KR101029261B1 - Construction method for retaining wall using shotcrete - Google Patents
Construction method for retaining wall using shotcrete Download PDFInfo
- Publication number
- KR101029261B1 KR101029261B1 KR1020100099533A KR20100099533A KR101029261B1 KR 101029261 B1 KR101029261 B1 KR 101029261B1 KR 1020100099533 A KR1020100099533 A KR 1020100099533A KR 20100099533 A KR20100099533 A KR 20100099533A KR 101029261 B1 KR101029261 B1 KR 101029261B1
- Authority
- KR
- South Korea
- Prior art keywords
- shotcrete
- permeable
- retaining wall
- installation step
- installing
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0208—Gabions
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0225—Retaining or protecting walls comprising retention means in the backfill
- E02D29/0233—Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0275—Retaining or protecting walls characterised by constructional features cast in situ
Abstract
Description
본 발명은 토목 분야에 관한 것으로서, 상세하게는 옹벽의 시공방법에 관한 것이다.The present invention relates to the field of civil engineering, and in particular, to a construction method of a retaining wall.
도 1 내지 3은 종래의 일반적인 옹벽의 시공방법의 공정을 도시한 것이다.1 to 3 show a process of a conventional method for constructing a retaining wall.
도시된 바와 같이, 종래의 공법은 기초저판(12) 위에 전후면 거푸집(11)을 설치하고(도 1), 그 전후면 거푸집(11) 사이에 콘크리트를 타설하여 표면 구조물(10)을 형성한 후(도 2), 배후토사(1)를 충전함과 함께, 표면 구조물(10)과 배후토사(1)의 사이에 잡석 채움 등에 의한 배수층(20)을 형성하는 공정에 의해 이루어진다.As shown, the conventional method is to install the front and
그런데, 이러한 종래의 옹벽 시공방법은 표면 구조물의 설치공정, 배후토사의 충전공정, 배수층의 형성공정 등이 서로 유기적으로 운용되지 못하고, 각각 별개로 이루어지는바, 효율적인 공법을 이루지 못한다는 문제점이 있었다.However, the conventional retaining wall construction method has a problem in that the installation process of the surface structure, the filling process of the rearing soil, the forming process of the drainage layer, etc. do not operate organically with each other, and are made separately, and thus do not achieve an efficient construction method.
본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 각 공정이 서로 유기적으로 운용됨에 따라, 공사기간 및 비용을 줄일 수 있도록 하는 옹벽의 시공방법을 제시하는 것을 그 목적으로 한다.The present invention was derived to solve the above problems, and the object of the present invention is to present a construction method of the retaining wall to reduce the construction period and cost as each process is organically operated.
상기 과제의 해결을 위하여, 본 발명은 배후토사의 전면에 투수 구조물(100)을 설치하는 투수 구조물 설치단계; 상기 투수 구조물(100)의 전면에 숏크리트를 타설하여 표면 구조물(200)을 형성하는 표면 구조물 설치단계;를 포함하는 숏크리트를 이용한 옹벽의 시공방법을 제시한다.In order to solve the above problems, the present invention is a permeable structure installation step of installing a
상기 투수 구조물(100)은 투수성 콘크리트에 의해 형성된 투수 블록(110)을 포함하는 것이 바람직하다.The
상기 투수 구조물(100)은 그물망 구조의 박스(121) 내부에 석재(122)가 충전된 투수 박스(120)를 포함하는 것이 바람직하다.The
상기 표면 구조물 설치단계는 상기 투수 구조물(100)을 관통하여 배후토사에 대하여 보강부재(220)를 설치하는 보강부재 설치단계; 상기 투수 구조물(100)의 전단에 지압판(230)을 설치하고, 상기 보강부재(220)의 전단을 상기 지압판(230)에 고정하는 지압판 설치단계;를 더 포함하고, 상기 표면 구조물 설치단계는 상기 보강부재(220)의 전단 및 지압판(230)이 매몰되도록, 상기 투수 구조물(100)의 전면에 숏크리트를 타설하여 표면 구조물(200)을 형성하는 것이 바람직하다.The surface structure installation step may include a reinforcing member installation step of installing a reinforcing
상기 투수 구조물 설치단계와 표면 구조물 설치단계의 사이에는, 상기 투수 구조물(100)의 공극을 보호하도록 투수성 재질에 의해 형성된 보호부재(300)를 상기 투수 구조물(100)의 전면에 설치하는 보호부재 설치단계를 더 포함하는 것이 바람직하다.Between the step of installing the permeable structure and the step of installing the surface structure, a protective member for installing a
본 발명은 각 공정이 서로 유기적으로 운용됨에 따라, 공사기간 및 비용을 줄일 수 있도록 하는 옹벽의 시공방법을 제시한다.The present invention proposes a method of constructing a retaining wall to reduce the construction period and cost as each process is organically operated.
도 1 내지 3은 종래의 일반적인 옹벽의 시공방법을 도시한 공정도.
도 4 이하는 본 발명의 실시예를 설명하기 위한 것으로서,
도 4 내지 6은 제1 실시예의 공정도.
도 7은 투수 블록의 사시도.
도 8은 투수 박스의 사시도.
도 9는 제2 실시예의 구성도.
도 10,11은 제3 실시예의 구성도.1 to 3 is a process chart showing a conventional construction method of the retaining wall.
4 is for explaining the embodiment of the present invention,
4 to 6 are process charts of the first embodiment.
7 is a perspective view of a pitcher block;
8 is a perspective view of a pitcher box;
9 is a configuration diagram of a second embodiment.
10 and 11 are block diagrams of the third embodiment.
이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
도 4 이하에 도시된 바와 같이, 본 발명에 의한 옹벽의 시공방법은 기본적으로, 배후토사의 전면에 투수 구조물(100)을 설치하는 투수 구조물 설치단계(도 4); 투수 구조물(100)의 전면에 숏크리트를 타설하여 표면 구조물(200)을 형성하는 표면 구조물 설치단계(도 5,6);를 포함하여 구성된다.As shown in Figure 4 below, the construction method of the retaining wall according to the present invention basically, the step of installing a
여기서, 투수 구조물(100)이란, 투수성 콘크리트에 의해 형성된 투수 블록(110)(도 7), 그물망 구조의 박스(121) 내부에 석재(122)가 충전된 투수 박스(120 : 돌망태)(도 8)와 같이, 투수성을 갖추면서도 일정한 형태를 가진 구조체를 축조 등의 방식에 의해 시공하여 이루어지는 구조물을 말한다.Here, the
본 발명은 이러한 투수 구조물(100)에 의해 옹벽의 투수층을 시공하고, 이어 그 투수구조물(100)의 전면에 숏크리트를 타설하는 방식으로 옹벽을 시공함을 특징으로 한다.The present invention is characterized by constructing the permeable layer of the retaining wall by the
따라서 종래 공법에서의 거푸집 작업을 생략할 수 있고, 배후토사의 성토, 투수 구조물의 축조, 숏크리트의 타설이라는 최소한의 공정이 서로 유기적으로 운용됨에 따라, 공사기간 및 비용을 최소로 줄일 수 있다는 효과가 있다.Therefore, the formwork in the conventional construction method can be omitted, and the minimum process of laying the soil behind the soil, constructing the permeable structure, and placing the shotcrete is operated organically with each other, thereby reducing the construction period and cost to the minimum. have.
또한, 숏크리트는 터널의 천정면에 타설되더라도 형상이 쉽게 허물어지지 않는 정도의 반죽질기를 갖는 것이므로, 연직구조의 옹벽의 표면 구조물(200)의 시공에도 충분히 적용될 수 있고(도 6), 경사식 옹벽의 경우에는 더욱 안정적인 적용이 가능하다(도 9).In addition, since the shotcrete has a kneading machine that does not collapse easily even when placed on the ceiling surface of the tunnel, the shotcrete can be sufficiently applied to the construction of the
도 4 내지 6의 실시예는 역 T형 옹벽에 관한 것으로서, 도면에 도시된 바와 같이 기초저판(12)과 표면 구조물(100)을 별도로 시공할 수도 있고, 일체로 시공할 수도 있다.4 to 6 relates to an inverted T-shaped retaining wall, and as shown in the drawing, the
표면 구조물의 설치를 위하여, 투수 구조물(100)의 전면에 직접 숏크리트를 타설할 수도 있지만, 이때 콘크리트에 의한 투수 구조물(100)의 공극 막힘을 방지하기 위해서는, 투수 구조물(100)의 공극을 보호하도록 투수성 재질에 의해 형성된 부직포 등의 보호부재(300)를 투수 구조물(100)의 전면에 설치하는 것이 바람직하다.In order to install the surface structure, shotcrete may be poured directly on the front surface of the
한편, 본 발명에 의한 공법의 경우에도 소일네일, 어스앵커 등의 보강부재(220)를 적용하여 옹벽 구조물을 보강할 수 있는데, 그 방법은 다음과 같다(도 10,11).On the other hand, in the case of the method according to the present invention can also reinforce the retaining wall structure by applying a reinforcing
투수 구조물(100)의 설치 후, 투수 구조물(100)을 관통하여 배후토사에 대하여 천공 홀을 형성하고, 그 천공 홀에 소일네일, 어스앵커 등의 보강부재(220)를 설치한다.After installation of the
천공 홀과 보강부재(220)의 사이 영역은 그라우팅(221)에 의해 충전한다.The area between the drilled hole and the reinforcing
투수 구조물(100)의 전단에 지압판(230)을 설치하고, 보강부재(220)의 전단을 지압판(230)에 고정한다.The
투수 구조물(100)의 전면에 숏크리트를 타설하되, 콘크리트에 보강부재(220)의 전단 및 지압판(230)이 매몰되도록 함으로써, 보강부재(220) 및 지압판(230)과 표면 구조물(200)이 일체화 구조를 형성하도록 한다.Placing shotcrete on the front surface of the
표면 구조물(200) 내부에 배근(201)을 설치하는 경우에는, 배근(201)가 보강부재(220)의 전단이 상호 결합하도록 하는 것이 바람직하다(도 11).When installing the reinforcement 201 in the
이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above has been described only with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention, as is well known, should not be construed as limited to the above embodiments, the present invention described above It will be said that both the technical idea and the technical idea which together with the base are included in the scope of the present invention.
100 : 투수 구조물 110 : 투수 블록
120 : 투수 박스 121 : 그물망
122 : 석재 200 : 표면 구조물
220 : 보강부재 230 : 지압판
300 : 보호부재100: pitcher structure 110: pitcher block
120: pitcher box 121: the net
122: stone 200: surface structure
220: reinforcing member 230: pressure plate
300: protection member
Claims (5)
상기 투수 구조물(100)의 전면에 숏크리트를 타설하여 표면 구조물(200)을 형성하는 표면 구조물 설치단계;를
포함하는 것을 특징으로 하는 숏크리트를 이용한 옹벽의 시공방법.The permeation structure 100 is installed on the front of the rear soil, but the permeation block 110 formed by the permeable concrete or the construction of the permeation box 120 filled with the stone 122 in the box 121 of the mesh structure A permeation structure installation step of installing the permeation structure 100 by;
Surface structure installation step of forming a surface structure 200 by pouring shotcrete on the front of the permeable structure 100;
Construction method of the retaining wall using shotcrete, characterized in that it comprises a.
상기 표면 구조물 설치단계는
상기 투수 구조물(100)을 관통하여 배후토사에 대하여 보강부재(220)를 설치하는 보강부재 설치단계;
상기 투수 구조물(100)의 전단에 지압판(230)을 설치하고, 상기 보강부재(220)의 전단을 상기 지압판(230)에 고정하는 지압판 설치단계;를 더 포함하고,
상기 표면 구조물 설치단계는
상기 보강부재(220)의 전단 및 지압판(230)이 매몰되도록, 상기 투수 구조물(100)의 전면에 숏크리트를 타설하여 표면 구조물(200)을 형성하는 것을 특징으로 하는 숏크리트를 이용한 옹벽의 시공방법.The method of claim 1,
The surface structure installation step
A reinforcing member installation step of installing the reinforcing member 220 through the permeable structure 100 and against the rearing soil;
Installing acupressure plate 230 at the front end of the water permeable structure 100, and installing the acupressure plate to fix the front end of the reinforcing member 220 to the acupressure plate 230;
The surface structure installation step
Method of constructing a retaining wall using a shotcrete, characterized in that to form a surface structure 200 by pouring a shotcrete on the front surface of the permeable structure 100 so that the front end and the pressure plate 230 of the reinforcing member 220 is buried.
상기 투수 구조물 설치단계와 표면 구조물 설치단계의 사이에는,
상기 투수 구조물(100)의 공극을 보호하도록 투수성 재질에 의해 형성된 보호부재(300)를 상기 투수 구조물(100)의 전면에 설치하는 보호부재 설치단계를 더 포함하는 것을 특징으로 하는 숏크리트를 이용한 옹벽의 시공방법.The method according to claim 1 or 4,
Between the pitcher structure installation step and the surface structure installation step,
Retaining wall using shotcrete further comprises a protective member installation step of installing a protective member 300 formed by a permeable material on the front of the water-permeable structure 100 to protect the air gap of the water-permeable structure 100 Construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100099533A KR101029261B1 (en) | 2010-10-12 | 2010-10-12 | Construction method for retaining wall using shotcrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100099533A KR101029261B1 (en) | 2010-10-12 | 2010-10-12 | Construction method for retaining wall using shotcrete |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101029261B1 true KR101029261B1 (en) | 2011-04-18 |
Family
ID=44050113
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100099533A KR101029261B1 (en) | 2010-10-12 | 2010-10-12 | Construction method for retaining wall using shotcrete |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101029261B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20220139847A (en) * | 2020-01-07 | 2022-10-17 | 대구대학교 산학협력단 | Block to reduce earth and water pressure and to increase load bearing, and a construction method to use the block |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004316416A (en) * | 2003-04-04 | 2004-11-11 | Daiwa Kogyo Kk | Formation method for water permeable concrete |
KR200405354Y1 (en) * | 2005-10-05 | 2006-01-10 | 최영근 | Bearing plate of soil nail for pull-out test |
KR200409161Y1 (en) * | 2005-11-15 | 2006-02-20 | (주) 일신하이텍 | Prefabricated Concrete Pannel Gabion for Constructing Gabion Walls |
-
2010
- 2010-10-12 KR KR1020100099533A patent/KR101029261B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004316416A (en) * | 2003-04-04 | 2004-11-11 | Daiwa Kogyo Kk | Formation method for water permeable concrete |
KR200405354Y1 (en) * | 2005-10-05 | 2006-01-10 | 최영근 | Bearing plate of soil nail for pull-out test |
KR200409161Y1 (en) * | 2005-11-15 | 2006-02-20 | (주) 일신하이텍 | Prefabricated Concrete Pannel Gabion for Constructing Gabion Walls |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20220139847A (en) * | 2020-01-07 | 2022-10-17 | 대구대학교 산학협력단 | Block to reduce earth and water pressure and to increase load bearing, and a construction method to use the block |
KR102597836B1 (en) * | 2020-01-07 | 2023-11-02 | 대구대학교 산학협력단 | Block to reduce earth and water pressure and to increase load bearing, and a construction method to use the block |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100743474B1 (en) | Earth of building land-side protection wall structure | |
KR101652163B1 (en) | Concrerte pannel for retaining wall and method for constructing retaining wall using the same | |
CN102444143B (en) | Construction method for cancelling operation channel for facades of basement | |
CN107542115A (en) | Underground project waterproof structure and its construction method | |
CN106948340B (en) | A kind of construction method of the Manual excavated pile structure of high polymer grouting protection | |
KR100890828B1 (en) | Geosynthetic reinforced soil and reinforced concrete retaining wall | |
KR101531799B1 (en) | Repair reinforcement method of the waterfront structure | |
KR101126666B1 (en) | Vertical drain induction type retaining wall reinforced by nailing | |
KR100698758B1 (en) | Retaining wall reinforced by nailing and construction method thereof | |
KR101902791B1 (en) | Under ground structure construction method using composite steel pile and under ground structure therewith | |
KR101902786B1 (en) | Under ground structure construction method using composite sheet pile and under ground structure therewith | |
JP2017096063A (en) | Earth retaining excavation method and skeleton construction method | |
KR101029261B1 (en) | Construction method for retaining wall using shotcrete | |
KR101063987B1 (en) | The method of wall for natural stone plat | |
CN207228173U (en) | A kind of underground project waterproof structure | |
KR101169437B1 (en) | The installation structure and construction method using a trough | |
JP5975726B2 (en) | Ground structure and ground improvement method | |
KR101385090B1 (en) | Foundation Structure and the method of wall and cut off wall | |
KR101021913B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
KR101525942B1 (en) | Method for slope reinforcement construction using the ground improvement product | |
KR101406865B1 (en) | Extension of foundation structure and constructing method for extension of foundaion structure using the same | |
JP6043574B2 (en) | Caisson method | |
KR101809554B1 (en) | Structure using key-block and sheetfile | |
KR20160004627A (en) | The slope reinforcement method | |
KR200223114Y1 (en) | A structure reinforcing for retaining wall for inclined plane which to cut off a rock wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20140320 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20160324 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20170329 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20180406 Year of fee payment: 8 |
|
R401 | Registration of restoration | ||
R401 | Registration of restoration |