JPS63277357A - Method of construction of execution of staircase - Google Patents
Method of construction of execution of staircaseInfo
- Publication number
- JPS63277357A JPS63277357A JP62084330A JP8433087A JPS63277357A JP S63277357 A JPS63277357 A JP S63277357A JP 62084330 A JP62084330 A JP 62084330A JP 8433087 A JP8433087 A JP 8433087A JP S63277357 A JPS63277357 A JP S63277357A
- Authority
- JP
- Japan
- Prior art keywords
- landing
- formwork
- floor
- slab
- members
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims 2
- 238000010276 construction Methods 0.000 title description 3
- 238000009415 formwork Methods 0.000 claims description 24
- 239000004567 concrete Substances 0.000 claims description 8
- 230000002787 reinforcement Effects 0.000 claims description 5
- 230000003014 reinforcing effect Effects 0.000 description 10
- 239000002184 metal Substances 0.000 description 2
- 239000011513 prestressed concrete Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 239000011505 plaster Substances 0.000 description 1
Landscapes
- Steps, Ramps, And Handrails (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
段々部材をP@C化(プレストレスコンクリート化)す
る事によって工期・手間を簡単にし、且つ安全通路の確
保を計ることができるようにした発明である。[Detailed description of the invention] [Industrial field of application] By converting terraced members into P@C (prestressed concrete), construction time and labor can be simplified, and safe passages can be ensured. It is an invention.
従来は型枠を枠組みし、配筋した後、コンクリートを打
設し、更に墨み出しして左官仕上鴨をしていたので時間
と手間が非常にかかり、又仕上時には約1週間位いの通
行止めをする必要がある等の欠点を有していたものであ
る。Traditionally, after constructing the formwork and arranging the reinforcement, concrete was poured, and then the concrete was painted and plastered, which was very time-consuming and labor-intensive, and it took about a week to finish. This had drawbacks such as the need for road closures.
型枠の枠組み、鉄筋の配筋、コンクリートの打設、仕上
のための墨み出し、及び左官仕上に時間と手間がかかる
という問題点を解決しようとする発明である。This invention attempts to solve the problem that it takes time and effort to frame formwork, arrange reinforcing bars, place concrete, mark out for finishing, and plaster.
フロア−から踊り場用及び踊り場からフロア−用の段々
部材を工場製作し、階段側型枠と受スラブ型枠並びにフ
ロア−用の型枠の枠組み完了後、フロア−から踊り場用
型枠及び踊り場用型枠から上部フロア−及びスラブ型枠
に段々部材をセットすると共に踊り場床、上部スラブの
配筋を行い踊り場のみコンクリートを打設することによ
り、段々部材の型枠の枠組み、配筋、コンクリートの打
設、墨み出し、左官作業、型枠の解体及び片付等の繁雑
な仕事をなくすこと、及び通行止めも仕上する1日です
むようにしたことにより問題点を解決したものである。Stepped members for the floor to the landing and from the landing to the floor are manufactured in a factory, and after the stair side formwork, receiving slab formwork, and floor formwork are completed, the formwork for the floor to landing and the landing form are completed. By setting the terrace members from the formwork to the upper floor and slab formwork, reinforcing the landing floor and upper slab, and pouring concrete only on the landing, the framework of the formwork of the terrace members, reinforcement arrangement, and concrete This problem was solved by eliminating complicated work such as pouring, inking, plastering, dismantling and clearing formwork, and by making it possible to finish road closures in one day.
フロア−当接用の切欠き(1)を下端に設けた複数の段
部(2)を有する階段のフロア−から踊り場用の段々部
材(3)を工場にてプレストレスコンクリート製作(p
−c化)し、更に複数の段部(4)を有する階段の踊り
場からフロア−用の段々部材に鉄゛筋(6)を水平に突
出させ、段々部材(3)の片側筋(8)を突出させ、最
上段(4b)の後面には斜状に鉄筋(8)を突出させ、
且つ段々部材(5)の片側面にジベル筋(9)を突出さ
せておくものである。The step members (3) for the landing are manufactured from prestressed concrete in a factory (p.
Furthermore, a reinforcing bar (6) is made to protrude horizontally from the landing of the staircase having a plurality of steps (4) to the step member for the floor, and one side reinforcement (8) of the step member (3) is are made to protrude, and a reinforcing bar (8) is made to protrude diagonally from the rear surface of the top stage (4b),
In addition, a dowel bar (9) is made to protrude from one side of the stepped member (5).
段々部材(3)及び(5)を現場に持ち込み、先づフロ
ア−から踊り場用の段々部(3)をクレーンで吊り下端
の切欠き(1)を既設のフロア−(lO)の端部に当接
し、フロア−〇〇)の埋め込み金具と段々部材(3)の
埋め込み金具とを溶接し最上段(2a)の下面を踊り場
用の既に枠組みされている型枠旧)に載置し、次に踊り
場からフロア−用の段々部材(5)をクレーンで吊って
既に枠組みされている踊り場用の型枠旧)上に最下部の
段部(4a)の下面を載置し、最上部の段部(4b)の
下面を既設の上階部のスラブ及びフロア−用の型枠(1
21に載置する。Bring the terrace members (3) and (5) to the site, and first suspend the terrace part (3) for the landing from the floor using a crane and attach the notch (1) at the lower end to the end of the existing floor (lO). Then, weld the embedded metal fittings of the floor (〇〇) and the embedded metal fittings of the step member (3), and place the lower surface of the top step (2a) on the existing formwork for the landing (old), and then Next, hang the floor terrace member (5) from the landing with a crane, place the lower surface of the lowermost step (4a) on the already framed formwork for the landing, and then The lower surface of section (4b) is attached to the formwork (1) for the existing upper floor slab and floor.
Place it on 21.
その後踊り場の型枠(11)上に前記した鉄筋(61(
8)及び他の鉄筋を使用して踊り場部分を配筋する。After that, the above-mentioned reinforcing bars (61 (
Reinforce the landing section using 8) and other reinforcing bars.
上階部のスラブ及びフロア−用の型枠(+2)内に鉄筋
(8)を他の鉄筋と共に配筋し、これらと平行して段々
部材(5)の背面に埋設されたインサートとフロア−(
10)に埋設されたインサート−発14〜咽峨→°゛
とをターンバックル(+3)付チェン04)で
引っ張り段々部材(5)がづれないようにすると共に段
々部材(5)の最上部の段部(4b)の鉄筋(8)と型
枠021に設けたスラブリング(19とを溶接し、その
後、踊り場のみコンクリートを打設する。Reinforcing bars (8) are arranged together with other reinforcing bars in the formwork (+2) for the slab and floor on the upper floor, and in parallel with these, inserts and floors are buried in the back of the stepped member (5). (
10) Insert buried in 14~pharyngeal →°゛
and pull it with a chain 04) with a turnbuckle (+3) to prevent the terrace member (5) from shifting, and also to install a reinforcing bar (8) of the uppermost step (4b) of the terrace member (5) and the formwork 021. Weld the slab ring (19) and then pour concrete only on the landing.
尚、(+6)は型枠(1旧121を支持しているパイプ
サポート、αηは段々部材(5)を支持するパイプサポ
ートを示すものである。Note that (+6) indicates a pipe support that supports the formwork (1 old 121), and αη indicates a pipe support that supports the step member (5).
又、ジベル筋(7)及び(9)は適宜階段側型枠内に配
筋するものである。Also, the dowel reinforcements (7) and (9) are appropriately arranged within the stair-side formwork.
酩
従来の型枠、鉄筋、コンクリート打設、墨出し、左官仕
上の繁雑な仕事がなくなり、トータルコストが下がり、
又仕上時の通行止めも踊り場のモルタル仕上をする1日
だけとなり安全通路としても使用できるものである。The conventional complicated work of formwork, reinforcing bars, concrete pouring, marking, and plastering is eliminated, reducing total costs.
Furthermore, the road closure during finishing is limited to one day when the landing is finished with mortar, so it can also be used as a safe passage.
第1図は階段部分の施工時の断面図、第2図はフロア−
から踊り場への段々部材の断面図、第3図は同平面図、
第4図は踊り場からフロア−への段々部材の断面図、第
5図は同平面図である。Figure 1 is a cross-sectional view of the staircase section during construction, and Figure 2 is the floor section.
A cross-sectional view of the step members from to the landing, FIG. 3 is a plan view of the same,
FIG. 4 is a sectional view of the step member from the landing to the floor, and FIG. 5 is a plan view thereof.
Claims (1)
の段々部材を工場製作し、階段側型枠と受スラブ型枠並
びフロアー用の型枠の枠組み完了後、フロアーから踊り
場用型枠及び踊り場用型枠から上部フロアー及びスラブ
型枠に段々部材をセットすると共に踊り場床、上部スラ
ブの配筋を行い踊り場のみコンクリートを打設すること
を特徴とする階段の施工工法。(1) Stepped members for the landing from the floor and from the landing to the floor are manufactured in a factory, and after the stair side formwork, receiving slab formwork, and floor formwork are completed, the formwork for the landing from the floor and the formwork for the landing are manufactured. This method of constructing stairs is characterized by setting step members from the frame to the upper floor and slab formwork, arranging reinforcement for the landing floor and upper slab, and pouring concrete only at the landing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62084330A JPS63277357A (en) | 1987-04-06 | 1987-04-06 | Method of construction of execution of staircase |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62084330A JPS63277357A (en) | 1987-04-06 | 1987-04-06 | Method of construction of execution of staircase |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS63277357A true JPS63277357A (en) | 1988-11-15 |
Family
ID=13827503
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP62084330A Pending JPS63277357A (en) | 1987-04-06 | 1987-04-06 | Method of construction of execution of staircase |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS63277357A (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6245858A (en) * | 1985-08-26 | 1987-02-27 | 鹿島建設株式会社 | Construction of upstairs |
JPS6259753A (en) * | 1985-09-09 | 1987-03-16 | 鹿島建設株式会社 | Constructure of upstairs |
-
1987
- 1987-04-06 JP JP62084330A patent/JPS63277357A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6245858A (en) * | 1985-08-26 | 1987-02-27 | 鹿島建設株式会社 | Construction of upstairs |
JPS6259753A (en) * | 1985-09-09 | 1987-03-16 | 鹿島建設株式会社 | Constructure of upstairs |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Hurd | Formwork for concrete | |
CN205242706U (en) | Cast -in -place constructional column of infilled wall and wall body synchronous construction structure between high -rise outer eaves window | |
JPH08312090A (en) | Construction method of concrete stair with stepped form left, and stepped form | |
CN218091465U (en) | Assembled non-bearing masonry wall structure | |
JPH0579049A (en) | Constructing method for beam and slab in underground body construction work | |
JP2706742B2 (en) | Construction method of reinforced concrete stairs, stair handrail precast concrete slab and stair step formwork used for it | |
JPS63277357A (en) | Method of construction of execution of staircase | |
JPS61169563A (en) | Construction of upstairs | |
TWI851481B (en) | Architecture unit | |
WO2001048327A1 (en) | A quickly building method with permanent fancy self-fixing plate | |
JP2529660B2 (en) | Concrete precast floorboard construction method | |
JP2002227408A (en) | Method for executing stair in building and rise directly used for its method | |
JPH0614225U (en) | Precast concrete block for wall | |
JP3108898B2 (en) | Construction method of underground structure by reverse construction method | |
CN209369596U (en) | Windowsill coping concrete prefabricated section | |
JP2843532B2 (en) | Reticulated formwork with finishing plate | |
EP1233123A2 (en) | A bricklaying method and an arrangement for the implementation thereof | |
JPH0452815B2 (en) | ||
JPH0470444A (en) | Partition wall of concrete building and execution method thereof | |
JP2846426B2 (en) | How to build concrete stairs | |
JPH04153421A (en) | Manufacturing method of precast concrete balcony | |
JPS598846A (en) | Construction of balcony | |
JPS6224563B2 (en) | ||
JPH03244760A (en) | Erecting method for stair | |
JP2004360266A (en) | Structure and construction method for floor post base part |