JPS63181893A - Reinforcing iron plate for tunnel lining - Google Patents

Reinforcing iron plate for tunnel lining

Info

Publication number
JPS63181893A
JPS63181893A JP62013036A JP1303687A JPS63181893A JP S63181893 A JPS63181893 A JP S63181893A JP 62013036 A JP62013036 A JP 62013036A JP 1303687 A JP1303687 A JP 1303687A JP S63181893 A JPS63181893 A JP S63181893A
Authority
JP
Japan
Prior art keywords
concrete
main body
ring
iron plate
tunnel lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP62013036A
Other languages
Japanese (ja)
Inventor
富雄 田村
和彦 松崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP62013036A priority Critical patent/JPS63181893A/en
Publication of JPS63181893A publication Critical patent/JPS63181893A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (a)、産業上の利用分野 本発明は、シールド掘削機により掘削されたトンネルの
覆工を、現場打ちのコンクリートで構築する際に使用す
るに好適なトンネル覆工用補強鉄板に関する。
Detailed Description of the Invention (a) Industrial Application Field The present invention provides a tunnel lining suitable for use when constructing a tunnel lining excavated by a shield excavator with cast-in-place concrete. Concerning reinforcing steel plates.

(b)8発明が解決しようとする問題点通常、トンネル
の覆工を現場打ちのコンクリートで構築する際には、ま
ず前回打設して形成した覆工の端面から所定距離に亙り
型枠を用いて筒状のコンクリ−1〜打打設量を形成し、
その中にコンクリートを注入する形で構築する。この際
、該コンクリート打設空間には、コンクリート補強部材
として、その外周面に多数の穴が穿設された筒状の補強
鉄板を設置するが、該補強鉄板には、コンクリ−1へ打
設空間に注入したコンクリートが外部に流出するのを防
ぐために、妻止めが設けられる。
(b) 8 Problems to be Solved by the Invention Normally, when constructing a tunnel lining using cast-in-place concrete, formwork is first placed over a predetermined distance from the end face of the lining that was previously cast. Use to form a cylindrical concrete 1 to pouring amount,
It will be constructed by pouring concrete into it. At this time, a cylindrical reinforcing iron plate with many holes bored on its outer circumferential surface is installed as a concrete reinforcing member in the concrete pouring space. Gables are installed to prevent concrete poured into the space from flowing outside.

しかし、妻止めが、補強鉄板に穿設された穴の部分に配
置されると、該穴を通して漏水する危険性があり、何ら
かの対策が望まれていた。
However, if the stopper is placed in a hole drilled in the reinforcing iron plate, there is a risk that water will leak through the hole, and some kind of countermeasure has been desired.

本発明は、上記事情に鑑み、妻止め部分からの漏水を効
果的に防止することが出来るトンネル覆工用補強鉄板を
提供することを目的とする。
In view of the above circumstances, an object of the present invention is to provide a reinforcing iron plate for tunnel lining that can effectively prevent water leakage from the end stop portion.

(C)2間層点を解決するための手段 即ち、本発明は、筒状に形成された本体(12A)を有
し、前記本体(12A)に、端面(12a)から所定距
離(L2)の範囲に互って無穴領域(ARA)を形成す
ると共に、前記無穴領域(ARAC外の本体部分(12
A)に複数個の穴(12c)を貫通穿設し、更に、前記
無穴領域(ARA>内の本体(12A)部分に、環状に
形成された妻止め(22)を設けて構成される。
(C) Means for solving the interlayer point, that is, the present invention has a main body (12A) formed in a cylindrical shape, and a predetermined distance (L2) from the end face (12a) to the main body (12A). A non-perforated area (ARA) is formed in the range of , and a main body portion (12
A) has a plurality of holes (12c) drilled through it, and a ring-shaped end stop (22) is further provided in the main body (12A) within the non-hole area (ARA). .

なお、括弧内の番号等は、図面における対応する要素を
示す、便宜的なものであり、従って、本記述は図面上の
記載に限定拘束されるものではない。以下のr (d)
、作用」の欄についても同様である。
Note that the numbers in parentheses are for convenience and indicate corresponding elements in the drawings, and therefore, this description is not limited to the descriptions on the drawings. r (d) below
The same applies to the column ``, action''.

(891作用 上記した構成により1本発明は、無穴領域(ARA)に
設けられた妻止め(22)及び前記無穴領域(ARA)
が、長い水道を形成するように作用する。
(891 Effect) With the above-described configuration, the present invention provides an end stop (22) provided in the non-perforated area (ARA) and the end stop (22) provided in the non-perforated area (ARA).
acts to form a long aqueduct.

(e)、実施例 以下、本発明の実施例を図面に基づき説明する。(e), Example Embodiments of the present invention will be described below based on the drawings.

第1図は本発明によるトンネル覆工用補強鉄板が用いら
れる覆工の構築現場の様子を示す図、第2図は第1図の
II−n線による断面図、第3図は第1図のm−FIT
線による断面図、第4図はシールド掘削機のジヤツキ部
分の拡大図、 第5図は第4図の■−v線による断面図。
Fig. 1 is a diagram showing a construction site of a tunnel lining in which the reinforcing iron plate for tunnel lining according to the present invention is used, Fig. 2 is a cross-sectional view taken along line II-n in Fig. 1, and Fig. 3 is a diagram showing the construction site of a tunnel lining in which the reinforcing iron plate for tunnel lining according to the present invention is used. m-FIT
4 is an enlarged view of the jacking part of the shield excavator, and FIG. 5 is a sectional view taken along line ■-v in FIG. 4.

第6図乃至第13図はトンネル覆工用補強鉄板を用いて
、覆工を構築する様子を示す工程図。
FIG. 6 to FIG. 13 are process diagrams showing how a tunnel lining is constructed using reinforcing iron plates for tunnel lining.

第14図は本発明によるトンネル覆工用補強鉄板の一実
施例を示す斜視図である。
FIG. 14 is a perspective view showing an embodiment of a reinforcing iron plate for tunnel lining according to the present invention.

シールド掘削機1は、第1図に示すように。The shield excavator 1 is as shown in FIG.

円筒状に形成された外222を有しており、外殻2の前
面、即ち第1図左側面にはカッタ3が回転自在に支持さ
九ている。カッタ3は、外殻2内部の空間を左右方向に
遮断する形で設けられた外殻2の隔壁2aに設けられた
駆動モータ5と接続しでおり、更に隔壁2aには掘進用
ジヤツキ6が複数個、第1図及び第2図に示すように、
外殻2に沿った形で円環状に配列設置されている。掘進
用ジ”v ツキ6にはラム6aが、矢印A、B方向に突
出後退自在に設けられており、更に外殻2の内側には、
円筒状に形成されたプレスリング7が1匁殻2内面と接
する形で、矢印A、B方向に摺動自在に設けられている
It has a cylindrical outer shell 222, and a cutter 3 is rotatably supported on the front surface of the outer shell 2, that is, the left side surface in FIG. The cutter 3 is connected to a drive motor 5 provided on a partition wall 2a of the outer shell 2, which is provided to block the space inside the outer shell 2 in the left-right direction. A plurality of pieces, as shown in FIGS. 1 and 2,
They are arranged in a circular ring along the outer shell 2. A ram 6a is provided on the digging lever 6 so as to be able to protrude and retreat in the directions of arrows A and B, and further inside the outer shell 2, a ram 6a is provided.
A cylindrical press ring 7 is provided in contact with the inner surface of the one-monme shell 2 and is slidable in the directions of arrows A and B.

プレスリング7には、第2図に示すように、所定の間隔
でプレスリングジヤツキ9が、外殻2に沿った形で複数
個配置されてお+J、更にそれ等プレスリングジヤツキ
9の間には、第2図及び第5図に示すように、複数個の
=ンクリート吐出管10が、先端の吐出口LOaをプレ
スリング7の側面7a、即ちシールド掘削機1の後方に
向けた形で設けられている。コンクリ−1−吐出管10
には、吐出管清掃用のシリンダ10bがロッド10Cを
矢印C,D方向に突出後退自在にした形で設けられてお
り、更に吐出管1oにはコンクリート供給ホース30が
接続している。
As shown in FIG. 2, the press ring 7 has a plurality of press ring jacks 9 arranged at predetermined intervals along the outer shell 2, and furthermore, the press ring jacks 9 are arranged at predetermined intervals along the outer shell 2. As shown in FIG. 2 and FIG. It is set in. Concrete 1-Discharge pipe 10
A cylinder 10b for cleaning the discharge pipe is provided with a rod 10C that can protrude and retreat in the directions of arrows C and D, and a concrete supply hose 30 is connected to the discharge pipe 1o.

ところで、掘進用ジヤツキ6のラム6aの先端には、円
環状に形成されたゲージリング11が、装着されており
、ゲージリング11には、54図に示すように、保合溝
Llaがゲージリングllの全周にわたり環状に穿設形
成されている。また、ゲージリンク11の図中右方には
、トンネル覆工用の補強鉄板12が、組立て配でさiて
いる、補強鉄板12は、第14図シこ示すように、円筒
状の本体12Aを有しており、水体12Aの切羽側端面
12aは、第4図に示すように、係合溝11aに嵌入し
ている。また、本体12Aには、後述のコンクリート流
通用の穴12cが穿設されていない無穴領域ARAが、
切羽側端面12aからB方向に所定距6L2の範囲に互
って円環状に形成さ九ており、無穴領域ARA内の本体
12A部分には、円環状に形成された妻止め22が、ゲ
ージリンク11の第4図GgJ面と密接する形で設けら
iでいる。妻止め22は、第14図に示すように、外リ
ング22 a及び内リング22bを有しており、外リン
グ22aは1本体L2Aの外周而12bに、接合部12
dを介して接続されている。
By the way, a gauge ring 11 formed in an annular shape is attached to the tip of the ram 6a of the digging jack 6, and a retaining groove Lla is formed in the gauge ring 11, as shown in Fig. 54. It is perforated in an annular shape around the entire circumference of the ll. Further, on the right side of the gauge link 11 in the figure, a reinforcing iron plate 12 for tunnel lining is assembled and installed.The reinforcing iron plate 12 has a cylindrical main body 12A as shown in FIG. As shown in FIG. 4, the face-side end surface 12a of the water body 12A is fitted into the engagement groove 11a. In addition, in the main body 12A, there is a hole-free area ARA in which holes 12c for concrete distribution, which will be described later, are not drilled.
They are formed in an annular shape mutually over a predetermined distance 6L2 in the B direction from the face side end surface 12a, and in the main body 12A portion within the no-hole area ARA, an end stop 22 formed in an annular shape is attached to the gauge. It is provided in close contact with the GgJ surface in FIG. 4 of the link 11. As shown in FIG. 14, the end stopper 22 has an outer ring 22a and an inner ring 22b.
connected via d.

また内リング22bは、外リング22aに整合する形で
1本体12Aの内周面12fに、接合部12gを介して
接続されており、更に、無穴領域ARA外の本体L2A
部分には、コンクリ−1−流通用の穴12 cが複数個
、円周上に所定ピッチ間隔で、かつ矢印A、B方向に互
いに所定距離だけ離れる形で貫通穿設さ九でいる。
In addition, the inner ring 22b is connected to the inner circumferential surface 12f of the main body 12A via the joint 12g in a manner that matches the outer ring 22a, and furthermore, the inner ring 22b is connected to the inner peripheral surface 12f of the main body 12A through the joint 12g.
A plurality of holes 12c for the passage of concrete are drilled through the portion at predetermined pitch intervals on the circumference and spaced apart from each other by a predetermined distance in the directions of arrows A and B.

また、ゲージリング11には、第2図及び第3図に示す
ように1円環状に組立られた型枠13が、第1図左右方
向に接続された形で設けられている。
Further, the gauge ring 11 is provided with a formwork 13 assembled in a ring shape as shown in FIGS. 2 and 3 and connected in the left-right direction in FIG. 1.

シールド掘削機1は、以上のような構成を有するので、
トンネル15の掘削に際しては、駆動モータSによりカ
ッタ3を回転′させると共に、掘進用ジヤツキ6のラム
6aを、第1図B方向に突出させて、隔壁2a及び外殻
2を介してカッタ3を切羽16方向、即ち矢印六方向に
押圧する。すると、その押圧力により、カッタ3と切羽
J6は所定の接触圧力で接し、切羽16はカッタ3によ
り掘削され、それと同時に、外殻2は入方向に掘進して
、トンネル15がシールド掘削機1の後方。
Since the shield excavator 1 has the above configuration,
When excavating the tunnel 15, the cutter 3 is rotated by the drive motor S, and the ram 6a of the excavation jack 6 is projected in the direction B in FIG. Press in the direction of the face 16, that is, in the six directions of the arrows. Then, due to the pressing force, the cutter 3 and the face J6 come into contact with each other with a predetermined contact pressure, the face 16 is excavated by the cutter 3, and at the same time, the outer shell 2 is excavated in the entry direction, and the tunnel 15 is connected to the shield excavator 1. behind.

即ち第1図右方に形成されてゆく。That is, it is formed on the right side of FIG.

こうして、トンネル15が形成されてゆくにつれ、掘削
された地山19の崩壊を防止するために覆工2oを構築
する必要が有るが、この覆工20の構築は、以下の手順
で行なわれる。即ち、シールド掘削機1が、型枠13の
1リング分の長さLlだけ入方向に掘進した状態では、
掘進用ジヤツキ6のラム6aは、第6図に示すように、
B方向に突出した状態となっており、またプレスリング
7もB方向に移動した状態となっている。
As the tunnel 15 is formed in this way, it is necessary to construct the lining 2o to prevent the excavated earth 19 from collapsing, and the construction of the lining 20 is performed in the following steps. That is, when the shield excavator 1 has dug in the entry direction by a length Ll corresponding to one ring of the formwork 13,
As shown in FIG. 6, the ram 6a of the digging jack 6 is
It is in a state of protruding in the B direction, and the press ring 7 is also in a state of moving in the B direction.

この状態で、第7図に示゛すように、ラム6aを入方向
に距離L1だけ後退させる。すると、直前にコンクリー
ト21の打設された部分の妻止め22 A及び型枠1’
 3 Aからゲージリング11が点れて、A方向に移動
し、妻止め22A及び型枠13Aとゲージリング11と
の間に距離L1なる空間が形成さ九る。そこで、該空間
部分に、第7図想像線で示すように、補強鉄板12を妻
止め22Bと共に組立て設置する。
In this state, as shown in FIG. 7, the ram 6a is moved back in the incoming direction by a distance L1. Then, the end stop 22A and formwork 1' of the part where concrete 21 was poured just before
3 The gauge ring 11 is turned on from A and moves in the A direction, and a space of distance L1 is formed between the gauge ring 11 and the end stop 22A and the formwork 13A. Therefore, the reinforcing iron plate 12 is assembled and installed together with the end stop 22B in the space, as shown by the imaginary line in FIG.

即ち1本体12Aの切羽側端面12aを係合溝11aに
嵌入させると共に1本体12Aの後端部12eを、第1
4図に示すように1図中右方に既設された補強鉄板12
の切羽側端面12aに接続する形で組立てる。
That is, the face side end surface 12a of the first main body 12A is fitted into the engagement groove 11a, and the rear end portion 12e of the first main body 12A is inserted into the first main body 12A.
As shown in Figure 4, the reinforcing steel plate 12 installed on the right side of Figure 1
It is assembled in such a way that it is connected to the face side end surface 12a of.

次に、第7図に示す型枠13Aに接する形で型枠13B
を組立設置し、該型枠13B、ゲージリング11(妻止
め22B)、プレスリング7及び妻止め22Aとの間に
コンクリート打設空間23を形成する。この状態で、第
8図に示すように。
Next, the formwork 13B is placed in contact with the formwork 13A shown in FIG.
are assembled and installed, and a concrete placement space 23 is formed between the formwork 13B, gauge ring 11 (end stop 22B), press ring 7, and end stop 22A. In this state, as shown in FIG.

型枠13Bにコンクリート供給管25を接続して、コン
クリート供給管25によりコンクリート打設空間23中
にコンクリート21を打設する。すると、コンクリート
21は、コンクリート打設空間23の内周部、即ち型枠
13B、補強鉄板12間に供給されると共に、その外周
部、即ち補強鉄板12、プレスリング7間にも、補強鉄
板12に形成された複数個の穴12&を通して供給され
る。
A concrete supply pipe 25 is connected to the formwork 13B, and concrete 21 is placed in the concrete placement space 23 using the concrete supply pipe 25. Then, the concrete 21 is supplied to the inner circumference of the concrete casting space 23, that is, between the formwork 13B and the reinforcing iron plate 12, and also to the outer circumference, that is, between the reinforcing iron plate 12 and the press ring 7. It is supplied through a plurality of holes 12& formed in the.

このため、コンクリート打設空間23の全体に。For this reason, the entire concrete placement space 23.

コンクリート21が密実に打設される。Concrete 21 is placed densely.

なお、この際、コンクリート打設空間23中の空気は、
型枠13に適宜設けられたエア抜き管L3aにより外部
に排出されるので、コンクリート21のコンクリート打
設空間23甲への注入打設動作は円滑に行なわれる5 こうして、コンクリート打設空間23中にコンクリート
21が打設されたところで、第9図に示すように、今度
はプレスリングジヤツキ9を駆動してプレスリング7を
入方向に徐々に後退させる。すると、プレスリング7が
通過した後には、外殻2と注入されたコンクリ−1〜2
1との間に空間26が形成される。そこで、プレスリン
グ7のA方向の移動と共に、第10図に示すように、コ
ンクリート吐出管10からコンクリート21を、空間2
6中に注入し、該空間26をコンクリート21で充填す
る。プレスリング7が入方向に移動して、第11図に示
すように、側面7aがゲージリング11何の妻止め22
Bの設置位置と略一致したところで、第12図に示すよ
うに、掘進用ジヤツキ6のラム6aをB方向に突出駆動
させると共に、カンタ3を回転させて掘削動作を開始す
る。
In addition, at this time, the air in the concrete placement space 23 is
Since the air is discharged to the outside through the air vent pipe L3a appropriately provided in the formwork 13, the pouring operation of the concrete 21 into the concrete placement space 23A is performed smoothly. Once the concrete 21 has been placed, as shown in FIG. 9, the press ring jack 9 is driven to gradually move the press ring 7 back in the entry direction. Then, after the press ring 7 has passed, the outer shell 2 and the poured concrete 1 to 2 are separated.
A space 26 is formed between the two. Therefore, as the press ring 7 moves in the A direction, the concrete 21 is discharged from the concrete discharge pipe 10 into the space 2, as shown in FIG.
6 and fills the space 26 with concrete 21. The press ring 7 moves in the entry direction, and as shown in FIG.
When the position substantially coincides with the installation position B, as shown in FIG. 12, the ram 6a of the excavation jack 6 is driven to protrude in the direction B, and the canter 3 is rotated to start the excavation operation.

すると、疵に述/\たように、外殻2が入方向に移動を
開始し、外殻2が移動した後に、打股光填されたコンク
リート21と地山19との間にテールボイド27が形成
される。従って、外殻2がA方向に移動するにつれてプ
レスリングジヤツキ9を駆動してプレスリング7を、外
殻2の移動に同期した形でB方向に徐々に移動させる。
Then, as mentioned in the defect, the outer shell 2 starts to move in the inward direction, and after the outer shell 2 moves, a tail void 27 is created between the concrete 21 filled with light and the ground 19. It is formed. Therefore, as the outer shell 2 moves in the A direction, the press ring jack 9 is driven to gradually move the press ring 7 in the B direction in synchronization with the movement of the outer shell 2.

すると、先程打設されたコンクリート打設空間23及び
空間26内の未硬化のコンクリート21は、プレスリン
グ7の側面7aに押圧されて、テールボイド27を充填
する形で流動する2 こうして、第13図に示すように、外殻2のA方向の移
動につれて、プレスリング7をB方向に移動させてゆく
と、外殻2の移動の結果発生するテールボイド27は、
効果的に充填されてゆく。
Then, the unhardened concrete 21 in the concrete placement space 23 and the space 26 that was previously placed is pressed against the side surface 7a of the press ring 7 and flows to fill the tail void 272. Thus, as shown in FIG. As shown in , when the press ring 7 is moved in the B direction as the outer shell 2 moves in the A direction, the tail void 27 generated as a result of the movement of the outer shell 2 is
It is filled effectively.

なお、プレスリング7は全体円環状に形成されているの
で、コンクリート21等の充填部材はリング全周に互り
均一な圧力で押圧され、従ってテールボイド27の充填
動作は外殻2の全周に亙り均一で良好な状態で行なわれ
る。
Since the press ring 7 is formed in an annular shape, the filling member such as the concrete 21 is pressed against the entire circumference of the ring with uniform pressure, and therefore the filling operation of the tail void 27 is applied to the entire circumference of the outer shell 2. The process is uniform and in good condition throughout.

こうして、1リング分外殻2が推進すると、プレスリン
グ7は、全6図に示すように、その側面7aが外殻2の
後端部に一致した形となり、1リング分の覆工20の構
築が完了する。なお、この際の、コンクリート21の打
ち継ぎ部29は、第1図に示すように、プレスリング7
の移動動作により、階段状に形成される。
In this way, when the outer shell 2 is propelled by one ring, the press ring 7 has its side surface 7a aligned with the rear end of the outer shell 2, as shown in all six figures, and the lining 20 for one ring is moved. Construction is complete. In addition, at this time, the pouring part 29 of the concrete 21 is connected to the press ring 7 as shown in FIG.
is formed into a stair-like shape.

なお、構築後の覆工2oの打ち継ぎ部29に、周囲の地
山19から第4図想像線で示す地下水33が流れ込み、
該地下水33が、打ち継ぎ部29の外周面29aに沿っ
てA方向に流れて妻止め22に達した場合、地下水33
は分岐して、その一部は、外リング22aの図中右側面
と打設されたコンクリートとの隙間に流れ込み、該隙間
を図中下方に流れ落ちて接合部12dに達する。すると
、接合部L2aは無人領域ARA内に設けられているの
で、該接合部12dで、地下水33は下方への流れを遮
られる形で進路を図中右方向に変えて、外周面12bに
沿ってB方向に流れて穴L2cに達する。すると、地下
水33は、穴12cを回り込む形で内周面12fに流れ
込み、更に入方向に流れて、接合部12gに達する。
In addition, groundwater 33 shown by the imaginary line in Figure 4 flows from the surrounding ground 19 into the pouring joint 29 of the lining 2o after construction.
When the groundwater 33 flows in the A direction along the outer circumferential surface 29a of the spouting portion 29 and reaches the end stop 22, the groundwater 33
branches, and a part of it flows into the gap between the right side surface of the outer ring 22a in the figure and the poured concrete, flows down the gap in the figure, and reaches the joint 12d. Then, since the joint L2a is located within the unmanned area ARA, the groundwater 33 changes its course to the right in the figure and flows along the outer peripheral surface 12b at the joint 12d, with its downward flow blocked. It flows in direction B and reaches hole L2c. Then, the groundwater 33 flows around the hole 12c into the inner peripheral surface 12f, further flows in the inlet direction, and reaches the joint 12g.

接合部12gにまで達した地下水33は、進路を変えて
、該接続部12gから内リング22bに沿って流れ落ち
、外部に漏出する。
The groundwater 33 that has reached the joint 12g changes its course, flows down from the joint 12g along the inner ring 22b, and leaks to the outside.

また、妻止め22に達した地下水33の他の部分は、外
リング22aの図中左側面に沿って図中下方に流れ落ち
、接合部L2dに達する。すると、接合部12dは、無
穴領域A RA内に設けられているので、地下水33は
、接続部12dで図中下方への流れを遮られる形で、進
路を変えて外周面12bに沿って入方向に流れ、図中左
方に設置された補強鉄板12の穴12(〕に達する。穴
12cに達した地下水33は、該穴12cを回り込み、
更に内周面12fに沿って、B方向に流れて接続部12
gに達する。
Further, the other part of the groundwater 33 that has reached the end stop 22 flows down along the left side surface of the outer ring 22a in the figure, and reaches the joint L2d. Then, since the joint 12d is provided in the non-perforated area ARA, the groundwater 33 changes its course and flows along the outer circumferential surface 12b, with its downward flow in the figure blocked by the joint 12d. The water flows in the inlet direction and reaches the hole 12 ( ) of the reinforcing iron plate 12 installed on the left side of the figure.The groundwater 33 that has reached the hole 12c goes around the hole 12c,
Further, it flows in the direction B along the inner circumferential surface 12f to form the connecting portion 12.
reaches g.

すると、地下水33は、進路を変えて内リング22 b
に沿って図中下方に流れて、外部に漏出する6しかし、
地下水33aの流れる道筋(水道)は、妻止め22が無
穴領域A RAに設けられたことによって屈折して、そ
の全長が長くなるために。
Then, the groundwater 33 changes its course and flows into the inner ring 22b.
6. However, the water flows downward in the figure and leaks to the outside.
This is because the path (aqueduct) through which the groundwater 33a flows is bent due to the end stop 22 being provided in the non-perforated area ARA, and its total length becomes longer.

地下水33の止水効果は大幅に高まる。The effectiveness of stopping groundwater 33 will be greatly enhanced.

(f)1発明の効果 以上、説明したように本発明は、筒状に形成された本体
コー2Aを有し、前記本体12 Aに、端面12aから
所定距離L2の範囲に亙って無穴領域ARAを形成する
と共に、前記無穴領域A RA外の本体部分12Aに複
数個の穴1.20を貫通穿設し、更に、前記無人領域A
RA内の本体12 A部分に、環状に形成された妻止め
22を設けて構成したので、妻止め22を、穴12c上
に重なる形で本体12Aに組み付けた場合よりも、地下
ボ33の流れる道筋(水道)の全長を長くすることが出
来、妻止め22からの漏水を効果的に防止することが出
来る。
(f) 1. Effects of the Invention As described above, the present invention has a main body 2A formed in a cylindrical shape, and has no holes in the main body 12A over a predetermined distance L2 from the end surface 12a. A plurality of holes 1.20 are formed through the main body portion 12A outside the unmanned area ARA, and the unmanned area ARA is formed.
Since the end stop 22 formed in an annular shape is provided in the A portion of the main body 12 in the RA, the flow of the underground boss 33 is improved more than when the end stop 22 is assembled to the main body 12A so as to overlap the hole 12c. The total length of the route (water supply) can be lengthened, and water leakage from the end stop 22 can be effectively prevented.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明によるトンネル覆工用補強鉄板が用いら
れる覆工の構S現場の様子を示す図、第2図は第1図の
■−汀線による断面図。 第3図は第1図の■−■線による断面図。 第4図はシールド掘削機のジヤツキ部分の拡大図。 第5図は第4図のV−■腺による断面図。 第6図乃至第13図はトンネル覆工用補強鉄・板を用い
て、覆工を構築する様子を示す工程図、第14図は本発
明によるトンネル覆工用補強鉄板の一実施例を示す斜視
図である。 12・・・・・・補強鉄板 12A・・・・・・本体 12a・・・・・・端面 12c・・・・・穴 22・・・・・妻止め A RA・・・・無穴領域 第6図 第7図 第9図 第10図 第11図 第12図 第14図 、/′e′
FIG. 1 is a diagram showing a construction site S of a tunnel lining in which the reinforcing steel plate for tunnel lining according to the present invention is used, and FIG. 2 is a sectional view taken along the - shore line in FIG. 1. FIG. 3 is a sectional view taken along the line ■-■ in FIG. 1. Figure 4 is an enlarged view of the jacking part of the shield excavator. FIG. 5 is a sectional view taken along the line V-■ gland in FIG. 4. Figures 6 to 13 are process diagrams showing how the lining is constructed using reinforcing iron plates for tunnel lining, and Figure 14 shows an embodiment of the reinforcing iron plate for tunnel lining according to the present invention. FIG. 12... Reinforcement iron plate 12A... Main body 12a... End face 12c... Hole 22... End stop A RA... No hole area No. Figure 6 Figure 7 Figure 9 Figure 10 Figure 11 Figure 12 Figure 14 /'e'

Claims (1)

【特許請求の範囲】 筒状に形成された本体を有し、 前記本体に、端面から所定距離の範囲に亙 って無穴領域を形成すると共に、前記無穴領域外の本体
部分に複数個の穴を貫通穿設し、 更に、前記無穴領域内の本体部分に、環状 に形成された妻止めを設けて構成したトンネル覆工用補
強鉄板。
[Scope of Claims] A main body formed in a cylindrical shape, a non-porous region is formed in the main body over a predetermined distance from an end face, and a plurality of non-porous regions are formed in the main body portion outside the non-porous region. A reinforcing iron plate for tunnel lining, comprising: a hole drilled through the plate; and a ring-shaped end stopper provided in the main body portion within the non-perforated region.
JP62013036A 1987-01-22 1987-01-22 Reinforcing iron plate for tunnel lining Pending JPS63181893A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62013036A JPS63181893A (en) 1987-01-22 1987-01-22 Reinforcing iron plate for tunnel lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62013036A JPS63181893A (en) 1987-01-22 1987-01-22 Reinforcing iron plate for tunnel lining

Publications (1)

Publication Number Publication Date
JPS63181893A true JPS63181893A (en) 1988-07-27

Family

ID=11821893

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62013036A Pending JPS63181893A (en) 1987-01-22 1987-01-22 Reinforcing iron plate for tunnel lining

Country Status (1)

Country Link
JP (1) JPS63181893A (en)

Similar Documents

Publication Publication Date Title
JP4768747B2 (en) Pre-support tunnel construction method and equipment adapted to it
JPS62194399A (en) Construction method for coating tunnel
JPS63181893A (en) Reinforcing iron plate for tunnel lining
JPH04357293A (en) Flexible pipe and executing method thereof
JP3208085B2 (en) Structure of passage of tunnel excavator in middle shaft
JPH0519000B2 (en)
JPS62121299A (en) Method for covering casting of tunnel and shield excavator used therein
KR102540940B1 (en) Pipe roof method with expanded boring and steel pipe jointing and structure using of the same
JPS63161298A (en) Shield excavator
JPH05287983A (en) Construction of underground space having long and large diametral dimension
JPH1054045A (en) Shaft construction method making use of cylindrical body used for manhole wall and excavation cutting edg body, excavation lubricant supply device and settlement cylindrical body used for manhole wall
JPS63134794A (en) Shield excavator
JP6935640B2 (en) Construction method of underground widening part
JP3734890B2 (en) Water stop structure and water stop method
JPS63181898A (en) Tail sealing structure in shield excavator
JPS63156199A (en) Shielding excavator
JP2634883B2 (en) Construction method of tunnel lining
JPH0369438B2 (en)
JP3178357B2 (en) Construction method of large section tunnel
JP3089591B2 (en) Circular underground diaphragm wall
JPS63181895A (en) Shield excavator
JPS62117993A (en) Method of constructing tunnel
JPH02153198A (en) Shield excavator
JPH0485499A (en) Construction of excavation space
JP3608135B2 (en) Construction method of large section tunnel