KR100724502B1 - A method for construction of waste landfills - Google Patents

A method for construction of waste landfills Download PDF

Info

Publication number
KR100724502B1
KR100724502B1 KR1020060093146A KR20060093146A KR100724502B1 KR 100724502 B1 KR100724502 B1 KR 100724502B1 KR 1020060093146 A KR1020060093146 A KR 1020060093146A KR 20060093146 A KR20060093146 A KR 20060093146A KR 100724502 B1 KR100724502 B1 KR 100724502B1
Authority
KR
South Korea
Prior art keywords
landfill
air dome
waste
support structure
new
Prior art date
Application number
KR1020060093146A
Other languages
Korean (ko)
Inventor
강영권
Original Assignee
강영권
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 강영권 filed Critical 강영권
Priority to KR1020060093146A priority Critical patent/KR100724502B1/en
Application granted granted Critical
Publication of KR100724502B1 publication Critical patent/KR100724502B1/en
Priority to US12/442,707 priority patent/US20100040416A1/en
Priority to JP2009529097A priority patent/JP2010504198A/en
Priority to PCT/KR2007/003115 priority patent/WO2008038890A1/en
Priority to CNA2007800354288A priority patent/CN101517167A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/002Ground foundation measures for protecting the soil or subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/002Ground foundation measures for protecting the soil or subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/006Sealing of existing landfills, e.g. using mining techniques
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B1/00Dumping solid waste
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B09DISPOSAL OF SOLID WASTE; RECLAMATION OF CONTAMINATED SOIL
    • B09BDISPOSAL OF SOLID WASTE NOT OTHERWISE PROVIDED FOR
    • B09B1/00Dumping solid waste
    • B09B1/004Covering of dumping sites
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/008Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against entry of noxious gases, e.g. Radon

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Toxicology (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

A method for forming a reclaimed land is provided to maximize an area of the reclaimed land by forming a new reclaimed land adjacent to a cleaning room after burying wastes in the reclaimed land. A method for forming a reclaimed land includes the steps of: forming a reclaimed land(S10); covering the reclaimed land by an air dome(S20); stacking a part of wastes on the reclaimed land(S30); manufacturing an air dome support structure on an upper portion of the wastes(S40); covering the reclaimed land with earth after the wastes are buried in the reclaimed land(S50); forming a new reclaimed land adjacent to a cleaning room(S60); moving the air dome, supporting one side of the air dome by the air dome support structure, and supporting the other side of the air dome to a progressing direction of the new reclaimed land so that the new reclaimed land is covered(S70); and repeating the above steps to continuously bury the wastes and maximize the reclaimed land.

Description

매립지 조성방법{A Method for construction of Waste landfills}A method for construction of waste landfills

도 1, 2는 종래에 따른 매립지 조성을 나타낸 도면.1 and 2 is a view showing a landfill composition according to the prior art.

도 3은 본 발명에 따른 매립지 조성방법을 나타낸 도면.3 is a view showing a landfill composition method according to the invention.

도 4는 본 발명에 따른 매립지 조성방법의 매립장의 단면도.Figure 4 is a cross-sectional view of the landfill of the landfill composition method according to the present invention.

도 5은 본 발명에 따른 매립지 조성방법의 순서도.5 is a flow chart of a landfill composition method according to the invention.

*도면의 주요부분에 대한 부호의 설명** Explanation of symbols for main parts of drawings *

100 : 매립지 110 : 매립장100: landfill 110: landfill

112 : 바닥부 114 : 경사부112: bottom 114: inclined portion

120 : 차수층 130 : 소제방120: order layer 130: small embankment

140 : 에어돔 142 : 외기 도입팬140: air dome 142: air inlet fan

144 : 배기용 팬144 exhaust fan

본 발명은 매립지 조성방법에 관한 것으로서, 보다 상세하게는 폐기물을 매립하는 매립장을 형성하여 폐기물을 매립한 후에, 매립장에 직접적으로 연이어 있는 소제방에 인접하여 신생매립장을 조성함으로써, 매립장의 면적을 최대화하여 매립지의 매립량을 늘리는 매립지 조성방법에 관한 것이다.The present invention relates to a method for forming a landfill, and more particularly, after forming a landfill site for embedding waste, and after filling the landfill, forming a new landfill site adjacent to a small embankment directly connected to the landfill site, thereby maximizing the area of the landfill site. The present invention relates to a landfill formation method for increasing landfill amount of landfill.

현대에는 인구의 증가와 생활 수준의 향상으로 인하여 폐기물 배출량이 급격히 증가하였으며, 이러한 폐기물 처리에 따른 많은 방법들이 연구되고 있다. 그 중, 현재 가장 많이 이용되고 있는 방법은 폐기물을 소각하는 방법과 폐기물을 매립하는 방법이 있으나, 폐기물 소각 방법은 환경 오염 물질을 배출하며, 지역 사회의 소각장의 거부가 심한 문제점이 있어 폐기물 매립이 선호되고 있는 경향이다. In modern times, due to the increase of the population and the improvement of living standards, the amount of waste is rapidly increased, and many methods for treating such waste have been studied. Among them, the most widely used methods are incineration of waste and landfill, but waste incineration emits environmental pollutants and there is a serious problem of rejection of incinerators in local communities. Tend to be favored.

일반적으로 '매립'을 이용한 폐기물 등 폐기물의 처리방법은, 폐기물을 일정높이로 적층한 다음, 적층된 폐기물을 흙 또는 이와 유사한 차폐물(통상, '복토층'이라 한다.)로 덮는 과정을 반복하여, 수년 내지 수십 년 동안 폐기물을 자연 분해시키는 폐기물 처리방법이다.In general, a method of treating waste such as waste by using a landfill includes stacking the waste to a certain height, and then repeating the process of covering the stacked waste with soil or a similar shield (commonly referred to as a 'soil layer'). It is a waste treatment method that naturally decomposes waste for many years to several decades.

도 1 또는 도 2는 일반적인 매립지 조성을 나타낸 도면이다.1 or 2 is a view showing a general landfill composition.

도 1과 도 2에서 도시한 바와 같이 매립지(1) 조성은 우선, 약 5000평을 상광하협 형상으로 2개의 매립장(10)을 형성한다.As shown in Fig. 1 and Fig. 2, the landfill 1 composition is first formed of two landfill sites 10 having a shape of about 5000 pyeong in a light-receiving narrow shape.

상기 매립장(10)은 바닥부(12)와 경사부(14)로 이루어지고, 상기 경사부는 다단으로 형성되며 상기 바닥부와 경사부는 차수층(25)을 형성하여 침출수가 땅속으로 흘러 들어가지 못하게 한다.The landfill site 10 is composed of a bottom portion 12 and the inclined portion 14, the inclined portion is formed in multiple stages, the bottom portion and the inclined portion forms the order layer 25 to prevent the leachate flow into the ground .

상기 매립장(10)사이에는 일정간격을 갖는 제방(20)이 형성되고, 상기 매립 장(10)은 상부에 외부에서 유입되는 우수를 차단하기 위해 에어돔(30)이 설치된다.A dike 20 having a predetermined interval is formed between the buried jang 10, the buried jang 10 has an air dome 30 is installed on the top to block rainwater flowing from the outside.

상기 에어돔(30)은 각 매립장(10)에 하나씩 설치되며, 상기 제방(20)은 상기 에어돔(30)의 설치 시 상기 에어돔(30)을 지지해주는 역할을 하게 된다.The air dome 30 is installed in each of the landfill 10, the embankment 20 serves to support the air dome 30 when the air dome 30 is installed.

상기 에어돔(30)에는 길이방향의 전방에 대형의 외기 도입팬(42)이 설치되어 매립 시 발생되는 악취 및 먼지 등을 상기 에어돔(30)의 후방으로 대류시켜 후방에 설치된 다른 배기용 팬(144)을 이용하여 외측으로 리턴시키게 된다.The air dome 30 is provided with a large outside air inlet fan 42 in the front of the longitudinal direction is condensed odor and dust generated during the landfill to the rear of the air dome 30, the other exhaust fan installed in the rear 144 is returned to the outside.

그러나, 종래의 매립지 조성에 있어서는 매립장과 매립장 사이에는 에어돔의 지지를 위해 제방이 존재하게 되고 제방에 의해 매립지의 매립량이 축소되는 문제가 있으며, 에어돔 2개를 제작하여야 함으로써, 에어돔 설치비용과 이전비용이 증대되는 문제점이 있었다.However, in the conventional landfill composition, a dike exists between the landfill site and the landfill to support the air dome, and the amount of landfill of the landfill is reduced by the embankment. There was a problem that the cost of the transfer increased.

이에 본 발명은 상기와 같은 문제점들을 해소하기 위해 안출된 것으로써, 본 발명은 폐기물을 매립하는 매립장을 형성하여 폐기물을 매립한 후에, 매립장에 직접적으로 연이어 있는 소제방에 인접하여 신생매립장을 조성하고 신생매립장의 에어돔(air dome) 설치는 매립장 내부에 구비되는 에어돔 지지구조물에 의해 설치됨으로써, 매립장의 면적을 최대화하여 매립지의 매립량을 늘리는 매립지 조성방법을 제공하는 것을 목적으로 한다.Accordingly, the present invention has been made in order to solve the above problems, the present invention forms a landfill to bury the waste, and after filling the waste, to form a new landfill adjacent to the small banks directly connected to the landfill The installation of an air dome of the new landfill site is provided by an air dome support structure provided in the landfill site, and aims to provide a landfill formation method of maximizing the landfill area by maximizing the landfill site.

상기와 같은 목적을 달성하기 위한 본 발명은, 상광하협 형상의 매립장을 형성하는 매립장 조성단계와, 상기 매립장을 조성하고, 상기 매립장의 상부를 에어돔으로 커버하는 에어돔 설치단계와, 상기 에어돔을 설치하고, 상기 매립장에 폐기물을 일부 적층하는 폐기물 일부 적층단계와, 상기 매립장에 일부 적층된 폐기물 상부에 상기 에어돔 지지하는 지지구조물을 제작하는 에어돔 지지구조물 제작단계와, 상기 에어돔 지지구조물을 제작한 후에 상기 매립장에 폐기물을 매립한 후 상기 매립장을 흙으로 덮어주는 매립단계와, 상기 매립장을 흙으로 매립하고, 상기 매립장에 소제방을 형성하도록 직접적으로 연이어 신생매립장을 조성하는 신생매립장 조성단계 및 상기 에어돔을 이동시켜 일측은 상기 에어돔 지지구조물에 지지되고, 타측은 상기 신생매립장 진행방향측에 지지되어 상기 신생매립장 상부를 커버하는 에어돔 이동설치단계를 포함하여 이루어지되, 상기 폐기물 일부 매립단계, 에어돔 지지구조물 제작단계, 매립단계, 신생매립장 조성단계와, 상기 에어돔 이동설치단계를 반복 수행하여 폐기물을 지속적으로 매립함과 동시에 매립장을 최대화하여 매립지의 이용률을 향상시키는 것을 특징으로 한다.The present invention for achieving the above object, the buried ground forming step of forming a buried jangsangbyeong shape, and the air dome installation step of forming the buried land, and covering the upper portion of the buried land with an air dome, and the air dome A part of the waste stacking step of partially stacking the waste in the landfill, and manufacturing a support structure for supporting the air dome on top of the waste partially stacked in the landfill; and an air dome supporting structure; After constructing the landfill step of embedding waste in the landfill and then cover the landfill with soil, landfill the landfill with soil, and form a new landfill site directly following the new landfill to form a small levee in the landfill Step and moving the air dome one side is supported by the air dome support structure, the other side is the Supported by the landfill progress direction side is made, including the air dome moving step of installing the cover to cover the new landfill, a part of the landfill step, airdome supporting structure manufacturing step, landfill step, new landfill construction step, and the air dome By repeatedly carrying out the mobile installation step, the landfill is continuously buried and the landfill is maximized to improve utilization of the landfill.

바람직하게 상기 에어돔 지지구조물은 시멘트와 철근으로 이루어진 지지체와, 로프로 이루어져 상기 지지체는 적층되는 폐기물의 하중에 의해 고정되고, 상기 로프는 엥카볼트에 의해 상기 지지체에 연결되어 상기 로프의 끝단이 상기 에어돔의 일측에 결합됨으로써, 상기 에어돔을 지지하는 것을 특징으로 한다.Preferably, the air dome support structure is composed of a support made of cement and reinforcing bar, and the support is fixed by load of waste to be stacked, and the rope is connected to the support by an anchor bolt so that the end of the rope is By being coupled to one side of the air dome, characterized in that for supporting the air dome.

또한, 상기 매립단계에서 상기 폐기물은 상기 소제방에서부터 상기 에어돔 지지구조물측으로 경사진 계단형상으로 적층됨으로써, 폐기물의 흘러내림을 방지한 다.In addition, in the landfilling step, the waste is stacked in a stepped shape inclined from the small bank to the air dome support structure, thereby preventing the waste from flowing down.

상기한 방법은 매립장의 면적을 최대화하여 매립지의 매립량을 늘리는 장점이 있다.The above method has the advantage of increasing the amount of landfills by maximizing the area of the landfill.

이하, 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 설명한다.Hereinafter, exemplary embodiments of the present invention will be described with reference to the accompanying drawings.

또한, 본 실시예는 본 발명의 권리범위를 한정하는 것이 아니라 단지 예시로 제시된 것이며, 종래 발명과 구성 및 작용이 동일한 구성요소는 동일한 부호 또는 명칭을 사용한다.In addition, the present embodiment is not intended to limit the scope of the present invention, but is presented by way of example only, and the components having the same construction and operation as the conventional invention use the same symbols or names.

도 3은 본 발명에 따른 매립지 조성방법을 나타낸 도면이고, 도 4는 본 발명에 따른 매립지 조성방법의 매립장의 단면도이며, 도 5은 본 발명에 따른 매립지 조성방법의 순서도이다.3 is a view showing a landfill composition method according to the invention, Figure 4 is a cross-sectional view of the landfill of the landfill composition method according to the present invention, Figure 5 is a flow chart of the landfill composition method according to the present invention.

도시한 바와 같이, 본 발명에 따른 매립지(100) 조성방법은 상광하협 형상의 매립장(110)을 형성하는 매립장 조성단계(S10)와, 상기 매립장(110)을 조성하고, 상기 매립장(110)의 상부를 에어돔(140)으로 커버하는 에어돔 설치단계(S20)와, 상기 에어돔(140)을 설치하고, 상기 매립장(110)에 폐기물(W)을 일부 적층하는 폐기물 일부 적층단계(S30)와, 상기 매립장(110)에 일부 적층된 폐기물 (W)상부에 상기 에어돔(140)을 지지하는 지지구조물(130)을 제작하는 에어돔 지지구조물 제작단계(S40)와, 상기 에어돔 지지구조물(130)을 제작한 후에 상기 매립장(110)에 폐기물(W)를 매립한 후 상기 매립장(110)을 흙으로 덮어주는 매립단계(S50)와, 상기 매립장(110)을 흙으로 매립하고, 상기 매립장(110)에 소제방(150)을 형성하도록 직접적으로 연이어 신생매립장(110')을 조성하는 신생매립장 조성단계(S60) 및 상기 에어 돔(140)을 이동시켜 일측은 상기 에어돔 지지구조물(130)에 지지되고, 타측은 상기 신생매립장(110') 진행방향측에 지지되어 상기 신생매립장(110') 상부를 커버하는 에어돔 이동설치단계(S70)를 포함하여 이루어지되, 상기 폐기물 일부 매립단계, 에어돔 지지구조물 제작단계, 매립단계, 신생매립장 조성단계와, 상기 에어돔 이동설치단계를 반복 수행하여 폐기물을 지속적으로 매립함과 동시에 매립장을 최대화하여 매립지의 이용률을 향상시키는 것을 특징으로 한다.As shown, the landfill 100 composition method according to the present invention is to form a landfill stage (S10) to form a landfill 110 of the ordinary light-strait form, and to form the landfill 110, the Air dome installation step (S20) to cover the upper portion with the air dome 140, and installing the air dome 140, part of the waste lamination step (S30) to partially deposit the waste (W) in the landfill 110 And, air dome support structure manufacturing step (S40) for producing a support structure 130 for supporting the air dome 140 on the part (W) stacked in the landfill 110, and the air dome support structure After making 130 and the landfill (110) in the landfill (110) and landfilling step (S50) for covering the landfill 110 with soil, and the landfill 110 is buried with soil, New landfill site that directly creates new landfill site 110 'to form small bank 150 in landfill 110 By moving the composition step (S60) and the air dome 140, one side is supported by the air dome support structure 130, the other side is supported in the direction of the new landfill (110 ') traveling direction the new landfill 110' A) cover the upper portion of the air dome moving installation step (S70) is made, including a part of the waste landfill step, air dome support structure manufacturing step, landfill step, new landfill creation step and repeating the air dome moving installation step It is characterized in that to continuously bury the waste and at the same time maximize the landfill to improve the utilization of the landfill.

상기 매립장 조성단계(S10)에서는 할당된 매립지(100)에 상광하협의 육면체형 매립장(110)을 형성한다.In the landfill stage forming step (S10) to form a hexahedral buried ground 110 of the ordinary light narrowing in the assigned landfill 100.

상기 매립장(110)은 내부에 바닥부(112)와 경사부(114)를 형성하고, 대부분은 고밀도 폴리에틸렌(HDPE) 차수막, 즉 폴리에틸렌 시트라이닝과 동시에 이것의 하부층에 적정한 두께의 점토나 벤토나이트 등 기타 첨가제를 다짐하는 Soil 몰탈, Soil 시멘트로 고화 처리하는 공법을 이용하여 차수층(120)을 형성한다.The landfill 110 has a bottom portion 112 and an inclined portion 114 therein, and most of them include a high density polyethylene (HDPE) liner, that is, a polyethylene sheet lining and a suitable thickness of clay or bentonite, etc. The order layer 120 is formed using a method of solidifying with Soil mortar and Soil cement to compact the additive.

이러한 차수층(120)은 상기 매립장(110)의 바닥부(112)와 경사부(114)에 포설함으로써 폐기물(W)에서 발생하는 침출수가 땅속으로 흘러 들어가지 못하게 한다.The order layer 120 is installed on the bottom 112 and the slope 114 of the landfill 110 to prevent the leachate generated from the waste (W) to flow into the ground.

상기 경사부(114)는 계단형상으로 다단 형성되고, 상기 일측 경사부(114)는 경사부(114) 전체에 차수층(120)을 형성하는 반면에 타측 경사부(114)는 최하단에만 차수층(120)을 형성한다.The inclined portion 114 is formed in multiple stages in a step shape, and the one inclined portion 114 forms the order layer 120 on the entire inclined portion 114, while the other inclined portion 114 is only the lowermost order layer 120 ).

상기와 같이 매립장(110) 조성이 끝단 뒤에는 상기 매립장(110)에 모이는 우수를 신속하고 안전하게 차단하기 위해 상기 매립장(110) 상부를 커버하도록 에어 돔(140)을 설치하는 에어돔 설치단계(S20)를 수행한다.Air dome installation step (S20) to install the air dome 140 to cover the top of the landfill 110 in order to block the rainwater gathered in the landfill 110 quickly and safely after the end of the landfill 110 composition as described above Perform

상기 에어돔(air dome,140)은 내부에 프레임이 형성된 타입을 사용하거나 공기 주입에 의한 부양식의 에어돔(140)을 사용하게 된다.The air dome 140 uses a type in which a frame is formed therein or uses an air dome 140 in a form of air injection.

상기 에어돔(140)에는 길이방향의 전방에 대형의 외기 도입팬(142)이 설치되고, 후방에는 배기용 팬(144)을 설치한다.The air dome 140 is provided with a large outside air introduction fan 142 in the front of the longitudinal direction, the exhaust fan 144 is installed in the rear.

상기 에어돔(140)의 외기 도입팬(142)이 설치되어 매립 시 발생되는 악취 및 먼지 등을 상기 에어돔(140)의 후방으로 대류시켜 후방에 설치된 다른 배기용 팬(144)을 이용하여 외측으로 리턴시키게 된다.The outside air introduction fan 142 of the air dome 140 is installed to the outside by using the other exhaust fan 144 installed in the rear by convection odors and dust generated when buried in the rear of the air dome 140 Will be returned.

상기 에어돔 설치단계(S20) 이후에는 상기 매립장(110)에 폐기물(W)을 일부 적층하는 폐기물 일부 적층단계(S30)를 수행한다.After the air dome installation step (S20), a part of the waste stacking step (S30) of partially stacking the waste (W) in the landfill 110 is performed.

이때, 폐기물(W)은 상기 경사부(114)의 최하단에 못미치게 적층한다.At this time, the waste (W) is laminated less than the bottom of the inclined portion (114).

상기 매립장(110)에 폐기물(W)을 일부 매립한 후에 적층된 폐기물(W) 상부에 상기 에어돔(140)을 지지하도록 지지구조물(130) 제작하는 에어돔 지지구조물 제작단계(S40)를 수행한다.After filling part of the waste (W) in the landfill 110, the air dome supporting structure manufacturing step (S40) for manufacturing the support structure 130 to support the air dome 140 on the stacked waste (W) is performed do.

상기 에어돔 지지구조물(130)은 시멘트와 철근으로 이루어진 지지체(132)와, 로프(134)로 이루어지며 상기 로프(134)의 일단은 상기 지지체(132)에 엥카볼트에 의해 고정되고 타측으로 외측으로 연장된다.The air dome support structure 130 is composed of a support 132 made of cement and reinforcement, and a rope 134, one end of the rope 134 is fixed by the anchor bolt to the support 132 and the outer side to the other side Extends.

상기 에어돔 지지구조물(130)이 제작된 후에 상기 매립장(110)에 폐기물(W)을 적층한 후 흙으로 덮는 매립단계(S50)를 수행한다.After the air dome support structure 130 is manufactured, the landfill 110 is stacked with the waste W and then the landfill step S50 is performed.

상기 폐기물(W) 적층시 폐기물(W)이 흘러내리지 않도록 상기 매립장(110)의 타측 최하단 즉, 상기 차수층(120)이 형성된 부위부터 상기 매립장(110)의 일측으로 경사지게 계단형상으로 적층하고, 폐기물(W)이 적층됨에 따라 상기 지지체(132)는 폐기물(W)의 하중에 의해 더욱 단단하게 고정되게 되고, 상기 지지체(132)에 연결된 로프(134)는 폐기물(W)에 덮어지지 않도록 외측으로 돌출되게 계속 꺼내어 놓는다.In order to prevent the waste (W) from stacking the waste (W), the bottom of the other side of the landfill 110, that is, the area in which the order layer 120 is formed, is stacked in a stepped shape to be inclined toward one side of the landfill 110, and waste As the (W) is stacked, the support 132 is more firmly fixed by the load of the waste W, and the rope 134 connected to the support 132 is moved outward so as not to be covered by the waste W. Keep it out to protrude.

상기 매립단계(S50) 이후 적층된 폐기물(W)이 흘러내리지 않도록 타측 최하단 경사부(114)에 연이어 신생매립장(110')을 형성하는 신생매립장 조성단계(S60)를 수행한다.After the landfill step (S50) is carried out to form a new landfill site (S60) to form a new landfill (110 ') in succession to the other bottom inclined portion 114 so that the stacked waste (W) does not flow.

상기 신생매립장(110')의 형성에 의해 상기 매립장(110)과 신생매립장(110')에는 소제방(150)이 형성된다.By the formation of the new landfill (110 ′), a small bank 150 is formed in the landfill 110 and the new landfill 110 (110).

상기 신생매립장(110')의 조성이 끝나면, 상기 매립장(110)의 에어돔(140)을 상기 신생매립장(110')의 상부로 이동 설치하는 에어돔 이동설치단계(S70)를 수행한다.When the composition of the new landfill 110 'is finished, the air dome moving installation step (S70) of moving the air dome 140 of the landfill 110 to the upper portion of the new landfill 110' is performed.

상기 에어돔(140)은 기존의 매립장(110)에서 이동되어 일측은 상기 지지체(132)에 연결되어 외측으로 연장된 로프(134)의 끝단에 연결되어 지지되고, 타측은 신생매립장(110')의 외측땅에 고정된다.The air dome 140 is moved from the existing landfill 110, one side is connected to the support 132 and is connected to the end of the rope 134 extending outward, the other side is buried new landfill 110 ' It is fixed to the outside of the ground.

상기 매립장(110) 내부에 상기 신생매립장(110')의 상부를 커버하기 위해 에어덤 지지구조물(130)을 미리 제작해 둠으로써, 에어돔(140)의 이동설치가 용이한 장점이 있다.Since the air dome support structure 130 is manufactured in advance in order to cover the upper portion of the new landfill 110 'in the landfill 110, there is an advantage that the installation of the air dome 140 is easy to move.

이후, 상기 폐기물 일부 적층단계(S30), 에어돔 지지구조물 제작단계(S40), 매립단계(S50), 신생매립장 조성단계(S60), 에어돔 이동설치단계(S70)를 반복 수행하여 폐기물(W)을 지속적으로 매립한다.Subsequently, by repeating the waste part stacking step (S30), air dome support structure manufacturing step (S40), buried step (S50), new landfill formation step (S60), air dome moving installation step (S70) to waste (W) Continually landfill.

상기한 바와 같이 본 발명에 따른 매립지 조성단계에 의하면 폐기물을 매립하는 매립장을 형성하여 폐기물을 매립한 후에, 매립장에 직접적으로 연이어 있는 소제방에 인접하여 신생매립장을 조성함으로써, 매립장의 면적을 최대화하여 매립지의 매립량을 늘리는 효과가 있다.According to the landfill formation step according to the present invention as described above, after forming the landfill to bury the waste, after filling the landfill, by forming a new landfill adjacent to the small banks directly connected to the landfill, by maximizing the area of the landfill This increases the amount of landfill in the landfill.

또한, 매립장에 폐기물을 일부 적층한 후 신생매립장의 상부를 커버할 에어돔을 설치하기 위한 에어돔 지지구조물을 먼저 제작함으로써, 에어돔 이동설치시 에어돔의 설치공간의 제약 없이 설치가 가능한 장점이 있다.In addition, by manufacturing the air dome supporting structure for installing the air dome to cover the upper part of the new landfill first after stacking some of the waste in the landfill, the advantage that can be installed without restriction of the air dome installation space when moving the air dome have.

또한, 기존 매립장의 에어돔 설치 시 2개의 매립장을 조성한 후에 2개의 에어돔을 사용하는데 반해 매립장의 규모를 확대하고 하나의 에어돔으로 우수를 차단할 수 있으므로, 에어돔의 제작비용 및 이동설치비용을 줄일 수 있는 장점이 있으며, 매립장에 에어돔을 설치하기 위해 매립장과 매립장 사이에 존재하여야 했던 제방을 제거함으로써, 매립지의 활용도를 극대화하는 장점이 있다.In addition, two air domes are used after the installation of two air domes in the existing landfill, whereas the size of the landfill can be expanded and the rainwater can be cut off with a single airdome. There is an advantage that can be reduced, by removing the embankment that had to exist between the landfill and the landfill in order to install the air dome in the landfill, there is an advantage to maximize the utilization of the landfill.

Claims (3)

상광하협 형상의 매립장을 형성하는 매립장 조성단계;A landfill site forming step of forming a buried land of the ordinary light-strait shape; 상기 매립장을 조성하고, 상기 매립장의 상부를 에어돔으로 커버하는 에어돔 설치단계;An air dome installation step of forming the landfill and covering an upper portion of the landfill with an air dome; 상기 에어돔을 설치하고, 상기 매립장에 폐기물을 일부 적층하는 폐기물 일부 적층단계;Installing the air dome and partially stacking waste to partially stack waste in the landfill; 상기 매립장에 일부 적층된 폐기물 상부에 상기 에어돔을 지지하는 지지구조물을 제작하는 에어돔 지지구조물 제작단계;An air dome support structure manufacturing step of manufacturing a support structure for supporting the air dome on the part of the wastes stacked in the landfill; 상기 에어돔 지지구조물을 제작한 후에 상기 매립장에 폐기물을 매립한 후 상기 매립장을 흙으로 덮어주는 매립단계;A landfilling step of covering the landfill with soil after embedding waste in the landfill after fabricating the air dome support structure; 상기 매립장을 흙으로 매립하고, 상기 매립장에 소제방을 형성하도록 직접적으로 연이어 신생매립장을 조성하는 신생매립장 조성단계 및;A new landfill site forming step of directly filling the landfill with soil and successively constructing a new landfill to form a small levee in the landfill; 상기 에어돔을 이동시켜 일측은 상기 에어돔 지지구조물에 지지되고, 타측은 상기 신생매립장 진행방향측에 지지되어 상기 신생매립장 상부를 커버하는 에어돔 이동설치단계를 포함하여 이루어지되;By moving the air dome one side is supported by the air dome support structure, the other side is made to include an air dome movement installation step to cover the new landfill progress direction side to cover the new landfill; 상기 폐기물 일부 매립단계, 에어돔 지지구조물 제작단계, 매립단계, 신생매립장 조성단계와, 상기 에어돔 이동설치단계를 반복 수행하여 폐기물을 지속적으로 매립함과 동시에 매립장을 최대화하여 매립지의 이용률을 향상시키는 것을 특징으로 하는 매립지 조성방법.The waste landfilling step, air dome support structure manufacturing step, landfill step, new landfill site creation step, and repeating the air dome moving step to continue to landfill while maximizing the landfill to improve the landfill utilization rate Landfill formation method characterized in that. 제 1항에 있어서,The method of claim 1, 상기 에어돔 지지구조물은 시멘트와 철근으로 이루어진 지지체와, 로프로 이루어져 상기 지지체는 적층되는 폐기물의 하중에 의해 고정되고, 상기 로프는 엥카볼트에 의해 상기 지지체에 연결되어 상기 로프의 끝단이 상기 에어돔의 일측에 결합됨으로서 상기 에어돔을 지지하는 것을 특징으로 하는 매립지 조성방법.The air dome support structure is composed of a support made of cement and reinforcing steel, and the rope is fixed by the load of waste to be stacked, the rope is connected to the support by the anchor bolt so that the end of the rope is the air dome Landfill composition method characterized in that for supporting the air dome by being coupled to one side of the. 제 1항에 있어서,The method of claim 1, 상기 매립단계에서 상기 폐기물은 상기 소제방에서부터 상기 지지구조물측으로 경사지도록 계단형상으로 적층되어 흘러내림을 방지하는 것을 특징으로 하는 매립지 조성방법.In the landfill step, the waste landfilling method characterized in that the stack is stacked in a step shape so as to be inclined from the fire bank to the side of the support structure.
KR1020060093146A 2006-09-25 2006-09-25 A method for construction of waste landfills KR100724502B1 (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
KR1020060093146A KR100724502B1 (en) 2006-09-25 2006-09-25 A method for construction of waste landfills
US12/442,707 US20100040416A1 (en) 2006-09-25 2007-06-27 Method for construction of waste landfills
JP2009529097A JP2010504198A (en) 2006-09-25 2007-06-27 Waste landfill construction method
PCT/KR2007/003115 WO2008038890A1 (en) 2006-09-25 2007-06-27 A method for construction of waste landfills
CNA2007800354288A CN101517167A (en) 2006-09-25 2007-06-27 A method for construction of waste landfills

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060093146A KR100724502B1 (en) 2006-09-25 2006-09-25 A method for construction of waste landfills

Publications (1)

Publication Number Publication Date
KR100724502B1 true KR100724502B1 (en) 2007-06-04

Family

ID=38358210

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060093146A KR100724502B1 (en) 2006-09-25 2006-09-25 A method for construction of waste landfills

Country Status (5)

Country Link
US (1) US20100040416A1 (en)
JP (1) JP2010504198A (en)
KR (1) KR100724502B1 (en)
CN (1) CN101517167A (en)
WO (1) WO2008038890A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2479721C1 (en) * 2011-10-24 2013-04-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Белгородский государственный технологический университет им. В.Г. Шухова" Recultivation method of open pits using industrial wastes
JP6764588B2 (en) * 2015-08-26 2020-10-07 清水建設株式会社 How to build a waste disposal site
CN111515214A (en) * 2020-04-17 2020-08-11 中国电建集团华东勘测设计研究院有限公司 Step type hazardous waste rigid landfill system based on valley terrain and operation method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0132710B1 (en) * 1993-08-07 1998-04-18 박옥연 Process for building an air house
KR100409266B1 (en) 2001-06-14 2003-12-18 현대건설주식회사 HICT Remediation for Domes on Abandonded Landfills

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5361550A (en) * 1993-12-08 1994-11-08 The United States Of America As Represented By The Secretary Of The Army Movable hardened air form dome-shaped structure for containing hazardous, toxic, or radioactive airborne releases
US6024513A (en) * 1996-11-14 2000-02-15 American Technologies Inc Aerobic landfill bioreactor
US5823716A (en) * 1997-02-25 1998-10-20 Dray; Joseph Method for providing on a landscape a series of terraces with augmented availability of usable level surface
JP3742898B2 (en) * 1997-12-03 2006-02-08 欣英 深田 Industrial waste landfill processing method and industrial waste packaging structure
US6311565B1 (en) * 1999-01-11 2001-11-06 Westinghouse Savannah River Company Techniques and equipment for assessing the structural integrity of subterranean tower anchor rods
US7347648B2 (en) * 2005-03-31 2008-03-25 Viridis Waste Control, Llc Landfills and methods of operating a landfill

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0132710B1 (en) * 1993-08-07 1998-04-18 박옥연 Process for building an air house
KR100409266B1 (en) 2001-06-14 2003-12-18 현대건설주식회사 HICT Remediation for Domes on Abandonded Landfills

Also Published As

Publication number Publication date
CN101517167A (en) 2009-08-26
JP2010504198A (en) 2010-02-12
WO2008038890A1 (en) 2008-04-03
US20100040416A1 (en) 2010-02-18

Similar Documents

Publication Publication Date Title
WO2007139122A1 (en) Facility at banking portion covering waste disposal plant
JP4397050B1 (en) Landfill waste covering structure at final disposal site
KR100724502B1 (en) A method for construction of waste landfills
NL9300923A (en) Land for depositing waste.
CA2201459A1 (en) Retaining wall system and method of construction thereof
KR100667262B1 (en) Waste landfill site preventing landfill gas escape by using waterproof mat
CN216007052U (en) Rigid refuse landfill
CN101049602B (en) The landfill having the drainage system against rain and the method for forming this landfill
KR20060110931A (en) The construction method for ventilation reclaimed institution of landfill using airdome
CA2568491C (en) Landfill including highly permeable zones
KR101016718B1 (en) landfill Gas exclusion really structure which uses the waste tire chip
JP3030604B2 (en) Inside slope structure of waste disposal site
KR101008566B1 (en) Repair, creation and operating method for aerobics of reclaimed land-type the circulation that used airdome structure
JPS5833618A (en) Reclamation treatment of urban refuges
KR102291820B1 (en) Method to landfill waste while constructing a landfill site
CN110303022A (en) A kind of consumer waste filling and embedding system and method for impermeable pollution
JP2500690B2 (en) Waste disposal structure and waste disposal method
KR100218546B1 (en) Build-up method of waste landfill sites for leachate recirculation and lfg extraction
JP2005042298A (en) Roof facility which covers waste disposal site, and roof facility constructing method
KR200404191Y1 (en) The environmental-friendly graveyard and charnel house
KR100655182B1 (en) Retaining wall used waste concrete and method to construct it
CN104341078A (en) Treatment method for leachate in garbage landfill
KR101081512B1 (en) Method reclamation waste of excavation landfill
RU2198745C2 (en) Method of sewage gas gathering and withdrawal at grounds of solid household and industrial wastes
JP2006122791A (en) Closed waste disposal site

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120510

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee