JPS62141242A - Construction of concrete floor panel - Google Patents
Construction of concrete floor panelInfo
- Publication number
- JPS62141242A JPS62141242A JP28245385A JP28245385A JPS62141242A JP S62141242 A JPS62141242 A JP S62141242A JP 28245385 A JP28245385 A JP 28245385A JP 28245385 A JP28245385 A JP 28245385A JP S62141242 A JPS62141242 A JP S62141242A
- Authority
- JP
- Japan
- Prior art keywords
- formwork
- floor
- truss
- trusses
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05K—PRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
- H05K1/00—Printed circuits
- H05K1/02—Details
- H05K1/03—Use of materials for the substrate
- H05K1/0393—Flexible materials
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Panels For Use In Building Construction (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
「産業上の利用分野」
本発明は建物のコンクリート床版をノンサポートで構築
する方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a method for constructing a concrete floor slab for a building without support.
「従来の技術」
コンクリート床版を構築する方法の一つに、いわゆるノ
ンサポート構法がある。この構法は型枠工事の末文保工
や支保工のための構台等が不要な構法であり、現場作業
の合理化、省力化を図る上で極めて有効である。``Conventional technology'' One of the methods of constructing concrete slabs is the so-called non-support construction method. This method of construction does not require maintenance work at the end of the formwork work or pedestals for shoring, and is extremely effective in streamlining on-site work and saving labor.
従来のノンサポート構法の一例について説明すると、ま
ず、矩形の角部に位置するように配された辛i数の住(
グリッドを形成する配置で立設された往)の間に、矩形
の各辺を描くように複数の梁用トラスを架け渡す。次い
で、隣り合う二辺のうち一方の辺を形成する乗用トラス
と平行な複数の床用トラスを他方の辺を形成する梁組ト
ラス間に架け渡す。そして、各床用トラスおよびこれと
平行な乗用トラスに、その下弦材の下側に位置するよう
に底板を取り付け、これら底板間に型枠(例えばプラス
チック板)を架け渡した後、これら型枠の上にコンクリ
ート床版を打設する。To explain an example of the conventional non-support construction method, first, we will start with a simple i-numbered housing located at the corner of a rectangle.
A plurality of beam trusses are laid across each side of a rectangle between the beams, which are erected to form a grid. Next, a plurality of floor trusses parallel to the passenger truss forming one of the two adjacent sides are bridged between the beam trusses forming the other side. Then, attach a bottom plate to each floor truss and the passenger truss parallel to it so that it is located below the lower chord member, and after spanning the formwork (for example, a plastic plate) between these bottom plates, A concrete slab will be poured on top of the concrete slab.
「発明が解決しようとする問題点」
上記の構法は、現場作業の合理化のみならず、底板や型
枠を工場生産することにより高品質、高精度化をも実現
することができる。しかしながら、この構法においても
例えば次のような点で検討の余地が残されていた。"Problems to be Solved by the Invention" The construction method described above not only streamlines on-site work, but also achieves high quality and precision by producing the bottom plate and formwork in a factory. However, even with this construction method, there was still room for consideration in the following points, for example.
■コンクリート床版の硬化後に底板および型枠の取り外
し作業を要する点。■The bottom plate and formwork must be removed after the concrete slab has hardened.
■一つのグリッドが9mX9111以上となった場合に
型枠の強度が不十分である点。■The strength of the formwork is insufficient when one grid is 9m x 9111 or more.
本発明は上記の事情に鑑みてなされたもので、その目的
とするところは、現場作業をさらに合理化および省力化
し、かつ、少ない物量でしから高強度の床版構造を実現
する新規なノンザボート購法(コンクリート床版の11
カ築方法)を提供することにある。The present invention was made in view of the above circumstances, and its purpose is to further streamline and save labor on site work, and to create a new non-the-boat structure that achieves a high-strength deck structure with a small amount of material. Act (11 of concrete floor slabs)
The objective is to provide a method of building
「問題点を解決するための手段」
かかる目的を達成するために本発明は、(イ)、複数の
乗用トラスが横一列にほぼ平行に並べられ、かつ、これ
ら乗用トラスの下弦材が一枚のプレキャストコンクリー
ト板内に埋設されてなる梁型枠と、
(ロ)、複数本の床用トラスが横一列にほぼ平行に並べ
られ、これら床用トラスの下弦材が一枚のプレキャスト
コンクリート板内に埋設され、しかも、各床用トラス間
のプレキャストコンクリート板上に床用トラスの延在方
向に沿う中空の型枠構成体が配設されてなる床版型枠と
を使用し、(ハ)、複数の梁型枠を柱の間に互いに平行
に架け渡した後、
(ニ)、梁型枠同士の間に床版型枠を架け渡し、(ホ)
1次いで、梁型枠および床版型枠上にコンクリート板を
打設するようにしたことを特徴とする。"Means for Solving the Problems" In order to achieve the above object, the present invention provides (a) a plurality of passenger trusses arranged horizontally in a row substantially parallel to each other, and a lower chord member of each of these passenger trusses is one piece. (b) A plurality of floor trusses are lined up horizontally in a horizontal row, and the lower chord members of these floor trusses are placed inside a single precast concrete plate. (c) using a floor slab formwork which is buried in the floor truss and in which a hollow formwork structure is arranged along the extending direction of the floor truss on a precast concrete plate between each floor truss; , After constructing multiple beam forms parallel to each other between the columns, (d), installing floor slab forms between the beam forms, (e)
First, a concrete plate is placed on the beam formwork and the floor slab formwork.
「作用」
本発明によれば、型枠としてトラスと一体のプレキャス
トコンクリート板を使用するので強度か高く、しかも、
この型枠は工場等において予め製造されており、かつ、
コンクリート板硬化後も取り外しが不要であるので現場
作業の効率が高い。"Function" According to the present invention, since the precast concrete plate integrated with the truss is used as the formwork, the strength is high, and
This formwork is manufactured in advance in a factory etc., and
There is no need to remove the concrete board even after it has hardened, making site work more efficient.
「実施例」
以下、本発明の一実施例を図面に基づいて工程順に説明
する。"Example" Hereinafter, an example of the present invention will be described in order of steps based on the drawings.
!、工場生産
(イ)、梁型枠の製造
工場等において、第1図、第2図に示すような梁型枠l
を製造する。この梁型枠Iは複数の梁川トラス2・・・
を横一列に平行に並べた状態で、これら梁組トラス2の
下弦材2aをプレキャストコンクリート板3内に埋設し
たものである。プレキャストコンクリート板3の両側縁
部には乗用トラス2の延在方向に沿う側壁部3aが立設
されている。な七;−i−中協鋤1プ浦田土4っス優r
TTk石フ9I士 笛言図のように下弦材2aと、これ
に平行な上弦+$2bとに対し、これらの間の空間を三
角形状に区分するラヂス材2cを組み合わせたものであ
る。また、図中符号4はメツシュ筋である。! , Factory production (a) In beam formwork manufacturing factories, beam formwork l as shown in Figures 1 and 2 is produced.
Manufacture. This beam formwork I has multiple Yanagawa trusses 2...
The lower chord members 2a of these beam trusses 2 are buried in a precast concrete plate 3, with the lower chord members 2a of the beam truss 2 arranged horizontally in parallel. On both side edges of the precast concrete plate 3, side wall portions 3a are erected along the extending direction of the riding truss 2. Na7;-i-Chuukyoho 1pu Urata soil 4suu r
As shown in the flute diagram, this is a combination of a lower chord member 2a, an upper chord +$2b parallel to this, and a radius member 2c that divides the space between them into triangular shapes. Further, reference numeral 4 in the figure is a mesh muscle.
(ロ)、床版型枠の製造
上記(イ)の工程と同時にあるいは前後して、第3図に
示ずような床版型枠5を製造する。この床版型枠5は、
梁型枠lとほぼ同様、複数の床用トラス6を平行に並べ
てその下弦材6aをプレキャストコンクリート板7内に
埋設したものである。各床用トラス6は乗用トラス2と
ほぼ同様、下弦材6aの他に上弦材6b、ラチスtオ6
Cを備えている。ただし、床用トラス6は乗用トラス2
より高さく下弦材6aから上弦材6bまでの距離)Hが
低く、小型に形成されている。そして、各床用トラス6
の間には型枠構成体8が固定されている。型枠構成体8
は、例えばスタイロフォームであり、床用トラス6の延
在方向に沿う長尺の箱(中空)を伏せfこ如き形状をな
している。(b) Manufacture of floor slab formwork Simultaneously with or before or after the above step (a), a floor slab formwork 5 as shown in FIG. 3 is manufactured. This floor slab formwork 5 is
Almost like the beam form 1, a plurality of floor trusses 6 are arranged in parallel, and their lower chord members 6a are buried in a precast concrete plate 7. Each floor truss 6 is almost the same as the passenger truss 2, in addition to the lower chord member 6a, the upper chord member 6b, and the lattice
It is equipped with C. However, the floor truss 6 is the passenger truss 2.
The height (distance from the lower chord member 6a to the upper chord member 6b) H is low, and it is formed small. And each floor truss 6
A formwork structure 8 is fixed between them. Formwork structure 8
is made of styrofoam, for example, and has the shape of a long box (hollow) extending along the extending direction of the floor truss 6 turned upside down.
11、現場作業工程
(ハ)梁型枠の架け渡し工程
上記(イ〕の工程で製造した複数の梁型枠Iを第4図の
如く住9・9の間に互いに平行に架け渡す。11. On-site work process (c) Beam formwork installation process A plurality of beam formworks I manufactured in the above process (a) are installed parallel to each other between the houses 9 and 9 as shown in FIG.
このときの架け渡し方向は両用トラス2の延在方向とす
る。ただし、本実施例において、各柱9は第6図の如く
鉄筋の周囲にスチール型枠10を取り付けた状態(コン
クリート打設前の状態)のものであり、全体としてはグ
リッドを形成する配置で立設されている。従って、梁型
枠lはスチール型枠10に支持させる。The spanning direction at this time is the direction in which the dual-purpose truss 2 extends. However, in this embodiment, each column 9 has a steel formwork 10 attached around the reinforcing bars as shown in FIG. 6 (before concrete is poured), and the overall arrangement is to form a grid. It is erected. Therefore, the beam formwork l is supported by the steel formwork 10.
(ニ)、床版型枠の架け渡し工程
上記(ハ)の工程で架け渡した複数の梁型枠l・lの間
に、上記(ロ)の工程で製造した複数の床板型枠5・・
・を第5図の如く架け渡す。このときの架け渡し方向は
床用トラス6の延在方向とし、床版型枠5の架け渡し方
向の°両端部を第6図の如く梁型枠1の側壁部3aの上
に載せるようにする。(d) Floor slab formwork installation step Between the plurality of beam formworks L and L constructed in the step (c) above, the plurality of floor plate formworks 5 and 5 manufactured in the step (b) above are・
- Bridge as shown in Figure 5. The spanning direction at this time is the extending direction of the floor truss 6, and both ends of the floor slab formwork 5 in the spanning direction are placed on the side walls 3a of the beam formwork 1 as shown in FIG. do.
(ポ)、コンクリート板の打設工程
上記(ニ)の工程の後、乗用トラス2および床用トラス
6の上に第7図の如くメツシュ筋11を敷設し、しかる
後に、梁型枠lおよび床版型枠5の上に第6図鎖線の如
くコンクリート板12を打設する。(Po) Concrete plate casting process After the above process (D), mesh reinforcements 11 are laid on the passenger truss 2 and the floor truss 6 as shown in Fig. 7, and then the beam form l and A concrete plate 12 is placed on the floor slab formwork 5 as shown by the chain line in FIG.
つまり、コンクリート板12が硬化すれば第8図に示す
ようなコンクリート床版F1すなイつち、梁型枠!、床
板型枠5、およびコンクリート板12が一体となった床
版が完成する。ちなみに、完成状態におけるコンクリー
ト床版Fはその床版型枠5の部分が型枠構成体8・・・
の存在により、第9図の如く中空部Sを有する構造とな
る。ただし、第9図において符号13は、床版型枠5同
士の継目の上に配設されたボイド(小型の型枠構成体)
である。In other words, if the concrete plate 12 hardens, it will become a concrete slab F1 as shown in Fig. 8, which means a beam formwork! , the floor plate formwork 5, and the concrete plate 12 are integrated to complete a floor slab. By the way, in the concrete slab F in the completed state, the part of the slab formwork 5 is the formwork structure 8...
Due to the presence of , a structure having a hollow portion S as shown in FIG. 9 is obtained. However, in FIG. 9, the reference numeral 13 indicates a void (a small formwork structure) arranged above the joint between the floor slab formworks 5.
It is.
なお、上記実施例においては型枠構成体8を工場にて床
版型枠5に取り付けるようにしたが、現場で取り付ける
ようにしてもよい。In the above embodiment, the formwork structure 8 is attached to the floor slab formwork 5 at the factory, but it may be attached at the site.
「発明の効果」
以上説明したように本発明によれば、トラスおよびプレ
キャストコンクリート造りの梁型枠ならびに床版型枠を
用い、複数の梁型枠を柱の間に架け渡した後、梁型枠同
士の間に床版型枠を架け渡し、これらの上にコンクリー
トを打設してコンクリート床版を構築するようにしたの
で、次のような優れた効果を得ることができる。"Effects of the Invention" As explained above, according to the present invention, beam formwork and floor slab formwork made of trusses and precast concrete are used, and after a plurality of beam formworks are spanned between columns, the beam formwork is By constructing a concrete slab by placing slab forms between the frames and pouring concrete on top of them, the following excellent effects can be obtained.
■床皮保工や構台等が不要であるばかりか、梁型枠およ
び床版型枠を工場生産することにより型枠工および鉄筋
工等を大幅に省力化することができろ。また、両型枠が
完成時のコンクリート床版の一部となるから、これら型
枠の取り外しが不要である。つまり、現場作業が著しく
合理化かつ省力化され、工期の短縮を図ることができる
。■Not only does floor skin maintenance and gantry work become unnecessary, but by producing beam formwork and floor slab formwork in a factory, it is possible to significantly reduce the labor involved in form work and reinforcing bar work. Furthermore, since both formworks become part of the concrete slab upon completion, there is no need to remove these formworks. In other words, on-site work is significantly streamlined and labor-saving, and the construction period can be shortened.
■トラスとプレギヤストコンクリートとを一体化した型
枠を使用するからノンサポートの型枠としての強度が浸
れており、また、これら型枠を工場生産ずろことにより
精度の高い骨組み構造となる。■The use of formwork that integrates the truss and pregeasted concrete provides the strength of a non-support formwork, and since these formworks are manufactured in a factory, the frame structure is highly precise.
さらに、型枠構成体により床版自体が軽量となる。Furthermore, the formwork structure makes the floor slab itself lightweight.
従って、大きいグリッド、例えば110mX9程度の長
方形グリッドを形成するように配された柱に対してコン
クリート床版を構築する場合にも好適である。Therefore, it is also suitable when constructing a concrete slab for columns arranged to form a large grid, for example, a rectangular grid of about 110 m x 9.
■梁を偏平粱とすることができるから同じ天井高でら階
高を低くすることができる。つまり、建物全体の軒高を
低くできるから、日陰および斜線制限に対し有利である
。また、梁高を低くできるから、配管、ダクト等を自由
に敷設することができる。■Since the beams can be made flat, the floor height can be lowered with the same ceiling height. In other words, the eave height of the entire building can be lowered, which is advantageous in terms of shade and diagonal line restrictions. Furthermore, since the beam height can be lowered, piping, ducts, etc. can be laid freely.
■面内剛性が高い床版を構築できるから、地震時の水平
力を周辺の耐震壁に伝え易い。従って、周囲を耐震壁で
囲まれた大きなボックス構造とする計画が可能となり、
間仕切りの変更等には非常に有効なためフレキシブルな
配置計画が可能となる。■Since it is possible to construct a floor slab with high in-plane rigidity, horizontal force during an earthquake can be easily transmitted to surrounding seismic walls. Therefore, it is possible to plan a large box structure surrounded by seismic walls,
It is very effective for changing partitions, etc., and allows for flexible layout planning.
第1図〜第9図は本発明の一実施例を工程順に示すもの
で、第1図は梁型枠の縦断面図、第2図は第1図の■−
■線矢視図、第3図は床板型枠の横断面図、第4図は梁
型枠の架け渡し工程を説明する平面図、第5図は床板型
枠の架け渡し工程を説明する平面図、第6図は第5図の
vt−vt線矢視図、第7図はコンクリート板の打設工
程を説明する平面図、第8図はコンクリート床版の完成
状態を示す斜視図、第9図は完成状態のコンクリート床
版の断面図である。
■・・・・・・梁型枠、2・・・・・・梁用トラス、2
a、6a・・・・・・下弦材、3.7・・・・・・プレ
キャストコンクリート阪、5・・・・・・床版型枠、6
・・・・・・床用トラス、8・・・・・・型枠構成体、
9・・・・・・柱、12・・・・・・コンクリート板。Figures 1 to 9 show an embodiment of the present invention in the order of steps. Figure 1 is a vertical cross-sectional view of a beam formwork, and Figure 2 is a
■ Linear view, Figure 3 is a cross-sectional view of the floor plate formwork, Figure 4 is a plan view explaining the process of constructing the beam formwork, and Figure 5 is a plan view explaining the process of constructing the floor plate formwork. Fig. 6 is a view taken along the line vt-vt in Fig. 5, Fig. 7 is a plan view explaining the process of placing a concrete plate, Fig. 8 is a perspective view showing the completed state of the concrete slab, and Fig. Figure 9 is a cross-sectional view of the completed concrete slab. ■・・・Beam formwork, 2・・・Beam truss, 2
a, 6a...Bottom chord material, 3.7...Precast concrete slope, 5...Floor slab formwork, 6
...... Floor truss, 8... Formwork structure,
9...Column, 12...Concrete plate.
Claims (1)
ており、これら柱に支持されるコンクリート床版を構築
する方法において、下記(イ)、(ロ)、(ハ)、(ニ
)、(ホ)の工程を有することを特徴とするコンクリー
ト床版の構築方法。 (イ)、複数の梁用トラスが横一列にほぼ平行に並べら
れ、かつ、これら梁用トラスの下弦材が一枚のプレキャ
ストコンクリート板内に埋設されてなる梁型枠を製造す
る工程。 (ロ)、複数本の床用トラスが横一列にほぼ平行に並べ
られ、これら床用トラスの下弦材が一枚のプレキャスト
コンクリート板内に埋設され、しかも、各床用トラス間
のプレキャストコンクリート板上に床用トラスの延在方
向に沿う中空の型枠構成体が配設されてなる床版型枠を
製造する工程。 (ハ)、複数の梁型枠を上記柱の間に互いに平行に架け
渡す工程。 (ニ)、上記(ハ)の工程の後、梁型枠同士の間に床版
型枠を架け渡す工程。 (ホ)、上記(ニ)の工程の後、梁型枠および床版型枠
上にコンクリート板を打設する工程。[Scope of Claims] A method for constructing a concrete slab in which a plurality of columns are arranged so as to be located at substantially corners of a rectangle and supported by these columns includes the following (a) and (b). , (C), (D), and (E). (a) A process of manufacturing a beam formwork in which a plurality of beam trusses are arranged horizontally in a row and substantially parallel, and the lower chords of these beam trusses are buried in a single precast concrete board. (b) A plurality of floor trusses are arranged horizontally in a row almost parallel to each other, the lower chord of these floor trusses is buried within a single precast concrete board, and the precast concrete board between each floor truss is A process of manufacturing a floor slab formwork on which a hollow formwork structure is arranged along the extending direction of the floor truss. (c) A step in which a plurality of beam forms are laid parallel to each other between the columns. (d) After the step (c) above, the step of installing the floor slab formwork between the beam forms. (e) After the step (d) above, a step of placing concrete plates on the beam formwork and floor slab formwork.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP28245385A JPS62141242A (en) | 1985-12-16 | 1985-12-16 | Construction of concrete floor panel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP28245385A JPS62141242A (en) | 1985-12-16 | 1985-12-16 | Construction of concrete floor panel |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS62141242A true JPS62141242A (en) | 1987-06-24 |
JPH0312184B2 JPH0312184B2 (en) | 1991-02-19 |
Family
ID=17652621
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP28245385A Granted JPS62141242A (en) | 1985-12-16 | 1985-12-16 | Construction of concrete floor panel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS62141242A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01287369A (en) * | 1988-05-12 | 1989-11-20 | Mitsui Constr Co Ltd | Structure of resin formwork to be driven-in for hollow slab construction work |
JPH0448317U (en) * | 1990-08-30 | 1992-04-24 | ||
JP2008223370A (en) * | 2007-03-14 | 2008-09-25 | Haneda Concrete Industrial Co Ltd | Rigidly connecting structure of corner part |
JP2011089390A (en) * | 2010-10-29 | 2011-05-06 | Haneda Concrete Industrial Co Ltd | Rigid connection structure of corner section |
JP2017002655A (en) * | 2015-06-15 | 2017-01-05 | 株式会社竹中工務店 | Flat slab structure |
JP2020059983A (en) * | 2018-10-05 | 2020-04-16 | 株式会社竹中工務店 | Base floor structure and construction method of base floor |
-
1985
- 1985-12-16 JP JP28245385A patent/JPS62141242A/en active Granted
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH01287369A (en) * | 1988-05-12 | 1989-11-20 | Mitsui Constr Co Ltd | Structure of resin formwork to be driven-in for hollow slab construction work |
JPH0448317U (en) * | 1990-08-30 | 1992-04-24 | ||
JP2008223370A (en) * | 2007-03-14 | 2008-09-25 | Haneda Concrete Industrial Co Ltd | Rigidly connecting structure of corner part |
JP2011089390A (en) * | 2010-10-29 | 2011-05-06 | Haneda Concrete Industrial Co Ltd | Rigid connection structure of corner section |
JP2017002655A (en) * | 2015-06-15 | 2017-01-05 | 株式会社竹中工務店 | Flat slab structure |
JP2020059983A (en) * | 2018-10-05 | 2020-04-16 | 株式会社竹中工務店 | Base floor structure and construction method of base floor |
Also Published As
Publication number | Publication date |
---|---|
JPH0312184B2 (en) | 1991-02-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8915042B2 (en) | Steel frame structure using U-shaped composite beam | |
CN206053131U (en) | Precast floor slab steel reinforcement cage component and floor | |
US20040098934A1 (en) | Load bearing building panel | |
JPS62141242A (en) | Construction of concrete floor panel | |
JP3315492B2 (en) | Floor beam construction method | |
JPH04323435A (en) | Assembling type construction | |
JPH0122827Y2 (en) | ||
JP2928002B2 (en) | Column formwork structure | |
JPH07292828A (en) | Precast synthesized voiod slab and structure thereof | |
JP2567805B2 (en) | Method for constructing multi-lattice slab, forming form for multi-lattice beam used in the constructing method, fixing jig for parallel flap square timber, reinforcing bar frame arrangement method, break-away forming form for multi-lattice beam, and multi-lattice beam Fixing jig for removing mold | |
CN217517874U (en) | Hidden column wall structure | |
CN217580287U (en) | Building structure of underground station | |
JP3207276B2 (en) | How to build a unit building | |
JPH0332678Y2 (en) | ||
JPS6222566Y2 (en) | ||
TW200930868A (en) | Waffle storey structure | |
JP3751727B2 (en) | Precast concrete boards, concrete slabs and structures | |
JPS61126255A (en) | Reverse flat slab structure | |
JP3751726B2 (en) | Precast concrete boards, concrete slabs and structures | |
CN112922144A (en) | Fabricated building construction method | |
GB2226061A (en) | Permanent formwork panels and structures | |
JPS6349773B2 (en) | ||
JPS63261037A (en) | Execution of waffle slab and lower constitution body of waffle slab | |
JPH0144686Y2 (en) | ||
JPH0194139A (en) | Construction of taper slab |