KR100898283B1 - Steel-frame for SRC-frame that steel reinforcement is pre-assembled and Steel-frame structure execution method by using the steel-frame - Google Patents
Steel-frame for SRC-frame that steel reinforcement is pre-assembled and Steel-frame structure execution method by using the steel-frame Download PDFInfo
- Publication number
- KR100898283B1 KR100898283B1 KR1020070080777A KR20070080777A KR100898283B1 KR 100898283 B1 KR100898283 B1 KR 100898283B1 KR 1020070080777 A KR1020070080777 A KR 1020070080777A KR 20070080777 A KR20070080777 A KR 20070080777A KR 100898283 B1 KR100898283 B1 KR 100898283B1
- Authority
- KR
- South Korea
- Prior art keywords
- steel
- bars
- assembled
- reinforcing
- column
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/185—Connections not covered by E04B1/21 and E04B1/2403, e.g. connections between structural parts of different material
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/19—Three-dimensional framework structures
- E04B1/1903—Connecting nodes specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B1/2403—Connection details of the elongated load-supporting parts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/58—Connections for building structures in general of bar-shaped building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/36—Columns; Pillars; Struts of materials not covered by groups E04C3/32 or E04C3/34; of a combination of two or more materials
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Joining Of Building Structures In Genera (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
본 발명은 철근이 선조립된 SRC 기둥용 철골기둥 및 이를 이용한 철골조 시공방법에 관한 것으로서, 더욱 상세하게는 H-형강에 주철근 및 띠철근을 선조립하여 철골기둥을 제작한 뒤 철골기둥의 시공이 이루어지도록 함으로써, 고소작업으로 인한 안전사고를 방지하고, 철근의 시공 정밀도를 향상시키며, 공중에서 철근을 조립하는 공법에 비해 공사기간을 단축시키고, 또한 연결철근의 한쪽 모서리부에 배치된 주철근이 연결철근에 밀착된 구조로 형성되어 철골기둥에 철골보 설치가 주철근과의 간섭없이 용이하게 이루어지는 철근이 선조립된 SRC 기둥용 철골기둥 및 이를 이용한 철골조 시공방법에 관한 것이다.The present invention relates to a steel pillar for SRC columns pre-assembled reinforcing bar and steel frame construction method using the same, and more specifically, the construction of the steel column after the pre-assembly of the cast iron and strip reinforcement in the H- section steel This prevents safety accidents caused by aerial work, improves the construction accuracy of rebars, shortens the construction period compared to the method of assembling rebars in the air, and connects the main reinforcing bars located at one corner of the connecting bars. Steel frame pillars for SRC columns pre-assembled steel bars made of a structure that is in close contact with the reinforcing steel pillars is easily installed without interference with the main steel bars, and a steel frame construction method using the same.
이를 위해, 철골보 접합용 거싯플레이트가 용접 설치된 H-형강을 지상의 작업대 상부에 안착시키고, 이 H-형강을 감싸는 구조로 연결철근을 용접한 후, 연결철근의 각 모서리부에 복수의 주철근을 배치시키고, 이 주철근을 띠철근으로 감아 철골기둥을 완성하고, 또한 이 철골기둥을 작업장에 직립으로 양중하여 철골보를 설치하는 철근이 선조립된 SRC 기둥용 철골기둥 및 이를 이용한 철골조 시공방법을 제공한다.To this end, H-beams, which are welded with gusset plates for welding steel beams, are seated on the workbench on the ground, and the connecting bars are welded with a structure surrounding the H-beams, and then a plurality of cast bars are placed at each corner of the connecting bars. The steel reinforcement pillars are wound around the reinforcing steel bars to complete the steel pillars, and the steel pillars are pre-assembled with steel bars to install steel steel beams by lifting the steel pillars upright in the workshop, and a steel frame construction method using the same.
SRC 기둥, 철골기둥, 철골보, 거싯플레이트, H-형강, 띠철근, 주철근, 연결철근 SRC columns, steel columns, steel beams, gusset plates, H-beams, band bars, cast bars, connecting bars
Description
본 발명은 철근이 선조립된 SRC 기둥용 철골기둥 및 이를 이용한 철골조 시공방법에 관한 것으로서, 더욱 상세하게는 H-형강에 주철근 및 띠철근을 선조립하여 철골기둥을 제작한 뒤 철골기둥의 시공이 이루어지도록 함으로써, 고소작업으로 인한 안전사고를 방지하고, 철근의 시공 정밀도를 향상시키며, 공중에서 철근을 조립하는 공법에 비해 공사기간을 단축시키고, 또한 연결철근의 한쪽 모서리부에 배치된 주철근이 연결철근에 밀착된 구조로 형성되어 철골기둥에 철골보 설치가 주철근과의 간섭없이 용이하게 이루어지는 철근이 선조립된 SRC 기둥용 철골기둥 및 이를 이용한 철골조 시공방법에 관한 것이다.The present invention relates to a steel pillar for SRC columns pre-assembled reinforcing bar and steel frame construction method using the same, and more specifically, the construction of the steel column after the pre-assembly of the cast iron and strip reinforcement in the H- section steel This prevents safety accidents caused by aerial work, improves the construction accuracy of rebars, shortens the construction period compared to the method of assembling rebars in the air, and connects the main reinforcing bars located at one corner of the connecting bars. Steel frame pillars for SRC columns pre-assembled steel bars made of a structure that is in close contact with the reinforcing steel pillars is easily installed without interference with the main steel bars, and a steel frame construction method using the same.
일반적으로 철골철근콘크리트구조(Steel framed Reinforced Concrete construction, SRC)는 철골을 중심으로 그 주위를 철근으로 둘러싸고 여기에 콘크 리트를 타설하여 단일체로 만든 구조, 즉 철근콘크리트구조와 철골구조의 중간적인 구조이다. In general, steel framed reinforced concrete construction (SRC) is a structure made of a single body by surrounding concrete with steel bars and casting concrete therein, that is, intermediate structure between reinforced concrete structure and steel structure. .
상기 철근콘크리트구조는 압축력에는 강하지만 인장력에는 매우 약한 콘크리트에 인장력이 강한 철근을 보강하여 상호보완되도록 한 구조로, 구조적으로나 경제적으로 많이 사용되고 있는데, 이러한 철근콘크리트구조는 여러 가지 장점에도 불구하고 부재의 단면과 중량이 커서 자중이 무겁고 고층이 될수록 기둥이 굵어지고 유효면적이 작아지는 결점이 있으며, 휨에 약하여 장스팬 건물(스팬이 7∼8m이상)이나 고층건물에는 부적합하고, 공사진행상황에 맞추어 콘크리트를 타설하고 양생해야 하므로 공사기간이 많이 소요되며, 균일한 시공이 어려워 철저한 관리가 요구되는 단점이 있다. The reinforced concrete structure is a structure that reinforces the reinforcing bar reinforced with concrete that is strong in compressive force but very weak in tensile force, and is used structurally and economically, and the reinforced concrete structure is used in spite of various advantages. The larger the cross-section and weight, the higher the weight and the higher the floor, the more thick the column and the smaller the effective area.The weaker the warpage, the more unsuitable for long span buildings (spans of 7 to 8m or more) or high-rise buildings. Since it is necessary to pour and cure concrete, it takes a lot of construction period, and it is difficult to uniform construction, which requires thorough management.
한편, 상기 철골구조는 철근콘크리트에 비해 강도와 연성이 우수한 재질이므로 지진이나 바람, 충격등에 의한 변형에너지를 많이 흡수할 수 있는 구조로서, 고층 또는 초고층 건물이나 장스팬 건물에 유리한 장점이 있는 반면, 압축력에 대하여 부재가 좌굴하기 쉽고, 용접연결시 고온에 의해 강도저하나 변형이 발생하기 쉬우며, 습기에 쉽게 녹슬기 쉬운 단점이 있고 내화성이 부족하므로 값비싼 내화피복을 필요로 한다. On the other hand, the steel structure is a structure that can absorb a lot of deformation energy due to earthquake, wind, impact, etc., because the strength and ductility of the material is superior to the reinforced concrete, while having advantages in high-rise or high-rise buildings or long span buildings, The member is easy to buckle against the compressive force, the strength and deformation are easily caused by high temperature during welding connection, and it is easy to be rusted with moisture.
따라서, 이들 양자간의 결점을 보완하기 위하여 이들을 혼용한 혼합구조(일예로 하층은 철근콘크리트구조로 하고, 상층은 철골구조로 한 구조)와 기둥ㆍ보가 서로다른 단일부재로 구성된 복합구조(일예로 기둥을 철근콘크리트로 하고 보를 철골로 한 구조)의 연구가 다양하게 이루어지고 있으며, 특히 단순하게 단일구조를 혼용한 혼합구조보다는 각각의 단일부재의 장점을 조합한 복합구조로 내화성이 좋고 자중이 가벼운 철골철근콘크리트 구조가 활발하게 개발되고 있다. Therefore, in order to make up for the shortcomings between the two, a mixed structure (eg, a reinforced concrete structure in the lower layer and a steel structure in the upper layer) and a composite structure composed of a single member having different columns and beams (for example, a pillar) Is made of reinforced concrete and beams made of steel). Especially, it is a composite structure that combines the advantages of each single member rather than a simple mixed structure. Reinforced concrete structures are actively being developed.
이러한 철골철근큰크리트구조는 철골뼈대를 철근콘크리트로 피복하고 보강한 형식으로 외력은 철골이 부담하고 그 주위를 둘러싼 철근콘크리트는 화재시에 피복으로서 보강을 해준다. This steel reinforced large concrete structure is a form of covering and reinforcing the steel frame with reinforced concrete, the external force is borne by the steel frame and the reinforced concrete surrounding the reinforcement as a coating in the event of fire.
일반적으로 5, 6층 정도의 내화구조물은 주로 철근콘크리트 구조이며, 그 이상의 층수건물은 철근콘크리트 구조로 되면 건물의 자중이 커지고 그것을 지지하는 만큼 아래층의 기둥이나 보의 단면이 과대하여 건물의 이용면에서 경제성 및 기능이 저하되므로 중량에 대해서 강도가 높은 철골을 주구조체로 사용하고 화재시의 철골의 강도저하를 보완하기 위하여 그 주위를 철근콘크리트로 감싸는 형식의 구조로 하여 고층건축에서는 철골철근콘크리트(이하"SRC"라 칭한다.)구조로 할 때가 많다.In general, fire resistant structures of 5 or 6 floors are mainly reinforced concrete structures, and more floor buildings have reinforced concrete structures, which increase the weight of the building and support the lower floors so that the cross section of columns and beams on the lower floor is excessive. In the high-rise construction, steel reinforced concrete is used because high economic strength and function of steel are used as the main structure, and the structure of surrounding structure is reinforced with reinforced concrete to compensate for the decrease in strength of steel in case of fire. The structure is often referred to as " SRC ".
이러한 SRC 기둥은 지상에 상하로 세워지는 H-형강과, 이 H-형강의 각 모세리측에 세워지는 주철근과, 이 H-형강 및 주철근이 일체화되도록 주철근을 감싸는 띠철근으로 이루어진 구조체에 콘크리트가 타설되어 형성되는 기둥을 일컫는다.These SRC columns are placed on a structure consisting of H-section steel that is erected up and down on the ground, cast steel bars that are erected on each capillary side of the H-beam, and a band reinforcing steel bar that encloses the steel reinforcement to integrate the H-shaped steel and the cast steel. Refers to the pillar formed.
이하 종래 SRC 기둥의 철근 조립공법 공정과 함께 그 문제점을 설명하기로 한다.Hereinafter, the problem with the rebar assembly method of the conventional SRC column will be described.
상기 복수의 H-형강이 통상의 크레인에 의해 작업장에 구축되고, 작업장에 세워진 H-형강 주위에 주철근 및 띠철근이 결속선에 의한 접합방식으로 조립된 후 기둥형상의 거푸집이 철근 접합된 H-형강에 장착되며, 이 거푸집에 콘트리트가 타 설 및 양생되는 과정으로 SRC 기둥이 완성된다.The plurality of H-beams are constructed in a workshop by a conventional crane, and H-beams are reinforced by column-shaped formwork after the main reinforcing bars and the band reinforcing bars are assembled in a joining manner by a ties. It is mounted on the section steel and SRC columns are completed by placing and curing concrete in the formwork.
이와 같이 종래에는 작업장에 H-형강을 먼저 세우고, 각종 철근을 접합하는 방식으로 SRC 기둥의 조립공정이 이루어진다.As such, in the related art, H-shaped steel is first placed in the workshop, and the assembly process of the SRC pillar is performed by joining various rebars.
그러나, 이러한 조립공정은 작업자가 고층높이의 H-형강에 올라가 직접 철근을 조립하게 되어 작업의 안정성이 확보되지 못하고, 현장관리가 쉽게 이루어지지 않는 문제점이 있었다.However, such assembling process has a problem that the worker ascends to the H-shaped steel of the high-rise height to directly assemble the reinforcing bar, the stability of the work is not secured, the site management is not easily made.
또한, 별도의 작업장치를 마련하여 작업함으로써, 조립공정기간이 늘어나고, 작업과정이 복잡해지는 문제점이 있었다.In addition, by providing a separate work device, there is a problem that the assembly process period is increased, and the work process is complicated.
본 발명은 상기와 같은 문제점을 해결하기 위하여 안출한 것으로서, 철골보 접합용 거싯플레이트가 용접 설치된 H-형강을 지상의 작업대 상부에 안착시키고, 이 H-형강을 감싸는 구조로 연결철근을 선조립한 후, 연결철근의 각 모서리부에 복수의 주철근을 배치시키고, 이 주철근을 띠철근으로 감아 철골기둥을 완성하고, 또한 이 철골기둥을 작업장에 직립으로 양중하여 철골보를 설치함으로써, 철골기둥을 양중하기 전에 H-형강을 지상의 작업대에 안착시켜 철근을 조립하는 철근이 선조립된 SRC 기둥용 철골기둥 및 이를 이용한 철골조 시공방법을 제공하는데 그 목적이 있다.The present invention has been made in order to solve the above problems, after mounting the H-shaped steel welded gusset plate for welding cheolgolbo is mounted on the upper surface of the workbench, and pre-assembled the connecting reinforcement with a structure surrounding the H-shaped steel By placing a plurality of cast steel bars at each corner of the connecting reinforcing bar, and winding the cast steel bars with a banded steel bar to complete the steel frame column, and installing the steel steel beams by lifting the steel column columns upright in the workshop, The purpose of the present invention is to provide a steel pillar column for the SRC column, which is pre-assembled with reinforcing steel bars, by placing H-beams on a workbench on the ground, and a method of constructing steel frames using the same.
상기한 목적을 달성하기 위한 본 발명은 철골보 접합용 거싯플레이트가 용접 설치된 H-형강을 지상의 작업대 상부에 안착시킨 뒤, 상기 H-형강을 감싸는 구조로 연결철근을 용접 설치하되, 상기 H-형강의 길이방향을 따라 정해진 간격으로 복수개의 연결철근을 설치하는 단계와; 상기 연결철근의 각 모서리부에 주철근을 선조립하고, 상기 주철근을 띠철근으로 감아 SRC 기둥용 철골기둥을 완성하는 단계와; 상기 철골기둥을 건물의 각 기둥위치에 수직으로 세워 설치하는 단계와; 철골보의 양단부를 이웃한 상기 철골기둥의 거싯플레이트에 볼트로 체결하여 상기 철골기둥에 철골보를 수평 설치하는 단계;를 포함하는 것을 특징으로 한다.In order to achieve the above object, the present invention seats the H-beam steel, which is welded with a gusset plate for welding steel cheolgolbo, on the work surface of the ground, and installs the connecting reinforcing steel in the structure surrounding the H-beam. Installing a plurality of connecting bars at predetermined intervals along a longitudinal direction of the; Pre-assembling the main reinforcing bar at each corner of the connecting reinforcing bar, and winding the main reinforcing bar with a band reinforcing bar to complete the steel column for the SRC pillar; Installing the steel column vertically at each column position of a building; And fastening the bolts to the gusset plates of the steel frame pillars adjacent to both ends of the steel frame beams to horizontally install the steel frame beams on the steel frame pillars.
바람직한 일 실시예에 있어서, 상기 작업대는 지상에 설치되는 빔과; 상기 빔 위에 설치되어 상기 빔에 횡으로 배치되는 H-형강을 지지하게 되는 목재지지부로 구성되는 것을 특징으로 한다.In a preferred embodiment, the work table and the beam is installed on the ground; It is characterized by consisting of a wooden support that is installed on the beam to support the H-shaped steel disposed laterally on the beam.
바람직한 다른 실시예에 있어서, 상기 연결철근은 H-형강의 각 설치위치에서 철근을 '井' 구조로 용접하여 설치하는 것을 특징으로 한다.In another preferred embodiment, the connecting reinforcing bar is characterized in that the installation of the reinforcing bars in the '井' structure at each installation position of the H-shaped steel.
또한, 상기 철골보를 철골기둥에 선조립한 주철근의 간섭없이 스윙시켜 설치할 수 있도록 상기 철골기둥에서 연결철근의 모서리부에 선조립되는 주철근들을 상기 연결철근에 일렬로 결속 고정시키는 것을 특징으로 한다.In addition, the steel reinforcement is characterized in that the main reinforcing bars are pre-assembled in the corner portion of the connection reinforcement in the steel frame to be installed without the interference of the pre-assembled cast steel reinforcement in the steel frame in line with the connection reinforcement.
그리고, 스윙되는 철골보와의 간섭을 방지하기 위해, 상기 주철근들이 일렬로 결속 고정되는 연결철근은 H-형강의 내측으로 이동시켜 설치함으로써 결속 고정된 주철근들이 H-형강의 외측으로 돌출되지 않도록 하는 것을 특징으로 한다.And, in order to prevent the interference with the swinging cheolgolbo, the connecting reinforcing bar is fixed in a row to move the installation to the inside of the H-beams so that the fixed fixed steel bars do not protrude out of the H-beams It features.
덧붙여, 상기 연결철근에 결속 고정시킨 주철근들은 철골기둥에 철골보를 설치한 후에 띠철근으로 이동시켜 이 띠철근에 결속 고정시키는 것을 특징으로 한다.In addition, the main reinforcing bars fixed to the connecting reinforcing bar is characterized in that the fastening to the reinforcing bars by moving to the band reinforcing bars after installing the cheolgolbo on the steel column.
바람직한 또 다른 실시예에 있어서, H-형강과; 철골보의 볼트 체결을 위해 상기 H-형강의 웹 및 플랜지에 용접 설치되는 거싯플레이트와; 상기 H-형강을 감싸는 구조로 용접 설치되되, 상기 H-형강의 길이방향을 따라 정해진 간격으로 복수개가 설치되는 연결철근과; 상기 연결철근과 하기 띠철근에 결속시켜 선조립되는 주철근과; 상기 주철근을 감는 구조가 되도록 주철근에 결속 고정되는 띠철근; 을 포함하여 구성되는 것을 특징으로 한다.In another preferred embodiment, the H-beam; Gusset plate is welded to the web and flange of the H-beam for fastening the bolt of the cheolgolbo; A connecting reinforcing bar installed in a structure surrounding the H-shaped steel, the plurality of connecting bars being installed at predetermined intervals along the longitudinal direction of the H-shaped steel; A main reinforcing bar pre-assembled by binding to the connecting reinforcing bar and the following band reinforcing bar; A band reinforcing bar fixed to the main bar so as to have a structure in which the main bar is wound; Characterized in that comprises a.
또한, 상기 연결철근은 H-형강의 각 설치위치에서 철근이 '井' 구조로 용접되어 구성되는 것을 특징으로 한다.In addition, the connecting reinforcing bar is characterized in that the reinforcing bar is welded in a '井' structure at each installation position of the H-shaped steel.
덧붙여, 상기 철골보가 철골기둥에 선조립된 주철근의 간섭없이 스윙되어 설치될 수 있도록 상기 철골기둥에서 연결철근의 모서리부에 선조립되는 주철근들은 상기 연결철근에 결속 고정되는 것을 특징으로 한다.In addition, the main steel bars pre-assembled in the corner portion of the connection reinforcement in the steel frame so that the steel frame can be installed swinging without interference of the pre-assembled main steel bars in the steel frame is characterized in that the binding to the connection steel.
그리고, 상기 주철근들이 일렬로 결속 고정되는 연결철근은 H-형강의 내측방향으로 이동한 위치에 설치되어 상기 연결철근에 결속 고정된 주철근이 H-형강의 외측으로 돌출되지 않도록 되어 있는 것을 특징으로 한다.In addition, the connecting reinforcing bar is fixed in a row is connected to the reinforcing bar is installed in a position moved in the inward direction of the H-shaped steel is characterized in that the main reinforcing bar fixed to the connecting bar does not protrude out of the H-shaped steel .
이상에서 본 바와 같이 본 발명에 따른 철근이 선조립된 SRC 기둥용 철골기둥 및 이를 이용한 철골조 시공방법은 다음과 같은 효과를 제공한다.As seen above, the steel column for SRC columns pre-assembled rebar according to the present invention and the steel frame construction method using the same provides the following effects.
우선, 철골기둥을 양중하기 전에 H-형강을 지상의 작업대에 안착시켜 철근을 조립함으로써, 고소작업으로 인한 안전사고를 방지하고, 철근의 시공 정밀도를 향상시키며, First of all, before lifting the steel pillars, H-shaped steel is placed on the workbench on the ground to assemble the reinforcing bars, thereby preventing safety accidents caused by aerial work, and improving the construction accuracy of the reinforcing bars.
따라서, 공중에서 철근을 조립하는 공법에 비해 현장관리가 용이해지며, 공사기간을 단축시키고,Therefore, it is easier to manage the site compared to the method of assembling the rebar in the air, shorten the construction period,
덧붙여, 연결철근의 한쪽 모서리부에 배치된 주철근이 연결철근에 밀착된 구조로 형성되어 철골기둥에 철골보 설치가 주철근과의 간섭없이 용이하게 이루어지는 효과가 있다.In addition, the main reinforcing bar disposed at one corner of the connecting reinforcing bar is formed in a structure in close contact with the connecting reinforcing steel beams on the steel column has the effect that can be easily performed without interference with the main reinforcing bars.
이하, 본 발명의 바람직한 실시예를 첨부도면을 참조로 상세하게 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
첨부한 도 1은 본 발명의 일실시예에 따른 H-형강의 작업대 개시도이고, 도 2 내지 도 4는 본 발명의 일실시예에 따른 철공기둥의 철근 선조립 공정도이고, 도 5 내지 도 8은 본 발명의 일실시예에 따른 철공기둥에 철골보가 설치되는 공정도이다.1 is a view showing a work bench of an H-shaped steel according to an embodiment of the present invention, FIGS. 2 to 4 are rebar line assembly process diagrams of an iron pillar according to an embodiment of the present invention, and FIGS. 5 to 8. Is a process chart in which the cheolgolbo is installed in the iron pillar according to an embodiment of the present invention.
도 1내지 도 8에서 도시한 바와 같이, SRC 기둥의 철근 선조립 공법은 작업대(130)에 안착된 H-형강(100)에 연결철근(140)을 용접하고, 연결철근(140)이 용접된 H-형강(100)에 주철근(160) 및 띠철근(170)을 선조립하여 철골기둥(200)을 완성시킨 후, 건물의 각 기둥위치에 철골기둥(200)을 수직으로 세워 이 철골기둥(200)에 철골보(210)를 설치하는 단계로 이루어진다.As shown in FIGS. 1 to 8, the rebar prefabrication method of the SRC column welds the connecting
우선, 도 1 및 도 2에서 도시한 바와 같이 철골보 접합용 거싯플레이트(150)가 용접 설치된 H-형강(100)은 철근조립이 용이하게 이루어지도록 지상에 수평으로 장착되는 작업대(130) 상부에 안착된다.First, as shown in FIG. 1 and FIG. 2, the H-
이때, 상기 작업대(130)는 상기 H-형강(100)에 횡으로 지상에 설치되는 빔(90)과, 상기 H-형강(100)을 지지하도록 상기 빔(90)과 H-형강(100) 사이에 설치되는 목재지지부(80)로 이루어지고, 이 목재지지부(80)의 상부에 상기 H-형강(100)은 플랜지(110)가 저면으로 놓이도록 안착되는 것이 바람직하다.At this time, the work bench 130 is a
여기서, 상기 빔(90)은 상기 H-형강(100)과 동일한 소재를 사용하는 것이 바람직하고, 상기 목재지지부(80)의 폭은 H-형강(100)의 플랜지(110) 폭보다 작게 형성되는 것이 바람직하다.Here, the
이는 상기 목재지지부(80)의 폭이 플랜지(110) 폭보다 크게 형성되는 경우 H-형강(100)의 하부모서리에 배치되는 주철근(160)이 이 목재지지부(80)와의 간섭으로 띠철근(170)에 결속될 공간이 확보되지 못함으로써, 주철근(160)의 조립공정이 어려워지기 때문이다.When the width of the
또한, 상기 H-형강(100)이 작업장에 운반되기 전에 공장에서 상기 거싯플레이트(150)를 H-형강(100)에 용접 설치함으로써, 공장에서 이미 거싯플레이트(150)가 설치된 H-형강(100)을 작업장으로 이송하여 거싯플레이트(150)가 설치된 H-형강(100)에 철근을 조립하는 작업을 진행하는 것이 바람직하다. In addition, by welding the
여기서, 상기 거싯플레이트(150)는 철골보(210)가 철골기둥(200)에 결합시 철골보(210)의 웹 또는 플랜지가 철골기둥(200)의 중심에 위치하여 결합하도록 도 2의 평면도에서 도시한 바와 같이 철골기둥면의 중심선에서 철골보(210)의 웹 또는 플랜지 두께만큼 이격을 두고 설치하는 것이 바람직하다.Here, the
또한, 상기 H-형강의 웹에 용접되는 거싯플레이트(150)의 상하부에는 철판(50)을 용접 설치하여, 철골보(210)와 볼팅결합하는 거싯플레이트(150)가 H-형강(100)에 설치되어 철골보(210)를 지지하는 고정력이 증가되도록 하는 것이 바람직하다.In addition, the upper and lower portions of the
다음으로, 도 3에서 도시한 바와 같이 거싯플레이트가 설치된 H-형강에 복수의 연결철근(140)을 용접 설치하되, 상기 H-형강에 길이 방향으로 정해진 간격을 두고 설치하는 것이 바람직하다.Next, as shown in FIG. 3, the welding bar is installed on the H-shaped steel in which the gusset plate is installed, but it is preferable to install the H-shaped steel at regular intervals in the longitudinal direction.
특히, 상기 연결철근(140)은 H-형강(100)의 각 외측면보다 길게 설치되어 주철근(160)이 조립되는 4개의 모서리부 공간이 형성되고, "井"형상을 이루는 연결철근(140) 구조물(145)은 H-형강(100)에 층별로 2~3개소씩 용접 설치되어 주철근(160) 및 띠철근(170)이 안정감있게 설치되도록 한다.In particular, the connecting
이때, 상기 복수의 연결철근(140)은 H-형강(100)에 밀착된 상태에서 각 연결철근(140)끼리 용접하거나 H-형강(100)의 플랜지(110)에 용접하는 것이 바람직하다.In this case, the plurality of connecting
또한, 도 3의 평면도에서 도시한 바와 같이 주철근(160)들이 일렬로 결속되는 연결철근(140)을 H-형강(100)의 내측방향으로 이동한 위치에 용접 설치하여, 상기 연결철근(140)에 결속 고정되는 주철근(160)이 H-형강(100)의 외측으로 돌출되지 않도록 하는 것이 바람직하다.In addition, as shown in the plan view of FIG. 3, the connecting
이는 상기 철골보(210)의 스윙시 철골보(210)가 상기 주철근(160)과 간섭되는 것이 방지되도록 철골보(210)의 이동경로를 확보하기 위함이다.This is to secure the movement path of the cheolgolbo 210 so that the cheolgolbo 210 is prevented from interfering with the
상기 연결철근(140)의 설치 후에는 도 4에서 도시한 바와 같이 복수의 주철근(160)을 상기 연결철근(140)의 모서리부에 배치시키고, 복수의 띠철근(170)을 이용하여 이 주철근(160)을 감게 된다.After the installation of the connecting
일 실시예에 있어서, 상기 주철근(160)은 도 4의 평면도에서 도시한 바와 같이 연결철근(140)의 한 모서리부당 3개씩 배치될 수 있고, 이중 2개의 주철근(160)은 연결철근(140) 및 띠철근(170)에 결속선 또는 용접에 의해 설치되며, 1개의 주철근(160)은 상기 띠철근(170)의 모서리에 설치될 수 있다.In one embodiment, as shown in the plan view of Figure 4, the
다만, 상기 3개의 모서리부는 삼각형 구조(2개의 주철근은 연결철근의 단부에 설치되고, 1개의 주철근은 띠철근의 모서리에 설치)로 주철근(160)이 설치되고, 나머지 한개의 모서리부(철골보가 스윙되는 방향의 모서리부)(A)는 도 4에서 도시한 바와 같이 3개의 주철근(160)이 띠철근(170)에 밀착되는 일렬 구조로 결속선(미도시, 통상적으로 철근과 철근을 결합시키는 미세선)에 의해 설치되는 것이 바람직하다.However, the three corner portion is a triangular structure (two main bars are installed at the end of the connecting bar, one main bar is installed at the edge of the band reinforcing bar), the
여기서, 상기 모서리부(A)의 연결철근은 상술한 바와 같이 H-형강(100)의 내측방향으로 상기 주철근(160)의 직경만큼 이동시킨 위치에 용접 설치하여, 상기 주철근(160)을 상기 모서리부(A)의 연결철근에 일렬로 설치하더라도 상기 주철근(160)이 상기 H-형강(100)의 외측으로 돌출되지 않도록 한다.Here, the connecting reinforcing bar of the corner portion (A) is welded at a position moved by the diameter of the
이는 작업장에 양중(직립으로 세움)된 철골기둥(200)에 철골보(210)가 연결 되기 위해 H-형강(100)에 접합된 거싯플레이트(150) 방향으로 철골보(210)가 스윙(swing)되는 경우 철골보(210)가 주철근(160)과 간섭되는 것을 막기 위함이다.This is the
이때, 상기 철골보(210) 또한 철골기둥(200)과 동일하게 한쪽 모서리부가 개방된 구조로 주철근(160)이 조립되어, 상기 철골기둥(200)에 이방향 철골보(210)를 주철근의 간섭없이 설치하는 것이 가능하다.At this time, the
다만, 상기 철골기둥(200)에 4방향으로 철골보(210)를 설치하는 경우 주철근(160)이 띠철근(170)에 일렬로 결속되는 개방구조는 연결철근(140)의 두개 모서리부에 형성되는 것이 바람직하다.However, in the case of installing the
한편, 상기 주철근(160)은 건축 구조물이나 현장상황에 따라 3개 이상 또는 그 이하의 개수로 조립하는 것이 가능하고, 주철근(160)의 설치구조 또한 설치개수에 따라 다양하게 변형되는 것이 가능하다.On the other hand, the main reinforcing
덧붙여, 상기 H-형강보다 길게 형성된 주철근(160)을 상기 H-형강의 상단보다 돌출되게 조립하여, 돌출 설치된 주철근(160)에 또 다른 철골기둥의 주철근을 결속선으로 겹침이음함으로써, 상기 철골기둥이 층별로 복수개가 연결될 수 있도록 한다.In addition, by assembling the
또한, 상기 철골기둥(200)이 양중된 후 주철근(160)이 하부방향으로 겹침이음되도록 상기 띠철근(170)은 도 5에서 도시한 바와 같이 H-형강(100)의 하부에는 설치하지 않는 것이 바람직하다. In addition, the
이와 같이 상기 복수의 볼트홀(155)이 형성된 거싯플레이트(150)를 H-형강(100)의 웹(120) 및 플랜지(110)에 용접하고, H-형강(100)에 복수의 연결철 근(140)을 용접한 후, 주철근(160) 을 연결철근(140)의 각 모서리부에 설치하여 띠철근(170)으로 감아줌으로써, 철근 선조립 공정에 의한 SRC 기둥용 철골기둥(200)이 완성된다.As such, the
여기서, 상기 철근이 선조립된 SRC 기둥용 철골기둥(200)은 지상의 작업대(130) 상부에 안착되는 H-형강(100)과,이 H-형강(100)을 감싸는 구조로 "井"형상이 되도록 용접되는 연결철근(140)과, 이 H-형강(100)의 웹(120) 및 플랜지(110)에 접합하는 거싯플레이트(150)와, 이 연결철근(140)의 각 모서리부에 배치되는 주철근(160)과, 이 주철근(160)을 감는 구조로 주철근(160)과 연결되는 띠철근(170)으로 구성되는 것이 바람직하다.Here, the
완성된 철골기둥(200)은 도 5에서 도시한 바와 같이 통상적인 타워 크레인을 사용하여 작업장의 원하는 위치에 양중(직립으로 세움)하고, 양중되는 철골기둥(200)의 수는 건축 구조물의 특성에 따라 달라지는 것이 바람직하다.The completed
상기 철골기둥이 양중된 후에는 도 6에서 도시한 바와같이 이 철골기둥(200)의 사방에 철골보(210)가 스윙되고, 이 철골보(210)는 H-형강(100)의 웹(120) 및 플랜지(110)에 설치된 복수의 거싯플레이트(150)와 볼팅 결합된다.After the steel column is lifted, as shown in FIG. 6, the
이때, 상기 철골보(210)가 스윙되는 경우 도 4에서 도시한 바와 같이 상기 연결철근(140)의 한쪽 모서리부(A)는 상기 주철근(160)이 연결철근(140)에 밀착되는 구조로 설치되어 이 철골보(210)가 주철근(160)의 간섭없이 거싯플레이트(150)에 접하는 방향으로 이동하게 된다.At this time, when the
또한, 일 실시예에 있어서 도 6에서 도시한 바와 같이 상기 거싯플레이 트(150)는 띠철근(170)에 의해 형성되는 외곽선(B) 안쪽으로 설치되고, 이 거싯플레이트에 볼트홀(155)이 1열로 형성되는 것이 바람직하다.In addition, in one embodiment, as shown in FIG. 6, the
다만, 상기 볼트홀(155)이 1열로 형성된 거싯플레이트(150)가 사용되는 경우 볼팅작업시 볼트를 체결하는데 필요한 도구인 렌치와 주철근(160)의 간섭으로 철골보(210)의 볼트체결이 어려워짐으로써, 이 렌치는 주철근(160)과 거싯플레이트(150) 사이에 삽입될 수 있을정도의 크기를 사용하는 것이 바람직하다. However, when the
또한, 다른 실시예에 있어서 도 7에서 도시한 바와 같이 상기 거싯플레이트(150)는 띠철근(170)에 의해 형성되는 외곽선(B) 바깥쪽으로 형성되어, 크기가 제한되지 않은 렌치와 주철근(160)의 간섭을 방지함으로써, 볼트의 체결작업이 용이하게 이루어지도록 하는 것이 가능하다.In addition, in another embodiment, as shown in FIG. 7, the
여기서, 상기 철골기둥과 철골보(210)의 접합부인 볼트홀(155)이 이 철골기둥(200)에서 멀어지는바 이 철골기둥(200)과 철골보(210)의 결합력을 상승시키기 위해 볼트홀(155)이 2열로 형성되는 것이 바람직하다.Here, the bolt hole 155 that is the junction of the steel column and the
다음으로, 상기 철골기둥(200)의 거싯플레이트(150)에 철골보(210)가 볼팅결합된 후에 연결철근(140)의 한쪽 모서리부(A)에 밀착 형성된 주철근(160)의 구조는 도 8에서 도시한 바와 같이 다른 모서리부의 주철근(160) 구조와 동일하게 변경되도록 2개의 주철근(160)이 띠철근(170) 방향으로 이동하는 것이 바람직하다.Next, after the
여기서, 상기 이동 주철근(160)은 세밀한 결속선으로 연결철근(140)에 결합되어 있는바, 이 결속선을 해체하여 주철근(160)을 이동시킨 후 이동한 주철근(160)을 띠철근(170)과 결속선으로 다시 결합시키는 것이 바람직하다.Here, the moving
상기 주철근(160)이 이동한 후에는 기존 철골기둥(200)의 상부에 돌출된 주철근(160)에 또 다른 철골기둥의 주철근 하부를 결속선으로 겹침이음함으로써, 건물 구조층에 따른 복수의 철골기둥이 연속적으로 연결되는 것이 가능하다.After the main reinforcing
또한, 상기 철골보(210)가 설치된 철골기둥(200)에는 건축 구조물에 맞는 형상으로 거푸집이 설치되어 이 거푸집에 콘크리크가 타설 및 양생됨으로서, SRC 기둥이 완성된다. In addition, the
이상에서는 본 발명을 특정의 바람직한 실시예에 대하여 도시하고 설명하였으나, 본 발명은 이러한 실시예에 한정되지 않으며, 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 특허청구범위에서 청구하는 본 발명의 기술적 사상을 벗어나지 않는 범위내에서 실시할 수 있는 다양한 형태의 실시예들을 모두 포함한다.While the invention has been shown and described with respect to certain preferred embodiments thereof, the invention is not limited to these embodiments, and has been claimed by those of ordinary skill in the art to which the invention pertains. It includes all the various forms of embodiments that can be carried out without departing from the spirit.
도 1은 본 발명의 일실시예에 따른 H-형강의 작업대 개시도, 1 is a working table of the H-shaped steel according to an embodiment of the present invention,
도 2 내지 도 4는 본 발명의 일실시예에 따른 철공기둥의 철근 선조립 공정도, 2 to 4 is a rebar line assembly process diagram of the iron pillar according to an embodiment of the present invention,
도 5 내지 도 8은 본 발명의 일실시예에 따른 철공기둥에 철골보가 설치되는 공정도, 5 to 8 is a process chart in which the cheolgolbo is installed in the iron pillar according to an embodiment of the present invention,
<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>
100 : H-형강 140 : 연결철근100: H-shaped steel 140: connecting rebar
150 : 거싯플레이트 155 : 볼트홀150: gusset plate 155: bolt hole
160 : 주철근 170 : 띠철근 160: cast iron 170: band steel
200 : 철골기둥 210 : 철골보200: steel column 210: steel ball
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020070080777A KR100898283B1 (en) | 2007-08-10 | 2007-08-10 | Steel-frame for SRC-frame that steel reinforcement is pre-assembled and Steel-frame structure execution method by using the steel-frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020070080777A KR100898283B1 (en) | 2007-08-10 | 2007-08-10 | Steel-frame for SRC-frame that steel reinforcement is pre-assembled and Steel-frame structure execution method by using the steel-frame |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20090016264A KR20090016264A (en) | 2009-02-13 |
KR100898283B1 true KR100898283B1 (en) | 2009-05-19 |
Family
ID=40685520
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020070080777A KR100898283B1 (en) | 2007-08-10 | 2007-08-10 | Steel-frame for SRC-frame that steel reinforcement is pre-assembled and Steel-frame structure execution method by using the steel-frame |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100898283B1 (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101033184B1 (en) * | 2011-01-20 | 2011-05-06 | 경서중공업(주) | Reinforcing rod one body type h-beam assembly |
WO2014014158A1 (en) * | 2012-07-19 | 2014-01-23 | (주)센벡스 | Prefabricated src structure using l-shaped steel sections |
KR101648422B1 (en) | 2015-02-10 | 2016-08-16 | (주)씨지스플랜 | Concrete filled tube with round angle |
KR101661542B1 (en) | 2015-12-17 | 2016-10-06 | (주)씨지스플랜 | Pre-fabricated column with ribbed round angle and reinforcing bar and Manufacturing method thereof |
KR20190126530A (en) | 2018-05-02 | 2019-11-12 | (주)씨지스플랜 | Pre-fabricated column with angle-type reinforcing bar |
KR102053859B1 (en) | 2019-04-30 | 2019-12-09 | (주)미르철강 | Construction structure of prefabricated steel frame |
KR102102415B1 (en) | 2019-09-07 | 2020-05-28 | (주)미르철강 | Construction structure of prefabricated steel frame |
KR102102430B1 (en) | 2019-09-07 | 2020-05-28 | (주)미르철강 | Construction structure of prefabricated steel frame |
KR20200069283A (en) | 2020-06-09 | 2020-06-16 | (주)씨지스플랜 | Pre-fabricated column with angle-type reinforcing bar |
KR20200069282A (en) | 2020-06-09 | 2020-06-16 | (주)씨지스플랜 | Pre-fabricated column with angle-type reinforcing bar |
KR102641227B1 (en) | 2023-02-20 | 2024-02-27 | 삼성엔지니어링(주) | Steel Reinforced Concrete Clolumn |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101457077B1 (en) * | 2013-09-17 | 2014-10-31 | 삼성물산 주식회사 | Reformed concrete filled tube column structure |
KR101457080B1 (en) * | 2013-09-17 | 2014-10-31 | 삼성물산 주식회사 | Reformed concrete filled tube column structure |
CN103924734A (en) * | 2014-04-10 | 2014-07-16 | 北京工业大学 | Batten plate constraint type I-shaped steel bone confined concrete column and fabrication method thereof |
CN105155777B (en) * | 2015-09-29 | 2017-07-07 | 江苏京沪重工有限公司 | A kind of double-T shaped post of reinforcing bar and its processing method |
CN105155776B (en) * | 2015-09-29 | 2017-06-27 | 江苏沪宁钢机股份有限公司 | A kind of box reinforcing bar coupled column and its processing method |
CN112609830A (en) * | 2020-12-01 | 2021-04-06 | 中国建筑第八工程局有限公司 | Connecting structure and connecting method of frame beam and steel pipe column |
KR20240055334A (en) * | 2022-10-20 | 2024-04-29 | 주식회사 대동에스앤티 | Pre-assembled column with exterior material attached to truss structure and manufacturing method thereof |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62260968A (en) | 1986-05-07 | 1987-11-13 | 鹿島建設株式会社 | Method for arrangement of beam bar in reinforced concrete structure |
JP2001193156A (en) | 2000-01-14 | 2001-07-17 | Maeda Corp | Structure of column-beam joining part |
JP2004225437A (en) | 2003-01-24 | 2004-08-12 | Nippon Industry Co Ltd | Main reinforcement holder for arrangement of bar in src construction column, and method for bar arrangement |
-
2007
- 2007-08-10 KR KR1020070080777A patent/KR100898283B1/en not_active IP Right Cessation
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62260968A (en) | 1986-05-07 | 1987-11-13 | 鹿島建設株式会社 | Method for arrangement of beam bar in reinforced concrete structure |
JP2001193156A (en) | 2000-01-14 | 2001-07-17 | Maeda Corp | Structure of column-beam joining part |
JP2004225437A (en) | 2003-01-24 | 2004-08-12 | Nippon Industry Co Ltd | Main reinforcement holder for arrangement of bar in src construction column, and method for bar arrangement |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101033184B1 (en) * | 2011-01-20 | 2011-05-06 | 경서중공업(주) | Reinforcing rod one body type h-beam assembly |
WO2014014158A1 (en) * | 2012-07-19 | 2014-01-23 | (주)센벡스 | Prefabricated src structure using l-shaped steel sections |
KR101648422B1 (en) | 2015-02-10 | 2016-08-16 | (주)씨지스플랜 | Concrete filled tube with round angle |
KR101661542B1 (en) | 2015-12-17 | 2016-10-06 | (주)씨지스플랜 | Pre-fabricated column with ribbed round angle and reinforcing bar and Manufacturing method thereof |
KR20190126530A (en) | 2018-05-02 | 2019-11-12 | (주)씨지스플랜 | Pre-fabricated column with angle-type reinforcing bar |
KR102053859B1 (en) | 2019-04-30 | 2019-12-09 | (주)미르철강 | Construction structure of prefabricated steel frame |
KR102102415B1 (en) | 2019-09-07 | 2020-05-28 | (주)미르철강 | Construction structure of prefabricated steel frame |
KR102102430B1 (en) | 2019-09-07 | 2020-05-28 | (주)미르철강 | Construction structure of prefabricated steel frame |
KR20200069283A (en) | 2020-06-09 | 2020-06-16 | (주)씨지스플랜 | Pre-fabricated column with angle-type reinforcing bar |
KR20200069282A (en) | 2020-06-09 | 2020-06-16 | (주)씨지스플랜 | Pre-fabricated column with angle-type reinforcing bar |
KR102641227B1 (en) | 2023-02-20 | 2024-02-27 | 삼성엔지니어링(주) | Steel Reinforced Concrete Clolumn |
Also Published As
Publication number | Publication date |
---|---|
KR20090016264A (en) | 2009-02-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100898283B1 (en) | Steel-frame for SRC-frame that steel reinforcement is pre-assembled and Steel-frame structure execution method by using the steel-frame | |
JP4823790B2 (en) | Column unit and method of building building using column unit | |
US20120023858A1 (en) | Truss-type shear reinforcement material having double anchorage functions at both top and bottom thereof | |
KR101050956B1 (en) | Rebar prefabricated column method | |
KR101998579B1 (en) | Steel Built Up Beam And Column-Beam Joint Construction Method Using Thereof | |
CN107989228A (en) | A kind of prefabricated steel reinforced concrete shear wall structure and its preparation and installation method | |
JP2010242390A (en) | Joining method and structure of column-beam joint part having steel brace | |
KR20100093369A (en) | Structure for connecting horizontal beam to h type beam | |
KR100949828B1 (en) | Steel beam and hybrid beam of steel concrete for slim floor | |
KR101176846B1 (en) | Structure for reinforcing proof stress of girder | |
CN111411643A (en) | Construction method of construction elevator foundation supported on basement top plate | |
JPS627344B2 (en) | ||
JP4996370B2 (en) | Frame assembly method and building frame | |
JP3106881B2 (en) | Mixed structure of reinforced concrete columns and steel beams | |
KR101315365B1 (en) | Hybrid beam structure | |
KR101324884B1 (en) | Hybrid building construction method combining dry type and wet type | |
JP2019132072A (en) | Foundation structure and construction method of the same | |
KR101038291B1 (en) | Steel beam and hybrid beam of steel concrete for slim floor | |
KR20020060429A (en) | Joint of reinforced concrete column and steel beam and a method of the same | |
JP5166055B2 (en) | Construction method of multistory parking lot | |
KR100947979B1 (en) | Method of 3-Storey 5-Car Column Free Plant Type Garage | |
JP3586121B2 (en) | Mixed structure of reinforced concrete column and steel beam and its construction method | |
KR101287031B1 (en) | Hybrid beam structure | |
JP3814265B2 (en) | How to build tower buildings | |
KR102612179B1 (en) | Floor structure using steel concrete composite beam and concrete panel and method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130513 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20140512 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20150310 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20160329 Year of fee payment: 8 |
|
LAPS | Lapse due to unpaid annual fee |