JPS6347466A - Method of constructing high concrete structure - Google Patents

Method of constructing high concrete structure

Info

Publication number
JPS6347466A
JPS6347466A JP20047487A JP20047487A JPS6347466A JP S6347466 A JPS6347466 A JP S6347466A JP 20047487 A JP20047487 A JP 20047487A JP 20047487 A JP20047487 A JP 20047487A JP S6347466 A JPS6347466 A JP S6347466A
Authority
JP
Japan
Prior art keywords
concrete
lot
formwork
scaffolding
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP20047487A
Other languages
Japanese (ja)
Other versions
JPH0346625B2 (en
Inventor
隆治 山本
俊文 越智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Construction Co Ltd
Original Assignee
Sumitomo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Construction Co Ltd filed Critical Sumitomo Construction Co Ltd
Priority to JP20047487A priority Critical patent/JPS6347466A/en
Publication of JPS6347466A publication Critical patent/JPS6347466A/en
Publication of JPH0346625B2 publication Critical patent/JPH0346625B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 この発明は高コンクリート構造物の構築方法に関するも
ので、高橋脚、高煙突、高層壁体購漬物等の高コンクリ
ート構造物の構築に利用する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing high concrete structures, and is used for constructing high concrete structures such as high piers, high chimneys, and high-rise wall structures.

従来この種の構造物を施工する方法としてはスライディ
ング工法やジャンピング工法があり、それぞれ種々の装
置により種々の施工方法が行われている。スライディン
グ工法はコンクリートの形状を決める型枠が一定速度で
連続してすべり移動するものであり、またジャンピング
工法は打設したコンクリートの養生、硬化に合わせて順
次型枠および足場を壁面に沿って1ロットずつ移動させ
、コンクリート構造物を連続的に構築施工して行くもの
である。
Conventionally, there are sliding construction methods and jumping construction methods as methods for constructing this type of structure, and various construction methods are performed using various devices. In the sliding method, the formwork that determines the shape of the concrete slides continuously at a constant speed, and in the jumping method, the formwork and scaffolding are sequentially moved along the wall surface as the poured concrete cures and hardens. Concrete structures are built and constructed continuously by moving lots one by one.

特開昭51−138024号公報には上記ジャンピング
工法の改良工法として、定規桿と型枠部とを互いに他方
に反力をとって昇降させるよう構成したものが記載され
ており、定規桿は下端の足場部より上方へ延び、上下の
ブラケットを介して既設コンクリート部分のネジパイプ
に固定できるようになっている。型枠部には型枠が一体
に固定されており、型枠部を定規桿に対し前後させるこ
とにより、型枠のセントおよび脱型を行っている。定規
桿と型枠部の上下方向の相対移動は定規枠側に取りつけ
たネジ桿と型枠部側で上下方向の移動を制約されるフラ
ンジギヤによりウオーム弐に行っている。
Japanese Unexamined Patent Publication No. 51-138024 describes an improved construction method of the above-mentioned jumping method in which the ruler rod and the formwork are raised and lowered by taking a reaction force against each other, and the ruler rod has a lower end. It extends upward from the scaffolding part and can be fixed to the threaded pipe of the existing concrete part via the upper and lower brackets. A formwork is integrally fixed to the formwork part, and by moving the formwork part back and forth with respect to the ruler rod, the centering and demolding of the formwork is performed. Relative movement of the ruler rod and the formwork in the vertical direction is performed on the worm 2 by a screw rod attached to the ruler frame side and a flange gear whose movement in the vertical direction is restricted on the formwork side.

しかし、上記工法および装置では型枠が型枠部本体と一
体となっているため、型枠のセットおよび脱型に際して
、型枠部全体を前後に移動しなければならない。また、
型枠のセットおよび脱型のために型枠部全体を前後させ
る必要があり、足場部を十分壁面に近接させることがで
きず、固定部分にかかるモーメントが大きくなり、荷重
支持の点で不利となる。さらに、型枠が型枠部本体と一
体であることからセントおよび脱型時の作業スペースを
十分にとることができず、型枠面の掃除が困難である。
However, in the above construction method and apparatus, the formwork is integrated with the formwork main body, so the entire formwork must be moved back and forth when setting and removing the formwork. Also,
It is necessary to move the entire formwork back and forth to set and remove the formwork, and the scaffolding cannot be brought close enough to the wall, which increases the moment applied to the fixed part, which is disadvantageous in terms of load support. Become. Furthermore, since the formwork is integrated with the main body of the formwork, it is not possible to take up a sufficient working space when removing and demolding the mold, and it is difficult to clean the surface of the formwork.

さらに、型枠部全体を前後に移動させるためには大きな
力が必要であり、装置の安定性を確保するのが難しく、
そのため、型枠部本体は小さくならざるを得ず、型枠部
を既設コンクリート面に係止固定した状態で、足場部を
上昇させる場合、コンクリート打設部分直下の若令の位
置で反力をとることになる。また、もしコンクリート強
度の問題を避けようとすると、打設したコンクリート部
分の養生のための時間を十分確保する必要があり、そう
すると施工速度が遅くなるといった問題がある。
Furthermore, a large amount of force is required to move the entire formwork back and forth, making it difficult to ensure the stability of the equipment.
Therefore, the main body of the formwork has to be made smaller, and when raising the scaffolding part with the formwork part locked and fixed to the existing concrete surface, the reaction force is generated at a young position directly below the concrete pouring part. I will take it. Furthermore, if problems with concrete strength are to be avoided, it is necessary to ensure sufficient time for curing of the poured concrete portion, which poses the problem of slowing down the construction speed.

この発明はこのような従来のジャンピング工法の改良を
目的としたものである。
The purpose of this invention is to improve the conventional jumping method.

この発明ではコンクリート既設部分上でコンクリート壁
面を取り囲んで設置した型枠間に、コンクリートを打設
し、打設したコンクリートの養生および硬化に合わせて
順次型枠および足場を1ロットずつ上方へ移動させて高
コンクリート構造物を構築する方法において、各ロット
ごとコンクリート壁面にレール部材と足場フレームを固
定するためのレール部材固定用および足場フレーム固定
用のアンカー金物をそれぞれ別個に設ける。そして、前
記レール部材と足場フレ−ムを互いに上下方向に相対移
動可能に連結するとともに、これらレール部材と足場フ
レームをそれぞれ複数のロットに跨がって前記アンカー
金物に固定し、それぞれ下端がコンクリート打設位置よ
り少なくとも1ロット分下で支持されるようにする。次
に前記足場フレームの上方に延びるアームから水平移動
可能に吊支持された型枠を足場フレームの足場上で水平
移動させて所定位置にセットし、コンクリートを打設し
て養生し、前記型枠を水平方向に後退させて脱型する。
In this invention, concrete is poured between formworks set up around the concrete wall surface on the existing concrete part, and the formwork and scaffolding are sequentially moved upward one lot at a time as the poured concrete cures and hardens. In the method of constructing a high-concrete structure, anchor metal fittings for fixing the rail members and the scaffolding frame are separately provided for fixing the rail member and the scaffolding frame to the concrete wall surface for each lot. Then, the rail member and the scaffold frame are connected to each other so as to be movable relative to each other in the vertical direction, and each of the rail members and the scaffold frame is fixed to the anchor hardware across a plurality of lots, and the lower end of each is made of concrete. It should be supported at least one lot below the pouring position. Next, the formwork, which is horizontally movably suspended and supported from an arm extending above the scaffold frame, is moved horizontally on the footing of the scaffold frame and set at a predetermined position, concrete is poured and cured, and the formwork is Retract horizontally and remove from the mold.

続いて前記レール部材の固定を解除してレール部材を足
場フレームに対して1ロット分上昇させて1ロット分上
の各レール部材固定用のアンカー金物に固定し、次に足
場フレームの固定を解除して足場フレームをレール部材
に対して1ロット分上昇させて1ロット分上の各足場フ
レーム固定用のアンカー金物に固定する。このようにこ
の発明では、常にコンクリート打設位置より1ロット分
以上離れた、コンクリート強度が十分発現している位置
でレール部材または足場フレームを支持した状態で、順
次上方のコンクリートを打設して行く。
Next, the fixation of the rail member is released, the rail member is raised one lot relative to the scaffold frame, and is fixed to the anchor hardware for fixing each rail member one lot above, and then the fixation of the scaffold frame is released. Then, the scaffold frame is raised by one lot relative to the rail member and fixed to the anchor hardware for fixing each scaffold frame one lot above. In this way, in this invention, the concrete above is poured in sequence while supporting the rail member or scaffolding frame at a location where the concrete strength is sufficiently developed, which is at least one lot away from the concrete placement location. go.

以下、この発明を図示した実施例に基づいて説明する。The present invention will be described below based on illustrated embodiments.

第1図は橋脚の施工に適用した場合の概要を示したもの
で、既設のコンクリート1が硬化し、所定の強度を発現
した部分の四隅にこの発明の施工装置を数組(図では計
6組)配置している。
Figure 1 shows an outline of the case where it is applied to the construction of bridge piers, in which several sets of the construction equipment of the present invention (a total of 6 group) are arranged.

コンクリート1の打設高さは例えば1ロットが3.5〜
5mであり、−組の装置は型枠幅6m程度まで適用する
ことができる。なお、装置の上昇は後述する油圧ジヤツ
キ7で行ない、油圧ポンプと油圧ジヤツキの配管により
四□面に配した装置を全部同時に上昇させることもでき
る。また、装置の外側は安全ネットまたはシートで覆わ
れる。
The pouring height of concrete 1 is, for example, 3.5 to 1 lot.
5 m, and the - set of equipment can be applied to formworks up to a width of about 6 m. Incidentally, the equipment can be raised by a hydraulic jack 7, which will be described later, and all the equipment arranged on the four sides can be raised at the same time using piping between a hydraulic pump and a hydraulic jack. Additionally, the outside of the device is covered with a safety net or sheet.

第2図〜第5図はこの発明で使用する装置の構成を示し
たもので、作業足場を有する足場フレーム2の上部に逆
り字形のアーム3を持つ柱が取りつけられ、これにギャ
ードトロリー付チェーンブロック5が組み込まれている
。この吊装置は型枠6を吊り上げ、また水平に移動する
ことができる。
Figures 2 to 5 show the configuration of the device used in this invention, in which a column with an inverted-shaped arm 3 is attached to the top of a scaffold frame 2 having a work scaffold, and a guard trolley is attached to this column. A chain block 5 with an attached chain block is incorporated. This lifting device can lift the formwork 6 and also move it horizontally.

レール部材は上下方向に延びる一対のレール12と、該
レール12間中央部に設けた一ヒ下方向の2木の吊鋼捧
13とを上下端で連結したものである。
The rail member is made up of a pair of rails 12 extending in the vertical direction, and two hanging steel rods 13 provided in the center between the rails 12 and connected in the downward direction at the upper and lower ends.

足場フレーム2本体には中央に油圧ジャンキ7が固定さ
れており、その上下にレールガイドローラー(車輪)1
1が取りつけである。この足場フレーム2にレール12
をガイドローラー11を介して組み込み、上記油圧ジヤ
ツキ7の作動により、吊鋼捧13を介してレール12を
上昇(または下降)させることができる。
A hydraulic jack 7 is fixed to the center of the scaffold frame 2, and rail guide rollers (wheels) 1 are installed above and below it.
1 is the installation. Rail 12 on this scaffolding frame 2
is assembled via the guide roller 11, and the rail 12 can be raised (or lowered) via the hanging bar 13 by operating the hydraulic jack 7.

また、コンクリート壁面に固定されたアンカー金物8と
足場フレーム2とは、キー状の金具10およびアンカー
鋼棒9で完全に固定される。
Further, the anchor hardware 8 fixed to the concrete wall surface and the scaffold frame 2 are completely fixed by a key-shaped metal fitting 10 and an anchor steel rod 9.

レール12も同様の固定方法によりアンカー金物14と
固定される。キー状の金具10.16はそれぞれ足場フ
レーム2およびレール12の最下部に取りつけられるよ
うな構造となっている。
The rail 12 is also fixed to the anchor hardware 14 by a similar fixing method. The key-shaped metal fittings 10.16 are structured to be attached to the lowest parts of the scaffold frame 2 and the rail 12, respectively.

また、壁面と装置との高さ調整のために調整用ジヤツキ
20、調整用ネジ21がそれぞれ足場フレーム2とレー
ル12に用意されている。
Furthermore, adjustment jacks 20 and adjustment screws 21 are provided on the scaffold frame 2 and rail 12, respectively, to adjust the height of the wall surface and the device.

なお、図中17は足場フレーム2のアーム3上に設けら
れた作業床、1日ははしご、19は作業足場の手摺、2
2は安全ネットである。
In addition, in the figure, 17 is a working floor installed on the arm 3 of the scaffolding frame 2, 1st is a ladder, 19 is a handrail of the working scaffold, 2
2 is a safety net.

第6図〜第10図は施工手順を示したもので、次にこれ
らの図に沿って施工手順を説明する。
FIGS. 6 to 10 show the construction procedure, and the construction procedure will be explained next with reference to these figures.

(1)第6図はコンクリート1”打設完了の様子を示し
たもので、コンクリート1°打設時には足場フレーム2
とレール12は各々既設コンクリート1に設けたアンカ
ー金物8,14に固定されたままである。
(1) Figure 6 shows the completion of concrete 1” pouring, and when concrete is poured 1°, the scaffolding frame 2
The rails 12 and 12 remain fixed to anchor hardware 8, 14 provided in the existing concrete 1, respectively.

(2)第7図は型枠6の脱型およびアンカー金物8.1
4の設置の様子を示す。打設コンクリート1′の養生後
、逆り字形アーム3のチェーンブロック5を操作して型
枠6を脱型し、外側へ移動させ、係止具23で動かない
ように仮固定する。また、型枠6とコンクリート1゜の
壁面との間には約60cmの空間ができるため、アンカ
ー金物8,14を高力ボルトで定着させる。
(2) Figure 7 shows demolding of formwork 6 and anchor hardware 8.1
The installation of item 4 is shown below. After curing of the poured concrete 1', the chain block 5 of the inverted-shaped arm 3 is operated to remove the formwork 6, move it to the outside, and temporarily fix it with a locking tool 23 so that it does not move. Further, since there is a space of approximately 60 cm between the formwork 6 and the concrete wall surface of 1°, the anchor metal fittings 8 and 14 are fixed with high-strength bolts.

(3)次に、第8図に示すようにレール12を1ロット
分上昇させセットする。まず、レール12を止めである
アンカー鋼棒15を取り外し、上昇用油圧ジヤツキ7を
作動させるとレール12は上昇する。油圧ジヤツキ7と
吊鋼棒13のもりかえを行い、レール12を1ロット分
上昇させ、高さ調整後、下部レールせん断キー16を上
述の(2)で述べたと同様に定着させたアンカー金物1
4に密着させ、さらにアンカー鋼棒15でアンカー金物
14に固定する。
(3) Next, as shown in FIG. 8, the rail 12 is raised by one lot and set. First, the anchor steel rod 15 that stops the rail 12 is removed, and when the lifting hydraulic jack 7 is operated, the rail 12 is raised. The hydraulic jack 7 and the hanging steel rod 13 were replaced, the rail 12 was raised by one lot, and the height was adjusted, and the lower rail shear key 16 was fixed in the same manner as described in (2) above.Anchor hardware 1
4, and further fixed to the anchor hardware 14 with an anchor steel rod 15.

(4)次に、第9図に示すように足場フレーム2を1ロ
ット分上昇させ、セットする。レール12を上昇させた
のと、全く同様の方法で上昇させることができる。すな
わち、足場フレーム2を止めているアンカー鋼棒9を取
り外し、油圧ジヤツキ7を作動させるとガイドロ−ラー
11により、足場フレーム2が上昇する。油圧ジヤツキ
7と吊鋼棒13のもりかえを行い、足場フレーム2を1
0ット分上昇させ、所定の位置で下部足場フレームせん
断キー10をアンカー金物8に密着させ、セットする。
(4) Next, as shown in FIG. 9, the scaffolding frame 2 is raised by one lot and set. It can be raised in exactly the same way as the rail 12 was raised. That is, when the anchor steel rod 9 fixing the scaffold frame 2 is removed and the hydraulic jack 7 is operated, the scaffold frame 2 is raised by the guide roller 11. Replace the hydraulic jack 7 and hanging steel rod 13, and replace the scaffolding frame 2 with 1
The lower scaffold frame shear key 10 is brought into close contact with the anchor hardware 8 at a predetermined position and set.

そして、アンカー鋼棒9でアンカー金物8に取りつけ高
さ調整し、高さ調整ジヤツキ20を作動させ固定する。
Then, the anchor steel rod 9 is attached to the anchor hardware 8 to adjust the height, and the height adjustment jack 20 is operated to fix it.

(5)第10図は型枠6のセットの様子を示す。(5) FIG. 10 shows how the formwork 6 is set.

レール12および足場フレーム2の上昇が完了したら、
型枠6と足場フレーム2との仮固定を外し、チェーンブ
ロック5を操作し、型枠6を吊込み、高さ調整後、セッ
トする。
Once the rail 12 and scaffolding frame 2 have been raised,
The temporary fixation between the formwork 6 and the scaffolding frame 2 is removed, the chain block 5 is operated, the formwork 6 is suspended, the height is adjusted, and then set.

以上、(1)〜(5)の操作を繰り返すことにより、コ
ンクリート構造物の連続施工がなされる。
By repeating the operations (1) to (5) above, concrete structures can be constructed continuously.

第11図および第12図は、それぞれレール12上昇時
および足場フレーム2上昇時における油圧ジヤツキ7の
操作を示したもので、次にこれらについて説明する。
FIG. 11 and FIG. 12 show the operation of the hydraulic jack 7 when the rail 12 and the scaffold frame 2 are raised, respectively, and these will be explained next.

(1)  レール12上界時の油圧ジヤツキ操作図中2
6が油圧ジヤツキ7のジヤツキ台、27がフォークで、
まず吊鋼棒13に螺合したナツト29をフォーク27の
上側に当てる。
(1) Hydraulic jack operation diagram when rail 12 is above 2
6 is the jack stand of the hydraulic jack 7, 27 is the fork,
First, the nut 29 screwed onto the hanging steel rod 13 is applied to the upper side of the fork 27.

この状態でジヤツキ7を引張側に加圧すると、吊鋼棒1
3を引上げるので、レール12が一体に上昇する。スト
ロークエンドでナツト30をガイド28に当て、ジヤツ
キ7を押倒に加圧し、ジヤツキ7をもりかえる。再びナ
ツト29をフォーク27に当て、以上の操作を繰り返す
In this state, when the jack 7 is pressurized to the tension side, the hanging steel rod 1
3, the rails 12 rise together. At the end of the stroke, the nut 30 is placed against the guide 28, the jack 7 is pressed down, and the jack 7 is replaced. Place the nut 29 on the fork 27 again and repeat the above operation.

(2)足場フレーム2上昇時の油圧ジヤツキ操作まず、
ナツト30をフォーク27に当てジヤツキ7を押倒に加
圧すると、吊鋼棒13が固定されているので、ジヤツキ
7および足場フレーム2が上昇する。ストロークエンド
でナツト29をジヤツキ台に当て、ジヤツキ7を引張側
に加圧し、ジヤツキ7をちりかえる。
(2) Hydraulic jack operation when lifting scaffold frame 2.
When the nut 30 is applied to the fork 27 and the jack 7 is pressed down, the jack 7 and the scaffold frame 2 rise because the hanging steel rod 13 is fixed. At the end of the stroke, place the nut 29 on the jack stand, press the jack 7 to the tension side, and replace the jack 7.

再びナツト30をフォーク27に当て、以上の操作を繰
り返す。
Place the nut 30 on the fork 27 again and repeat the above operation.

この発明は上述のような構成からなり、次のような利点
、特徴を有する。
The present invention has the above-described configuration and has the following advantages and features.

(1)単純な構造のレール部材とこれに沿って昇降する
足場フレームとを、足場フレームに設けた油圧ジヤツキ
で相互に移動させて昇降を行うため、装置が邪魔あるい
は無駄になる部分が少なく操作が容易である。
(1) Since the simple structure of the rail member and the scaffolding frame that goes up and down along it are moved relative to each other using hydraulic jacks installed on the scaffolding frame, the equipment can be operated with less interference or wasted parts. is easy.

(2)  レール部材と足場フレームはコンクリート壁
面に反力受けとして設けられた別個のアンカー金物に支
持させ、常にコンクリート打設位置より10ット分以上
離れた十分強度の発現した既設コンクリート壁面で支持
するため、施工の安全性が高い。
(2) The rail members and scaffolding frame shall be supported by separate anchor hardware installed on the concrete wall surface as a reaction force receiver, and shall always be supported on an existing concrete wall surface of sufficient strength that is at least 10 tons away from the concrete placement location. Therefore, construction safety is high.

(3)型枠は足場フレームより上方に延びるアームに吊
支持され、その状態で水平に移動する構造であるため、
型枠のセットおよび脱型を足場フレームあるいはレール
部材の移動と別個に独立して行うことができ、足場フレ
ーム上において作業スペースが十分確保できる。
(3) The formwork is suspended from an arm that extends above the scaffolding frame, and moves horizontally in that state.
The setting and demolding of the formwork can be performed separately and independently from the movement of the scaffolding frame or rail members, and sufficient work space can be secured on the scaffolding frame.

また、アームに吊支持されているだけなので、型枠のセ
ント時、型枠がフリーの状態にあり、位置調整も容易で
ある。
In addition, since it is only suspended and supported by the arm, the formwork is in a free state when the formwork is centered, and its position can be easily adjusted.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はこの発明の実施例を示したもので、第1図は橋脚
の施工に適用した場合の斜視図、第2図は施工装置の概
要を示す正面図、第3図はその右側面、第4図および第
5図はそれぞれ第2図のA−A断面図およびB−B断面
図、第6図〜第10図は施工手順を示す側面図(橋脚部
分断面)、第11図はレール上昇時の油圧ジヤツキの操
作を示す説明図、第12図は足場フレーム上昇時の操作
を示す説明図である。 1.1゛・・・コンクリート、2・・・足場フレーム、
3・・・アーム、4・・・ギャードトロリー、5・・・
チェーンブロック、6・・・型枠、7・・・油圧ジヤツ
キ、8・・・足場フレーム用アンカー金物、9・・・足
場フレーム用アンカー鋼棒、10・・・足場フレーム用
せん断キー、11・・・ガイドローラー(車輪)、12
・・・レール部材、13・・・吊鋼棒、14・・・レー
ル用アンカー金物、14”・・・アンカーボルト、15
・・・レール用アンカー鋼棒、16・・・レール用せん
断キー、17・・・作業床、18・・・はしご、19・
・・手摺、20・・・足場フレーム高さ調整ジヤツキ、
21・・・レール高さ調整ネジ、22・・・安全ネット
、23・・・係止具、26・・・ジャ・ンキ台、27・
・・フォーク、28・・・ガイド、29・・・す・ント
、30・・・ナツト 築 12I 第4図 第6図    第7図 第8図    第9図 第10図 第11図 第12図
The drawings show an embodiment of the present invention; Fig. 1 is a perspective view when applied to the construction of bridge piers, Fig. 2 is a front view showing an overview of the construction equipment, and Fig. 3 shows the right side and Figures 4 and 5 are A-A and B-B cross-sectional views of Figure 2, respectively, Figures 6 to 10 are side views (partial cross-section of the pier) showing the construction procedure, and Figure 11 is the rail elevation. FIG. 12 is an explanatory diagram showing the operation of the hydraulic jack when the scaffold frame is raised. 1.1゛...Concrete, 2...Scaffolding frame,
3... Arm, 4... Guard trolley, 5...
Chain block, 6... Formwork, 7... Hydraulic jack, 8... Anchor hardware for scaffolding frame, 9... Anchor steel rod for scaffolding frame, 10... Shear key for scaffolding frame, 11.・・Guide roller (wheel), 12
...Rail member, 13...Hanging steel rod, 14...Anchor hardware for rail, 14"...Anchor bolt, 15
... Anchor steel rod for rail, 16... Shear key for rail, 17... Work floor, 18... Ladder, 19.
...Handrail, 20...Scaffolding frame height adjustment jack,
21... Rail height adjustment screw, 22... Safety net, 23... Locking tool, 26... Jacket stand, 27...
...Fork, 28...Guide, 29...Summary, 30...Natsuto Construction 12I Fig. 4 Fig. 6 Fig. 7 Fig. 8 Fig. 9 Fig. 10 Fig. 11 Fig. 12

Claims (2)

【特許請求の範囲】[Claims] (1)コンクリート既設部分上でコンクリート壁面を取
り囲んで設置した型枠間に、コンクリートを打設し、打
設したコンクリートの養生および硬化に合わせて順次型
枠および足場を1ロットずつ上方へ移動させて高コンク
リート構造物を構築する方法において、各ロットごとコ
ンクリート壁面にレール部材と足場フレームを固定する
ためのレール部材固定用および足場フレーム固定用のア
ンカー金物をそれぞれ別個に設け、前記レール部材と足
場フレームを互いに上下方向に相対移動可能に連結する
とともに、これらレール部材と足場フレームをそれぞれ
複数のロットに跨がって前記アンカー金物に固定し、そ
れぞれ下端がコンクリート打設位置より少なくとも1ロ
ット分下で支持されるようにし、次に前記足場フレーム
の上方に延びるアームから水平移動可能に吊支持された
型枠を足場フレームの足場上で水平移動させて所定位置
にセットし、コンクリートを打設して養生した後、前記
型枠を水平方向に後退させて脱型し、続いて前記レール
部材の固定を解除してレール部材を足場フレームに対し
て1ロット分上昇させて1ロット分上の各レール部材固
定用のアンカー金物に固定し、次に足場フレームの固定
を解除して足場フレームをレール部材に対して1ロット
分上昇させて1ロット分上の各足場フレーム固定用のア
ンカー金物に固定し、順次上方のコンクリートを打設し
て行くことを特徴とする高コンクリート構造物の構築方
法。
(1) Concrete is poured between the formwork installed on the existing concrete area surrounding the concrete wall surface, and the formwork and scaffolding are sequentially moved upward one lot at a time as the poured concrete cures and hardens. In this method, anchor hardware for fixing rail members and scaffolding frames for fixing rail members and scaffolding frames to a concrete wall surface is provided separately for each lot, and the rail members and scaffolding The frames are connected to each other so that they can move relative to each other in the vertical direction, and the rail members and scaffolding frames are each fixed to the anchor hardware across multiple lots, and each lower end is at least one lot below the concrete placement position. Next, the formwork, which is suspended and supported horizontally from an arm extending above the scaffold frame, is moved horizontally on the footing of the scaffold frame and set in a predetermined position, and concrete is poured. After curing, the formwork is moved back horizontally to remove the mold, and then the rail member is released from the fixation, and the rail member is raised by one lot relative to the scaffolding frame, and each lot above each lot is removed. Fix it to the anchor hardware for fixing the rail member, then release the fixation of the scaffold frame, raise the scaffold frame one lot relative to the rail member, and fix it to the anchor hardware for fixing each scaffold frame one lot above. A method of constructing a high-concrete structure, which is characterized by sequentially pouring concrete from above.
(2)コンクリート壁面を取り囲んで設置した複数の足
場フレームを同時に上昇させる特許請求の範囲第1項記
載の高コンクリート構造物の構築方法。
(2) A method for constructing a high concrete structure according to claim 1, which simultaneously raises a plurality of scaffold frames installed surrounding a concrete wall surface.
JP20047487A 1987-08-11 1987-08-11 Method of constructing high concrete structure Granted JPS6347466A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20047487A JPS6347466A (en) 1987-08-11 1987-08-11 Method of constructing high concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20047487A JPS6347466A (en) 1987-08-11 1987-08-11 Method of constructing high concrete structure

Publications (2)

Publication Number Publication Date
JPS6347466A true JPS6347466A (en) 1988-02-29
JPH0346625B2 JPH0346625B2 (en) 1991-07-16

Family

ID=16424917

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20047487A Granted JPS6347466A (en) 1987-08-11 1987-08-11 Method of constructing high concrete structure

Country Status (1)

Country Link
JP (1) JPS6347466A (en)

Also Published As

Publication number Publication date
JPH0346625B2 (en) 1991-07-16

Similar Documents

Publication Publication Date Title
US3550723A (en) Bridge scaffold
CN112458918A (en) High-pier hydraulic jacking integral steel frame platform formwork turnover construction system and construction method
JP3804883B2 (en) Concrete high structure construction apparatus and concrete oblique column construction method
CN115306136B (en) Inclined wall eversion climbing type steel platform construction device and method
JPH07247695A (en) Construction method for high structure and construction device used therefor
CN216765625U (en) Integral hydraulic creeping formwork structure for double-column pier construction
CN207727440U (en) Whole self-crawling type integrated platform for bridge tower construction
JPS6331629B2 (en)
JP3531111B2 (en) Apparatus and method for constructing tower-like structure
JPS6347466A (en) Method of constructing high concrete structure
JP3063548B2 (en) Formwork method and equipment
JP2829363B2 (en) Formwork equipment for pillar construction
JP3032477B2 (en) Moving scaffold for floor slab assembly
CN113175201A (en) A operation platform that rises that slides for elevartor shaft construction
JP2001098559A (en) Total lift-up form device
JP3425353B2 (en) Formwork material for sliding formwork device
KR200324558Y1 (en) Slip-form improving device for construction of bridge
JPH11311021A (en) Fall preventing device in slip form construction method
CN218933831U (en) A construction structures for high mound processing
CN214384047U (en) Hydraulic system for high-rise building climbing pouring
JPS5916608B2 (en) Concrete formwork method and its equipment
CN211421802U (en) High-rise building construction machinery
JPS6352188B2 (en)
SU1087634A1 (en) Sliding forms
JP3224152B2 (en) Construction method of cross beam in concrete building