CN112796325A - Double-deck trestle type reverse construction method - Google Patents

Double-deck trestle type reverse construction method Download PDF

Info

Publication number
CN112796325A
CN112796325A CN202110141104.4A CN202110141104A CN112796325A CN 112796325 A CN112796325 A CN 112796325A CN 202110141104 A CN202110141104 A CN 202110141104A CN 112796325 A CN112796325 A CN 112796325A
Authority
CN
China
Prior art keywords
plate
construction method
double
layer
trestle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110141104.4A
Other languages
Chinese (zh)
Inventor
王飞
丁应章
周圣平
徐强
孙玉叶
沈东杰
唐立帆
周炜炜
程大勇
林永祥
熊超逸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN202110141104.4A priority Critical patent/CN112796325A/en
Publication of CN112796325A publication Critical patent/CN112796325A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G27/00Temporary arrangements for giving access from one level to another for men or vehicles, e.g. steps, ramps
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to the field of building construction, and provides a double-layer trestle type reverse construction method construction process. The technology comprises a double-layer trestle formed by an upper layer of structural plate and a lower layer of structural plate, a containment stress monitoring system and a traffic management system, and has the following advantages: the construction is convenient, and the popularization is easy; the second unearthing efficiency is high; thirdly, the traffic line is clear and reasonable, and fourthly, the dust emission in the earth excavation process can be reduced, so that the method is green and environment-friendly; the double-layer trestle reverse construction method provided by the invention solves the problems that in the prior art, because the roof opening is limited, the reverse construction method has lower unearthing efficiency than the forward construction method, and because the reverse construction method adopts earthwork excavation and the underground structure to be constructed simultaneously, a large amount of mechanical equipment and material yards are invested, the traffic environment in a field is severe, the concept is expanded for the development of the deep foundation pit reverse construction method construction technology, and the double-layer trestle reverse construction method has considerable social benefits.

Description

Double-deck trestle type reverse construction method
Technical Field
The invention relates to the field of building construction, in particular to a double-deck trestle type reverse construction method.
Background
With the high-speed increase of economy in China, super high-rise buildings and large-scale multi-storey basement engineering are gradually increased, and extra-large and extra-deep foundation pits are also increased. Due to the development of urban construction, the situations that other important buildings and underground traffic tunnels exist in the adjacent foundation pit are very common. Under the condition, the foundation pit is difficult to adopt the technical means of external anchoring, the traditional internal supporting method is not economical and applicable due to the appearance of the ultra-large foundation pit, and the large deep foundation pit support has the dilemma that the external anchoring cannot be realized and the internal supporting is difficult to realize.
Under the dilemma that the inner part is difficult to support and the outer part is difficult to anchor, the reverse construction method is selected for more and more oversized ultra-deep foundation pits. However, because the opening of the top plate is limited, the reverse construction method has lower unearthing efficiency than the forward construction method, and the earth excavation and the underground structure are constructed simultaneously by the reverse construction method, so that the traffic environment in the yard is severe due to the large investment of mechanical equipment and material yards.
Disclosure of Invention
On the basis of the common general knowledge in the field, the above-mentioned preferred conditions can be combined arbitrarily without departing from the concept and the protection scope of the invention.
In order to solve the technical problem, the invention provides a double-layer trestle type reverse construction method construction process which comprises a double-layer trestle formed by structural plates, a containment stress monitoring system and a traffic management system.
As a preferred technical solution, the construction method for forming a double-deck trestle by using the structural slab of the present invention at least comprises the following steps:
step (1): excavating a first layer of earthwork to an elevation below the bottom of the B0 board, pouring a cushion layer, erecting a formwork support, constructing the B0 board, reserving a soil taking hole, after the construction of the B0 board is completed, driving an excavator to the side of the soil taking hole of the B0 board, and enabling an earthwork vehicle to pass through the B0 board;
step (2): excavating a second layer of earthwork to the elevation below the B2 plate, transporting the earthwork outside through an excavated hole of the B0 plate, pouring a cushion layer, building a formwork support, constructing slopes of the B2 plate and the B2 plate below the B0, and reinforcing a lattice column in the range of a heavy roadway between the B0 plate and the B2 plate;
and (3): after the construction of the B2 plate is completed, the excavator drives to the B2 plate soil taking wharf to take soil, the earth moving vehicles pass through the B0 plate and the B2 plate, and the B0 plate is used as a main material storage yard and a large mechanical equipment parking yard.
As a preferable technical solution, the construction method for forming a double-deck trestle by using the structural slab further includes:
and (4): excavating the third layer of earthwork to the elevation below the B3 board, transporting the earthwork outside through the unearthed openings of the B0 and B2 boards, pouring a cushion layer, erecting a formwork support and constructing the B3 board;
and (5): and excavating the earthwork of the fourth layer to the elevation of the bottom surface of the foundation pit, vertically transporting the earthwork through the excavated openings of the B0, B2 and B3 boards, pouring a cushion layer, binding a bottom plate reinforcing steel bar, and constructing the bottom plate of the basement.
As a preferable technical solution, the construction method for forming a double-deck trestle by using the structural slab further includes:
and (6): dismantling the slope ramp of the B2 plate below the B0 plate, building a formwork support on the B2 plate, constructing the B1 plate structure, and stopping using the heavy lane on the B2 plate;
and (7): and (4) sequentially manufacturing a structure plate and a B1 plate structure plate reserved in the range of the unearthed hole of the construction, and integrally finishing the basement.
As a preferable technical scheme, the formwork support in the step (1), the formwork support in the step (2), the formwork support in the step (4) and the formwork support in the step (6) all adopt socket-type disc buckle tool scaffolds.
As a preferable technical scheme, the slope of the B2 plate under the B0 plate is 1: (5-10), wherein the width is an integral multiple of the space between the lattice columns; concrete anti-collision guardrails are required to be arranged on two sides of the ramp.
As a preferable technical scheme, in the step (2) of the invention, the latticed column is reinforced in a mode of cross reinforcement of the steel inclined struts, and each span of the steel inclined struts is reinforced in the heavy lane range along the lane direction.
As a preferable technical scheme, the B1 plate structure is constructed by a forward construction method after the construction of the bottom plate is completed, so that the height between the B0 and the B2 plate meets the requirement of the working space of conventional mechanical equipment.
As a preferable technical scheme, traffic flow lines of construction vehicles on the B0 plate and the B2 plate are all one-way circular lines, and traffic flow driving directions of overlapped parts of different circular lines are the same.
As a preferred technical solution, the containment stress monitoring system in the present invention includes: monitoring vertical stress of the lattice column and monitoring axial stress of a force transfer beam at an unearthed opening.
As a preferable technical solution, in the invention, the lattice column vertical stress monitoring controls the arrangement of the B0 plate yard and the accumulation of heavy-duty vehicles according to the monitoring data; and monitoring the axial stress of the unearthed tunnel entrance force transfer beam, and evaluating the safety of the enclosure system according to monitoring data.
As a preferable technical scheme, the traffic management system comprises traffic signal management and pedestrian and vehicle distribution management.
As a preferable technical solution, in the traffic signal management of the present invention, it is required to set traffic guide signs, zebra crossings and traffic lights at the intersections of B0 boards and B2 boards, and draw guide lines for each lane; and the man-vehicle flow distribution management requires that a rigid isolation belt is erected between a sidewalk and a roadway by using a shaped fence.
Compared with the prior art, the invention has the following remarkable advantages and effects:
the invention provides a double-layer trestle type reverse construction method construction process, which consists of a double-layer trestle formed by an upper layer of structural plate and a lower layer of structural plate, an envelope stress monitoring system and a traffic management system, provides a novel reverse construction method construction technology, can be applied to all projects with more than four layers, and has the following advantages: the construction is convenient, and the popularization is easy; the second unearthing efficiency is high; thirdly, the traffic line is clear and reasonable, and fourthly, the dust emission in the earth excavation process can be reduced, so that the method is green and environment-friendly; the double-layer trestle reverse construction method provided by the invention solves the problems that in the prior art, because the roof opening is limited, the reverse construction method has lower unearthing efficiency than the forward construction method, and because the reverse construction method adopts earthwork excavation and the underground structure to be constructed simultaneously, a large amount of mechanical equipment and material yards are invested, the traffic environment in a field is severe, the concept is expanded for the development of the deep foundation pit reverse construction method construction technology, and the double-layer trestle reverse construction method has considerable social benefits. The double-layer trestle type top-down construction technology effectively solves the problems of limited space and low unearthing efficiency of a top-down construction method construction project site, and has the advantages of high construction efficiency and clear and reasonable traffic line.
Drawings
Fig. 1 to 7 are drawings illustrating an example of reverse four-layer engineering in embodiment 1.
Fig. 1 is a plan view of a double-deck trestle type inverse method foundation pit bracing system in the construction method of the invention, version B0.
FIG. 2 is a schematic structural view of step (1) in the construction method according to the present invention;
FIG. 3 is a schematic structural diagram of step (2) in the construction method of the present invention;
FIG. 4 is a schematic structural view of a cross-sectional position A-A in FIG. 1 in step (3) of the construction method according to the present invention;
FIG. 5 is a schematic structural view of step (4) in the construction method according to the present invention;
FIG. 6 is a schematic structural view of step (5) in the construction method according to the present invention;
FIG. 7 is a schematic structural view showing a cross-sectional position A-A in FIG. 1 at step (6) in the construction method according to the present invention;
fig. 8 is a schematic view of a lattice column diagonal bracing reinforcing structure in the construction method of the present invention.
1-underground diaphragm wall; 111-bracing stress monitoring points; 112-unearthed hole; 113-heavy lanes; 114-traffic flow lines; 2-a muck truck; 3-an excavator; 4-lattice columns; 5-concrete tank truck; 6-a ground pump; 7-B0 lower B2 plate ramp; 8-long arm excavator; 9-steel diagonal bracing; 10-a base plate; 101-B0 board; 102-B2 board; 103-B3 board; 104-B1 board.
Detailed Description
The technical solutions of the present invention are described in detail below with reference to the drawings and the embodiments, but the present invention is not limited to the scope of the embodiments. The invention provides a double-deck trestle type top construction technology aiming at the problems in the prior art, and aims to solve the problems that in the prior art, because a roof hole is limited, a top-down construction method is lower in unearthing efficiency than a forward construction method, and because a large amount of mechanical equipment and a material yard are invested in an onsite traffic environment due to the fact that a top-down construction method and an underground structure are constructed simultaneously, the onsite earth excavation is poor in efficiency.
The invention provides a double-deck trestle type reverse construction method construction process, which comprises a double-deck trestle formed by structural plates, a containment stress monitoring system and a traffic management system.
In some embodiments, the construction method of the double-layer trestle formed by the structural plates at least comprises the following steps:
step (1): excavating a first layer of earthwork to an elevation below the bottom of the B0 board, pouring a cushion layer, erecting a formwork support, constructing the B0 board, reserving a soil taking hole, after the construction of the B0 board is completed, driving an excavator to the side of the soil taking hole of the B0 board, and enabling an earthwork vehicle to pass through the B0 board; step (2): excavating a second layer of earthwork to the elevation below the B2 plate, transporting the earthwork outside through an excavated hole of the B0 plate, pouring a cushion layer, building a formwork support, constructing slopes of the B2 plate and the B2 plate below the B0, and reinforcing a lattice column in the range of a heavy roadway between the B0 plate and the B2 plate; and (3): after the construction of the B2 plate is completed, the excavator drives to the B2 plate soil taking wharf to take soil, the earth moving vehicles pass through the B0 plate and the B2 plate, and the B0 plate is used as a material yard and a large mechanical equipment parking yard.
In some embodiments, the construction method for forming the double-layer trestle by the structural plate further comprises the following steps: and (4): excavating the third layer of earthwork to the elevation below the B3 board, transporting the earthwork outside through the unearthed openings of the B0 and B2 boards, pouring a cushion layer, erecting a formwork support and constructing the B3 board; and (5): and excavating the earthwork of the fourth layer to the elevation of the bottom surface of the foundation pit, vertically transporting the earthwork through the excavated openings of the B0, B2 and B3 boards, pouring a cushion layer, binding a bottom plate reinforcing steel bar, and constructing the bottom plate of the basement.
In some preferred embodiments, the construction method of the structural slab to form the double-deck trestle further comprises: and (6): dismantling the slope ramp of the B2 plate below the B0 plate, building a formwork support on the B2 plate, constructing the B1 plate structure, and stopping using the heavy lane on the B2 plate; and (7): and (4) sequentially manufacturing a structure plate and a B1 plate structure plate reserved in the range of the unearthed hole of the construction, and integrally finishing the basement.
In some preferred embodiments, the construction method of the double-layer trestle formed by the structural plates at least comprises the following steps:
step (1): excavating the first layer of earthwork to the elevation of 2.5m below the bottom of the B0 board, pouring a cushion layer, erecting a formwork support, constructing the B0 board, uniformly reserving a soil taking hole, after the construction of the B0 board is finished, driving an excavator to the side of the soil taking hole of the B0 board, and allowing an earthwork vehicle to pass through the B0 board;
step (2): excavating the second layer of earthwork to the elevation 2.5m below the B2 plate, transporting the earthwork outside through the hole of the B0 plate, pouring a cushion layer and erecting a formwork support, constructing slopes of the B2 plate and the B2 plate under the B0, and reinforcing a lattice column in the range of a heavy lane between the B0 plate and the B2 plate;
and (3): after the construction of the B2 plate is completed, the excavator drives to the B2 plate soil taking wharf to take soil, the earth moving vehicles pass through the B0 plate and the B2 plate, and the B0 plate is used as a material yard and a large mechanical equipment parking yard.
And (4): excavating the third layer of earthwork to the elevation of 2.5m below the B3 board, transporting the earthwork out of the soil outlet of the B0 board and the B2 board, pouring a cushion layer, erecting a formwork support and constructing a B3 board;
and (5): and excavating the earthwork of the fourth layer to the elevation of the bottom surface of the foundation pit, vertically transporting the earthwork through the excavated openings of the B0, B2 and B3 boards, pouring a cushion layer, binding a bottom plate reinforcing steel bar, and constructing the bottom plate of the basement.
And (6): dismantling the slope ramp of the B2 plate below the B0 plate, building a formwork support on the B2 plate, constructing the B1 plate structure, and stopping using the heavy lane on the B2 plate;
and (7): and (4) sequentially manufacturing a structure plate and a B1 plate structure plate reserved in the range of the unearthed hole of the construction, and integrally finishing the basement.
In some embodiments, the B0 board has several unearthed holes 112 distributed on a small and dense basis.
In some embodiments, the concrete diagonal bracing in the unearthed opening 112 of the B0 slab buries diagonal bracing stress monitoring points 111.
In some embodiments, the B0 board has several heavy lanes 113 disposed thereon; and traffic flow lines 114 are drawn among the multiple heavy lanes 113 according to the principle of a one-way multi-loop line to guide traffic.
In some embodiments, the formwork support in step (1), the formwork support in step (2), the formwork support in step (4), and the formwork support in step (6) all use socket-type disc fastener tool scaffolds.
In some embodiments, the slope of the B2 plate ramp under the B0 plate is 1: (5-10), the width is integral multiple of the space between the lattice columns; concrete anti-collision guardrails are required to be arranged on two sides of the ramp.
In some preferred embodiments, the slope of the B2 plate ramp under the B0 plate is 1: 8, taking the integral multiple of the space between the lattice columns as the width; concrete anti-collision guardrails with the height of 50cm are required to be arranged on two sides of the slope way.
In some embodiments, in the step (2), the lattice column is reinforced by cross bracing of the steel sections, and each span of the steel sections is reinforced in the lane direction within the range of the heavy vehicle lane.
In some embodiments, in the step (3), the size of the earth taking wharf is required to meet the space requirement of the earth taking and loading operation of the excavator, and is determined by simulating the construction process through the BIM technology.
In some embodiments, the B1 plate structure is constructed by a forward construction method after the floor construction is completed, so that the height between the B0 and the B2 plate meets the requirement of the working space of the conventional mechanical equipment.
In some embodiments, the traffic flow lines of the construction vehicles on the B0 plates and the B2 plates are all one-way circular lines, and the traffic flow driving directions of the overlapped parts of the different circular lines are the same.
In some embodiments, the containment stress monitoring system comprises: monitoring vertical stress of the lattice column and monitoring axial stress of a force transfer beam at an unearthed opening.
In some embodiments, the lattice column vertical stress monitoring controls the placement of B0 panel yards and the accumulation of heavy roadway vehicles according to monitored data; and monitoring the axial stress of the unearthed tunnel entrance force transfer beam, and evaluating the safety of the enclosure system according to monitoring data.
In some embodiments, the traffic management system includes traffic signal management and people-vehicle separation management.
In some embodiments, the traffic signal management requires that a traffic guide board, a zebra crossing and a traffic signal lamp are arranged at the road junctions of the B0 board and the B2 board, and a guide line is drawn for each lane; and the man-vehicle flow distribution management requires that a rigid isolation belt is erected between a sidewalk and a roadway by using a shaped fence.
The double-layer trestle type reverse construction method construction process can be applied to all reverse construction projects with more than four layers.
The experimental methods without specifying specific conditions in the following examples were selected according to the conventional methods and conditions, or according to the commercial instructions. The reagents and starting materials used in the present invention are commercially available.
Example 1
A double-layer trestle type reverse construction method construction process comprises a double-layer trestle formed by structural plates, an enclosure stress monitoring system and a traffic management system. An example of the technique is as follows: hangzhou XiaoA three-phase project traffic center project of a mountain airport, wherein the single-layer area of a foundation pit in a C1 area is 4.1 ten thousand meters2And 4 layers of underground structures with the excavation depth of 18.9m are constructed by adopting a semi-reverse construction method. The double-layer trestle type inverse construction technology is adopted in the foundation pit construction stage.
The construction method for forming the double-layer trestle by the structural plates at least comprises the following steps: step (1): excavating a first layer of earthwork to an elevation below the bottom of the B0 board, pouring a cushion layer, erecting a formwork support, constructing the B0 board, uniformly reserving soil taking holes, after the construction of the B0 board is finished, driving an excavator to the side of the soil taking hole of the B0 board, and allowing an earthwork vehicle to pass through the B0 board; step (2): excavating a second layer of earthwork to the elevation below the B2 plate, transporting the earthwork outside through an excavated hole of the B0 plate, pouring a cushion layer, building a formwork support, constructing slopes of the B2 plate and the B2 plate below the B0, and reinforcing a lattice column in the range of a heavy roadway between the B0 plate and the B2 plate; and (3): after the construction of the B2 plate is completed, the excavator drives to the B2 plate soil taking wharf to take soil, the earth moving vehicles pass through the B0 plate and the B2 plate, and the B0 plate is used as a material yard and a large mechanical equipment parking yard. And (4): excavating the third layer of earthwork to the elevation of 2.5m below the B3 board, transporting the earthwork out of the soil outlet of the B0 board and the B2 board, pouring a cushion layer, erecting a formwork support and constructing a B3 board; and (5): and excavating the earthwork of the fourth layer to the elevation of the bottom surface of the foundation pit, vertically transporting the earthwork through the excavated openings of the B0, B2 and B3 boards, pouring a cushion layer, binding a bottom plate reinforcing steel bar, and constructing the bottom plate of the basement. And (6): dismantling the slope ramp of the B2 plate below the B0 plate, building a formwork support on the B2 plate, constructing the B1 plate structure, and stopping using the heavy lane on the B2 plate; and (7): and (4) sequentially manufacturing a structure plate and a B1 plate structure plate reserved in the range of the unearthed hole of the construction, and integrally finishing the basement. The slope of the B2 plate under the B0 plate is 1: 8, taking the integral multiple of the space between the lattice columns as the width; concrete anti-collision guardrails with the height of 50cm are required to be arranged on two sides of the slope way.
The B1 plate structure is constructed by a forward method, the elevation of the B0 plate surface is-1.1 m, the elevation of the B2 plate surface is-9.1 m, the height difference between the B0 plate and the B2 plate is 8m, the clear height of the space after the height of the beam is deducted is about 7m, and the operation requirement of conventional mechanical equipment is met.
The B0 board is provided with a plurality of soil outlet holes 112 which are distributed according to the principle of small and dense.
And inclined strut stress monitoring points 111 are embedded in concrete inclined struts in unearthed holes 112 on the B0 board.
A plurality of heavy lanes 113 are arranged on the B0 board; and traffic flow lines 114 are drawn among the multiple heavy lanes 113 according to the principle of a one-way multi-loop line to guide traffic.
The above embodiments are preferred embodiments of the present invention, but the present invention is not limited to the above embodiments, and any other changes, modifications, substitutions, combinations, and simplifications which do not depart from the spirit and principle of the present invention should be construed as equivalents thereof, and all such changes, modifications, substitutions, combinations, and simplifications are intended to be included in the scope of the present invention.

Claims (10)

1. A double-layer trestle type reverse construction method construction process is characterized by comprising a double-layer trestle formed by structural plates, a containment stress monitoring system and a traffic management system.
2. The double-deck trestle type reverse construction method construction process of claim 1, wherein the construction method for forming the double-deck trestle by the structural plate at least comprises the following steps:
step (1): excavating a first layer of earthwork to an elevation below the bottom of the B0 board, pouring a cushion layer, erecting a formwork support, constructing the B0 board, reserving a soil taking hole, after the construction of the B0 board is completed, driving an excavator to the side of the soil taking hole of the B0 board, and enabling an earthwork vehicle to pass through the B0 board;
step (2): excavating a second layer of earthwork to the elevation below the B2 plate, transporting the earthwork outside through an excavated hole of the B0 plate, pouring a cushion layer, building a formwork support, constructing slopes of the B2 plate and the B2 plate below the B0, and reinforcing a lattice column in the range of a heavy roadway between the B0 plate and the B2 plate;
and (3): after the construction of the B2 plate is completed, the excavator drives to the B2 plate soil taking wharf to take soil, the earth moving vehicles pass through the B0 plate and the B2 plate, and the B0 plate is used as a main material storage yard and a large mechanical equipment parking yard.
3. The double-deck trestle type reverse construction method construction process of claim 2, wherein the construction method for forming the double-deck trestle by the structural plate further comprises the following steps:
and (4): excavating the third layer of earthwork to the elevation below the B3 board, transporting the earthwork outside through the unearthed openings of the B0 and B2 boards, pouring a cushion layer, erecting a formwork support and constructing the B3 board;
and (5): and excavating the earthwork of the fourth layer to the elevation of the bottom surface of the foundation pit, vertically transporting the earthwork through the excavated openings of the B0, B2 and B3 boards, pouring a cushion layer, binding a bottom plate reinforcing steel bar, and constructing the bottom plate of the basement.
4. The double-layer trestle type reverse construction method construction process of claim 2 or 3, wherein the construction method for forming the double-layer trestle by the structural plates further comprises the following steps:
and (6): dismantling the slope ramp of the B2 plate below the B0 plate, building a formwork support on the B2 plate, constructing the B1 plate structure, and stopping using the heavy lane on the B2 plate;
and (7): and (4) sequentially manufacturing a structure plate and a B1 plate structure plate reserved in the range of the unearthed hole of the construction, and integrally finishing the basement.
5. The double-deck trestle type reverse construction method construction process of claim 4, wherein the formwork support in the step (1), the formwork support in the step (2), the formwork support in the step (4) and the formwork support in the step (6) all adopt socket-type disc buckle type tool scaffolds.
6. The double-deck trestle type reverse construction method construction process of claim 2, wherein the slope of the slope way of the B2 plate under the B0 plate is 1: (5-10), the width is integral multiple of the space between the lattice columns; concrete anti-collision guardrails are required to be arranged on two sides of the slope of the B2 plate below the B0 plate.
7. The double-deck trestle type reverse construction method construction process according to claim 2, wherein in the step (2), the latticed column is reinforced in a mode of cross reinforcement of steel inclined struts, and each span of the steel inclined struts is reinforced in the lane direction within the range of a heavy vehicle lane.
8. The double-deck trestle type reverse construction method construction process of claim 4, wherein the B1 board structure is constructed by a forward construction method after the bottom board construction is completed, so that the height between the B0 and B2 boards meets the requirement of the working space of conventional mechanical equipment.
9. The double-deck trestle type reverse construction method construction process of claim 4, wherein the traffic flow lines of the construction vehicles on the B0 board and the B2 board are all unidirectional circular lines, and the traffic flow traveling directions of the overlapped parts of the different circular lines are the same.
10. The double-deck trestle type reverse construction method construction process of claim 2, wherein the containment stress monitoring system comprises: monitoring vertical stress of the lattice column and monitoring axial stress of a force transfer beam at an unearthed opening.
CN202110141104.4A 2021-02-01 2021-02-01 Double-deck trestle type reverse construction method Pending CN112796325A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110141104.4A CN112796325A (en) 2021-02-01 2021-02-01 Double-deck trestle type reverse construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110141104.4A CN112796325A (en) 2021-02-01 2021-02-01 Double-deck trestle type reverse construction method

Publications (1)

Publication Number Publication Date
CN112796325A true CN112796325A (en) 2021-05-14

Family

ID=75813583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110141104.4A Pending CN112796325A (en) 2021-02-01 2021-02-01 Double-deck trestle type reverse construction method

Country Status (1)

Country Link
CN (1) CN112796325A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115405277A (en) * 2022-09-27 2022-11-29 中海石油(中国)有限公司 Hot landing stage is annotated in removal based on return bend steam line

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115405277A (en) * 2022-09-27 2022-11-29 中海石油(中国)有限公司 Hot landing stage is annotated in removal based on return bend steam line
CN115405277B (en) * 2022-09-27 2024-02-06 中海石油(中国)有限公司 Movable heat injection trestle based on bent pipe steam pipeline

Similar Documents

Publication Publication Date Title
CN105862910B (en) A kind of the inverse of assembled stereoscopic underground garage makees formula method of construction
CN107558494B (en) Underground station structure for rail transit and construction method thereof
CN105236275B (en) Soil lifting system and soil lifting method for building deep foundation pit construction in narrow zone
WO2022016720A1 (en) Temporary passage construction method employing support structure in deep foundation pit
CN104594204B (en) Urban light rail viaduct mountain type U beam Construction Supporting System and construction method
Paul et al. Comparative study of construction technologies for underground metro stations in India
CN110578339A (en) construction method of shaft type underground stereo garage
CN105064711A (en) Method for constructing underground garage between residential buildings
CN112796325A (en) Double-deck trestle type reverse construction method
CN214614086U (en) Double-deck landing stage formula reverse construction method foundation ditch enclosure system
CN108589568B (en) Rapid construction method for shed tunnel T-shaped beam crossing business line in narrow space
CN204475184U (en) Urban light rail viaduct mountain type U beam Construction Supporting System
CN105986830B (en) The tunneling method of construction of roadside strip underground garage
CN209669718U (en) A kind of existing hangar tunnel combination stone cut off wall structure of rockfall protection
CN109778700B (en) Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road
CN205061417U (en) What narrow regional building deep basal pit was under construction puies forward soil series all
CN111608429B (en) Assembled ultra-deep foundation pit ramp system and construction method thereof
CN210797573U (en) Underground structure internal transportation system based on under-board sliding groove
CN111188275B (en) Method for quickly erecting steel-concrete combined temporary bridge spanning existing tunnel U-shaped groove
CN112177042A (en) Rail transit station construction method without affecting ground traffic
CN113389218A (en) Retaining wall structure for entrance and exit of road bridge and construction method thereof
CN113293766A (en) Comprehensive earthwork excavation method for large-scale cover excavation top-down T-shaped transfer subway station
CN116623714A (en) Reverse construction method for spring layer of basement structure
CN219343473U (en) Cross-street corridor mounting structure
CN104912200B (en) Building method of underground shallow layer fully automatic parking garage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination