JPS6360392A - Method of constructing pressure conduit tunnel made of precast - Google Patents
Method of constructing pressure conduit tunnel made of precastInfo
- Publication number
- JPS6360392A JPS6360392A JP20017486A JP20017486A JPS6360392A JP S6360392 A JPS6360392 A JP S6360392A JP 20017486 A JP20017486 A JP 20017486A JP 20017486 A JP20017486 A JP 20017486A JP S6360392 A JPS6360392 A JP S6360392A
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- side plates
- bottom plate
- arch
- prestress
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 28
- 239000010959 steel Substances 0.000 claims description 28
- 239000000463 material Substances 0.000 claims description 26
- 238000005304 joining Methods 0.000 claims description 4
- 238000010276 construction Methods 0.000 claims description 3
- 239000011440 grout Substances 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 238000005266 casting Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000010248 power generation Methods 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
(産業上の利用分野)
この発明は、水力発電の導水路として用いられるプレキ
ャスト製圧力水路トンネルの構築方法に関するもので、
強度向上のためにプレストレスが導入できるように、又
、現場打ちの不利を解消するためにプレキャストされて
小さい部材に分割造型されているこれらの部材を、地山
の狭い坑道内で効率良くトンネルに組立てできるように
工夫したものである。[Detailed Description of the Invention] (Industrial Application Field) This invention relates to a method for constructing a precast pressure waterway tunnel used as a headrace for hydroelectric power generation.
These parts, which are precast and divided into small parts in order to introduce prestress to improve strength and eliminate the disadvantages of casting in place, can be efficiently tunneled in narrow tunnels in the ground. It has been devised so that it can be assembled easily.
(従来の技術)
従来の圧力トンネルは、地山の坑道内に型枠を組込んで
現場打ち工法によって造型するものであって、掘削断面
積が大きくなり、土圧と内圧によってひび割れが発生し
易く、長期の養生を要すると云う種々の問題がある。(Conventional technology) Conventional pressure tunnels are built using a cast-in-place method by incorporating formwork into a tunnel in the ground, which increases the cross-sectional area of the excavation and causes cracks to occur due to earth pressure and internal pressure. There are various problems that are easy to deal with and require long-term curing.
かかる従来の問題を解決するために、底板と左右側板と
に2分割又は3分割された部材を、プレキャスト方法に
よって造型し、坑道内にて組立て、又、プレストレスを
導入できるようにすることが最も望ましいのであるが、
狭い坑道内で能率良く組立てるには、特別な工夫を必要
としている。In order to solve such conventional problems, it is possible to mold the bottom plate and the left and right side plates into two or three parts using a precast method, and to assemble them in the mine shaft and to introduce prestress. Most desirable,
Special ingenuity is required to efficiently assemble it in a narrow tunnel.
(発明が解決しようとする問題点)
この発明は、各部材を能率良く組立てることができると
共に、組立て動作と同時に所定のプレストレスが導入さ
れ、又、坑道の掘削断面積が小さくできるように工夫さ
れたものである。(Problems to be Solved by the Invention) This invention enables efficient assembly of each member, introduces a predetermined prestress at the same time as the assembly operation, and is devised to reduce the cross-sectional area of the tunnel excavated. It is what was done.
(問題点を解決するための手段)
各部材を能率良く組立てるなどのためのこの発明の構成
は、
予め造型された底板3とアーチ状の左右側板6とを結合
し、この底板3と左右側板6の多数組を長手方向に合接
してトンネル26を構成する圧力水路トンネルの構築方
法において、左右側板6の左右の基部5を底板3の左右
部2に接合し、アーチ状に沿い左右側板6内及び底板3
内に配設される周方向のpc鋼材15を緊張することに
よってで左右側板6と底板3が互いに結合されてトンネ
ルユニット26aが形成されると共に、アーチ状方向に
プレストレスが導入され、地山の坑道27内に上記トン
ネルユニッ)26aを搬入してトンネルユニッ)26a
の多数を長手方向に据え付け、上記複数個毎に長手方向
のPC鋼材15を緊張することによって長手方向にプレ
ストレスが導入されると共に、トンネル26が形成され
ることを特徴とするプレキャスト製圧力水路トンネルの
製造方法である。(Means for Solving the Problems) The structure of the present invention for efficiently assembling each member is as follows: A pre-shaped bottom plate 3 and arch-shaped left and right side plates 6 are combined, and this bottom plate 3 and left and right side plates are combined. In the method of constructing a pressure waterway tunnel in which a large number of sets of 6 are joined in the longitudinal direction to form the tunnel 26, the left and right bases 5 of the left and right side plates 6 are joined to the left and right parts 2 of the bottom plate 3, and the left and right side plates 6 are connected along an arch shape. Inner and bottom plate 3
By tensioning the PC steel material 15 disposed in the circumferential direction, the left and right side plates 6 and the bottom plate 3 are connected to each other to form a tunnel unit 26a, and prestress is introduced in the arch-like direction, so that the ground The tunnel unit) 26a is carried into the tunnel 27 of the tunnel unit) 26a.
A precast pressure waterway characterized in that a plurality of prestresses are installed in the longitudinal direction, and prestress is introduced in the longitudinal direction by tensioning the longitudinal prestressing steel material 15 for each of the plurality of pieces, and a tunnel 26 is formed. This is a tunnel manufacturing method.
(作 用)
左右側板6の左右の基部5を底板3の左右部2に接合し
、周方向のPC鋼材15を緊張すると、底板3と左右側
板6とが大きい圧縮力で強固に結合されてアーチ状のト
ンネルユニット26aが形成されると共に、このアーチ
状に沿うプレストレスが導入されることになる。(Function) When the left and right bases 5 of the left and right side plates 6 are joined to the left and right parts 2 of the bottom plate 3 and the circumferential PC steel members 15 are tensioned, the bottom plate 3 and the left and right side plates 6 are firmly connected with a large compressive force. An arch-shaped tunnel unit 26a is formed, and a prestress along the arch shape is introduced.
このようにして形成されたトンネルユニット26aを数
個を、順次坑道27内に搬入し、pc鋼材15をこれら
複数個毎に緊張することによって長手方向のプレストレ
スが導入され、トンネル26に形成されるので、坑道2
7は、トンネルユニット26aを搬入できるていどの狭
い断面積にて足りることになる。Several tunnel units 26a formed in this manner are sequentially carried into the tunnel 27, and by tensioning the PC steel material 15 for each of these plurality, prestress in the longitudinal direction is introduced, and the tunnel 26 is formed. Therefore, mine shaft 2
7, any narrow cross-sectional area that can carry the tunnel unit 26a is sufficient.
このように、左右側板6と底板3の結合作業及び、プレ
ストレス導入が簡易に行われるものである。In this way, the work of joining the left and right side plates 6 and the bottom plate 3 and the introduction of prestress are easily performed.
(実施例) 次に、この発明の一実施例を図にもとづいて説明する。(Example) Next, one embodiment of the present invention will be described based on the drawings.
第1図に正面を、第2図に左側面を、第3図に右側面を
、第4図に平面を、夫々示したように、平な底部lの左
右部2.2をこの底部1から立上らせている底板3及び
、その上部4,4を互に合接することによってアーチ状
となり、その基部5゜5が底板3の上記左右部2,2に
接合できるように形成されている左右側板6,6を、プ
レキャスト方式によって造型する。As shown in the front view in Fig. 1, the left side in Fig. 2, the right side in Fig. 3, and the plan view in Fig. 4, the left and right parts 2.2 of the flat bottom l are The bottom plate 3 stands up from the base plate 3 and its upper parts 4, 4 are joined together to form an arch shape, and its base 5° 5 is formed so as to be joined to the left and right parts 2, 2 of the bottom plate 3. The left and right side plates 6, 6 are molded by a precasting method.
底板3及び左右側板6,6は、共に運搬などの取扱いの
便宜のため、長さを短かく造型する。The bottom plate 3 and the left and right side plates 6, 6 are both shaped to have short lengths for ease of handling such as transportation.
第5図に示している斜視図によって明らかなように、左
右側板6.6の夫々の上部4,4及び一つの左右側板6
をアーチ状に沿って貫通するシース管7,7及び8,8
を、一方のシース管7,7は、左右側板6の長手方向中
心附近に、又、他のシース管8.8は、長手方向外側に
、夫々、位置するように配設し、上部4の附近にはシー
ス管9を、基部5にもシース管10を、共に左右側板6
の長手方向に沿って貫設している。As is clear from the perspective view shown in FIG.
Sheath tubes 7, 7 and 8, 8 that penetrate along the arch shape
One of the sheathed pipes 7, 7 is arranged near the longitudinal center of the left and right side plates 6, and the other sheathed pipe 8.8 is arranged on the outside in the longitudinal direction, respectively. There is a sheath tube 9 nearby, a sheath tube 10 at the base 5, and both left and right side plates 6.
It runs through the longitudinal direction.
底板3の左右部2には、基部5にこの左右部2が接合さ
れる状態で左右側板6の上記シース管7又は8に夫々連
通できる位置にシース管11.11と12.12を、夫
々設け、左右部2を長手方向に貫通するシース管13及
び、底部1を左右方向に貫通するシース管14.14を
、夫々、設けている。Sheath tubes 11.11 and 12.12 are respectively provided on the left and right portions 2 of the bottom plate 3 at positions where they can communicate with the sheath tubes 7 and 8 of the left and right side plates 6, respectively, with the left and right portions 2 being joined to the base 5. A sheath tube 13 and a sheath tube 14 and 14 are provided, respectively, passing through the left and right parts 2 in the longitudinal direction, and sheath pipes 14 and 14 passing through the bottom part 1 in the left and right direction.
pc鋼材15を定着するための定着板16を、底部1の
隅部外側とに設けている例えば凹状の定着座17. 1
?、 18. 18 及び19に夫々固設し、左右
側板6の上部4.4の外側部にも、例えば凹状の定着板
20と21.21を夫々設け、左右側板6の数個のうち
の1個に、凹状の定着座22と23を夫々、内側部に設
け、底板3の数個のうちの1個に、凹状の定着座24を
左右部2の内側部に設けている。For example, a concave fixing seat 17 is provided with a fixing plate 16 for fixing the PC steel material 15 on the outer corner of the bottom part 1. 1
? , 18. 18 and 19, respectively, and for example, concave fixing plates 20 and 21.21 are also provided on the outer side of the upper part 4.4 of the left and right side plates 6, respectively, and one of the several pieces of the left and right side plates 6 is provided with fixing plates 20 and 21.21, respectively. Concave fixing seats 22 and 23 are provided on the inner side, respectively, and a concave fixing seat 24 is provided on one of several pieces of the bottom plate 3 on the inner side of the left and right parts 2.
このようにしてプレキャストされている左右側板6.6
と底板3を、第7図と第8図に例示したように、上部4
.4を互いに合接し、基部5を底板3の左右部2に接合
し、シース管7とシース管11に周方向のpc鋼材15
を挿通して定着座20の定着板16にこのPC鋼材の上
端を定着し、又、シース管8とシース管12に周方向の
PC鋼材15を夫々、挿通して定着座21の定着板16
にこのpcm材15の上端を定着し、緊張装置25を用
いて底部1の側からこれらのPC鋼材15を夫々緊張し
て、底板3の定着座18と19の定着板16に、上記4
本の周方向のPC鋼材15を定着すれば、左右側板6.
6が上記4.4にて互に合接し、左右側板6,6と底板
3が基部5と左右部2にて互に接合されて1体のアーチ
状のトンネルユニット26aに形成されると共に、この
アーチ状に沿ってプレストレスがトンネルユニット26
aに導入される。多数のトンネルユニット26aを前後
方向に互いに合接し、シース管9.10.13に挿通し
たpc鋼材15を緊張することによってトンネルユニッ
ト26aが互いに結合されて所望の長さのトンネル26
に構成されると共に、このトンネル26に、長手方向の
プレストレスが導入される。Left and right side plates precast in this way 6.6
and the bottom plate 3, as illustrated in FIGS. 7 and 8, the upper part 4
.. 4 to each other, the base 5 to the left and right parts 2 of the bottom plate 3, and the PC steel material 15 in the circumferential direction to the sheath pipe 7 and the sheath pipe 11.
The upper end of this PC steel material is fixed to the fixing plate 16 of the fixing seat 20 by inserting the PC steel material 15 in the circumferential direction through the sheath pipe 8 and the sheath pipe 12 respectively.
Fix the upper end of this PCM material 15 to the fixing plates 16 of the fixing seats 18 and 19 of the bottom plate 3 by tensioning these PC steel materials 15 from the side of the bottom part 1 using the tensioning device 25.
Once the PC steel material 15 in the circumferential direction of the book is fixed, the left and right side plates 6.
6 are joined to each other at 4.4 above, and the left and right side plates 6, 6 and the bottom plate 3 are joined to each other at the base 5 and the left and right parts 2 to form one arch-shaped tunnel unit 26a, Prestress is applied to the tunnel unit 26 along this arch shape.
introduced into a. A large number of tunnel units 26a are joined to each other in the front-rear direction, and the tunnel units 26a are joined to each other by tensioning the PC steel material 15 inserted into the sheath pipe 9, 10, 13, and a tunnel 26 of a desired length is created.
, and a longitudinal prestress is introduced into this tunnel 26.
次に、トンネルの構築手順を説明する。Next, the tunnel construction procedure will be explained.
地山に坑道27を掘削し、坑道27の外にて第7図のよ
うに、組立台Gを用いて、左右側板6の基部5を側板ガ
イードGlにさし込み、次に底板3の底部1を、底板ガ
イドG2にさし込むと左右側板6の基部5が底板3の左
右部2に合接する位置となる。A tunnel 27 is excavated in the ground, and outside the tunnel 27, as shown in FIG. 1 is inserted into the bottom plate guide G2, the base portions 5 of the left and right side plates 6 will be in positions where they join the left and right portions 2 of the bottom plate 3.
シース管7と11に、又シース管8と12に、夫々周方
向のPC鋼材15を挿通し、定着座20及び21にこれ
らのPC鋼材15の上端を定着し、第8図のように底板
3の左右部2の定着座18からこれらのPC鋼材15の
下端部を引き出し、底板3に当接した緊張装置25を用
いてこの下端部側からPC鋼材15を緊張すると、周方
向にプレストレスが導入されると共に、左右側板6,6
と底板3が大きい圧縮力にて互いに強固に結合されてア
ーチ状のトンネルユニット26aが形成される。The PC steel members 15 are inserted in the circumferential direction into the sheath tubes 7 and 11 and the sheath tubes 8 and 12, respectively, and the upper ends of these PC steel members 15 are fixed to the fixing seats 20 and 21, and the bottom plate is attached as shown in FIG. When the lower ends of these PC steel materials 15 are pulled out from the fixing seats 18 on the left and right portions 2 of 3, and the tension device 25 in contact with the bottom plate 3 is used to tension the PC steel materials 15 from the lower end side, prestress is created in the circumferential direction. is introduced, and the left and right side plates 6, 6
and the bottom plate 3 are firmly connected to each other with a large compressive force to form an arch-shaped tunnel unit 26a.
次にこれらのトンネルユニット26aを、例えば5個、
シース管9,10.13に挿通したPC鋼材15を用い
て仮締めし、この一体となった5個を第9図のように例
えばジヤツキ36のある台車28を用いて坑道27内に
搬入し、上記仮締めを解除して第10図のようにフォー
クリフトの如き持上移動機29を用いてトンネルユニッ
ト26aの内側上部を持上げ、据え付けの終った奥側の
トンネルユニッ)26a内をこの持上移動機29が移動
して、上記の持上げられたトンネルユニット26aを、
所定位置におろして据え付けを行い、ジヤツキ36にて
台車28上のトンネルユニット26aを持上移動機29
に向って押し出し、再び持上移動機29による上記の持
上げを行い、このようにしてトンネルユニット26aを
坑道27内に据え付けする。このようにして据え付けの
終った例えば5個毎に、長手方向のシース管9.10゜
13へPCfJ材15を夫々挿通し、これらのpc鋼材
15を緊張することになる。Next, for example, five of these tunnel units 26a,
The PC steel material 15 inserted into the sheath pipes 9, 10, and 13 is temporarily tightened, and the five integrated pieces are carried into the tunnel 27 using, for example, a cart 28 with jacks 36, as shown in FIG. , release the temporary tightening and lift the inner upper part of the tunnel unit 26a using a lifting machine 29 such as a forklift as shown in FIG. The mobile device 29 moves and lifts the tunnel unit 26a,
The tunnel unit 26a on the trolley 28 is lifted by the jack 36 and moved to the moving machine 29.
The tunnel unit 26a is pushed out toward the tunnel 26a and lifted again by the lifting and moving machine 29, and the tunnel unit 26a is installed in the tunnel 27 in this way. For example, for every five pieces that have been installed in this way, the PCfJ material 15 is inserted into the sheath pipe 9.10° 13 in the longitudinal direction, and these PC steel materials 15 are tensioned.
この緊張作業の手順を、第13図に拡大して示したシー
ス管9と定着座22について例示して説明すると、すで
に据え付けが終って定着済みの長手方向のPC鋼材15
(同図の左側)のねじ部15aに、カップラ30を介
して未緊張側の長手方向のPCN材ユ(同図の右側)を
接続し、第11図に示すように、定着座22.23の無
い1個のトンネルユニット26aを、上記5個のトンネ
ルユニット26aの最外側に接合して短いPC鋼材15
を同図の右側のpcm材15に、カップラ30を介して
連結し、緊張装置25を用いてこれらのPC鋼材15.
15を緊張し、アンカナツト31をねじ部15aにねじ
込んでPC鋼材15を定着すると、上記5個のトンネル
ユニッ) 26 aの延長継ぎ足しが終わると共に長手
方向にプレストレスが導入される。The procedure for this tensioning work will be explained by exemplifying the sheath pipe 9 and the fixing seat 22 shown in an enlarged scale in FIG. 13.
Connect the unstressed longitudinal PCN material (on the right side in the figure) to the threaded portion 15a (on the left side in the figure) via the coupler 30, and as shown in FIG. One tunnel unit 26a without a hole is joined to the outermost side of the five tunnel units 26a to form a short PC steel member 15.
are connected to the PCM material 15 on the right side of the figure via a coupler 30, and the tension device 25 is used to tighten these PC steel materials 15.
15 is tightened and the anchor nut 31 is screwed into the threaded portion 15a to fix the PC steel material 15, the extension and addition of the five tunnel units 26a is completed and prestress is introduced in the longitudinal direction.
定着が終れば最外側の短かいpc鋼材T丁を抜き取って
再び上述した順序で5個宛トンネルニットツ6aをジヤ
ツキ付台車28で坑道27内に搬入し、フォークリフト
29を用いて据え付け、この搬入された5個と1個のト
ンネルユニット26aに緊張力を与え、この新たな5個
のトンネルユニット26aの結合を行い、このようにし
て例えば5個宛、トンネルユニット26aを継足してい
くことになる。When the fixing is completed, the outermost short PC steel T-pieces are removed, and the five tunnel knits 6a are carried into the tunnel 27 using the jacked cart 28 again in the above-mentioned order, and installed using the forklift 29. A tension force is applied to the five tunnel units 26a that were added and one tunnel unit 26a, and these five new tunnel units 26a are combined, and in this way, for example, five tunnel units 26a are added. Become.
所定の長さのトンネル26を形成し終え、シース管9.
10.13にグラウトを注入し、第12図のように底板
3及び左右側板6の夫々のグラウト注入孔32,33.
34を用いてトンネル26の内部からグラウトを、坑道
27とトンネル26との間隙に充填する。After forming the tunnel 26 of a predetermined length, the sheath tube 9.
10. Inject grout into the grout holes 32, 33.13 in the bottom plate 3 and left and right side plates 6, respectively, as shown in FIG.
34 is used to fill the gap between the shaft 27 and the tunnel 26 with grout from inside the tunnel 26.
上述した左右側板6,6は、左右部々のものがその上部
4,4を互いに合接することによってアーチ状に形成さ
れるものであるが、第14図に正面図を、第15図に側
面図を、夫々例示したように左右側板■として、非分割
で一体に造型したものを用いてもこの発明は適用できる
ものであって、左右側板■のアーチ状方向に配置される
シース管Tは、左右部2のシース管11.11に連通ず
る単純な形となっている。The left and right side plates 6, 6 mentioned above are formed into an arch shape by joining the upper parts 4, 4 of the left and right parts to each other, and FIG. 14 shows a front view, and FIG. 15 shows a side view. As illustrated in the figure, the present invention can be applied even if the left and right side plates (■) are integrally molded without being divided, and the sheath tube T arranged in the arched direction of the left and right side plates (■) is , it has a simple shape that communicates with the sheath tubes 11.11 of the left and right parts 2.
PC鋼材15は、上述の如きシース管に挿通ずる代りに
、アンボンドPC鋼材を用いてもよい。The PC steel material 15 may be an unbonded PC steel material instead of being inserted into the sheath tube as described above.
夫々の定着座17,18.・・・には、モルタルを充填
してその凹部を平滑にしている。Respective anchorage seats 17, 18. ... is filled with mortar to smooth out the recesses.
(発明の効果)
この発明に係るプレキャスト製圧力水路トンネルの構築
方法は上述のように構成したものであって、左右側板6
と底板3をまず互い結合してトンネルユニット26aに
構成し、このトンネルユニッ)26aを坑道27内に順
次、搬入してトンネルニット26aを前後方向に合接す
ることによってトンネル26に構築するものであるので
、坑道27内においては、搬入及びトンオルユニット2
6a相互の合接と長手方向のPC鋼材15の緊張作業の
如く、トンネルユニット26aのアーチ形状内から外へ
は殆んどはみ出さないで行われ、坑道27は、トンネル
ユニット26aを搬入するのに必要なていどの狭い断面
積を掘削しておけば良く、坑道27の掘削コストは減少
することになる。(Effects of the Invention) The method for constructing a precast pressure waterway tunnel according to the present invention is configured as described above, and the left and right side plates 6
and the bottom plate 3 are first connected to each other to form a tunnel unit 26a, and the tunnel units 26a are sequentially carried into the tunnel 27 and the tunnel knits 26a are joined in the front-rear direction to construct the tunnel 26. Therefore, in the tunnel 27, the loading and tonnage unit 2
6a mutually joining and tensioning the longitudinal prestressing steel members 15, which are performed without protruding from inside the arch shape of the tunnel unit 26a, and the tunnel 27 is used to transport the tunnel unit 26a. It is only necessary to excavate as narrow a cross-sectional area as necessary for the tunnel 27, and the cost of excavating the tunnel 27 is reduced.
坑道27内に搬入されたトンネルユニット26aは、複
数個毎に、長手方向のPC@材15を緊張するので、こ
れらのトンネルユニット26aには大きい圧縮力が作用
して互いに強固に結合され、充分に大きいプレストレス
が導入される。The tunnel units 26a carried into the tunnel 27 tension the PC@ material 15 in the longitudinal direction, so that a large compressive force acts on these tunnel units 26a and they are firmly connected to each other and are sufficiently A large prestress is introduced.
トンネルユニッ)26aの内側上部を持上移動機29に
よって持上げて坑道27内に搬入を行う方法の発明は、
トンネルユニッ)26aを安定な状態で支持できるるう
え、トンネルユニット26aのアーチ形状内に持上移動
機29が納まる状態で搬入作業が行われるため、坑道2
7の掘削断面を、トンネルユニット26aのアーチ形状
面よりもわづかに大きいていどで足りることになって、
掘削コストの低減に一層有利となった。The invention of a method for lifting the inner upper part of the tunnel unit 26a with a lifting moving machine 29 and carrying it into the tunnel 27 is as follows:
The tunnel unit 26a can be stably supported, and the lifting work is carried out with the lifting machine 29 housed within the arch shape of the tunnel unit 26a.
It is sufficient that the excavation cross section of No. 7 is slightly larger than the arch-shaped surface of the tunnel unit 26a.
This has become even more advantageous in reducing drilling costs.
図はこの発明の実施例を示し、第1図と第14図は夫々
の実施例におるトンネルユニットの正面図、第2図、第
3図、第4図は夫々左側面図、右側面図、平面図であり
、第5図はトンネルの斜視図、第6図は第5図における
縦断面図、第7図、第8図、第9図、第10図、第11
図、第12図はトンネルの組立工程における説明図、第
13図は第11図における要部拡大断面図、第15図は
第14図の右側面図である。
2・・・左右部、3・・・底板、4・・・上部、5・・
・基部、6・・・左右側板、15・・・pci+材、2
6・・・トンネル、26a・・・トンネルユニット、2
7・・・坑道、29・・・持上移動機。The figures show embodiments of the present invention, and FIGS. 1 and 14 are front views of tunnel units in the respective embodiments, and FIGS. 2, 3, and 4 are left and right side views, respectively. , a plan view, FIG. 5 is a perspective view of the tunnel, FIG. 6 is a vertical sectional view of FIG. 5, FIGS. 7, 8, 9, 10, 11.
12 is an explanatory view of the tunnel assembly process, FIG. 13 is an enlarged sectional view of the main part in FIG. 11, and FIG. 15 is a right side view of FIG. 14. 2...Left and right parts, 3...Bottom plate, 4...Top, 5...
・Base, 6...Left and right side plates, 15...PCI+ material, 2
6...Tunnel, 26a...Tunnel unit, 2
7... Mine shaft, 29... Lifting moving machine.
Claims (4)
合し、この底板と左右側板の多数組を長手方向に合接し
てトンネルを構成する圧力水路トンネルの構築方法にお
いて、 左右側板の左右の基部を底板の左右部に接合し、アーチ
状に沿い左右側板内及び底板内に配設される周方向のP
C鋼材を緊張することによって左右側板と底板が互いに
結合されてトンネルユニットが形成されると共に、アー
チ状方向にプレストレスが導入され、 地山の坑道内に上記トンネルユニットを搬入してトンネ
ルユニットの多数を長手方向に据え付け、複数個のトン
ネルユニット毎に長手方向のPC鋼材を緊張することに
よって長手方向にプレストレスが導入されると共に、ト
ンネルが形成されることを特徴とするプレキャスト製圧
力水路トンネルの構築方法。(1) In a pressure waterway tunnel construction method in which a pre-shaped bottom plate and arch-shaped left and right side plates are combined, and multiple sets of the bottom plate and left and right side plates are joined in the longitudinal direction to form a tunnel, the left and right sides of the left and right side plates are The base of the is joined to the left and right parts of the bottom plate, and the circumferential P is arranged in the left and right side plates and in the bottom plate along an arch shape.
By tensioning the C steel material, the left and right side plates and the bottom plate are connected to each other to form a tunnel unit, and prestress is introduced in the arch-shaped direction, and the tunnel unit is carried into the underground tunnel and the tunnel unit is formed. A precast pressure waterway tunnel characterized in that prestress is introduced in the longitudinal direction and a tunnel is formed by installing a large number of units in the longitudinal direction and tensioning the longitudinal prestressing steel material for each of the plurality of tunnel units. How to build.
なるものであることを特徴とする特許請求の範囲第1項
記載のプレキャスト製圧力水路トンネル。(2) The precast pressure waterway tunnel according to claim 1, wherein the left and right side plates are each divided into left and right side plates.
を特徴とする特許請求の範囲第1項記載のプレキャスト
製圧力水路トンネルの構築方法。(3) The method for constructing a precast pressure waterway tunnel according to claim 1, wherein the left and right side plates are formed so that the left and right sides are not divided.
合し、この底板と左右側板の多数を長手方向に合接して
トンネルを構成する圧力水路トンネルの構築方法におい
て、 左右側板の左右の基部を底板の左右部に接合し、アーチ
状に沿い左右側板内及び底板内に配設される周方向のP
C鋼材を緊張することによって左右側板と底板が互いに
結合されてトンネルユニットが形成されると共に、アー
チ状方向にプレストレスが導入され、トンネルユニット
の内側上部を持上げる持上移動機によって地山の坑道内
の所定位置に搬入と据え付けを行い、複数個のトンネル
ユニット毎に長手方向のPC鋼材を緊張することによっ
て長手方向にプレストレスが導入されると共に、トンネ
ルが形成されることを特徴とするプレキャスト製圧力水
路トンネルの構築方法。(4) In a pressure waterway tunnel construction method in which a pre-shaped bottom plate and arch-shaped left and right side plates are combined, and a tunnel is constructed by joining the bottom plate and a large number of the left and right side plates in the longitudinal direction, the left and right sides of the left and right side plates are The base is joined to the left and right parts of the bottom plate, and the circumferential P is arranged along the arch shape inside the left and right side plates and inside the bottom plate.
By tensioning the C steel material, the left and right side plates and the bottom plate are connected to each other to form a tunnel unit. At the same time, prestress is introduced in the arch-shaped direction, and a lifting machine that lifts the inner upper part of the tunnel unit moves the ground. A tunnel is formed by carrying in and installing at a predetermined position in the tunnel, and by tensioning the longitudinal prestressing steel for each of the plurality of tunnel units, a prestress is introduced in the longitudinal direction, and a tunnel is formed. How to build a precast pressure waterway tunnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20017486A JPS6360392A (en) | 1986-08-28 | 1986-08-28 | Method of constructing pressure conduit tunnel made of precast |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20017486A JPS6360392A (en) | 1986-08-28 | 1986-08-28 | Method of constructing pressure conduit tunnel made of precast |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6360392A true JPS6360392A (en) | 1988-03-16 |
Family
ID=16420022
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP20017486A Pending JPS6360392A (en) | 1986-08-28 | 1986-08-28 | Method of constructing pressure conduit tunnel made of precast |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6360392A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013133593A (en) * | 2011-12-26 | 2013-07-08 | Yamax Corp | Arch culvert and assembly construction method thereof |
JP2015045202A (en) * | 2013-08-29 | 2015-03-12 | 株式会社ヤマックス | Arch culvert and manufacturing method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS49104448A (en) * | 1973-02-09 | 1974-10-03 | ||
JPS5429658U (en) * | 1977-07-29 | 1979-02-27 | ||
JPS569598A (en) * | 1979-07-06 | 1981-01-31 | Nippon Rotsukuraapipe Kk | Archhshaped culvert |
JPS587043A (en) * | 1981-07-06 | 1983-01-14 | 株式会社アンド− | Assembling type arch culvert |
-
1986
- 1986-08-28 JP JP20017486A patent/JPS6360392A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS49104448A (en) * | 1973-02-09 | 1974-10-03 | ||
JPS5429658U (en) * | 1977-07-29 | 1979-02-27 | ||
JPS569598A (en) * | 1979-07-06 | 1981-01-31 | Nippon Rotsukuraapipe Kk | Archhshaped culvert |
JPS587043A (en) * | 1981-07-06 | 1983-01-14 | 株式会社アンド− | Assembling type arch culvert |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013133593A (en) * | 2011-12-26 | 2013-07-08 | Yamax Corp | Arch culvert and assembly construction method thereof |
JP2015045202A (en) * | 2013-08-29 | 2015-03-12 | 株式会社ヤマックス | Arch culvert and manufacturing method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100571102B1 (en) | Device of Innovative Prestressed Scaffolding System for Improving Workability | |
KR101099885B1 (en) | Arch structure using concrete block assembly and construction method thereof | |
JP5703159B2 (en) | Precast prestressed concrete beam | |
KR20060112504A (en) | Downward construction system and method for 1-way girder and slab of underground structure | |
KR101478131B1 (en) | Construction Method of Precast Pier | |
JP6715092B2 (en) | Construction method of underground structure | |
KR20120051314A (en) | Precast tunnel structure using corrugated multi plate | |
JP4080621B2 (en) | Large section tunnel and its construction method | |
JPS6360392A (en) | Method of constructing pressure conduit tunnel made of precast | |
CN114658002B (en) | External prestress steel support supporting system and construction method thereof | |
JP6827294B2 (en) | Segment wall and tunnel lining | |
JP3760302B2 (en) | Joint structure of members and construction method of joint between cast-in-place concrete pile and superstructure | |
JPS6367318A (en) | Method for constructing precast pressure-waterway tunnel | |
JPS6360391A (en) | Method of constructing pressure conduit tunnel made of precast | |
JP2009108500A (en) | Precast beam construction method, precast beam, precast beam joint structure, and building | |
JP2008138486A (en) | Reinforcing construction method of pier | |
JP6720761B2 (en) | How to build a ramen structure | |
CN221721684U (en) | Assembled anchor pier suitable for rock slope | |
KR102255360B1 (en) | Prestressed steel pipe structure and non-crackable construction method using the same | |
CN212225244U (en) | Prestressing force reinforcing formula buckled plate tunnel composite support structure | |
JPS6360393A (en) | Pressure conduit tunnel made of precast | |
JPH057357Y2 (en) | ||
CN114457912A (en) | Tie beam assembly, supporting device and tie beam assembly installation method | |
JPH066823B2 (en) | Precast structural members | |
CN117868178A (en) | Semi-prefabricated assembled steel pipe concrete slope anchoring counterforce structure and construction method |