order to construct a large seabed vertical sphere, the excavation of such a large diameter seabed at once, there is a problem that the excavator is overloaded, causing the excavator failure.

본 발명은 전술한 종래 기술의 문제점을 해결하기 위한 것으로서, 그 목적은 해저면 굴착을 위해 설치되는 케이싱의 침하를 방지할 수 있고, 해저면 굴착 시 과부하로 굴착기 고장이 발생되는 것을 방지할 수 있는 해저 굴착 및 수직구 시공 방법을 제공하고자 한다.The present invention is to solve the above-mentioned problems of the prior art, the purpose of which can prevent the settlement of the casing is installed for bottom drilling, it is possible to prevent the occurrence of excavator failure due to overload during the bottom drilling It is intended to provide a subsea excavation and vertical sphere construction method.

상기와 같은 목적을 달성하기 위한 본 발명에 의하면, a) 준설면에 케이싱이 배치될 수 있도록 잭업 바지(jack-up barge)를 고정 설치하는 단계; b) 상기 잭업 바지의 일측에 가이드 프레임을 설치하는 단계; c) 상기 케이싱을 인양하여 상기 가이드 프레임을 통해 상기 준설면에 상기 케이싱을 배치하는 단계; d) 상기 케이싱의 외주에 수중 콘크리트를 타설하는 단계; e) 상기 케이싱 외주면에 타설된 상기 수중 콘크리트의 상면을 지지하는 침하방지 지지대를 설치하는 단계; f) 상기 케이싱에 굴착기를 삽입하여 상기 준설면을 수직으로 굴착하는 단계; g) 이너케이싱을 제작하는 단계; h) 상기 케이싱에 상기 이너케이싱을 삽입하여 상기 준설면의 굴착된 부분에 설치하는 단계; 및 i) 상기 케이싱의 상기 수중 콘크리트의 상측으로 돌출된 부분을 절단 후 제거하는 단계를 포함하되, 상기 f) 단계는, f-1) 상기 케이싱의 내주보다 작은 직경으로 1차 굴착하는 단계; 및 f-2) 상기 케이싱의 내주에 대응되는 직경으로 2차 굴착하는 단계를 포함하는 해저 굴착 및 수직구 시공 방법을 제공한다.According to the present invention for achieving the above object, a) fixing the jack-up barge (jack-up barge) so that the casing can be disposed on the dredging surface; b) installing a guide frame on one side of the jack-up pants; c) lifting the casing and placing the casing on the dredging surface through the guide frame; d) placing underwater concrete on the outer periphery of the casing; e) installing a settlement preventing support for supporting the upper surface of the underwater concrete poured on the outer peripheral surface of the casing; f) inserting an excavator into the casing to excavate the dredge surface vertically; g) manufacturing the inner casing; h) inserting the inner casing into the casing and installing on the excavated portion of the dredging surface; And i) cutting and removing the protruding portion of the casing above the underwater concrete, wherein f) comprises: f-1) primary excavation with a diameter smaller than the inner circumference of the casing; And f-2) provides a subsea excavation and vertical sphere construction method comprising the step of secondary drilling to a diameter corresponding to the inner circumference of the casing.

본 발명은 해저면 굴착을 위해 설치되는 케이싱에 침하 방지 지지대를 연결하여 수중 콘크리트를 지지할 수 있어 케이싱의 침하를 방지할 수 있으며, 해저면 굴착을 다단계로 나누어 굴착기에 과부하가 발생되는 것을 방지하여 굴착기가 고장나는 것을 방지할 수 있는 해저 굴착 및 수직구 시공 방법을 제공할 수 있다.The present invention can support the submerged concrete by connecting the subsidence support to the casing is installed for the bottom surface excavation to prevent the settlement of the casing, by dividing the bottom surface excavation in multiple stages to prevent the overload occurs in the excavator It is possible to provide a subsea excavation and vertical sphere construction method that can prevent the excavator from failing.

도 1은 잭업 바지를 고정시키는 단계가 도시된 것이다.
도 2는 잭업 바지의 일측에 가이드 프레임을 설치하는 단계가 도시된 것이다.
도 3 내지 도 6은 케이싱이 인양되는 단계가 도시된 것이다.
도 7a 및 도 7b는 케이싱을 설치하는 단계가 도시된 것이다.
도 8은 사석을 쌓는 단계가 도시된 것이다.
도 9a 내지 도 10은 준설면을 굴착하는 단계가 도시된 것이다.
도 11a 및 도 11b는 이너케이싱이 제작되는 단계가 도시된 개략도이다.
도 12 내지 도 14는 이너케이싱이 인양되는 단계가 도시된 것이다.
도 15는 준설면의 굴착된 부분에 설치될 이너케이싱 및 일부 확대도가 도시된 것이다.
도16 및 도 17은 이너케이싱을 고정시키는 단계가 도시된 것이다.
도 18a 내지 도 18c는 사석을 준설하는 단계가 도시된 것이다.
도 19는 케이싱을 절단하여 제거하는 단계가 도시된 것이다.
Figure 1 shows the step of fixing the jack-up pants.
Figure 2 shows the step of installing the guide frame on one side of the jack-up pants.
3 to 6 show the step in which the casing is lifted.
7A and 7B show the steps of installing the casing.
8 illustrates the step of stacking the dead stone.
9A to 10 illustrate a step of digging a dredging surface.
11A and 11B are schematic diagrams showing the steps in which the inner casing is manufactured.
12 to 14 illustrate the steps in which the inner casing is lifted.
15 shows an inner casing and some enlarged views to be installed in the excavated portion of the dredging surface.
16 and 17 show the step of fixing the inner casing.
18A to 18C illustrate steps of dredging the dead stone.
19 shows the steps of cutting and removing the casing.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

명세서 전체에서, 어떤 부분이 다른 부분과 "연결"되어 있다고 할 때, 이는 "직접적으로 연결"되어 있는 경우뿐 아니라, 그 중간에 다른 소자를 사이에 두고 "전기적으로 연결"되어 있는 경우도 포함한다. 또한 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.Throughout the specification, when a part is "connected" to another part, this includes not only "directly connected" but also "electrically connected" with another element in between. . In addition, when a part is said to "include" a certain component, which means that it may further include other components, except to exclude other components unless otherwise stated.

본 발명에 따른 해저 굴착 및 수직구 시공 방법을 도면을 참조하여 시공 순서대로 설명하기로 하겠다.Subsea excavation and vertical sphere construction method according to the present invention will be described in the order of construction with reference to the drawings.

도 1은 잭업 바지(jack-up barge)를 고정시키는 단계가 도시된 것으로, 수직구 즉, 이너케이싱(90)를 형성할 해저면의 적정한 위치를 준설하여 준설면(1)을 형성하고, 준설면(1)에 케이싱(50)을 설치할 수 있도록 해상에는 잭업 바지 (10)를 위치시킨 후 준설면(1)과 연결하여 고정시킨다.1 shows a step of fixing a jack-up barge, and dredging the proper position of the sea bottom to form a vertical sphere, that is, the inner casing 90, to form a dredging surface 1, and dredging Position the jack-up pants 10 on the sea so that the casing 50 can be installed on the surface 1 and then fixed by connecting with the dredging surface 1.

한편, 상기 단계에서 형성되는 준설면(1)은 다양한 형태로 형성될 수 있는데, 예시적으로 본 발명의 실시예에서는 단면의 형상이 역 마름모 형태를 가지도록 형성된다. 이는 후술될 단계에서 설명될 케이싱(50)의 설치 및 수중 콘크리트(4)의 타설 시 편의성과 마무리 작업 시 안전성을 확보하기 위함이다.On the other hand, the dredging surface (1) formed in the step may be formed in various forms, for example, in the embodiment of the present invention is formed so that the shape of the cross section has an inverse rhombus shape. This is to ensure the convenience of the casing 50 to be described in the steps to be described later and the safety during finishing of the installation of the underwater concrete (4).

잭업 바지(10)는 해수면의 파고 또는 간만의 차에 영향받지 않고 정교한 시공을 할 수 있도록 설치하는 것으로, 본 발명의 실시예에서는 랙 앤 피니언 유압시스템에 의해 작동된다.The jack-up pants 10 are installed to allow precise construction without being affected by sea level digging or tidal difference. In the embodiment of the present invention, the jack-up pants 10 are operated by a rack and pinion hydraulic system.

도 2는 잭업 바지(10)의 일측에 가이드 프레임(30)을 설치하는 단계가 도시된 것으로, 잭업 바지(10)의 일측, 보다 정확하게는 케이싱(60)이 설치될 준설면(1)과 대향하는 위치에 가이드 프레임(30)이 설치된다. 예시적으로 본 발명의 실시예에서 가이드 프레임(30)은 도 2에 도시된 바와 같이 골조 형태로 형성되지만, 판상체로 형성되어도 무방하다.2 is a step of installing the guide frame 30 on one side of the jack-up pants 10, one side of the jack-up pants 10, more precisely facing the dredging surface (1) on which the casing 60 will be installed The guide frame 30 is installed at the position. For example, in the exemplary embodiment of the present invention, the guide frame 30 is formed in a frame shape as shown in FIG. 2, but may be formed in a plate-like body.

한편, 가이드 프레임(30)에는 케이싱(50)을 준설면(1)에 설치하기 위해 케이싱(50)을 지지할 수 있는 클램프(31)가 장착된다. 클램프(31)는 케이싱(50)의 상부에 고정되어 케이싱(50)을 인양한 후 케이싱(50)의 하부에 준설면(1)이 맞닿도록 이동시킬 수 있다.On the other hand, the guide frame 30 is mounted with a clamp 31 that can support the casing 50 to install the casing 50 on the dredging surface (1). The clamp 31 may be fixed to the upper portion of the casing 50 to lift the casing 50, and then move the dredging surface 1 to abut the lower portion of the casing 50.

도 3 내지 도 6은 케이싱(50)을 인양하는 단계가 순차적으로 도시되어 있다.3 to 6 show the steps of lifting the casing 50 sequentially.

도 3 내지 도 6을 참조하면, 먼저 플로팅 크레인(40)을 이용하여 케이싱(50)을 평바지(20)로 이동시킬 수 있는데, 이때 케이싱(50)은 도 3에 도시된 바와 같이 평바지(20)에 수평한 방향으로 평바지(20)에 배치될 수 있다. 그리고 케이싱(50)은 평바지(20)의 일측에 회전 가능하게 구비된 리프팅 프레임(21)에 케이싱(50)의 일부가 지지되도록 배치시킬 수 있다.3 to 6, first, the casing 50 may be moved to the flat pants 20 using the floating crane 40, wherein the casing 50 may be flat pants (as shown in FIG. 3). 20 may be disposed on the flat pants 20 in a horizontal direction. The casing 50 may be disposed to support a part of the casing 50 on the lifting frame 21 rotatably provided at one side of the flat pants 20.

케이싱(50)이 평바지(20)에 배치된 후에는 플로팅 크레인(40)의 후크부(60)를 케이싱(50)의 타측(평바지(20)의 리프팅 프레임(21)에 지지된 일측과 반대되는 측)에 연결시킬 수 있고, 이 때 평바지(20)와 플로팅 크레인(40)은 교차되게 배치될 수 있다. 평바지(20)와 플로팅 크레인(40)이 교차되게 배치되면, 도 3 내지 도 6에 도시된 바와 같이 플로팅 크레인(40)의 후크부(60)가 케이싱(50)의 일측을 수직으로 들어올리고 평바지(20)가 후진(케이싱(50)이 회전되는 방향의 반대 방향으로 이동)하면서 수평 방향으로 배치되어 있던 케이싱(50)을 수직 방향으로 회전시킬 수 있다.After the casing 50 is disposed on the flat pants 20, the hook portion 60 of the floating crane 40 is connected to the other side of the casing 50 (one side supported by the lifting frame 21 of the flat pants 20). On the opposite side), wherein the flat pants 20 and the floating crane 40 can be arranged to intersect. When the flat pants 20 and the floating crane 40 are arranged to cross each other, as shown in FIGS. 3 to 6, the hook portion 60 of the floating crane 40 lifts one side of the casing 50 vertically. The flat pants 20 can rotate the casing 50 arranged in the horizontal direction while moving backwards (moving in the opposite direction to the direction in which the casing 50 is rotated).

특히, 평바지(20)에 구비되어 있는 리프팅 프레임(21)은 케이싱(50)을 지지하고 있기 때문에 케이싱(50)의 일측이 플로팅 크레인(40)의 후크부(60)에 의해 수직으로 들어올려지면 케이싱(50)의 타측은 후크부(60)에 의해 들어올려지는 방향과 반대 방향으로 무게가 집중되므로 리프팅 프레임(21)이 회전되면서 케이싱(50)이 수평 방향에서 수직 방향으로 회전될 수 있게 도울 수 있다.In particular, since the lifting frame 21 provided in the flat pants 20 supports the casing 50, one side of the casing 50 is lifted vertically by the hook portion 60 of the floating crane 40. The other side of the ground casing 50 is concentrated in the direction opposite to the direction lifted by the hook portion 60, so that the casing 50 can be rotated from the horizontal direction to the vertical direction while the lifting frame 21 is rotated. Can help.

한편, 후크부(60)는 메인 후크(61)와 보조 후크(63)를 포함할 수 있는데, 메인 후크(61)는 후크 가이드 프레임(61a)을 통해서 케이싱(50)의 일측에 연결될 수 있고, 보조 후크(63)는 케이싱(50)의 외주면에 연결될 수 있다. 메인 후크(61)는 복수 개 구비될 수 있으며, 복수 개의 메인 후크(61)가 케이싱(50)의 둘레 방향을 따라 케이싱(50)의 일측에 연결될 수 있다. On the other hand, the hook portion 60 may include a main hook 61 and the auxiliary hook 63, the main hook 61 may be connected to one side of the casing 50 through the hook guide frame 61a, The auxiliary hook 63 may be connected to the outer circumferential surface of the casing 50. A plurality of main hooks 61 may be provided, and a plurality of main hooks 61 may be connected to one side of the casing 50 along the circumferential direction of the casing 50.

이 때 복수 개의 메인 후크(61)가 일정한 간격으로 케이싱(50)에 연결되지 않으면 케이싱(50)의 무게가 메인 후크(61)에 골고루 분산되어 전달되지 않고 각각의 메인 후크(61)에 서로 다르게 케이싱(50)의 무게가 전달될 수 있고, 메인 후크(61)에 케이싱(50)의 무게가 골고루 전달되지 않으면, 케이싱(50)을 들어올리기 위한 메인 후크(61)의 무게 중심이 흐트러져 케이싱(50)이 기울어지는 것과 같은 문제점이 있을 수 있다. At this time, if the plurality of main hooks 61 are not connected to the casing 50 at regular intervals, the weight of the casing 50 is distributed evenly to the main hooks 61 and is not transmitted to each main hook 61 differently. If the weight of the casing 50 can be transmitted, and if the weight of the casing 50 is not evenly transmitted to the main hook 61, the center of gravity of the main hook 61 for lifting the casing 50 is disturbed and the casing ( There may be a problem such as 50) tilting.

따라서 메인 후크(61)가 전술한 바와 같이 후크 가이드 프레임(61a)을 통해 케이싱(50)의 일측에 연결되면 복수 개의 메인 후크(61)는 일정한 간격으로 후크 가이드 프레임(61a)에 미리 연결되어 있으므로 케이싱(50)의 무게도 각각의 메인 후크(61)에 골고루 분산되어 전달될 수 있다.Therefore, when the main hook 61 is connected to one side of the casing 50 through the hook guide frame 61a as described above, the plurality of main hooks 61 are previously connected to the hook guide frame 61a at regular intervals. The weight of the casing 50 may be evenly distributed to each main hook 61.

보조 후크(63)도 메인 후크(61)와 마찬가지로 복수 개 구비될 수 있고, 보조 후크(63)는 전술한 바와 같이 케이싱(50)의 외주면에 연결될 수 있는데 보조 후크(63)는 작업자가 케이싱(50)의 외주면에 메인 후크(61)와 적당히 이격되게 연결시킬 수 있다. Like the main hook 61, a plurality of auxiliary hooks 63 may be provided, and the auxiliary hooks 63 may be connected to the outer circumferential surface of the casing 50 as described above. The outer circumferential surface of the 50 may be properly spaced apart from the main hook 61.

메인 후크(61)와 보조 후크(63)는 케이싱(50)이 수평 방향에서 수직 방향으로 회동될수록 케이싱(50)의 무게가 전달되는 비율이 변동될 수 있다. 즉, 케이싱(50)이 수평 방향에서 수직 방향으로 회동되기 시작할 때에는 보조 후크(63)가 케이싱(50)의 무게를 더 많이 전달받지만 케이싱(50)이 수평 방향에서 수직 방향으로 회동될수록 메인 후크(61)가 케이싱(50)의 무게를 더 많이 전달받을 수 있다.As the main hook 61 and the auxiliary hook 63 rotate the casing 50 from the horizontal direction to the vertical direction, the ratio of the weight of the casing 50 may be varied. That is, when the casing 50 starts to rotate in the vertical direction from the horizontal direction, the auxiliary hook 63 receives more weight of the casing 50, but as the casing 50 rotates in the vertical direction from the horizontal direction, the main hook ( 61 may receive more weight of the casing 50.

한편, 전술한 바와 같은 과정을 거쳐 인양된 케이싱(50)은 가이드 프레임(30)을 통과하여 준설면(1)에 배치될 수 있다.Meanwhile, the casing 50 lifted through the process as described above may be disposed on the dredging surface 1 through the guide frame 30.

케이싱(50)이 준설면(1)에 배치되면 도 7a에 도시된 바와 같이 클램프(31)가 케이싱(50)의 상부에 고정된 상태로 케이싱(50)을 지지하고, 케이싱(50)의 하부가 고정될 수 있는 높이까지 수중 콘크리트(4)를 타설한다.When the casing 50 is disposed on the dredging surface 1, as shown in FIG. 7A, the casing 50 is supported with the clamp 31 fixed to the upper portion of the casing 50, and the lower portion of the casing 50 is provided. Pour the underwater concrete (4) to a height where it can be fixed.

도 7b를 참조하여 보면, 케이싱(50)의 하부 외주면에는 둘레 방향으로 돌출된 스틸밴드(51)가 형성되어있다. 예시적으로 스틸밴드(51)는 케이싱(50)을 육상에서 제작할 때 형성하게 되는데, 케이싱(50) 하부에 형성된 스틸밴드(51)가 수중 콘크리트(4)와 부착됨으로써, 케이싱(50)의 침하가 효과적으로 방지될 수 있다.Referring to FIG. 7B, a steel band 51 protruding in the circumferential direction is formed on the lower outer circumferential surface of the casing 50. For example, the steel band 51 is formed when the casing 50 is manufactured on land. The steel band 51 formed below the casing 50 is attached to the underwater concrete 4, so that the casing 50 is settled. Can be effectively prevented.

수중 콘크리트(4)를 타설하여 케이싱(50)을 고정시킨 후에는 도 7b에 도시된 바와 같이 케이싱(50)의 외주면에 침하 방지 지지대(100)를 연결시킨다.After placing the underwater concrete 4 to fix the casing 50, the settlement preventing support 100 is connected to the outer circumferential surface of the casing 50 as shown in FIG. 7B.

침하 방지 지지대(100)는 케이싱(50)의 외주면에 장착된 연결부재(140)와, 연결부재(140)와 체결되어 케이싱(50)의 외측 방향으로 연장되는 지지부재(110)를 포함한다.The settlement prevention support 100 includes a connection member 140 mounted on an outer circumferential surface of the casing 50, and a support member 110 fastened to the connection member 140 and extending outward of the casing 50.

연결부재(140)는 케이싱(50)을 준설면(1)에 설치하기 전, 케이싱(50)을 육상에서 제작할 때 미리 장착시켜 둘 수 있거나, 케이싱(50)이 준설면(1)에 설치된 후 잠수부에 의해 장착될 수 있으며, 연결부재(140)는 예시적으로 볼트 체결 또는 용접에 의해 장착될 수 있다.The connecting member 140 may be pre-mounted when the casing 50 is manufactured on land before the casing 50 is installed on the dredging surface 1, or after the casing 50 is installed on the dredging surface 1. It can be mounted by a diver, the connecting member 140 may be mounted by bolt fastening or welding by way of example.

지지부재(110)는 케이싱(50)에 미리 설치할 수 있지만, 예시적으로 지지부재(110)가 "I" 빔 형상의 복수의 단위 부재로 이루어질 수 있다. 그리고 단위 부재를 별도의 연결부품(130), 예를 들면 경첩(판형 플레이트)과 같은 연결부품(130)과 볼트 체결에 의해 연결시킬 수 있다. 한편, 연결부품(130) 대신 연결부재(140)를 이용하여 단위 부재를 연결시킬 수도 있다.The support member 110 may be installed in advance in the casing 50, but for example, the support member 110 may be formed of a plurality of unit members having an “I” beam shape. In addition, the unit member may be connected to a separate connection part 130, for example, a connection part 130 such as a hinge (plate-shaped plate) by bolting. Meanwhile, the unit member may be connected using the connection member 140 instead of the connection component 130.

특히, "I" 빔은 시중에 판매되는 기성 제품이기 때문에 구하기 쉽고, "I" 빔 간의 볼트 체결 또한 용이하게 이루어질 수 있기 때문에 잠수부가 수중에서 단위 부재들을 연결시키는 작업 시 작업성을 높일 수 있으며, 보다 안정적이고 신속한 작업이 이루어지는 효과를 얻을 수 있다.In particular, since the "I" beam is a commercially available ready-made product, it is easy to obtain, and since bolting between the "I" beams can be easily performed, it is possible to increase workability when the diver connects the unit members underwater. More stable and faster work can be achieved.

예시적으로, 이러한 연결부재(140)와 지지부재(110)는 케이싱(50)을 준설면(1)에 설치한 후 잠수부가 해저로 잠수하여 볼트 체결을 함으로써 연결될 수 있다. 침하 방지 지지대(100)가 케이싱(50)이 준설면(1)에 놓이기 전부터 이미 설치되어 있으면, 케이싱(50)의 운반 시 외측 반경 방향으로 방사상으로 돌출되어 있는 침하 방지 지지대(100)로 인해 케이싱(50)의 운반이 지장이 생길 수 있고, 침하 방지 지지대(100)가 운반 시의 충격 등으로 인해 손상될 우려도 있다.For example, the connecting member 140 and the supporting member 110 may be connected by installing a casing 50 on the dredging surface 1 and then diving into the seabed to fasten the bolts. If the anti-seizure support 100 is already installed before the casing 50 is placed on the dredging surface 1, the casing 50 may be caused by the anti-sediment support 100 that protrudes radially in the outer radial direction when the casing 50 is transported. The transportation of the 50 may be disturbed, and the settlement preventing support 100 may be damaged due to an impact during transportation.

따라서, 케이싱(50)을 준설면(1)에 설치한 후 이와 같이 별도로 침하 방지 지지대(100)를 연결하는 작업을 함으로써, 케이싱(50)의 운반이 보다 용이해질 수 있고, 침하 방지 지지대(100)가 보다 안정적으로 설치될 수 있다.Therefore, after the casing 50 is installed on the dredging surface 1, the work of connecting the anti-sedimentation support 100 separately in this manner may facilitate the carrying of the casing 50, and the anti-seizure support 100 ) Can be installed more stably.

아울러, 케이싱(50) 하부 외주면에 형성된 스틸밴드(51)와 케이싱(50) 외주면에 침하 방지 지지대(100)가 유기적으로 조합됨으로써 케이싱(50)의 침하 방지를 더욱 효과적으로 방지할 수 있다. 즉, 스틸밴드(51)를 통해 수중 콘크리트(4)에 대한 케이싱(50)의 부착력을 더욱 향상시키고, 더불어 침하 방지 지지대(100)를 통해 수중 콘크리트(4) 상면을 지지함으로써 케이싱(50)의 침하를 방지시키는 효과가 크게 향상될 수 있다.In addition, the steel band 51 formed on the outer circumferential surface of the lower casing 50 and the anti-sink supporter 100 are organically combined on the outer circumferential surface of the casing 50 to prevent the subsidence of the casing 50 more effectively. That is, by further improving the adhesion of the casing 50 to the underwater concrete 4 through the steel band 51, and also by supporting the upper surface of the underwater concrete 4 through the anti-sedimentation support 100 of the casing 50 The effect of preventing settlement can be greatly improved.

준설면(1)에 케이싱(50)을 설치한 후 수중 콘크리트(4)를 타설한 후에는 도 8에 도시된 바와 같이 사석(5)을 쌓는 단계가 이루어진다. 수중 콘크리트(4)의 상측에 쌓이는 사석(5)은 케이싱(50) 중간 높이까지 해당하는 외주면에 접하여 케이싱(50)을 지지하는 역할을 하게 된다.After placing the casing 50 on the dredging surface 1 and pouring the underwater concrete 4, a step of stacking the sandstone 5 is performed as shown in FIG. 8. The sandstone 5 stacked on the upper side of the underwater concrete 4 serves to support the casing 50 in contact with the outer circumferential surface corresponding to the middle height of the casing 50.

사석(5)으로 케이싱(50)의 중간 높이까지 지지하게 되면, 케이싱(50)의 하부만 고정하여 지지할 때 보다 해수면의 파고 또는 간만의 차에 영향받아 케이싱(50)의 상부 측이 흔들리는 것을 방지할 수 있기 때문에 후술될 굴착 단계에서 굴착기(70, 70’)를 케이싱(50) 내부로 인입시키는 작업이 수월하게 진행될 수 있다.When it is supported to the middle height of the casing (50) by the sandstone (5), the upper side of the casing (50) is shaken under the influence of the sea wave digging or tidal difference than when only the lower portion of the casing (50) is fixed and supported Since it can be prevented in the excavation step to be described later, the operation of introducing the excavator (70, 70 ') into the casing 50 can be carried out easily.

도 9a 및 도 9b는 굴착기(70, 70’)가 케이싱(50)을 통해 준설면(1)을 수직으로 굴착하는 단계를 도시한 것으로, 굴착하는 단계는 크게 1차 굴착 단계와 2차 굴착 단계로 이루어진다.9A and 9B illustrate a step in which the excavators 70 and 70 'vertically excavate the dredging surface 1 through the casing 50, and the excavating step is mainly a first excavation step and a second excavation step. Is made of.

도 9a는 1차 굴착 단계가 도시된 것으로, 1차 굴착 단계는 케이싱(50)의 내주보다 작은 직경으로 굴착되는 굴착기(70)를 이용하여 굴착하는 것이고, 도 9b는 2차 굴착 단계가 도시된 것으로, 2차 굴착 단계는 케이싱(50)의 내주에 대응되는 직경으로 굴착되는 굴착기(70’)를 이용하여 굴착하는 것이다.FIG. 9A illustrates a first excavation step, in which the first excavation step is an excavation using an excavator 70 which is excavated to a diameter smaller than the inner circumference of the casing 50, and FIG. 9B is a second excavation step. In this case, the second excavation step is to excavate using an excavator 70 'which is excavated to a diameter corresponding to the inner circumference of the casing 50.

한편, 2차 굴착 단계에서 케이싱(50)의 내주에 대응된다는 것은 케이싱(50)의 내주로 2차 굴착 단계에 사용되는 굴착기(70’)를 인입하였을 때 굴착기(70’)의 외주면과 케이싱(50)의 내주면이 맞닿아 마찰이 발생되지 않을 정도로 케이싱(50)과 굴착기(70’)가 맞물림 되는 것을 의미할 수 있다.On the other hand, corresponding to the inner circumference of the casing 50 in the secondary excavation step, when the excavator 70 'used in the secondary excavation step is introduced into the inner circumference of the casing 50, the outer circumferential surface of the excavator 70' and the casing ( The inner circumferential surface of the 50 may contact with the casing 50 and the excavator 70 'such that friction does not occur.

준설면(1)을 굴착할 때 전술한 바와 같이, 1차 굴착 단계와 2차 굴착 단계로 나누어 진행하면 한번에 큰 직경을 굴착할 경우 굴착기에 과부하가 발생되는 것을 방지할 수 있다. 이에 따라 굴착기가 고장나거나 손상되는 것을 예방할 수 있어 큰 직경을 한번에 굴착하는 경우보다 오히려 신속하면서도 안정적인 굴착이 이루어질 수 있다.As described above, when digging the dredging surface (1), by dividing into the first and second excavation step it can be prevented from overloading the excavator when digging a large diameter at a time. Accordingly, the excavator can be prevented from being broken or damaged, so that a quick and stable excavation can be made rather than a case of digging a large diameter at a time.

굴착기(70, 70’)는 준설면(1)을 굴착하기 위해 준설면(1)과 맞닿는 하측면에 특수한 롤러비트(roller bit)가 형성되어 있어 이 롤러비트가 360˚ 회전으로 암반을 파쇄하고 파쇄된 굴착토는 드릴로드 파이프를 통해 배출되어 토사운반선에 수집된다. 그리고 굴착기(70, 70’)로 준설면을 굴착할 때에는 케이싱(50) 내부에 물을 채운 후 굴착을 하면 굴착되는 굴착토가 진흙과 같은 슬라임의 형태로 배출되게 할 수 있다.Excavators 70 and 70 'have a special roller bit formed on the lower side of the dredging surface 1 in contact with the dredging surface 1 to crush the rock with 360 ° rotation. The crushed excavated soil is discharged through the drill rod pipe and collected on the soil carrier. And when excavating the dredged surface with the excavator (70, 70 ') to fill the water in the casing 50 and excavation can be excavated excavated soil in the form of slime like mud.

한편, 준설면(1)을 굴착하는 단계에서 준설면(1)을 굴착하는 도중에 파쇄대(3)가 나오면 굴착을 잠시 멈추고, 도 10에 도시된 바와 같이 파쇄대 공벽 붕괴를 방지하기 위한 작업이 이루어질 수 있다.On the other hand, if the crushing stand 3 comes out during the excavation of the dredging surface 1 in the step of excavating the dredging surface 1, the excavation is stopped for a while, and the operation for preventing the collapse of the crushing wall can be made as shown in FIG. have.

파쇄대 공벽 붕괴 방지 작업은, 먼저 파쇄대(3)가 있는 위치에 수중 거푸집(81)을 만들어 설치하고 수중 거푸집(81)과 파쇄대(3) 사이로 수중 콘크리트(83)를 타설하여 진행한다.The crushing stand collapsing prevention work is performed by first making and installing the underwater formwork 81 at the position where the crushing stand 3 is located and placing the underwater concrete 83 between the underwater formwork 81 and the crushing stand 3.

이때, 수중 거푸집(81)은 굴착되는 직경보다 수중 거푸집(81)의 외주 직경이 더 작도록 만들어 설치하여야 전술한 바와 같이 수중 거푸집(81)과 파쇄대(3) 사이로 수중 콘크리트(83)를 타설할 수 있다.At this time, the underwater formwork 81 should be installed so that the outer peripheral diameter of the underwater formwork 81 is smaller than the diameter to be excavated to pour the underwater concrete 83 between the underwater formwork 81 and the crushing stand 3 as described above. Can be.

준설면(1)을 굴착하는 단계는 이너케이싱(90)을 굴착된 부분에 인입시키기 위해 진행되는 것으로, 굴착되는 깊이는 이너케이싱(90)의 높이보다 짧도록 굴착한다.Excavating the dredging surface 1 is carried out to pull the inner casing 90 into the excavated portion, the excavation depth is excavated to be shorter than the height of the inner casing (90).

굴착이 완료된 후에는 전술한 바와 같이 준설면(1)의 굴착된 부분에 이너케이싱(90)을 설치하는 단계가 이루어진다. 굴착된 부분에 설치되는 이너케이싱(90)은 육상에서 미리 제작(precast)된 후 인양되어 설치 된다.After the excavation is completed, as described above, the step of installing the inner casing 90 on the excavated portion of the dredging surface 1 is performed. The inner casing 90 installed in the excavated portion is pre-manufactured on land and then lifted and installed.

도 11a및 도 11b는 이너케이싱(90)이 제작되는 단계가 개략적으로 도시된 개략도이다. 이너케이싱(90)은 강관을 인양하여 제작장에 세워 배치시킨 후 강관이 전도되는 것을 방지하기 위해 강관의 내부에 물을 충진시킬 수 있다. 11A and 11B are schematic diagrams schematically showing the steps in which the inner casing 90 is manufactured. The inner casing 90 may fill the inside of the steel pipe to prevent the steel pipe from falling after lifting the steel pipe and placing the steel pipe upright.

강관(90’)의 내부에 물을 충진시킨 후에는 단계적으로 강관(90’)의 외주에 철근 콘크리트를 타설하는데, 먼저 강관(90’)의 외주 둘레에 동바리 및 비계를 설치하고 철근을 조립한다. 그리고 그 둘레에 거푸집을 설치한 후 강관(90’)의 외주 및 거푸집 사이에 콘크리트를 타설한다. 그 후 거푸집을 해체하고 콘크리트를 양생시킨다.After filling the water inside the steel pipe 90 ', reinforcement concrete is poured on the outer circumference of the steel pipe 90', first, a copper bar and a scaffold are installed around the outer circumference of the steel pipe 90 ', and the reinforcing bars are assembled. . And after installing the formwork around it, the concrete is poured between the outer periphery and formwork of the steel pipe (90 '). After that, the formwork is dismantled and the concrete is cured.

전술한 강관(90’)의 외주에 철근 콘크리트를 타설하는 단계는 강관을 층별로 구획하여 반복적인 공정으로 이루어질 수 있다. 이를테면, 본 발명의 실시예에서는 단계적으로 콘크리트를 타설하는 단계가 도 11b에 도시된 바와 같이 1단부터 5단까지 진행됨에 따라 이루어질 수 있다.The step of pouring reinforced concrete on the outer circumference of the above-described steel pipe (90 ') may be made of a repetitive process by dividing the steel pipe by layers. For example, in the embodiment of the present invention, the step of pouring concrete step by step may be made as it proceeds from 1 to 5 steps as shown in Figure 11b.

이렇게 강관(90’)의 외주에 철근 콘크리트를 단계적으로 타설하면서 프리캐스트 라이닝을 형성하는 이너케이싱(90)을 제작할 수 있다. 여기서, 프리캐스트 라이닝은 철근 콘크리트를 프리캐스팅하여 상측에서 보았을 때, 원형의 라이닝(Lining)이 형성되도록 이너케이싱(90)을 제작하는 것을 말한다.Thus, the inner casing 90 to form the precast lining while pouring reinforced concrete on the outer circumference of the steel pipe (90 ') can be manufactured. Here, the precast lining refers to manufacturing the inner casing 90 so that a circular lining is formed when the cast concrete is precast and viewed from above.

한편, 이너케이싱(90)이 제작된 후 이너케이싱(90)을 준설면(1)의 굴착된 부분에 인입하기 위한 이너케이싱(90)의 인양 단계가 도 12 내지 도 14에 도시되어 있다.이너케이싱(90)이 인양되는 단계는, 전술에서 케이싱(50)을 설치하기 위해 케이싱(50)을 인양하는 단계와 동일하므로 이에 대한 설명은 생략하기로 한다.Meanwhile, a lifting step of the inner casing 90 for pulling the inner casing 90 into the excavated portion of the dredging surface 1 after the inner casing 90 is manufactured is shown in FIGS. 12 to 14. Since the step of lifting the casing 90 is the same as the step of lifting the casing 50 to install the casing 50 in the above description, a description thereof will be omitted.

한편, 도 15를 참조하면 알 수 있듯이, 이너케이싱(90)의 둘레면 하부에는 배수 밸브(91)가 구비될 수 있고, 이너케이싱(90)의 하측에는 바닥판(92)이 구비될 수 있으며, 바닥판(92)에는 통수 밸브(95)가 구비될 수 있다. 이너케이싱(90)의 둘레면 하부에 배수 밸브(91)가 구비됨으로써 이너케이싱(90) 제작 단계에서 내부에 충진되었던 물을 배수할 때 배수 밸브(91)에 배수 파이프를 연결하여 배수할 수 있다.On the other hand, as can be seen with reference to Figure 15, the lower surface of the inner casing 90 may be provided with a drain valve 91, the lower side of the inner casing 90 may be provided with a bottom plate 92 The bottom plate 92 may be provided with a water flow valve 95. Since the drain valve 91 is provided under the peripheral surface of the inner casing 90, the drain pipe 91 may be connected to the drain valve 91 to drain water when the water filled in the inner casing 90 manufacturing step is drained. .

이너케이싱(90)의 내부에 충진되었던 물은 이너케이싱(90)이 제작된 직후 배수하지 않고, 이너케이싱(90)을 설치하기 바로 전에 배수한다. 그 이유는, 제작된 이너케이싱(90)의 내부에 물을 채우지 않고 그냥 세워두면 풍하중 등으로 인해 이너케이싱(90)이 흔들리거나 넘어지는 등의 전도가 발생할 수 있게 된다. 즉, 이러한 진동이나 움직임을 방지하기 위해 육상에서 대기 중일 때는 이너케이싱(90)의 내부에 물을 채워두어야 한다.The water filled in the inner casing 90 is not drained immediately after the inner casing 90 is manufactured, but immediately before the inner casing 90 is installed. The reason is that if the air casing 90 is left without filling the inner casing 90, the inner casing 90 may be shaken or fallen due to wind load or the like. That is, in order to prevent such vibrations or movements, the interior of the inner casing 90 should be filled with water when standing on land.

따라서 전술한 바와 같이 이너케이싱(90)의 하부에 구비된 배수 밸브(91)는 이너케이싱(90)을 준설면(1)의 굴착된 부분에 인입하기 위해 인양될 때 이너케이싱(90)의 내부에 채워진 물을 배수할 때 사용될 수 있다.Therefore, as described above, when the drain valve 91 provided at the lower portion of the inner casing 90 is lifted to pull the inner casing 90 into the excavated portion of the dredging surface 1, the interior of the inner casing 90 is removed. It can be used to drain the water filled in.

준설면(1)의 굴착된 부분에 이너케이싱(90)을 인입할 때에는 이너케이싱(90)이 해저에 소정 깊이까지 들어간 상태에서 이너케이싱(90)의 내부에 물을 채울 수 있다. 이렇게 이너케이싱(90)의 내부에 물을 채운 후, 이너케이싱(90)을 굴착된 부분에 인입을 완료시키면 이너케이싱(90)은 하부 본선 터널과 연결이 되고, 이너케이싱(90)의 하측에 구비된 바닥판(92)을 제거할 수 있다. 이 때 바닥판(92)을 제거하기 전에 바닥판(92)에 구비된 통수 밸브(95)를 이용하여 이너케이싱(90)의 내부에 채워진 물을 통수시키고 바닥판(92)를 제거할 수 있다.When the inner casing 90 is introduced into the excavated portion of the dredging surface 1, water may be filled in the inner casing 90 while the inner casing 90 enters the sea bottom to a predetermined depth. In this way, after filling the inner casing 90 with water, when the inner casing 90 is completed, the inner casing 90 is connected to the lower main line tunnel, and the inner casing 90 is connected to the lower main tunnel. The provided bottom plate 92 can be removed. At this time, before the bottom plate 92 is removed, the water filled in the inner casing 90 may be passed through the water flow valve 95 provided in the bottom plate 92 and the bottom plate 92 may be removed. .

또한, 도 15에 도시된 바와 같이 이너케이싱(90)의 하부에는 이너케이싱(90)의 둘레 방향을 따라 복수 개의 저면 가이드(93)가 더 구비될 수 있다. 저면 가이드(93)는 이너케이싱(90)을 케이싱(50)의 내부로 인입시킬 때 이너케이싱(90)이 수월하게 인입될 수 있도록 이너케이싱(90)의 인입 위치를 가이드 해주는 역할을 한다.In addition, as shown in FIG. 15, a plurality of bottom guides 93 may be further provided below the inner casing 90 along the circumferential direction of the inner casing 90. The bottom guide 93 serves to guide the inlet position of the inner casing 90 so that the inner casing 90 can be easily inserted when the inner casing 90 is introduced into the casing 50.

따라서 도 15에 도시된 바와 같이 저면 가이드(93)는 이너케이싱(90)의 하측 단부와 접하는 시작점에서 하측 방향으로 갈수록 이너케이싱(90)의 내부 방향으로 경사지도록 구비될 수 있다.Therefore, as shown in FIG. 15, the bottom guide 93 may be provided to be inclined in the inner direction of the inner casing 90 toward the lower direction from the starting point of contact with the lower end of the inner casing 90.

이너케이싱(90)을 준설면(1)의 굴착된 부분에 인입시킨 후에는 도 16에 도시된 바와 같이, 이너케이싱(90)과 케이싱(50) 사이로 몰탈(80)을 주입하여 이너케이싱을 굴착된 부분에 고정시킨다.After inserting the inner casing 90 into the excavated portion of the dredging surface 1, as shown in FIG. 16, the mortar 80 is injected between the inner casing 90 and the casing 50 to excavate the inner casing. To the fixed part.

한편, 몰탈(80)을 주입하여 이너케이싱(90)을 고정시키기 전에 도 17에 도시된 바와 같이 굴착된 부분으로 인입된 이너케이싱(90)을 임시 고정하는 단계가 이루어지는데, 이 때 이너케이싱(90)의 상측에 미리 구비되어 있던 수중 고정대(97)에 의해 이너케이싱(90)이 케이싱(50)에 임시 고정될 수 있다.Meanwhile, before the mortar 80 is injected to fix the inner casing 90, a step of temporarily fixing the inner casing 90 drawn into the excavated portion is performed as shown in FIG. 17, wherein the inner casing ( The inner casing 90 may be temporarily fixed to the casing 50 by the underwater stator 97 provided in advance above the 90.

이너케이싱(90)을 임시 고정하는 단계는 잠수부가 케이싱(50) 내부로 들어가 수중 고정대(97)의 일측을 케이싱(50)의 내주면에 수중용접(99)시켜 고정시킬 수 있다. 이와 같이 이너케이싱(90)을 임시 고정시키면 전술한 몰탈 주입 단계에서 몰탈(80) 주입이 수월하게 이루어질 수 있으며 이너케이싱(90)을 보다 정확한 위치에 고정시킬 수 있는 효과를 가질 수 있다.In the step of temporarily fixing the inner casing (90), the diver may enter the casing (50) and fix one side of the underwater holding bracket (97) to the underwater welding (99) on the inner circumferential surface of the casing (50). As such, temporarily fixing the inner casing 90 may facilitate the injection of the mortar 80 in the above-described mortar injection step, and may have an effect of fixing the inner casing 90 at a more accurate position.

몰탈(80) 주입으로 이너케이싱(90)을 고정한 후에는 케이싱(50) 외측에 쌓여있던 사석(5)을 준설하는 단계가 이루어진다. 도 18a 내지 도 18c에 도시된 바와 같이 쌓여있는 사석(5)의 크기에 따라 단계적으로 사석(5)을 제거하고 마지막에는 잠수부가 동원되어 사석 제거 작업을 마무리 한다. After fixing the inner casing 90 by mortar 80 injection, a step of dredging the dead stone 5 stacked on the outside of the casing 50 is performed. As shown in Figure 18a to 18c step by step according to the size of the stacked stacking stone (5) to remove the stepping stone (5) and finally the divers are mobilized to finish the work of removing the stone.

사석(5)이 제거된 후에는 도 19에 도시된 바와 같이 케이싱(50)을 절단하는 작업이 이루어진다. 케이싱(50)의 하부는 전술한 단계에서 수중 콘크리트(4)에 의해 고정되어 있다. 따라서 케이싱(50)을 수중 콘크리트(4)로부터 분리시키기 어려우므로 수중 콘크리트(4)의 상측면에 해당하는 위치에서 잠수부가 절단기를 이용하여 케이싱(50)을 절단하게 된다. 즉, 케이싱(50)을 절단한 후, 절단된 케이싱(50)을 인양하여 제거하는 것으로 이너케이싱(90) 시공이 완료될 수 있다. 이렇게 시공이 완료된 이너케이싱(90)이 해저 수직구라 할 수 있다.After the dead stone 5 is removed, a work of cutting the casing 50 is performed as shown in FIG. 19. The lower part of the casing 50 is fixed by the underwater concrete 4 in the above-mentioned step. Therefore, since it is difficult to separate the casing 50 from the underwater concrete 4, the diver cuts the casing 50 by using a cutter at a position corresponding to the upper side of the underwater concrete 4. That is, after cutting the casing 50, the construction of the inner casing 90 can be completed by lifting and removing the cut casing 50. In this way, the completed inner casing 90 may be referred to as a vertical seabed.

본 발명에 따른 해저 수직구(이너케이싱) 시공방법에 따르면, 준설면을 굴착하는 단계가 1차 굴착 단계와 2차 굴착 단계로 이루어져 한번에 큰 직경을 굴착할 경우 굴착기로 걸리는 과부하에 의해 굴착기가 고장나는 것을 방지하는 효과를 얻을 수 있다.According to the construction method of the seabed vertical sphere (inner casing) according to the present invention, the step of excavating the dredging surface consists of the first excavation step and the second excavation step, when the excavator is excavated by the overload applied to the excavator when excavating a large diameter at one time You can get the effect of preventing flying.

그리고 준설면을 굴착하기 전에 준설면 굴착을 위해 구비되는 케이싱에 침하 방지 지지대가 구비되도록 함으로써, 케이싱이 굴착 작업이 이루어지는 동안 침하되는 것을 방지할 수 있다.And by digging the dredging surface before the excavation support is provided in the casing provided for the dredging surface excavation, it is possible to prevent the casing is settled during the excavation operation.

특히, 침하 방지 지지대는 수중 콘크리트의 부착력을 향상시키기 위해 케이싱 하부 외측에 형성된 스틸밴드와 유기적으로 조합됨으로써, 케이싱의 침하를 보다 효과적으로 방지할 수 있게 된다.In particular, the anti-settling support is organically combined with the steel band formed on the outer side of the casing to improve the adhesion of the underwater concrete, it is possible to more effectively prevent the settlement of the casing.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.The foregoing description of the present invention is intended for illustration, and it will be understood by those skilled in the art that the present invention may be easily modified in other specific forms without changing the technical spirit or essential features of the present invention. will be. It is therefore to be understood that the above-described embodiments are illustrative in all aspects and not restrictive. For example, each component described as a single type may be implemented in a distributed manner, and similarly, components described as distributed may be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.

1: 준설면 3: 파쇄대
4: 수중 콘크리트 5: 사석
10: 잭 업 바지 20: 평바지
21: 리프팅 프레임 30: 가이드 프레임
31: 클램프 40: 플로팅 크레인
50: 케이싱 51: 스틸 밴드
60: 후크부 61: 메인 후크
61a: 후크 가이드 프레임 63: 보조 후크
70, 70’: 굴착기 80: 몰탈
81: 수중 거푸집 83: 수중 콘크리트
90: 이너케이싱 91: 배수 밸브
92: 바닥판 93: 저면 가이드
95: 통수 밸브 97: 수중 고정대
99: 수중 용접 100: 침하 방지 지지대
110: 지지부재 130: 연결부품
140: 연결부재
1: dredge surface 3: crushing stand
4: underwater concrete 5: sandstone
10: Jack Up Pants 20: Flat Pants
21: lifting frame 30: guide frame
31: clamp 40: floating crane
50: casing 51: steel band
60: hook portion 61: main hook
61a: hook guide frame 63: auxiliary hook
70, 70 ': Excavator 80: Mortar
81: underwater formwork 83: underwater concrete
90: inner casing 91: drain valve
92: bottom plate 93: bottom guide
95: water flow valve 97: submersible fixture
99: underwater welding 100: anti-sediment support
110: support member 130: connecting parts
140: connecting member

Claims (20)

해저 굴착 및 수직구 시공 방법에 있어서,
a) 준설면에 케이싱이 배치될 수 있도록 잭업 바지(jack-up barge)를 고정 설치하는 단계;
b) 상기 잭업 바지의 일측에 가이드 프레임을 설치하는 단계;
c) 상기 케이싱을 인양하여 상기 가이드 프레임을 통해 상기 준설면에 상기 케이싱을 배치하는 단계;
d) 상기 케이싱의 외주에 수중 콘크리트를 타설하는 단계;
e) 상기 케이싱 외주면에 타설된 상기 수중 콘크리트의 상면을 지지하는 침하방지 지지대를 설치하는 단계;
f) 상기 케이싱에 굴착기를 삽입하여 상기 준설면을 수직으로 굴착하는 단계;
g) 이너케이싱을 제작하는 단계;
h) 상기 케이싱에 상기 이너케이싱을 삽입하여 상기 준설면의 굴착된 부분에 설치하는 단계; 및
i) 상기 케이싱의 상기 수중 콘크리트의 상측으로 돌출된 부분을 절단 후 제거하는 단계를 포함하되,
상기 f) 단계는,
f-1) 상기 케이싱의 내주보다 작은 직경으로 1차 굴착하는 단계; 및
f-2) 상기 케이싱의 내주에 대응되는 직경으로 2차 굴착하는 단계를 포함하는 해저 굴착 및 수직구 시공 방법.
In the seabed excavation and vertical sphere construction method,
a) fixing the jack-up barge so that the casing can be placed on the dredging surface;
b) installing a guide frame on one side of the jack-up pants;
c) lifting the casing and placing the casing on the dredging surface through the guide frame;
d) placing underwater concrete on the outer periphery of the casing;
e) installing a settlement preventing support for supporting the upper surface of the underwater concrete poured on the outer peripheral surface of the casing;
f) inserting an excavator into the casing to excavate the dredge surface vertically;
g) manufacturing the inner casing;
h) inserting the inner casing into the casing and installing on the excavated portion of the dredging surface; And
i) cutting and removing a portion protruding upward of the underwater concrete of the casing,
Step f),
f-1) first drilling to a diameter smaller than the inner circumference of the casing; And
f-2) subsea excavation and vertical sphere construction method comprising the step of secondary drilling to a diameter corresponding to the inner circumference of the casing.
제1항에 있어서,
상기 침하방지 지지대는
상기 케이싱의 외주면에 장착된 연결부재; 및
상기 연결부재와 체결되고 상기 케이싱의 외측 방향으로 연장되는 지지부재를 포함하는 해저 굴착 및 수직구 시공 방법.
The method of claim 1,
The settlement prevention support
A connection member mounted on an outer circumferential surface of the casing; And
Seabed excavation and vertical sphere construction method comprising a support member coupled to the connection member and extending in the outward direction of the casing.
제2항에 있어서,
상기 지지부재는 설치 작업 시 무게가 경감되도록 복수 개의 단위부재를 체결하여 구비되는 것인 해저 굴착 및 수직구 시공 방법.
The method of claim 2,
The support member is a seabed excavation and vertical sphere construction method that is provided by fastening a plurality of unit members so that the weight is reduced during installation.
제3항에 있어서,
상기 복수의 단위부재 및 상기 연결부재는 서로 볼트 체결되는 것인 해저 굴착 및 수직구 시공 방법.
The method of claim 3,
The plurality of unit members and the connecting member is bolted to each other subsea excavation and vertical sphere construction method.
제 2 항에 있어서,
상기 연결부재 및 상기 지지부재는 "I"빔인 것인 해저 굴착 및 수직구 시공방법.
The method of claim 2,
The connecting member and the support member is an "I" beam is a seabed excavation and vertical sphere construction method.
제 1 항에 있어서,
상기 c) 단계는,
c-1) 평바지에 상기 케이싱을 수평 방향으로 배치하고, 플로팅 크레인의 후크부를 상기 케이싱에 연결하는 단계;
c-2) 상기 평바지를 수평으로 이동시키고 상기 플로팅 크레인이 상기 케이싱을 수직으로 들어 올림으로써, 상기 케이싱을 상기 수평 방향에서 수직 방향으로 회전시키는 단계; 및
c-3) 상기 케이싱을 상기 준설면에 인양하여 배치하는 단계를 포함하되,
상기 평바지는 일측에 힌지 결합되어 상기 케이싱을 회전 가능하게 지지하는 리프팅 프레임을 포함하며,
상기 평바지는 상기 케이싱이 회전되는 방향의 반대 방향으로 이동하는 것인 해저 굴착 및 수직구 시공 방법.
The method of claim 1,
The step c)
c-1) placing the casing in a flat pants in a horizontal direction and connecting the hook portion of the floating crane to the casing;
c-2) moving the flat pants horizontally and the floating crane lifting the casing vertically, thereby rotating the casing from the horizontal direction to the vertical direction; And
c-3) lifting and placing the casing on the dredging surface,
The flat pants are hinged to one side and includes a lifting frame rotatably supporting the casing,
The flat pants are subsea excavation and vertical sphere construction method to move in a direction opposite to the direction in which the casing is rotated.
제 6 항에 있어서,
상기 평바지와 상기 플로팅 크레인은 교차되게 배치되는 해저 굴착 및 수직구 시공 방법.
The method according to claim 6,
The flat pants and the floating crane is arranged to cross the seabed excavation and vertical sphere construction method.
제 6 항에 있어서,
상기 후크부는,
후크 가이드 프레임을 통해서 상기 케이싱의 일측과 연결되는 메인 후크; 및
상기 메인 후크와 연결되며, 상기 케이싱의 외주면에 연결되는 보조 후크를 포함하는 해저 굴착 및 수직구 시공 방법.
The method according to claim 6,
The hook portion,
A main hook connected to one side of the casing through a hook guide frame; And
And a sub hook connected to the main hook and connected to an outer circumferential surface of the casing.
제1항에 있어서,
상기 g) 단계는,
g-1) 강관을 인양하여 제작장에 세워 배치하는 단계;
g-2) 상기 강관의 전도가 방지되도록 상기 강관의 내부에 물을 충진하는 단계;
g-3) 상기 강관의 외주에 철근 콘크리트를 단계적으로 타설하여 프리캐스팅 라이닝을 형성하는 이너케이싱의 제작을 완료하는 단계; 및
g-4) 상기 강관의 하부에 구비된 배수 밸브에 연결된 배수 파이프를 통해 충진된 상기 물을 배수하는 단계를 포함하는 해저 굴착 및 수직구 시공 방법.
The method of claim 1,
Step g),
g-1) lifting the steel pipes and placing them in the manufacturing site;
g-2) filling water into the steel pipe to prevent the steel pipe from falling over;
g-3) completing the production of the inner casing to form precast lining by gradually pouring reinforced concrete on the outer circumference of the steel pipe; And
g-4) subsea excavation and vertical sphere construction method comprising the step of draining the water filled through the drain pipe connected to the drain valve provided in the lower portion of the steel pipe.
제9항에 있어서,
상기 g-3) 단계는,
g-31) 상기 강관의 둘레에 동바리 및 비계를 설치하는 단계;
g-32) 상기 강관의 외주에 철근을 조립하는 단계;
g-33) 상기 강관의 둘레에 거푸집을 설치하는 단계;
g-34) 상기 강관의 외주 및 상기 거푸집 사이에 콘크리트를 타설하는 단계;
g-35) 상기 거푸집을 해체하고 상기 콘크리트를 양생하는 단계; 및
g-36) 상기 양생된 콘크리트의 상측에 상기 g-31) 내지 g-35) 단계를 반복하는 단계를 포함하는 해저 굴착 및 수직구 시공 방법.
10. The method of claim 9,
Step g-3),
g-31) installing clubs and scaffolding around the steel pipe;
g-32) assembling reinforcing bars on the outer circumference of the steel pipe;
g-33) installing formwork around the steel pipe;
g-34) placing concrete between the outer circumference of the steel pipe and the formwork;
g-35) dismantling the formwork and curing the concrete; And
g-36) subsea excavation and vertical sphere construction method comprising the step of repeating the steps g-31) to g-35) on the cured concrete.
제9항에 있어서,
상기 g) 단계는,
g-5) 충진된 상기 물의 배수가 완료된 후 상기 이너케이싱을 들어올려 상기 배수 파이프를 제거하고 상기 배수 밸브를 잠그는 단계; 및
g-6) 상기 케이싱 내부로의 삽입이 가이드 되도록 상기 이너케이싱의 저면의 둘레에 가이드 부재를 장착하는 단계를 더 포함하는 해저 굴착 및 수직구 시공 방법.
10. The method of claim 9,
Step g),
g-5) lifting the inner casing to remove the drain pipe and closing the drain valve after draining the filled water is complete; And
g-6) further comprising the step of mounting a guide member around the bottom of the inner casing to guide the insertion into the casing.
제 1 항에 있어서,
상기 f)단계는 서로 직경이 다른 두 대의 역순환 굴착 장치를 통해 수행되는 것인 해저 굴착 및 수직구 시공 방법.
The method of claim 1,
The step f) is a subsea excavation and vertical sphere construction method that is performed through two reverse circulation excavation device having a different diameter.
제1항에 있어서,
상기 f) 단계는
f-3) 상기 굴착된 부분에 파쇄대가 있는 경우, 상기 파쇄대 공벽 붕괴를 방지하기 위한 작업이 이루어지는 단계를 더 포함하는 해저 굴착 및 수직구 시공 방법.
The method of claim 1,
Step f)
f-3) if there is a crushing zone in the excavated portion, the step of the seabed excavation and vertical sphere construction method further comprises the step of preventing the collapse of the crushing wall.
제13항에 있어서,
상기 f-3) 단계는,
f-31) 상기 파쇄대가 있는 위치에 수중 거푸집을 설치하는 단계; 및
f-32) 상기 수중 거푸집과 상기 파쇄대 사이로 수중 콘크리트를 타설하는 단계를 포함하는 해저 굴착 및 수직구 시공 방법.
The method of claim 13,
Step f-3),
f-31) installing an underwater formwork at the location of the shredding stand; And
f-32) subsea excavation and vertical sphere construction method comprising the step of placing underwater concrete between the underwater formwork and the crushing zone.
제 1 항에 있어서,
상기 e) 단계는 상기 수중 콘크리트의 상측에 사석을 쌓는 단계를 포함하는 해저 굴착 및 수직구 시공 방법.
The method of claim 1,
The step e) is a seabed excavation and vertical sphere construction method comprising the step of stacking the sandstone on the upper side of the underwater concrete.
제 15 항에 있어서,
상기 i)단계는 상기 사석을 준설하는 단계를 포함하는 해저 굴착 및 수직구 시공 방법.
The method of claim 15,
The step i) seabed excavation and vertical sphere construction method comprising the step of dredging the sandstone.
제1항에 있어서,
상기 수중 콘크리트가 타설되는 상기 케이싱의 하부 외주면에는 상기 수중 콘크리트와의 부착력을 향상시키는 스틸밴드가 구비되는 것인 해저 굴착 및 수직구 시공 방법.
The method of claim 1,
The bottom outer circumferential surface of the casing in which the underwater concrete is poured is provided with a steel band for improving the adhesion to the underwater concrete, seabed excavation and vertical sphere construction method.
제1항에 있어서,
상기 h) 단계는,
h-1) 평바지에 상기 이너케이싱을 수평 방향으로 배치하고, 플로팅 크레인의 후크부를 상기 이너케이싱에 연결하는 단계;
h-2) 상기 평바지를 수평으로 이동시키고 상기 플로팅 크레인이 상기 이너케이싱을 수직으로 들어 올림으로써, 상기 이너케이싱을 상기 수평 방향에서 수직 방향으로 회전시키는 단계;
h-3) 상기 이너케이싱을 상기 굴착된 부분에 인입 후, 상기 이너케이싱을 임시 고정시키는 단계; 및
h-4) 몰탈을 주입하여 상기 이너케이싱을 고정시키는 단계를 포함하되,
상기 평바지는 일측에 힌지 결합되어 상기 이너케이싱을 회전 가능하게 지지하는 리프팅 프레임을 포함하며,
상기 평바지는 상기 이너케이싱이 회전되는 방향의 반대 방향으로 이동하는 것인 해저 굴착 및 수직구 시공 방법.
The method of claim 1,
Step h),
h-1) placing the inner casing in a flat pants in a horizontal direction and connecting the hook portion of the floating crane to the inner casing;
h-2) rotating said inner casing in a vertical direction by moving said flat pants horizontally and said floating crane lifting said inner casing vertically;
h-3) temporarily pulling the inner casing after introducing the inner casing into the excavated portion; And
h-4) injecting mortar to fix the inner casing,
The flat pants are hinged to one side and includes a lifting frame rotatably supporting the inner casing,
The flat pants are subsea excavation and vertical sphere construction method is to move in the direction opposite to the direction in which the inner casing is rotated.
제 18 항에 있어서,
상기 평바지와 상기 플로팅 크레인은 교차되게 배치되는 해저 굴착 및 수직구 시공 방법.
The method of claim 18,
The flat pants and the floating crane is arranged to cross the seabed excavation and vertical sphere construction method.
제 18 항에 있어서,
상기 후크부는,
후크 가이드 프레임을 통해서 상기 이너케이싱의 일측과 연결되는 메인 후크; 및
상기 메인 후크와 연결되며, 상기 이너케이싱의 외주면에 연결되는 보조 후크를 포함하는 해저 굴착 및 수직구 시공 방법.
The method of claim 18,
The hook portion,
A main hook connected to one side of the inner casing through a hook guide frame; And
Subsea excavation and vertical sphere construction method is connected to the main hook, including an auxiliary hook connected to the outer peripheral surface of the inner casing.
KR1020110122939A 2011-11-23 2011-11-23 Method for excavating submarine surface and constructing submarine vertical waterway KR101119195B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020110122939A KR101119195B1 (en) 2011-11-23 2011-11-23 Method for excavating submarine surface and constructing submarine vertical waterway
PCT/KR2012/009704 WO2013077595A1 (en) 2011-11-23 2012-11-16 Seabed drilling and vertical shaft construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110122939A KR101119195B1 (en) 2011-11-23 2011-11-23 Method for excavating submarine surface and constructing submarine vertical waterway

Publications (1)

Publication Number Publication Date
KR101119195B1 true KR101119195B1 (en) 2012-03-21

Family

ID=46141408

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110122939A KR101119195B1 (en) 2011-11-23 2011-11-23 Method for excavating submarine surface and constructing submarine vertical waterway

Country Status (2)

Country Link
KR (1) KR101119195B1 (en)
WO (1) WO2013077595A1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146811A (en) 2000-11-16 2002-05-22 Kajima Corp Construction method for underwater structure foundation
KR100621410B1 (en) 2003-03-26 2006-09-13 배석동 Dry Construction Method of Underwater Structure Using Watertight Caisson
KR100721676B1 (en) 2006-04-12 2007-05-23 삼보지질 주식회사 Construction method of submarine vertical waterway for supplying and discharging cooling water for industrial facilities utilizing jack up barge and guide frame and inner casing and casing clamp
KR100880367B1 (en) 2008-06-02 2009-01-30 삼보이엔씨 주식회사 Process for constructing diffuser in the water

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6128617A (en) * 1984-07-18 1986-02-08 Penta Ocean Constr Co Ltd Method of hammering and securing steel pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002146811A (en) 2000-11-16 2002-05-22 Kajima Corp Construction method for underwater structure foundation
KR100621410B1 (en) 2003-03-26 2006-09-13 배석동 Dry Construction Method of Underwater Structure Using Watertight Caisson
KR100721676B1 (en) 2006-04-12 2007-05-23 삼보지질 주식회사 Construction method of submarine vertical waterway for supplying and discharging cooling water for industrial facilities utilizing jack up barge and guide frame and inner casing and casing clamp
KR100880367B1 (en) 2008-06-02 2009-01-30 삼보이엔씨 주식회사 Process for constructing diffuser in the water

Also Published As

Publication number Publication date
WO2013077595A1 (en) 2013-05-30

Similar Documents

Publication Publication Date Title
KR100758113B1 (en) Cast-in-place large diameter piling method by casing rotator in underwater rock conditions
EP2837554A1 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
CN110359476B (en) Construction method of construction platform for mounting steel sheet pile cofferdam inner support and bored pile steel casing
EP3118374A1 (en) Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same
KR101211811B1 (en) Cast in concrete pile With precast type Caisson
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
CN102839681A (en) Combined steel pipe pile cofferdam used under condition of no cover layer in deep water and construction method thereof
CN112761644A (en) Suspension sinking vertical shaft well completion process
CN102561371A (en) Steel caisson enclosure structure at island-tunnel combination part
KR101650232B1 (en) Semipermeable breakwater of combined power generation facility
KR101650231B1 (en) Construction structures with wave power generator of semipermeable breakwater
KR100914650B1 (en) The well foundation method for which a steel caisson for pier reinforcement was used
JP2002146811A (en) Construction method for underwater structure foundation
RU2386755C1 (en) Method for arrangement of shallow subway at water area bottom
KR20150137725A (en) Construction structures of semipermeable breakwater with wind power generator
JP2000265474A (en) Temporary cofferdam constructing method for construction
KR101119195B1 (en) Method for excavating submarine surface and constructing submarine vertical waterway
CN102605801A (en) Suspension semi-reverse-construction method for underground circular water tank
JP2020128672A (en) Installation method of mono-pile foundation for offshore wind power generation and mono-pile foundation for offshore wind power generation
JP2001303883A (en) Excavation method using earth retaining structure composed of ring beam, inverted lining wall and rock bolt
KR200387372Y1 (en) The underwater casing form
KR20200014531A (en) Fixed anchor construction method of marine structure
CN113356247B (en) Large deep foundation protection lock catch steel pipe pile cofferdam structure and construction method thereof
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150204

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20161219

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20171213

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20191209

Year of fee payment: 9