KR100793178B1 - Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad - Google Patents

Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad Download PDF

Info

Publication number
KR100793178B1
KR100793178B1 KR1020070008772A KR20070008772A KR100793178B1 KR 100793178 B1 KR100793178 B1 KR 100793178B1 KR 1020070008772 A KR1020070008772 A KR 1020070008772A KR 20070008772 A KR20070008772 A KR 20070008772A KR 100793178 B1 KR100793178 B1 KR 100793178B1
Authority
KR
South Korea
Prior art keywords
sand
soft ground
mat
film
gravel
Prior art date
Application number
KR1020070008772A
Other languages
Korean (ko)
Inventor
홍병남
Original Assignee
(주)신성엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)신성엔지니어링 filed Critical (주)신성엔지니어링
Priority to KR1020070008772A priority Critical patent/KR100793178B1/en
Application granted granted Critical
Publication of KR100793178B1 publication Critical patent/KR100793178B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B19/00Protection of permanent way against development of dust or against the effect of wind, sun, frost, or corrosion; Means to reduce development of noise
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/001Track with ballast
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/008Drainage of track
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/24Methods or arrangements for preventing slipperiness or protecting against influences of the weather
    • E01C11/26Permanently installed heating or blowing devices ; Mounting thereof
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/05Use of geotextiles
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/07Drainage

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

An apparatus for preventing cold weather damage installed at the soft ground to support a ballast of a railroad is provided to increase support force, and to support the ballast effectively by draining moisture or underground water contained in the soft ground through a sand mat and underground drain films to the outside. A pebble ballast(13) is installed on the ground, and a sleeper(12) is installed on the pebble ballast. Rails(11) are fixed to the sleeper to mount a railroad(10). A sand mat(30) is laid on the soft ground. Underground water drain films(40) are inserted in the sand mat, and the two sides of the underground water drain films are exposed to the outside. The two exposed ends of the underground water drain films are exposed to draining holes(15) formed on the both sides of the ballast. The sand mat is manufactured with a high strength geotextile(32) to be a bag shaped mat. The sand mat is filled with sands(31).

Description

철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치 {Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad}Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad}

도 1은 본 발명의 동해방지장치를 연약지반상에 설치한 것을 전체적으로 보여주는 도면.  1 is a view showing the overall installation of the anti-donghae device of the present invention on the soft ground.

도 2는 본 발명의 연약지반상에 설치된 동해방지장치로서 자갈도상폭에 해당하는 크기의 모래매트내에 지하수배수필름을 관통설치하고, 관통된 지하수배수필름의 양끝단이 배수구에 노출설치되도록 한 것을 보여주는 도면.        Figure 2 is installed on the soft ground of the present invention to prevent the installation of groundwater drainage film in the sand mat of the size corresponding to the gravel island width, and installed so that both ends of the groundwater drainage film penetrated exposed to the drain hole Showing drawings.

도 3은 본 발명의 지하수배수필름을 보여주는 도면.        Figure 3 is a view showing the groundwater drainage film of the present invention.

도 4는 본 발명의 동해방지장치의 다른 실시예로서 다수개의 모래매트를 자갈도상 폭에 걸쳐 설치하고, 지하수배수필름을 관통설치하고 관통설치된 지하수배수필름의 양끝단이 배수구에 노출설치되도록 한 것을 보여주는 도면.       Figure 4 is to install a plurality of sand mats across the gravel island width as another embodiment of the anti-donghae device of the present invention, through the groundwater drainage film and installed so that both ends of the groundwater drainage film installed through the exposure to the drain hole Showing drawings.

도 5는 본 발명의 동해방지장치의 모래매트를 상호연결시켜주는 연결구를 전체적으로 보여주는 도면.       Figure 5 is a view showing the connector as a whole interconnecting the sand mat of the device for preventing the damage of the present invention.

도 6은 본 발명의 동해방지장치인 모래매트를 상호연결시켜주는 연결구를 설치한 것을 보여주는 도면.       Figure 6 is a view showing the installation of the connector for interconnecting the sand mat, which is a device for preventing the damage of the present invention.

도 7은 본 발명의 동해방지장치의 다른 실시예로서 연약지반상에 다수개의 모래매트를 설치하고, 네방향에서 모래매트를 상호연결시켜주는 연결구를 이용하여 상호연결한 것을 보여주는 도면.       FIG. 7 is a view showing that a plurality of sand mats are installed on a soft ground as another embodiment of the apparatus for preventing a sea hazard of the present invention and interconnected by using a connector for interconnecting sand mats in four directions.

도 8은 본 발명의 동해방지장치의 또 다른 실시예로서 연약지반상에 다수개 설치된 모래기둥내에 지하수배수필름을 삽입하고, 그 위에 모래매트를 설치하되, 모래기둥내에 설치된 지하수매수필름이 모래매트내에 삽입관통된 지하수배수필름과 접한 접촉부가 형성된 것을 보여주는 도면.       Figure 8 is another embodiment of the East Sea prevention apparatus of the present invention, while inserting the ground water drainage film in a plurality of pillars of sand installed on the soft ground, the sand mat is installed thereon, the ground water purchase film installed in the sand pillar is a sand mat Figure showing that the contact portion formed in contact with the ground water drainage film inserted through.

<도면의 주요 부분에 대한 부호의 설명>  <Explanation of symbols for the main parts of the drawings>

w ; 도상폭         w; Phase width

10 ; 철도궤도 11 ; 레일         10; Railway tracks 11; rail

12 ; 침목 13 ; 자갈도상         12; Sleepers 13; Gravel

14 ; 지반         14; Ground

20 ; 동해(凍害)방지장치         20; Donghae prevention device

30 ; 모래매트 31 ; 모래         30; Sand mat 31; sand

32 ; 토목섬유          32; Geotextile

40 ; 지하수배수필름 41 ; 필름         40; Groundwater drainage film 41; film

42 ; 통공부         42; Through-hole

50 ; 연결구 51 ; 사각틀         50; Connector 51; Square frame

52 ; 모서리부 53 ; 수직부         52; Corner portion 53; Vertical section

54 ; 삼각돌출부 55 ; 삽입부         54; Triangular projection 55; Insert

60 ; 모래기둥 61 ; 접촉부  60; Sand pillar 61; Contact

본 발명은 지하수가 많거나, 지하수를 다량 함유한 연약지반 위에 불가피하게 철도를 부설하는 경우, 연약지반 내에 다량 함유된 수분에 의하여 동절기에 연약지반이 동결되어 지반내에 서리발과 같은 현상이 발생되어 지반을 구성하고 있는 토사가 위로 들어올려지게되어 중량의 열차가 철도궤도 위를 운행할 때 자갈도상을 지지하고 있던 연약지반이 침하됨과 동시에 철도궤도도 침하되어 철도궤도 위를 운행중인 차량이 탈선하는등의 사고를 미연에 방지하기 위하여 연약지반상에 동해(凍害)방지장치를 설치한 것이다.According to the present invention, when the railway is inevitably laid on a soft ground containing a large amount of groundwater or a large amount of groundwater, the soft ground is frozen in winter by moisture contained in a large amount of soft ground, and a phenomenon such as frost foot occurs in the ground. When the earth and sand that make up the ground are lifted up, when the heavy train runs on the rail track, the soft ground that was supporting the gravel road is subsided, and the rail track is also settled, causing the vehicle running on the rail track to derail. In order to prevent such accidents, the East Sea prevention device was installed on the soft ground.

일반적으로 실트질 또는 점성토질의 지반은 지지력이 약할 뿐만 아니라 다량의 수분도 동시에 함유하고 있어 동절기에 기온이 급강하하여 영하로 수일 또는 수개월간 지속되는 경우 일반적으로 지반표면에서부터 0.6 ~ 1m정도의 심도까지 지반이 동결되는 영향을 받는 것으로서, 특히 수분이 다량함유된 연약지반인 경우에는 함유된 수분에 의하여 서릿발과 같은 침상의 얼음결정체로 인하여 지반을 이루고 있는 토사가 위로 들어 올려지게되는 현상이 발생되는 것이다.        In general, silt or viscous soils are not only supportive but also contain a large amount of water at the same time. So, when the temperature drops sharply during winter and lasts for several days or months, it is generally about 0.6 ~ 1m from the ground surface. This freezing effect, particularly in the case of soft ground containing a large amount of water is a phenomenon that the soil is raised by the needle-like ice crystals such as frost feet lifted up by the moisture contained.

이렇게 토사가 위로 들어올려진 현상은 글자그대로 지반을 이루고 있는 토사가 상부로 들려져있게되어 그 위에 중량물이 재하되면 바로 침상의 얼음결정체가 부서지면서 들어올려진 토사가 일시에 붕괴되는 현상이 발생되어 지반의 지지력을 전혀 기대할 수 없게되는 것이다.        The phenomenon of earth and sand lifting up is literally lifted up the soil that forms the ground, and when heavy loads are loaded on it, the sedimentary ice crystals are broken and the raised soil is collapsed at once. You will not be able to expect at all.

이러한 현상을 방지하기 위하여 동결의 영향을 비교적 적게받되 지지력이 유지될 수 있는 일정한 입도로 구성된 모래를 이용하여 연약지반을 걷어내고 모래로 채우는 연약지반을 모래로 치환하게되는 것이다.        In order to prevent this phenomenon, the soft ground is removed by using the sand composed of a certain particle size, which is relatively less affected by freezing, but the bearing capacity can be maintained, and the soft ground filled with sand is replaced with sand.

그러나 상기와 같이 연약지반을 일정깊이까지 모래로 치환하는 것은 고가인 모래의 자재비로 인하여 공사비가 향상될 우려와 현장까지 모래를 운반하여야 하는 어려움이 상존하므로서 실질적으로 모래로 연약지반을 치환하는 것은 현실적으로 적용되지 않는 단점이 있는 것이다.        However, replacing the soft ground with sand to a certain depth as described above has the concern that the construction cost will be improved due to the expensive material cost of sand and the difficulty of transporting sand to the site is practical. There is a disadvantage that does not apply.

따라서 본 발명은 고강도의 토목섬유로 일정한 면적과 높이를 갖는 포대를 제작한 다음 그 내부에 동결영향을 거의 받지 않는 일정 입도로 이루어진 모래로 채우고, 상기 충전된 모래를 관통하여 폴리에틸렌과 같은 지하수배수필름을 한 개 이상 삽입설치하여 필름의 양측단부가 상기 모래매트의 외부로 돌출설치되도록 한 모래매트를 제작하되, 상기 모래매트를 자갈도상의 폭에 맞게 제작하고, 상기 제작된 모래매트를 연약지반상에 종방향으로 연이어서 설치하거나 또는 일정한 면적을 갖는 모래매트를 자갈도 상폭에 맞게 다수개 연약지반상에 설치하면서 종방향으로 모래매트가 깔리도록 포설하거나, 또는 연약지반상에 자갈도상폭에 따라 일정한 간격으로 일정한 깊이를 갖는 천공구멍을 다수개 종방향으로 설치하고, 상기 천공구멍내에 모래를 충전하면서 지하수배수필름을 수직으로 설치하되, 일단을 외부로 일정길이 노출시키고, 상기 모래기둥이 설치된 연약지반 상에 모래매트를 종방향으로 연이어서 설치하거나, 자갈도상폭에 맞게 복수개 이상의 모래매트를 설치하면서 종방향으로 연이어서 포설하되, 상기 모래기둥에 수직으로 설치하여 그 일단이 외부 로 노출된 지하수배출필름과 그 위에 설치되는 모래매트내에 관통삽입된 지하수배수필름과 밀착접촉되는 접촉부를 갖도록 설치하고, 상기 설치된 모래매트내를 삽입관통되어 외부로 돌출된 지하수배수필름은 자갈도상의 양측에 설치된 배수구에 노출되도록 한 동해(凍害)방지장치인 것이다.        Therefore, the present invention is to produce a bag having a certain area and height with high-strength geosynthetic fiber and then filled with sand made of a certain particle size that is hardly affected by freezing, and penetrates the filled sand to ground water drainage film such as polyethylene Insert and install at least one sand mat so that both ends of the film is installed to protrude out of the sand mat, the sand mat is made to fit the width of the gravel map, and the produced sand mat on the soft ground Or install sand mats with a certain area on the ground of a plurality of soft grounds in accordance with the gravel width, or spread sand mats in the longitudinal direction, or according to the gravel width on the soft ground. A plurality of drill holes having a constant depth at regular intervals are installed in the longitudinal direction, and sand is injected into the drill holes. While filling, install the groundwater drainage film vertically, expose one end to a certain length to the outside, and install the sand mat in the longitudinal direction on the soft ground where the sand column is installed, or install a plurality of sand mats according to the gravel width. It is installed so as to be installed in the longitudinal direction while being installed. It is installed vertically on the sand pillar so that one end thereof has a contact portion in close contact with the groundwater drainage film exposed to the outside and the groundwater drainage film inserted through the sand mat installed thereon. In addition, the groundwater drainage film protruded to the outside through the installed sand mat is the East Sea (凍害) prevention device to be exposed to the drains installed on both sides of the gravel road.

상기와 같이 지하수가 많거나 수분을 많이 함유한 연약지반상에 모래매트를 설치하고, 상기 모래매트내에 설치된 지하수배수필름에 표면장력 및 모세관현상에 의하여 모래매트내의 모래와 모래사이의 간극내에 유입된 간극수인 지하수 또는 연약지반상에 함유된 수분이 지하수배수필름의 표면을 타고 양측의 배수구에 노출되도록 설치된 지하수배수필름에 의하여 배수구로 배수되도록 하므로서 자갈도상의 하부의 연약지반상에 발생된 지하수 또는 수분이 외부로 배수되도록 하여 물의 함유량을 줄이도록 하여 연약지반이 동결에 의한 영향을 적게받도록 하면서, 일정한 입도로 구성된 모래는 동결의 영향을 거의 받지않으므로 자갈도상의 하부에 설치된 모래매트에 의하여 지지력이 유지되도록 하여 동결에 의한 지지력 약화로 발생된 열차탈선을 사전에 방지하도록 하면서 철도노반의 유지보수작업도 대폭적으로 줄일 수 있도록 한 것이다.A sand mat is installed on a soft ground containing a lot of ground water or water, and introduced into the gap between sand in the sand mat by surface tension and capillary phenomenon on the ground water drainage film installed in the sand mat. Groundwater or moisture generated on the soft ground under the gravel road by allowing the water contained in the groundwater or the soft ground, which is the pore water, to be drained by the groundwater drainage film installed on the surface of the groundwater drainage film to be exposed to drains on both sides. It is drained to the outside to reduce the water content so that the soft ground is less affected by freezing, while the sand composed of a certain particle size is hardly affected by freezing, so the bearing capacity is maintained by the sand mat installed at the lower part of the gravel road. Train deviation caused by weakening of bearing capacity by freezing. It prevented the railway roadbed maintenance work while being prevented in advance.

본 발명은 상기의 문제점을 개선하기 위하여 제안된 것으로서, 일정한 면적과 높이를 갖는 토목섬유로 매트를 제작하고, 그 내부에 동결의 영향을 적게 받는 일정 입도로 구성된 모래로 채우면서 자하수배수필름을 삽입관통시킨 모래매트를 제작하여 연약지반상에 설치하여 연약지반상에 함유된 수분 또는 지하에서 발생된 지하수를 지하수배수필름에 의하여 외부로 배수시키면서, 모래매트내에 충전된 모래에 의하여 동절기에도 동결의 영향을 거의 받지 않도록 하여 연약지반 상에 설치된 자갈도상에 의하여 지지되는 철도궤도를 효율적으로 지지하도록 하면서, 연약지반상에 설치할때에도 단위매트를 간단히 운반하여 연약지반상에 깔기만 하면되므로 운반과 설치가 간편하도록 한 연약지반의 동해(凍害)방지장치를 제공함에 있다.The present invention has been proposed in order to improve the above problems, to produce a mat from geosynthetic fibers having a certain area and height, while filling the self-drainage film while filling it with sand composed of a certain particle size less affected by freezing After inserting through the sand mat and installing it on the soft ground, the water contained in the soft ground or groundwater generated in the underground is drained to the outside by the groundwater drainage film, and freezes even in winter by the sand packed in the sand mat. Effortlessly supporting the railroad tracks supported by gravel roads installed on the soft ground with little effect, and simply installing the unit mat and laying on the soft ground when installing on the soft ground The purpose of the present invention is to provide a soft ground preventing device for simplicity.

이하, 본 발명의 첨부된 도면에 의하여 상세히 설명하면 다음과 같다.Hereinafter, described in detail by the accompanying drawings of the present invention.

도 1은 자갈도상을 지지하는 연약지반 상에 동해방지장치인 모래매트를 설치하고 모래매트 내에 삽입관통된 지하수배수필름을 양측에 설치된 배수구에 노출시키도록 한 것을 전체적으로 보여주는 도면이고, 도 2는 모래매트의 일실시예를 보여주는 것으로서, 자갈도상의 폭에 해당하도록 모래매트의 폭을 만들어서 길이방향인 종방향으로 연이어서 연약지반상에 포설하도록 하면서, 모래매트내에 삽입관통된 지하수배수필름을 모래매트의 양측으로 돌출설치되도록 한 도면이고, 도 3은 모래매트내에 삽입관통된 지하수배수필름의 형성을 보여주는 도면이고, 도 4는 자갈도상폭에 비하여 모래매트의 폭을 작게하여 다수개를 자갈도상 폭방향으로 연이어서 설치하도록 하면서, 이 또한 길이방향인 종방향으로 연약지반상에 포설되도록 한 것을 보여주는 도면이고, 도 5는 연약지반상에 설치되는 모래매트를 상호 연결하여 연약지반상에 설치된 모래매트가 지정된 위치에 포설되도록 하기 위한 연결구를 전체적으로 보여주는 도면이고, 도 5와 6은 도 5의 연결구를 이용하여 모래매트를 상호연결하여 연약지반상에 정하여진 위치에 포설되도록 한 도면이고, 도 8은 상기와 다른 동해방지장치를 보여주는 것으로서, 자갈도상의 폭에 해당하는 연약지반 상에 일정한 깊이의 구멍을 일정한 간격이 유지되도록 종방향으로 천공하고, 상기 천공된 구멍내에 모래를 충전한 모래기둥을 설치하면서 지하수배수필름을 수직으로 설치하되, 일단은 연악지반상의 외측으로 돌출시킨 다음, 그 위에 모래매트를 설치하면서 모래매트내에 삽입관통되어 양측에 지하수배수필름을 돌출시켜 배수구에 노출설치하고, 상기 모래기둥에 설치되고 일단이 외부로 노출된 지하수배수필름과 모래매트내에 삽입된 지하수배수필름과 접한 접촉부가 형성되도록 하여 원활히 지하수 또는 연약지반상에 함유된 수분이 외부로 배출되도록 한 동해(凍害)방지장치의 다른 실시예를 보여주는 도면이다.     FIG. 1 is a view showing the installation of a sand mat, which is a device for preventing a sea damage, on a soft ground supporting a gravel road and exposing the groundwater drainage film inserted through the sand mat to drains installed at both sides, and FIG. As an example of the mat, the ground mat drainage film inserted through the sand mat in the sand mat while making the width of the sand mat to extend in the longitudinal direction in the longitudinal direction to correspond to the width of the gravel map Figure 3 is a view to be installed protruding to both sides, Figure 3 is a view showing the formation of groundwater drainage film inserted through the sand mat, Figure 4 is a small width of the sand mat as compared to the gravel bed width of the plurality of gravel bed width Showing the installation on the soft ground in the longitudinal direction as well, 5 is a view showing the connector as a whole for interconnecting the sand mats installed on the soft ground so that the sand mats installed on the soft ground are installed at a designated position, Figures 5 and 6 show the connector of FIG. The sand mats are interconnected to be installed at a predetermined position on the soft ground, and FIG. 8 is a view showing a device for preventing the damage of the east sea, and a hole having a predetermined depth on the soft ground corresponding to the width of the gravel diagram. Perforate in the longitudinal direction to maintain a constant interval, and install the ground water drainage film vertically while installing the sand column filled with sand in the perforated hole, once protruded to the outside on the soft ground, and then sand Inserted into the sand mat while installing the mat protrudes the groundwater drainage film on both sides and is installed in the drain opening, Donghae (한), which is installed on the column and made contact with the groundwater drainage film exposed to the outside and the groundwater drainage film inserted in the sand mat, so that the water contained in the groundwater or the soft ground is discharged to the outside. Figure showing another embodiment of the prevention device.

본 발명은 지하수가 많거나, 지하수를 다량함유한 연약지반(14) 위에 불가피하게 철도를 부설하는 경우, 연약지반(14) 내에 다량 함유된 수분에 의하여 동절기에 연약지반이 동결되어 지반토사내에 서리발과 같은 현상이 발생되어 지반을 구성하고 있는 토사가 위로 들어올려지게되어 중량의 열차가 철도궤도(10) 위를 운행할 때 자갈도상(13)을 지지하고 있던 연약지반(14)이 침하됨과 동시에 철도궤도(10)도 침하되어 철도궤도(10) 위를 운행중인 차량이 탈선하는등의 사고를 미연에 방지하기 위하여,According to the present invention, when the railway is inevitably laid on the soft ground 14 having a lot of groundwater or a large amount of ground water, the soft ground is frozen in winter by moisture contained in a large amount of the soft ground 14 and then frost in the ground soil. As a phenomenon such as feet occurs, the earth and sand constituting the ground is lifted upward, and when the heavy train runs on the railroad track 10, the soft ground 14 supporting the gravel road 13 sinks and At the same time, the rail track 10 is also settled to prevent accidents such as derailment of the vehicle running on the rail track 10,

고강도토목섬유(32)로 일정한 면적과 높이를 갖도록 포대형상의 매트를 제작하고, 상기 매트내에 동결의 영향을 적게 받는 일정 입도로 구성된 모래(31)로 채우면서 지하수배수필름(40)을 삽입관통시킨 모래매트(30)를 제작한다.        The high-strength geosynthetic fiber 32 is fabricated into a bag-shaped mat to have a constant area and height, and the groundwater drainage film 40 is inserted through the sand 31 having a predetermined granularity which is less affected by freezing. The sand mat 30 is prepared.

상기 제작된 모래매트를 연약지반(14)상에 설치하여 연약지반(14)내에 함 유된 수분 또는 지하에서 발생된 지하수를 지하수배수필름(40)에 의하여 외부로 배수시키면서, 모래매트(30)내에 충전된 모래(31)에 의하여 동절기에도 동결의 영향을 거의 받지 않도록 하여 연약지반(14)에 설치된 자갈도상(13)에 의하여 지지되는 철도궤도(10)를 효율적으로 지지하도록 한다.        The manufactured sand mat is installed on the soft ground 14 to drain the water contained in the soft ground 14 or groundwater generated in the ground to the outside by the groundwater drainage film 40, The sand (31) is filled with little effect of freezing even in winter, so as to efficiently support the rail track 10 supported by the gravel phase 13 installed on the soft ground (14).

또한, 모래매트(30)를 연약지반(14)에 설치할때에도 단위매트를 간단히 운반하여 연약지반(14)에 깔기만 하면되도록 한 운반과 설치가 간편한 동해(凍害)방지장치(20)인 것이다.        In addition, even when the sand mat 30 is installed on the soft ground 14, the unit mat simply transports and installs on the soft ground 14 so that it is easy to transport and install it.

도 1, 2에서보는바와 같이 고강도의 토목섬유(32)로 일정한 면적과 높이를 갖는 포대를 제작한 다음 그 내부에 동결영향을 거의 받지 않는 일정 입도로 이루어진 모래(31)로 채우고, 상기 충전된 모래(31)를 관통하여 폴리에틸렌과 같은 지하수배수필름(40)을 한 개 이상 삽입설치하여 필름(40)의 양측단부가 상기 매트의 외부로 돌출설치되도록 한 모래매트(30)를 제작하되, 상기 모래매트(30)를 자갈도상(13)의 폭(W)에 맞게 제작하여 연약지반(14)내에 단일로 종방향으로 연이어서 설치하면서, 모래매트(30)내에 삽입관통되어 양측에 돌출설치된 지하수배수필름(40)의 양측단이 자갈도상(13)의 양측면에 형성된 배수구(15)에 노출설치되도록 한 동해(凍害)방지장치(20)인 것이다.        As shown in FIGS. 1 and 2, a bag having a predetermined area and height is made of high-strength geotextiles 32, and then filled with sand 31 having a predetermined granularity that is hardly affected by freezing. By inserting one or more groundwater drainage film 40, such as polyethylene, through the sand 31 to produce a sand mat 30 so that both ends of the film 40 protrude out of the mat. Groundwater 30 is made to fit the width W of the gravel drawing 13 and is continuously installed in the soft ground 14 in a longitudinal direction, while being inserted into the sand mat 30 and protruded on both sides. Both ends of the drainage film 40 will be the East Sea (배수) prevention device 20 to be installed exposed to the drain 15 formed on both sides of the gravel drawing (13).

또 다른 실시예로서 도 4와 같이 일정한 면적의 모래매트(30)를 다수개 연약지반(14)에 설치하여 자갈도상폭(W)과 일치하도록 하면서 종방향으로 모래매 트(30)를 포설하고, 상기 각각의 모래매트(30)내에 일괄적으로 삽입관통되어 양측에 위치한 모래매트(30)의 양측면에 일정길이로 돌출설치된 지하수배수필름(40)을 설치하되, 상기 돌출설치된 지하수배수필름(40)을 자갈도상(13)의 양측에 설치된 배수구(15)에 노출설치되도록 한 동해(凍害)방지장치(20)인 것이다.        As another embodiment, as shown in FIG. 4, the sand mat 30 having a predetermined area is installed on the plurality of soft grounds 14 so that the sand mat 30 is installed in the longitudinal direction while matching the gravel island width (W). Is inserted into each of the sand mat 30 is installed through the ground water drainage film 40 protruding to a certain length on both sides of the sand mat 30 located on both sides, but the projected ground water drainage film 40 ) Will be the East Sea (凍害) prevention device 20 to be installed to the drain port 15 installed on both sides of the gravel phase (13).

또 다른 실시예로서, 도 8과 같이 연약지반(14)에 자갈도상폭(W)에 따라 일정한 간격으로 일정한 깊이를 갖는 천공구멍을 다수개 종방향으로 설치하고, 상기 천공구멍내에 모래(31)를 충전하면서 지하수배수필름(40)을 수직으로 설치하되, 일단을 천공구멍 외부로 일정길이 노출시킨 모래기둥(60)을 설치하고, 상기 모래기둥(60)이 설치된 연약지반(14)에 모래매트(30)를 종방향으로 연이어서 설치하거나, 자갈도상폭(W)에 맞게 복수개 이상의 모래매트(30)를 설치하면서 종방향으로 연이어서 포설하되, 상기 모래기둥(60)에 수직으로 설치하여 그 일단이 외부로 노출된 지하수배출필름(40)과 그 위에 설치되는 모래매트(30)내에 삽입관통된 지하수배수필름(40)과 밀착접촉되는 접촉부(61)를 갖도록 설치하고, 상기 설치된 모래매트(30)내를 삽입관통하여 외부로 돌출되도록 한 지하수배수필름(40)은 자갈도상(13)의 양측에 설치된 배수구(15)에 노출되도록 한 동해(凍害)방지장치(20)인 것이다.        As another embodiment, as shown in FIG. 8, a plurality of perforation holes having a predetermined depth are provided in the soft ground 14 at regular intervals at regular intervals according to the gravel drawing width W, and the sand 31 is formed in the perforation holes. While installing the groundwater drainage film 40 vertically while filling the installation, the sand pillars 60 having one end exposed to a predetermined length outside the perforation hole are installed, and the sand mat on the soft ground 14 on which the sand pillars 60 are installed. (30) is installed in the longitudinal direction, or installed in the longitudinal direction while installing a plurality of sand mats 30 in accordance with the gravel island width (W), and installed vertically to the sand pillar (60) One end is installed to have a contact portion 61 in close contact with the ground water drainage film 40 inserted through the ground water discharge film 40 and the sand mat 30 installed thereon, and the sand mat ( 30) Protrude outward through the inside To a ground water drainage film 40 is in the East Coast (凍害) protection device 20 to expose the drain port 15 installed on both sides of a gravel ballast (13).

상기 도 1, 2와 도 4 및 도 8에 의한 것은 자갈도상폭(W)에 맞도록 제작된 모래매트(30)를 연약지반(14) 위에 길이방향으로 설치하거나, 자갈도상폭(W)에 맞 게 다수개의 모래매트(30)를 설치하고, 상기 설치된 모래매트(30)를 관통하여 지하수배수필름(40)을 설치하면서 상기 모래매트(30) 외측의 양측으로 노출되도록 하면서 자갈도상(13)의 양측면에 형성된 배수구(15)에 노출설치되도록 하거나,         1, 2 and 4 and 8 is installed on the soft ground 14 to the sand mat 30 is made to fit the gravel bed width (W) in the longitudinal direction, or on the gravel bed width (W) While installing a plurality of sand mat 30 to fit, while installing the groundwater drainage film 40 through the installed sand mat 30 so as to be exposed to both sides of the sand mat 30 outside the gravel phase (13) Or to be exposed to drains 15 formed on both sides of the

또는, 연약지반(14)내에 모래기둥(60)을 설치하고 모래기둥(60)내에 지하수배수필름(40)을 삽입설치하며서 일단은 외부로 노출되도록 한 다음, 모래매트(30)를 모래기둥(60)이 설치된 연약지반(14) 위에 설치하면서 모래매트(30)내에 삽입관통된 지하수배수필름(40)과 접하는 접촉부(61)를 형성하도록 하면서 모래매트(30)를 관통하여 양측에 노출되도록 설치된 지하수배수필름(40)의 양측단이 자갈도상(13)의 양측면에 형성된 배수구(15)에 노출설치되도록 하고, 상기 모래매트(30)가 설치된 위에 자갈을 일정높이로 포설하여 자갈도상(13)을 설치한 다음, 그 위에 침목(12)을 설치하고, 침목(12)에 레일(11)을 고정설치하여 철도궤도(10)를 부설하여 철로를 설치하는 것이다.        Alternatively, the sand pillar 60 is installed in the soft ground 14 and the ground water drainage film 40 is inserted into the sand pillar 60 so that the sand mat 30 is exposed to the outside, and then the sand mat 30 is sand pillar ( 60 is installed to be exposed on both sides through the sand mat 30 while forming a contact portion 61 in contact with the groundwater drainage film 40 inserted through the sand mat 30 while being installed on the soft ground 14 installed. Both ends of the groundwater drainage film 40 are exposed to drains 15 formed on both sides of the gravel drawing 13, and the gravel is laid at a predetermined height on the sand mat 30 on which the gravel drawing 13 is installed. After the installation, the sleeper 12 is installed thereon, the rail 11 is fixed to the sleeper 12 to install the railroad track 10 to install the railroad.

또한, 도 6과 도 7은 상기 도 1, 도 2, 도 4, 도 8에 의하여 연약지반(14) 위에 설치된 모래매트(30)를 설치하는 다른 실시예로서, 도 5와 같은 연결구(50)를 이용하여 모래매트(30)를 상호연결하여 연약지반(14) 위에 설치된 모래매트(30)가 이동되는 것을 방지하여 보다 강한 지지력을 발휘하도록 하기 위한 것이다.        6 and 7 show another embodiment in which the sand mat 30 is installed on the soft ground 14 according to FIGS. 1, 2, 4, and 8, and the connector 50 as shown in FIG. By using to interconnect the sand mat 30 to prevent the sand mat 30 installed on the soft ground 14 is moved to exert a stronger bearing force.

즉, 도 6은 도 2와 같은 방법으로 연약지반(14) 위에 모래매트(30)를 자갈궤도의 폭(W)에 맞도록 설치된 모래매트(30)를 길이방향으로 연이어서 설치하면서 인접하여 설치된 모래매트(30)의 측면끼리 도 5의 연결구(50)의 삽입부(55)가 삽입 되도록 하여 모래매트(30)를 연결구(50)에 의하여 고정되도록 한 것이며,        That is, Figure 6 is installed adjacent to the sand mat 30 installed in the longitudinal direction in the longitudinal direction on the soft ground 14 to fit the sand mat 30 to the width (W) of the gravel track in the same manner as in FIG. Side surfaces of the sand mat 30 are to be inserted into the insertion portion 55 of the connector 50 of FIG. 5 so that the sand mat 30 is fixed by the connector 50,

도 7은 도 4에 의하여 자갈도상의 폭(W)에 다수개의 작은 모래매트(30)를 설치하면서, 길이방향으로 설치한 모래매트(30)를 도 5의 연결구(50)의 사각틀(51)의 네모서리부(52)에 설치된 각각의 삽입부(55)가 네방향에 설치된 각각의 모래매트(30) 모서리에 삽입되어 모래매트(30)가 고정지지되도록 한 것이다.        7 is a rectangular frame 51 of the connector 50 of FIG. 5 with the sand mat 30 installed in the longitudinal direction while installing a plurality of small sand mats 30 at the width W of the gravel drawing by FIG. Each inserting portion 55 installed in the four corner portion 52 of the sand mat 30 is installed in the four corners of the sand mat 30 is to be fixed and supported.

도 5의 연결구(50)를 상세히 설명하면 금속 또는 강도가 있는 프라스틱재질로 사각틀(51)을 형성하고, 네모서리부(52)에 하향의 수직부(43)와 수직부(43) 하부에 삼각형의 삼각돌출부(54)가 형성된 삽입부(55)가 설치되도록 한 것이다.        When the connector 50 of FIG. 5 is described in detail, a rectangular frame 51 is formed of a metal or plastic material having a strength, and a triangle below the vertical portion 43 and the vertical portion 43 is formed on the four corner portions 52. The triangular protrusion 54 of the insertion portion 55 is to be installed.

상기 수직부(43) 하부에 형성된 삼각형상의 삼각돌출부(54)는 모래매트(30)내로 삽입될 때는 쉽게 삽입되도록 하면서 양측으로 돌출된 삼각부에 의하여 모래매트(30) 외부로 삽입부(55)가 이탈되는 것을 방지하여 모래매트(30)가 연결구(50)에 의하여 단단히 고정설치되도록 한 것이다.        The triangular triangular protrusion 54 formed below the vertical portion 43 is inserted into the sand mat 30 by the triangular portions protruding to both sides while being easily inserted when inserted into the sand mat 30. It is to be prevented from being separated so that the sand mat 30 is firmly installed by the connector 50.

상기 연결구(50)로 상호연결하는 것은 연약지반(14) 위에 설치된 모래매트(30)는 유동성이 강한 연약지반(14)에 의하여 쉽게 이동할 수 있으며, 특히 철도궤도(10)에서 중량의 하중이 반복적으로 작용하면 유동성이 있는 연약지반(14)에 의하여 이동 가능성이 있어 이를 방지하기 이하여 인접하여 설치된 모래매트(30)를 연결구(50)로 상호 연결하여 고정설치되도록 한 것이다.        Interconnecting with the connector 50, the sand mat 30 installed on the soft ground 14 can be easily moved by the soft ground (14) having a high fluidity, in particular, the weight of the load repeatedly in the rail track 10 If it acts as a soft ground (14) with the possibility of movement to prevent this is to be installed to be fixed by interconnecting the sand mat 30 is installed adjacent to the connector (50).

물론 도 8의 경우에도 도 2와 같이 자갈도상폭(W)에 맞게 모래매트(30)를 설치하거나 또는 도 4와 같이 자갈도상폭(W)에 다수개의 모래매트(30)가 설치되도록 한 후에 도 5의 연결구(50)로 도 6 또는 도 7과 같은 방법으로 상호 연결하여 고정지지되도록 한다.        Of course, in the case of FIG. 8 after the sand mat 30 is installed in accordance with the gravel island width (W) as shown in FIG. 2 or after the plurality of sand mats 30 are installed in the gravel island width (W) as shown in FIG. 4. The connector 50 of FIG. 5 is connected to each other in the same manner as in FIG. 6 or 7 to be fixed and supported.

철도를 부설하는 현장의 연약지반(14)의 지질특성에 따라 연결구(50)의 사용여부를 결정하여 사용할 수 있다.        According to the geological characteristics of the soft ground 14 on which the railway is laid, it is possible to determine whether to use the connector 50.

상기 본원 발명을 종합적으로 요약하여 설명하면, 철도를 설치하기 위하여 지반(14)을 조성할 때 수분이 많이 함유된 실트질 또는 점질토이거나 지하수가 발생되는 연약지반(14) 위에 자갈도상(13)을 설치하는 경우, 연약지반(14) 위에 모래매트(30)를 설치하고, 그 위에 자갈도상(13)을 설치하고, 그 위에 침목(12)을 설치하고 침목(12)에 레일(11)을 고정설치하여 철도를 부설한다.         When summarizing and explaining the present invention, the gravel phase 13 is formed on the soft ground 14 which is a silty silt or viscous soil or groundwater containing a lot of water when the ground 14 is formed to install the railway. In the case of installation, the sand mat 30 is installed on the soft ground 14, the gravel phase 13 is installed thereon, the sleeper 12 is installed thereon, and the rail 11 is fixed to the sleeper 12. Install the railroad.

상기의 방법으로 설치하되 연약지반(14) 위에 설치된 모래매트(30)가 연약지반의 유동성에 의하여 이동이 예상될 경우 모래매트(30)를 연결구(50)로 상호 연결하여 모래매트(30)가 연약지반(14) 위에서 이동하는 것을 방지한다.        If the sand mat 30 installed on the soft ground 14 is expected to move due to the fluidity of the soft ground, the sand mat 30 is connected to the connector 50 by the sand mat 30. Prevent movement on the soft ground (14).

상기와 같이 모래매트(30)를 설치하거나 모래매트(30)를 연결구(50)로 상호 연결하되, 모래매트(30)내를 삽입관통하는 지하수배수필름(40)은 모래매트(30)의 양측부로 노출되도록 하면서 자갈도상(13)의 양측면에 설치된 배수구(15)에 노출설치되도록 하여 모래매트(30)내의 모래(31)에 의하여 삼투압과 표면장력에 의하여 모래매트(30)내로 침투된 지하수 및 수분이 지하수배수필름(40)을 타고 배수 구(15)로 배수되도록 한다.        As described above, the sand mat 30 or the sand mat 30 is connected to each other by the connector 50, the ground water drainage film 40 through the sand mat 30 is inserted into both sides of the sand mat 30 Groundwater penetrated into the sand mat 30 by osmotic pressure and surface tension by sand 31 in the sand mat 30 by being exposed to drains 15 provided on both sides of the gravel drawing 13 while being exposed to the negative. The water is drained to the drain hole (15) by the ground water drainage film (40).

또 다른 방법으로 도 8과 같이 연약지반(14)에 모래기둥(60)을 설치하고 모래기둥(60)내에 지하수배수필름(40)을 삽입설치하며서 일단은 외부로 노출되도록 한 다음, 모래매트(30)를 모래기둥(60)이 설치된 연약지반 위에 설치하면서 모래매트(30)내에 삽입관통된 지하수배수필름(40)과 접하는 접촉부(61)를 형성하도록 하면서 모래매트(30)를 관통하여 양측에 노출되도록 설치된 지하수배수필름(40)의 양측단이 자갈도상(13)의 양측면에 형성된 배수구(15)에 노출설치되도록 하여 모래매트(30)내의 모래(31)에 의하여 삼투압과 표면장력으로 모래매트(30)내로 침투된 지하수 및 수분이 지하수배수필름(40)을 타고 배수구(15)로 배수되도록 한 것이다.        In another method, as shown in FIG. 8, the sand pillars 60 are installed on the soft ground 14, and the ground water drainage film 40 is inserted into the sand pillars 60 so as to be exposed to the outside. 30 is installed on the soft ground on which the sand pillars 60 are installed, while forming the contact portion 61 in contact with the groundwater drainage film 40 inserted through the sand mat 30, and penetrates the sand mat 30 on both sides. Both ends of the groundwater drainage film 40 installed to be exposed are exposed to the drain holes 15 formed on both sides of the gravel drawing 13 so that the sand mat with osmotic pressure and surface tension by the sand 31 in the sand mat 30. The ground water and water penetrated into the 30 are to be drained to the drain 15 by the ground water drainage film 40.

상기에서 열거한 모든 방법과 같이 연약지반(14) 위에 설치된 모래매트(30) 상에 자갈을 일정높이로 포설하여 자갈도상(13)을 설치한 다음, 그 위에 침목(12)을 설치하고, 침목에 레일(11)을 고정설치하여 철도궤도(10)를 부설하여 철로를 설치하는 것이다.        Like all the methods listed above, the gravel phase 13 is installed on the sand mat 30 installed on the soft ground 14 at a predetermined height, and then the sleepers 12 are installed thereon, and the sleepers The rail 11 is fixed to the rail track 10 to install the railroad to install.

상기 지하수배수필름(40)은 도 3과 같은 형태로 하되, 폴리에틸렌과 같은 재료를 이용하여 필름(41)형태로 제작하고, 수분이 쉽게 필름(41)을 타고 이동할 수 있도록 필름면에 일정한 크기의 통공부(42)를 일정한 간격을 두고 형성하도록 하거나, 또는 필름(41)의 양쪽 전체면에 걸쳐 좁쌀크기의 돌기(미도시)를 형성하도 록 하거나, 또는 필름(41)에 일정한 간격을 두고, 일정한 크기의 통공부(42)를 형성하면서 양측면에 돌기를 형성한 것이다.        The ground water drainage film 40 is formed in the form as shown in Figure 3, using a material such as polyethylene in the form of a film 41, and a certain size on the film surface so that moisture can easily move on the film 41 To form the through-holes 42 at regular intervals, or to form a narrow-sized projections (not shown) on both sides of the film 41, or at regular intervals in the film 41, While forming the through-holes 42 having a constant size, projections are formed on both sides.

상기의 필름(41) 면에 통공부(42)를 형성하거나, 또는 돌기를 설치한 것은 수분의 모세관현상 및 표면장력현상이 보다 더 활발히 작용되도록 한 것이다.        Forming the through-holes 42 or providing projections on the surface of the film 41 allows the capillary phenomenon and the surface tension phenomenon of the water to be more active.

상기와 같이 지하수배수필름에 돌기 또는 통공부를 형성하므로서 지하수배수필름의 양면을 타고 연약지반내의 수분이 배수되는 기능이 보다 활발히 작용되도록 하여 연약지반내에 함유된 지하수를 외부로 배출하여 연약지반(14)의 지지력을 증강시키면서 동절기에는 수분의 함유를 적게하여 동해의 피해를 방지하도록 하기 위한 것이다.        By forming projections or through-holes in the groundwater drainage film as described above, the function of draining the water in the soft ground is more active by riding on both sides of the groundwater drainage film to discharge the groundwater contained in the soft ground to the outside. In order to prevent the damage of the East Sea by reducing the content of water in the winter season while increasing the bearing capacity of).

또한, 모래매트(30) 내에 상기 지하수배수필름(40)을 삽입관통시켜 필름(41)을 타고 모래매트(30)내로 침투된 지하수에 의하여 모래(31)의 다짐이 강화되어 지지력이 증강되도록 한 것이다.        In addition, the ground water drainage film 40 is inserted through the sand mat 30 so that the compaction of the sand 31 is strengthened by the ground water penetrated into the sand mat 30 by the film 41. will be.

일반적으로 건조된 모래는 지지력이 없지만 수분이 함유된 모래는 지지력이 증강되는 현상을 이용하기 위하여 본 발명에서는 지하수배수필름(40)을 모래매트(30)내에 삽입관통시켜 항상 연약지반(14) 내에 수분이 모래매트(30)내의 모래(31)로 유입되도록 하여 지지력을 유지하도록 한 것이다         In general, the dried sand is not supportive force, but the sand containing moisture is inserted into the groundwater drainage film 40 in the sand mat 30 in order to use the phenomenon that the bearing capacity is enhanced in the soft ground (14) at all times Moisture is to be introduced into the sand 31 in the sand mat 30 to maintain the support force

도 8과 같은 경우 연약지반(14)에 일정한 간격을 두고 천공구멍을 천공하고, 그 내부에 모래(31)를 충전하면서 중심부에 도 3과 같은 지하수배수필름(40)을 삽입한 모래기둥(60)을 형성하고, 상기 모래기둥(60)내에 삽입된 지하수배수필름(40)의 일단을 연약지반(14) 상에 노출되도록 하고, 모래기둥(60)이 다수개 형성된 연약지반(14) 상에 모래매트(30)를 포설하면서 모래매트(30)내에 삽입관통된 지하수배수필름(40)과 상기 모래기둥(60)의 외부로 노출된 지하수배수필름(40)을 상호연결한 접촉부(61)를 형성하여, 모래기둥(60)내에 함유된 지하수가 지하수배수필름(40)을 타고 상부로 이동하여 접촉부(61)에 의하여 모래매트(30)내에 수평으로 설치된 지하수배수필름(40)으로 지하수가 자연스럽게 이동하여 모래매트(30)의 양측부에 설치된 배수구(15)를 통하여 외부로 배수되도록 한 것이다.        In the case shown in FIG. 8, the perforated hole is drilled at regular intervals in the soft ground 14, and the sand pillar 60 is inserted with the groundwater drainage film 40 as shown in FIG. 3 in the center while filling the sand 31 therein. ) To expose one end of the groundwater drainage film 40 inserted into the sand pillar 60 on the soft ground 14, and on the soft ground 14 on which a plurality of sand pillars 60 are formed. The contact portion 61 interconnecting the groundwater drainage film 40 inserted through the sand mat 30 and the groundwater drainage film 40 exposed to the outside of the sand column 60 while laying the sand mat 30 is provided. The ground water contained in the sand column 60 moves upward through the ground water drainage film 40, and the groundwater naturally flows into the ground drainage film 40 horizontally installed in the sand mat 30 by the contact portion 61. Moves to the outside through the drain hole 15 installed on both sides of the sand mat 30 To be.

상기에서 언급한바와 같이 다양한 방법으로 모래매트(30)를 연약지반(14) 상에 설치하도록 하면서 지하수배수필름(40)을 모래매트(30) 내를 관통하여 외부에 설치된 배수구(15)에 노출되도록 한 것은 결국 연약지반(14) 내에 함유된 지하수를 용이하게 외부로 배출시켜 연약지반이 지지력을 갖도록 하면서 연약지반이 동절기에도 동해(凍害)에 의한 피해를 모래매트에 의하여 방지되도록 한 것이다.        As mentioned above, while allowing the sand mat 30 to be installed on the soft ground 14 in various ways, the groundwater drainage film 40 is exposed to the drain 15 installed outside through the sand mat 30. In the end, the groundwater contained in the soft ground 14 is easily discharged to the outside so that the soft ground has a bearing capacity, so that the soft ground is prevented by the sand mat during the winter season.

또 다른 이유는 모래매트(30) 내에 모래(31)에 지속적으로 수분을 유입시켜 모래가 일정한 지지력을 갖도록 한 것이다.        Another reason is to continuously inject water into the sand 31 in the sand mat 30 so that the sand has a constant supporting force.

또한, 다른 이유는 동절기에 수분이 함유된 연약지반(14)이 동결되는 경우 토사가 서릿발에 의하여 상부로 들어 올려져 결국 지지력의 저하를 가져오게된다.        In addition, the other reason is that when the soft ground (14) containing moisture in the winter is frozen, the soil is lifted up by the frost feet, which leads to a decrease in the bearing capacity.

이러한 현상을 방지하기 위하여 동절기의 동결영향을 거의 받지 않는 모 래(31)를 이용하기 위하여 운반과 설치가 간편한 모래를 담을 수 있는 매트를 제작하여, 그 내부에 모래를 충전한 모래매트(30)를 이용한 것이다.        In order to prevent this phenomenon, in order to use the sand (31) which is hardly affected by the freezing of the winter season, to manufacture a mat that can hold sand easy to carry and install, sand mat filled with sand therein Will be used.

만약 모래매트(30)를 이용하지 않고 모래(31)를 연약지반(14) 상에 직접포설하고자 하는 경우에는 모래(31)를 현장까지 운반하여야 하는데 일반적으로 철도를 부설하는 현장은 차량의 운행이 어려운 산악지역 또는 하천등과 같은 조건이 열악한 현장인 경우가 많아 이러한 현장에 모래(31)를 운반하여야 하므로 운반이 어려운점과 이로인하여 운반비가 과다하게 소요되며, 또한 현장의 연약지반(14)에 모래(31)를 직접포설하더라도 연약한 지반의 특성상 각각의 모래알이 연약지반(14)내로 침투되어 고가인 모래(31)가 끝없이 소요되어 모래자재비가 과다하게 증액되는 문제점이 있으며, 연약지반(14)에 모래(31)를 직접 포설하는 경우 지지력이 없는 연약한 지반인 관계로 중장비가 포설할 수 없어 결국 인력에 의하여 모래를 포설하여야 하므로 비싼 인건비로 인한 총체적인 공사비가 엄청나게 증액되는 문제점을 개선하기 위하여 운반이 용이하면서, 설치작업도 간편하며, 제작도 용이한 모래매트(30)를 제작하여 동해방지장치(20)로 이용하도록 한 것이다.         If the sand 31 is to be directly laid on the soft ground 14 without using the sand mat 30, sand 31 should be transported to the site. Many sites have poor conditions such as difficult mountain areas or rivers, and therefore, sand (31) must be transported to these sites, which is difficult to transport, and therefore, excessive transportation costs are required, and also on the soft ground (14) of the site. Even if the sand 31 is directly laid, each grain of sand penetrates into the soft ground 14 due to the characteristics of the soft ground, and the expensive sand 31 is endlessly consumed. If sand (31) is directly installed on the ground, the heavy equipment cannot be installed because it is a soft ground without supporting force. Therefore, sand must be laid by manpower. In order to improve the problem that the overall construction cost is greatly increased, easy to transport, easy to install, and easy to manufacture sand mat 30 to be used as a device for preventing the sea damage (20).

본 발명은 모래(31)가 수분을 모세관현상 및 표면장력에 의하여 손쉽게 이동시키도록 하는 최적의 자재특성을 이용한 것이다.        The present invention utilizes the optimal material properties to allow sand 31 to easily move moisture by capillary action and surface tension.

연약지반(14) 상에 설치되는 모래매트(30)를 단층으로 포설하거나, 복수층이상으로 모래매트(30)를 적층하여 설치할 수도 있다.        The sand mat 30 provided on the soft ground 14 may be provided in a single layer, or may be provided by stacking the sand mat 30 in a plurality or more layers.

상기와 같이 모래매트(30)를 단층 또는 복수층이상으로 적층하는 것은 현장의 연약지반(14)의 상태에 따라 다양하게 모래매트를 포설할 수 있다.  As described above, stacking the sand mat 30 in a single layer or a plurality of layers or more may be provided with a variety of sand mats depending on the state of the soft ground 14 in the field.

본 발명은 일정한 면적과 높이를 갖는 토목섬유로 매트를 제작하고, 그 내부에 동결의 영향을 적게 받는 일정 입도로 구성된 모래로 채우면서 자하수배수필름을 삽입관통시킨 모래매트를 제작하여 연약지반상에 설치하여 연약지반상에 함유된 수분 또는 지하에서 발생된 지하수를 지하수배수필름에 의하여 외부로 배수시켜 지지력을 강화함과 동시에 모래매트내에 충전된 모래에 의하여 동절기에도 동결의 영향을 거의 받지 않도록 하여 연약지반 상에 설치된 자갈도상에 의하여 지지되는 철도궤도를 효율적으로 지지하도록 하면서, 연약지반상에 설치할때에도 단위매트를 간단히 운반하여 연약지반에 포설하기만 하면되는 운반과 설치가 간편한 연약지반의 동해방지장치인 것이다.The present invention is to produce a mat of geosynthetic fiber having a certain area and height, and to fill the sand mat composed of a certain particle size with less influence of freezing therein while manufacturing a sand mat inserted through the self-drainage film, soft ground It is installed on the ground so that the water contained in the soft ground or groundwater generated in the ground can be drained to the outside by the groundwater drainage film to strengthen the bearing capacity and at the same time, it is hardly affected by freezing even in winter by the sand packed in the sand mat. Easily transport and install the soft ground, which is easy to carry and install on the soft ground by simply carrying the unit mat even when installing on the soft ground, while efficiently supporting the rail track supported by the gravel road installed on the ground. It is

Claims (14)

철도를 부설하기 위하여 지반을 조성하고, 상기 조성된 지반 위에 자갈을 일정높이로 포설하여 자갈도상(13)을 설치하고, 상기 자갈도상 위에 침목(12)을 설치하고, 상기 침목에 레일(11)을 고정하여 철도궤도(10)를 설치하여 철로를 부설하는 것에 있어서,In order to lay a railroad, the ground is formed, and the gravel is laid at a predetermined height on the ground, the gravel bed 13 is installed, the sleeper 12 is installed on the gravel bed, and the rail 11 is placed on the sleeper. In installing the railroad track 10 by installing the railroad tracks, 상기 지반이 연약지반인 경우 연약지반 위에 모래매트(30)를 포설하고, 상기 포설된 모래매트내로 삽입관통되어 양측에 노출설치된 지하수배수필름(40)과, 상기 노출된 지하수배수필름의 노출된 양측단이 자갈도상(13)의 양측면에 형성된 배수구(15)에 노출설치되도록 한 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.      When the ground is a soft ground, the sand mat 30 is installed on the soft ground, and inserted into the installed sand mat, the groundwater drainage film 40 installed on both sides and the exposed groundwater drainage film exposed both sides. A device for preventing the damage of the east sea installed on the soft ground supporting the gravel road on which the railroad tracks are laid, characterized in that the stage is exposed to the drain holes 15 formed on both sides of the gravel roadway 13. 제 1항에 있어서,The method of claim 1, 상기 모래매트(30)는 고강도토목섬유(32)로 일정한 면적과 높이를 갖도록 포대형상의 매트로 제작하고, 상기 매트내에 동결의 영향을 적게 받는 일정 입도로 구성된 모래(31)로 채우면서 지하수배수필름(40)을 삽입관통시킨 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.         The sand mat 30 is made of a high-strength geosynthetic fiber 32 and made of a bag-shaped mat so as to have a constant area and height, and filled with sand 31 composed of a predetermined granularity which is less affected by freezing in the mat. An East Sea prevention device installed on the soft ground supporting the gravel road on which the railroad tracks are placed, characterized by inserting the film (40). 제 1항에 있어서The method of claim 1 상기 모래매트(30)를 자갈도상 폭(W)에 맞게 단일로 설치하면서 철도궤도(10)의 길이방향인 종방향으로 모래매트(30)를 연이어서 설치하는 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.While installing the sand mat 30 in accordance with the gravel road width (W) as a single rail track is characterized in that the installation of the sand mat 30 in the longitudinal direction in the longitudinal direction of the rail track 10 East Sea prevention device installed on soft ground supporting gravel road. 제 1항에 있어서,The method of claim 1, 상기 모래매트(30)를 자갈도상 폭(W)에 맞게 복수개 이상의 모래매트(30)를 설치하면서, 철도궤도(10)의 길이방향인 종방향으로 모래매트(30)를 연이어서 설치하는 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.  Characterized in that the sand mat 30 is installed in the longitudinal direction of the rail track 10 in the longitudinal direction while installing a plurality of sand mat 30 in accordance with the width (W) of gravel road The East Sea prevention device installed on the soft ground supporting the gravel road on which the railway tracks are installed. 제 1항 또는 제2항에 있어서,The method according to claim 1 or 2, 상기 지하수배수필름(40)은 폴리에틸렌과 같은 재료를 이용하여 필름(41)형태로 제작하고, 수분이 쉽게 필름(41)을 타고 이동할 수 있도록 필름면에 일정한 크기의 통공부(42)를 일정한 간격을 두고 형성하도록 하거나, 또는 필름(41)의 양쪽 전체면에 걸쳐 좁쌀크기의 돌기(미도시)를 형성하도록 하거나, 또는 필름(41)에 일정한 간격을 두고, 일정한 크기의 통공부(42)를 형성하면서 양측면에 돌기를 형성한 것 중에 어느 한 것인 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.  The ground water drainage film 40 is manufactured in the form of a film 41 using a material such as polyethylene, and a predetermined interval of the through-hole 42 having a predetermined size on the film surface so that moisture can easily move on the film 41. Or to form a narrow-sized protrusion (not shown) on both sides of the film 41, or at regular intervals on the film 41, to form a through hole 42 having a constant size. The East Sea prevention device installed on the soft ground which supports the gravel road on which the railway tracks are laid, characterized in that any one of the projections are formed on both sides while forming. 제 3항 또는 제4항에 있어서,The method according to claim 3 or 4, 상기 포설된 모래매트(30)의 양측면 또는 네방향의 측면을 연결구(50)를 이용하여 상호 연결하여 연약지반(14)상에서 이동을 방지하도록 한 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.  Both sides or four sides of the laid sand mat 30 is connected to each other using the connector 50 to prevent the movement on the soft ground 14 to support the gravel road in which the railway tracks are laid. Donghae prevention device installed on the soft ground. 제 6항에 있어서,The method of claim 6, 상기 연결구(50)는 금속 또는 강도가 있는 프라스틱재질로 사각틀(51)을 형성하고, 네모서리부(52)에 하향의 수직부(43)와 수직부(43) 하부에 삼각형의 삼각돌출부(54)가 형성된 삽입부(55)가 설치된 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.  The connector 50 forms a rectangular frame 51 made of metal or a plastic material having strength, and has a triangular triangular protrusion portion 54 below the vertical portion 43 and the vertical portion 43 downwardly on the corner portion 52. ) Is a freeze preventing device installed on the soft ground supporting the gravel road on which the railroad tracks are placed, characterized in that the insertion portion 55 is installed. 철도를 부설하기 위하여 지반(14)을 조성하고, 상기 조성된 지반 위에 자갈을 일정높이로 포설하여 자갈도상(13)을 설치하고, 상기 자갈도상 위에 침목(12)을 설치하고, 상기 침목에 레일(11)을 고정하여 철도궤도(10)를 설치하여 철로를 부설하는 것에 있어서,In order to lay a railroad, the ground 14 is formed, the gravel is laid at a predetermined height on the ground, and the gravel phase 13 is installed, and the sleeper 12 is installed on the gravel phase, and the rails on the sleeper In fixing (11) and installing railroad tracks 10 and laying railroad tracks, 상기 지반이 연약지반인 경우 연약지반(14)에 일정한 간격을 두고 천공구멍을 천공하고, 상기 천공구멍내에 모래(31)를 충전하면서 중심부에 지하수배수필름(40)을 삽입한 모래기둥(60)을 형성하고, 상기 모래기둥(60)내에 삽입된 지하수배수필름(40)의 일단을 연약지반(14) 상에 노출되도록 하고, 상기 모래기둥(60)이 다수개 형성된 연약지반(14) 상에 모래매트(30)를 포설하면서 모래매트(30)내에 삽입관통된 지하수배수필름(40)과 상기 모래기둥(60)의 외부로 노출된 지하수배수필름(40)을 상호연결한 접촉부(61)를 형성하고, 상기 모래매트(30)를 삽입관통하여 양측으로 노출된 지하수배수필름(40)이 자갈도상(13)의 양측에 형성된 배수구(15)에 노출되도록 한 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약 지반상에 설치된 동해방지장치.  When the ground is a soft ground, the drilled holes at regular intervals in the soft ground 14, the sand pillar 60 is inserted into the ground drainage film 40 in the center while filling the sand 31 in the drilling holes (60) To form, to expose one end of the groundwater drainage film 40 inserted into the sand pillar 60 on the soft ground 14, on the soft ground 14 is formed a plurality of sand pillars 60 The contact portion 61 interconnecting the groundwater drainage film 40 inserted through the sand mat 30 and the groundwater drainage film 40 exposed to the outside of the sand column 60 while laying the sand mat 30 is provided. Formed and inserted through the sand mat 30, the underground water drainage film 40 exposed to both sides is laid railroad tracks characterized in that exposed to the drain hole 15 formed on both sides of the gravel phase (13) East Sea prevention device installed on soft ground supporting gravel road. 제 8항에 있어서,The method of claim 8, 상기 모래매트는 고강도토목섬유(32)로 일정한 면적과 높이를 갖도록 포대형상의 매트로 제작하고, 상기 매트내에 동결의 영향을 적게 받는 일정 입도로 구성된 모래(31)로 채우면서 지하수배수필름(40)을 삽입관통시킨 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치  The sand mat is made of a bag-shaped mat to have a constant area and height with high-strength geotextiles (32), and filled with sand (31) composed of a predetermined particle size that is less affected by freezing in the mat, and the groundwater drainage film (40). Donghae prevention device installed on soft ground supporting gravel road with railroad tracks 제 8항에 있어서The method of claim 8 상기 모래매트(30)를 자갈도상 폭(W)에 맞게 단일로 설치하면서 철도궤도(10)의 길이방향인 종방향으로 모래매트(30)를 연이어서 설치하는 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.  While installing the sand mat 30 in accordance with the gravel road width (W) as a single rail track is characterized in that the installation of the sand mat 30 in the longitudinal direction in the longitudinal direction of the rail track 10 East Sea prevention device installed on soft ground supporting gravel road. 제 8항에 있어서,The method of claim 8, 상기 모래매트(30)를 자갈도상 폭(W)에 맞게 복수개 이상의 모래매트(30)를 설치하면서, 철도궤도(10)의 길이방향인 종방향으로 모래매트(30)를 연이어서 설치하는 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.  Characterized in that the sand mat 30 is installed in the longitudinal direction of the rail track 10 in the longitudinal direction while installing a plurality of sand mat 30 in accordance with the width (W) of gravel road The East Sea prevention device installed on the soft ground supporting the gravel road on which the railway tracks are installed. 제 8항 또는 제9항에 있어서,The method according to claim 8 or 9, 상기 지하수배수필름(40)은 폴리에틸렌과 같은 재료를 이용하여 필름(41)형태로 제작하고, 수분이 쉽게 필름(41)을 타고 이동할 수 있도록 필름면에 일정한 크기의 통공부(42)를 일정한 간격을 두고 형성하도록 하거나, 또는 필름(41)의 양쪽 전체면에 걸쳐 좁쌀크기의 돌기(미도시)를 형성하도록 하거나, 또는 필름(41)에 일정한 간격을 두고, 일정한 크기의 통공부(42)를 형성하면서 양측면에 돌기를 형성한 것 중에 어느 한 것인 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.  The ground water drainage film 40 is manufactured in the form of a film 41 using a material such as polyethylene, and a predetermined interval of the through-hole 42 having a predetermined size on the film surface so that moisture can easily move on the film 41. Or to form a narrow-sized protrusion (not shown) on both sides of the film 41, or at regular intervals on the film 41, to form a through hole 42 having a constant size. The East Sea prevention device installed on the soft ground which supports the gravel road on which the railway tracks are laid, characterized in that any one of the projections are formed on both sides while forming. 제 10항 또는 제 11항에 있어서,The method according to claim 10 or 11, wherein 상기 포설된 모래매트(30)의 양측면 또는 네방향의 측면을 연결구(50)를 이용하여 상호 연결하여 연약지반(14)상에서 이동을 방지하도록 한 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.  Both sides or four sides of the laid sand mat 30 is connected to each other using the connector 50 to prevent the movement on the soft ground 14 to support the gravel road in which the railway tracks are laid. Donghae prevention device installed on the soft ground. 제 13항에 있어서,The method of claim 13, 상기 연결구(50)는 금속 또는 강도가 있는 프라스틱재질로 사각틀(51)을 형성하고, 네모서리부(52)에 하향의 수직부(43)와 수직부(43) 하부에 삼각형의 삼각돌출부(54)가 형성된 삽입부(55)가 설치된 것에 특징이 있는 철도궤도가 부설된 자갈도상을 지지하는 연약지반상에 설치된 동해방지장치.        The connector 50 forms a rectangular frame 51 made of metal or a plastic material having strength, and has a triangular triangular protrusion portion 54 below the vertical portion 43 and the vertical portion 43 downwardly on the corner portion 52. ) Is a freeze preventing device installed on the soft ground supporting the gravel road on which the railroad tracks are placed, characterized in that the insertion portion 55 is installed.
KR1020070008772A 2007-01-29 2007-01-29 Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad KR100793178B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070008772A KR100793178B1 (en) 2007-01-29 2007-01-29 Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070008772A KR100793178B1 (en) 2007-01-29 2007-01-29 Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad

Publications (1)

Publication Number Publication Date
KR100793178B1 true KR100793178B1 (en) 2008-01-10

Family

ID=39217328

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070008772A KR100793178B1 (en) 2007-01-29 2007-01-29 Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad

Country Status (1)

Country Link
KR (1) KR100793178B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101568370B1 (en) * 2015-04-30 2015-11-12 (주)우진테크놀로지 Fiber mats for soft soil drainage method
CN111304969A (en) * 2020-03-31 2020-06-19 中铁二院工程集团有限责任公司 Anti-bulging structure of ballastless track tramcar on strongly expansive soil or expansive rock section

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH116140A (en) 1997-06-13 1999-01-12 Penta Ocean Constr Co Ltd Draining method for soft soil and extensible draining material
JPH11241342A (en) 1998-02-25 1999-09-07 Oyo Corp Soil bed strengthening construction method, and panel for strengthening soil bed
JP2001073301A (en) 1999-09-03 2001-03-21 Sumitomo Osaka Cement Co Ltd Ground water drainage method
KR200354460Y1 (en) 2004-03-16 2004-06-29 케이테크개발 주식회사 Interior water proofing member of tunnel having effective draining function
KR20050060991A (en) * 2003-12-17 2005-06-22 한국철도기술연구원 Structure of a road bed for slab track in a high speed railway

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH116140A (en) 1997-06-13 1999-01-12 Penta Ocean Constr Co Ltd Draining method for soft soil and extensible draining material
JPH11241342A (en) 1998-02-25 1999-09-07 Oyo Corp Soil bed strengthening construction method, and panel for strengthening soil bed
JP2001073301A (en) 1999-09-03 2001-03-21 Sumitomo Osaka Cement Co Ltd Ground water drainage method
KR20050060991A (en) * 2003-12-17 2005-06-22 한국철도기술연구원 Structure of a road bed for slab track in a high speed railway
KR200354460Y1 (en) 2004-03-16 2004-06-29 케이테크개발 주식회사 Interior water proofing member of tunnel having effective draining function

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101568370B1 (en) * 2015-04-30 2015-11-12 (주)우진테크놀로지 Fiber mats for soft soil drainage method
CN111304969A (en) * 2020-03-31 2020-06-19 中铁二院工程集团有限责任公司 Anti-bulging structure of ballastless track tramcar on strongly expansive soil or expansive rock section

Similar Documents

Publication Publication Date Title
KR20200054409A (en) Road way construction method for mountain railway
CN109505201A (en) A kind of seasonal frozen soil region non-fragment orbit high-speed railway immersion roadbed anti-freeze expansion structure
KR20180098794A (en) Method for reinforcing rail roadbed of earthwork transitional zone considering transfer range of train load
KR101298008B1 (en) road pavement methods of using stone basket
CN105926391B (en) A kind of curb method for widening of existing railway roadbed
CN210857182U (en) Roadbed drainage structure
KR100793178B1 (en) Apparatus for preventing cold weatherdamage installed at the softground for supporting a ballast of railroad
Kondratiev Geocryological problems of railroads on permafrost
RU2618108C2 (en) Drainage system on permafrost soils
RU2668529C1 (en) High speed main road
RU83511U1 (en) EARTH CANVAS OF THE ROAD IN THE FROZEN SOIL ZONE
CN210596858U (en) Plateau permafrost region roadbed structure
US10364564B2 (en) Super drainage system and method for flood control
CN111809470A (en) Structure and method for preventing cracks of road base layer and road subbase layer
CN208151798U (en) A kind of seasonal frozen soil region high-speed rail roadbed water cut infiltration ditch system
JP6782404B2 (en) Groundwater level lowering method, groundwater drainage channel construction method and groundwater drainage channel structure
JP2013083144A (en) Liquefaction preventing structure
KR101083032B1 (en) Pavement
Raymond Installation factors that affect performance of railroad geotextiles
RU2795020C1 (en) Method for constructing subgrade of additional track on weak base in case of thawing
RU2761272C1 (en) Drainage system for stabilising the roadway on thawed soft soils
CN214992706U (en) Railway soft soil roadbed
CN113699835B (en) Construction method of integral type turnout drainage structure of railway track bed of cargo yard in port area
CN110055827B (en) Construction method of cutting large-gradient toothed rail railway structure
CN221297461U (en) Road subgrade construction structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130103

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20131209

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20150105

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20160104

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20170103

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180103

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20190103

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20200103

Year of fee payment: 13