JPS63181813A - Construction of steel tubular sheet pile - Google Patents

Construction of steel tubular sheet pile

Info

Publication number
JPS63181813A
JPS63181813A JP1292387A JP1292387A JPS63181813A JP S63181813 A JPS63181813 A JP S63181813A JP 1292387 A JP1292387 A JP 1292387A JP 1292387 A JP1292387 A JP 1292387A JP S63181813 A JPS63181813 A JP S63181813A
Authority
JP
Japan
Prior art keywords
steel pipe
pile
pipe sheet
hole
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1292387A
Other languages
Japanese (ja)
Other versions
JPH0645934B2 (en
Inventor
Hiroshi Yoshizuka
吉塚 博史
Takashi Endo
遠藤 隆司
Koji Sumi
光二 須見
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takechi Koumusho KK
Original Assignee
Takechi Koumusho KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takechi Koumusho KK filed Critical Takechi Koumusho KK
Priority to JP62012923A priority Critical patent/JPH0645934B2/en
Publication of JPS63181813A publication Critical patent/JPS63181813A/en
Publication of JPH0645934B2 publication Critical patent/JPH0645934B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To simply and exactly set and connect steel tubular sheet piles by a method in which steel tubular sheet piles are set into an excavated pit while joining their couplers. CONSTITUTION:A pit 8 is excavated adjacently to a reference pile 2 by an excavator 6 while joining the guider 7 of the excavator 6 to the coupler 3' of the pile 2 under the guidance of the joint. In penetrating a steel tubular sheet pile 9 into the pit 8, the setting is made while joining the coupler 3' with the coupler 3. Excavation for the pit 8 is made while turning not only an auger head 4 but also a casing 5.

Description

【発明の詳細な説明】 [技術分野1 本発明は、大径の鋼管矢板を地盤中に連続して建て込ん
で接続する方法に関する発明である。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field 1] The present invention relates to a method for continuously erecting and connecting large diameter steel pipe sheet piles into the ground.

[背景技術1 従来にあっては、鋼管矢板は打ち込み磯に地盤に打ち込
むことで建て込んでいたので、振動、騒音が発生してい
た。そこで振動、騒音を発生させない方法として掘削機
で掘削孔を穿孔してその孔の中に*W杭を建て込む方法
が考えられるが、これだと掘削孔に対して隣りに掘削し
た掘削孔が傾いて掘削されるおそれがあり、wIW杭の
正確な建て込みが期待できず、また鋼管杭同士の接続が
容易でないという問題があった。
[Background technology 1] Conventionally, steel pipe sheet piles were built by driving them into the ground on rocky shores, which caused vibration and noise. Therefore, one possible method to avoid generating vibrations and noise is to use an excavator to drill a hole and install a *W pile into the hole, but in this case, the hole drilled next to the hole is There was a risk that the wIW piles would be excavated at an angle, making it impossible to expect accurate erection of the wIW piles, and there were also problems in that it was not easy to connect steel pipe piles to each other.

[発明の目的] 本発明は、上記の点に鑑みて発明したものであって、そ
の目的とするところは、鋼管矢板の建て込み及び接続が
簡単且つ正確にできるw4管矢板の施工方法を提供する
にある。
[Object of the Invention] The present invention was invented in view of the above points, and its purpose is to provide a construction method for W4 pipe sheet piles that allows easy and accurate erection and connection of steel pipe sheet piles. There is something to do.

[発明の開示] 本発明の鋼管矢板の施工方法は、側部に継手部3′を有
する基準杭2を地盤1に建て込み、オーガヘッド4とケ
ーシング5とを組み合わせた掘削機6に継手81S3’
に対して上下にスフイド自在に係合するガイド部材7を
設け、ガイド部材7を基準杭2の継手&!S 3 ’に
係合させて掘削のガイドとしながらオー〃へラド4及び
ケーシング5を回転して地盤1中に掘削孔8を穿孔し、
ついで掘削機6を引き抜き、次に両側に継手部3を有す
る鋼管矢板9の一方の継手部3を基準杭2の継手部3′
に係合しながら掘削孔8に建て込み、次に上記掘削孔8
に建て込んだ鋼管矢板9の他方の継手部3に掘削8!6
に設けたがイド部材7を係合してオーガへラド4及びケ
ーシング5を回転して掘削孔8を穿孔し、掘削機6を引
き抜いた後、すでに建て込んだ鋼管矢板9の他方の継手
部3に次のw4W矢板9の一方の継手部3を係合しなが
ら掘削孔8に建て込み、同様にして順次鋼管矢板9を立
て込むとともに鋼管矢板9同士を継手部3で係合接続す
ることを特徴とするものであって、このような構成を採
用することで上記した本発明の目的を達成したものであ
る。すなわち本発明にあっては、基準杭2の継手部3′
に掘削機6のがイド部材7を係合しながらこの保合をガ
イドとして正確に掘削機6にて基準杭2の隣りに掘削孔
8を穿孔し、この掘削孔8に#4管矢板9を挿入して建
て込む際に継手部3′と継手部3とを係合しながら建て
込むことで、正確に鋼管矢板9の建て込み及び接続がで
き、同様にして鋼管矢板9同士の建て込み接続ができる
ものであり、また鋼管矢板9を建て込むための掘削孔8
を穿孔するに当たり、オーがヘッド4だけでなくケーシ
ング5も回転しながら掘削するので、鋼管矢板9を建て
込むための掘削孔8の崩壊を防ぐとともに掘削孔8の鉛
直性を確保しながら正確な径の掘削孔が簡単に形成でき
るようになったものである。
[Disclosure of the Invention] The method for constructing a steel pipe sheet pile according to the present invention is to erect a reference pile 2 having a joint portion 3' on the side in the ground 1, and install a joint 81S3 on an excavator 6 that combines an auger head 4 and a casing 5. '
A guide member 7 is provided that can be freely engaged vertically with respect to the reference pile 2, and the guide member 7 is connected to the joint of the reference pile 2 &! Drilling an excavation hole 8 in the ground 1 by rotating the O-herad 4 and the casing 5 while engaging with S3' and serving as a guide for excavation,
Next, the excavator 6 is pulled out, and one joint part 3 of the steel pipe sheet pile 9 having joint parts 3 on both sides is connected to the joint part 3' of the reference pile 2.
is installed in the drill hole 8 while engaging with the drill hole 8, and then the drill hole 8 is
Excavation 8!6 in the other joint 3 of the steel pipe sheet pile 9 built in
After engaging the id member 7 provided in the holder and rotating the auger head 4 and casing 5 to drill the excavation hole 8 and pulling out the excavator 6, the other joint of the steel pipe sheet pile 9 that has already been erected is 3, insert the next w4W sheet pile 9 into the excavated hole 8 while engaging one of the joint parts 3, and similarly, sequentially insert the steel pipe sheet piles 9 and connect the steel pipe sheet piles 9 by engaging with each other at the joint part 3. By employing such a configuration, the above-mentioned object of the present invention can be achieved. That is, in the present invention, the joint portion 3' of the reference pile 2
Using this engagement as a guide, the excavator 6 accurately drills an excavation hole 8 next to the reference pile 2 while engaging the ID member 7, and inserts #4 pipe sheet pile 9 into this excavation hole 8. By inserting and building the steel pipe sheet piles 9 while engaging the joint parts 3' and 3, the steel pipe sheet piles 9 can be accurately built and connected, and the steel pipe sheet piles 9 can be installed in the same way. It is possible to connect, and also has an excavated hole 8 for erecting the steel pipe sheet pile 9.
When drilling, not only the head 4 but also the casing 5 are rotated while drilling, which prevents the collapse of the excavated hole 8 for erecting the steel pipe sheet pile 9, as well as ensuring the verticality of the excavated hole 8 while ensuring accurate accuracy. It is now possible to easily drill holes of the same diameter.

以下本発明を実施例により詳述する。基準杭2は側部に
継手部3′を有したものであり、本発明にあっては、ま
ず基準杭2を地盤1中に建て込むものである。基準杭2
の建て込みに当たっては例えば次のようにしておこなう
ものである。すなわち、第1図(a)に示すような掘削
機6′を用いて地盤1を掘削して掘削孔8′を穿孔する
のである。
The present invention will be explained in detail below with reference to Examples. The reference pile 2 has a joint portion 3' on its side, and in the present invention, the reference pile 2 is first built into the ground 1. Reference stake 2
For example, the construction is carried out as follows. That is, an excavator 6' as shown in FIG. 1(a) is used to excavate the ground 1 to form an excavated hole 8'.

掘削8!6′は掘削軸10の外周にケーシング5を配設
し、掘削軸10の下端部のケーシング5がら下方に突出
した部分にオーがヘッド4を設けたものであり、ケーシ
ング5と下端部にオーがヘッド4とは連動して回転する
ようになっている。実施例においては第5図に示すよう
に掘削軸10の下端部に連結部材11を固着し、この連
結部材11の外周部をケーシング5に固着してあり、ま
たf部においてはケーシング5の下端部から垂設した当
部材12をオーガヘッド4の回転方向の側面に当ててあ
り、下端部にオーがヘッド4を有する掘削軸10を回転
することで、同時にケーシング5も回転するようになっ
ている。しかしてオーガヘッド4及びケーシング5を回
転し、オーガヘッド4乃至掘削軸10からジェット水を
第1図のように上向き及び下向きに噴出しながら掘削孔
8′を掘削するものである。この場合、掘削すべき掘削
孔8′が深い場合にはケーシング5及び掘削軸10を$
1図(b)のように継ぎ足して所定の深度まで掘削する
。所定の深度まで掘削が完了すると、ベントナイト安定
液13を吐出しグラウトして掘削孔8′の崩壊を防ぐ。
The excavation 8!6' has a casing 5 disposed around the outer periphery of the excavation shaft 10, and a head 4 is provided at the part of the lower end of the excavation shaft 10 that protrudes downward from the casing 5. The head 4 rotates in conjunction with the head 4. In the embodiment, as shown in FIG. 5, a connecting member 11 is fixed to the lower end of the excavation shaft 10, and the outer circumference of this connecting member 11 is fixed to the casing 5. At the part f, the lower end of the casing 5 The member 12 hanging from the auger head 4 is placed against the side surface of the auger head 4 in the direction of rotation, and as the auger rotates the excavation shaft 10 having the head 4 at its lower end, the casing 5 also rotates at the same time. There is. Thus, the auger head 4 and the casing 5 are rotated, and the drilled hole 8' is excavated while jet water is spouted upward and downward from the auger head 4 and the excavation shaft 10 as shown in FIG. In this case, if the drilling hole 8' to be drilled is deep, the casing 5 and drilling shaft 10 are
As shown in Figure 1 (b), excavation is continued to a specified depth. When the excavation is completed to a predetermined depth, bentonite stabilizing liquid 13 is discharged and grouted to prevent collapse of the excavated hole 8'.

この場合ベントナイト安定液13を注入しながら回転及
びケーシング5の上下反攬作業を行う。なお地盤によっ
てはベントナイト安定液13をはじめから吐出しながら
掘削する場合がある。このようにして掘削孔8′の全長
にベントナイト安定液13をグラウト注入してケーシン
グ5及び下端部にオーがへラド4を有する掘削軸10を
引き上げる。同様にして掘削8!6′を移動して次の基
準杭用の掘削孔8′を掘削する。
In this case, the operation of rotating and lifting the casing 5 up and down is performed while injecting the bentonite stabilizing liquid 13. Note that depending on the ground, excavation may be performed while discharging bentonite stabilizing liquid 13 from the beginning. In this way, the bentonite stabilizing liquid 13 is injected into the entire length of the excavation hole 8', and the casing 5 and the excavation shaft 10 having the O-shaft 4 at the lower end are pulled up. Similarly, the excavation hole 8!6' is moved to excavate the next excavation hole 8' for the reference pile.

このようにして掘削した掘削孔8′内にはクローラクレ
ーン14等により基準杭2が建て込まれる。
A reference pile 2 is erected into the excavated hole 8' by a crawler crane 14 or the like.

ここで掘削孔8′が深い場合には下の基準杭2に続いて
上の基準杭2を建て込んで溶接継ぎを行って掘削孔8′
に降ろすものである。この際鉛直方向はトランシット、
傾斜計によりチェックし、水平方向は定規を取り付けて
管理するものである。
If the excavation hole 8' is deep, the upper reference pile 2 is built following the lower reference pile 2, and a welded joint is performed to make the excavation hole 8'.
It is to be unloaded. In this case, the vertical direction is transit,
It is checked using an inclinometer, and the horizontal direction is controlled by attaching a ruler.

そして鉛直性をチェックしながら建て込み、最終根入れ
に当たって必要とあれば第1図(e)のような油圧押込
fi15で圧入するものである。ここで基準杭2は後述
のa管矢@9と同様に鋼管にて形成してあり、片側また
は両側の略全艮に亘って継手部3′が設けである。継手
MS3’は側部開口が内部よりも中挟となった雌状継手
部3a’ またはこの溝状継手部3a’ に係合するこ
とのできる側端部が膨大部となったR11手部のいずれ
かが設けられる。
Then, it is installed while checking the verticality, and if necessary during the final installation, it is press-fitted with a hydraulic pusher fi15 as shown in Fig. 1(e). Here, the reference pile 2 is formed of a steel pipe similarly to the later-described a-pipe arrow @9, and a joint portion 3' is provided over substantially the entire length on one or both sides. The joint MS3' has a female joint part 3a' in which the side opening is sandwiched between the inner parts, or an R11 hand part in which the side end part that can be engaged with the groove joint part 3a' is an enlarged part. Either one is provided.

次にγイド部材7を有する掘削機6を用いてガイド部材
7を既に建て込んだ基準杭2の継手部3′に係合しなが
ら、掘削機6により基準杭2の隣りに鋼管矢板打ち込み
用の掘削孔8を掘削する。
Next, using an excavator 6 having a gamma-id member 7, the guide member 7 is engaged with the joint part 3' of the already erected reference pile 2, and the excavator 6 is used to drive a steel pipe sheet pile next to the reference pile 2. Drill a borehole 8.

ここで用いる掘削機6は基本的には前述の掘削杭2建て
込み用の掘削機6′と同じ構造であり、掘削機6′とは
γイド部材7を設けている点が異なるものである。すな
わち掘削機6は掘削W16′にガイド部材7を設けた構
成となっている。fイド部材7はケーシング5あるいは
掘削軸10に回転自在に取り付けである。第2図の実施
例ではケーシング5の外周に回転自在に取り付けたロー
タリサポート16にガイド部材7が設けである1、また
第6図の実施例では掘削軸10に回転自在に取り付けた
ロータリサポート16にがイド部材7が取り付けである
。そして、がイド部材7を基準杭2の継手部3′に係合
させて掘削のガイドとしながらオーガヘッド4及びケー
シング5を回転して地4f11中に掘削孔8を穿孔する
。この場合掘削軸10またはオーガヘッド4からジェッ
ト水を上方及び下方に噴射しながら所定深度まで掘削し
ていく。
The excavator 6 used here basically has the same structure as the excavator 6' for erecting the excavated pile 2 described above, and differs from the excavator 6' in that it is provided with a γ-id member 7. . That is, the excavator 6 has a configuration in which a guide member 7 is provided on the excavator W16'. The f-id member 7 is rotatably attached to the casing 5 or the excavation shaft 10. In the embodiment shown in FIG. 2, a guide member 7 is provided on a rotary support 16 rotatably attached to the outer periphery of the casing 5, and in the embodiment shown in FIG. The bittern member 7 is attached. Then, the auger head 4 and the casing 5 are rotated while the guide member 7 is engaged with the joint portion 3' of the reference pile 2 to serve as an excavation guide, and the excavation hole 8 is bored in the ground 4f11. In this case, the excavation is carried out to a predetermined depth while jet water is injected upward and downward from the excavation shaft 10 or the auger head 4.

この場合既に建て込んだ基準杭2の継手部3′とガイド
部材7とを係合してこの保合をがイドとしながら掘削し
ていくことで、ケーシング5の鉛直性を確保しながら正
確に掘削がで終る。ここで本発明にあっては、ケーシン
グ5を回転することでケーシング5を抵抗なく所定の深
さまで到達させることができるものである。この場合上
方に噴射されるジェット水がケーシング5と掘削孔8の
孔壁との間に流入してケーシング5の進入に際しての摩
擦抵抗をいっそう低減してよりスムーズにケーシング5
を所定の深さまで到達させることができるものである。
In this case, by engaging the joint part 3' of the reference pile 2 that has already been erected with the guide member 7 and excavating while keeping this engagement, the verticality of the casing 5 can be ensured and the guide member 7 can be excavated accurately. The excavation ends. Here, in the present invention, by rotating the casing 5, the casing 5 can be made to reach a predetermined depth without resistance. In this case, the jet water injected upward flows between the casing 5 and the hole wall of the borehole 8, further reducing the frictional resistance when the casing 5 enters, and allowing the casing 5 to move more smoothly.
can reach a predetermined depth.

掘削すべき掘削孔8が深い場合には、掘削機6′の場合
と同様にケーシング5及掘削削紬10を継ぎ足して施工
を続けるものである。所定の深度に到達すると、ベント
ナイト安定液13を吐出しながら回転攪拌及び上下反復
作業をおこないながら掘削孔8の崩壊防止を計るもので
ある。その後、掘削1596を引外抜き、次にベントナ
イト安定液13を注入攪拌した掘削孔8内に鋼管矢板9
を建て込むものである。この場合鋼管矢板9には両側の
略全艮にわたり基準杭2に設けた継手部3′と同様の継
手部3が設けである。この継手部3は基準杭2の継手部
3′と同様に側部開口が内部よりも中挟となった雌状継
手部3aまたはこの溝状継手部3aに係合することので
きる側端部が膨大部となった雄継手g3bのいずれかで
ある。そして、両側に継手部3を有する!llill板
管の一方の継手部3を基準杭2の継手部3′に係合しな
がら掘削孔8に建て込むものである。この場合最終根入
れに際して必要があれば油圧押込fi15を用いて静的
に圧入するものえある。また建て込み時の鉛直性はトラ
ンシフト2、傾斜計を用いてチェックしながら建て込む
ものである。また掘削孔8が深くてw4管矢板9として
長いものが必要な場合には第3図(a)のように溶接に
より接続するものである。fIfJ3図中20は溶接部
を示す。
When the excavated hole 8 to be excavated is deep, the casing 5 and the excavated pongee 10 are added and the construction is continued in the same way as in the case of the excavator 6'. When a predetermined depth is reached, the bentonite stabilizing liquid 13 is discharged while rotating and stirring and repeating up and down operations to prevent the excavation hole 8 from collapsing. After that, the excavation 1596 was pulled out, and then the bentonite stabilizing liquid 13 was injected into the agitated excavation hole 8 and the steel pipe sheet pile 9
It is something that builds in. In this case, the steel pipe sheet pile 9 is provided with a joint portion 3 similar to the joint portion 3' provided on the reference pile 2 over substantially the entire length on both sides. Similar to the joint part 3' of the reference pile 2, this joint part 3 has a female joint part 3a in which the side opening is sandwiched between the inner side or a side end part that can be engaged with the groove joint part 3a. is one of the male joints g3b which has become an ampulla. And it has joint parts 3 on both sides! One joint part 3 of the llill plate pipe is inserted into the excavated hole 8 while engaging with the joint part 3' of the reference pile 2. In this case, if necessary at the time of final insertion, a hydraulic pusher fi15 may be used to statically press fit. In addition, the verticality during construction is checked using Transshift 2 and an inclinometer. Further, if the excavated hole 8 is deep and a long W4 pipe sheet pile 9 is required, the connection is made by welding as shown in FIG. 3(a). 20 in the figure fIfJ3 indicates a welded part.

次に、上記掘削孔8に建て込んだ鋼管矢板9の他方の継
手部3に掘削機6に設けたガイド部材3を係合してオー
がヘッド4及びケーシング5を回転して上記と同様にし
て次の掘削孔8を穿孔する。
Next, the guide member 3 provided on the excavator 6 is engaged with the other joint 3 of the steel pipe sheet pile 9 built in the excavated hole 8, and the O rotates the head 4 and the casing 5 in the same manner as above. Then, the next drilling hole 8 is drilled.

そして、掘削fi6を引き抜いた後、すでに建て込んだ
鋼管矢板9の他方の継手部3に次の鋼管矢板9の一方の
継手部3を係合しながら掘削孔8に建て込み、同様にし
て順次鋼管矢板9を立て込むとともに鋼管矢板9同士を
継手部3で係合接続するものである。
After pulling out the excavation fi 6, one joint part 3 of the next steel pipe sheet pile 9 is engaged with the other joint part 3 of the already installed steel pipe sheet pile 9, and the excavated hole 8 is erected, and in the same manner, one after another. The steel pipe sheet piles 9 are erected and the steel pipe sheet piles 9 are engaged and connected to each other at the joint portion 3.

そして、このようにして次々と掘削孔8を掘削して掘削
孔8に鋼管矢板9を建て込むと共に隣り合う鋼管矢板9
の継手部3間士を接続していさ、離れた処に掘削して建
て込んだ他の基準杭2の処まで建て込んでいさ、他の基
準杭2の処では鋼管矢板9の継手部3と他の基準杭2の
継手部3′とを係合して接続するものである。
In this way, the excavated holes 8 are drilled one after another, and the steel pipe sheet piles 9 are installed in the excavated holes 8, and the adjacent steel pipe sheet piles 9
Connect the joints 3 of the steel pipe sheet piles 9, and then build the joints 3 of the steel pipe sheet piles 9 at the other standard piles 2, which were excavated and erected in a distant place. and the joint portion 3' of another reference pile 2 are engaged and connected.

なお基準杭2を建て込むための掘削孔8′の掘削径りは
基準杭2として両側に継手83’ を設けたらのの場合
には両側の継手部3′間の距離よりもやや大径となって
おり、鋼管矢板9を建て込むための掘削孔8の掘削径間
は第4図に示すように一方の継手部3の突出先端から他
方の継手部3の突出基部までの長さよりやや長(なって
いる、第4図においてNはケーシング5の径を示してい
る。
In addition, the diameter of the excavated hole 8' for erecting the reference pile 2 should be slightly larger than the distance between the joints 3' on both sides if joints 83' are provided on both sides as the reference pile 2. As shown in Fig. 4, the excavated span of the excavated hole 8 for erecting the steel pipe sheet pile 9 is slightly longer than the length from the protruding tip of one joint part 3 to the protruding base of the other joint part 3. (In FIG. 4, N indicates the diameter of the casing 5.

なお上記実施例でははじめに基準杭2を複数箇所に建て
込み、基準杭2間に一方の基準杭2がら他方の基準杭に
かけて鋼管矢板9を建て込み接続していく例について説
明したが、1本の基準杭2を建て込みこれを基点にして
次々と鋼管矢板9を建て込み連結していって最後に出発
点の基準杭2の処にもどって最後の鋼管矢板9と基準杭
2とを継手部3.3′で接続するようにしてもよいもの
である。
In the above embodiment, the reference piles 2 are first erected at multiple locations, and the steel pipe sheet piles 9 are erected and connected between the reference piles 2 from one reference pile 2 to the other reference pile. The standard pile 2 is erected, and using this as a base, the steel pipe sheet piles 9 are successively erected and connected, and finally, returning to the starting point of the standard pile 2, the last steel pipe sheet pile 9 and the standard pile 2 are connected. The connection may be made at the portion 3.3'.

なおまた掘削孔8にw4管矢板9を建て込んだ場合掘削
孔9の孔壁と鋼管矢板9の外壁との間の部分に後で孔を
穿孔してセメントミルク、モルタル等を流入して外周を
強化するようにしてもよい。
Furthermore, when a W4 pipe sheet pile 9 is built into the excavated hole 8, a hole is later drilled between the hole wall of the excavated hole 9 and the outer wall of the steel pipe sheet pile 9, and cement milk, mortar, etc. are poured into the outer periphery. may be strengthened.

この場合、掘削孔8′の孔壁と基準杭2の外壁との間に
も同様に孔を穿孔してセメントミルク、モルタル等を流
入して外周を強化するようにしてもよいものである。
In this case, a hole may be similarly drilled between the hole wall of the excavated hole 8' and the outer wall of the reference pile 2, and cement milk, mortar, etc. may be introduced thereinto to strengthen the outer periphery.

[発明の効果1 本発明にあっては、叙述のように構成したので基準杭の
継手部に掘削機のガイド部材を係合しながらこの保合を
ガイドとして正確に掘削機にて基準杭の隣りに掘削孔を
穿孔し、この掘削孔に鋼管矢板を挿入して建て込む際に
継手部同士を係合しながら建て込むことで、正確に鋼管
矢板の建て込み及び接続が簡単且つ正確にでき、同様に
して鋼管矢板同士の建て込み接続が簡単且つ正確にでき
るものであり、また鋼管矢板を建て込むための掘削孔を
穿孔するに当たり、オーガヘッドだけでなくケーシング
も回転しながら掘削するので、鋼管矢板を建て込むため
の掘削孔の崩壊を防ぐとともに掘削孔の鉛直性を確保し
ながら能率よく正確な径の掘削孔が簡単に形成できるも
のである。
[Effect of the invention 1] Since the present invention is constructed as described above, the guide member of the excavator is engaged with the joint of the reference pile, and the excavator is used to accurately move the reference pile using this engagement as a guide. By drilling an adjacent excavation hole and inserting the steel pipe sheet pile into this excavation hole, the joint parts are engaged with each other when erecting, making it possible to easily and accurately erect and connect the steel pipe sheet pile. Similarly, steel pipe sheet piles can be connected easily and accurately, and when drilling holes for installing steel pipe sheet piles, not only the auger head but also the casing are rotated. This prevents the collapse of an excavated hole for erecting steel pipe sheet piles and ensures the verticality of the excavated hole, making it possible to efficiently and easily form an excavated hole with an accurate diameter.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図(a)(b)(e)(d)(e)は本発明におい
て基準杭を建て込むための順序を示す説明図、PIIJ
2図(、)(b)は同上の基準杭を基準にして鋼管矢板
を建て込んでいる状態の平面図及び側面図、第3図(a
)(b)は鋼管矢板を上下に接続して建て込んでいる状
態の説明図及び油圧押込機による押し込み状態の説明図
、第4図は本発明の施工状態を示す拡大平面図、第5図
は掘削機の上部のケーシングの取り付は状態を示す断面
図、第6図は本発明の他の実施例の説明図であって、1
は地盤、2は基準杭、3は継手部、3′は継手部、4は
オーガヘッド、5はケーシング、6は掘削機、7はγイ
ド部、8は掘削孔、9は鋼管矢板である。 第1図 第1図 (b) 第1図 (d) 第2図 (b) 第3図
Figure 1 (a), (b), (e), (d), and (e) are explanatory diagrams showing the order for erecting reference piles in the present invention, PIIJ
Figure 2 (,) (b) is a plan view and side view of the state in which steel pipe sheet piles are erected based on the same reference pile as above, and Figure 3 (a)
) (b) is an explanatory diagram of the state in which steel pipe sheet piles are connected vertically and erected, and an explanatory diagram of the state in which they are pushed in by a hydraulic pushing machine, Fig. 4 is an enlarged plan view showing the construction state of the present invention, and Fig. 5 6 is a cross-sectional view showing the installation state of the upper casing of the excavator, and FIG. 6 is an explanatory view of another embodiment of the present invention.
is the ground, 2 is the reference pile, 3 is the joint part, 3' is the joint part, 4 is the auger head, 5 is the casing, 6 is the excavator, 7 is the gamma side part, 8 is the excavation hole, and 9 is the steel pipe sheet pile. . Figure 1 Figure 1 (b) Figure 1 (d) Figure 2 (b) Figure 3

Claims (1)

【特許請求の範囲】[Claims] (1)側部に継手部を有する基準杭を地盤に建て込み、
オーガヘッドとケーシングとを組み合わせた掘削機に継
手部に対して上下にスライド自在に係合するガイド部材
を設け、ガイド部材を基準杭の継手部に係合させて掘削
のガイドとしながらオーガヘッド及びケーシングを回転
して地盤中に掘削孔を穿孔し、ついで掘削機を引き抜き
、次に両側に継手部を有する鋼管矢板の一方の継手部を
基準杭の継手部に係合しながら掘削孔に建て込み、次に
上記掘削孔に建て込んだ鋼管矢板の他方の継手部に掘削
機に設けたガイド部材を係合してオーガヘッド及びケー
シングを回転して掘削孔を穿孔し、掘削機を引き抜いた
後、すでに建て込んだ鋼管矢板の他方の継手部に次の鋼
管矢板の一方の継手部を係合しながら掘削孔に建て込み
、同様にして順次鋼管矢板を立て込むとともに鋼管杭同
士を継手部で係合接続することを特徴とする鋼管矢板の
施工方法。
(1) A reference pile with joints on the side is built into the ground,
An excavator that combines an auger head and a casing is provided with a guide member that is slidably engaged with the joint part up and down, and the guide member is engaged with the joint part of the reference pile to serve as a guide for excavation, Rotate the casing to drill a hole in the ground, then pull out the excavator, and then engage one joint of the steel pipe sheet pile, which has joints on both sides, with the joint of the reference pile while building in the hole. Then, the guide member installed on the excavator was engaged with the other joint of the steel pipe sheet pile installed in the excavation hole, the auger head and casing were rotated to drill the excavation hole, and the excavator was pulled out. After that, one joint part of the next steel pipe sheet pile is engaged with the other joint part of the steel pipe sheet pile that has already been erected, and one joint part of the next steel pipe sheet pile is inserted into the excavated hole, and in the same way, the steel pipe sheet piles are erected one after another, and the steel pipe piles are connected to each other at the joint part. A method for constructing steel pipe sheet piles, which is characterized by engaging and connecting with each other.
JP62012923A 1987-01-22 1987-01-22 Construction method of steel pipe sheet pile Expired - Fee Related JPH0645934B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62012923A JPH0645934B2 (en) 1987-01-22 1987-01-22 Construction method of steel pipe sheet pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62012923A JPH0645934B2 (en) 1987-01-22 1987-01-22 Construction method of steel pipe sheet pile

Publications (2)

Publication Number Publication Date
JPS63181813A true JPS63181813A (en) 1988-07-27
JPH0645934B2 JPH0645934B2 (en) 1994-06-15

Family

ID=11818855

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62012923A Expired - Fee Related JPH0645934B2 (en) 1987-01-22 1987-01-22 Construction method of steel pipe sheet pile

Country Status (1)

Country Link
JP (1) JPH0645934B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05311654A (en) * 1992-05-08 1993-11-22 Norio Kagota Forming method for wall and pipe used for the same
JP2021017757A (en) * 2019-07-22 2021-02-15 日本コンクリート工業株式会社 Jig for excavation and construction method of earth retaining structure

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101466136B1 (en) * 2013-05-06 2014-11-27 최근규 Excavating apparatus for sheetfile

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS50102114A (en) * 1974-01-16 1975-08-13
JPS5327881A (en) * 1976-08-26 1978-03-15 Heihachirou Toshi Container adapted to expel viscous material
JPS5375902U (en) * 1976-11-27 1978-06-24
JPS55142835A (en) * 1979-04-24 1980-11-07 Toshio Enoki Earth retaining method
JPS60219321A (en) * 1984-04-16 1985-11-02 Shiroyama Hideji Pile driving method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS50102114A (en) * 1974-01-16 1975-08-13
JPS5327881A (en) * 1976-08-26 1978-03-15 Heihachirou Toshi Container adapted to expel viscous material
JPS5375902U (en) * 1976-11-27 1978-06-24
JPS55142835A (en) * 1979-04-24 1980-11-07 Toshio Enoki Earth retaining method
JPS60219321A (en) * 1984-04-16 1985-11-02 Shiroyama Hideji Pile driving method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05311654A (en) * 1992-05-08 1993-11-22 Norio Kagota Forming method for wall and pipe used for the same
JP2021017757A (en) * 2019-07-22 2021-02-15 日本コンクリート工業株式会社 Jig for excavation and construction method of earth retaining structure

Also Published As

Publication number Publication date
JPH0645934B2 (en) 1994-06-15

Similar Documents

Publication Publication Date Title
CN106013151A (en) Continuous pile wall construction method and construction device used for continuous pile wall construction method
JPH0460022A (en) Sheathing method and sheathing pile therefor
JPS63181813A (en) Construction of steel tubular sheet pile
JPH02289718A (en) Drilling method of expanded head pile hole, constructing method of expanded head pile and pile hole drill
JP2942779B1 (en) Underground wall construction method
KR102325623B1 (en) Construction method of retaining wall
CN205742191U (en) A kind of piling wall constructing device continuously
JP6729902B1 (en) Construction method of soil cement continuous wall
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JPS5827366B2 (en) Head reinforcement pile construction equipment
JP2017197910A (en) Construction method of earth retaining wall structure, and earth retaining wall structure
JPS5820825A (en) Pile formation work and device therefor
JPS6128774B2 (en)
JP2001146739A (en) Construction method for impervious wall
JP2981164B2 (en) Drilling rig
JP2832481B2 (en) Drilling rig for hole for concrete pile installation
JPH0649855A (en) Constructing method for provisionally installed mating column for use in counter-drive method
JP2729940B2 (en) Drilling rig
JP3232196B2 (en) Drilling method and excavator for pile hole
JPH0448898B2 (en)
JP4414325B2 (en) Connected steel pipe pile method
JPS5985022A (en) Underground continuous wall constructing work
JP3325550B2 (en) Pile construction equipment and pile construction method
JPH10252080A (en) Method for reinforcing foundation of pier for high level road
JPS58204222A (en) Pile foundation work

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees