KR101075574B1 - A reinforced soil retaining wall for cutting slope and method of construction for the same - Google Patents

A reinforced soil retaining wall for cutting slope and method of construction for the same Download PDF

Info

Publication number
KR101075574B1
KR101075574B1 KR1020110059696A KR20110059696A KR101075574B1 KR 101075574 B1 KR101075574 B1 KR 101075574B1 KR 1020110059696 A KR1020110059696 A KR 1020110059696A KR 20110059696 A KR20110059696 A KR 20110059696A KR 101075574 B1 KR101075574 B1 KR 101075574B1
Authority
KR
South Korea
Prior art keywords
reinforcement
retaining wall
primary
pressure plate
installing
Prior art date
Application number
KR1020110059696A
Other languages
Korean (ko)
Inventor
원명수
Original Assignee
지반이엔씨 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 지반이엔씨 주식회사 filed Critical 지반이엔씨 주식회사
Priority to KR1020110059696A priority Critical patent/KR101075574B1/en
Application granted granted Critical
Publication of KR101075574B1 publication Critical patent/KR101075574B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B37/00Nuts or like thread-engaging members
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

본 발명은 다양한 절취지반에 있어서 구축되는 보강토옹벽의 횡방향 내구성을 향상시키고 응력 분산이 가능하도록 한 보강토옹벽을 제공하고자 한 것이다. 이를 위해, 본 발명은 보강토옹벽이 설치되는 지형의 상부로부터 하측으로 1차천공홀을 형성하는 단계와, 상기 형성된 1차천공홀에 1차그라우팅재를 주입하는 단계와, 상기 주입된 1차그라우팅재의 전방측 지형을 절취하는 단계와, 상기 절취된 지형의 전방 외측으로 상하 및 좌우 각각 다수 열을 이룸과 동시에 소정 길이 노출된 상태로 보강재를 설치하는 단계와, 상기 외부 노출된 보강재 중 좌우 횡방향으로 복수 개의 보강재에 동시에 연결되도록 1차지압판을 설치하는 단계 및 상기 1차지압판으로부터 소정 간격 이격된 상태로 상기 보강재에 2차지압판을 설치하는 단계를 포함하여 구성되는 절토용 보강토옹벽의 시공방법을 제공한다.It is an object of the present invention to provide a reinforced soil retaining wall for improving the lateral durability of reinforced soil retaining walls constructed in various cutting grounds and enabling stress distribution. To this end, the present invention comprises the steps of forming a primary boring hole from the top of the top of the terrain on which the reinforced earth retaining wall is installed, injecting the primary grouting material into the formed primary boring hole, and the injected primary grouting Cutting the front side of the ash, installing a reinforcement in a state of being exposed to a predetermined length at the same time as forming a plurality of rows each up and down and left and right outward of the cut terrain, and in the left and right transverse direction of the externally exposed reinforcement Installing a primary pressure plate to be connected to a plurality of reinforcement at the same time and the step of installing a secondary pressure plate on the reinforcement in a state spaced apart from the primary pressure plate by a predetermined interval to the construction method to provide.

Description

절토용 보강토옹벽 및 그 시공방법{A reinforced soil retaining wall for cutting slope and method of construction for the same}Reinforced soil retaining wall for cutting and its construction method {A reinforced soil retaining wall for cutting slope and method of construction for the same}

본 발명은 보강토옹벽에 관한 것으로서, 더욱 상세하게는 지반의 성질에 따라서 구축 형태를 달리 할 수 있으며 보강재에 걸리는 응력을 분산시켜 전체적인 안전성을 크게 향상시킨 절토용 보강토옹벽 및 그 시공방법에 관한 것이다.The present invention relates to a reinforced soil retaining wall, and more particularly, to a reinforcement soil retaining wall and a construction method which can vary the construction form according to the properties of the ground and greatly improves the overall safety by dispersing the stress applied to the reinforcement.

일반적으로 보강토옹벽은 표고 차이를 유지하기 위하여 벽의 한쪽 면 상에서 물질을 억누르는 벽체로서 정의되며, 이러한 보강토옹벽은 형태별로 중력식, 보강콘크리트식, 보강토식 보강토옹벽 등으로 구분된다.In general, reinforcement soil wall is defined as a wall that suppresses the material on one side of the wall in order to maintain the difference in elevation, and such reinforcement soil wall is divided into gravity type, reinforced concrete type and reinforced soil reinforcement soil wall.

이하, 종래의 일반적인 보강토옹벽 구조에 대하여 설명하면 다음과 같다.Hereinafter, a conventional general reinforced earth retaining wall structure will be described.

도 1a 내지 도 1f는 종래 일반적인 보강토옹벽이 구축되는 과정을 순서대로 나타낸 측면도이다.1A to 1F are side views illustrating a process of constructing a conventional general reinforcement soil wall in order.

먼저 도 1a에 도시된 바와 같이, 지반의 일부 구간을 상측으로부터 하향으로 절토하는 단계를 거치게 된다.First, as shown in FIG. 1A, a portion of the ground is cut down from the upper side.

그리고, 도 1b에서와 같이, 굴착된 지반의 내측으로 천공홀(10)을 형성하고, 도 1c에서와 같이 네일(11) 설치 및 그라우팅재(12) 타설을 행하여 지반보강을 수행한다.Then, as shown in Figure 1b, the perforated hole 10 is formed in the inside of the excavated ground, and as shown in Figure 1c, the nail 11 is installed and the grouting material 12 is placed to perform the ground reinforcement.

다음으로는, 도 1d에서와 같이, 임시벽체로서 경사면에 숏크리트(20) 작업을 수행하고 상황에 따라서는 전방 노출된 네일(11)에 지압판(미도시)을 체결한다.Next, as shown in FIG. 1D, the shotcrete 20 is performed on the inclined surface as a temporary wall and, depending on the situation, the pressure plate (not shown) is fastened to the nail 11 exposed forward.

이와 같은 과정을 하향으로 계획절토고에 이르기까지 다단에 걸쳐 반복 수행하면 도 1e와 같은 형태를 이루게 되고, 최종적으로는 도 1f에서와 같이 배수공(미도시) 등 및 최종 옹벽(30) 시공을 통하여 전체 보강토옹벽의 구축이 완료된다.Repeating this process in multiple stages until the planned cut-off to the bottom is achieved as shown in Figure 1e, and finally through the construction of drainage holes (not shown) and the final retaining wall 30, as shown in Figure 1f The construction of the whole reinforced soil retaining wall is completed.

그리고, 이와 같은 종래 보강토 옹벽의 구축 과정에 있어서 지압판 또는 쇼크리트 등의 공법은 생략하여 옹벽이 시공되기도 한다.In addition, in the process of constructing such a conventional reinforced soil retaining wall, a method such as a pressure plate or shockcrete may be omitted and a retaining wall may be constructed.

상술한 절토용 보강토옹벽의 경우는 종래 다양한 보강토옹벽 중 일 형태를 도시 및 설명한 것이며, 이 외에도 별도로 콘크리트 블록을 적층하는 방식 등의 보강토옹벽 등도 많이 시공되고 있는 추세이다.In the case of the above-mentioned reinforcement earth retaining wall for cutting, one form of various reinforcement earth retaining walls is conventionally illustrated and described. In addition, reinforcement earth retaining walls, such as a method of stacking concrete blocks, are tended to be constructed.

도 2a 내지 도 2e는 종래 보강토옹벽이 파괴되는 몇 가지 형태를 나타낸 도면들이다.2a to 2e are views showing some forms of conventional reinforced soil retaining wall is broken.

도시된 바와 같이, 종래 보강토옹벽의 경우는 옹벽 전면의 벽체가 시간이 지남에 따라 도 2a, 도 2b에서와 같이, 보강토옹벽의 후방측 지형 앞쪽의 주동영역에 걸쳐 하중이 걸리어 슬라이딩 이동이 발생하여 앞쪽 부분의 옹벽 전체가 붕괴되는 경우가 발생하였다.As shown, in the case of the conventional reinforcement earth retaining wall, as the wall of the retaining wall front over time, as shown in Figures 2a, 2b, the load is applied over the driving area in front of the terrain on the rear side of the reinforcement earth retaining wall, the sliding movement occurs As a result, the entire retaining wall of the front part collapsed.

또는, 도 2c 및 도 2d에서와 같이 각각의 쏘일 네일(11)에 연결된 각각의 지압판(17)에 집중적인 하중이 걸리어 지압판과 함께 옹벽의 일부 영역이 탈락하는 현상이 발생되기도 하였으며, 이때 일부 영역의 탈락으로 인하여 다른 옹벽 영역도 시간이 지남에 따라 내구성이 약화되어 마찬가지로 탈락되는 경우가 빈번하였다.Alternatively, as shown in FIGS. 2C and 2D, intensive loads are applied to the respective pressure plates 17 connected to the respective nail nails 11, thereby causing some areas of the retaining wall to fall off together with the pressure plates. Due to the dropping out of the area, other retaining wall areas were also frequently dropped due to a decrease in durability over time.

나아가, 도 2e와 같은 1차 보강안정 후 전방측에 지오블록(22) 등을 설치하여 축조되는 옹벽의 경우에는 지오블록(22)과 1차지반안정을 위한 옹벽(21) 사이에서 채워지는 잡석(28)에 배수구(24)를 통하여 배수되는 지표수가 저장되는 경우가 있는데, 이 경우 지표수가 일정 위치에 집중되어 저장되는 경우 그에 따른 하중이 전방의 지오블록에 응력으로 작용하여 전방 지오블록이 탈락 또는 붕괴되는 경우도 발생하였다.Furthermore, in the case of the retaining wall constructed by installing the geoblock 22 on the front side after the primary reinforcement stability as shown in FIG. 2E, the rubble filled between the geoblock 22 and the retaining wall 21 for the primary ground stability There is a case where the surface water drained through the drain hole 24 is stored in (28), in this case, if the surface water is stored concentrated in a certain position, the resulting load acts as a stress on the front geoblock, the front geoblock is eliminated Or collapsed.

본 발명은 상술한 종래의 문제점 및 제결점을 해결하기 위하여 안출된 것으로서, 본 발명의 목적은 다음과 같다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the aforementioned problems and drawbacks of the prior art, and an object of the present invention is as follows.

첫째, 본 발명은 절토 후 성토 및 절성토 경계면에서의 평면파괴 등을 방지할 수 있는 보강토옹벽을 제공하는데 그 목적이 있다.First, it is an object of the present invention to provide a reinforcement soil retaining wall that can prevent the plane destruction at the interface of the fill and cut soil after cutting.

둘째, 본 발명은 지표수 유입에 따른 우수 등의 집중에 의하여 판넬 또는 블록이 탈락하거나 활동파괴가 일어나는 것을 방지할 수 있는 보강토옹벽을 제공하는데 그 목적이 있다.Secondly, an object of the present invention is to provide a reinforced soil retaining wall that can prevent the panel or block from falling off or destroying activity due to concentration of rainwater due to the inflow of surface water.

셋째, 지반의 성질에 따라 선택적으로 공법을 적용하여 전체적으로 안정된 보강토옹벽을 제공함과 동시에 전체 시공기간 및 시공작업을 효율성 있도록 하는 보강토옹벽을 제공하는데 그 목적이 있다.Third, the purpose of the present invention is to provide a reinforcement soil wall that can be applied to the construction method selectively according to the nature of the ground, and to make the overall construction period and construction work efficient at the same time.

넷째, 보강토 전체 구조에 있어서 하중이 분산되어 구조물의 안정성을 향상시킨 보강토옹벽을 제공하는데 그 목적이 있다.Fourth, the purpose of the present invention is to provide a reinforced soil retaining wall in which the load is distributed in the overall structure of the reinforced soil to improve the stability of the structure.

상술한 목적을 달성하기 위하여, 본 발명은 보강토옹벽이 설치되는 지형의 상부로부터 하측으로 1차천공홀을 형성하는 단계와, 상기 형성된 1차천공홀에 1차그라우팅재를 주입하는 단계와, 상기 주입된 1차그라우팅재의 전방측 지형을 절취하는 단계와, 상기 절취된 지형의 전방 외측으로 상하 및 좌우 각각 다수 열을 이룸과 동시에 소정 길이 노출된 상태로 보강재를 설치하는 단계와, 상기 외부 노출된 보강재 중 좌우 횡방향으로 복수 개의 보강재에 동시에 연결되도록 1차지압판을 설치하는 단계 및 상기 1차지압판으로부터 소정 간격 이격된 상태로 상기 보강재에 2차지압판을 설치하는 단계를 포함하여 구성되는 절토용 보강토옹벽의 시공방법을 제공한다.
여기서, 상기 1차천공홀에 보강빔을 설치하는 단계를 더 포함하여 구성될 수 있다.
또한, 상기 보강빔은 절토 지형의 상부로 일부 노출되게 설치되며, 상기 노출된 보강빔에 보강콘크리트캡을 설치하는 단계를 더 포함하여 구성될 수 있다.
그리고, 상기 2차지압판은 횡방향으로 복수 개의 보강재에 동시에 체결될 수 있다.
한편, 본 발명은 상부로부터 하측으로 형성된 1차천공홀에 1차그라우팅재를 주입하여 형성되는 보강칼럼모듈과, 상기 보강칼럼모듈의 전방측 절토되는 지형에 상하 및 좌우 다수 열을 이루도록 일단부가 외부에 노출된 상태로 설치되는 다수 개의 보강재와, 상기 외부 노출된 보강재 중 좌우 횡방향으로 복수 개의 보강재에 동시에 연결되도록 설치되는 1차지압판과, 상기 1차지압판으로부터 소정 간격 이격된 상태로 상기 보강재의 노출된 부위에 설치되는 2차지압판 및 상기 1차지압판 및 2차지압판이 내설된 상태를 이루도록 함과 동시에 상기 노출된 보강재의 전방측에 설치되는 콘크리트 옹벽을 포함하여 구성되는 절토용 보강토옹벽을 제공한다.
In order to achieve the above object, the present invention comprises the steps of forming a primary punching hole from the top of the top of the terrain on which the reinforced earth retaining wall is installed, and injecting the primary grouting material into the formed primary drilling hole, and Cutting the front topography of the injected primary grouting material, and installing a reinforcement in a state of exposing a predetermined length at the same time as forming a plurality of rows respectively up and down and left and right toward the front and outside of the cut topography; Reinforcement soil for cutting comprising the steps of installing the primary pressure plate to be connected to the plurality of reinforcement at the same time in the left and right of the reinforcement and the secondary pressure plate on the reinforcement in a state spaced apart from the primary pressure plate by a predetermined interval Provide the construction method of the retaining wall.
Here, the method may further include installing a reinforcing beam in the primary drilling hole.
In addition, the reinforcement beam is installed to be partially exposed to the top of the cut terrain, it may be configured to further comprise the step of installing a reinforcement concrete cap on the exposed reinforcement beam.
In addition, the secondary pressure plate may be simultaneously fastened to a plurality of reinforcing members in the transverse direction.
On the other hand, the present invention is the reinforcement column module is formed by injecting the primary grouting material into the primary drilling hole formed from the upper side to the lower side, one end portion to form a plurality of rows up and down and left and right on the front cut of the reinforcement column module A plurality of reinforcing members which are installed in a state exposed to the first reinforcement member, and a primary pressure plate which is installed to be connected to a plurality of reinforcing members simultaneously in the left and right transverse direction of the externally exposed reinforcing members; Provides a reinforcement earth retaining wall for the cut including a secondary retaining plate installed on the exposed site and the concrete retaining wall is installed on the front side of the exposed reinforcement while at the same time to achieve the state of the primary pressure plate and the secondary pressure plate. do.

삭제delete

삭제delete

삭제delete

삭제delete

삭제delete

삭제delete

삭제delete

상기와 같이 구성된 본 발명 절토용 보강토옹벽의 시공방법은 다음과 같은 효과가 있다.The construction method of the present invention cut reinforcement soil retaining wall configured as described above has the following effects.

첫째, 본 발명은 지반의 견고한 정도에 따라서 보강칼럼 설치단계 등을 선택 적용하여 전체 보강토옹벽이 시공되도록 함으로써 전체적으로 안전성이 향상되도록 함과 동시에 시공기간 및 시공비용을 줄일 수 있는 효과를 가져온다.First, the present invention, by applying the reinforcing column installation step, etc. according to the solidity of the ground so that the entire reinforcement soil wall is constructed, the overall safety is improved and at the same time the construction period and construction costs are reduced.

둘째, 본 발명은 지압판을 이중으로 설치하여 응력의 분산이 이루어지도록 함으로써 안전성 및 내구성을 향상된 보강토옹벽을 제공할 수 있게 된다.Second, the present invention is to provide a reinforced earth retaining wall with improved safety and durability by providing a double pressure plate to distribute the stress.

셋째, 본 발명은 1차지압판을 횡방향으로 일정 길이 연장되도록 하되 복수 개의 보강재에 동시에 결합되도록 함으로써 힘의 분산효과를 극대화할 수 있게 되며 지압판의 설치작업 또한 간편해지게 되는 효과를 가져온다.Third, the present invention is to extend the length of the primary pressure plate in the transverse direction but to be coupled to the plurality of reinforcement at the same time to maximize the effect of the force distribution and brings the effect of simplifying the installation of the pressure plate.

넷째, 보강콘크리트캡을 별도 설치하여 보강칼럼을 지면에 일체화시킴으로써 굴착과정 중 발생할 수 있는 전도와 활동파괴에 대한 저항성을 커지게 함으로써 전반적인 안전성이 향상되고 굴착 중 시공이 용이하여 지는 효과를 가져온다.Fourth, by installing a reinforced concrete cap to integrate the reinforcement column on the ground to increase the resistance to conduction and active destruction that may occur during the excavation process, the overall safety is improved and the construction is easy during the excavation.

다섯째, 본 발명은 안정된 보강토옹벽에 별도의 식생용 구성을 적용함으로써 미관을 향상시킬 수 있는 효과를 가져온다.Fifth, the present invention has the effect of improving the appearance by applying a separate vegetation configuration to the stable reinforced soil retaining wall.

도 1a 내지 도 1f는 종래 일반적인 보강토옹벽 시공방법을 순차적으로 나타낸 측면도;
도 2a 내지 도 2e는 종래 보강토옹벽이 파괴되는 다 수의 형태를 나타낸 도면들;
도 3은 본 발명에 따른 보강토옹벽에 있어서 보강칼럼이 설치된 모습을 나타낸 측단면도;
도 4는 본 발명에 따른 보강토옹벽에 있어서 보강칼럼이 설치된 모습을 나타낸 평면도;
도 5는 본 발명에 따른 보강토옹벽에 있어서 보강칼럼에 보강콘크리트캡이 설치된 모습을 나타낸 측단면도;
도 6은 본 발명에 따른 보강토옹벽에 있어서 보강재 및 지압판이 설치된 모습을 나타낸 측단면도;
도 7은 본 발명에 따른 보강토옹벽에 있어서 계획고까지 굴착된 사면에 보강재 및 지압판이 설치된 모습을 나타낸 측단면도;
도 8은 본 발명에 따른 보강토옹벽에 있어서 계획고까지 굴착된 사면에 보강재 및 지압판이 설치된 모습을 나타낸 사시도;
도 9는 본 발명에 따른 보강토옹벽에 설치되는 1차지압판을 나타낸 도면;
도 10 내지 도 12는 본 발명에 따른 보강토옹벽에 설치되는 2차지압판을 나타낸 도면;
도 13은 본 발명에 따른 보강토옹벽에 있어서 철근배근 및 거푸집 등이 설치된 모습을 나타낸 측단면도;
도 14는 본 발명에 따른 보강토옹벽이 구축된 모습을 나타낸 측단면도;
도 15는 본 발명에 따른 보강토옹벽의 전방에 구축되는 입체 조형물의 일 예를 나타낸 도면;
도 16은 다양한 암반 및 지형에 따른 본 발명 보강토옹벽이 다양한 형태로 구축되는 모습을 나타낸 측단면도; 및
도 17은 본 발명에 따른 절토용 보강토옹벽을 시공하는 단계를 나타낸 순서도이다.
Figure 1a to 1f is a side view sequentially showing a conventional general reinforcement retaining wall construction method;
Figures 2a to 2e is a view showing a number of forms of conventional reinforced earth retaining wall is broken;
Figure 3 is a side cross-sectional view showing a state in which the reinforcement column is installed in the reinforcement soil retaining wall according to the present invention;
4 is a plan view showing a state in which the reinforcement column is installed in the reinforcement soil retaining wall according to the present invention;
Figure 5 is a side cross-sectional view showing a state in which the reinforcement concrete cap is installed on the reinforcement column in the reinforcement soil retaining wall according to the present invention;
Figure 6 is a side cross-sectional view showing a state in which the reinforcement and the pressure plate is installed in the reinforcement soil retaining wall according to the present invention;
Figure 7 is a side cross-sectional view showing a state in which the reinforcement and the pressure plate is installed on the slope excavated in the reinforcement soil retaining wall according to the present invention;
8 is a perspective view showing the reinforcement and the pressure plate is installed on the slope excavated to the plan in the reinforcement soil retaining wall according to the present invention;
9 is a view showing a primary pressure plate is installed on the reinforced soil retaining wall according to the present invention;
10 to 12 is a view showing a secondary pressure plate is installed on the reinforced soil retaining wall according to the present invention;
Figure 13 is a side cross-sectional view showing a state in which reinforcement and formwork is installed in the reinforcement soil retaining wall according to the present invention;
Figure 14 is a side cross-sectional view showing a state that the reinforced soil retaining wall is constructed in accordance with the present invention;
15 is a view showing an example of a three-dimensional sculpture that is built in front of the reinforced soil retaining wall according to the present invention;
Figure 16 is a side cross-sectional view showing a state in which the present invention reinforcement soil retaining wall is constructed in various forms according to a variety of rock and terrain; And
Figure 17 is a flow chart showing the steps of constructing a reinforced soil retaining wall for cutting according to the present invention.

이하 본 발명의 목적이 구체적으로 실현될 수 있는 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 설명한다. 본 실시예를 설명함에 있어서, 동일 구성에 대해서는 동일 명칭 및 동일 부호가 사용되며 이에 따른 부가적인 설명은 생략하기로 한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings. In describing the present embodiment, the same designations and the same reference numerals are used for the same components, and further description thereof will be omitted.

먼저, 첨부된 도면을 참조하여 본 발명 절토용 보강토옹벽 및 이를 위한 시공방법의 바람직한 실시예에 따른 구조 및 그 시공방법을 설명하기로 한다.First, with reference to the accompanying drawings will be described the structure and construction method according to a preferred embodiment of the present invention reinforcement soil retaining wall and a construction method therefor.

도 3은 본 발명에 따른 절토용 보강토옹벽에 있어서 지반의 1차적 안정성을 가져오기 위한 보강칼럼모듈(85)이 설치된 모습을 나타낸 측단면도이고, 도 4는 본 발명에 따른 절토용 보강토옹벽에 있어서 보강칼럼모듈이 설치된 모습을 나타낸 평면도이며, 도 17은 본 발명에 따른 보강토옹벽의 시공방법을 나타낸 순서도이다.Figure 3 is a side cross-sectional view showing a reinforcement column module 85 is installed to bring the primary stability of the ground in the reinforcement earth retaining wall for cut according to the present invention, Figure 4 is a reinforcement earth retaining wall for cutting in accordance with the present invention 17 is a plan view showing a reinforcement column module installed, and FIG. 17 is a flowchart illustrating a method of constructing a reinforced soil retaining wall according to the present invention.

도 3 및 도 4에 도시된 바와 같이, 지형의 견고한 정도를 분석하여 연약한 지반으로 파악된 지형에 보강토옹벽을 축조 시에는 지반의 기초 안정을 위하여 보강칼럼모듈(85)이 설치됨이 바람직하다(S11).As shown in Figure 3 and 4, when constructing the reinforcement soil wall on the terrain identified as soft ground by analyzing the degree of solidity of the terrain it is preferable that the reinforcement column module 85 is installed for the foundation stability of the ground (S11) ).

이를 위해, 보강토옹벽이 시공될 지형에 횡방향을 따라서 상하로 다수의 1차천공홀(80)을 굴착하도록 한다(S1).To this end, the reinforced earth retaining wall is to be excavated a plurality of primary drilling holes 80 in the vertical direction along the transverse direction (S1).

이때, 상기 1차천공홀(80)은 절토계획고보다 소정 깊이 더 깊게 형성되며, 상기 1차천공홀(80)은, 첨부된 도 4에서와 같이, 양측 가장자리 부위가 일부 중첩된 형태로 형성함이 바람직하다. 이와 같이 하는 이유는 차후 그라우팅재가 굳어진 후에 보강칼럼모듈(85)이 전체가 일체화되도록 함으로써 내구성이 향상되도록 하기 위함이다.In this case, the primary drilling hole 80 is formed deeper than the cut plan height, and the primary drilling hole 80, as shown in Figure 4, is formed in a form in which both side edge portions overlapped It is preferable to. The reason for doing so is to improve durability by allowing the whole reinforcing column module 85 to be integrated after the grouting material is hardened in the future.

상기 1차천공홀(80)은 축조되는 보강토옹벽과 수평하게 형성됨이 바람직하며, 도 3에서는 거의 수직하게 형성되는 보강토옹벽이 축조 시에 1차천공홀(800이 형성된 것을 나타낸 것이다.The primary boring hole 80 is preferably formed horizontally with the reinforcing earth retaining wall to be built, Figure 3 shows that the reinforcing earth retaining wall is formed substantially vertically when the primary drilling hole 800 is formed.

그리고, 상기 1차천공홀(80)에는 보강용 1차그라우팅재(82)를 주입한다(S3).Then, the primary grouting material 82 for reinforcement is injected into the primary drilling hole 80 (S3).

이때, 상기 보강용 1차그라우팅재(82)로는 시멘트교반토 등을 주입하여 굳히는 형태를 이루게 된다.At this time, the reinforcing primary grouting material 82 is formed by injecting cement stir and solidified.

한편, 도시된 바와 같이, 상기 1차천공홀(80)에는 별도로 보강빔(84)을 설치하여 이중의 보강구조를 이루도록 함이 바람직하며, 이때 상기 보강빔(84)은 지형의 상부로 끝단부 일부가 노출된 상태로 설치된다(S2).On the other hand, as shown, it is preferable to form a double reinforcement structure by separately installing a reinforcement beam 84 in the primary drilling hole 80, wherein the reinforcement beam 84 is the end of the top of the terrain Some are installed in an exposed state (S2).

도 3 및 도 4에서는 상기 보강빔(84)으로서 H빔이 적용된 것을 나타낸 것이다.3 and 4 show that the H beam is applied as the reinforcement beam 84.

이때, 상기 보강빔(84)은 모든 1차천공홀(80)에 설치되지는 않고, 일정 거리 이격된 위치의 1차천공홀(80)에만 설치되어 구조적 보강은 가져오면서도 재료비의 증대를 방지할 수 있게 되며, 후술하는 보강재(108) 설치를 위한 2차천공홀의 굴착작업이 유리해진다.In this case, the reinforcing beam 84 is not installed in all the primary drilling holes 80, but is installed only in the primary drilling holes 80 at positions spaced apart from each other by a certain distance to prevent structural increase and increase in material cost. It becomes possible, and the excavation work of the secondary drilling hole for installing the reinforcing material 108 to be described later is advantageous.

다음으로는, 첨부된 도 5에 도시된 바와 같이, 지형의 외측으로 노출된 상기 보강빔(84)에 보강콘크리트캡(88)을 설치하여 보강빔(84)이 지형에 일체화되도록 한다.Next, as shown in FIG. 5, a reinforcement concrete cap 88 is installed on the reinforcement beam 84 exposed to the outside of the terrain so that the reinforcement beam 84 is integrated with the terrain.

이때, 상기 보강콘크리트캡(88)은 복수 개의 보강빔(84)을 서로 연결하는 형태로 적용할 수도 있으며, 이 경우 지형에 걸리게 되는 응력을 수평방향으로 분산하는 효과를 가져온다.In this case, the reinforcement concrete cap 88 may be applied in the form of connecting the plurality of reinforcement beams 84 with each other, in this case, the effect of dispersing the stress applied to the terrain in the horizontal direction.

다음으로는, 도 6에 도시된 바와 같이, 상기 보강칼럼모듈(85)의 전방측 지형을 상부로부터 하부로 일정 구간 절토한 후(S12), 절토된 지형의 전방 외측으로 소정 길이 노출된 상태로 보강재(108)를 설치하는 단계를 거치게 된다.Next, as shown in Figure 6, after cutting the front side terrain of the reinforcement column module 85 from the top to a predetermined section (S12), in a state of being exposed to the front outside of the cut terrain a predetermined length. The reinforcement 108 is to go through the step of installing.

이를 위해 미리 시멘트교반토로 이루어지는 상기 보강칼럼모듈(85)과 지형을 동시에 관통하는 2차천공홀(102)을 굴착하는 단계를 수행하게 된다(S13). To this end, the step of excavating the secondary drilling hole 102 through the reinforcement column module 85 and the terrain simultaneously made of cement agitating is performed in advance (S13).

그리고, 상기 2차천공홀(102)에 상기 보강재(108)를 설치하며 또한 2차그라우팅재(103)를 주입한다(S14,S15).In addition, the reinforcing member 108 is installed in the secondary drilling hole 102, and the secondary grouting material 103 is injected (S14 and S15).

여기서, 상기 보강재(108)로는 쏘일 네일링 또는 앵커 등이 적용될 수 있다.In this case, as the reinforcing material 108, nail nailing or an anchor may be applied.

이와 같은 쏘일 네일링 또는 앵커는 이미 다수의 공지된 기술이 나와 있으며 이 중 적절한 부재가 적용 가능하고 이미 당업자에게 자명한 사항이므로 이에 대한 자세한 설명은 생략한다.Such a nail nailing or anchor has already been disclosed a number of known techniques, of which appropriate members are applicable and already well known to those skilled in the art, a detailed description thereof will be omitted.

그리고, 상기 지형의 절토 및 보강재(108)의 설치와 2차그라우팅재(103)의 주입은 절토되는 지형의 상부로부터 하부로 절토계획고에 이르기까지 다단의 구간에 걸쳐 반복적으로 수행된다.In addition, installation of the cut and reinforcement material 108 and injection of the secondary grouting material 103 of the terrain is repeatedly performed over a plurality of sections from the top of the cut terrain to the cut plan height.

절토계획고까지 굴착이 완료된 지형은 첨부된 도 7에 도시된 바와 같다.Excavation is completed until the cut plan is as shown in Figure 7 attached.

한편, 상기 각각의 절토 구간에 있어서 상기 보강재(108)가 외부로 노출된 부위에는 판상의 지압판(111,122)을 설치한다(S16).On the other hand, in the cut section of each of the reinforcing member 108 is provided with plate-shaped acupressure plate (111, 122) is exposed to the outside (S16).

그리고, 본 발명에 따른 보강토옹벽의 시공에 있어서의 상기 보강재(108)에 연결되는 지압판은 1차지압판(111)과 2차지압판(122)으로 나누어 설치된다.In addition, the pressure plate connected to the reinforcing member 108 in the construction of the reinforcing soil retaining wall according to the present invention is provided by dividing the primary pressure plate 111 and the secondary pressure plate 122.

이를 위해, 상기 1차지압판(111)과 2차지압판(122)은 중앙 부위로 보강재(108)가 관통되는 관통홀(115,125)이 구비된다.To this end, the primary pressure plate 111 and the secondary pressure plate 122 is provided with through holes 115 and 125 through which the reinforcement 108 penetrates to the central portion.

즉, 상기 보강재(108)의 외부 노출된 부위에 상기 보강재(108)의 길이방향을 따라서 상기 1차지압판(111)과 2차지압판(122)은 소정 거리 이격된 상태로 설치된다.That is, the primary pressure plate 111 and the secondary pressure plate 122 along the longitudinal direction of the reinforcement 108 on the externally exposed portion of the reinforcement 108 is installed at a predetermined distance apart.

그리고, 상기 각각의 지압판(111,122)은, 첨부된 도 8에 도시된 바와 같이, 별도의 결합부재(133)를 이용 상기 보강재(108)에 각각의 지압판(111,122)을 고정시키게 된다.In addition, each of the pressure plate (111, 122), as shown in the accompanying Figure 8, to secure the respective pressure plate (111, 122) to the reinforcing member 108 using a separate coupling member 133.

상기 결합부재(133)는 소정의 결합너트 등의 형태가 적용 가능하다.The coupling member 133 may be applied in the form of a predetermined coupling nut.

한편, 도시된 바와 같이, 상기 1차지압판(111)은 횡방향으로 소정 길이 연장된 형상으로 이루어짐이 바람직하다. 나아가, 도 11 및 도 12에서와 같이, 상기 1차지압판(111)은 인접하는 복수 개의 보강재(108)를 동시에 연결하는 형태로 설치 가능하도록, 즉 상기 보강재(108)가 동시에 관통하는 두 개 이상의 관통홀(115)이 구비될 수 있다.On the other hand, as shown, the primary pressure plate 111 is preferably made of a shape extending a predetermined length in the horizontal direction. 11 and 12, the primary pressure plate 111 may be installed in such a manner as to connect a plurality of adjacent reinforcing materials 108 at the same time, that is, two or more through which the reinforcing materials 108 pass simultaneously. The through hole 115 may be provided.

이와 같이, 상기 1차지압판(111)이 양측으로 소정 길이 연장되게 형성하거나 또는 횡방향으로 복수 개의 보강재(108)가 동시에 연결되도록 이루어진 경우에는 보강토옹벽이 구축된 후 후방 측 지형으로부터 걸리는 응력을 1차지압판(111)을 따라서 횡방향으로 분산시킬 수 있는 효과를 가져오게 된다.As such, when the primary pressure plate 111 is formed to extend a predetermined length on both sides, or when the plurality of reinforcing materials 108 are connected at the same time in the transverse direction, the stress applied from the rear side terrain after the reinforcing soil wall is constructed is 1 According to the charge pressure plate 111, the effect that can be dispersed in the transverse direction is brought.

결국, 연약지반으로 판단되어 보강칼럼모듈(85)이 설치된 경우에는 상기 보강칼럼모듈(85)을 통하여 1차적으로 지형에 걸리는 응력의 분산을 가져옴과 동시에 보조적으로 상기 1차지압판(111)이 횡방향으로 응력을 분산시키는 효과를 가져오므로 보강토옹벽의 내구성 강화를 이중으로 도모할 수 있게 된다.After all, when the reinforcement column module 85 is determined to be the soft ground, the primary pressure plate 111 is laterally assisted while bringing the dispersion of stress applied to the terrain primarily through the reinforcement column module 85. Since the effect of dispersing the stress in the direction can be doubled to enhance the durability of the reinforced earth retaining wall.

다음으로는 상기 보강칼럼모듈(85)이 설치된 후방측 지형으로부터 전방측에 이르기까지 소정의 관통홀 또는 파이프관 등을 이용하여 배수공(150)을 형성하는 단계를 거치도록 한다. 상기 배수공(150)은 지형 후방측에 저장되는 저장수를 구축되는 보강토옹벽의 외측으로 배출되도록 하는 역할을 수행하게 되며 이를 위해 적절한 길이를 지니도록 형성된다.Next, a step of forming the drainage hole 150 using a predetermined through hole or a pipe pipe from the rear topography to the front side where the reinforcement column module 85 is installed is performed. The drain hole 150 serves to discharge the storage water stored in the rear side of the terrain to the outside of the reinforcing soil retaining wall is built to have an appropriate length for this purpose.

상기 과정을 계획절토고에 이르기까지 반복적으로 수행하여 보강토옹벽 전체에 걸친 보강작업을 하게 되고(S17), 다음으로는 상기 1차지압판(111)과 2차지압판(122)이 콘크리트옹벽에 내설되어 설치되도록 보강철근(180) 및 거푸집(170)을 설치하는 단계를 거친다(S18).The process is repeatedly carried out until the planned cutting height, and the reinforcement work is carried out throughout the reinforcement soil retaining wall (S17). Next, the primary pressure plate 111 and the secondary pressure plate 122 are embedded in the concrete retaining wall. Go through the step of installing the reinforcing bar 180 and the formwork 170 to be installed (S18).

다음으로는 상기 거푸집(170)과 보강칼럼모듈(85) 사이로 콘크리트 타설작업을 수행한 후 콘크리트의 양생이 완료된 후에 상기 거푸집(170)을 제거한다(S19,S20).Next, after the concrete is poured between the formwork 170 and the reinforcement column module 85, the formwork 170 is removed after the curing of the concrete is completed (S19, S20).

이때, 콘크리트가 타설되어 생성되는 보강토옹벽 하부 전방측으로는 소정 깊이로 식생존(195)을 형성하여 식물의 생식이 가능하도록 한다.In this case, the vegetation zone 195 is formed to a predetermined depth to the lower front side of the reinforcement soil wall which is generated by pouring concrete to enable the reproduction of plants.

도시되어 있지는 않으나, 상기 2차지압판(122) 또한 1차지압판(111)과 마찬가지로 소정 길이 양측으로 연장 형성되도록 하여 응력의 횡방향 분산을 유도할 수도 있을 것이다.Although not shown, the secondary pressure plate 122 may also be formed to extend to both sides of a predetermined length like the primary pressure plate 111 to induce lateral dispersion of stress.

그리고, 양생되는 보강토옹벽의 전방측으로는, 첨부된 도 15에 도시된 바와 같이, 입체형상의 구조물(198)을 형성하여 외관상 심미관을 불러일으키도록 할 수도 있다.In addition, as shown in the accompanying FIG. 15, the front side of the reinforcement soil retaining wall to be cured may form a three-dimensional structure 198 to bring out the appearance of the aesthetic tube.

이때, 도 15와 다른 형태로 이루어진 입체형상 구조물을 구축하여 이용하거나 또는 별도의 얇은 철근(미도시) 등을 콘크리트옹벽 전방에 설치하여 상기 식생존(195)을 통하여 자라는 덩쿨 등의 식물이 옹벽 전반을 감싼 형태로 성장되도록 할 수도 있다.At this time, a plant such as a vine growing through the vegetation zone 195 is installed in the front of the concrete retaining wall by using a three-dimensional structure having a different shape from that of FIG. 15 or by installing a separate thin reinforcing bar (not shown). It can also be grown in a wrapped form.

도 16은 다양한 암반이 혼합된 지형에 본 발명에 따른 보강토옹벽 시공방법을 적용하여 다양한 형태의 보강토옹벽이 구축되는 모습을 나타낸 측단면도이다.FIG. 16 is a side sectional view showing a state in which various types of reinforced soil retaining walls are constructed by applying a method of constructing a reinforced soil retaining wall according to the present invention on a terrain mixed with various rocks.

도시된 바와 같이, 견고한 암반이 위치된 부근에 보강토옹벽을 설치 시에는 암반 일부를 탑다운 방식으로 굴착하고 보강재(108) 및 상기 1차/2차지압판(111,122)을 설치한 후, 콘크리트 타설 또는 콘크리트블록의 적층 등을 이용 보강토옹벽을 구축한다.As shown, when installing the reinforcement retaining wall in the vicinity of the solid rock is excavated a portion of the rock in the top-down manner, after installing the reinforcing material 108 and the primary / secondary pressure plate (111, 122), concrete pouring or Reinforcement retaining wall is constructed by laminating concrete blocks.

이와 같은 견고한 암반에 보강토옹벽(301)을 축조하는 경우에는 별도로 지반의 1차 보강을 위한 보강칼럼모듈을 설치하지 않아도 지형의 붕괴 위험 등이 작으므로 보강토옹벽의 내구성 보장이 가능해진다.When constructing the reinforced soil retaining wall 301 on such a solid rock, it is possible to guarantee the durability of the reinforced soil retaining wall because the risk of collapse of the terrain is small even without installing a reinforced column module for primary reinforcement of the ground.

한편, 암반 정도의 견고한 수준에 이르지는 않더라도 상대적으로 일정 수준의 견고한 지반에 보강토옹벽(288)의 축조 시에는 지반의 상부로부터 하부로 구간을 나누어 절토된 지형에 각 구간별로 쇼크리트(201)공법을 수행하여 지반을 가보강하는 작업을 한 후, 보강재(108) 및 1차/2차지압판(111,122)을 설치하는 작업을 거친다.On the other hand, when constructing the reinforcement soil wall 288 in a relatively constant level of solid ground, even if it does not reach the level of rock, it is divided into sections from the top of the ground to the bottom of the cut concrete 201 for each section. After performing the work to reinforce the ground by performing the work to install the reinforcement 108 and the primary / secondary pressure plate (111, 122).

계획절토고에 해당되는 높이에 이르기까지 상술한 과정을 모두 완료한 후에는 전방 측을 덮어 감싸는 형태로 콘크리트 등을 이용 보강토옹벽(288)을 구축한다.After completing all of the above processes up to the height corresponding to the planned cutting height, the reinforcing soil retaining wall 288 is constructed using concrete in the form of covering the front side.

다음으로, 연약지반의 경우에는 상기 도시 및 설명한 바와 마찬가지로 보강칼럼모듈(85)을 설치 후 보강재(108) 및 1차/2차지압판(111,122)을 설치는 과정을 거치고, 최종적으로 보강토옹벽을 구축하게 된다.Next, in the case of soft ground, the reinforcement column 108 and the first and second secondary pressure plates 111 and 122 are installed after the reinforcement column module 85 is installed, as described above and described. Done.

상술한 바와 같이 구성되는 본 발명 절토용 보강토옹벽 시공방법에 의하면 지반의 견고한 정도에 따라서 보강칼럼모듈의 설치를 선택 적용하여 전체 보강토옹벽이 시공되도록 함으로써 전체적으로 안전성이 향상되도록 함과 동시에 시공기간 및 시공비용을 줄일 수 있는 효과를 가져온다.According to the present invention, the reinforcement soil retaining wall construction method configured as described above by selecting the installation of the reinforcement column module according to the solidity of the ground so that the entire reinforcement soil retaining wall construction to improve the overall safety and construction period and construction The effect is to reduce costs.

또한, 지압판을 이중으로 설치함으로써 보강재에 걸리는 응력의 분산을 방지함과 동시에 1차지압판을 횡방향으로 일정 길이 연장되도록 하되 복수 개의 보강재에 동시에 결합되도록 함으로써 응력의 분산효과를 극대화할 수 있게 되며 설치작업 또한 간편해지게 되는 효과를 가져온다.In addition, by installing a double pressure plate to prevent the dispersion of stress applied to the reinforcement, while extending the length of the primary pressure plate in the transverse direction, but to be coupled to a plurality of reinforcement at the same time to maximize the stress distribution effect Work also has the effect of simplifying.

나아가, 상기 보강콘크리트캡(88)을 별도로 설치하여 보강칼럼모듈(85)을 지면과 일체화되도록 함으로써 굴착과정 중 발생할 수 있는 전도와 활동파괴에 대한 저항성을 커지게 하고 전반적인 안전성이 향상되도록 함은 물론 굴착시공이 용이해지게 되는 효과를 가져온다.Furthermore, by separately installing the reinforcement concrete cap 88 so that the reinforcement column module 85 is integrated with the ground, the resistance to conduction and activity destruction that may occur during the excavation process is increased and the overall safety is improved. It brings the effect of easy excavation construction.

이와 같이, 상기한 도면을 참조하여 본 발명의 바람직한 실시예에 대해 상술하였으나 본 발명은 전술한 실시예에 한정되지 않으며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 본 발명의 사상을 벗어나지 않고 변형 가능하며, 이러한 변형은 본 발명의 권리범위에 속할 것이다.As described above, preferred embodiments of the present invention are described above with reference to the drawings, but the present invention is not limited to the above-described embodiments, and those skilled in the art do not depart from the spirit of the present invention. Modifications can be made without departing from the scope of the present invention.

80: 천공홀 82: 그라우팅재
84: 보강빔 85: 보강칼럼모듈
102: 천공홀 103: 그라우팅재
108: 보강재 111: 1차지압판
115,125: 관통홀 122: 2차지압판
133: 결합부재 150: 배수공
170: 거푸집 180: 보강철근
80: drilling hole 82: grouting material
84: reinforcement beam 85: reinforcement column module
102: punched hole 103: grouting material
108: reinforcing material 111: primary pressure plate
115, 125: through hole 122: secondary pressure plate
133: coupling member 150: drain hole
170: formwork 180: rebar

Claims (8)

보강토옹벽이 설치되는 지형의 상부로부터 하측으로 1차천공홀을 형성하는 단계;
상기 형성된 1차천공홀에 1차그라우팅재를 주입하는 단계;
상기 주입된 1차그라우팅재의 전방측 지형을 절취하는 단계;
상기 절취된 지형의 전방 외측으로 상하 및 좌우 각각 다수 열을 이룸과 동시에 소정 길이 노출된 상태로 보강재를 설치하는 단계;
상기 외부 노출된 보강재 중 좌우 횡방향으로 복수 개의 보강재에 동시에 연결되도록 1차지압판을 설치하는 단계; 및
상기 1차지압판으로부터 소정 간격 이격된 상태로 상기 보강재에 2차지압판을 설치하는 단계;
를 포함하여 구성되는 절토용 보강토옹벽의 시공방법.
Forming a primary perforation hole from an upper side of a terrain on which a reinforced earth retaining wall is installed;
Injecting a primary grouting material into the formed primary boring hole;
Cutting the front side terrain of the injected primary grouting material;
Installing a reinforcing material in a state of exposing a predetermined length at the same time as a plurality of rows respectively up and down and left and right toward the front outside of the cut terrain;
Installing a primary pressure plate to be connected to a plurality of reinforcement at the same time in the left and right transverse direction of the externally exposed reinforcement; And
Installing a secondary pressure plate on the reinforcement in a state spaced apart from the primary pressure plate by a predetermined interval;
Construction method of the reinforcement soil retaining wall for cutting comprising a.
삭제delete 삭제delete 제1항에 있어서,
상기 1차천공홀에 보강빔을 설치하는 단계를 더 포함하여 구성되는 것을 특징으로 하는 절토용 보강토옹벽의 시공방법.
The method of claim 1,
Construction method of the reinforcing soil retaining wall for cutting, characterized in that further comprising the step of installing a reinforcing beam in the primary drilling hole.
제4항에 있어서,
상기 보강빔은 절토 지형의 상부로 일부 노출되게 설치되며, 상기 노출된 보강빔에 보강콘크리트캡을 설치하는 단계를 더 포함하여 구성되는 것을 특징으로 하는 절토용 보강토옹벽의 시공방법.
The method of claim 4, wherein
The reinforcement beam is installed to be partially exposed to the top of the cut topography, the construction method of the reinforcement earth retaining wall for cut, characterized in that further comprising the step of installing a reinforcement concrete cap on the exposed reinforcement beam.
삭제delete 제1항에 있어서,
상기 2차지압판은 횡방향으로 복수 개의 보강재에 동시에 체결되도록 한 것을 특징으로 하는 절토용 보강토옹벽의 시공방법.
The method of claim 1,
The secondary acupressure plate is a construction method of reinforcing soil retaining wall, characterized in that to be fastened to a plurality of reinforcement at the same time in the transverse direction.
상부로부터 하측으로 형성된 1차천공홀에 1차그라우팅재를 주입하여 형성되는 보강칼럼모듈;
상기 보강칼럼모듈의 전방측 절토되는 지형에 상하 및 좌우 다수 열을 이루도록 일단부가 외부에 노출된 상태로 설치되는 다수 개의 보강재;
상기 외부 노출된 보강재 중 좌우 횡방향으로 복수 개의 보강재에 동시에 연결되도록 설치되는 1차지압판;
상기 1차지압판으로부터 소정 간격 이격된 상태로 상기 보강재의 노출된 부위에 설치되는 2차지압판; 및
상기 1차지압판 및 2차지압판이 내설된 상태를 이루도록 함과 동시에 상기 노출된 보강재의 전방측에 설치되는 콘크리트 옹벽;
을 포함하여 구성되는 절토용 보강토옹벽.
A reinforcement column module formed by injecting a primary grouting material into a primary drilling hole formed from an upper side to a lower side;
A plurality of reinforcing members installed at one end of the reinforcing column module to be exposed to the outside so as to form a plurality of rows in the upper and lower left and right sides of the top cut surface;
A primary pressure plate installed to be simultaneously connected to a plurality of reinforcing members in left and right transverse directions among the externally exposed reinforcing members;
A secondary pressure plate installed at an exposed portion of the reinforcement in a state spaced apart from the primary pressure plate by a predetermined interval; And
A concrete retaining wall installed at the front side of the exposed reinforcement while simultaneously forming the primary pressure plate and the secondary pressure plate in an insulated state;
Reinforcement soil retaining wall configured to include.
KR1020110059696A 2011-06-20 2011-06-20 A reinforced soil retaining wall for cutting slope and method of construction for the same KR101075574B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110059696A KR101075574B1 (en) 2011-06-20 2011-06-20 A reinforced soil retaining wall for cutting slope and method of construction for the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110059696A KR101075574B1 (en) 2011-06-20 2011-06-20 A reinforced soil retaining wall for cutting slope and method of construction for the same

Publications (1)

Publication Number Publication Date
KR101075574B1 true KR101075574B1 (en) 2011-10-20

Family

ID=45033170

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110059696A KR101075574B1 (en) 2011-06-20 2011-06-20 A reinforced soil retaining wall for cutting slope and method of construction for the same

Country Status (1)

Country Link
KR (1) KR101075574B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100393515B1 (en) * 2001-03-29 2003-08-14 김상수 Afforestation Retaining-Wall laying Concrete-block
KR100793743B1 (en) * 2007-08-13 2008-01-10 (주)엠케이 Method for fixing permanent anchor assembly and apparatus thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100393515B1 (en) * 2001-03-29 2003-08-14 김상수 Afforestation Retaining-Wall laying Concrete-block
KR100793743B1 (en) * 2007-08-13 2008-01-10 (주)엠케이 Method for fixing permanent anchor assembly and apparatus thereof

Similar Documents

Publication Publication Date Title
JP2007154413A (en) Soldier pile type earth retaining anchor type retaining wall and its construction method
KR102195504B1 (en) Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method
KR20060103309A (en) Gradual bottom-up slice and gradual infilling method for removing underground retaining wall
KR100660379B1 (en) Plantable reinforced earth wall and its block and construction method of reinforced earth wall
KR20110077334A (en) Retaining wall structure and construction method of the retaining wall structure
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
KR102402815B1 (en) Retaining wall structure using support member and method constructing the same
KR101182704B1 (en) Construction method of undergroud structure using PHC pile
KR102195510B1 (en) Construction method for earth self-retaining wall using reinforcing member and PHC pile
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
KR101147459B1 (en) Construction method of cutting the ground retaining wall using the pole
KR101334749B1 (en) Vegetation block in tiers for retaining wall and method for construction of retaining wall using the same
KR101075574B1 (en) A reinforced soil retaining wall for cutting slope and method of construction for the same
KR100984040B1 (en) Method of reinforced earth retaining wall for cutting face through double reinforcing execution
KR101234270B1 (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR100665338B1 (en) Latticed assembly of retaing wall with soil nailing and anchor
KR101300071B1 (en) Concrete reinforced block for satabilization face of slope
KR101147460B1 (en) Cutting the ground retaining wall using the pole and construction method of the same
KR101524302B1 (en) Construction method for underground structure without temporary structure
KR100479500B1 (en) The slope tree-planting structure using socket type steel pipe, and his construction method
JPS6018769B2 (en) Construction method of underground structure
KR102570649B1 (en) Method of demolition of underground exterior walls
KR101399275B1 (en) Method of construction for RWC reinforced soil retaining wall consisting of sidewall for architectural structure
JP4423390B2 (en) Construction method of slope protection retaining wall
KR102194394B1 (en) Construction method for earth self-retaining wall using reinforcing member and SCW construction method

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150616

Year of fee payment: 4

R401 Registration of restoration
FPAY Annual fee payment

Payment date: 20160919

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170926

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20191002

Year of fee payment: 9