KR100203014B1 - Method and apparatus for lifting heavy materials - Google Patents

Method and apparatus for lifting heavy materials Download PDF

Info

Publication number
KR100203014B1
KR100203014B1 KR1019960039527A KR19960039527A KR100203014B1 KR 100203014 B1 KR100203014 B1 KR 100203014B1 KR 1019960039527 A KR1019960039527 A KR 1019960039527A KR 19960039527 A KR19960039527 A KR 19960039527A KR 100203014 B1 KR100203014 B1 KR 100203014B1
Authority
KR
South Korea
Prior art keywords
arch
lifting
land
supported
towers
Prior art date
Application number
KR1019960039527A
Other languages
Korean (ko)
Other versions
KR19980020867A (en
Inventor
심옥진
조성웅
박정일
이원표
Original Assignee
이내흔
현대건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이내흔, 현대건설주식회사 filed Critical 이내흔
Priority to KR1019960039527A priority Critical patent/KR100203014B1/en
Publication of KR19980020867A publication Critical patent/KR19980020867A/en
Application granted granted Critical
Publication of KR100203014B1 publication Critical patent/KR100203014B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 중량물 양중방법 및 그 장치에 관한 것으로, 강변을 기준으로 하여 육상부(1)에서 수상부(2)쪽으로 동일면상으로 가로질러 연장되고 그 하부는 파일(3)들로 지지되며 서로 마주보면서 평행하게 배치되는 보(4)와, 상기 보(4)의 육상부(1) 상부에 인접하여 일정간격으로 지중에 매설되어 있으면서 소정의 높이만큼 지상으로 상기 보(4)의 상부면까지 돌출되어 위치되는 아치받침대(8)와, 상기 보(4)의 수상부(2) 외측에 일정한 간격으로 두고 수중에 지지되어 배치되는 승강탑(5)들과 이 승강탑(5)들에 구비되는 승강수단(7)을 포함하는 구조로서, 아치(6)를 작업이 용이한 육상의 제작장(13)에서 조립한 후 아치(6)를 밀어내기잭(11)과 활주판(12)을 이용하여 원활하게 이송시킬 수 있는 이점이 있다.The present invention relates to a heavy lifting method and an apparatus thereof, which extend across the same plane from the land part 1 to the water level part 2 on the basis of the riverside, the lower part of which is supported by the piles 3 and faces each other. Beams 4 arranged in parallel and adjacent to the upper portion of the land portion 1 of the beams 4 are embedded in the ground at regular intervals and protrude to the upper surface of the beams 4 to the ground by a predetermined height. Arch bases (8), and elevating towers (5) which are supported and arranged in water at regular intervals outside the water section (2) of the beam (4) and elevating means provided in the elevating towers (5) (7), the arch (6) is assembled in the easy-to-use manufacturing ground 13, and then smoothly using the jack (11) and the sliding plate 12 to push the arch (6). There is an advantage that can be transferred easily.

Description

중량물 양중방법 및 그 장치Heavy weight lifting method and apparatus

제1도는 본 발명에 따른 아치를 조립할 수 있도록 마련된 제작장을 도시한 평면도.1 is a plan view showing a manufacturing site provided to assemble the arch according to the present invention.

제2도는 본 발명에 따른 아치가 육상부에서 수상부로 수평이송되는 상태를 도시한 정면도.Figure 2 is a front view showing a state in which the arch in accordance with the invention the horizontal transfer from the land portion to the water portion.

제3도는 본 발명에 따라 아치가 육상부에서 수상부로 수평이송되는 상태를 도시한 평면도.3 is a plan view showing a state in which the arch is horizontally transferred from the land portion to the water portion according to the present invention.

제4도는 본 발명에 따른 활주판을 도시한 정면도.4 is a front view showing a sliding plate according to the present invention.

제5도는 제4도의 A-A선 단면도.5 is a cross-sectional view taken along the line A-A of FIG.

제6도는 제4도의 B-B선 단면도.6 is a sectional view taken along the line B-B in FIG.

제7도는 본 발명에 따른 아치를 제작장에서 제작시 사용되는 설치잭이 설치된 상태를 도시한 정면도.Figure 7 is a front view showing a state in which the installation jack is used when manufacturing the arch in accordance with the present invention manufacturing.

제8도는 제7도의 C-C선 단면도.8 is a cross-sectional view taken along the line C-C of FIG.

제9도는 본 발명에 따른 승강탑을 도시한 정면도.9 is a front view showing an elevator tower according to the present invention.

제10도는 본 발명에 따른 승강탑을 도시한 평면도.10 is a plan view showing an elevator tower according to the present invention.

제11도는 본 발명에 따른 아치가 수상부로 수평이송되어 승강탑에 탑재된 상태를 도시한 정면도.11 is a front view showing a state in which the arch in accordance with the present invention is horizontally transported to the water level mounted on the lifting tower.

제12도는 본 발명에 따른 아치가 승강탑에 올라가는 상태를 도시한 정면도.12 is a front view showing a state where the arch according to the present invention ascends the lifting tower.

* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

1 : 육상부 2 : 수상부1: Athletics 2: Water Division

3 : 파일 4 : 보3: file 4: bo

5 : 승강탑 6 : 아치5: lift tower 6: arch

7 : 승강수단 8 : 아치받침대7: lifting means 8: arch support

9 : 철근콘크리트보 10 : 철골보9: reinforced concrete beam 10: steel ball

11 : 밀어내기잭 12 : 활주판11: extrude jack 12: sliding plate

13 : 제작장 14 : 침목13: production 14: sleepers

15 : 양중잭 16 : 연직와이어로프15: double jack 16: vertical wire rope

17 : 아치받침판 18 : 받침잭17: arch support plate 18: support jack

[발명의 상세한 설명]Detailed description of the invention

본 발명은 중량물 양중방법 및 그 장치에 관한 것으로, 특히 아치를 작업이 용이한 육상의 제작장에서 조립하여 완성한 후에 이를 원하는 위치로 원활히 이송시킬 수 있도록 한 중량물 양중방법 및 그 장치에 관한 것이다.The present invention relates to a heavy lifting method and apparatus, and more particularly, to a heavy lifting method and apparatus for assembling and completing the arch in the fabrication site of the easy-to-operate land to smoothly transport it to a desired position.

일반적으로 건축물이 초고층화 및 대규모화됨에 따라 자재의 양이 증가하게 되고, 이에 따라 자재운반에 따른 양중시간이 증대하게 되어서 현장의 공사작업능률이 저하되게 된다. 이를 해소하기 위해서는 양중기의 능력향상을 꾀하고 공정계획에 따라 소요장소에 적합한 자재를 확실히 수송하는 것이 필요하다.In general, as the building is ultra-high and large-scale, the amount of materials increases, thereby increasing the lifting time according to the material transportation, thereby reducing the construction work efficiency of the site. To solve this problem, it is necessary to improve the capacity of the heavy lifting equipment and to ensure that the material suitable for the required place is transported according to the process plan.

또한, 초고층 건물 등의 계획 대상이 되는 대지주변부 도로는 가장 교통량이 번잡한 지역에 위치하기 때문에 그 공사 자체가 큰 도시문제가 되며, 건설관계 차량의 운행은 엄격한 규제를 받는 것이 보통이며, 시공은 심한 제약을 받게 된다.In addition, since the road around the site, which is the planning target of high-rise buildings, is located in the area with the most traffic, the construction itself is a big city problem, and the operation of construction-related vehicles is usually subject to strict regulations. You will be severely restricted.

즉, 규정이상의 대형차량에 대해서 일정한 시간 통행금지의 도로구역이 지시됨에 따라 자재운반 때문에 요로의 제한이나 노상주차 및 노상점의 금지를 받아, 운반능률의 저하나 공사의 침체를 초래하는 원인이 됨에 따라서 이 자재운반의 제약에 의한 교통난의 극복이 시공계획, 운반계획의 기본조건으로 되어 있다.In other words, as a road area with a certain time curfew is instructed for oversize vehicles, the restriction of urinary tract and the ban of roadside parking and roadsides are prohibited due to material transportation, which causes the deterioration of transportation efficiency and construction slowdown. Therefore, overcoming traffic shortcomings due to this material transportation constraint is the basic condition of construction plan and transportation plan.

따라서 모래, 자갈, 철골 등에 현장에 반입되는 중량제나 장대한 재료의 운반차량의 대개는, 금지규제를 받는 대형차량이며, 그 운반은 도시내에 있어서 심야 시간대 이외는 규제를 받게 되기 때문에 1일의 작업에 필요한 자재의 총량을 이른 아침까지 현장에 반입하고, 대지내의 가치장에 적재하지 않으면 시공을 원할하게 하기 어렵다.As a result, heavy vehicles and heavy materials carried on the sand, gravel, steel, etc. are large vehicles subject to prohibition, and their transportation is regulated outside the nighttime zone in the city. It is difficult to smooth construction without bringing the total amount of materials necessary for the construction into the site by early morning and not loading it on the site of value.

이와 같은 시가지에 있어서 교통과 도로사정은 오늘날 건축시공상 큰 제약으로 되어 있으나, 대규모화 초고층 건축공사에 있어서는 다종다량의 자재를 전기간에 걸쳐서 공정계획에 따라 또는 현장의 사정과 능력에 맞춰서 지체없이 반입하는 것이 시공관리상 요점이 된다.Traffic and road conditions in today's cities are a big limitation in today's building construction, but in large-scale high-rise construction work, large quantities of materials are brought in without delay according to the process plan or according to the circumstances and capabilities of the site. This is the point of construction management.

이에 본 발명은 상기한 바와 같은 제문제점을 해결하기 위하여 안출된 것으로서, 자재운반 및 작업이 용이한 육상의 제작장에서 아치를 조립한 후 이 아치를 활주판과 밀어내기잭을 이용하여 원활하게 이송시킬 수 있도록 한 중량물 양중방법 및 그 장치를 제공함에 그 목적이 있다.Therefore, the present invention was devised to solve the problems described above, and after assembling the arch in the fabrication site of the land for easy material transport and operation, the arch is smoothly transported using a slide plate and an extrusion jack. It is an object of the present invention to provide a weight lifting method and an apparatus thereof.

상기한 바의 목적을 달성하기 위한 본 발명은 강변을 기준으로 하여 육상부에서 수상부쪽으로 동일면상으로 가로질러서 연장되고 그 하부는 파일들로 지지되며 서로 마주보면서 평행하게 배치되는 보와, 상기 보의 육상부 상부에 인접하여 일정간격으로 지중에 매설되어 있으면서 소정의 높이만큼 지상으로 상기 보의 상부면까지 돌출되어 위치되는 아치받침대와, 상기 보의 수상부 외측에 일정한 간격을 두고 수중에 지지되어 배치되는 승강탑들과 이 승강탑들에 구비되는 승강수단을 포함하는 것을 특징으로 한다.The present invention for achieving the object of the above is a beam that extends in the same plane from the land side to the water surface relative to the river side and the lower portion is supported by piles and arranged in parallel facing each other, The arch support which is buried in the ground at a predetermined interval adjacent to the upper part of the land part and is projected to the upper surface of the beam to the ground by a predetermined height, and is supported and disposed in the water at regular intervals outside the water part of the beam. And elevating towers and elevating means provided in the elevating towers.

상기한 바와 같이 이루어진 본 발명은 자재반입 및 조립작업이 용이한 육상의 제작상에서 아치를 조립한 후 이를 활주판과 밀어내기잭을 이용하여 원활하게 이송시킬 수 있는 이점이 있다.The present invention made as described above has the advantage that can be smoothly transported by using the sliding plate and the push jack after assembling the arch on the fabrication of the land that is easy to import and assembly work.

이하 본 발명을 첨부한 예시도면을 참조하여 자세히 설명한다.Hereinafter, with reference to the accompanying drawings, the present invention will be described in detail.

제1도는 본 발명에 따른 아치를 조립할 수 있도록 마련된 제작장을 도시한 평면도, 제2도는 본 발명에 따른 아치가 육상부에서 수상부로 수평이송되는 상태를 도시한 정면도, 제3도는 본 발명에 따라 아치가 육상부에서 수상부로 수평이송되는 상태를 도시한 평면도, 제4도는 본 발명에 따른 활주판을 도시한 정면도, 제5도는 제4도의 A-A선 단면도, 제6도는 제4도의 B-B선 단면도, 제7도는 본 발명에 따른 아치를 제작장에서 제작시 사용되는 설치잭이 설치된 상태를 도시한 정면도, 제8도는 제7도의 C-C선 단면도, 제9도는 본 발명에 따른 승강탑을 도시한 정면도, 제10도는 본 발명에 따른 승강탑을 도시한 평면도, 제11도는 본 발명에 따른 아치가 수상부로 수평이송되어 승강탑에 탑재된 상태를 도시한 정면도, 제12도는 본 발명에 따른 아치가 승강탑에 올라가는 상태를 도시한 정면도이다.1 is a plan view showing a manufacturing site prepared to assemble the arch according to the present invention, Figure 2 is a front view showing a state in which the arch according to the present invention horizontally transferred from the land portion to the water portion, Figure 3 is in accordance with the present invention 4 is a front view showing a sliding plate according to the present invention, FIG. 5 is a sectional view taken along line AA of FIG. 4, and FIG. 6 is a sectional view taken along line BB of FIG. 7 is a front view showing a state in which the installation jack is used when manufacturing the arch according to the invention in the manufacturing site, FIG. 8 is a cross-sectional view taken along line CC of FIG. 7, FIG. 9 is a front view showing the lifting tower according to the present invention Figure 10 is a plan view showing the elevating tower according to the present invention, Figure 11 is a front view showing a state in which the arch according to the present invention is mounted on the lifting tower horizontally transferred to the water portion, Figure 12 is an arch according to the present invention Go up to the tower Is a front view showing a state.

이들 도면에 도시된 바와 같이 본 발명에 따른 중량물 양중방법 및 그 장치는, 강변을 기준으로 하여 육상부(1)에서 수상부(2)쪽으로 동일면상으로 가로질러서 연장되고 그 하부는 파일(3)들로 지지되며 서로 마주보면서 평행하게 배치되는 보(4)와, 상기 보(4)의 육상부(1) 상부에 인접하여 일정간격으로 지중에 매설되어 있으면서 소정의 높이만큼 지상으로 상기 보(4)의 상부면까지 돌출되어 위치되는 아치받침대(8)와, 상기 보(4)의 수상부(2) 외측에 일정한 간격을 두고 수중에 지지되어 배치되는 승강탑(5)들과 이 승강탑(5)들에 구비되는 승강수단(7)을 포함하는 구조로 이루어져 있다.As shown in these figures, the heavy lifting method and the apparatus according to the present invention extend across the same plane from the land part 1 to the water part 2 on the basis of the riverside and the lower part of the piles 3. A beam 4 which is supported in parallel with each other and arranged in parallel with each other, and is buried in the ground at a predetermined interval adjacent to the upper portion of the land portion 1 of the beam 4 and at a predetermined height, Arch tower 8 protruding up to the upper surface, the elevating tower (5) and the elevating tower (5) which is supported and arranged in the water at regular intervals outside the water section (2) of the beam (4) It consists of a structure including the lifting means (7) provided in the field.

여기서, 상기 보(4)는 그 설치되는 위치에 따라 육상부(1)는 철근 콘크리트보(9)가 설치되고, 수상부(2)는 철골보(10)가 설치된다.In this case, the beam 4 is a reinforced concrete beam 9 is installed on the land portion 1 according to the installation position thereof, the water column 2 is provided with a cheolgolbo 10.

상기한 바와 같이 이루어진 본 발명에 따른 보의 제작 과정은 제2도에 도시된 바와 같이 먼저 강변을 기준으로 하여 육상부(1)에서 수상부(2)쪽으로 동일평면상으로 가로질러서 연장되고 그 하부는 파일(3)들로 지지되면서 서로 마주보면서 평행하게 한쌍의 보(4)를 배치한다.The manufacturing process of the beam according to the present invention made as described above is first extended across the same plane from the land portion (1) to the water portion (2) on the basis of the river side as shown in FIG. The pair of beams 4 are arranged parallel to each other while being supported by piles 3.

이때, 상기 보(4)는 그 설치되는 위치에 따라 육상부(1)는 철근콘크리트보(9)를 설치하고, 수상부(2)는 철골보(10)로 설치하도록 한다.At this time, the beam 4 is to be installed on the land portion 1 is reinforced concrete beam (9), and the water receiving portion (2) is to be installed as a cheolgolbo (10).

즉, 이와 같이 보(4)를 그 위치에 따라 분리하여 제작하는 이유는 육상에서 제작한 아치(6)를 이송후 적재하기 편리하도록 하기 위함이며, 물론 필요에 따라 보(4)를 단일보로 제작할 수도 있으나 민일, 철근콘크리트보(9)로 할 경우에는 아치(6)를 수평이송후 별도의 중장비를 이용하여 적재하여야 되기 때문에 번거로움이 따르게 되나, 철골보(10)로 할 경우에는 제작 비용은 철근콘크리트보(9)에 비하여 많이 발생되나 아치(6)를 이송후 이를 소정의 길이만큼 절단하여 승강탑(5)들에 아치(6)와 같이 탑재될 수 있으므로 별도의 중장비 없이 적재작업을 원활하게 할 수 있다.That is, the reason for separating and manufacturing the beam 4 according to its position is to make it easy to transport and load the arch 6 produced on land, and, of course, if necessary, the beam 4 as a single beam. Although it can be manufactured, but the minil, reinforced concrete beams (9), the arch (6) has to be loaded using a separate heavy equipment after horizontal transfer, but it is cumbersome, but if the steel ball (10) production costs Compared to the reinforced concrete beam (9), but is generated a lot, but after transporting the arch (6) and cut it by a predetermined length can be mounted on the elevating tower (5) as the arch (6) so that the loading operation without additional heavy equipment smoothly It can be done.

상기한 바와 같이 보를 제작한 후 제1도 및 제9도에 도시된 바와 같이, 상기 철골보(10)의 수상부(2)에 인접하여 위치되게 아치(6)의 크기와 무게 및 그 폭을 고려해서 이 아치(6)를 안전하게 양중할 수 있도록 그 높이와 폭을 적절히 고려하여 승강탑(5)들을 설치하고, 상기 철근콘크리트보(9)의 육상부(1)상에 유지하면서 소정의 높이만큼 지상으로 철근콘크리트보(9)의 상부면까지 돌출되도록 설치하며, 상기 아치받침대(8)상에 받침잭(18)을 설치하여 이를 조정하면서 아치(6)를 제작하도록 한다.After fabricating the beam as described above, as shown in FIGS. 1 and 9, the size, weight, and width of the arch 6 are positioned to be adjacent to the water portion 2 of the cheolgolbo 10. In order to safely lift the arch 6, the lifting towers 5 are installed in consideration of the height and width thereof, and the ground level is maintained above a predetermined height while being kept on the land portion 1 of the reinforced concrete beam 9. By installing so as to protrude up to the upper surface of the reinforced concrete beam (9), by installing the support jack 18 on the arch support (8) to make the arch (6) while adjusting it.

상기한 바와 같은 구조로 이루어진 본 발명에 따른 중량물 양중장치의 작동과정을 설명한다.It describes the operation of the heavy lifting device according to the invention made of a structure as described above.

제2도 및 제3도에 도시된 바와 같이, 제작장(13)에서 조립완료된 아치(6)를 밀어내기잭(11)을 이용하여 육상부(1)쪽 철근콘크리트보(9)로부터 수상부(2)쪽 철골보(10)상으로 수평 이송시키도록 하며, 이때 아치(6)의 단횡형과 보(4) 사이에 마찰로 인하여 아치(6)에 하중이 전달되지 않도록 하기 위하여 단횡형 하부에 활주판(12)을 설치하여 활주판(12)을 직접 견인하도록 한다.As shown in FIG. 2 and FIG. 3, by using the jack 11 of the assembled arch 6 in the fabrication site 13 from the reinforced concrete beam 9 toward the land portion 1 from the reinforced concrete beam 9 2) It is to be horizontally transported on the side cheolgolbo (10), at this time sliding to the lower side of the lateral cross in order not to transfer the load to the arch (6) due to friction between the lateral cross of the arch (6) and the beam (4) The plate 12 is installed to pull the slide plate 12 directly.

여기서, 상기 아치(6)는 거대구조물이므로 이에 따른 마찰력은 상당하므로 마찰력을 줄이기 위하여 마찰면에 그리스를 도포하고 활주판(12) 바닥은 침목(14)을 삽입한다.Here, since the arch 6 is a large structure, the frictional force is considerable, so that grease is applied to the friction surface to reduce the frictional force, and the bottom of the sliding plate 12 inserts the sleeper 14.

또한, 보(4)는 육상부(1)의 철근콘크리트보(9) 구간과 수상부(2)의 철골보(10) 구간으로 나누어지므로 철골보(10)는 아치(6) 이송후 양중시 아치받침판(17)으로도 이용되므로 휨에 대하여 충분히 강성을 유지해야 한다.In addition, the beam (4) is divided into the reinforced concrete beam (9) section of the land portion (1) and the steel frame beam (10) section of the water receiving section (2), so the steel frame beam 10 is the arch support plate at the time of lifting the arch (6) ( It is also used as 17), so it must maintain sufficient rigidity against bending.

더불어, 아치(6) 수평이송시 아치(6)에 의한 집중하중으로 인하여 지반의 부등침하가 예상되므로 보(4) 하부는 파일 기초로 보강한다.In addition, since the uneven settlement of the ground is expected due to the concentrated load by the arch 6 during horizontal transfer of the arch 6, the lower portion of the beam 4 is reinforced with a pile foundation.

상기와 같이 아치(6)를 육상부(1) 철근콘크리트보(9)로부터 수상부(2)쪽으로 철골보(10)상으로 활주판(12)을 미끄러지듯이 밀어내기잭(11)으로 아치(6)를 당겨 수상부(2)에 위치된 승강탑(5)들로 수평 이송시킨 후, 상기 각 승강탑(5)들 사이에 철골보(10)를 삽입한 후 승강수단(7)의 하나인 양중잭(15)으로 소정의 높이로 아치받침판(17)상에 위치된 아치(6)를 양중시킬 수 있도록 한다.As described above, the arch 6 slides the slide plate 12 from the land portion 1 reinforced concrete beam 9 onto the steel beam 10 from the reinforced concrete beam 9 onto the steel frame 10. After pulling the horizontal transfer to the elevating tower (5) located in the water receiving section (2), inserting the cheolgolbo 10 between each of the elevating tower (5) and then lifting jacks one of the elevating means (7) (15) to lift the arch (6) located on the arch support plate 17 to a predetermined height.

여기서, 각 승강탑(5)들 사이로 아치받침판(17)에 지지된 아치(6)를 승강탑(5)의 중앙부에 위치된 승강수단(7)에 있는 양중잭(15)을 작동시켜 연직와이어로프(16)를 늘어뜨려 아치(6)와 아치받침판(17)을 함께 묶어서 소정의 높이로 양중 시키면 된다.Here, by operating the double jack 15 in the elevating means (7) located in the center of the elevating tower 5 to the arch (6) supported between the elevating tower (5) between the elevating tower (5) By hanging the rope 16, the arch 6 and the arch support plate 17 are tied together and lifted to a predetermined height.

이상에서 설명한 바와 같이 본 발명에 따른 중량물 양중방법 및 그 장치는 아치(6)를 작업이 용이한 육상의 제작장(13)에서 조립한 후 이 아치(6)를 밀어내기잭(11)과 활주판(12)을 이용하여 원활하게 이송시킬 수 있는 이점이 있다.As described above, the heavy lifting method and the apparatus according to the present invention assemble the arch 6 in the easy-to-use manufacturing site 13 and then slide the arch 6 and the jack 11 and slide. There is an advantage that can be smoothly transferred using the plate (12).

이상에서 서술된 것은 모든 점에서 단순한 예시에 불과한 것이고, 이를 가지고 한정적으로 해석해서는 안되며, 단지 본 발명의 진정한 정신 및 범위 내에 존재하는 실시예는 모두 본 발명의 청구범위에 포함되는 것이다.What has been described above is merely illustrative in all respects, and should not be construed as limited thereto, and all embodiments that fall within the true spirit and scope of the present invention are included in the claims of the present invention.

Claims (3)

강변을 기준으로 하여 육상부(1)에서 수상부(2)쪽으로 동일면상으로 가로질러서 연장되고 그 하부는 파일(3)들로 지지되며 서로 마주보면서 평행하게 한쌍의 보(4)를 배치하고, 상기 보(4)의 수상부(2)에 인접되게 승강탑(5)들을 설치하며, 상기 보(4)가 위치되는 육상부(1)의 상부에서 아치(6)가 지지되는 상태로 제작한 후 이 아치(6)를 보(4)의 육상부(1)에서 수상부(2)쪽으로 미끄러 당겨 승강탑(5)들로 수평 이송시킨 후, 상기 승강탑(5)들에 구비되는 승강수단(7)으로 소정의 높이로 양중시킬 수 있도록 함을 특징으로 하는 중량물 양중방법.On the basis of the riverside extends across the same plane from the land part (1) to the water level (2), the lower part is supported by the piles (3) and arranged a pair of beams (4) in parallel facing each other, The elevating towers 5 are installed adjacent to the water level 2 of the beam 4, and after the arch 6 is supported at the upper portion of the land portion 1 where the beam 4 is located, After the arch 6 is moved horizontally from the land portion 1 of the beam 4 toward the water level 2 to the lifting towers 5, the lifting means 7 provided on the lifting towers 5 are provided. Weight lifting method characterized in that for lifting to a predetermined height. 강변을 기준으로 하여 육상부(1)에서 수상부(2)쪽으로 동일면상으로 가로질러서 연장되고 그 하부는 파일(3)들로 지지되며 서로 마주보면서 평행하게 배치되는 보(4)와, 상기 보(4)의 육상부(1) 상부 인접하여 일정간격으로 지중에 매설되어 있으면서 소정의 높이만큼 지상으로 상기 보(4)의 상부면까지 돌출되어 위치되는 아치받침대(8)와, 상기 보(4)의 수상부(2) 외측에 일정한 간격을 두고 수중에 지지되어 배치되는 승강탑(5)들과 이 승강탑(5)들에 구비되는 승강수단(7)을 포함하는 중량물 양중장치.A beam 4 which extends across the same plane from the land part 1 to the water level part 2 on the basis of the river side and whose lower part is supported by the piles 3 and arranged in parallel to each other, 4) the arch support 8 which is buried in the ground at a predetermined interval adjacent the upper portion of the land part 1 and protrudes to the upper surface of the beam 4 to the ground by a predetermined height, A heavy lifting device including lifting towers (5) which are supported and arranged in the water at regular intervals outside the water receiving unit (2) and lifting means (7) provided in the lifting towers (5). 제2항에 있어서, 상기 보(4)는 그 설치되는 위치에 따라 육상부(1)는 철근콘크리트보(9)가 설치되고, 수상부(2)는 철골보(10)가 설치되는 것을 특징으로 하는 중량물 양중장치.According to claim 2, wherein the beam (4) is characterized in that the reinforcement concrete beam (9) is installed on the land portion (1), the steel plate (10) is installed in accordance with the installation position Heavy lifting device.
KR1019960039527A 1996-09-12 1996-09-12 Method and apparatus for lifting heavy materials KR100203014B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019960039527A KR100203014B1 (en) 1996-09-12 1996-09-12 Method and apparatus for lifting heavy materials

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019960039527A KR100203014B1 (en) 1996-09-12 1996-09-12 Method and apparatus for lifting heavy materials

Publications (2)

Publication Number Publication Date
KR19980020867A KR19980020867A (en) 1998-06-25
KR100203014B1 true KR100203014B1 (en) 1999-06-15

Family

ID=19473510

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019960039527A KR100203014B1 (en) 1996-09-12 1996-09-12 Method and apparatus for lifting heavy materials

Country Status (1)

Country Link
KR (1) KR100203014B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101026014B1 (en) 2010-11-25 2011-03-30 (주) 한국비계 Bridge deck construction method by means of pulling jack on the water

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101026014B1 (en) 2010-11-25 2011-03-30 (주) 한국비계 Bridge deck construction method by means of pulling jack on the water

Also Published As

Publication number Publication date
KR19980020867A (en) 1998-06-25

Similar Documents

Publication Publication Date Title
WO2022016720A1 (en) Temporary passage construction method employing support structure in deep foundation pit
US6574818B1 (en) Provisional bridge of prefabricated elements
US20040148717A1 (en) Method and installation for building a highway and a highway
CN110578339A (en) construction method of shaft type underground stereo garage
CN105908639A (en) Prefabricated box culvert and rapid positioning construction method
CN111827149A (en) Bridge widening hinge structure and construction method
JP3851539B2 (en) Block-type traffic roads, split-bridge-type traffic roads, and bridge traffic roads
CN112609735B (en) Semi-embedded column base positioning and mounting device and construction method thereof
KR100203014B1 (en) Method and apparatus for lifting heavy materials
US20100272509A1 (en) Traffic barrier section
RU2652050C2 (en) Anchoring device for ski lift structure foundations, lift station, linear support comprising said device and method of manufacturing said device
JP3453553B2 (en) Continuous construction method of precast concrete column wall members
CN111608429B (en) Assembled ultra-deep foundation pit ramp system and construction method thereof
CN114856248A (en) Corridor type safety channel applied to sloping type deep foundation pit and construction method
CN214302989U (en) Build assembled garage parking on ground additional
CN214995238U (en) Semi-embedded column base and positioning and mounting device thereof
JP3940587B2 (en) Construction method of divided bridge type traffic route
JP2004225529A (en) Continuous laying method for precast concrete slab
CN112796325A (en) Double-deck trestle type reverse construction method
RU2453650C1 (en) Complex for construction of motor road on piles
JP2536376B2 (en) Foundation structure of shed for road protection
CN217174339U (en) Cross transportation bridge and culvert for strip mine and cross transportation system for strip mine
US3385180A (en) Construction of roads and associated surfaces
CN214194648U (en) Urban open cut tunnel excavation supporting system
KR100627103B1 (en) a structure transportation means and precast structure installation method using the same

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20030324

Year of fee payment: 5