KR101109724B1 - A slope territory or heat of city level ground road construction work method - Google Patents

A slope territory or heat of city level ground road construction work method Download PDF

Info

Publication number
KR101109724B1
KR101109724B1 KR1020110048411A KR20110048411A KR101109724B1 KR 101109724 B1 KR101109724 B1 KR 101109724B1 KR 1020110048411 A KR1020110048411 A KR 1020110048411A KR 20110048411 A KR20110048411 A KR 20110048411A KR 101109724 B1 KR101109724 B1 KR 101109724B1
Authority
KR
South Korea
Prior art keywords
upper slab
area
cip
slope
slab
Prior art date
Application number
KR1020110048411A
Other languages
Korean (ko)
Inventor
김현경
정인혁
Original Assignee
(주)나우이앤씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)나우이앤씨 filed Critical (주)나우이앤씨
Priority to KR1020110048411A priority Critical patent/KR101109724B1/en
Application granted granted Critical
Publication of KR101109724B1 publication Critical patent/KR101109724B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C1/00Design or layout of roads, e.g. for noise abatement, for gas absorption
    • E01C1/002Design or lay-out of roads, e.g. street systems, cross-sections ; Design for noise abatement, e.g. sunken road
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/32Arched structures; Vaulted structures; Folded structures
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Electromagnetism (AREA)
  • Physics & Mathematics (AREA)
  • Sustainable Development (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Road Paving Structures (AREA)

Abstract

PURPOSE: A covered road construction method for a slope area or a city level ground area is provided to construct a covered road with a minimized cut area, thereby reducing a construction period. CONSTITUTION: A covered road construction method for a slope area or a city level ground area is as follows. In a covered road area, the ground is excavated in a stepwise manner along a slope from an end where an upper slab is installed. Holes are bored along width edges of the covered road area, CIP bulbs are inserted in the holes, and concrete is placed and cured(S10). Wall foundation excavating work is implemented from the inner side of the CIP bulbs and earth anchors are formed outward from the CIP bulbs(S20). A column part is formed vertically upward from a lower girder and a supporting part for supporting upper slabs is formed on the top of the column part(S30). The upper slabs are installed in crossing directions on the top of the supporting part(S40). A ventilation tower is installed through a selected area of the upper slabs in order to circulate and discharge air inside covered ground to outside(S50). Lower slab bars are assembled after the foundation cured, concrete is placed and cured, asphalt is placed, and lower slabs are installed(S60).

Description

사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법{A SLOPE TERRITORY OR HEAT OF CITY LEVEL GROUND ROAD CONSTRUCTION WORK METHOD}Method of constructing open road in slope existence area or urban plain area {A SLOPE TERRITORY OR HEAT OF CITY LEVEL GROUND ROAD CONSTRUCTION WORK METHOD}

본 발명은 복개도로 시공 방법에 관한 것으로 특히 산과 같은 지형지물이 존재하면서 사면을 갖는 구간의 영역으로 도로를 건설하기 위한 복개도로 시공 방법에 관한 것이다.
The present invention relates to a method of construction of the open road, and more particularly, to a method of constructing the open road for constructing a road to an area of a section having a slope while a feature such as a mountain exists.

산과 같은 지형 지물이 존재하는 구간에 도로를 건설 할 때 특히, 산 허리나 산 아래 영역에 걸쳐지는 도로를 건설할 때에는 일반적으로 도로의 공사 영역으로부터 산의 정상 방향으로 계단식 대절토를 행한 후, 도로를 건설하게 된다.When constructing a road in a section where a feature such as a mountain exists, especially when constructing a road that covers a mountain waist or an area below the mountain, a stepped cut from the construction area of the road toward the top of the mountain is generally performed. Will be built.

이와 같은 종래의 도로 건설 방법의 경우, 도로 폭의 끝 지점에서부터 좌상향 또는 우상향의 방향으로 일정각도를 이루며 대절토를 하게 되고, 도로 완공 후에는 대절토 된 영역이 완전하게 복구되지 않는 상태를 유지하게 되어, 환경은 물론 생태계 파괴의 원인이 되고 있다.In the case of the conventional road construction method, the cut soil is formed at an angle from the end of the road width to the left upward or right upward direction, and after the completion of the road, the uncut soil is not completely recovered. The environment is, of course, the cause of ecosystem destruction.

본 발명은 상기한 문제점 등을 해결하기 위한 것으로, 산과 같은 지형 지물에 형성되는 도로를 건설 할 때, 대절토되는 영역을 최소화하면서도 도로 건설이 가능하도록 하여 도로 건설에 따른 공기를 현저하게 줄일 수 있도록 하는 데 그 목적이 있으며, 도로 건설 후 대절토 되는 영역의 필요부분에 복토 가능하도록 하여 환경과 생태계를 보호하도록 하는 데 다른 목적이 있다.
The present invention is to solve the above problems, such as, when constructing a road formed on a terrain feature, such as mountains, so that the road construction can be made while minimizing the area of the soil so as to significantly reduce the air due to the construction of the road Its purpose is to protect the environment and the ecosystem by making it possible to cover the necessary parts of the soil that is laid off after road construction.

상기한 목적을 달성하기 위한 본 발명은, The present invention for achieving the above object,

토공굴착 및 CIP 천공 단계(S10), 벽체부 시설단계(S20), 기둥부 시설단계(S30), 상부 슬래브 설치 단계(S40), 환기탑 설치 단계(S50), 하부 슬래브 설치단계(S60)의 과정을 거쳐 이루어진다.
Earth excavation and CIP drilling step (S10), wall unit installation step (S20), column installation step (S30), upper slab installation step (S40), ventilation tower installation step (S50), lower slab installation process (S60) Is done through.

본 발명에 의하면, 산과 같은 지형 지물에 형성되는 도로를 건설할 때, 대절토되는 영역을 최소화하면서도 도로 건설이 가능하도록 하여 도로 건설에 따른 공기를 현저하게 줄일 수 있음은 물론, 도로 건설 후 대절토 되는 영역의 필요부분 에 복토가 가능하도록 하여 환경과 생태계 보호 효과를 기대할 수 있다.
According to the present invention, when constructing a road formed on a terrain feature such as a mountain, it is possible to significantly reduce the air due to the road construction by minimizing the area to be cut off, as well as after the road construction It is possible to cover the necessary areas of the areas to be protected, thereby protecting the environment and the ecosystem.

도 1은 본 발명의 공정 흐름도를 도시한 블럭도
도 2는 도로를 형성하는 영역으로부터 사선방향으로 사면을 굴착하여 도로가 형성되는 상방 영역이 노출되도록 하는 토공 굴착을 하는 과정을 개괄적으로 도시한 도면
도 3은 CIP구군의 내부를 도시한 개괄적 도면
도 4는 벽체부의 터파기 작업이 이루어진 상태를 도시한 도면
도 5는 벽체부 시설단계가 완료된 후, 복개도로를 이루는 중앙 부분을 터파기 하여 기둥부가 시공되도록 하는 것을 도시한 도면
도 6은 도 5에 의한 기둥부의 분리 상태를 도시한 분리 사시도
도 7은 상부슬래브가 설치된 상태의 개괄적 단면도
도 8 내지 도 9는 상부슬래브 및 환기탑이 설치된 후 상부슬래브의 상면을 복토하고 하부슬래브를 시설한 상태를 도시한 개괄적 도면
도 10은 도 9의 "A"부분 확대 도면
도 11은 상부슬래브와 상부슬래브간 단부가 접하며 이루어지는 부분을 연결하기 위한 중앙연결부를 도시한 도면
도 12는 상부슬래브와 CIP구근 및 벽체간 접하는 부분을 고정 연결하는 일실시예를 도시한 확대도면
도 13 내지 도 14는 상부슬래브와 CIP구근 및 벽체간 접하는 부분을 연결하는 각각 다른 실시예로 힌지 회동 가능한 상태로 연결되는 것을 도시한 확대도면
도 15는 상기와 같이 상부슬래브(300)의 측면을 상호 연결하게 되는 부분을 확대 도시한 도면
도 16은 도 15에서의 상부슬래브와 상부슬래브 측면간 접하는 부분을 확대 도시한 도면
도 17은 상부슬래브가 분리된 상태를 도시한 분리 사시도
도 18은 복개 지하도가 완성된 상태를 도시한 사시도면
1 is a block diagram illustrating a process flow diagram of the present invention.
FIG. 2 is a view schematically illustrating a process of excavating earthworks to excavate a slope in an oblique direction from an area forming a road so that an upper area where a road is formed is exposed; FIG.
3 is a schematic diagram showing the interior of the CIP group;
4 is a view showing a state in which the trench work of the wall portion is made;
5 is a view showing that after the completion of the wall unit installation step, the pillar portion is constructed by digging the central portion constituting the abdominal road
FIG. 6 is an exploded perspective view illustrating a detached state of the pillar part according to FIG. 5. FIG.
7 is a schematic cross-sectional view of the upper slab is installed
8 to 9 are schematic views showing a state in which the upper slab is covered and the lower slab is installed after the upper slab and the ventilation tower are installed.
FIG. 10 is an enlarged view of a portion “A” of FIG. 9; FIG.
FIG. 11 is a view showing a central connection part for connecting a portion formed by contacting an end portion between an upper slab and an upper slab.
Figure 12 is an enlarged view showing an embodiment for fixing the connection between the upper slab and the CIP bulb and the wall contacting
13 to 14 are enlarged views showing that the hinges can be connected to each other by connecting the upper slab, the CIP bulb, and the contact portion between the walls.
FIG. 15 is an enlarged view of a portion connecting the side surfaces of the upper slab 300 as described above.
FIG. 16 is an enlarged view of a portion of the upper slab contacting the upper slab side in FIG. 15.
17 is an exploded perspective view showing a state in which the upper slab is separated
18 is a perspective view illustrating a state where the covered underpass is completed;

이하 본 발명의 바람직한 실시예를 첨부하는 도면을 참조하여 상세히 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명은 토공굴착 및 CIP 천공 단계(S10), 벽체부 시설단계(S20), 기둥부 시설단계(S30), 상부 슬래브 설치 단계(S40), 환기탑 설치 단계(S50), 하부 슬래브 설치단계(S60)의 과정을 거쳐 이루어진다.
The present invention is earth excavation and CIP drilling step (S10), wall unit installation step (S20), pillar installation step (S30), upper slab installation step (S40), ventilation tower installation step (S50), lower slab installation step (S60) )

토공굴착Earth excavation  And CIPCIP 천공 단계 -  Drilling Steps- S10S10

본 단계는 도 2에서 보는 바와 같이, 도로를 형성하는 영역으로부터 사선방향으로 사면을 굴착하여 도로가 형성되는 상방 영역이 노출되도록 하는 토공 굴착을 하게 된다.In this step, as shown in Figure 2, excavation of the slope in an oblique direction from the area forming the road to be excavated to expose the upper area where the road is formed.

도로 영역에서 측도 부분으로부터 사면을 굴착할 경우에는 그 토공 작업량이 상당하게 되므로, 본 발명에서는 복개 지하도 영역에서 상부 슬래브가 설치되는 끝단으로부터 토공 굴착이 이루어지도록 하여, 토공 작업량을 절감하도록 하였다. When excavating the slope from the side of the road in the road area, the amount of earthwork work is considerable, in the present invention was to be excavated from the end where the upper slab is installed in the covered underpass area, to reduce the amount of earthwork.

이와 같이 산이 존재하는 경사지를 통과하는 영역에 도로를 형성하기 위해서는 사면 방향으로 굴착하는 작업을 수행한 후 복개 지하도의 폭에 해당되는 양단측에 각각 CIP구근(100)이 삽입될 수 있는 홀(101)을 천공하여 내벽체로 형성될 수 있도록 하기 위한 것이다.As described above, in order to form a road in the area passing through the slope where the mountain exists, the hole 101 in which the CIP bulbs 100 can be inserted at both ends corresponding to the width of the covered underpass after excavation in the slope direction is performed. Perforated) to be formed into an inner wall.

본 발명에서의 CIP구근(100)을 이용하여 내벽체로 형성하되, 중앙부의 벽체는 별도의 구성을 통해 실현되도록 하였으며, 이에 대한 설명은 후술한다.Formed as an inner wall using the CIP bulb 100 in the present invention, the wall of the central portion is to be realized through a separate configuration, a description thereof will be described later.

한편 상기한 CIP(Cast-in-place pile) 구근(100)은 도 2에서 보는 바와 같이 다수의 철근(110)이 구형상으로 배열 배치되고 그 철근(110)의 외주측을 감싸는 사각 형태를 갖도록 하는 띠철근(120)을 등간격 이격 시키며 형성하게 된다. On the other hand, the cast-in-place pile (CIP) bulb 100 is a plurality of reinforcement 110 is arranged in a spherical shape as shown in Figure 2 to have a rectangular shape surrounding the outer peripheral side of the reinforcement 110 The band reinforcing bars 120 are formed at equal intervals.

이러한 CIP구근(100)의 내부에 콘크리트를 타설, 양생 처리하므로서, 하나의 유닛으로 이루어지는 원기둥 형태의 CIP구근(100)을 형성할 수 있고, 이와는 달리 CIP구근(100)이 삽입되기 위한 홀(101)을 천공한 후 그 홀(101)에 CIP구근(100)을 삽입한 다음 콘크리트를 타설 양생하여 완성된 CIP구근(100)을 얻을 수 있을 것이다.By placing and curing concrete in the interior of the CIP bulb 100, it is possible to form a cylindrical CIP bulb 100 consisting of a single unit, otherwise the hole 101 for the CIP bulb 100 is inserted ) And then insert the CIP bulb 100 into the hole 101 and then pour concrete to obtain a finished CIP bulb 100.

이때, 기반암층이 높을 경우에는 CIP구근(100)을 토사층에만 형성되도록 하고, 기반암층이 더욱 높을 경우에는 CIP구근(100)을 형성치 않을 수 있다.
In this case, when the bedrock layer is high, the CIP bulb 100 may be formed only in the soil layer, and when the bedrock layer is higher, the CIP bulb 100 may not be formed.

벽체부Wall 시설단계 -  Facility Level- S20S20

본 단계는 상기한 토공굴착 및 CIP 천공단계(S10)를 거쳐 CIP구근(100)의 삽입이 완성되면, CIP구근(100)의 내측 방향으로 벽체부 터파기 작업을 하게 된다. In this step, when the insertion of the CIP bulb 100 is completed through the earth excavation and the CIP drilling step S10, the wall part is excavated in the inward direction of the CIP bulb 100.

도 4 은 상기한 벽체부의 터파기 작업이 이루어진 상태를 도시한 도면으로, 벽체부 터파기 작업이 완료된 후 CIP구근(100)으로부터 외측방향으로 Earth Anchor를 형성하여 CIP구근(100)의 외측방향에서 제공되는 토사압을 견딜 수 있도록 한다. Figure 4 is a view showing a state in which the above-mentioned wall excavation work is made, after completing the wall excavation work to form an Earth Anchor from the CIP bulb 100 to the outward direction from the outer direction of the CIP bulb 100 Make sure to withstand the earth pressure provided.

도면부호 102는 벽체를 나타내는 것으로 전술한 CIP구근(100)의 내측으로 콘크리트 구조물로 양생된다.Reference numeral 102 denotes a wall and is cured into a concrete structure inward of the above-described CIP bulb 100.

이때, 전술한 바와 같이 기반암층이 높을 경우에는 CIP구근(100) 이하의 암을 절취하여 벽체를 시설하거나 기반암층이 더욱 높을 경우에는 바로 암을 절취하여 벽체를 시설할 수 있다.
In this case, as described above, when the bedrock layer is high, the cancer may be cut off by the cancer of the CIP bulb 100 or less and the wall may be installed.

기둥부Column 시설단계 -  Facility Level- S30S30

본 단계는 벽체부 시설단계(S20)가 완료된 후, 복개도로를 이루는 중앙 부분을 터파기 하여 기둥부(200)가 시공될 수 있도록 한다.In this step, after the wall part facility step S20 is completed, the pillar part 200 may be constructed by digging the central part constituting the abdominal road.

상기한 기둥부(200)는 도 5에서 보는 바와 같이, 하부에 하부거더(210)가 양생되도록 하고, 하부거더(210)로부터 수직상방향으로 양생되는 기둥부(200)를 구성하게 된다.5, the lower girder 210 is cured in the lower portion, as shown in FIG. 5, and the pillar 200 is cured vertically from the lower girder 210.

이러한 기둥부(200)는 벽체로 형성하거나 원형 또는 구형의 기둥 형태로 이루어질 수 있는바, 작업 현장 조건 등에 따라 선택적인 설치 시공이 가능할 수 있음은 물론이다. The pillar part 200 may be formed in a wall or in the form of a circular or spherical column, which may be selectively installed depending on work site conditions.

상기한 기둥부(200)의 내측으로는 상부슬래브(300)를 지지하기 위한 지지부(220)가 구성된다.The support part 220 for supporting the upper slab 300 is configured inside the pillar part 200.

상기 지지부(220)는 도 6에 도시된 것과 같이 실시할 수 있는데, 단면상 "○"자 이루며 중공(中空) 형태를 갖는 한조의 고정부재(221)를 상호 대향 되며 활개 되는 형태를 갖도록 기둥부(200) 내면에 고정되도록 하고, 상기 고정부재(221)와 고정부재(221)간을 PC강봉(222)을 이용하여 연결 고정하도록 한다. The support 220 may be implemented as shown in FIG. 6, which is formed in a cross-section “○” and has a hollow shape to have a shape in which a pair of fixing members 221 are opposed to each other and have a shape that is open. 200 to be fixed to the inner surface, and between the fixing member 221 and the fixing member 221 to be connected and fixed using a PC steel bar 222.

상기한 PC강봉(222)을 이용하여, 고정부재(221)와 고정부재(221)간을 긴장되도록 연결 하는 것은, 상부슬래브(300)가 한조로 이루어지며 "Y"자 형태로 활개되어 있는 고정부재(221) 상면에 안착되어질 때 상부슬래브(300)의 자중에 의해 고정부재(221)가 점차 활개 각도가 넓어지며 파단되거나 파손되는 등의 현상을 방지하고, 상부슬래브(300)의 안정적 지지가 가능하도록 하기 위함이다. Using the PC steel bar 222, connecting the fixing member 221 and the fixing member 221 to be tensioned, the upper slab 300 is made of a pair of fixed in the form of a "Y" When the mounting member 221 is seated on the upper surface of the upper slab by the weight of the upper slab 300, the fixing member 221 gradually widens the opening angle to prevent phenomena such as fracture or breakage, and the stable support of the upper slab 300 To make it possible.

아울러, 도 6에서 보는 바와 같이 한 조의 고정부재(221)와 측면에 이격되어 설치되는 또 다른 한 조의 고정부재(221)간을 횡간연결강관(223)을 이용하여 연결 고정되도록 하는 것이 바람직하다. In addition, as shown in Figure 6 it is preferable to be connected and fixed between the set of fixing members 221 and another set of fixing members 221 which are spaced apart from the side using the cross-connection steel pipe 223.

이와 같이 횡간연결강관(223)이 고정부재(221)와 측면방향 즉 복개도로 진행방향으로 이격되며 기둥부(200)의 지지부(220) 상면에 고정되는 타 고정부재(221)간을 상호 연결하기 위해, 상기 횡간연결강관(223)을 고정부재(221)와 고정부재(221)를 걸쳐 접하는 부분에 용접 및 볼트 등의 방법으로 고정되도록 하였다. As described above, the connecting steel pipe 223 is spaced apart from the fixing member 221 in the lateral direction, that is, the opening direction, and the other fixing member 221 fixed to the upper surface of the support part 220 of the pillar part 200. To this end, the transverse connection steel pipe 223 is fixed to the part in contact with the fixing member 221 and the fixing member 221 by welding or bolting.

상기 횡간연결강관(223)에 의해 한 조의 고정부재(221)와 측면으로 이격 구성되는 다른 한 조의 횡간연결강관(223)간을 고정 연결하므로서, 상부슬래브(300)가 고정부재(221)에 안착 시공 된 후 상부슬래브(300)의 자중에 의해 고정부재(221)가 비틀어지는 현상을 미연에 방지할 수 있을 것이다. The upper slab 300 is seated on the fixing member 221 by fixedly connecting between the set of the fixing member 221 and the other set of the horizontal connecting steel tube 223 spaced apart laterally by the transverse connecting steel pipe 223. After the construction will be able to prevent the phenomenon that the fixing member 221 is twisted by the weight of the upper slab 300 in advance.

한편, 상기 고정부재(221)와 측방향으로 이격 되는 타 고정부재(221)의 단부측으로 평플레이트(224)를 불연속으로 구비하되 평플레이트(224)의 하방면에 상기한 횡간연결강관(223)의 상면이 접하도록 하여 상기 평플레이트(224)를 상향 지지 구성하고, 상기 평플레이트(224) 상면으로는 무수축패드(225)를 구비하여, 상기 상부슬래브(300)와의 접촉 지지시 안정적 지지가 가능하도록 구성하는 것이 바람직하다.
On the other hand, provided with a flat plate 224 discontinuously to the end side of the other fixing member 221 which is laterally spaced apart from the fixing member 221, the transverse connecting steel pipe 223 described above on the lower side of the flat plate 224. The flat plate 224 is configured to support the upper surface of the upper plate 224, and the non-shrink pad 225 is provided on the upper surface of the flat plate 224, so that the stable support when contacting the upper slab 300 is supported. It is preferable to configure so that it is possible.

상부 슬래브 설치 단계 - Upper slab installation steps- S40S40

본 단계는 상기와 같이 기둥부(200)의 지지부(220) 상면에 등간격 이격 되며 복개 지하도 진행 방향을 따라 설치되는 고정부재(221)의 상면으로 단위편재로 이루어지는 상부슬래브(300)를 도 7 에서와 같이 안착하는 단계를 의미한다.This step is an upper slab 300 made of unit material as the upper surface of the fixing member 221 is spaced at equal intervals on the upper surface of the support portion 220 of the pillar portion 200 and installed along the advancing underpass. As in the step means to settle.

이러한 상부슬래브(300)는 다수개의 단위편재로 이루어지는 콘크리트 양생 구조물로 원호형태를 갖는 구조물을 이용하여 상호 접하는 상태로 설치되도록 하되, 각 단위편재로 이루어지는 상부슬래브(300)를 서로 얼기설기 엇갈리며 설치되도록 하되, 서로 접하도록 구성하는 것이 바람직하다.(도 15, 도 17 내지 도 18 참조)The upper slab 300 is to be installed in a state in contact with each other by using a structure having an arc shape as a concrete curing structure consisting of a plurality of unit ubiquitous, so that the upper slab 300 consisting of the unit ubiquitous staggered mutually installed However, it is preferable to be configured to be in contact with each other. (See Figs. 15 and 17 to 18).

또한, 상부슬래브(300)들을 각 측면으로 벽체(102)와 연결하기 위한 구성이 필요한 바, 도 16에서 보는 바와 같이 상부슬래브(300)와 상부슬래브(300) 측면간을 상호 철근(310,320)을 이용하여 연결한다. In addition, a configuration for connecting the upper slabs 300 with the wall 102 on each side is required, as shown in FIG. 16, between the upper slab 300 and the upper slab 300 sides between the reinforcing bars 310 and 320. To connect.

상기 철근(310,320)은, 하나의 상부슬래브(300) 측면에서 일직선상으로 돌출되는 철근(310)의 단부를 절곡하여 절곡부(311)를 형성하고, 이에 대응되는 철근(320)은 타 상부슬래브(300)의 측면에 요홈(330)을 형성한 후 수직상태로 형성되도록 하여, 상기 철근(310)의 절곡부(311)가 상기 철근(320)을 파지하도록 한 후, 상기 요홈(330) 내부를 몰탈 처리하여 상부슬래브(300)들의 측면 부분을 견고하게 고정할 수 있게 된다.(도 15 내지 도 16 참조)The reinforcing bars 310 and 320 are bent end portions of the reinforcing bar 310 protruding in a straight line from one side of the upper slab 300 to form a bent portion 311, and the corresponding reinforcing bar 320 is the other upper slab. After forming the groove 330 on the side of the 300 to be formed in a vertical state, the bent portion 311 of the reinforcement 310 to hold the reinforcement 320, and then inside the groove 330 By mortar treatment it is possible to firmly fix the side portions of the upper slab (see Figs. 15 to 16).

또한, 상기 상부슬래브(300)와 상부슬래브(300)가 접하는 부분의 상면으로는 방수시트 및 수밀성시트 등을 이용하여 상부슬래브(300)를 통해 유입되는 물기를 차단하는 것이 바람직하다. In addition, it is preferable to block the water flowing through the upper slab 300 by using a waterproof sheet and a watertight sheet as the upper surface of the upper slab 300 and the upper slab 300 contact.

한편, 상부슬래브(300)와 상부슬래브(300)가 원호형태를 이루며 상호 접하게 되는 중앙부분을 연결하기 위한 중앙연결부(340)는 도 11에 도시되어 있는 바와 같이 구성하게 되는데, 상기 중앙연결부(340)는 상부슬래브(300)간 접하는 부분 내부에 콘크리트로 양생 된 고정블럭(342)을 형성하고 상기 고정블럭(342)과 상부슬래브(300)간을 고정구(343)를 이용하여 연결 고정하고, 상기 고정구(343) 상단측을 몰탈(344)처리하게 된다. On the other hand, the upper slab 300 and the upper slab 300 is formed in an arc shape, the center connecting portion 340 for connecting the center portion is in contact with each other is configured as shown in Figure 11, the center connecting portion 340 ) Forms a fixed block 342 cured with concrete in a portion between the upper slab 300 and the connection between the fixed block 342 and the upper slab 300 using a fastener 343, the Mortar 344 is processed on the upper end side of the fixture 343.

이와 같이 상부슬래브(300)와 상부슬래브(300)간 접하는 중앙 부분은 상기한 중앙연결부(340)에 의해 각각 고정 연결되도록 하는데, 전술한 바와 같이 상부슬래브(300)는 상호 교호 되며 접하는 상태로 설치되므로 상기한 중앙연결부(340)는 상부슬래브(300)가 중앙부분 전체에 걸쳐, 즉 복개도로의 진행 방향에 걸쳐 형성되어야 할 것이다. As described above, the central portion in contact with the upper slab 300 and the upper slab 300 is fixedly connected to each other by the central connecting portion 340. As described above, the upper slab 300 is installed to be in contact with each other. Therefore, the center connecting portion 340 is to be formed over the entire upper portion of the upper slab 300, that is, the direction of travel to the open road.

한편, 상기 상부슬래브(300)와 벽체(102)의 상단측이 접하며 고정되어야 한다. On the other hand, the upper side of the upper slab 300 and the wall 102 should be in contact with and fixed.

상부슬래브(300)와 CIP구근(100) 및 벽체(102)의 상단간 상호 연결하는 방법은 고정식과 힌지식으로 나누어 실시가능하게 되는데, 도 12는 상부슬래브(300)와 CIP구근(100) 및 벽체(102)의 고정식 연결 방법을 도시한 것이고, 도 13 내지 도 14는 상부슬래브(300)와 CIP구근(100) 및 벽체(102)의 힌지식 연결 방법을 도시한 것이다.The method of interconnecting the upper slab 300 and the upper end of the CIP bulb 100 and the wall 102 can be implemented by dividing the fixed and hinged, Figure 12 is the upper slab 300 and the CIP bulb 100 and A fixed connection method of the wall 102 is illustrated, and FIGS. 13 to 14 illustrate a hinged connection method of the upper slab 300, the CIP bulb 100, and the wall 102.

먼저, 도 12에 도시되어 있는 상부슬래브(300)와 CIP구근(100) 및 벽체(102)간의 고정식 연결 방법에 대하여 설명한다.First, a fixed connection method between the upper slab 300 and the CIP bulb 100 and the wall 102 shown in FIG. 12 will be described.

도 12에서 보는 바와 같이 CIP구근(100) 내측으로는 벽체(102) 내부에 구비되는 철근(110)이 상방향으로 연장되도록 하고, 상부슬래브(300) 내부에 구비되는 철근(351)과 연결고정되도록 하고, 외측으로는 상부슬래브(300)의 내부에 구비되는 철근(350)이 상부슬래브(300)의 단부측으로부터 연장되어 CIP구근(100) 내부에서 상방향으로 연장된 CIP구근주철근(108)과 철근(350)이 용접 및 겹이음 등의 방법에 의해 연결 고정되도록 하게 되는데, 상기 상부슬래브(300) 단부와 CIP구근(100) 및 벽체(102) 상단간에는 상기한 CIP구근주철근(108)과 철근(110)(350)이 상호 고정되도록 하는 작업을 위해 공간(130a, 130b)이 형성되도록 구성하여야 하고, 상기 CIP구근주철근(108)과 철근(110)(350)의 고정 작업이 완료된 후에는 2차 콘크리트를 타설토록 한다.
As shown in FIG. 12, inside the CIP bulb 100, the reinforcing bar 110 provided inside the wall 102 extends upwards, and fixing and connecting the reinforcing bar 351 provided inside the upper slab 300. To the outside, the reinforcing bar 350 provided in the interior of the upper slab 300 is extended from the end side of the upper slab 300 CIP bulb main reinforcement 108 extending upward in the CIP bulb 100 And the reinforcement 350 is to be connected and fixed by welding and lap method, such as between the upper slab 300 and the upper end of the CIP bulb 100 and the wall 102 and the above CIP bulb reinforcement 108 and The spaces 130a and 130b should be configured to form the reinforcing bars 110 and 350 so as to be fixed to each other. After the fixing of the CIP bulb main reinforcing bars 108 and the reinforcing bars 110 and 350 is completed, Pouring secondary concrete.

또한 도 13 내지 도 14는 상부슬래브(300)와 CIP구근(100) 및 벽체(102)간의 힌지식 연결 방법에 대하여 도시한 것인바, 도 12는 상부슬래브(300)의 단부측이 라운딩되도록 라운드부(360)를 형성하되 그 라운드부(360)에는 원호상 감싸지는 라운드플레이트(361)가 형성된다. 13 to 14 are shown for the hinged connection method between the upper slab 300 and the CIP bulb 100 and the wall 102, Figure 12 is rounded so that the end side of the upper slab 300 rounded A round plate 361 is formed on the round part 360, wherein the round part 360 is formed in an arc shape.

한편 이와 대응되는 CIP구근(100) 및 벽체(102)의 상단면은 원호형태로 이루어지는 원호홈(140)을 형성하고 그 원호홈(140) 내주면으로 원호플레이트(141)를 고정하여, 상기 상부슬래브(300)의 라운드부(360)와 상기 원호홈(140)이 상호 접하도록 하여 상부슬래브(300)를 설치하면서 상기한 바와 같이 상부슬래브(300)와 상부슬래브(300)간 중앙 부분을 연결하는 작업이 이루어거나 상부슬래브(300)의 중앙부분을 맞추는 작업을 수행할 때 일정각도 회동 가능한 범위를 제공할 수 있어 작업의 유용성과 편리성을 제공할 수 있다. Meanwhile, the upper surfaces of the corresponding CIP bulb 100 and the wall 102 form an arc groove 140 having an arc shape, and fix the arc plate 141 to the inner circumferential surface of the arc groove 140, thereby allowing the upper slab to be fixed. Round part 360 of the 300 and the arc groove 140 to be in contact with each other while installing the upper slab 300 to connect the central portion between the upper slab 300 and the upper slab 300 as described above When the work is made or the work to fit the center portion of the upper slab 300 can provide a range that can be rotated at a certain angle can provide the usefulness and convenience of the work.

한편, 상기 원호플레이트(141)가 CIP구근(100) 상면상으로 돌출되도록 하는 이유는, 외부의 방수시트(370)가 손상되어 지하수가 유입되는 것을 방지하기 위함이며, 상기 벽체(102) 상면상의 돌출된 원호플레이트(141)와 전면에 설치되는 브라켓(142)은 상부슬래브(300)의 회동시 변형방지 및 상부슬래브(300)의 탈락을 방지하기 위함이다. Meanwhile, the reason why the arc plate 141 protrudes on the upper surface of the CIP bulb 100 is to prevent the external waterproof sheet 370 from being damaged and inflow of groundwater, and on the upper surface of the wall 102. The protruding arc plate 141 and the bracket 142 installed on the front surface are to prevent deformation of the upper slab 300 and to prevent the upper slab 300 from falling off.

아울러 상부슬래브(300)가 일정각도 범위내에서 회동되어질 때 상부슬래브(300)와 CIP구근(100)간 외측면을 통해 외부로부터 물기 등이 스며들 우려가 있게 되는데, 도 12에서 보는 바와 같이 상부슬래브(300)의 외측면으로부터 CIP구근(100)의 상단측 외측면을 커버하게 되는 방수시트(370)를 구성하고, 상기 상부슬래브(300)의 단부 외측면과 상기 CIP구근(100)의 상단 외측 부분의 경계부분에는 상기 방수시트(370)가 자바라형태를 이루도록 하여 상부슬래브(300)의 회동시 유연성을 갖도록 하였다. In addition, when the upper slab 300 is rotated within a certain angle range, there is a risk that water, such as moisture from the outside through the outer surface between the upper slab 300 and the CIP bulb 100, seep, as shown in Figure 12 Comprising a waterproof sheet 370 to cover the upper side outer surface of the CIP bulb 100 from the outer surface of the slab 300, the outer end surface of the upper slab 300 and the upper end of the CIP bulb 100 The waterproof portion 370 has a bellows shape at the boundary portion of the outer portion to have flexibility when the upper slab 300 rotates.

한편, 상기 원호홈(140)내의 원호플레이트(141)와 커버플레이트(161)간 마찰작용을 돕고, 녹이 발생 되는 것을 방지하기 위해 원호홈(140) 내부에 윤할제를 주입하는 것이 바람직하다.
On the other hand, it is preferable to inject a lubricant into the arc groove 140 to help the friction action between the arc plate 141 and the cover plate 161 in the arc groove 140, to prevent rust.

또한 이러한 방법과는 달리 도 14에서 보는 바와 같은 힌지 방식을 채택할 수 있다.In addition, unlike the above method, a hinge method as shown in FIG. 14 may be adopted.

예를 들면 도 14에서 보듯이 벽체(102) 상면에 반원형태의 고정부재(150)를 한조로 구성하여 이격되도록 고정하고, 상기 고정부재(150) 사이에 끼워지면서 힌지(381)에 의해 회동 가능하도록 구성하는 회동부재(380)를 상기 상부슬래브(300)의 단부측에 삽입 고정하여, 상부슬래브(300)의 설치시 벽체(102) 상면과 접하면서도 상부슬래브(300)간의 중앙 부분의 접합 과정에서의 용이성을 확보할 수 있게 된다.
For example, as shown in FIG. 14, the semi-circular fixing member 150 is formed in a pair on the upper surface of the wall 102 and fixed to be spaced apart, and is pivotable by the hinge 381 while being sandwiched between the fixing members 150. Rotating member 380 is configured to be inserted into and fixed to the end side of the upper slab 300, the process of joining the central portion between the upper slab 300 while contacting the upper surface of the wall 102 when installing the upper slab 300 Ease of use can be secured.

환기탑 설치 단계 ; Installation of ventilation tower; S50S50

본 단계는 전술한 바와 같이 상부슬래브(300)의 설치 시공이 완료된 후, 도 17 내지 도 18에서와 같은 환기탑(400)을 설치하여, 복개 지하도 내부의 혼탁한 공기를 외부로 배출하도록 하는 것이 바람직하다.In this step, after the installation of the upper slab 300 is completed as described above, it is preferable to install the ventilation tower 400 as shown in FIGS. 17 to 18 to discharge the cloudy air inside the covered underpass to the outside. Do.

상기한 환기탑(400)의 경우, 일반적으로 알려진 설치 공법에 의해 설치할 수 있을 것이다.In the case of the ventilation tower 400, it may be installed by a generally known installation method.

예를 들면 복개 지하도의 길이방향으로 형성되는 상부슬래브(300)들의 상단 부분에 환기탑(400)이 설치될 수 있는 영역이 관통되도록 절개 시공한 후, 별도로 제작되는 환기탑(400)을 얹어 설치하거나 현장에서 직접 제작하는 방법으로 시공할 수 있다.
For example, after cutting the construction to penetrate the area where the ventilation tower 400 can be installed in the upper portion of the upper slab 300 formed in the longitudinal direction of the abdominal underpass, and install the ventilation tower 400 is produced separately or installed on-site Can be constructed by direct production method from.

한편, 환기탑(400)이 설치되는 부위에 해당되는 상부슬래브(300) 부위는 전술한 바와 같이 관통되도록 절개 시공하게 되는데 환기탑(400)이 설치되기 전에 그 절개되는 부위측을 횡단하는 형강(600)을 다수개 설치하여, 서로 마주보며 형성되는 상부슬래브(300)와 상부슬래브(300)간을 지지하도록 하는 것이 바람직하다. On the other hand, the upper slab 300 corresponding to the site where the ventilation tower 400 is installed is to be cut so as to penetrate as described above, before the ventilation tower 400 is installed, the section steel 600 to cross the side of the section to be cut By installing a plurality, it is preferable to support between the upper slab 300 and the upper slab 300 formed to face each other.

이와 같이 형강(600)에 의해 상부슬래브(300)간의 지지가 이루어진 후, 환기탑(400)이 설치에 따라 환기탑(400)과 상부슬래브(300) 상면간 연결 작업이 완료되면, 상기한 형강(600)은 철거하도록 한다.
After the support between the upper slab 300 is made by the section steel 600 as described above, when the connection between the top of the ventilation tower 400 and the upper slab 300 is completed according to the installation of the ventilation tower 400, the section steel 600 Should be demolished.

아울러, 상부슬래브(300)의 상면측, 상부슬래브(300)간의 측면 연결 부위와 상부슬래브(300)와 상부슬래브(300)간 단부측이 접하게 되는 중앙 부분에 각각 방수시트(370)와 수밀성방수제(도면부호 미기재) 등을 반복 실시하여 방수처리를 하게 된다.In addition, the upper surface side of the upper slab 300, the side connection portion between the upper slab 300 and the end portion between the upper slab 300 and the upper slab 300 is in contact with the water resistant sheet 370 and the watertight waterproofing agent, respectively. (Not shown) repeatedly performs waterproofing.

상기의 과정을 통해 완성된 복개 지하도 형태를 갖출 수 있다.Through the above process can be completed in the form of a covered underpass.

상기와 같은 단계를 거쳐, 사면이 존재하는 영역에서 복개 지하도의 상부 및 벽체 시공이 완료되면, 복개 지하도의 상면측을 복토하여 최초 시공 단계에서 복개 지하도를 형성하기 위해 대절토하였던 영역을 원상 복귀되도록 한다. After completing the above steps, when the upper and wall construction of the covered underpass is completed in the area where the slope exists, the upper surface side of the covered underpass is covered to return the area that was cut through to form the covered underpass in the initial construction stage. do.

이때, 기반암층의 경우 암을 절취하게 되는데, 암 절취시 무진동 또는 미진동의 방법을 이용, 굴착하여 구조물에 피해가 없도록 하여야 하며, 하부슬래브(500)를 설치할 필요없이 도로에 아스팔트 포장 후 기타 보도나 난간, 전기등의 내부 시설물을 설치하여 마무리할 수 있다.
At this time, in the case of the base rock layer, the cancer is cut off, and when cutting the arm, it should be excavated using no vibration or non-vibration method so as not to damage the structure, and other sidewalks after asphalt paving on the road without installing the lower slab 500. It can be finished by installing internal facilities such as railings and electricity.

하부 슬래브 설치단계 - Lower Slab Installation Steps- S60S60

본 발명을 이용하여 복개도로를 시공할 때 그 시공되는 지역이 토사로 이루어져 있을 경우에는 하부슬래브를 설치하여야 한다. When constructing the open road using the present invention, when the construction area is made of earth and sand, the lower slab should be installed.

따라서 본 단계는 복개도로로 시공되는 지역의 성질이 토사등으로 이루어져 있을 때, 상술한 각 단계를 복개 지하도의 형태를 형성한 후 복개 지하도의 하부측의 하부슬래브(500)를 설치하여 마무리 하기 위한 단계로 먼저, 기초바닥이 양생된 후 하부슬래브 철근을 조립하고 콘크리트를 타설하며, 양생 후 아스팔트를 시설함과 아울러 기타 내부 시설물(보도, 난간, 전기 등)을 설치하여 완성된 복개도로를 이룰 수 있다.
Therefore, this step is a step for finishing by installing the lower slab 500 of the lower side of the abdominal underpass after forming the shape of the abdominal underpass when each of the above-described step is composed of earth and sand, etc. First, after the foundation floor is cured, the lower slab reinforcing bars are assembled and concrete is poured. After curing, asphalt is installed and other internal facilities (walkway, railing, electricity, etc.) can be installed to achieve a completed road. .

100; CIP구근 101; 홀
102; 벽체 108; CIP구근 주철근
110; 철근 120; 띠철근
130a,b; 공간 140; 원호홈
141; 원호플레이트 142; 브라켓
150; 고정부재 200; 기둥부
210; 하부거더 220; 지지부
221; 고정부재 222; PC강봉
223; 횡간연결강관 224; 평플레이트
225; 무수축패드 300; 상부슬래브
310, 320; 철근 311; 절곡부
330; 요홈 340; 중앙연결부
342; 고정블럭 343; 고정구
344; 몰탈 350, 351; 철근
360; 라운드부 361; 라운드플레이트
370; 방수시트 380; 회동부재
381; 힌지 400; 환기탑
500; 하부슬래브 600; 형강
100; CIP bulb 101; hall
102; Wall 108; CIP Bulb Cast Iron
110; Rebar 120; Steel bars
130a, b; Space 140; Home
141; Arc plate 142; Brackets
150; Fixing member 200; Column
210; Lower girder 220; Support
221; Fixing member 222; PC steel bar
223; Transverse connecting steel pipe 224; Flat plate
225; Non-contraction pad 300; Upper slab
310, 320; Rebar 311; Bent portion
330; Groove 340; Center connection
342; Fixed block 343; Fixture
344; Mortar 350, 351; rebar
360; Round part 361; Round Plate
370; Waterproof sheet 380; Rotating member
381; Hinge 400; Ventilation tower
500; Lower slab 600; Section steel

Claims (9)

복개 지하도를 굴착 시공하는 방법에 있어서,
복개 지하도 영역에서 상부슬래브(300)가 설치되는 끝단으로부터 토공 굴착이 사면을 따라 계단식으로 토공 굴착하고, 복개지하도 영역의 폭을 이루는 양단측을 따라 CIP구근(100)이 삽입되어 내벽체로 형성될 수 있도록 홀(101)을 천공하는 토공굴착 및 CIP 천공 단계(S10),
상기 토공굴착 및 CIP 천공단계(S10)를 거쳐 CIP구근(100)의 삽입이 완성되면, CIP구근(100)의 내측 방향으로의 벽체부 터파기 작업 후, 상기 CIP구근(100)으로부터 외측방향으로 Earth Anchor를 형성하는 벽체부 시설단계(S20),
하부에 양생되는 하부거더(210)로부터 수직상방향으로 기둥부(200)를 구성하고, 상기 기둥부(200)의 내측으로는 상부슬래브(300)를 지지하기 위한 지지부(220)를 구성하는 기둥부 시설단계(S30),
다수개의 단위편재로 이루어지는 콘크리트 양생 구조물로 원호형태를 갖는 구조물을 이용하여 상호 접하는 상태로 설치되도록 하되, 각 단위편재로 이루어지는 상부슬래브(300)를 서로 얼기설기 엇갈리며 설치되도록 하는 상부 슬래브 설치 단계(S40),
상기 상부슬래브 설치단계(S40)에 의해 설치 시공되는 상부슬래브(300)들에서 선택되는 영역을 관통하며 복개 지하도 내부의 공기를 외부로 순환 배출되도록 하는 환기탑 설치 단계(S50)로 이루어지는 것을 특징으로 하는 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
In the method of excavating the undercover underpass,
Earthwork excavation is stepwise excavated along the slope from the end where the upper slab 300 is installed in the covered underpass area, and the CIP bulb 100 is inserted along both end sides forming the width of the underpass area to be formed as an inner wall. Earth excavation and CIP drilling step (S10), which drills the hole 101 so that,
When the insertion of the CIP bulb 100 through the earth excavation and CIP drilling step (S10) is completed, after the wall part dig in the inward direction of the CIP bulb 100, outward from the CIP bulb 100 Wall unit facility step (S20) to form the Earth Anchor,
The pillar 200 constitutes a vertical portion from the lower girder 210 which is cured in the lower portion, and the pillar constituting the support portion 220 for supporting the upper slab 300 inside the pillar portion 200. Secondary facility stage (S30),
The upper slab installation step to be installed in a state in contact with each other by using a structure having an arc shape as a concrete curing structure consisting of a plurality of unit pieces, the upper slab 300 made of each unit piece alternately freezing each other (S40) ),
Characterized in that it comprises a ventilation tower installation step (S50) penetrating the area selected from the upper slab 300 is installed by the upper slab installation step (S40) and circulated to discharge the air in the covered underpass to the outside Method of construction on the open road in slope area or urban flat area.
제 1 항에 있어서,
상기 지지부(220)는 단면상 "○"자를 이루며 중공(中空) 형태를 갖는 한조의 고정부재(221)를 상호 대향 되며 활개 되는 형태를 갖도록 기둥부(200) 내면에 고정되도록 하고, 상기 고정부재(221)와 고정부재(221)간을 PC강봉(222)을 이용하여 연결 고정하는 것을 포함하는 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
The method of claim 1,
The support portion 220 is fixed to the inner surface of the pillar portion 200 so as to have a form in which a pair of fixing members 221 having a hollow shape in a cross-section and having a “○” shape in cross section and facing each other. 221) and the method of construction in the open road in the slope presence area or the urban flat area including the fixing between the fixing member (221) using a PC steel bar (222).
제 2 항에 있어서,
상기 한 조의 고정부재(221)와 측면에 이격되어 설치되는 또 다른 한 조의 고정부재(221)간을 횡간연결강관(223)을 이용하여 연결 고정하는 것을 포함하는 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
The method of claim 2,
In the presence of the slope or the urban flat area comprising the connection between the fixing member 221 and the other set of fixing members 221 which are installed spaced apart from the side by using the transverse connection steel pipe 223 How to construct a road on the road.
제 2 항 내지 제 3 항 중 어느 한 항에 있어서,
지지부(220)의 고정부재(221)와 횡간연결강관(223) 상측에 불연속성 평플레이트(224)를 고정하고, 상기 평플레이트(224) 상면에 무수축패드(225)를 구비하여, 상기 무수축패드(225) 상면에 상부슬래브(300) 저면이 접하며 지지되도록 하는 것을 포함하는 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
The method according to any one of claims 2 to 3,
The discontinuous flat plate 224 is fixed on the fixing member 221 and the transverse connecting steel pipe 223 of the support unit 220, and the non-contraction pad 225 is provided on the flat plate 224. Method of construction in the open road in the slope presence area or urban flat area comprising the upper surface of the upper slab (300) in contact with the upper surface of the pad (225).
제 1 항에 있어서,
상기 상부슬래브(300)의 각 측면을 연결하기 위해, 상부슬래브(300)와 상부슬래브(300) 측면간을 상호 철근(310,320)을 이용하여 연결하되, 하나의 상부슬래브(300) 측면에서 일직선상으로 돌출되는 철근(310)의 단부를 절곡하여 절곡부(311)를 형성하고, 이에 대응되는 철근(320)은 타 상부슬래브(300)의 측면에 요홈(330)을 형성한 후 돌출되는 부분이 수직상태로 형성되도록 하여, 상기 철근(310)의 절곡부(311)가 상기 철근(320)을 파지하도록 한 후, 상기 요홈(330) 내부를 몰탈 처리하여 상부슬래브(300)들의 측면 부분이 고정 연결되도록 하는 것을 포함하는 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
The method of claim 1,
In order to connect each side of the upper slab 300, between the upper slab 300 and the upper slab 300 side by using mutual reinforcement (310,320), but in a straight line on one side of the upper slab 300 The bent portion 311 is formed by bending an end of the reinforcing bar 310 protruding into the reinforcing bar 310, and the corresponding reinforcing bar 320 forms a recess 330 on the side of the other upper slab 300, and then protrudes. By forming in a vertical state, the bent portion 311 of the reinforcement 310 to hold the reinforcement 320, and then mortar the inside of the groove 330 to fix the side portions of the upper slab (300) A method of constructing a covered road in a slope present zone or downtown flat area comprising connecting.
제 1 항에 있어서,
상기 상부슬래브(300)와 상부슬래브(300)가 원호형태를 이루며 상호 접하게 되는 중앙부분을 연결하기 위한 것으로, 상부슬래브(300)간 접하는 부분 내부에 콘크리트로 양생 된 고정블럭(342)을 형성하고 상기 고정블럭(342)과 상부슬래브(300)간을 고정구(343)를 이용하여 연결 고정하고, 상기 고정구(343) 상단측을 몰탈(344)처리하여서 되는 중앙연결부(340)에 의해 상부슬래브(300)와 상부슬래브(300)간 단부측으로 상호 접하는 중앙부분을 연결하도록 하는 것을 포함하는 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
The method of claim 1,
The upper slab 300 and the upper slab 300 to form a circular arc shape to connect the center portion to be in contact with each other, forming a fixed block 342 cured with concrete inside the portion between the upper slab 300 and The upper slab is connected to and fixed between the fixing block 342 and the upper slab 300 by using a fastener 343, and a central connection part 340 is formed by mortar 344 on the upper end of the fastener 343. 300) and the construction method of the open road in the slope presence area or the urban flat area comprising connecting the central portion in contact with the end side between the upper slab (300).
제 1 항에 있어서,
상기 CIP구근(100) 상면으로 상기 상부슬래브(300)의 단부측이 얹혀지며 고정 지지되도록 하기 위해, 상기 내측으로는 벽체(102) 내부의 철근(110)이 상방향으로 연장되도록 하여, 상기 상부슬래브(300) 내부에 구비되는 철근(351)과 연결 고정되도록 하고, 외측으로는 상부슬래브(300) 내부에 구비되는 철근(351)의 단부측으로부터 연장되어 CIP구근(100) 내부에서 상방향으로 연결된 철근(108)(350)을 연결 고정한 후, 2차콘크리트를 타설하여 고정되도록 하는 것을 포함 하는 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
The method of claim 1,
In order for the end side of the upper slab 300 to be mounted and fixedly supported on the upper surface of the CIP bulb 100, the reinforcing bar 110 inside the wall 102 extends upwardly, and the upper portion It is connected to the reinforcing bar 351 provided in the slab 300, and extends from the end side of the reinforcing bar 351 provided in the upper slab 300 to the outside in the CIP bulb 100 in the upward direction After connecting and fixing the connected reinforcing bars (108) (350), the method of construction on the road in the slope presence area or urban flat area comprising the second concrete to be fixed.
제 1 항에 있어서,
상기 상부슬래브(300)의 단부측이 라운딩되도록 라운드부(360)를 형성하되 그 라운드부(360)에는 원호상 감싸지는 라운드플레이트(361)가 형성되도록 하고, 이와 대응되는 CIP구근(100) 및 벽체(102)의 상단면은 원호형태로 이루어지는 원호홈(140)을 형성하고 상기 원호홈(140) 내주면으로 원호플레이트(141)를 고정하여, 상기 상부슬래브(300)의 라운드부(360)와 상기 원호홈(140)이 상호 접하도록 하여 상부슬래브(300)를 설치하는 것을 포함하는, 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
The method of claim 1,
The round part 360 is formed so that the end side of the upper slab 300 is rounded, but the round part 360 is formed with a circular plate 361 which is formed in an arc shape, and the corresponding CIP bulb 100 and The upper surface of the wall 102 forms an arc groove 140 having an arc shape, and fixes the arc plate 141 to the inner circumferential surface of the arc groove 140 to form a round portion 360 of the upper slab 300. Method of constructing the open road in the slope existing area or the urban flat area, including installing the upper slab 300 so that the arc groove 140 is in contact with each other.
제 1 항에 있어서,
상기 벽체부 시설단계(S20)에 의해 시설되는 벽체(102) 상면에 반원형태의 고정부재(150)를 한조로 구성하여 이격되도록 고정하고, 상기 고정부재(150) 사이에 끼워지면서 힌지(381)에 의해 회동 가능하도록 구성하는 회동부재(380)를 상기 상부슬래브(300)의 단부측에 삽입 고정하여, 상부슬래브(300)의 설치시 벽체(102) 상면과 접하면서도 상부슬래브(300)간의 중앙 부분의 접합 과정에서의 용이성이 확보되도록 하는 것을 포함하는, 사면 존재 영역 또는 도심 평지 영역에서의 복개도로 시공 방법.
The method of claim 1,
The semi-circular fixing member 150 is formed in a pair on the upper surface of the wall 102 to be installed by the wall part installation step (S20) and fixed to be spaced apart, and the hinge 381 is fitted between the fixing members 150. Rotating member 380 configured to be rotatable by insertion is fixed to the end side of the upper slab 300, the center between the upper slab 300 while contacting the upper surface of the wall 102 when the upper slab 300 is installed A method of constructing a covered road in a slope present area or a downtown flat area, comprising ensuring ease of joining of parts.
KR1020110048411A 2011-05-23 2011-05-23 A slope territory or heat of city level ground road construction work method KR101109724B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110048411A KR101109724B1 (en) 2011-05-23 2011-05-23 A slope territory or heat of city level ground road construction work method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110048411A KR101109724B1 (en) 2011-05-23 2011-05-23 A slope territory or heat of city level ground road construction work method

Publications (1)

Publication Number Publication Date
KR101109724B1 true KR101109724B1 (en) 2012-02-24

Family

ID=45839954

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110048411A KR101109724B1 (en) 2011-05-23 2011-05-23 A slope territory or heat of city level ground road construction work method

Country Status (1)

Country Link
KR (1) KR101109724B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759367A (en) * 2017-02-24 2017-05-31 中铁大桥勘测设计院集团有限公司 The temporary road laying method of open-cut foundation ditch

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050091355A (en) * 2004-03-12 2005-09-15 주식회사 후레씨네코리아 A tunnel structure and method for constructing of it
KR100701633B1 (en) * 2005-06-01 2007-03-30 윤석렬 Load dispersing plate for supporting central part of a twin tunnel and a construction method of a twin tunnel using the load dispersing plate
KR20100088974A (en) * 2009-02-02 2010-08-11 바스코코리아(주) Tunnel the upside reinforced structure and reinforcement method
KR101033621B1 (en) * 2009-03-30 2011-05-11 삼성물산 주식회사 Construction method for duct structure in tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050091355A (en) * 2004-03-12 2005-09-15 주식회사 후레씨네코리아 A tunnel structure and method for constructing of it
KR100701633B1 (en) * 2005-06-01 2007-03-30 윤석렬 Load dispersing plate for supporting central part of a twin tunnel and a construction method of a twin tunnel using the load dispersing plate
KR20100088974A (en) * 2009-02-02 2010-08-11 바스코코리아(주) Tunnel the upside reinforced structure and reinforcement method
KR101033621B1 (en) * 2009-03-30 2011-05-11 삼성물산 주식회사 Construction method for duct structure in tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759367A (en) * 2017-02-24 2017-05-31 中铁大桥勘测设计院集团有限公司 The temporary road laying method of open-cut foundation ditch

Similar Documents

Publication Publication Date Title
KR101274974B1 (en) Earth retaining wall and construction method thereof
KR100640716B1 (en) Precast concrete block for cantilever retaining wall and construction method using the same
KR20070072417A (en) Panel module for tunnel lining and method of tunnel lining using the same
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
JP6186267B2 (en) How to build an underground tunnel
KR101118263B1 (en) Rain retaining facility and constructing method thereof using precast concrete block
KR20080061580A (en) Precast concrete file and method for constructing thereof
JP2000008394A (en) Construction method for underground structure such as underground pit for installation of parking lot
KR101187369B1 (en) Cip use of underground motorways construction work method
KR20120037212A (en) Excavation tunnel constructing method using vertical side wall and arch celling, and excavation tunnel using vertical side wall and arch celling constructed by this
KR100806867B1 (en) Steel pipe roof assembly and the construction method for Tunnel using thereof
KR101632840B1 (en) Construction method of underground road way having drain structure of temporary and permanent wall
KR101109724B1 (en) A slope territory or heat of city level ground road construction work method
KR101169437B1 (en) The installation structure and construction method using a trough
KR20120122024A (en) Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts.
JP5280150B2 (en) Yamadome retaining wall and method of forming Yamadome retaining wall
KR101234270B1 (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR200420394Y1 (en) Precast concrete block for cantilever retaining wall
KR100753140B1 (en) Steel pipe roof assembly and the construction method for tunnel using thereof
KR200390421Y1 (en) Top-down substructure by deck suspension
JP2011157719A (en) Earth retaining method
KR101285987B1 (en) Improved Compound Roof Tunnel Method
KR101524302B1 (en) Construction method for underground structure without temporary structure
KR20200003488A (en) Underground road using self-supporting pile wall with temporary wall and its construction method
JP2515227B2 (en) Installation method of cast-in-place concrete foundation and precast concrete wall slab

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee