KR101001084B1 - Composite Wall Using Angled Channel and Constructing Method thereof - Google Patents
Composite Wall Using Angled Channel and Constructing Method thereof Download PDFInfo
- Publication number
- KR101001084B1 KR101001084B1 KR1020070132693A KR20070132693A KR101001084B1 KR 101001084 B1 KR101001084 B1 KR 101001084B1 KR 1020070132693 A KR1020070132693 A KR 1020070132693A KR 20070132693 A KR20070132693 A KR 20070132693A KR 101001084 B1 KR101001084 B1 KR 101001084B1
- Authority
- KR
- South Korea
- Prior art keywords
- wall
- thumb pile
- pile
- filler
- front side
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0061—Production methods for working underwater
- E02D2250/0076—Drilling
Abstract
본 발명은, 지하 굴착 또는 사면 절취 단계에서 배면 지반의 붕괴를 막기 위하여 설치되는 흙막이 벽체를 시공함에 있어서, 흙막이 벽체를 위한 지지말뚝을 이용하여, 지하 굴착부 또는 사면 절취부에 설치되는 지하 구조물의 벽체 또는 옹벽 벽체와 상기 흙막이 벽체가 일체로 되도록 함으로써, 흙막이 벽체를 가시설이 아닌 굴착 또는 절취 완료 후에 시공되는 본 구조물의 벽체의 일부로서 활용되도록 구성한, 길이 방향으로 연속된 중공부를 갖는 엄지 말뚝을 구비한 지지말뚝, 이를 이용한 합성 벽체 및 그 시공방법에 관한 것이다.
본 발명에서는 두 개의 판부재(11a, 11b)가 길이 방향으로 간격을 두고 마주 하고 있어 상기 판부재(11a, 11b) 사이에 길이 방향으로 연속된 중공부(12)가 형성되어 있고 상기 판부재(11a, 11b)의 후면에는 상기 중공부(12)의 후방을 폐쇄하는 후면 덮개(13)가 설치되어 있는 구조를 가진 엄지 말뚝(10)이, 지반에 천공된 구멍(100)에 삽입 설치되어 있되, 상기 구멍(100) 내의 충진재(101)는 상기 엄지 말뚝(10)의 후면 측 외부에만 부착되어 엄지 말뚝(10)의 후면 측이 충진재(101)와 일체화되어 있으며; 전면 지반의 굴착에 의해 상기 엄지 말뚝(10)의 전면 측이 외부에 노출되도록 한 후에, 상기 엄지 말뚝(10)의 전면 측의 양측과 일체화되도록 배면 지반의 절취면 전면으로 콘크리트가 타설되어 지지벽체(2)가 형성되어 있으며; 상기 지지벽체(2)의 전면으로 콘크리트가 타설되어 구조물 벽체(3)가 형성되어 있되, 상기 구조물 벽체(3)를 이루는 콘크리트가 상기 엄지 말뚝(10)의 중공부(12)에도 일체로 채워지게 되어, 상기 엄지 말뚝(10)과 지지벽체(2)와 구조물 벽체(3)가 일체를 이루는 하나의 구조체를 형성하여 배면 토사를 지지하는 구조를 가지는 것을 특징으로 하는 합성 벽체가 제공된다.
엄지 말뚝, 벽체, 굴착, 사면, 앵커
The present invention, in the construction of the earth wall to prevent the collapse of the back ground in the underground excavation or slope cutting step, by using a support pile for the earth wall, of the underground structure to be installed in the underground excavation or slope cutting By having the wall or retaining wall wall and the retaining wall integrated, a thumb pile having a longitudinally continuous hollow part configured to be used as a part of the wall of the present structure constructed after completion of excavation or cutting is not a temporary facility. A support pile, a composite wall using the same, and a construction method thereof.
In the present invention, the two plate members 11a and 11b face each other at intervals in the longitudinal direction, and the hollow members 12 which are continuous in the longitudinal direction are formed between the plate members 11a and 11b. 11a, 11b) is provided with a thumb pile 10 having a structure in which a rear cover 13 for closing the rear of the hollow part 12 is installed in a hole 100 bored in the ground. The filler 101 in the hole 100 is attached only outside the rear side of the thumb pile 10 so that the rear side of the thumb pile 10 is integrated with the filler 101; After the front side of the thumb pile 10 is exposed to the outside by excavation of the front ground, concrete is poured into the front of the cut surface of the back ground so as to be integrated with both sides of the front side of the thumb pile 10, and the supporting wall (2) is formed; Concrete is poured into the front surface of the support wall 2 to form a structure wall 3, so that the concrete constituting the structure wall 3 is integrally filled with the hollow part 12 of the thumb pile 10. Thus, a composite wall is provided, which has a structure for supporting the back soil by forming a structure in which the thumb pile 10, the support wall 2, and the structure wall 3 are integrally formed.
Anchor, thumb pile, wall, excavation, slope
Description
본 발명은 길이 방향으로 연속된 중공부를 갖는 엄지말뚝을 구비한 지지말뚝, 이를 이용한 합성 벽체 및 그 시공방법에 관한 것으로서, 구체적으로는 지하 굴착 또는 사면 절취 단계에서 배면 지반의 붕괴를 막기 위하여 설치되는 흙막이 벽체를 시공함에 있어서, 흙막이 벽체를 위한 지지말뚝을 이용하여, 지하 굴착부 또는 사면 절취부에 설치되는 지하 구조물의 벽체 또는 옹벽 벽체와 상기 흙막이 벽체가 일체로 되도록 함으로써, 흙막이 벽체를 가시설이 아닌 굴착 또는 절취 완료 후에 시공되는 본 구조물의 벽체의 일부로서 활용되도록 한 지지말뚝, 합성 벽체 및 그 시공방법에 관한 것이다. The present invention relates to a support pile having a thumb pile having a continuous hollow portion in the longitudinal direction, a composite wall using the same, and a construction method thereof. In constructing the retaining wall, by using the support pile for the retaining wall, the wall or retaining wall of the underground structure installed in the underground excavation or slope cut portion and the retaining wall are integrated so that the retaining wall is not a temporary facility. The present invention relates to a support pile, a composite wall, and a construction method thereof that are used as part of a wall of the present structure to be constructed after completion of excavation or cutting.
토지 이용이 고도화됨에 따라 지하 공간의 개발과, 사면 절취가 날로 증가하고 있으며, 그 규모와 높이도 커지고 있다. 지하 굴착 공사 또는 사면 절취 공사 중에 굴착부의 배면 지반이 붕괴되는 것을 막기 위하여 주열식 흙막이 벽체가 많이 사용되고 있다. As land use is advanced, the development of underground spaces and cutting of slopes are increasing day by day, and the size and height are also increasing. In order to prevent the back ground of the excavation from collapsing during the underground excavation or slope cutting, a columnar wall is used.
주열식 흙막이 벽체에서는 지반을 천공하고, 천공된 구멍에 강재 빔으로 이루어진 엄지 말뚝을 설치한 후 소일 시멘트 또는 콘크리트 등의 충진재를 주입하여 지지말뚝을 연속되게 설치하게 된다. 그런데, 이 경우 엄지 말뚝이 충진재에 완전히 매립되어 있으므로, 굴착 또는 사면 절취 공사가 완료된 후 엄지 말뚝을 인발하여 재활용하기가 극히 어렵다. 반면에 엄지 말뚝은 주로 강재로 만들어지고 고가이기 때문에 엄지말뚝을 충진재 속에 단순히 매립하여 사장시키는 것은 경제적으로도 매우 불리하다. 특히, 흙막이 벽체에 바로 인접하여 건물 지하층의 벽체나 옹벽의 벽체 등과 같은 지하 구조물의 지하 벽체를 시공하는 경우가 많은데, 이러한 경우에 고가의 강재로 이루어진 엄지 말뚝을 사장시키지 말고 콘크리트 지하 벽체의 강성을 증가시키는 구조 부재로 활용하는 것이 바람직하다. In the main thermal wall, the ground is drilled, the thumb pile made of steel beams is installed in the drilled hole, and then the supporting pile is continuously installed by injecting filler such as cement or concrete. However, in this case, since the thumb pile is completely embedded in the filler, it is extremely difficult to draw and recycle the thumb pile after the excavation or slope cutting work is completed. On the other hand, because the thumb pile is mainly made of steel and expensive, it is economically disadvantageous to simply buried the thumb pile in the filling material. In particular, there are many cases where underground walls of underground structures, such as walls of basement floors or retaining walls, are directly adjacent to earthen walls, and in this case, the rigidity of concrete basement walls is avoided without placing the thumb pile made of expensive steel. It is desirable to utilize as a structural member to increase.
엄지 말뚝을 구조 부재로 활용하기 위해서는, 엄지 말뚝에 연결부재를 설치하여 상기 연결부재가 지하 벽체의 콘크리트와 일체로 결합되도록 할 필요가 있다. 그런데 터파기 공사가 완료된 상태 또는 진행 중인 상태에서 엄지 말뚝에 연결부재를 설치하는 것이 매우 어렵다. 우선, 연결부재를 설치하기 위해서는 엄지 말뚝을 노출시켜야 하는데, 충진재 속에 매립된 엄지 말뚝의 일부를, 연결부재가 설치될 수 있을 정도로 깨끗하게 노출시키려면 많은 시간과 노력이 필요하게 된다. 또한, 많은 수량의 연결부재를 설치하는 것 역시 많은 시간과 노력이 필요하게 된다. 이와 같은 연결부재의 설치를 위해서는 별도의 발판을 이용하거나 별도의 장비를 이 용하여 엄지 말뚝의 측면에 접근하여야 하는데, 이러한 작업은 안전사고의 위험이 매우 높을 뿐만 아니라, 작업의 정밀성도 낮아 품질 관리가 매우 어렵다는 문제점이 있다. 이러한 이유에서 지금까지는 엄지 말뚝이 지하 벽체의 강성을 증가시키는 구조 부재로 활용되지 못하고 사장되어 왔다. In order to utilize the thumb pile as a structural member, it is necessary to install a connecting member on the thumb pile so that the connecting member is integrally combined with the concrete of the underground wall. By the way, it is very difficult to install the connection member to the thumb pile in the state of completion or ongoing construction of the trench. First, in order to install the connecting member to expose the thumb pile, a portion of the thumb pile embedded in the filler, it takes a lot of time and effort to expose the clean enough to install the connecting member. In addition, installing a large number of connecting members also requires a lot of time and effort. In order to install such a connection member, it is necessary to use a separate scaffold or a separate equipment to approach the side of the thumb pile. This operation not only has a high risk of a safety accident, but also has a high level of precision and low quality control. There is a problem that is very difficult. For this reason, until now, thumb piles have not been used as structural members to increase the rigidity of underground walls.
한편, 엄지 말뚝에 연결부재를 미리 부착한 상태에서 지반의 구멍에 설칠 수도 있으나, 이 경우 연결부재의 사전 부착으로 인하여 지반의 구멍이 커지게 되며, 그에 따라 천공에 소요되는 비용이 증가되고, 대지 경계선에 여유가 없는 현장에서는 지하 시설물의 연면적이 감소되는 등의 문제가 야기된다. On the other hand, it may be installed in the hole of the ground in the state that the connecting member is pre-attached to the thumb pile, in this case, the hole of the ground is increased due to the pre-attachment of the connecting member, the cost of drilling increases accordingly, At sites with no margins, there are problems such as reduced total floor area of underground facilities.
최근에는 건물 지하층의 한 개층 층고가 높은 경우가 많은데, 이와 같이 층고가 높아지게 되면 지하 벽체의 지지점으로서 기능하게 되는 각 층의 슬래브 사이의 간격이 넓어지게 되고, 그 결과 지하 벽체가 부담해야할 토압이 증가하게 되어, 결국 지하 벽체의 두께가 더 증가된다. 이러한 지하 벽체의 두께 증가는 공사비의 증가뿐만 아니라 지하층의 연면적 감소를 가져오게 되고, 극단적인 경우에는 필요한 지하 공간의 확보를 위하여 지하층의 수를 더 늘려 지하 굴착 깊이를 더 증가시키게 될 수도 있다. In recent years, the height of one floor of the basement of a building is often high. As the height of such a floor increases, the spacing between slabs of each floor serving as a supporting point of the underground wall becomes wider, and as a result, the earth pressure to be burdened by the underground wall increases. As a result, the thickness of the underground wall is further increased. This increase in the thickness of the basement wall not only increases the construction cost but also reduces the total floor area of the basement floor. In extreme cases, the basement depth may be further increased by increasing the number of basement floors to secure the necessary underground space.
본 발명은 상기한 것처럼 종래의 엄지 말뚝을 이용한 주열식 흙막이 벽체가 가지는 문제점과 한계를 극복하기 위하여 개발된 것으로서, 엄지 말뚝과 구조물 벽 체를 일체로 합성시킴으로써, 엄지 말뚝을 사장시키지 아니하고 흙막이 벽체에 접하여 시공되는 구조물의 강성을 보강하는 구조 부재로서도 용이하게 활용될 수 있도록 함으로써, 지하 벽체의 두께를 줄일 수 있도록 하는 지지말뚝과, 이를 이용한 합성 벽체를 제공하는 것을 목적으로 한다. The present invention was developed in order to overcome the problems and limitations of the conventional heating pile wall using the thumb pile, by synthesizing the thumb pile and the structure wall integrally, without the thumb pile to the earth wall It is an object of the present invention to provide a support pile that can reduce the thickness of an underground wall and a composite wall using the same, by being able to be easily used as a structural member to reinforce the rigidity of the structure to be contacted and constructed.
특히, 본 발명에서는 엄지 말뚝이 구조 부재로 활용되도록 하기 위하여 엄지 말뚝을 지하 벽체의 콘크리트와 일체로 결합되도록 함에 있어서, 연결부재를 설치하는데 따르는 여러 가지 단점들을 해소할 수 있도록 하는 합성 벽체를 제공하는 것을 목적으로 한다. In particular, in the present invention to provide a composite wall to solve the various disadvantages of installing the connecting member in the thumb pile is integrally combined with the concrete of the underground wall in order to use the thumb pile as a structural member. The purpose.
본 발명에 의하면, 지지말뚝에 구비되는 엄지 말뚝에 별도의 연결부재를 설치하지 않고도 엄지 말뚝을 구비한 지지말뚝이 지하 벽체와 견고하게 일체화됨으로써 자칫 사장될 수 있는 고가의 재료로 만들어진 엄지말뚝이 콘크리트 지하 벽체의 강성을 증가시키는 구조부재로서 활용될 수 있게 되는 효과가 발휘된다. According to the present invention, the thumb pile made of an expensive material that can be easily put together by the support pile with the thumb pile is firmly integrated with the underground wall without installing a separate connecting member to the thumb pile provided on the support pile concrete basement wall The effect that can be utilized as a structural member to increase the rigidity is exhibited.
또한, 이와 같이 본 발명에서는 지지말뚝이 구조부재로서 활용되므로, 콘크리트 지하 벽체의 두께를 줄일 수 있으며, 본 발명에서는 앵커의 설치가 매우 용이하므로, 필요한 개소에 적절하게 앵커를 설치할 수 있고, 따라서 지하 벽체의 지지점 개수를 늘릴 수 있어 그 만큼 지하 벽체의 두께를 줄일 수 있는 효과가 있다. In addition, since the support pile is utilized as a structural member in the present invention as described above, the thickness of the concrete underground wall can be reduced, and in the present invention, since the anchor is very easy to install, the anchor can be appropriately installed in the required location, and therefore, the underground wall The number of support points can be increased so that the thickness of the underground wall can be reduced by that much.
이와 같이 지하 벽체의 두께가 줄어들게 되면 그 만큼 콘크리트 지하 벽체 시공비가 절감될 뿐만 아니라 콘크리트 지하 벽체가 차지하고 있던 면적이 줄어들 어 더 넓은 지하 면적을 확보할 수 있게 되는 효과가 발휘된다. As such, when the thickness of the underground wall is reduced, the construction cost of the concrete underground wall is not only reduced, but the area occupied by the concrete underground wall is reduced, thereby securing a wider underground area.
본 발명에서는, 지반에 천공된 구멍에 삽입 설치된 엄지 말뚝을 포함하며; 상기 엄지 말뚝은, 두 개의 판부재가 길이 방향으로 간격을 두고 마주 하고 있어 상기 판부재 사이에 길이 방향으로 연속된 중공부가 형성되어 있는 구조를 가지며; 상기 판부재의 후면에는 상기 중공부의 후방을 폐쇄하는 후면 덮개가 설치되어 있고; 상기 구멍에 충진재가 채워져 있되, 상기 엄지 말뚝의 후면 측의 외부에는 충진재가 부착되어 엄지 말뚝의 후면 측이 충진재에 매립되어 충진재와 일체화되어 있지만, 상기 엄지 말뚝의 전면 측의 외부에는 충진재가 부착되지 아니하며, 상기 중공부 내부에는 충진재가 채워져 있지 아니한 구조를 가지는 것을 특징으로 하는 지지말뚝이 제공된다. The present invention includes a thumb pile inserted into a hole drilled into the ground; The thumb pile has a structure in which two plate members face each other at intervals in the longitudinal direction such that a hollow portion extending in the longitudinal direction is formed between the plate members; A rear cover for closing the rear of the hollow part is installed at the rear of the plate member; Filler is filled in the hole, but the filler is attached to the outside of the rear side of the thumb pile and the rear side of the thumb pile is embedded in the filler and integrated with the filler, but the filler is not attached to the outside of the front side of the thumb pile No, there is provided a support pile, characterized in that the hollow portion has a structure that is not filled with a filler.
또한, 본 발명에서는, 두 개의 판부재가 길이 방향으로 간격을 두고 마주 하고 있어 상기 판부재 사이에 길이 방향으로 연속된 중공부가 형성되어 있고 상기 판부재의 후면에는 상기 중공부의 후방을 폐쇄하는 후면 덮개가 설치되어 있는 구조를 가진 엄지 말뚝이, 지반에 천공된 구멍에 삽입 설치되어 있되, 상기 구멍 내의 충진재는 상기 엄지 말뚝의 후면 측 외부에만 부착되어 엄지 말뚝의 후면 측이 충진재와 일체화되어 있으며; 전면 지반의 굴착에 의해 상기 엄지 말뚝의 전면 측이 외부에 노출되도록 한 후에, 상기 엄지 말뚝의 전면 측의 양측과 일체화되도록 배면 지반의 절취면 전면으로 콘크리트가 타설되어 지지벽체가 형성되어 있으며; 상기 지지벽체의 전면으로 콘크리트가 타설되어 구조물 벽체가 형성되어 있되, 상기 구조물 벽체를 이루는 콘크리트가 상기 엄지 말뚝의 중공부에도 일체로 채워지게 되어, 상기 엄지 말뚝과 지지벽체와 구조물 벽체가 일체를 이루는 하나의 구조체를 형성하여 배면 토사를 지지하는 구조를 가지는 것을 특징으로 하는 합성 벽체가 제공되며, 위와 같은 합성 벽체를 시공하는 방법이 제공된다. In addition, in the present invention, the two plate members face each other at intervals in the longitudinal direction, the hollow member is formed in the longitudinal direction between the plate member and the rear cover for closing the rear of the hollow portion on the rear of the plate member The thumb pile having a structure is installed, is inserted into the hole drilled in the ground, the filler in the hole is attached only to the outside of the rear side of the thumb pile, the rear side of the thumb pile is integrated with the filler; After the front side of the thumb pile is exposed to the outside by excavation of the front ground, concrete is poured into the front surface of the cut surface of the rear ground so as to be integrated with both sides of the front side of the thumb pile; Concrete is poured into the front surface of the support wall to form a structure wall, wherein the concrete constituting the structure wall is integrally filled in the hollow part of the thumb pile, and the thumb pile, the support wall and the structure wall are integrally formed. There is provided a composite wall, characterized in that it has a structure for supporting the back soil by forming a structure, there is provided a method for constructing such a composite wall.
위와 같은 본 발명에 있어서, 상기 엄지 말뚝의 전면 측 외부에 충진재가 부착되지 않도록 엄지 말뚝의 전면 측에는 전면 덮개가 덮어져 보호될 수 있다. In the present invention as described above, the front cover of the thumb pile may be covered and protected so that the filler is not attached to the outside of the front side of the thumb pile.
또한, 상기한 합성 벽체 및 시공방법에 있어서, 구조물 벽체가 형성되기 전의 상태에서, 상기 엄지 말뚝의 중공부 사이로 천공된 앵커공에 앵커가 삽입되고, 상기 앵커의 외부 단부가 상기 엄지 말뚝의 전면 측에 정착됨으로써, 앵커가 더 설치될 수 있다. Further, in the above-described composite wall and construction method, in the state before the structure wall is formed, an anchor is inserted into the anchor hole drilled between the hollow portions of the thumb pile, and the outer end of the anchor is the front side of the thumb pile. By fixing in, the anchor can be further installed.
이하, 첨부된 예시도면을 참조하여 본 발명의 구성 및 그 시공방법에 대하여 상세히 설명한다. Hereinafter, with reference to the accompanying drawings, the configuration of the present invention and its construction method will be described in detail.
도 1에는 본 발명에서 지지말뚝(1)을 시공하기 위하여 지반에 구멍(100)을 형성한 상태를 보여주는 평면도가 도시되어 있으며, 도 2에는 구멍(100)에 엄지 말뚝(10)을 삽입한 상태를 보여주는 평면도가 도시되어 있고, 도 3에는 구멍(100)의 전면 측을 굴착하여 엄지 말뚝(10)의 전면 측이 노출되도록 한 상태를 보여주는 평면도가 도시되어 있다. FIG. 1 is a plan view showing a state in which the
도 1에 도시된 것처럼 우선 지반에 구멍(100)을 천공하고, 도 2에 도시된 것처럼 상기 구멍(100)에 엄지 말뚝(10)을 삽입 설치한다. 본 발명에 있어서 엄지 말뚝(10)은, 두 개의 판부재(11a, 11b)가 길이 방향으로 간격을 두고 마주 하고 있어 상기 판부재(11a, 11b) 사이에 중공부(12)가 형성되어 있는 구조를 가진다. 도면에 도시된 실시예에서는 각각의 판부재(11a, 11b)가 "ㄷ"자 형상의 형강으로 이루어져, 상기 "ㄷ"자 형강의 평면부가 서로 간격을 두고 마주보도록 배치되어 엄지 말뚝(10)을 이루고 있다. 그러나 본 발명에 있어서 엄지 말뚝(10)은 위와 같은 "ㄷ"자 형상의 형강이 마주보고 있는 것에 한정되지 아니한다. As shown in FIG. 1, a
한편, 상기 엄지 말뚝(10)에 있어서, 상기 판부재(11a, 11b)의 마주 보는 면 사이 즉, 중공부(12)에는 간격 유지를 위한 간격유지부재(19)가 설치될 수도 있다. 상기 간격유지부재(19)는 후술하는 것처럼 중공부(12)에 콘크리트가 채워질 때, 보강재로서의 기능도 수행한다. 또한, 상기 판부재(11a, 11b)의 마주 보는 면에는 상기 간격유지부재(19) 이외에도 중공부(12)에 채워지는 콘크리트와의 접착 및 보강을 위하여 스터드 등의 전단보강재(21)가 구비될 수 있다. On the other hand, in the
구멍(100)에 엄지 말뚝(10)이 배치된 상태에서, 구멍(100)에 소일 시멘트 또는 콘크리트 등의 충진재(101)를 주입하게 된다. In the state where the
도 3에 도시된 것처럼, 본 발명에서는 구멍(100)의 전면 방향의 토사를 굴착하거나 또는 사면 절취를 하였을 때, 엄지 말뚝(10)의 전면 측이 외부에 노출되어야 한다. 이를 위하여, 본 발명에서는, 구멍(100)에 충진재(101)를 주입한 상태에서, 엄지 말뚝(10)의 배면 토사 방향 즉, 상기 엄지 말뚝(10)의 후면 측(도시된 실시예에서는 "ㄷ"자 형강의 배면 토사 방향의 플랜지와 복부 일부) 외부에는 충진 재(101)가 부착되어 엄지 말뚝(10)의 후면 측이 충진재(101)와 일체가 되지만, 엄지 말뚝(10)의 전면 측(도시된 실시예에서는 "ㄷ"자 형강의 굴착 토사 방향의 플랜지와 복부 일부) 외부에는 충진재(101)가 부착되지 않은 상태를 이루게 된다. 또한, 말뚝(10)의 마주 보는 상기 판부재(11a, 11b) 사이의 중공부(12)에도 충진재(101)가 주입되지 아니한 상태가 된다. 이를 위하여 다음과 같은 구조를 적용할 수 있다. As shown in FIG. 3, in the present invention, when excavation or slope cutting of the soil in the front direction of the
도 4a 및 도 4b에는 구멍(100)에 엄지 말뚝(10)을 배치하는 상태를 보여주는 개략적인 정면 사시도 및 배면 사시도가 각각 도시되어 있는데, 도면에 도시된 실시예처럼, 상기 판부재(11a, 11b)의 중공부(12) 후면 측에는 후면 덮개(13)를 설치하여 중공부(12)의 후면 측을 폐쇄함으로써, 구멍(100)에 충진재(101)를 채웠을 때 충진재(101)가 중공부(12)로 유입되는 것을 방지할 수 있다. 이 때 도 4b에 도시된 것처럼 후면 덮개(13)는 고정부재(14)를 이용하여 그 위치를 고정할 수 있다. 즉, 후면 덮개(13)를 지지하는 고정부재(14)를 배치하고 고정부재(14)를 엄지 말뚝(10)에 용접하거나 또는 접착제 등으로 부착하여 후면 덮개(13)의 위치를 고정할 수 있다. 물론 고정부재(14) 없이 후면 덮개(13) 자체를 엄지 말뚝(10)에 고정시킬 수도 있다. 4A and 4B show schematic front and rear perspective views, respectively, showing a state where the
한편, 엄지 말뚝(10)의 전면 측 외부에 충진재(101)가 붙지 않도록, 엄지 말뚝(10)의 전면 측을 전면 덮개(15)로 덮어 보호한다. 도 4a에 도시된 실시예에서는 엄지 말뚝(10)을 이루는 "ㄷ"자 형강의 전면 측 플랜지와 복부 일부를 감싸도록 전면 덮개(15)가 설치되어 있다. 도면에서 부재번호 16과 17은 각각 전면 덮 개(15)를 설치하기 위하여 "ㄷ"자 형강의 복부 측면에 설치된 앵글 부재(16)와, 전면 덮개(15)와 앵글 부재(16)를 결합하는 체결부재(17)이다. 부재번호 18은 2분할 된 전면 덮개(15)를 사용하는 경우 전면 덮개(15)를 서로 결합하는 체결부재(18)이다. 본 발명에 있어서 전면 덮개(15)는 도면에 도시된 실시예에 한정되지 아니하며 전면 측 플랜지와 복부 일부를 감싸도록 구성된 것이면 다양한 형태로 변형될 수 있다. On the other hand, the front cover side of the
이와 같이 전면 덮개(15)를 이용하여 엄지 말뚝(10)의 전면 측을 덮어 보호한 상태에서 충진재(101)를 구멍(100)에 주입하게 되면, 엄지 말뚝(10)의 후면 측 외부에는 충진재(101)가 부착되어 엄지 말뚝(10)의 후면 측이 충진재(101)와 일체가 되지만, 엄지 말뚝(10)의 전면 측 외부에는 충진재(101)가 부착되지 않은 상태가 되는 본 발명에 따른 지지말뚝(1)을 형성하게 된다. When the
후속하여 지하 굴착 또는 사면 절취 단계에서 구멍(100)의 전면 측을 굴착하고 전면 덮개(23)를 제거하게 된다. 이 때, 엄지 말뚝(10)의 전면 측 외부에 있는 충진재(101)도 제거된다. 따라서 도 5의 평면도에 도시된 것처럼, 엄지 말뚝(10)의 후면 측은 충진재(101)에 매립되어 있지만, 엄지 말뚝(10)의 전면 측 외부에는 충진재(101)가 부착되어 있지 아니하였으므로, 후면 측은 충진재(101)와 일체로 되어 있는 상태이고, 전면 측은 쉽게 그대로 외부에 노출된 상태가 된다. Subsequently, in the underground excavation or slope cutting step, the front side of the
지지말뚝(1)이 시공된 상태에 후속하여 지하 굴착 또는 사면 절취 작업을 수행하여 도 5에 도시된 바와 같이 엄지 말뚝(10)의 전면 측을 외부로 노출시킨 상태에 후속하여, 지반의 절취면 전면으로 지지벽체(2)를 형성한 상태의 평단면도가 도 6에 도시되어 있으며, 도 7에는 도 6에 도시된 상태의 개략적인 사시도가 도시되어 있다. Subsequent excavation or slope cutting operation is performed after the
도 5에 도시된 것처럼 본 발명의 지지말뚝(1)이 시공된 상태에서 전면 지반을 굴착하여, 엄지 말뚝(10)의 전면 측이 외부에 그대로 노출되도록 한 후에는 도 6 및 도 7에 도시된 것과 같이 지반의 절취면 전면으로 콘크리트를 타설하여 지지말뚝(1) 사이의 배면 지반을 지지하기 위한 지지벽체(2)를 형성한다. 상기 지지벽체(2)는 외부로 노출되어 있는 엄지 말뚝(10)부분의 두께로 형성될 수 있는데, 도면에 도시된 실시예와 같이 "ㄷ" 자 형강의 엄지 말뚝(10)의 경우, 상기 지지벽체(2)는 "ㄷ" 자 형강의 외부 플랜지까지의 두께로 형성되는 것이 바람직하다. 도 8에서 부재번호 22는 지지벽체(2)의 보강을 위한 보강철근(22)이다. 이와 같이 지지벽체(2)를 설치하는 것은 지지말뚝(1) 전면의 지반을 굴착해가면서 계속하여 진행된다. After excavating the front ground in a state in which the
도 8에는 구조물 벽체(3)가 시공된 상태를 보여주는 평단면도가 도시되어 있는데, 상기 지지벽체(2)가 시공된 후에는 도 8에 도시된 것처럼, 상기 지지벽체(2)의 전방으로 콘크리트를 타설하여 구조물 벽체(3)를 일체로 시공한다. FIG. 8 is a plan sectional view showing a state in which the
상기 구조물 벽체(3)를 이루는 콘크리트는 상기 엄지 말뚝(10)의 판부재(11a, 11b) 사이의 중공부(12)에도 채워지게 되어, 지지말뚝(1)의 휨강성을 보강하게 되며, 엄지 말뚝(10)과 구조물 벽체(3)가 일체로 합성되어 하나의 구조체로서 기능하게 된다. 즉, 지지말뚝(1)의 엄지 말뚝(10)과 지지벽체(2), 그리고 구조물 벽체(3)가 일체화된 합성 벽체가 시공되는 것이다. The concrete constituting the structure wall (3) is also filled in the
상기 구조물 벽체(3)의 시공을 위한 콘크리트를 타설하기에 앞서, 상기 엄지 말뚝(10)의 중공부(12)에는 결합철근(23)을 미리 설치하는 것이 바람직하다. 상기 결합철근(23)은 그 일측이 중공부(12) 내에 배치되고, 그 단부는 상기 지지벽체(2)의 외부로 돌출되어 구조물 벽체(3)를 이루는 콘크리트 내에 매립됨으로써, 상기 중공부(12) 즉, 지지말뚝(1)과 지지벽체(2), 그리고 구조물 벽체(3)를 모두 일체화시키는 기능을 함과 동시에 보강부재로서의 기능을 수행하게 된다. 도면에 도시된 실시예에서 상기 결합철근(23)은 루프 형상으로 이루어져 있으나, 그 형상은 도면의 실시예에 한정되지 아니하며 자유롭게 변형될 수 있다. Prior to placing the concrete for the construction of the
상기 구조물 벽체(3)는 굴착된 지반에 설치되는 지하 구조물의 벽체일 수도 있으며, 굴착된 지반에 설치되는 옹벽의 벽체일 수도 있다. 상기 구조물 벽체(3)를 시공함에 있어서, 상기 엄지 말뚝(10)의 노출된 전면 측에는 구조물 벽체(3)와의 일체 결합을 위하여 스터드 등의 전단연결재(31)를 더 설치하여(도 7 및 도 8 참조), 상기 전단연결재(31)가 구조물 벽체(3)의 콘크리트 내에 매립되도록 할 수도 있다. The
한편, 상기 구조물 벽체(3)를 시공하기에 앞서, 지지벽체(2)를 시공한 후 또는 지지벽체(2)를 시공하기 전에 상기 지지말뚝(1)에는 앵커(4)를 더 설치할 수도 있다. Meanwhile, an
도 9는 앵커(4)를 설치한 후 옹벽의 수직 벽체로서 구조물 벽체(3)를 시공한 상태의 측면도이며, 도 10은 앵커(4)를 설치한 후 지하 구조물의 벽체로서 구조물 벽체(3)를 시공한 상태의 측면도다. 본 발명에 있어서는, 간격을 두고 마주보게 배치된 판부재(11a, 11b)로 엄지 말뚝(10)이 구성되므로, 상기 판부재(11a, 11b) 사이로, 상기 후면 덮개(13)를 지나 배면 지반 내에 앵커공을 천공하고, 상기 앵커공에 앵커(4)를 삽입한 후, 상기 앵커(4)의 외부 단부를 상기 엄지 말뚝(10)의 전면 측에 정착함으로써 용이하게 앵커(4)를 설치할 수 있다. 상기 엄지 말뚝(10)의 전면에 정착판을 양측 판부재(11a, 11b) 사이에 걸쳐지게 하고 상기 정착판에 앵커(4)의 단부를 정착함으로써 용이하게 앵커를 정착할 수 있는데, 앵커의 정착 방법이 이에 한정되는 것은 아니다. FIG. 9 is a side view of the
이와 같이, 본 발명에서는 엄지 말뚝(10)을 관통하여 앵커(4)를 용이하게 설치할 수 있으므로, 도 9 및 도 10에 도시된 것처럼, 굴착 지반 높이에 충분한 개소의 앵커(4)를 설치할 수 있고, 이러한 앵커(4)는 영구 앵커로서 이용되어 지지말뚝(2)에 의한 배면 지반 지지력을 크게 향상시키게 되므로, 지지벽체(2) 및 구조물 벽체(3)의 두께를 그 만큼 줄일 수 있게 되는 효과가 발휘된다. Thus, in this invention, since the
앞서 종래 기술의 문제점에서 살펴보았듯이, 지하 구조물의 한 개층 층고가 높아지는 경우, 각 층의 슬래브 간의 간격이 넓어지게 되고, 그 결과 지하 벽체가 부담해야할 토압이 증가하게 되어, 결국 지하 벽체의 두께가 더 증가되지만, 본 발명에서는 앵커의 설치가 매우 용이하므로, 각 층 높이에서 필요한 개소에 충분하게 앵커를 설치할 수 있으므로, 구조물 벽체의 두께를 줄일 수 있으며 따라서 종래의 경우처럼, 지하 벽체의 두께 증가, 그로 인한 공사비의 증가 및 지하층의 연면적 감소 등의 단점을 해소할 수 있게 된다. As discussed in the above-mentioned problems of the prior art, when the height of one floor of an underground structure is increased, the spacing between slabs of each floor becomes wider, and as a result, the earth pressure to be burdened by the underground wall increases, resulting in an increase in the thickness of the underground wall. Although it is further increased, in the present invention, the installation of the anchor is very easy, so that the anchor can be sufficiently installed at the required location at each floor height, so that the thickness of the structure wall can be reduced, and thus, as in the conventional case, the thickness of the underground wall is increased, As a result, it is possible to solve the disadvantages such as increase in construction cost and decrease of floor area of basement floor.
도 1은 본 발명에서 지지말뚝을 시공하기 위하여 지반에 구멍을 형성한 상태를 보여주는 평면도이다. 1 is a plan view showing a state in which a hole is formed in the ground to construct a support pile in the present invention.
도 2는 도 1의 구멍에 엄지 말뚝을 삽입한 상태를 보여주는 평면도이다. FIG. 2 is a plan view illustrating a state where a thumb pile is inserted into the hole of FIG. 1. FIG.
도 3은 도 2의 상태에서 구멍의 전면 측을 굴착하여 엄지 말뚝의 전면 측이 노출되도록 한 상태를 보여주는 평면도이다. 3 is a plan view showing a state in which the front side of the thumb pile is exposed by excavating the front side of the hole in the state of FIG.
도 4a 및 도 4b는 각각 구멍에 엄지 말뚝을 배치하는 상태를 보여주는 개략적인 정면 사시도 및 배면 사시도이다. 4A and 4B are schematic front and rear perspective views showing a state where a thumb pile is disposed in a hole, respectively.
도 5는 지하 굴착 또는 사면 절취 단계에서 구멍의 전면 측을 굴착하고 엄지 말뚝에 구비되었던 전면 덮개를 제거한 상태를 보여주는 평면도이다. 5 is a plan view showing a state in which the front cover of the hole was excavated and the front cover provided in the thumb pile was removed in an underground excavation or a slope cutting step.
도 6은 지하 굴착 또는 사면 절취 작업을 수행한 후, 지반의 절취면 전면으로 지지벽체를 형성한 상태를 보여주는 평단면도이다. Figure 6 is a cross-sectional view showing a state in which the support wall is formed in front of the cut surface of the ground after performing the underground excavation or slope cutting operation.
도 7은 도 6에 도시된 상태의 개략적인 사시도이다. 7 is a schematic perspective view of the state shown in FIG. 6.
도 8은 구조물 벽체가 시공된 상태를 보여주는 평단면도이다. 8 is a plan sectional view showing a state in which a structure wall is constructed.
도 9는 앵커를 설치한 후 옹벽의 수직 벽체로서 구조물 벽체를 시공한 상태를 보여주는 측면도이다. 9 is a side view showing a state in which a structure wall is constructed as a vertical wall of the retaining wall after installing the anchor.
도 10은 앵커를 설치한 후 지하 구조물의 벽체로서 구조물 벽체를 시공한 상태를 보여주는 측면도이다. 10 is a side view showing a state in which a structure wall is constructed as a wall of an underground structure after installing an anchor.
<도면의 주요 부분에 대한 부호의 설명> <Explanation of symbols for the main parts of the drawings>
1 : 지지말뚝1: support pile
2 : 지지벽체2: support wall
3 : 구조물 벽체3: structure wall
10 : 엄지말뚝10: Thumb pile
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020070132693A KR101001084B1 (en) | 2007-12-17 | 2007-12-17 | Composite Wall Using Angled Channel and Constructing Method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020070132693A KR101001084B1 (en) | 2007-12-17 | 2007-12-17 | Composite Wall Using Angled Channel and Constructing Method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20090065216A KR20090065216A (en) | 2009-06-22 |
KR101001084B1 true KR101001084B1 (en) | 2010-12-14 |
Family
ID=40993623
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020070132693A KR101001084B1 (en) | 2007-12-17 | 2007-12-17 | Composite Wall Using Angled Channel and Constructing Method thereof |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101001084B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101687495B1 (en) * | 2015-10-01 | 2016-12-16 | 박광호 | Partial top-down construction method for building underground structures |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10298976A (en) * | 1997-05-01 | 1998-11-10 | Kajima Corp | Foundation structure for building bound with soil cement column row earth retaining wall to skeleton |
JP2000297440A (en) | 1999-04-15 | 2000-10-24 | Toda Constr Co Ltd | Underground exterior wall and construction thereof |
JP2002097631A (en) | 2000-09-26 | 2002-04-02 | Ohbayashi Corp | Main body utilizing method for soil cement column row wall |
JP2002146774A (en) | 2000-11-13 | 2002-05-22 | Tekken Constr Co Ltd | Soil-cement column-row wall construction method |
-
2007
- 2007-12-17 KR KR1020070132693A patent/KR101001084B1/en active IP Right Grant
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH10298976A (en) * | 1997-05-01 | 1998-11-10 | Kajima Corp | Foundation structure for building bound with soil cement column row earth retaining wall to skeleton |
JP2000297440A (en) | 1999-04-15 | 2000-10-24 | Toda Constr Co Ltd | Underground exterior wall and construction thereof |
JP2002097631A (en) | 2000-09-26 | 2002-04-02 | Ohbayashi Corp | Main body utilizing method for soil cement column row wall |
JP2002146774A (en) | 2000-11-13 | 2002-05-22 | Tekken Constr Co Ltd | Soil-cement column-row wall construction method |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101687495B1 (en) * | 2015-10-01 | 2016-12-16 | 박광호 | Partial top-down construction method for building underground structures |
Also Published As
Publication number | Publication date |
---|---|
KR20090065216A (en) | 2009-06-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101696916B1 (en) | Construction method of permanent wall with retaining wall combined PHC pile and steel pipe | |
JP5584542B2 (en) | Ground deformation prevention method and underground structure construction method using the same | |
KR101014018B1 (en) | Composite Wall Using Angled Channel | |
KR101973565B1 (en) | Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate | |
KR101103142B1 (en) | Retaining wall structure and construction method of the retaining wall structure | |
KR101640449B1 (en) | Construction method for open cutting in tunnel portal area | |
KR101655217B1 (en) | Construction method for open cutting in tunnel portal area | |
KR20140013497A (en) | Method for constructing block type reinforced retaining wall in cut site | |
KR101524303B1 (en) | The wall members and underground wall, underground wall construction method using the same | |
JPH1150457A (en) | Earth retaining construction used for earth anchor | |
KR102208236B1 (en) | Semi Open Cut Type Supporting System of Tunnel and the Construction Method of Tunnel Using by Same | |
JP2000265484A (en) | CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL | |
JPH06116942A (en) | Construction method of critical sheathing wall | |
JP3829319B2 (en) | Construction method of underground hollow structure and its underground hollow structure | |
KR100969778B1 (en) | Composite Wall Using Angled Channel and Constructing Method thereof | |
KR102113291B1 (en) | Soil retaining wall using phc pile and construction method thererof | |
KR101041264B1 (en) | Displacement control tunnelling reinforcing structure using pressurizing support | |
KR101001084B1 (en) | Composite Wall Using Angled Channel and Constructing Method thereof | |
KR100534603B1 (en) | Apparatus for Retaining Wall Using a Ground Anchor And the Method Using the Same | |
KR20090011442A (en) | Tunnel boring method using sheet pile and tunnel structure therof | |
KR20090078684A (en) | Composite wall using angled channel and constructing method thereof | |
JP4485006B2 (en) | Construction method for underground structures | |
KR100984040B1 (en) | Method of reinforced earth retaining wall for cutting face through double reinforcing execution | |
JP7053402B2 (en) | Rectangular shaft and its construction method | |
KR100400853B1 (en) | Removable soil nailing method and its nail assembly |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E90F | Notification of reason for final refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20131030 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20141103 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20151102 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20161124 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20171106 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20181031 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20191111 Year of fee payment: 10 |