JPS63251546A - Method for building concrete structure - Google Patents

Method for building concrete structure

Info

Publication number
JPS63251546A
JPS63251546A JP8666587A JP8666587A JPS63251546A JP S63251546 A JPS63251546 A JP S63251546A JP 8666587 A JP8666587 A JP 8666587A JP 8666587 A JP8666587 A JP 8666587A JP S63251546 A JPS63251546 A JP S63251546A
Authority
JP
Japan
Prior art keywords
concrete
concrete structure
ice
constructing
structure according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8666587A
Other languages
Japanese (ja)
Inventor
岩島 澄雄
清次 児玉
孝一 後田
清 清水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP8666587A priority Critical patent/JPS63251546A/en
Publication of JPS63251546A publication Critical patent/JPS63251546A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、基礎用型枠を設置した後、コンクリートを打
設し、所定時間経過させて固化させるコンクリート構造
物の建造方法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for constructing a concrete structure, in which a foundation form is installed, then concrete is poured and allowed to harden over a predetermined period of time.

〔従来の技術〕[Conventional technology]

一般のコンクリート構造物の建築においては、砂利、砂
、及びセメントと水の混合物であるコンクリートを建物
の躯体形状として設けられた合板。
In the construction of general concrete structures, plywood is used to form the building frame using concrete, which is a mixture of gravel, sand, cement, and water.

または鉄板等の基礎用型枠の中へ流し込み、コンクリー
トが固化した後、基礎用型枠を撤去する工法が取られて
いた(特開昭55−75055号公報)。
Alternatively, a construction method has been adopted in which concrete is poured into a foundation formwork such as an iron plate, and after the concrete has solidified, the foundation formwork is removed (Japanese Patent Laid-Open Publication No. 75055/1983).

次に、原子カプラントの原子炉を運転・制御するための
中央制御室に設置される電気盤、制御盤用ケーブルトレ
ーとして中操室床上に設けられる基礎台の成型工法につ
いて説明する。
Next, we will explain the method for molding the electric panel installed in the central control room for operating and controlling the reactor of a nuclear couplant, and the foundation that will be installed on the floor of the central control room as a cable tray for the control panel.

中揉室床は、第7図に示した如く、制御盤1゜の形状及
び配置計画に従って基礎台4が設計され。
As shown in FIG. 7, the floor of the middle massage room has a base 4 designed according to the shape and layout plan of the control panel 1°.

その基礎台4間にはケーブルを通すための溝2゜が設け
られている。溝の深さは約500 m / m有り、こ
の溝を確保しながら基礎台を成型する方法として、前記
した如く建築一般に使用される合板等の組合せにより基
礎用型枠19を組み、基礎台4を成型する工法が採られ
ている。同図で、7は床スラブ、2.9は配筋、3はデ
ツキ・プレート。
A groove 2° is provided between the bases 4 for passing the cable through. The depth of the groove is approximately 500 m/m, and as a method of forming the foundation while securing this groove, as described above, the foundation form 19 is assembled from a combination of plywood etc. commonly used in construction, and the foundation 4 is assembled. A method of molding is used. In the same figure, 7 is the floor slab, 2.9 is the reinforcement, and 3 is the deck plate.

7はケーブル、8はさし筋、11は床板、12は合板、
13は支え板を示す。すなわち、合板12と支え板13
により基礎用型枠19が形成されている。
7 is a cable, 8 is a strut, 11 is a floorboard, 12 is a plywood,
13 indicates a support plate. That is, the plywood 12 and the support plate 13
A foundation formwork 19 is formed.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

ところが、従来の建造方法では、コンクリート養生後に
基礎用型枠を撤去する作業が残る。この撤去作業は人手
を要し、しかも原子炉プラントのような大型構造物の場
合は、−日に8時間労働として数日間以上を要し1人手
削減及び建造期間短スケジュールから考えた場合、6.
9  kV受電を行うためには建物の構築・機器設定・
電気系統始動と中操室の作業工程がクリティカル工程を
形成しているため、工程短縮を図る上で最も効率的な作
業工程を組み上げることが要求されていた。ここでクリ
ティカル工程とは一工程が終了しないと他工程に入れな
いことを意味する。
However, with conventional construction methods, the work of removing the foundation formwork remains after the concrete has cured. This removal work requires manpower, and in the case of large structures such as nuclear reactor plants, it takes more than several days with 8 hours of work per day. ..
In order to receive 9 kV power, building construction, equipment settings,
Since the electrical system start-up and the operation process for the central control room constitute critical processes, it was necessary to assemble the most efficient work process in order to shorten the process. Here, a critical process means that another process cannot be started until one process is completed.

そのため、本エリアで発生するコンクリート固化後の基
礎用型枠の撤去作業等は機器据付開始時期を遅らせるの
みでなく、機械側の工事開始後において、建築と機械の
両作業が錯湊し現地工数が増加する要因となっていた。
Therefore, work such as removing the foundation formwork after concrete hardens, which occurs in this area, not only delays the start of equipment installation, but also causes confusion between construction and mechanical work after the start of mechanical work, resulting in reduced on-site man-hours. was the cause of the increase.

本発明の目的は、人手削減及び建造期間の短縮を図れ、
また原子炉建物のような構造物であってもコンクリート
同化後は建築作業と機械据付作業とが錯湊しないコンク
リート構造物の建造方法を提供するにある。
The purpose of the present invention is to reduce manpower and construction period,
Another object of the present invention is to provide a method of constructing a concrete structure, such as a nuclear reactor building, in which construction work and machine installation work are not complicated after concrete assimilation.

〔問題点を解決するための手段〕[Means for solving problems]

本発明は、基礎用型枠を設置した後、コンクリートを打
設し、所定時間経過させて固化させるコンクリート構造
物の建造方法において、基礎用型枠に氷ブロックを用い
るものである。
The present invention is a method for constructing a concrete structure in which a foundation form is installed, concrete is poured, and then solidified after a predetermined period of time, in which ice blocks are used in the foundation form.

〔作用〕[Effect]

氷ブロックにより基礎用型枠を作り、コンクリート固化
後に氷ブロックを融解して水として流出させ、基礎用型
枠の撤去作業を不用にしたものである。また1人手によ
る撤去作業は1日8時間時間和限られてしまうが、氷の
融解には1日24時間使用できることを利用して早期融
解が可能になり、以って建造期間の短縮を図るものであ
る。
The foundation formwork is made from ice blocks, and after the concrete hardens, the ice blocks are melted and released as water, eliminating the need to remove the foundation formwork. In addition, although removal work by one person is limited to 8 hours a day, ice can be melted 24 hours a day, making it possible to melt ice earlier, thereby shortening the construction period. It is something.

〔実施例〕〔Example〕

以下、本発明の実施例を第1図乃至第3図を用いて説明
する6本実施例は原子炉プラントの中央制御室の床を建
造する場合であるが、本発明の氷ブロックはコンクリー
ト構造物全般に用いることができる。
Hereinafter, embodiments of the present invention will be explained with reference to FIGS. 1 to 3. Six embodiments are for constructing the floor of the central control room of a nuclear reactor plant, and the ice block of the present invention has a concrete structure. Can be used for all things.

第2図は中央制御室の床の平面図、第3図にその断面図
、第1図はコンクリート構造物の要部拡大断面図を示す
ものである。中揉室床は電気盤・制御盤設定用の基礎台
4と各制御盤10間を連絡するケーブル7用のトレーと
から成り立っている。
FIG. 2 is a plan view of the floor of the central control room, FIG. 3 is a sectional view thereof, and FIG. 1 is an enlarged sectional view of the main part of the concrete structure. The floor of the middle massage room is made up of a base 4 for setting electrical panels and control panels, and a tray for cables 7 that communicate between each control panel 10.

中揉室床の床スラブ1の打設手順は、スラブ下面に設け
られるデツキプレート3の設定用受梁14の工事完了後
、デツキプレート3を敷設し、その上に床スラブ1の主
筋である配筋3を取付ける。
The procedure for placing the floor slab 1 for the middle rolling room floor is that after completing the construction of the support beam 14 for setting the deck plate 3 provided on the bottom surface of the slab, the deck plate 3 is laid, and the main reinforcement of the floor slab 1 is placed on top of it. Install reinforcement 3.

その後コンクリートを打設して床スラブ1を打ち終る。After that, concrete is poured and floor slab 1 is finished.

次に基礎台4の主筋用さし筋8を取り付けて、そのさし
筋8を基盤として配筋9を設定する。基礎台4はその隣
りの基礎台4との間が500〜600m/m程度の距離
があり、基礎台4の高さも500m/m程度ある。
Next, the main reinforcing bars 8 of the foundation 4 are attached, and the reinforcing bars 9 are set using the inserts 8 as a base. The distance between the foundation pedestal 4 and the adjacent foundation pedestal 4 is approximately 500 to 600 m/m, and the height of the foundation pedestal 4 is also approximately 500 m/m.

各基礎台4間には、基礎用型枠として氷ブロック5を設
置する。この氷ブロック5を製造するブロック用型枠は
床スラブ1の作業エリア周辺か、または屋外等に設置し
ておくのが作業効率上の見地から望ましい。氷ブロック
5の製造については。
Ice blocks 5 are installed between each foundation 4 as a formwork for the foundation. From the viewpoint of work efficiency, it is desirable that the block formwork for manufacturing the ice blocks 5 be installed around the working area of the floor slab 1 or outdoors. Regarding the production of ice block 5.

このブロック型枠の中に水を流し込み、かつ、このブロ
ック用型枠の中にセットされた熱媒体輸送用の小口径の
熱媒体流路管6の内部に例えば液体窒素等の冷却媒体を
流すことによって、該流路管6が冷却されてブロック用
型枠内の水が氷って熱媒体流路管6を有する氷ブロック
5が製造される。
Water is poured into this block formwork, and a cooling medium such as liquid nitrogen is poured into the small diameter heat medium flow pipe 6 for transporting the heat medium set in this block formwork. As a result, the flow pipes 6 are cooled, the water in the block mold is frozen, and the ice block 5 having the heat medium flow pipes 6 is manufactured.

ここで、熱媒体流路管6は互いに連結可能に形成する。Here, the heat medium flow pipes 6 are formed so as to be connectable to each other.

この氷ブロック5をクレーンだ吊上げ、床スラブ1上の
所定の位置に順次設置して各流路管6を連結する。第1
図に示す長手方向(紙面に垂直な方向)にも同様な氷ブ
ロック5が設置されている。
The ice blocks 5 are lifted up by a crane and sequentially installed at predetermined positions on the floor slab 1 to connect each flow pipe 6. 1st
Similar ice blocks 5 are also installed in the longitudinal direction shown in the figure (direction perpendicular to the plane of the paper).

設置後は氷ブロック5の熱媒体流路管6の中に液体窒素
等の冷却媒体を流しておけば、氷ブロックが氷の融解温
度環境下に設置された場合でも該氷ブロック5が自然融
解により流れ去るのを防止できる。
After installation, if a cooling medium such as liquid nitrogen is flowed into the heat medium flow pipe 6 of the ice block 5, the ice block 5 will naturally melt even if the ice block is installed in an environment with the melting temperature of ice. This can prevent it from flowing away.

次に氷ブロック5に挟まれた基礎台4となるスペースに
コンクリートを打設する。これにより。
Next, concrete is placed in the space between the ice blocks 5 that will become the foundation 4. Due to this.

基礎台4の成型は完了する。コンクリート打設面はテコ
で仕上げて、必要な養生期間を経る。コンクリートが固
化して氷ブロック5が不要となった段階で熱媒体流路管
6への冷却媒体の供給をストップして氷を自然に溶かす
。または、加熱媒体を流して、より短期間で溶かす。溶
けた水は付近の仮設排水配管によって処理する。なお、
冬期の北海道の如く、氷ブロック5を氷の非融解温度環
境下で利用する場合は、打設したコンクリートが固化す
るまでは、熱媒体流路管6に冷却媒体を流す必要はなく
、コンクリート同化後に同流路管6内に加熱水のような
加熱媒体を流す。
The molding of the base 4 is completed. The concrete surface is finished using levers and the required curing period is completed. When the concrete hardens and the ice block 5 becomes unnecessary, the supply of cooling medium to the heat medium flow pipe 6 is stopped to naturally melt the ice. Or, run a heating medium through it to melt it in a shorter period of time. Melted water will be disposed of through nearby temporary drainage piping. In addition,
When the ice block 5 is used in an environment where ice does not melt, such as in Hokkaido during the winter, there is no need to flow the cooling medium through the heat transfer pipe 6 until the poured concrete has solidified, and the concrete assimilation Afterwards, a heating medium such as heated water is flowed into the flow path pipe 6.

このようにして、建築側の躯体工事が完了し、機械側の
盤据付工事が開始される段階になってもコンクリートの
基礎用型枠の撤去作業がなくなるので、同一エリアで建
築/機械の作業の錯湊がなくなると同時にプラント全般
としての工事工程のクリティカルパスを緩和することが
可能となる。
In this way, even when the structural work on the construction side is completed and the panel installation work on the machinery side begins, there is no need to remove the concrete foundation formwork, so construction and machinery work can be done in the same area. At the same time, it becomes possible to alleviate the critical path of the construction process for the entire plant.

また、氷ブロック5内に熱媒体流路管6を設けないで、
中操室雰囲気温度を氷の融解しない0℃近辺で管理して
、氷ブロック5の形状を維持させて、コンクリート基礎
台4の養生期間を確保することもできる。以上において
は、氷ブロック5の形状は四角柱体の場合について説明
したが、例えばブロック円型枠を第1図に示した氷ブロ
ック5と床材11を合わせた形状の氷ブロックを製造で
きるように形成すれば、建造後に床板11が基礎台4と
面一となる。
Moreover, without providing the heat medium flow pipe 6 in the ice block 5,
It is also possible to maintain the shape of the ice blocks 5 and secure the curing period of the concrete foundation 4 by controlling the atmospheric temperature of the central operation room at around 0° C., where the ice does not melt. In the above, the case where the shape of the ice block 5 is a rectangular prism has been explained, but for example, it is possible to manufacture an ice block having a shape that is a combination of the ice block 5 and the floor material 11 shown in FIG. If this is done, the floorboard 11 will be flush with the foundation 4 after construction.

第4図乃至第6図は、本発明の他実施例を示したもので
あり、原子炉格納容器17のペネトレーション18を貫
通させる生体遮蔽壁16の貫通穴の基礎用型枠について
本発明を適用したものである。この場合、ペネトレーシ
ョン18は既に固定されている状態で生体遮蔽壁16を
建造しなければならないため、氷ブロック5は前記で述
べたような単純な形状でなく、円筒形状の曲面から構成
されることになる。したがって、予め、流体を流し込む
ことによって同図に示す形状となるような被覆カバー1
5を準備しておき、この中に熱媒体流路管6を配設し、
その中に冷却媒体を流す。これにより同図に示す円筒形
状の氷ブロック5ができあがる。この氷ブロック5を生
体遮蔽壁16のコンクリート打設前にペネトレーション
18に被嵌させて〃設置することによってペネトレーシ
ョン18の貫通穴を生体遮蔽壁16に設けることが可能
となる。
4 to 6 show other embodiments of the present invention, in which the present invention is applied to a formwork for the foundation of a through hole in the biological shielding wall 16 through which the penetration 18 of the reactor containment vessel 17 is penetrated. This is what I did. In this case, since the biological shielding wall 16 must be constructed with the penetration 18 already fixed, the ice block 5 should not have a simple shape as described above, but be composed of a cylindrical curved surface. become. Therefore, in advance, the covering cover 1 is made into the shape shown in the figure by pouring fluid into it.
5 is prepared, a heat medium flow pipe 6 is arranged therein,
A cooling medium flows through it. As a result, a cylindrical ice block 5 shown in the figure is completed. By fitting and installing this ice block 5 over the penetration 18 before placing concrete for the biological shielding wall 16, it becomes possible to provide a through hole for the penetration 18 in the biological shielding wall 16.

コンクリート固化後は、前記と同様に氷を融解させ水と
して流し去り被覆カバー15及び熱媒体流路管6を取外
す。予め被覆カバー15を外しておけば、氷融解後の残
留物が熱媒体流路管6だけとなる。
After the concrete hardens, the ice is melted and washed away as water, and the covering cover 15 and the heat medium flow pipe 6 are removed in the same manner as described above. If the cover 15 is removed in advance, only the heat medium flow pipe 6 will remain after the ice melts.

〔発明の効果〕〔Effect of the invention〕

本発明によれば、基礎用型枠として氷ブロックを用いた
ので、コンクリート同化後の形枠撤去作業における人手
削減を図ることができ、更に−日24時間使用して氷を
融解させることができることによって時間短縮を図れ、
全体としてコンクリート構造物の建造期間を短縮するこ
とができる。
According to the present invention, since ice blocks are used as the foundation formwork, it is possible to reduce the number of labor involved in removing the formwork after concrete assimilation, and furthermore, the ice can be melted by using it 24 hours a day. Save time by
Overall, the construction period of the concrete structure can be shortened.

また、原子炉建物のような構造物の場合、コンクリート
養生後の機械側工事を行うに当たり、建築/4!械工事
の錯湊が改善されると共に、プラント建設工程の中でク
リティカルパスを形成している中操室建設作業工数の低
減を図ることが可能となる。
In addition, in the case of structures such as nuclear reactor buildings, construction/4! Not only will the complexity of mechanical work be improved, but it will also be possible to reduce the number of man-hours required to construct the central control room, which forms a critical path in the plant construction process.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の氷ブロック工法の適用例を示す基礎台
の断面図、第2図は中揉室床の平面図。 第3図は第2図のm−m線断面図、第4薗は本発明の他
実施例を示す要部断面図、第5図及び第6図は第4図の
氷ブロックの正面図及び断面図、第7図は中揉室床の従
来工法の型枠構造例を示す断面図である。 4・・・基礎台、5・・・氷ブロック、6・・・熱媒体
流路管、7・・・ケーブル、10・・・電゛気・制御盤
、15・・・被覆カバー、16・・・生体遮蔽壁、17
・・・原子炉格納容器、18・・・ヘネトレーション。
FIG. 1 is a sectional view of a foundation showing an application example of the ice block construction method of the present invention, and FIG. 2 is a plan view of the floor of the middle massage room. 3 is a sectional view taken along the line m-m in FIG. FIG. 7 is a cross-sectional view showing an example of the formwork structure of the conventional construction method for the floor of the middle kneading room. 4... Foundation stand, 5... Ice block, 6... Heat medium flow pipe, 7... Cable, 10... Electricity/control panel, 15... Sheathing cover, 16... ...Biological shielding wall, 17
... Reactor containment vessel, 18... Henetration.

Claims (1)

【特許請求の範囲】 1、基礎用型枠を設置した後、コンクリートを打設し、
所定時間経過させて固化させるコンクリート構造物の建
造方法において、基礎用型枠に氷ブロックを用いること
を特徴とするコンクリート構造物の建造方法。 2、特許請求の範囲第1項において、氷ブロックに熱媒
体流路管が設けられているコンクリート構造物の建造方
法。 3、特許請求の範囲第1項において、コンクリート構造
物が原子炉プラントの中央制御室の床であるコンクリー
ト構造物の建造方法。 4、特許請求の範囲第1項において、コンクリート構造
物が原子炉格納容器のペネトレーシヨンを貫通させる生
体遮蔽壁であるコンクリート構造物の建造方法。 5、特許請求の範囲第1項又は第3項において、コンク
リート打設後、コンクリートが固化するまで室内温度を
氷ブロックの融解を防止する温度まで低下し保持するコ
ンクリート構造物の建造方法。 6、特許請求の範囲第2項において、氷の融解温度環境
下に設置された氷ブロックの熱媒体流路管に打設したコ
ンクリートが固化するまで冷却媒体を流すコンクリート
構造物の建造方法。 7、特許請求の範囲第2項において、氷の非融解温度環
境下に設置された氷ブロックの熱媒体流路路に打設した
コンクリートが固化した後、加熱媒体を流すコンクリー
ト構造物の建造方法。
[Claims] 1. After installing the foundation formwork, pouring concrete;
A method for constructing a concrete structure in which the concrete structure is solidified over a predetermined period of time, the method comprising using ice blocks as a foundation formwork. 2. A method of constructing a concrete structure according to claim 1, wherein the ice block is provided with a heat medium flow pipe. 3. A method of constructing a concrete structure according to claim 1, wherein the concrete structure is a floor of a central control room of a nuclear reactor plant. 4. The method of constructing a concrete structure according to claim 1, wherein the concrete structure is a biological shielding wall that allows penetration of a nuclear reactor containment vessel. 5. A method for constructing a concrete structure according to claim 1 or 3, wherein after concrete is poured, the indoor temperature is lowered to a temperature that prevents ice blocks from melting and maintained until the concrete solidifies. 6. A method for constructing a concrete structure according to claim 2, in which a cooling medium is poured into a heat medium flow pipe of an ice block installed in an environment at an ice melting temperature until the concrete cast is solidified. 7. A method for constructing a concrete structure according to claim 2, in which a heating medium is poured after the concrete cast in the heating medium flow path of an ice block installed in an environment with a non-melting temperature of ice has solidified. .
JP8666587A 1987-04-08 1987-04-08 Method for building concrete structure Pending JPS63251546A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8666587A JPS63251546A (en) 1987-04-08 1987-04-08 Method for building concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8666587A JPS63251546A (en) 1987-04-08 1987-04-08 Method for building concrete structure

Publications (1)

Publication Number Publication Date
JPS63251546A true JPS63251546A (en) 1988-10-19

Family

ID=13893330

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8666587A Pending JPS63251546A (en) 1987-04-08 1987-04-08 Method for building concrete structure

Country Status (1)

Country Link
JP (1) JPS63251546A (en)

Similar Documents

Publication Publication Date Title
CN110439137B (en) Prefabricated wall board, wall body, prefabricated wall board production method and prefabricated wall body construction method
KR100731593B1 (en) A pre-fabricating forms for concrete-structure and the construction method thereof
CN114108917B (en) Height-adjustable assembly type composite floor slab construction method
CN213143104U (en) Hoisting type finished product earth retaining enclosure device
JPS63251546A (en) Method for building concrete structure
JP3511159B2 (en) Concrete casting method
CN112359965A (en) Precast concrete assembled structure with rib mold structure and construction method thereof
KR100392189B1 (en) Unit grille beam and construction method thereof
CN111206493A (en) Construction method for improving yield of pier stud steel bar protection layer and template device used by same
CN110843095A (en) Concrete box mould, manufacturing method thereof and mould-dismantling-free building method
JP2004092333A (en) Prestress force introducing method under temperature control, and steel concrete composite structure constructed by using the methods
CN100422463C (en) Cast in-site hollow shuttering component
RU2773897C1 (en) Method for manufacturing reinforced concrete buildings for substations
JPS6073936A (en) Construction of synthetic floor panel by using precast concrete panel changed in thickness in grid-like form
JPS62141242A (en) Construction of concrete floor panel
CN220815117U (en) Vertical L type connected node of high big wallboard of semi-prefabrication
KR100297426B1 (en) Glass block panel and manufacturing method of glass block panel
JPH0531604B2 (en)
CN206707087U (en) Cast-in-situ floor component and floor construction
JPH10219709A (en) Construction method of precast concrete foundation
CN110578334A (en) Lattice beam member, lattice beam, and method for laying lattice beam
JP3207276B2 (en) How to build a unit building
JPH03290528A (en) Fabrication method for equipment rack foundation
CN115164584A (en) Construction mode of refractory material in large rotary hearth furnace
CN117266190A (en) Prefabricated assembly type overlapped lattice beam ecological slope protection structure and construction method