KR101096304B1 - The anchor with helix and the vegetation construction method with the anchor and egetation mat - Google Patents

The anchor with helix and the vegetation construction method with the anchor and egetation mat Download PDF

Info

Publication number
KR101096304B1
KR101096304B1 KR1020110016891A KR20110016891A KR101096304B1 KR 101096304 B1 KR101096304 B1 KR 101096304B1 KR 1020110016891 A KR1020110016891 A KR 1020110016891A KR 20110016891 A KR20110016891 A KR 20110016891A KR 101096304 B1 KR101096304 B1 KR 101096304B1
Authority
KR
South Korea
Prior art keywords
anchor
vegetation mat
wire
fixing
mat
Prior art date
Application number
KR1020110016891A
Other languages
Korean (ko)
Inventor
윤정배
윤홍기
윤택규
Original Assignee
윤정배
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤정배 filed Critical 윤정배
Priority to KR1020110016891A priority Critical patent/KR101096304B1/en
Application granted granted Critical
Publication of KR101096304B1 publication Critical patent/KR101096304B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G13/00Protecting plants
    • A01G13/02Protective coverings for plants; Coverings for the ground; Devices for laying-out or removing coverings
    • A01G13/0256Ground coverings
    • A01G13/0268Mats or sheets, e.g. nets or fabrics
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G24/00Growth substrates; Culture media; Apparatus or methods therefor
    • A01G24/40Growth substrates; Culture media; Apparatus or methods therefor characterised by their structure
    • A01G24/44Growth substrates; Culture media; Apparatus or methods therefor characterised by their structure in block, mat or sheet form
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • E02D5/801Ground anchors driven by screwing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P60/00Technologies relating to agriculture, livestock or agroalimentary industries
    • Y02P60/40Afforestation or reforestation

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental Sciences (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Toxicology (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PURPOSE: An anchor with a spiral unit and a method of constructing using the anchor and a vegetation mat are provided to enable easy installation of an anchor, firm installation and fixation of a vegetation mat and prevent the separation of the vegetation mat. CONSTITUTION: An anchor(10) comprises a shaft(11), and a spiral unit(12). The shaft is formed in a cylinder shape so that the central part of the shaft is hollow. A plurality of fixing holes(11b) are formed on the upper surface of the shaft. The spiral unit is protruded along the outer circumferential surface of the fixing hole in a spiral shape.

Description

나선부를 가지는 앵커 및 그 앵커와 식생매트를 이용한 녹화 공법{the anchor with helix and the vegetation construction method with the anchor and egetation mat}Anchor with helix and the vegetation construction method with the anchor and egetation mat}

본 발명은 나선부를 가지는 앵커 및 그 앵커와 식생매트를 이용한 녹화 공법으로, 길이 방향을 따라 내부가 관통된 원통형의 삽입축을 구성하고, 그 삽입축 상부 측면에 관통된 고정공을 다수개 형성하며, 그 고정공 하부의 외주연을 따라 스파이럴 형상으로 돌출된 나선부를 일체로 형성하는 앵커가 구비되어, 별도의 와이어를 상기 고정공으로 끼워, 와이어 양단이 상부로 돌출되게 조립한 다음, 정리된 시공지에 드릴류를 이용해서 앵커를 지면 하부로 설치하고, 각 와이어 양단은 지면 상부로 돌출되게 다수개 설치하며, 시공지에 식생매트를 포설하고, 앞서 돌출된 와이어는 식생매트 상부로 돌출되게 하며, 상기 식생매트 상부에 고정망을 격자 구조로 설치하고, 앞서 돌출된 와이어를 고정망에 고정하며, 전체적으로 흙을 포설함으로써, 앵커와 식생매트를 이용한 녹화 공법이 완료되어, 앵커의 설치가 빠르고 용이하며, 그 설치 구조에 의해 식생매트의 설치 및 고정이 견고하고, 외부 환경에도 식생매트의 이탈을 방지하여, 다양한 시공지에 녹화 시공을 적용할 수 있는 것이다.
The present invention is a greening method using an anchor having a spiral portion and its anchor and vegetation mat, and constitutes a cylindrical insertion shaft penetrating the inner side in the longitudinal direction, and forms a plurality of fixing holes penetrating the upper side of the insertion shaft, An anchor is formed to integrally form a spiral portion protruding in a spiral shape along the outer circumference of the lower part of the fixing hole. A separate wire is inserted into the fixing hole, and both ends of the wire are assembled to protrude upwards, and then drilled in the assembled construction paper. Using anchors to install the anchor to the bottom of the ground, each end of each wire is installed a plurality of protruding to the top of the ground, install a vegetation mat in the construction site, the wire protruding above to protrude above the vegetation mat, the vegetation mat By installing a fixed net on the upper part of the grid structure, fixing the wires projecting above the fixed net, and laying soil as a whole, The mating method is completed, and anchor installation is quick and easy. The installation structure makes the installation and fixation of the vegetation mat secure and prevents the departure of the vegetation mat to the external environment. You can do it.

일반적으로 식생매트(vegetation mat, seed mat)는, 종자를 가진 시트(짚, 섬유망, 부직포 등)와 침식방지매트가 일체된 구조를 가지며, 이러한 식생매트는 주로 사면지에 포설되어, 포함된 종자가 자라면서, 침식방지매트에 의해 사면지의 흙이 유실, 침식되는 것을 방지하는 녹화 작업에 많이 이용되고 있다.In general, vegetation mat (vegetation mat, seed mat) has a structure in which the seed sheet (straw, fiber, non-woven fabric, etc.) and the erosion prevention mat is integrated, such vegetation mat is mainly installed on the slope paper, As it grows, the erosion prevention mat is used for a variety of greening operations to prevent soil and erosion of slope paper.

또한, 이러한 식생매트는 기존 많이 적용하는 사면지, 즉, 도로변, 택지개발지구, 절성토 비탈면 등의 사면 녹화에 사용하고, 또한, 최근에는 하천 및 하천 주변의 토양침식 및 토양침식을 방지하기 위해서 사용되어, 하천 제내지 사면, 하천 제외지 고수/저수 호안 사면, 하천 고수부지 녹화 등에 적용함은 물론, 기존 하천에 많이 적용되던 콘크리트를 대신하여 시공하거나, 또는, 개비온 매트리스로 시공된 호안을 녹화하는데 적용하며, 그외에도 저류조 비탈면에 적용하거나, 또, 배수로 등에 적용할 수 있다.
In addition, these vegetation mats are used for slope greening of existing slopes, that is, roadsides, residential land development zones, and cut slopes, and more recently, to prevent soil erosion and soil erosion around rivers and streams. It is used to apply to river sediment slopes, river exclusion coarse water / reservoir revetment slopes, river coarse grounds, etc. In addition, it can be applied to storage slopes or drainage.

아울러, 상기 식생매트를 이용한 녹화 공법을 보면, 정리한 사면지에 식생매트를 포설하고, 그 포설된 식생매트를 고정하는 과정으로 완료하는데, 포설한 식생매트의 고정은, 포설한 식생매트의 상부를 네트(메시) 구조의 고정 네트를 포설하고, 그 상부에서 핀이나 앵커 등의 고정수단으로 박아 넣어 고정하되, 고정수단의 상단은 고정네트에 고정되고, 고정수단의 하단은 식생매트를 통과하여, 그 하부까지 박혀서 식생매트가 사면지에 고정될 수 있도록 시공한다.
In addition, in the greening method using the vegetation mat, the vegetation mat is laid on the arranged slope and the process is completed by fixing the vegetation mat installed, the installation of the vegetation mat is installed, the upper part of the vegetation mat Laying a fixing net of the net (mesh) structure, and fixed by driving it into the fixing means such as pins or anchors from the top, the upper end of the fixing means is fixed to the fixing net, the lower end of the fixing means passes through the vegetation mat, It is embedded to its lower part and constructed so that the vegetation mat can be fixed on the slope.

앞서 설명한 식생매트를 고정하는 고정수단은 그 끝이 핀 구조를 가지는 핀 형식과, 끝이 측면으로 돌출된 구조의 앵커 형식이 있으며, 핀 형식의 예를 보면, 국내특허공개 제2009-0014058에는 ‘ㄷ’자 형태의 앵커 핀을 박아넣어 침식방지매트와 앵커매트를 고정하는 구조를 가지는 ‘토목섬유 보강커튼 월 구조 및 녹화공법’에 대해 게시되어 있다.The fixing means for fixing the vegetation mat described above has a pin type having a pin structure at its end, and an anchor type having a structure at which the tip protrudes laterally. For example, the Korean Patent Publication No. 2009-0014058 It is posted about 'geotextile reinforced curtain wall structure and greening method' that has a structure to fix the erosion prevention mat and anchor mat by injecting '-' type anchor pin.

또한, 식생매트를 고정하는 고정수단 중에서 앵커 형식을 가지는 두 가지 예시를 보면, 첫 번째로, 국내특허공개 제2009-0087775호에는 사각판상과 날개부를 가지는 본체와, 철선와이어과, 원통 형상의 보조금속캡으로 구성하는 ‘법면의 녹화구조에 사용되는 철판앵커 고정장치’에 대해 게시되어 있고, 국내실용신안등록 제0419598혼에는, 하단에 테이퍼부를 가지는 볼트부와 상기 볼트부 상단에 지지파이프와 매트지지구가 순차로 끼움되어 구성하는 ‘식생매트 지지구’에 대해 게시되어 있다.
In addition, when looking at two examples having an anchor type among the fixing means for fixing the vegetation mat, firstly, Korean Patent Publication No. 2009-0087775 discloses a main body having a rectangular plate shape and a wing, a wire wire, a cylindrical auxiliary metal It is published about the 'iron plate anchor fixing device used in the greening structure of the surface' consisting of a cap, the domestic utility model registration No. 0419598 horn, the bolt portion having a tapered portion at the bottom and the support pipe and mat paper at the upper end of the bolt portion It is posted about the Vegetation Mat Support, which consists of the earth being inserted one after another.

그러나 기존 식생매트를 사용한 녹화 공법에서, 식생매트를 고정하는 고정수단이 핀 형식의 경우에는, 핀 형식의 고정수단은 지반에 박히는 부분이 핀 구조이기 때문에, 박히더라도 외력에 의해 빠질 우려가 크고, 또한, 핀 형식의 고정 수단은 앵커 형식의 고정수단보다 박히는 길이가 길어야 하고, 또한, 지반이 경질의 경우에는 박을 때, 힘을 주어 박아야 하므로, 핀이 변형될 우려가 큰 문제점이 있었다.
However, in the greening method using the conventional vegetation mat, when the fixing means for fixing the vegetation mat is a pin type, the pin-type fixing means has a pin structure, so there is a high risk of falling out due to external force even if it is stuck. In addition, the pin-type fixing means has a longer length to be nailed than the anchor-type fixing means, and, in the case of hard ground, the force must be applied when it is driven, there is a big problem that the pin is deformed.

또한, 기존 식생매트를 사용한 녹화 공법에서, 식생매트를 고정하는 고정수단이 앵커 형식의 경우에는, 설치를 위해서 지반을 미리 천공해야 하므로, 천공 기계와 천공하는데 인력과 시간이 소모되며, 또, 식생매트와 고정 매트를 포설한 다음에, 천공된 곳을 파악하여 설치된 식생매트 하부에 위치된 고정 수단을 찾아서 고정 매트에 고정해야 하기 때문에 작업성이 떨어지는 문제점이 있었다.
In addition, in the greening method using the existing vegetation mat, when the fixing means for fixing the vegetation mat is anchor type, the ground must be drilled in advance for installation, so manpower and time are required to drill the boring machine and the vegetation. After laying the mat and the fixing mat, there was a problem that the workability is inferior because it is necessary to find the fixing means located on the lower portion of the vegetation mat installed by identifying the perforated place.

따라서 본 발명은 상기의 문제점을 해결하고자, 길이 방향을 따라 내부가 관통된 원통형의 삽입축을 구성하고, 그 삽입축 상부 측면에 관통된 고정공을 다수개 형성하며, 그 고정공 하부의 외주연을 따라 스파이럴 형상으로 돌출된 나선부를 일체로 형성하는 앵커가 구비되어, 별도의 와이어를 상기 고정공으로 끼워, 와이어 양단이 상부로 돌출되게 조립한 다음, 정리된 시공지에 드릴류를 이용해서 앵커를 지면 하부로 설치하고, 각 와이어 양단은 지면 상부로 돌출되게 다수개 설치하며, 시공지에 식생매트를 포설하고, 앞서 돌출된 와이어는 식생매트 상부로 돌출되게 하며, 상기 식생매트 상부에 고정망을 격자 구조로 설치하고, 앞서 돌출된 와이어를 고정망에 고정하며, 전체적으로 흙을 포설함으로써, 앵커와 식생매트를 이용한 녹화 공법이 완료되어, 앵커의 설치가 빠르고 용이하며, 그 설치 구조에 의해 식생매트의 설치 및 고정이 견고하고, 외부 환경에도 식생매트의 이탈을 방지하도록 한다.Therefore, the present invention to solve the above problems, to form a cylindrical insertion shaft penetrating the inner side in the longitudinal direction, to form a plurality of fixing holes penetrated in the upper side of the insertion shaft, the outer periphery of the lower fixing hole Along with the spiral is formed along the spiral portion protruding, the separate wire is inserted into the fixing hole, the both ends of the wire is assembled so as to protrude to the upper, and then the anchor is used to arrange the construction site using a drill Install a plurality of wires at both ends to protrude to the upper part of the ground, and install a vegetation mat in the construction site, and the wires protruded above to protrude to the top of the vegetation mat. The greening method using anchor and vegetation mat is completed by installing, fixing the wire which protruded previously to the fixed net, and laying the soil as a whole. Thus, the installation of the anchor is quick and easy, the installation structure of the anchoring and fixing the vegetation mat is firm, and to prevent the departure of the vegetation mat in the external environment.

또한, 상기 내부가 관통된 테두리 형상으로 구성하고, 그 가장자리의 저면에 돌출된 고정부가 일체로 다수개 형성된 구조의 고정구가 더 구비되어, 설치된 고정망과 식생매트 사이에 고정구를 설치하되, 그 고정부가 지면에 박히도록 고정구를 설치하여, 식생매트의 고정이 더욱 견고하도록 한다.In addition, the interior is penetrated through the rim shape, and the fixture is further provided with a structure formed integrally a plurality of fixing parts protruding on the bottom surface of the edge, the fixture is installed between the fixed net and vegetation mat installed, the fixing Fixtures are installed so that the additional parts are embedded in the ground, making the fixation of the vegetation mat more robust.

그리고 상기 녹화 공법에 사용된 시공자재는 부식이 방지되는 자재를 사용하되, 앵커, 와이어형 지지구의 와이어, 고리형 지지구, 고정구, 식생매트의 침식방지매트와 보강네트, 고정망의 재질은, 메탈 자재를 사용하여 부식 방지 코팅한 것을 사용하거나, 또는, 합성수지와 같이 자체 재질에 의해 부식이 방지되는 자재(비부식성 자재)를 사용하여, 본 발명에 따른 녹화 시공 후에도 부식이 방지되어 강도와 내구성을 유지하도록 있도록 한다.And the construction material used in the greening method is to use the material to prevent corrosion, anchor, wire of the support wire, ring support, fasteners, vegetation mat erosion prevention mat and reinforcing net, the material of the fixed net, Corrosion-resistant coating using a metal material or using a material (non-corrosive material) which is prevented from corrosion by its own material such as synthetic resin, and corrosion is prevented even after the greening construction according to the present invention. To keep it.

또는, 상기 녹화 공법에 사용된 시공자재는 생분해성 자재를 사용하되, 식생매트의 시트는 천연 펄프, 짚, 섬유 망과 같은 생분해성 자재를 사용하고, 앵커, 와이어형 지지구의 와이어, 고리형 지지구, 고정구, 식생매트의 침식방지매트와 보강네트, 고정망의 재질은, 피엘에이(PLA)와 같은 생분해성 자재로 제조되어, 본 발명에 따른 녹화 시공 후에 시간이 지나면서 분해되도록 한다.
Or, the construction materials used in the greening method used biodegradable materials, the sheet of vegetation mat using biodegradable materials such as natural pulp, straw, fiber mesh, anchor, wire of support wire, ring paper Earth, fixture, vegetation mat erosion prevention mat and reinforcing net, the material of the fixing net is made of biodegradable materials such as PLA, so as to decompose over time after greening construction according to the present invention.

이와 같이 본 발명은, 길이 방향을 따라 내부가 관통된 원통형의 삽입축을 구성하고, 그 삽입축 상부 측면에 관통된 고정공을 다수개 형성하며, 그 고정공 하부의 외주연을 따라 스파이럴 형상으로 돌출된 나선부를 일체로 형성하는 앵커가 구비되어, 별도의 와이어를 상기 고정공으로 끼워, 와이어 양단이 상부로 돌출되게 조립한 다음, 정리된 시공지에 드릴류를 이용해서 앵커를 지면 하부로 설치하고, 각 와이어 양단은 지면 상부로 돌출되게 다수개 설치하며, 시공지에 식생매트를 포설하고, 앞서 돌출된 와이어는 식생매트 상부로 돌출되게 하며, 상기 식생매트 상부에 고정망을 격자 구조로 설치하고, 앞서 돌출된 와이어를 고정망에 고정하며, 전체적으로 흙을 포설함으로써, 앵커와 식생매트를 이용한 녹화 공법이 완료되어, 앵커의 설치가 빠르고 용이하며, 그 설치 구조에 의해 식생매트의 설치 및 고정이 견고하고, 외부 환경에도 식생매트의 이탈을 방지하며, 다양한 시공지에 녹화 시공을 적용할 수 있는 효과가 있다.As described above, the present invention constitutes a cylindrical insertion shaft penetrating through the longitudinal direction, and forms a plurality of fixing holes penetrated at the upper side of the insertion shaft, and protrudes in a spiral shape along the outer circumference of the lower portion of the fixing hole. An anchor is formed to integrally form a spiral portion, and a separate wire is inserted into the fixing hole, and both ends of the wire are assembled to protrude upwards, and then the anchor is installed below the ground using drills in the assembled construction paper. Both ends of the wires are installed to a plurality of protruding to the top of the ground, install a vegetation mat in the construction site, the wires protruding above to protrude above the vegetation mat, install a fixed net in a grid structure on the vegetation mat, and protrudes before The fixed wire is fixed to the fixed net, and the soil is entirely laid, so that the greening method using the anchor and the vegetation mat is completed, and the anchor is installed quickly. Easily and securely, the installation and fixing of the vegetation mat by the mounting structure, to prevent the detachment of the vegetation mat in an external environment, and there is an effect that can be applied to the recording construction how different construction.

또한, 상기 내부가 관통된 테두리 형상으로 구성하고, 그 가장자리의 저면에 돌출된 고정부가 일체로 다수개 형성된 구조의 고정구가 더 구비되어, 설치된 고정망과 식생매트 사이에 고정구를 설치하되, 그 고정부가 지면에 박히도록 고정구를 설치하여, 식생매트의 고정이 더욱 견고한 효과가 있다.In addition, the interior is penetrated through the rim shape, and the fixture is further provided with a structure formed integrally a plurality of fixing parts protruding on the bottom surface of the edge, the fixture is installed between the fixed net and vegetation mat installed, the fixing By installing the fixture to be embedded in the additional ground, the fixing of the vegetation mat is more robust effect.

그리고 상기 녹화 공법에 사용된 시공자재는 부식이 방지되는 자재를 사용하되, 앵커, 와이어형 지지구의 와이어, 고리형 지지구, 고정구, 식생매트의 침식방지매트와 보강네트, 고정망의 재질은, 메탈 자재를 사용하여 부식 방지 코팅한 것을 사용하거나, 또는, 합성수지와 같이 자체 재질에 의해 부식이 방지되는 자재(비부식성 자재)를 사용하여, 본 발명에 따른 녹화 시공 후에도 부식이 방지되어 강도와 내구성을 유지하는 효과가 있다.And the construction material used in the greening method is to use the material to prevent corrosion, anchor, wire of the support wire, ring support, fasteners, vegetation mat erosion prevention mat and reinforcing net, the material of the fixed net, Corrosion-resistant coating using a metal material or using a material (non-corrosive material) that is prevented from corrosion by its own material such as synthetic resin, and corrosion is prevented even after the greening construction according to the present invention, resulting in strength and durability. It is effective to maintain.

또는, 상기 녹화 공법에 사용된 시공자재는 생분해성 자재를 사용하되, 식생매트의 시트는 천연 펄프, 짚, 섬유망과 같은 생분해성 자재를 사용하고, 앵커, 와이어형 지지구의 와이어, 고리형 지지구, 고정구, 식생매트의 침식방지매트와 보강네트, 고정망의 재질은, 피엘에이(PLA)와 같은 생분해성 자재로 제조되어, 본 발명에 따른 녹화 시공 후에 시간이 지나면서 분해되어, 친환경적인 효과가 있다.
Or, the construction materials used in the greening method is using biodegradable materials, the sheet of vegetation mat using biodegradable materials such as natural pulp, straw, fiber mesh, anchors, wire of wire support, ring-shaped paper Earth, fixture, vegetation mat erosion prevention mat and reinforcing net, the material of the fixing net is made of biodegradable materials such as PLA, decomposes over time after greening construction according to the present invention, environmentally friendly It works.

도 1은 본 발명에 따른 녹화 공법에 따라 앵커가 설치된 구조를 보여주는 사시도.
도 2는 본 발명에 따른 녹화 공법이 적용된 제방을 보여주는 측단면도.
도 3은 본 발명에 따른 녹화 공법이 적용된 배수로를 보여주는 측단면도.
도 4는 본 발명에 따른 녹화 공법이 시공된 평면도.
도 5는 본 발명에 따른 앵커의 사시도.
도 6은 본 발명에 따라 와이어형 지지구를 이용한 앵커의 설치를 방법을 보여주는 측단면도.
도 7은 도 2의 A부분에 대한 확대도.
도 8은 본 발명에 따른 식생매트에 고정용 앵커와 고리형 지지구의 결합 사시도 및 일부 확대도.
도 9는 도 2의 B부분에 대한 확대도.
도 10은 본 발명의 녹화 공법에 따른 공정도.
1 is a perspective view showing a structure in which the anchor is installed according to the greening method according to the present invention.
Figure 2 is a side cross-sectional view showing a bank to which the greening method according to the present invention is applied.
Figure 3 is a side cross-sectional view showing a drainage to which the greening method according to the present invention is applied.
4 is a plan view of the greening method according to the present invention constructed.
5 is a perspective view of the anchor according to the present invention.
Figure 6 is a side cross-sectional view showing the method of installing the anchor using a wire-shaped support in accordance with the present invention.
7 is an enlarged view of a portion A of FIG. 2.
8 is a perspective view and a partially enlarged view of the anchoring and the annular support for fixing to the vegetation mat according to the present invention.
9 is an enlarged view of a portion B of FIG. 2.
10 is a process chart according to the greening method of the present invention.

본 발명은 나선부를 가지는 앵커 및 그 앵커와 식생매트를 이용한 녹화 공법으로, 길이 방향을 따라 내부가 관통된 원통형의 삽입축을 구성하고, 그 삽입축 상부 측면에 관통된 고정공을 다수개 형성하며, 그 고정공 하부의 외주연을 따라 스파이럴 형상으로 돌출된 나선부를 일체로 형성하는 앵커가 구비되어, 별도의 와이어를 상기 고정공으로 끼워, 와이어 양단이 상부로 돌출되게 조립한 다음, 정리된 시공지에 드릴류를 이용해서 앵커를 지면 하부로 설치하고, 각 와이어 양단은 지면 상부로 돌출되게 다수개 설치하며, 시공지에 식생매트를 포설하고, 앞서 돌출된 와이어는 식생매트 상부로 돌출되게 하며, 상기 식생매트 상부에 고정망을 격자 구조로 설치하고, 앞서 돌출된 와이어를 고정망에 고정하며, 전체적으로 흙을 포설함으로써, 앵커와 식생매트를 이용한 녹화 공법이 완료되어, 앵커의 설치가 빠르고 용이하며, 그 설치 구조에 의해 식생매트의 설치 및 고정이 견고하고, 외부 환경에도 식생매트의 이탈을 방지하여, 다양한 시공지에 녹화 시공을 적용할 수 있는 것이다.
The present invention is a greening method using an anchor having a spiral portion and its anchor and vegetation mat, and constitutes a cylindrical insertion shaft penetrating the inner side in the longitudinal direction, and forms a plurality of fixing holes penetrating the upper side of the insertion shaft, An anchor is formed to integrally form a spiral portion protruding in a spiral shape along the outer circumference of the lower part of the fixing hole. A separate wire is inserted into the fixing hole, and both ends of the wire are assembled to protrude upwards, and then drilled in the assembled construction paper. Using anchors to install the anchor to the bottom of the ground, each end of each wire is installed a plurality of protruding to the top of the ground, install a vegetation mat in the construction site, the wire protruding above to protrude above the vegetation mat, the vegetation mat By installing a fixed net on the upper part of the grid structure, fixing the wires projecting above the fixed net, and laying soil as a whole, The mating method is completed, and anchor installation is quick and easy. The installation structure makes the installation and fixation of the vegetation mat secure and prevents the departure of the vegetation mat to the external environment. You can do it.

우선, 나선부를 가지는 앵커를 설명하고, 이어서, 앵커와 식생매트를 이용한 녹화 공법을 순차로 설명한다.First, the anchor having a spiral portion will be described, and then the greening method using the anchor and the vegetation mat will be described sequentially.

먼저, 앵커(10)는, 도5에 도시한 바와 같이, 삽입축(11)과 나선부(12)가 일체되어 구성하는데, 우선 삽입축(11)은 원통형 형상이고, 그 길이 방향을 따라 중앙 내부가 관통된 관 형상으로 구성하며, 삽입축(11) 상단에는 지름 방향으로 키자리(11a)를 형성하며, 또한, 삽입축(11) 상부 측면에는 관통된 고정공(11b)을 다수개 형성한다.First, as shown in Fig. 5, the anchor 10 is composed of an insertion shaft 11 and a spiral portion 12 integrally formed. First, the insertion shaft 11 has a cylindrical shape and is centered along its longitudinal direction. The inside is formed in a tubular shape, the upper end of the insertion shaft (11) forms a key seat (11a) in the radial direction, and the upper side of the insertion shaft (11) formed a plurality of through holes fixed (11b) do.

그리고 나선부(12)는 상기 삽입축(11)의 원주면에 원주 방향으로 판형으로 돌출되되, 길이 방향을 따라 스파이럴 형태로 돌출된 형상이며, 나선부(12)는 고정공(11b)의 위치보다 낮은 위치에서 하단까지 형성되되, 하부로 갈수록 돌출된 폭이 점점 좁아지는 구조이며, 이러한 구조로 인해서, 지면 아래로 파고들어가기가 용이하다.The spiral portion 12 protrudes in a plate shape in the circumferential direction on the circumferential surface of the insertion shaft 11, and protrudes in a spiral shape along the longitudinal direction, and the spiral portion 12 is a position of the fixing hole 11b. It is formed from the lower position to the lower end, the structure is a narrower projecting width toward the lower portion, due to this structure, it is easy to penetrate under the ground.

이렇게 앵커(10)는 키자리(11a)와 고정공(11b)이 형성된 삽입축(11)과 상기 삽입축(11)에 스파이럴 형태로 돌출된 나선부(12)가 일체로 형성되어 구성한다.
In this way, the anchor 10 includes an insertion shaft 11 in which a key seat 11a and a fixing hole 11b are formed, and a spiral portion 12 protruding in a spiral form on the insertion shaft 11 is integrally formed.

아울러 앵커(10)의 설치를 위한 지지구를 더 구성하는데, 이러한 지지구는 앵커(10)의 설치 위치에 따라 와이어형 지지구(20)와 고리형 지지구(30)로 구성한다.In addition, the support for the installation of the anchor 10 is further configured, such a support is composed of a wire-shaped support 20 and the ring support 30 according to the installation position of the anchor 10.

먼저, 도6 및 도7에 도시한 바와 같이, 와이어형 지지구(20)는 와이어(21)와 보조구(22)로 구성하는데, 와이어(21)는 철사와 같이 메탈 재질의 와이어(21)를 사용하고, 그 길이는 앵커(10)가 설치되는 환경에 따라 적절한 길이를 가지도록 한다.First, as shown in Figures 6 and 7, the wire support 20 is composed of a wire 21 and the auxiliary tool 22, the wire 21 is a metal wire 21, such as a wire To use, the length is to have an appropriate length depending on the environment in which the anchor 10 is installed.

그리고 보조구(22)는 앵커(10)의 설치를 용이하게 하기 위한 보조 도구로, 일정 길이로 형성된 관으로 구성되어, 그 일단은 설치부(미도시)로 구성하고, 그 타측 내부에는 중앙을 관통하는 방향(지름 방향)으로 키(22a)를 형성하며, 그 키(22a) 방향에 대해서 수직 방향 양단에는 일정 폭 및 일정 높이로 제거된 트임부(22b)를 형성한다.And the assisting tool 22 is an auxiliary tool for facilitating the installation of the anchor 10, is composed of a tube formed in a predetermined length, one end is composed of an installation portion (not shown), the other side inside the center The key 22a is formed in the penetrating direction (diameter direction), and the trimming portion 22b removed at a predetermined width and a predetermined height is formed at both ends in the vertical direction with respect to the key 22a direction.

앞서 설명한 설치부는 드릴류(300)(핸드 드릴, 드릴 머신, 기타 회전 장치)과 같은 장치에 끼움 되어서 설치를 용이하게 할 수 있는 일반적인 구조로 형성되므로 구체적인 설명은 생략한다.Since the above-described installation part is formed in a general structure that can be fitted to a device such as a drill 300 (hand drill, drill machine, other rotating device) to facilitate the installation, a detailed description thereof will be omitted.

이렇게 와이어(21)와 보조구(22)로 구성된 와이어형 지지구(20)를 이용한 앵커의 설치 방법 및 구조를 살펴 보면, 우선, 와이어(21)를 앵커(10)의 고정공(11b)으로 끼우고, 와이어(21)의 양단은 앵커(10) 상부로 돌출되도록 하여, 도6에 도시한 바와 같이, ‘ㄷ’자 형태로 꺾인 구조를 가지도록 한다.Looking at the installation method and structure of the anchor using the wire-shaped support 20 composed of the wire 21 and the auxiliary tool 22, first, the wire 21 to the fixing hole (11b) of the anchor 10 Inserted, both ends of the wire 21 to protrude to the upper portion of the anchor 10, as shown in Figure 6, to have a structure bent in the 'c' shape.

그리고 도7에 도시한 바와 같이, 보조구(22)는 설치부를 통해 드릴류(300)에 고정하고, 앵커(10)의 상부로 돌출된 와이어(21) 양단을 각각 트임부(22b)를 통해서 보조구(22) 내부로 밀어 넣고, 보조구(22)의 키(22a)가 앵커(10)의 키자리(11a)에 안착되도록 한다.As shown in FIG. 7, the assisting tool 22 is fixed to the drills 300 through the mounting portion, and both ends of the wire 21 protruding upward from the anchor 10 are respectively through the trimming portion 22b. It is pushed into the assisting tool 22 and the key 22a of the assisting tool 22 is seated in the key seat 11a of the anchor 10.

그리고 앵커(10)를 설치할 위치에 지면에 수직으로 앵커(10)를 위치하고, 드릴류(300)을 작동하면서 밀어 넣으면, 앵커(10)가 드릴류(300)의 힘과 나선부(12)의 회전으로 지면을 파고들어가 박히고, 드릴류(300)을 들어내면, 보조구(22)도 같이 빠져나오고, 박힌 앵커(10)와 와이어(21)만 남는다.
And when the anchor 10 is positioned perpendicular to the ground at the position where the anchor 10 is to be installed and pushed while operating the drills 300, the anchors 10 may be formed by the force of the drills 300 and the spirals 12. When the ground is dug into the ground, and the drill 300 is lifted up, the assisting tool 22 also comes out, leaving only the anchored anchor 10 and the wire 21.

다음으로, 고리형 지지구(30)는 일정 길이를 가지고, 일단은 뾰족하게 형성하고, 그 타단은 고리(31)를 형성하는데, 고리(31)는 반 원형으로 형성되어 도8에 도시된 형상을 가지거나, 또는, 고리(31) 부분에 해당하는 끝 부분이 두 번 꺾임되어, 고리형 지구(30)가 전체적으로 ‘

Figure 112011013720795-pat00001
’의 형상으로 형성한다.Next, the annular support 30 has a certain length, one end is formed pointed, the other end forms a ring 31, the ring 31 is formed in a semi-circular shape shown in Figure 8 Or the end portion corresponding to the portion of the ring 31 is bent twice, so that the annular earth 30 as a whole becomes'
Figure 112011013720795-pat00001
Form in the shape of '.

아울러, 상기 고리형 지지구(30)를 적용하는 앵커(10)에서는, 그 삽입축(11)의 고정공(11b)은 암나사로 형성하고, 상기 고리형 지지구(30)의 고리(31)의 상단부분에는 설치부(미도시)를 구성하되, 설치부는 드릴류(300)(드릴류 머신)과 같은 장치에 설치를 용이하게 할 수 있는 일반적인 구조로 형성되므로 구체적인 설명은 생략한다.In addition, in the anchor 10 to which the annular support 30 is applied, the fixing hole 11b of the insertion shaft 11 is formed of a female screw, and the ring 31 of the annular support 30 is formed. The upper portion of the installation portion (not shown) is configured, but the installation portion is formed in a general structure that can be easily installed in the device, such as drills 300 (drilling machine), a detailed description thereof will be omitted.

그리고 이러한 고리형 지지구(30)를 이용한 앵커(10)의 설치 방법 및 구조를 도8 및 도9를 참고하여 살펴 보면, 먼저, 고리형 지지구(30)의 삽입축(11) 내부로 고리형 지지구(30)의 뾰족한 부분으로 밀어 넣어, 삽입축(11) 하부로 고리형 지지구(30)의 뾰족한 부분이 돌출되도록 하고, 그 상태에서, 고정공(11b), 즉, 암나사로 볼트나 나사와 고정수단(32)으로 넣어 죄어 고리형 지지구(30)를 고정하는데, 사용하는 고정수단(32)은 무두볼트를 사용하면 앵커의 삽입축(11) 측면으로 돌출되는 부분이 없고, 앵커의 설치 시에 마찰을 최소화하는 특징이 있다.And look at the installation method and structure of the anchor 10 using the annular support 30 with reference to Figures 8 and 9, first, the loop into the insertion shaft 11 of the annular support 30 Pushed into the pointed portion of the shaped support 30, so that the pointed portion of the annular support 30 protrudes below the insertion shaft 11, and in that state, bolts with a fixing hole 11b, that is, a female screw B screws and fastening means to secure the annular support (30) by inserting into the fixing means 32, the fixing means to be used there is no portion protruding to the side of the insertion shaft (11) of the anchor when using a tanned bolt, There is a feature to minimize the friction when installing the anchor.

그리고 앵커(10)를 설치할 곳에 지면에 대해 수직으로 앵커(10)를 놓고, 드릴류(300)과 같은 회전 장치에 고리형 지지구(30)의 고리(31) 부분을 설치하며, 드릴류(300)을 작동하면서 지면으로 앵커(10)를 회전시키면서 밀어 넣으면, 앵커(10)가 드릴류(300)의 회전하는 힘과 나선부(12)에 의해 지면을 파고들어가 박힌다.
And the anchor 10 is placed perpendicular to the ground where the anchor 10 is to be installed, and the hook 31 of the annular support 30 is installed in a rotating device such as the drill 300, and the drills ( When the anchor 10 is pushed into the ground while the 300 is being operated, the anchor 10 is dug into the ground by the rotating force of the drills 300 and the spiral portion 12.

이러한 구조의 앵커(10)와 지지구를 이용한 식생매트를 이용한 녹화 공법을 설명하기에 앞서, 그 녹화 공법에 필요한 식생매트(50)와 고정구(40) 및 고정망(60)을 설명하면 다음과 같다.Prior to describing the greening method using the vegetation mat using the anchor 10 and the support of such a structure, the vegetation mat 50 and the fixture 40 and the fixed net 60 necessary for the greening method will be described as follows. same.

먼저, 식생매트(50)는 시트(51)와 침식방지매트(52)로 구성하는데, 시트(51)는 그 내부에 식물이나 꽃의 종자(51a)를 포함하고 있으며, 시트(51)는 부직포로 구성하거나, 또는, 천연 펄프, 짚, 섬유망과 같은 생분해성 자재를 이용하여 구성하여, 녹화 시공 후에 시간이 지나면서 분해될 수 있도록 한다.First, the vegetation mat 50 is composed of a sheet 51 and the erosion prevention mat 52, the sheet 51 includes a seed 51a of a plant or a flower therein, the sheet 51 is a nonwoven fabric Or, using biodegradable materials such as natural pulp, straw, fiber mesh, so as to be able to decompose over time after greening construction.

또, 침식방지매트(52)는 네트 구조(네트의 구조는 일반적인 사각 구조, 또는 오각, 육각 구조를 가진다)를 가지거나, 또는, 입체적인 망의 구조(선이 3차원으로 얽힌 구조)를 가지면서 약간의 두께가 있도록 구성하여, 침식을 방지하고, 토사 유출을 방지하도록 한다.In addition, the erosion prevention mat 52 has a net structure (the structure of the net has a general quadrangular structure, or a pentagonal or hexagonal structure), or has a three-dimensional network structure (structure in which lines are entangled in three dimensions). It is configured to have a slight thickness to prevent erosion and to prevent soil leakage.

아울러, 앞서 식생매트(50)는 시트(51)와 그 상부의 침식방지매트(52)로 구성되어 사용하거나, 또한, 식생매트(50)는 시트(51) 하부에 보강네트(53)를 추가한 식생매트(50)를 구성할 수 있으며, 보강네트(53)는 메시 구조를 가지고, 이 보강네트(53)에 의해 시트(51)를 보호하면서, 토사 유출을 방지한다.
In addition, the vegetation mat 50 is composed of the sheet 51 and the erosion prevention mat 52 of the upper portion, or the vegetation mat 50 is added to the reinforcing net 53 in the lower sheet 51 One vegetation mat 50 can be configured, and the reinforcing net 53 has a mesh structure, and the reinforcing net 53 protects the sheet 51 while preventing soil leakage.

그리고 고정구(40)는 내부가 관통된 테두리 형상으로 구성하고, 가장자리의 저면을 따라 돌출된 고정부(41)가 일체로 형성된 구조로, 고정부(41)는 하부로 갈수록 좁아지는 형상, 즉, 뾰족한 형상으로 형성되어 지면에 박히기가 용이하도록 구성하며, 고정구(40)는 간단하기에는 링 형상으로 형성한다.
And the fastener 40 is configured in the shape of the penetrating through the inside, the fixing portion 41 protruding along the bottom surface of the structure is formed integrally, the fixing portion 41 is narrowed toward the lower shape, that is, It is formed in a pointed shape so as to be easily embedded in the ground, and the fixture 40 is simply formed in a ring shape.

그리고 고정망(60)은 격자 구조로 구성된 네트를 사용하거나, 또는, 와이어를 사용하여 격자 모양으로 배치하여 사용한다.The fixed net 60 uses a net formed of a lattice structure, or uses a wire and is arranged in a lattice shape using a wire.

이렇게 구성한 앵커(10)와 식생매트(50), 지지구, 고정구(40)를 이용한 녹화 공법을 도10의 공정도를 참고하여 설명하면 다음과 같다.Referring to the greening method using the anchor 10, the vegetation mat 50, the support, the fixture 40 configured as described above with reference to the process diagram of FIG.

우선, 시공지 정리 공정(S1)은 식생매트(50)를 이용한 녹화 공법이 적용되는 지면을 정리하는 공정으로, 시공지는 식생매트(50)를 일반적으로 많이 적용하는 사면지, 즉, 도로변, 택지개발지구, 절성토 비탈면 등이 적용될 수 있으며, 이외에도 하천 제내지 사면, 하천 제외지 고수/저수 호안 사면, 하천 고수부지, 저류조 비탈면, 배수로에 적용하며, 또한, 콘크리트가 적용된 기존 하천이나 개비온 매트리스로 시공된 호안을 녹화하는데 적용되며, 이외에도 녹화가 필요한 여러 곳에 적용할 수 있으며, 녹화 공법이 적용되는 시공지는 지반의 흙이 드러나면서 울퉁불퉁한 부분이 없도록 고르도록 한다.
First, the construction site arranging process (S1) is a process of arranging the ground to which the greening method using the vegetation mat 50 is applied, and the construction site is a slope where the vegetation mat 50 is generally applied, that is, a roadside, a residential land. Development zones, cut soil slopes, etc. may be applied.In addition, it is applied to slopes in rivers, sediments, reservoir drainage slopes, river reservoirs, reservoir slopes, drainage channels and drainage channels. It is applied to greening the constructed revetment, and it can be applied to various places where greening is needed. The construction site to which the greening method is applied is selected so that the soil of the ground is exposed and there are no bumps.

그리고 앵커 설치 공정(S2)은, 정리된 시공지에 앞서 설명한 앵커(10)를 설치하는 공정으로, 도6에 도시한 바와 같이, 앵커(10)에 와이어형 지지구(20)를 설치하고, 보조구(22) 및 드릴류(300)을 이용하여, 시공지의 지면 환경 및 상태를 고려하여, 시공지에 적정 간격과 적절한 깊이로 박히도록 하고, 와이어형 지지구(20)의 와이어(21)의 끝단은 지면 상부로 돌출되도록 한다.
And anchor installation process (S2) is a process of providing the anchor 10 demonstrated previously in the gathered construction site, as shown in FIG. 6, and installs the wire-shaped support tool 20 in the anchor 10, and assists. Using the sphere 22 and the drills 300, in consideration of the ground environment and condition of the construction site, to be embedded in the construction site at an appropriate interval and the appropriate depth, the end of the wire 21 of the wire support 20 To protrude above the ground.

다음으로, 식생매트 포설 공정(S3)은, 도4에 도시한 바와 같이, 앞서 구비한 식생매트(50)를 정리된 시공지를 따라 포설하는 공정으로, 식생매트(50)를 포설하면서, 지면에서부터, 보강네트(53), 시트(51), 침식방지매트(52)가 순차로 위치되도록 하며, 앞서 지면에서 돌출된 와이어(21)의 끝단은 식생매트(50) 상부로 돌출되도록 한다.
Next, the vegetation mat laying step (S3) is a step of laying the vegetation mat 50 provided above along the construction site as shown in FIG. 4, while laying the vegetation mat 50 from the ground. The reinforcing net 53, the sheet 51, and the erosion preventing mat 52 are sequentially positioned, and the ends of the wires 21 protruding from the ground above protrude upward from the vegetation mat 50.

또한, 고정망 설치 공정(S4)은, 앞서 포설된 식생매트(50)와 상부에 고정망(60)을 설치하는 공정으로, 고정망(60)은 격자 구조로 설치되어, 식생매트(50)를 고정한다.In addition, the fixed net installation step (S4) is a step of installing the fixed vegetation mat 50 and the upper installation of the fixed net 60, the fixed net 60 is installed in a lattice structure, the vegetation mat 50 Fix it.

아울러, 상기 고정망 설치 공정(S4)에서는, 설치하는 고정망(60)은 돌출된 와이어(21) 사이를 통과하도록 설치하며, 이를 위해서, 도1에 도시한 바와 같이, 앞서 앵커(10) 설치 공정(S2)에서는, 고정망(60)이 교차하는 부분이나, 고정망(60)이 지나가는 부분을 고려하여 앵커(10)를 설치하고, 식생매트(50)를 설치한 다음에는, 돌출된 와이어(21)가 고정망(60)이 교차하거나 지나가는 부분 하부에 앵커(10)가 위치되도록 한다.
한편, 상기 고정망 설치 공정(S4) 다음에는 고정구 설치 공정(S4´)가 추가될 수 있는데, 고정구 설치 공정(S4´)는, 도1에 도시한 바와 같이, 설치된 고정망(60)과 식생매트(50) 사이에 고정구(40)를 설치하되, 그 고정부(41)가 지면에 박히도록 고정구(50)를 설치하여, 식생매트(50)의 고정이 더욱 견고하도록 한다.
In addition, in the fixed net installation step (S4), the fixed net 60 to be installed is installed so as to pass through between the protruding wire 21, for this purpose, as shown in Figure 1, previously installed anchor 10 In the step S2, the anchor 10 is installed in consideration of the portion where the fixed net 60 crosses or the portion where the fixed net 60 passes, and after the vegetation mat 50 is installed, the protruded wire 21 allows the anchor 10 to be positioned under the portion where the fixed net 60 intersects or passes.
On the other hand, after the fixing net installation step (S4) can be added to the fixture installation process (S4 '), the fixture installation process (S4'), as shown in Figure 1, the fixed net 60 and the vegetation installed The fastener 40 is installed between the mat 50, but the fastener 50 is installed so that the fastening portion 41 is embedded in the ground, so that the fixing of the vegetation mat 50 is more firm.

그리고 와이어 고정 공정(S5)은, 도1에 도시한 바와 같이, 설치된 앵커(10)의 와이어형 지지구(20)에서 돌출된 와이어(21)를 고정망(60)에 상부에서 꼬거나 묶어서 고정하는 공정으로, 꼬거나 묶은 와이어(21)는 뉘어서 돌출되지 않도록 하는 것이 바람직하다.
And wire fixing step (S5), as shown in Figure 1, to fix the wire 21 protruding from the wire-shaped support 20 of the anchor 10 provided by twisting or binding to the fixing net 60 from the top In this process, it is preferable that the twisted or bundled wires 21 do not lie down and protrude.

다음으로, 고정망 가장자리 고정 공정(S6)은, 도2 및 도9에 도시한 바와 같이, 고정망(60) 가장자리를 따라, 앵커(10)에 고리형 지지구(30)를 설치하고, 드릴류(300) 등을 이용해 지면에 박아 넣으면서, 고리(31) 내부에 고정망(60)을 걸리도록 하여, 이렇게 고리형 지지구(30)에 의해 고정망(60) 가장자리가 들려지지 않도록 하는데, 이러한 고정망 가장자리 고정 공정(S6)은, 고정망 설치 공정(S4)을 하면서, 또는, 그 고정망 설치 공정(S4)을 실시한 다음에 바로 실시하여도 무방하다.Next, as shown in FIGS. 2 and 9, in the fixing net edge fixing step S6, an annular support 30 is provided at the anchor 10 along the edge of the fixing net 60, and the drill is drilled. While being driven into the ground using the flow (300) or the like, so as to hook the fixed net 60 inside the ring 31, so that the edge of the fixed net 60 by the annular support 30 is not lifted, Such fixed net edge fixing step S6 may be performed immediately after performing the fixed net installing step S4 or after performing the fixed net installing step S4.

마지막으로, 흙 포설 공정(S7)은, 도2 및 도3과 같이, 상기 식생매트(50)와 고정망(60) 상부로 흙(200)을 포설하여, 전체적으로 흙(200)으로 덮는 공정이며, 필요에 따라, 물을 뿌리기도 하며, 이러한 설치로 앵커(10)와 식생매트(50)를 이용한 녹화 공법을 완료한다.
Finally, the soil laying step (S7), as shown in Figures 2 and 3, is the process of laying the soil 200 to the vegetation mat 50 and the fixed net 60, and covered with the soil 200 as a whole , If necessary, watering, and with this installation to complete the greening method using the anchor 10 and the vegetation mat (50).

이렇게 본 발명에 따른 앵커(10)와 식생매트(50)를 이용한 녹화 공법은, 앵커(10)와 지지구(와이어형 지지구, 고리형 지지구)를 드릴류(300)를 사용해서 빠르고 용이하게 설치할 수 있으므로, 기존처럼 지면을 미리 천공할 필요가 없고, 이에 따라, 식생매트(50)를 빠르고 용이하게 설치·고정할 수 있으며, 지면 아래에 박힌 앵커(10)는 고정력이 우수하고, 나선부(12)에 의해서 외력에 의해서도 견고히 고정되는 구조를 가지며, 또한, 식맹매트(50)를 고정하기 위해 설치하는 고정망(60)의 가장자리는 앵커(10)와 고리형 지지구(30)의 설치하여 고정망(60) 가장자리가 들뜨지 않는 특징이 있다.
Thus, the greening method using the anchor 10 and the vegetation mat 50 according to the present invention, the anchor 10 and the support (wire-type support, annular support) using a drill 300 quickly and easily Since it is possible to install it, it is not necessary to drill the ground in advance as before, accordingly, the vegetation mat 50 can be installed and fixed quickly and easily, and the anchor 10 embedded under the ground has excellent fixing force and spirals It has a structure that is firmly fixed by the external force by the part 12, and the edge of the fixing net 60 to be installed to fix the mating mat 50 of the anchor 10 and the annular support 30 There is a feature that does not lift the edge of the fixed net 60 by installing.

한편, 앞서 본 발명의 녹화 공법에 사용된 시공자재의 재질, 즉, 앵커(10), 와이어형 지지구의 와이어(21), 고리형 지지구(30), 고정구(40), 식생매트(50)의 침식방지매트(52)와 보강네트(53), 고정망(60)의 재질은, 메탈 자재를 사용하여 부식 방지 코팅한 것을 사용하거나, 또는, 합성수지와 같이 자체 재질에 의해 부식이 방지되는 자재(비부식성 자재)를 사용하여, 본 발명에 따른 녹화 시공 후에도 부식이 방지되어 강도와 내구성을 유지할 수 있도록 한다.On the other hand, the material of the construction material previously used in the greening method of the present invention, that is, the anchor 10, the wire 21 of the wire support, the ring support 30, the fixture 40, vegetation mat 50 The material of the anti-erosion mat 52, the reinforcing net 53, and the fixing net 60 is a material that is corrosion-resistant coated using a metal material, or the material is prevented from corrosion by its own material such as synthetic resin. By using (non-corrosive material), corrosion is prevented even after the greening construction according to the present invention to maintain strength and durability.

그리고 또 다른 한편으로는, 앞서 본 발명의 녹화 공법에 사용된 시공자재의 재질, 즉, 앵커(10), 와이어형 지지구의 와이어(21), 고리형 지지구(30), 고정구(40), 식생매트(50)의 침식방지매트(52)와 보강네트(53), 고정망(60)의 재질은, 피엘에이(PLA, Poly Lactic Acid, 옥수수나 감자에서 나오는 전분 등으로 만든 친환경 생분해성 수지)와 같은 생분해성 자재로 제조되어, 본 발명에 따른 녹화 시공 후에 시간이 지나면서 분해될 수 있도록 한다.
On the other hand, the material of the construction material used in the greening method of the present invention, that is, the anchor 10, the wire 21 of the wire support, the ring support 30, the fastener 40, The material of the erosion prevention mat 52, the reinforcing net 53, and the fixed net 60 of the vegetation mat 50 is made of PLA, poly lactic acid, starch from corn or potato, and the like. It is made of a biodegradable material such as), so that it can be decomposed over time after the greening construction according to the present invention.

10 : 앵커 12 : 나선부
20 : 와이어형 지지구 21 : 와이어
22 : 보조구 30 : 고리형 지지구
31 : 고리 40 : 고정구
50 : 식생매트 60 : 고정망
10: anchor 12: helix
20: wire type support 21: wire
22: auxiliary tool 30: annular support
31 ring 40 fastener
50: vegetation mat 60: fixed net

Claims (8)

삭제delete 길이 방향을 따라 내부가 관통된 원통형의 삽입축이 구성되어, 그 상단에는 키자리를 형성하며, 그 삽입축 상부 측면에는 관통된 고정공을 다수개 형성하고, 그 고정공 하부의 외주연을 따라 원주방향으로 돌출된 스파이럴 형상의 돌출 나선부가 일체로 형성되고, 이 나선부는 삽입축의 하부로 갈수록 그 돌출된 폭이 점차 좁아지게 구성한 나선부를 가지는 앵커와,
일정길이를 가진 와이어와,
일정 길이로 형성된 관 형태로, 그 일단에는 드릴류에 끼움 되어 설치할 수 있는 설치부를 구비하고, 그 타측 내부에는 중앙을 관통하는 키를 형성하며, 키 방향의 수직 방향 양단은 와이어의 양단이 끼울 수 있는 트임부를 형성한 보조구로 구성된 와이어형 지지구를 더 구비하여,
상기 와이어를 앵커의 고정공에 끼움 된 상태에서 와이어의 양단이 상부로 돌출되게 구성하며, 설치부를 통해 드릴류에 끼워 설치된 보조구 내부로, 상기 앵커의 상부로 돌출된 와이어 양단이 각각 트임부를 통해서 보조구 내부로 삽입하고, 보조구의 키가 앵커의 키자리에 안착한 상태에서, 드릴류을 작동하면 앵커가 드릴류의 회전하는 힘과 나선부에 의해 지면을 파고들어가 박히도록 함으로써,
상기 드릴류의 작동 및 나선부에 의해 앵커의 설치가 용이함을 특징으로 하는 나선부를 가지는 앵커.
A cylindrical insertion shaft penetrates the inner side in the longitudinal direction, and forms a key seat at an upper end thereof, and a plurality of penetrating fixing holes are formed at an upper side of the insertion shaft, and along the outer periphery of the lower fixing hole. Spiral-shaped protruding spirals protruding in the circumferential direction are integrally formed, and the spirals have anchors having spirals configured such that their protruding widths gradually become narrower toward the lower portion of the insertion shaft;
Wire with constant length,
In the form of a tube formed in a predetermined length, one end is provided with a mounting portion that can be fitted to install the drill, the inside of the other side to form a key penetrating through the center, both ends of the wire in the vertical direction of the key direction can be fitted It is further provided with a wire-shaped support consisting of an auxiliary tool formed a recessed portion,
Both ends of the wires are configured to protrude upwards in the state where the wires are fitted in the fixing holes of the anchors. Insert the inside of the assisting tool, and when the drill is operated with the assisting tool's key seated in the key seat of the anchor, the anchor is drilled into the ground by the rotating force and the spiral of the drill,
Anchor having a spiral portion, characterized in that the installation of the anchor is easy by the operation of the drill and the spiral portion.
삭제delete 통상의 식생매트를 이용한 녹화 공법에 있어서,
청구항 2에 해당하는 앵커가 구비되어,
시공할 시공지의 드러나는 흙을 고르게 정리하는 시공지 정리 공정(S1);
드릴류를 이용하여 다수의 앵커를 설치하되, 선행공정에서 정리된 시공지에 앵커가 지면 하부로 박히도록 설치하고, 나선형 앵커의 각 와이어 양단은 지면 상부로 돌출되게 하는 앵커 설치 공정(S2);
시공지에 식생매트를 포설하고, 앞서 돌출된 와이어는 식생매트 상부로 돌출되도록 하는 식생매트 포설 공정(S3);
상기 식생매트 상부로 고정망을 격자 구조로 설치하는 고정망 설치 공정(S4);
상기 돌출되어 있는 와이어를 고정망에 고정하는 와이어 고정 공정(S5);
전체적으로 흙을 포설하는 흙 포설 공정(S7)으로 완료됨을 특징으로 하는 나선부를 가지는 앵커와 식생매트를 이용한 녹화 공법.
In the greening method using a normal vegetation mat,
The anchor according to claim 2 is provided,
A construction site cleaning process for uniformly arranging the exposed soil of the construction site to be constructed (S1);
Install a plurality of anchors using drills, the anchors are installed in the construction site arranged in the preceding process so that the anchors are driven to the bottom of the ground, and each wire end of the spiral anchor is anchored to be projected to the upper portion of the ground (S2);
Vegetation mat laying on the construction site, the wire is projected before the vegetation mat laying step (S3) to protrude to the upper vegetation mat;
A fixed net installation process (S4) of installing the fixed net in a lattice structure above the vegetation mat;
A wire fixing step (S5) of fixing the protruding wire to a fixed net;
Greening method using an anchor and a vegetation mat having a spiral, characterized in that completed in the soil laying step (S7) for laying soil as a whole.
제 4항에 있어서,
내부가 관통된 테두리 형상으로 구성하고, 그 가장자리의 저면에 돌출된 고정부가 일체로 다수개 형성된 구조의 고정구가 더 구비되어,
고정망 설치 공정(S4) 다음에는,
앞서 설치된 고정망과 식생매트 사이에 고정구를 설치하되, 그 고정부가 지면에 박히도록 고정구를 다수개 설치하는 고정구 설치 공정(S4´)이 추가됨을 특징으로 하는 나선부를 가지는 앵커와 식생매트를 이용한 녹화 공법.
The method of claim 4, wherein
It is configured with a rim shape penetrating the inside, and is further provided with a fastener of the structure formed a plurality of fixed parts protruding on the bottom of the edge,
After the fixed network installation process (S4),
A fixture is installed between the anchoring net and the vegetation mat previously installed, but the anchoring process and the vegetation mat having the spiral portion are characterized by the addition of a fixture installation process (S4´) for installing a plurality of fixtures so that the fixture is embedded in the ground. Method.
제 4항에 있어서,
상기 고정망 설치 공정(S4) 또는, 와이어 고정 공정(S5) 다음에는,
상부 측면에 고정공을 다수 구비하고, 길이 방향을 따라 내부가 관통된 원통형의 삽입축 외주연을 따라 원주방향으로 돌출되며, 하부로 갈수록 점차 돌출폭이 좁아진 나선부를 가진 앵커와, 이 앵커의 삽입축에 일단은 뾰족하고 타단은 고리가 형성된 고리형 지지구의 뾰족한 부분을 끼워 고정수단을 고정공에 체결한 고리형 지지구가 설치된 앵커를, 상기 설치된 고정망의 가장자리에 해당하는 고정망에 설치하여, 고리형 지지구의 고리가 고정망에 걸리도록 설치하는 고정망 가장자리 고정 공정(S6)이 추가됨을 특징으로 하는 나선부를 가지는 앵커와 식생매트를 이용한 녹화 공법.
The method of claim 4, wherein
After the fixed net installation step (S4) or wire fixing step (S5),
Anchor having a plurality of fixing holes on the upper side, helical portion projecting in the circumferential direction along the outer periphery of the cylindrical insertion shaft penetrating the inside along the longitudinal direction, and gradually narrowing the protrusion width toward the bottom, the insertion of this anchor The anchor is provided with an annular support for fastening the fixing means to the fixing hole by inserting the pointed portion of the annular support having a pointed end and a ring formed at the other end thereof, , Fixing net edge fixing step (S6) is installed so that the hook of the annular support is fastened to the fixing net is a greening method using an anchor and vegetation mat having a spiral portion.
제 4항 내지 제 6항 중 어느 한 항에 있어서,
상기 식생매트는 메시 구조의 보강네트, 종자를 포함하는 시트, 선이 입체적인 얽힌 구조의 침식방지매트가 순차로 형성된 구조이고,
상기 녹화 공법에 사용된 시공자재의 재질은, 부식 방지 코팅이 된 것이거나, 비부식성 재질로 구성됨을 특징으로 하는 나선부를 가지는 앵커와 식생매트를 이용한 녹화 공법.
The method according to any one of claims 4 to 6,
The vegetation mat is a structure in which a reinforcing net of a mesh structure, a sheet including seeds, and an erosion prevention mat of a three-dimensional entangled structure are sequentially formed,
The material of the construction material used in the greening method, the anti-corrosive coating, or a non-corrosive material, characterized in that it consists of a non-corrosive material anchoring and vegetation mat using a vegetation mat.
제 4항 내지 제 6항 중 어느 한 항에 있어서,
상기 식생매트는,
메시 구조의 보강네트, 종자를 포함하는 시트, 선이 입체적인 얽힌 구조의 침식방지매트가 순차로 형성된 구조이고,
상기 녹화 공법에 사용된 시공자재의 중 적어도 하나는 생분해성 재질로 구성됨을 특징으로 하는 나선부를 가지는 앵커와 식생매트를 이용한 녹화 공법.
The method according to any one of claims 4 to 6,
The vegetation mat,
Reinforcing net of mesh structure, sheet containing seeds, erosion prevention mat of three-dimensional entangled structure is formed in sequence,
At least one of the construction materials used in the greening method is a greening method using an anchor having a spiral portion and vegetation mat, characterized in that composed of a biodegradable material.
KR1020110016891A 2011-02-25 2011-02-25 The anchor with helix and the vegetation construction method with the anchor and egetation mat KR101096304B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110016891A KR101096304B1 (en) 2011-02-25 2011-02-25 The anchor with helix and the vegetation construction method with the anchor and egetation mat

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110016891A KR101096304B1 (en) 2011-02-25 2011-02-25 The anchor with helix and the vegetation construction method with the anchor and egetation mat

Publications (1)

Publication Number Publication Date
KR101096304B1 true KR101096304B1 (en) 2011-12-20

Family

ID=45506630

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110016891A KR101096304B1 (en) 2011-02-25 2011-02-25 The anchor with helix and the vegetation construction method with the anchor and egetation mat

Country Status (1)

Country Link
KR (1) KR101096304B1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101261494B1 (en) 2013-02-13 2013-05-30 (주)생태공간 Coupling tool for vegetation cultivating panel and vegetation cultivating panel assembly including the same
WO2015009088A1 (en) * 2013-07-18 2015-01-22 주식회사 보림 Underground buried pile
KR200476500Y1 (en) * 2014-06-27 2015-03-19 주식회사 석송 The eco-friendly vegetational rapids structure
KR101801035B1 (en) * 2016-11-29 2017-12-20 정송천 Lawn protection mate
WO2018101553A1 (en) * 2016-11-29 2018-06-07 정송천 Subsidence prevention-type lawn protective mat system and construction method therefor
KR20180092023A (en) * 2017-02-08 2018-08-17 정송천 Lawn protection mate and using the same
KR102253411B1 (en) * 2020-08-04 2021-05-18 주식회사 석송 Ground fixing structurer which the plants can be lived in
KR102275088B1 (en) 2020-12-01 2021-07-08 한국건설기술연구원 Anchor with a vegetation space, a shore protection block with an anchor, and a method of installing a vegetation mat using the same
KR102626135B1 (en) * 2023-06-08 2024-01-17 에이치디씨현대산업개발 주식회사 Inter-floor floor impact sound blocking structure and inter-floor floor floor impact sound blocking structure construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200395340Y1 (en) * 2005-06-20 2005-09-08 장문석 Revetment plate
KR100925982B1 (en) 2007-10-26 2009-11-10 구자석 A greening core-net construction method for an incline plane protection
KR200450097Y1 (en) * 2008-04-03 2010-09-03 임용관 Perforating drill of earth anchor operative without draining water and soil

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200395340Y1 (en) * 2005-06-20 2005-09-08 장문석 Revetment plate
KR100925982B1 (en) 2007-10-26 2009-11-10 구자석 A greening core-net construction method for an incline plane protection
KR200450097Y1 (en) * 2008-04-03 2010-09-03 임용관 Perforating drill of earth anchor operative without draining water and soil

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101261494B1 (en) 2013-02-13 2013-05-30 (주)생태공간 Coupling tool for vegetation cultivating panel and vegetation cultivating panel assembly including the same
WO2015009088A1 (en) * 2013-07-18 2015-01-22 주식회사 보림 Underground buried pile
KR101545189B1 (en) * 2013-07-18 2015-08-20 주식회사 보림 Linked holding anchor
KR200476500Y1 (en) * 2014-06-27 2015-03-19 주식회사 석송 The eco-friendly vegetational rapids structure
KR101801035B1 (en) * 2016-11-29 2017-12-20 정송천 Lawn protection mate
WO2018101553A1 (en) * 2016-11-29 2018-06-07 정송천 Subsidence prevention-type lawn protective mat system and construction method therefor
KR20180092023A (en) * 2017-02-08 2018-08-17 정송천 Lawn protection mate and using the same
KR102000198B1 (en) * 2017-02-08 2019-07-15 정송천 Lawn protection mate and using the same
KR102253411B1 (en) * 2020-08-04 2021-05-18 주식회사 석송 Ground fixing structurer which the plants can be lived in
KR102275088B1 (en) 2020-12-01 2021-07-08 한국건설기술연구원 Anchor with a vegetation space, a shore protection block with an anchor, and a method of installing a vegetation mat using the same
KR102626135B1 (en) * 2023-06-08 2024-01-17 에이치디씨현대산업개발 주식회사 Inter-floor floor impact sound blocking structure and inter-floor floor floor impact sound blocking structure construction method

Similar Documents

Publication Publication Date Title
KR101096304B1 (en) The anchor with helix and the vegetation construction method with the anchor and egetation mat
US20220372725A1 (en) Drain assembly for use in an outdoor setting
KR200448984Y1 (en) Steel plate anchor fixing device used for greening structure of front surface
US11306454B2 (en) Erosion control apparatus
KR100844925B1 (en) A device for fixing a natural stone
KR101065626B1 (en) Microsoft pile and construction methods
KR101210572B1 (en) Stone net and construction method thereof
WO2018045224A1 (en) Erosion control apparatus
JP4313837B1 (en) Waterside environmental improvement method in existing concrete revetment using pussy willow
KR100938119B1 (en) Fixing apparatus for greening slope of a ground
KR101790243B1 (en) Stone net structure using stone net fixing member
KR101401730B1 (en) Reinforcing method of bearing power for soft ground and reinforcing apparatus used in the same method
KR20030038894A (en) Plant tree structure for surface of slope surface
KR100402924B1 (en) slope afforestation sheet and thereby method of construction for slope afforestation
CN114541325B (en) Ecological slope protection of hydraulic engineering and construction method thereof
US9394661B2 (en) Maintainable soil drain
KR101764407B1 (en) Stone net structure and construction method using thereof
KR101384586B1 (en) Underground structure and structure for protecting landslide using the same
KR101995201B1 (en) Construction method for ultra eco-mat anchoring slope
KR20110032069A (en) Stakes for seed net and construction method of seed net using the same
KR101546723B1 (en) Stabilizing structure of slope area and construction method of stabilizing slope area using the same
CN212316949U (en) Supporting construction of side slope
CN110939141A (en) Supporting construction of side slope
KR100930115B1 (en) Environment-friendly slope type fill section structure and its construction method
KR100992076B1 (en) Structure of raising the ground level and excecution method thereof

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20141202

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20151213

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20170213

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20181212

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20191123