JPS63160992A - Method of erection construction of different length beam between same erection diameter and device thereof - Google Patents
Method of erection construction of different length beam between same erection diameter and device thereofInfo
- Publication number
- JPS63160992A JPS63160992A JP30740886A JP30740886A JPS63160992A JP S63160992 A JPS63160992 A JP S63160992A JP 30740886 A JP30740886 A JP 30740886A JP 30740886 A JP30740886 A JP 30740886A JP S63160992 A JPS63160992 A JP S63160992A
- Authority
- JP
- Japan
- Prior art keywords
- girder
- girders
- erection
- construction
- crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 16
- 238000000034 method Methods 0.000 title description 16
- 239000000725 suspension Substances 0.000 claims description 7
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000001556 precipitation Methods 0.000 description 5
- 238000000151 deposition Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000005096 rolling process Methods 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
- 230000008021 deposition Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 230000001376 precipitating effect Effects 0.000 description 1
- 239000011513 prestressed concrete Substances 0.000 description 1
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、橋梁の桁の架設工法に関し、ピアが「八」の
字形になっている径間に長さの異なる桁を安全に能率的
に架設する工法およびその工法に直接使用する祈出装置
に関する。[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method for constructing bridge girders, and relates to a method for constructing girders of bridges, and the present invention relates to a method for constructing girders of bridges, and relates to a method for safely and efficiently installing girders of different lengths in a span in which the piers are in the shape of an "eight." The present invention relates to construction methods for constructing bridges and prayer equipment used directly in the construction methods.
一般に、橋梁の架設において、桁製造所で製造したプレ
キャスト桁を橋の長手方向に移送し、この桁を、架設す
べき両方のピア上に載設した門型クレーンによって横方
向に移動して所φの位置に据付ける橋桁架設工法が行わ
れている。Generally, when constructing a bridge, precast girders manufactured at a girder factory are transported in the longitudinal direction of the bridge, and then moved laterally by a gantry crane mounted on both piers to be erected. A bridge girder construction method is being used in which the bridge girder is installed at the φ position.
カーブ橘では、隣接するピアがいわゆる「バチ」(「八
」の字形)になっており、カーブの内側と外側、例えば
上下線の橋では桁長が異なる。In the Tachibana curve, the adjacent piers form a so-called ``dachi'' (shaped like an ``eight''), and the girder lengths on the inside and outside of the curve, such as the upper and lower bridges, are different.
従ってこのような径間でプレキャスト桁を架設する場合
、
α)例えば桁長の異なる上下線の桁を上下線それぞれ別
の作業として架設するか。Therefore, if precast girders are to be erected in such a span, α) For example, should the upper and lower girders with different girder lengths be erected as separate work?
■ 門型クレーンを用いて横方向に小距離移動するごと
に桁をピア上に卸して仮置きし、門型クレーンの出立の
吊替え(桁の盛替え)を繰返しながら横方向に移動する
方法がとられていた。■ Each time a gantry crane is used to move a short distance laterally, the girder is unloaded onto the pier and temporarily placed there, and the gantry crane moves laterally while repeating the departure and rehanging (reshuffling of the girder). A method was taken.
前者の方法では、同一径間の作業に二度手間を要し、後
者の方法では、吊替え作業に大幅の手間を要し、また、
墨点が門型クレーンの吊下げ中心から外れることが避け
られないのでその許容範囲を誤ると事故につながる恐れ
がある。The former method requires twice the effort to work on the same span, and the latter method requires a significant amount of effort to rehang.
It is inevitable that the ink dot will deviate from the center of suspension of the gantry crane, so if the allowable range is incorrect, it may lead to an accident.
本発明はこのような従来の非能率な作業を効率化すると
共に、不安全作業の可能性のある作業を廃止し、短工期
、安価、安全に異長桁を同一径間に架設する工法および
その装置を提供することを目的とする。The present invention improves the efficiency of such conventional inefficient work, eliminates potentially unsafe work, and provides a construction method for constructing girders of different lengths in the same span in a short construction period, at low cost, and safely. The purpose is to provide such equipment.
本発明方法は、同一架設径間に複数の長さの異なる桁を
架設するに当り、桁吊点を桁長方向に連続的に移動させ
ながら、この桁をピア上に載設された門型クレーンによ
り、横移動することを特徴とする架設工法である。In the method of the present invention, when a plurality of girders of different lengths are erected in the same span, the girder suspension point is continuously moved in the length direction of the girder, and the girder is attached to a gate-shaped girder mounted on a pier. This construction method is characterized by horizontal movement using a crane.
上記方法を実現するための好適な装置は、桁とゲビンデ
鋼棒で結合する結合部を有し、内部にローラガイドレー
ルを内蔵し、このガイドレールに沿って転動するローラ
を桁長手方向に移動自在なクレーン吊具を備え、かつ該
クレーン吊具を移動させる動力装置を備えたことを特徴
とする析出装置である。A suitable device for realizing the above method has a joint that connects the girder with a Gebinde steel rod, has a roller guide rail built inside, and rolls the rollers rolling along the guide rail in the longitudinal direction of the girder. This is a precipitation apparatus characterized by comprising a movable crane hanging tool and a power device for moving the crane hanging tool.
本発明方法は、桁の墨点を桁長方向にJ!l!続的に移
動させながら桁を横移動させるので次のような好結果の
作用を生ずる。The method of the present invention moves the ink points of the digits in the direction of the digit length to J! l! Since the girder is moved laterally while being continuously moved, the following favorable effects are produced.
a) 墨点を常に門型クレーンの吊下げ中心に保って鉛
の横移動を行うので、桁の盛替え作業が全く不要となり
高部率化する。a) Since the ink point is always kept at the center of suspension of the gate type crane and the lead is moved laterally, there is no need to replace the girder at all, resulting in a high percentage of work.
b) 門型クレーンは斜出となることがなく、偏心荷重
を受けないので、安全性が極めて高い。b) Gate-type cranes are extremely safe because they do not tilt out and are not subjected to eccentric loads.
C) 人力が大幅に節減される。C) Manpower is significantly reduced.
d) もち論、上下線ごとの別の架設を要しないので、
短工期の施工ができ経済性が高い。d) Since there is no need for separate construction for each upper and lower line,
It can be constructed in a short construction period and is highly economical.
次に、本発明装置を用いれば、上記作用をすべてこなす
と共にざらに墨点の移動は遠隔操作により容易、安全、
確実に行うことができる。Next, if the device of the present invention is used, all of the above functions can be achieved, and the rough movement of ink points can be easily, safely, and by remote control.
It can be done reliably.
まず本発明方法を好適に実施することのできる本発明の
析出装置について図面を参照して説明する。First, a precipitation apparatus of the present invention that can suitably carry out the method of the present invention will be described with reference to the drawings.
第1図は実施例の三面図であって、(a)は平面図、(
b)は立面図、(C)はA−A矢視断面図である。第2
図はこの装置を桁に取り付けた状態を示す説明図である
。FIG. 1 is a three-sided view of the embodiment, in which (a) is a plan view and (a) is a plan view;
b) is an elevational view, and (C) is a sectional view taken along the line A-A. Second
The figure is an explanatory diagram showing the state in which this device is attached to a girder.
析出装置1は、そのほぼ中央部に桁と結合する結合部2
を備え、桁20上に載置した枕材21上に載せ、ゲビン
デ鋼棒22によって第2図に示すように桁20に剛結す
る。析出装置1はガイドレール8を内蔵しており、この
ガイドレール8に沿って転動するローラ7を介してクレ
ーン吊具5を備えている。クレーン吊具5は、上端に吊
手6を備え、下端に転動ローラ7を取り付け、この転動
ローラ7が析出装置1内に固定したガイドレール8に沿
って転動すると共に析出装置lを吊り上げる。クレーン
吊具5自身はこのガイドレール8に沿ってローラ7によ
って前後に移動可能となっている。The precipitation device 1 has a connecting portion 2 connected to the girder almost in the center thereof.
It is placed on the pillow material 21 placed on the girder 20, and is rigidly connected to the girder 20 with Gebinde steel rods 22 as shown in FIG. The precipitation apparatus 1 has a built-in guide rail 8, and is equipped with a crane hoist 5 via rollers 7 that roll along the guide rail 8. The crane hanging tool 5 is equipped with a hanging hand 6 at the upper end, and a rolling roller 7 is attached to the lower end. lift. The crane hanging tool 5 itself can be moved back and forth along this guide rail 8 by rollers 7.
クレーン吊具5には移動用スクリュー装置が取り付けら
れており、析出装置1内に内蔵したモータ9はスクリュ
ー10−を正逆転させ、クレーン吊具5を桁20の長手
方向に前後移動させる。A moving screw device is attached to the crane hanging tool 5, and a motor 9 built in the precipitation device 1 rotates the screw 10- in forward and reverse directions to move the crane hanging tool 5 back and forth in the longitudinal direction of the girder 20.
モータiは遠隔操作によって駆動され、図示しない門型
クレーンの移動に応じてクレーン吊具5を適切に移動さ
せることができ、門型クレーンの墨点を常に吊下げ中心
に保つ。The motor i is driven by remote control, and can appropriately move the crane hanging tool 5 in accordance with the movement of the gantry crane (not shown), thereby keeping the ink point of the gantry crane always at the center of the suspension.
クレーン吊具5の析出装置内の移動両極端位置には安全
のためにストロークリミットスイッチ11.12が設け
られ、ブザー等が取りつけられている。For safety, stroke limit switches 11 and 12 are provided at both extreme positions of movement of the crane hanging tool 5 in the deposition device, and a buzzer and the like are attached.
第1図の装置を用いて本発明方法により、曲率半径75
0mのカーブ道路橋を施工した。全幅員26m、平均径
間36mの「バチ」形をなすピア間に、上下線で長さが
1.25 mの差のあるプレストレストコンクリート製
I形桁を架設する必要があった。By the method of the present invention using the apparatus shown in FIG.
A 0m curved road bridge was constructed. It was necessary to erect I-shaped prestressed concrete girders with a difference of 1.25 m in length between the top and bottom lines between the drumstick-shaped piers with a total width of 26 m and an average span of 36 m.
従来方法による上下線別々の桁の架設工法、または桁を
ピア上に仮置きして吊替えながら横移動する方法に代り
、本発明方法を採用した。The method of the present invention was adopted in place of the conventional method of constructing separate girders for the upper and lower lines, or the method of temporarily placing girders on piers and moving them laterally while changing the suspension.
ピアの中央に仮設桁を設け、ピア上にはそれぞれ吊荷重
52Tの円形クレーンを配設した。ピア中央の仮設桁上
を長手方向に移送されてきたI形格の両端にそれぞれ第
1図に示す析出装置1を第2図に示すように装着しく第
2図は桁の一端のみを示している)、門型クレーンで工
形格を吊り上げ、遠隔操作によって出立移動モータ9を
駆動して墨点位置を円形クレーンの吊下げ中心に保持し
つつ、I形格を横移動して、桁の架設を行った。A temporary girder was installed in the center of the pier, and a circular crane with a hanging load of 52T was installed on each pier. The depositing device 1 shown in Fig. 1 is attached to each end of the I-shaped girder that has been transported in the longitudinal direction on the temporary girder in the center of the pier as shown in Fig. 2. Fig. 2 shows only one end of the girder. ), hoist the engineering shape with a gantry crane, drive the take-off movement motor 9 by remote control to maintain the ink point position at the center of suspension of the circular crane, move the I-shape laterally, and lift the girder. The construction work was carried out.
省力、安全、短工期の点で大成功を収めた。It was a great success in terms of labor saving, safety, and short construction period.
本発明方法により、プレキャスト桁をピア間に架設する
場合であって同一径間に異なる長さの桁を架設する場合
、省力、安全、短工期に架設を行うことができ、橋梁建
設工事に寄与するところが極めて大である。By the method of the present invention, when precast girders are to be erected between piers and girders of different lengths are to be erected in the same span, construction can be performed in a labor-saving, safe and short construction period, contributing to bridge construction work. There is a huge amount to do.
第1図は本発明装置の実施例の三図面、第2図・はこの
装置を桁に取り付けた状態を示す説明図である。
l・・・析出装置
2・・・結合部
5・・・クレーン吊具
6・・・吊手
7・・・支持ローラ
8・・・ガイドレール
9・・・モータ
10・・・スクリュー
11.12・・・リミットスイッチ
20・・・桁
21・・・枕材
22・・・ゲビンデ鋼棒FIG. 1 is a three-dimensional drawing of an embodiment of the device of the present invention, and FIG. 2 is an explanatory diagram showing the state in which this device is attached to a girder. l...Precipitating device 2...Joining part 5...Crane hanging tool 6...Hanger 7...Support roller 8...Guide rail 9...Motor 10...Screw 11.12 ... Limit switch 20 ... Girder 21 ... Pillow material 22 ... Gebinde steel bar
Claims (1)
当り、桁吊点を桁長方向に連続的に移動させながら、該
桁をピア上に載設された門型クレーンにより、横移動す
ることを特徴とする同一架設径間における異長桁の架設
工法。 2 桁とゲビンデ鋼棒で結合する結合部を有すると共に
、ガイドレールを内蔵し、該ガイドレールに沿って転動
するローラを介して桁長手方向に移動自在なクレーン吊
具を備え、かつ該吊具を移動させる動力装置を備えたこ
とを特徴とする桁吊装置。[Claims] 1. When constructing a plurality of girders of different lengths in the same construction span, the girder is mounted on a pier while continuously moving the girder suspension point in the length direction of the girder. A construction method for constructing girders of different lengths over the same span, characterized by horizontal movement using a portal crane. 2. It has a joint that connects the girder with a Gebinde steel rod, has a built-in guide rail, and is equipped with a crane hoist that can be moved in the longitudinal direction of the girder via rollers that roll along the guide rail. A girder hanging device characterized by being equipped with a power device for moving tools.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30740886A JPH0649963B2 (en) | 1986-12-23 | 1986-12-23 | Construction method and equipment for different length girders in the same span |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30740886A JPH0649963B2 (en) | 1986-12-23 | 1986-12-23 | Construction method and equipment for different length girders in the same span |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS63160992A true JPS63160992A (en) | 1988-07-04 |
JPH0649963B2 JPH0649963B2 (en) | 1994-06-29 |
Family
ID=17968691
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30740886A Expired - Fee Related JPH0649963B2 (en) | 1986-12-23 | 1986-12-23 | Construction method and equipment for different length girders in the same span |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0649963B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102079473A (en) * | 2011-01-14 | 2011-06-01 | 海南大学 | Self-aligning hanger |
CN104058334A (en) * | 2014-06-05 | 2014-09-24 | 上海卫星装备研究所 | Automatic leveling type lifting appliance device |
-
1986
- 1986-12-23 JP JP30740886A patent/JPH0649963B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102079473A (en) * | 2011-01-14 | 2011-06-01 | 海南大学 | Self-aligning hanger |
CN104058334A (en) * | 2014-06-05 | 2014-09-24 | 上海卫星装备研究所 | Automatic leveling type lifting appliance device |
Also Published As
Publication number | Publication date |
---|---|
JPH0649963B2 (en) | 1994-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111851313A (en) | Pile-driving bridge erecting construction all-in-one machine and construction method thereof | |
US3579759A (en) | Trellis unit for making of beams | |
CN112342915B (en) | Construction method for gantry hoisting beam of overhead track | |
JP2010031607A (en) | Construction method for grade separation | |
JPS63160992A (en) | Method of erection construction of different length beam between same erection diameter and device thereof | |
CN212612030U (en) | Pile bridge erection construction all-in-one | |
CN107792802A (en) | A kind of small members movement and mounting system and method | |
JPH084034A (en) | Basement skeleton building construction in inverted construction work of building | |
JP2768281B2 (en) | Bridge construction method | |
JPH0546407B2 (en) | ||
CN218373343U (en) | Movable bridge floor hogging moment stretch-draw operating means | |
JPH0475323B2 (en) | ||
CN214783320U (en) | Prefabricated assembly component erecting equipment driven by change gear to move forward | |
CN220953007U (en) | Portal frame for installing embedded plates of arch seats of middle-bearing arch bridge | |
JPH0711620A (en) | Construction method of artificial ground | |
CN217377146U (en) | Gantry support spanned in middle of cable and cable system | |
CN210966786U (en) | Flexible manufacturing production line for spatial three-dimensional reinforcing mesh | |
JP3131799B2 (en) | Bar arrangement method and bar arrangement device for caisson sidewall reinforcement | |
CN112663509A (en) | Gate-type mound roof beam construction equipment | |
JPS62185905A (en) | Moving type mold frame construction method of slab of high bridge | |
CN115522473A (en) | Bridge high pier making machine and construction method thereof | |
CN114319067A (en) | Large-section steel box girder and construction method thereof | |
CN115094793A (en) | Protective dismantling method for pier in limited operation space | |
CN117862373A (en) | Beam field steel bar processing plant | |
CN110700108A (en) | Method for installing orthotropic bridge deck slab of steel truss arch bridge in segmented mode |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees | ||
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |