JPS627706Y2 - - Google Patents

Info

Publication number
JPS627706Y2
JPS627706Y2 JP4899883U JP4899883U JPS627706Y2 JP S627706 Y2 JPS627706 Y2 JP S627706Y2 JP 4899883 U JP4899883 U JP 4899883U JP 4899883 U JP4899883 U JP 4899883U JP S627706 Y2 JPS627706 Y2 JP S627706Y2
Authority
JP
Japan
Prior art keywords
foundation
underground
underground structure
ground
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP4899883U
Other languages
Japanese (ja)
Other versions
JPS59156937U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP4899883U priority Critical patent/JPS59156937U/en
Publication of JPS59156937U publication Critical patent/JPS59156937U/en
Application granted granted Critical
Publication of JPS627706Y2 publication Critical patent/JPS627706Y2/ja
Granted legal-status Critical Current

Links

Description

【考案の詳細な説明】 本考案は簡易な工事で埋設部分に作用する浮力
による浮上がりを防止できるようにした地下構造
物に関するものである。
[Detailed Description of the Invention] The present invention relates to an underground structure that can prevent floating due to buoyancy acting on a buried portion by simple construction.

近来、土地の有効利用を図るために、例えば台
所、リビングなどの床下からその地面下にかけて
埋設するようにした地下収納式の地下収納庫や地
下室等の地下構造物に関する提案が種々なされ、
またこの地下構造物自体の素材として、施工に長
時間を要していた従来のコンクリート造に比べ
て、工業生産化にとつて有利なFRP等の合成樹
脂や金属板等を用いることにより、現場施工の簡
易化や工期の短縮などを図るようにした提案もな
されている。
In recent years, in order to make effective use of land, various proposals have been made regarding underground structures such as underground storage sheds and basements that are buried under the floors of kitchens, living rooms, etc.
In addition, as the material for this underground structure itself, compared to conventional concrete construction, which takes a long time to construct, synthetic resins such as FRP and metal plates, etc., which are advantageous for industrial production, can be used on-site. Proposals have also been made to simplify construction and shorten the construction period.

そして、この合成樹脂製や金属板等から構成さ
れた地下構造物の場合においては、合成樹脂製の
場合にはその素材自体の特性として、また金属板
製の場合は使用する鋼板等の肉厚が薄いので軽量
であり、この軽量となること自体は工業生産化に
とつては一般的には有利な条件ではあるが、地下
構造物においては地下水等による浮力を考慮しな
ければならないので、この点に対しては不利とな
るのである。
In the case of underground structures made of synthetic resin or metal plates, the characteristics of the material itself in the case of synthetic resin, and the thickness of the steel plate used in the case of metal plates, etc. Since it is thin, it is lightweight, and although this light weight itself is generally an advantageous condition for industrial production, in underground structures, buoyancy due to groundwater etc. must be taken into account, so this This is a disadvantage in terms of points.

このような合成樹脂製や金属板等からなる比較
的軽量な地下構造物の場合には、従来第1図及び
第2図に示すように、地下収納庫や地下室等の地
下構造物1が埋設される根切り底に割栗石2を敷
いて突き固めた後、この上にコンクリートを打設
して地下水等による浮力に対抗するだけの基礎板
3を設け、この基礎板3中に埋設したアンカーボ
ルト4により固定用アングル5等を介して地下構
造物1を基礎板3に固定することにより地下構造
物1の浮上がりを防止する構造が採られている。
しかしながら、このように基礎板3の重量により
基礎板3上に固定した地下構造物1の地下水等に
よる浮上りを防止する構造では、浮力に対抗でき
る重量分の基礎板3を打設することになるので、
結果として基礎板3の高さを高くしなければなら
ないので根切りの深さが深くなり、地下構造物1
自体を合成樹脂や金属板等で構成することにより
プレハブ的手法を採り入れ短工期施工を期待して
いるにもかかわらず、現実には、前記割栗石2や
基礎板3施工のため、根伐後に、山留め工事、割
栗地業、型枠の組立、配筋、コンクリート打設
等、従来の基礎一体型の地下室等と変わりのない
面倒な作業を伴うことになるのである。
In the case of such relatively lightweight underground structures made of synthetic resin, metal plates, etc., as shown in Figures 1 and 2, underground structures 1 such as underground storage sheds and basements are conventionally buried. After laying and tamping cracked stones 2 at the bottom of the root cut, concrete is poured on top of this to provide a foundation plate 3 that resists the buoyancy caused by groundwater, etc., and an anchor buried in this foundation plate 3. A structure is adopted in which the underground structure 1 is fixed to the foundation plate 3 with bolts 4 via fixing angles 5 and the like to prevent the underground structure 1 from floating up.
However, in a structure in which the weight of the foundation plate 3 prevents the underground structure 1 fixed on the foundation plate 3 from floating due to groundwater, etc., it is necessary to cast the foundation plate 3 with a weight that can counteract the buoyancy. So,
As a result, the height of the foundation plate 3 must be increased, so the depth of the root cutting becomes deeper, and the underground structure 1
Although it is hoped that a prefabricated method will be adopted and the construction period will be shortened by constructing the structure itself from synthetic resin or metal plates, in reality, due to the above-mentioned split stone 2 and foundation plate 3 construction, it will be necessary to construct the stone after the root cutting. It involves the same troublesome work as a conventional foundation-integrated basement, such as mountain retaining work, cracking ground work, formwork assembly, reinforcing, and concrete pouring.

本考案は上記の点に鑑み、地下収納庫や地下室
等の地下構造物の地下水等による浮上りを簡易な
工事で防止できるようにしたものであり、以下に
本考案の実施例を第3図〜第6図により説明す
る。
In view of the above points, the present invention has been developed to prevent underground structures such as underground storage sheds and basements from floating up due to groundwater etc. with simple construction. This will be explained with reference to FIG.

第3図は本考案による地下構造物の一実施例を
示し、この地下構造物が地上構造物の基礎の間に
位置して埋設された状態の斜視図、第4図は第3
図の側面図であり、10は地下収納庫や地下室等
の地下構造物であり、この地下構造物10は地上
構造物(図示せず)の基礎7の間に位置して配設
され、その一部または全部を地面下に埋設されて
いる。6は上記基礎7の下方に敷かれた割栗石で
ある。2′は、従来と同様に上記地下構造物10
が埋設される根切り底に敷いて突き固めた割栗石
で、この割栗石2′は従来よりも広く、すなわ
ち、地下構造物10の基礎7の下方位置まで延長
して布設されており、この上にコンクリートを打
設して基礎板3′を設け、この基礎板3′中に埋設
したアンカーボルト4により固定用アングル5等
を介して地下構造物10が基礎板3′に固定され
ている。本考案においては、上記地上構造物の基
礎7の下方に位置する地下構造物10の基礎板
3′上に、コンクリート等からなる柱11を立設
し、この柱11の上端を前記地上構造物の基礎7
の下方にこの基礎7と当接して設けるか、または
柱11の上端に適宜連結金具(図示せず)等を取
付け、この連結金具と地上構造物の基礎7とを連
結することにより、地下構造物10に作用する地
下水等の浮力による力が、柱11により地上構造
物の基礎7に伝達され、地上構造物及びこの地上
構造物の基礎7の自重によつて、地下構造物10
の地下水等による浮上りを防止するようにしてい
る。その結果基礎板3′の高さを従来よりも薄く
することが可能となるので、地下構造物10を埋
設するための全体としての根切り深さが浅くてす
み、工事が簡単となるようにしているのである。
Fig. 3 shows an embodiment of the underground structure according to the present invention, and Fig. 4 is a perspective view of the underground structure located between the foundations of above-ground structures.
10 is a side view of the figure, and 10 is an underground structure such as an underground storage or a basement, and this underground structure 10 is located between the foundations 7 of an above-ground structure (not shown), and Part or all of it is buried underground. Reference numeral 6 indicates a split stone placed below the foundation 7. 2' is the underground structure 10 as in the conventional case.
This split stone 2' is laid and compacted at the bottom of the root cut where the underground structure 10 is to be buried. A foundation plate 3' is provided by pouring concrete on top, and the underground structure 10 is fixed to the foundation plate 3' via anchor bolts 4 buried in this foundation plate 3' via fixing angles 5, etc. . In the present invention, a column 11 made of concrete or the like is erected on the foundation plate 3' of the underground structure 10 located below the foundation 7 of the above ground structure, and the upper end of this column 11 is connected to the above ground structure. Basics 7
The underground structure can be constructed by installing a connecting fitting (not shown) below the pillar 11 in contact with the foundation 7, or attaching an appropriate connecting fitting (not shown) to the upper end of the pillar 11, and connecting this connecting fitting to the foundation 7 of the above-ground structure. The force due to the buoyancy of groundwater or the like acting on the object 10 is transmitted to the foundation 7 of the above-ground structure by the pillar 11, and the weight of the above-ground structure and the foundation 7 of this above-ground structure causes the underground structure 10 to
This is to prevent surfacing due to groundwater, etc. As a result, the height of the foundation plate 3' can be made thinner than before, so the overall root cutting depth for burying the underground structure 10 can be shallower, making the construction easier. -ing

本考案は上記の如く、地上構造物の基礎の間に
位置して配設され、その一部または全部を地下に
埋設してなる地下構造物において、該地下構造物
の基礎上に柱を立設すると共に、該柱の上端を前
記地上構造物の基礎の下方に該基礎と当接させ、
または該基礎と連結した地下構造物であり、地下
構造物に作用する地下水等による浮力が柱を経て
地上構造物の基礎に伝達され、地上構造物及びこ
の地上構造物の基礎の自重により地下構造物の浮
上りが防止できるようになり、従つて、第5図に
示すような従来における基礎板3の重量により地
下構造物10の浮上りを防止する構造と比べて、
第6図に示すように、基礎板3′の高さを薄くす
ることが可能となつたことによつて、全体として
の根切り深さが浅くてすむようになり、工事が簡
単となるのである。尚根切りの深さが浅くなるこ
とは、地下水位のことを考慮する上でも有利な条
件となる。
As described above, the present invention provides an underground structure that is located between the foundations of above-ground structures and is partially or wholly buried underground, in which pillars are erected on the foundations of the underground structure. and bringing the upper end of the column into contact with the foundation below the foundation of the above-ground structure,
Or, it is an underground structure connected to the foundation, and the buoyant force due to groundwater, etc. acting on the underground structure is transmitted to the foundation of the above-ground structure through the columns, and the weight of the above-ground structure and the foundation of this above-ground structure is used to build up the underground structure. This makes it possible to prevent objects from floating, compared to the conventional structure shown in FIG. 5, which prevents the underground structure 10 from floating due to the weight of the foundation plate 3.
As shown in Figure 6, by making it possible to reduce the height of the foundation plate 3', the overall root cutting depth can be reduced, making construction easier. . The shallower root cutting depth is also an advantageous condition when considering the groundwater level.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来の地下構造物の埋設状態を示す斜
視図、第2図は第1図の側面図である。第3図は
本考案による地下構造物の一実施例を示す埋設状
態の斜視図であり、第4図は第3図の側面図であ
る。第5図は従来の地下構造物の埋設状態を示す
側面図であり、第6図は本考案による地下構造物
の埋設状態を示す側面図で、従来の地下構造物と
本考案による地下構造物との根切り深さを比較し
た図面である。 符号の説明、1……地下構造物、1a……開口
部、2,2′……割栗石、3,3′…基礎板、4…
…アンカーボルト、5……固定用アングル、6…
…割栗石、7……基礎(地上構造物の)、8……
地面、10……地下構造物、10a……開口部、
11……柱、D1……根切り深さ(従来)、D2……
根切り深さ(本考案)、D3……本考案と従来との
根切り深さの差。
FIG. 1 is a perspective view showing a buried state of a conventional underground structure, and FIG. 2 is a side view of FIG. 1. FIG. 3 is a perspective view of an embodiment of the underground structure according to the present invention in a buried state, and FIG. 4 is a side view of FIG. 3. Fig. 5 is a side view showing a buried state of a conventional underground structure, and Fig. 6 is a side view showing a buried state of an underground structure according to the present invention. This is a drawing comparing the root cutting depth with. Explanation of symbols, 1... Underground structure, 1a... Opening, 2, 2'... Split stone, 3, 3'... Foundation plate, 4...
...Anchor bolt, 5...Fixing angle, 6...
...Warikuri stone, 7...Foundation (above ground structure), 8...
Ground, 10... Underground structure, 10a... Opening,
11...Column, D 1 ... Root cutting depth (conventional), D 2 ...
Root cutting depth (this invention), D 3 ... Difference in root cutting depth between this invention and the conventional one.

Claims (1)

【実用新案登録請求の範囲】 1 地上構造物の基礎の間に位置して配設され、
その一部または全部を地下に埋設してなる地下
構造物において、該地下構造物の基礎上に柱を
立設すると共に、該柱の上端を前記地上構造物
の基礎の下方に該基礎と当接させ、または該基
礎と連結してなることを特徴とする地下構造
物。 2 合成樹脂材からなるものであることを特徴と
する実用新案登録請求の範囲第1項記載の地下
構造物。 3 合成樹脂材がFRPであることを特徴とする
実用新案登録請求の範囲第2項記載の地下構造
物。
[Scope of claims for utility model registration] 1. Located between the foundations of above-ground structures,
In an underground structure partially or completely buried underground, a column is erected on the foundation of the underground structure, and the upper end of the column is placed below the foundation of the above-ground structure so that it is in contact with the foundation. An underground structure characterized by being in contact with or connected to the foundation. 2. The underground structure according to claim 1 of the utility model registration, characterized in that it is made of a synthetic resin material. 3. The underground structure according to claim 2 of the utility model registration claim, characterized in that the synthetic resin material is FRP.
JP4899883U 1983-04-04 1983-04-04 underground structure Granted JPS59156937U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4899883U JPS59156937U (en) 1983-04-04 1983-04-04 underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4899883U JPS59156937U (en) 1983-04-04 1983-04-04 underground structure

Publications (2)

Publication Number Publication Date
JPS59156937U JPS59156937U (en) 1984-10-22
JPS627706Y2 true JPS627706Y2 (en) 1987-02-23

Family

ID=30179513

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4899883U Granted JPS59156937U (en) 1983-04-04 1983-04-04 underground structure

Country Status (1)

Country Link
JP (1) JPS59156937U (en)

Also Published As

Publication number Publication date
JPS59156937U (en) 1984-10-22

Similar Documents

Publication Publication Date Title
US5039256A (en) Pinned foundation system
AU2019222970B2 (en) Building System
JPS627706Y2 (en)
KR102172651B1 (en) Simple pool construction method
US4818142A (en) Method and apparatus for constructing a walled pool excavation
JP6639006B1 (en) Architectural solid foundation and its construction method.
JPS627707Y2 (en)
JP3029343U (en) Form tool for mortar material injection in exposed elastic fixed column base method
JPH0324541B2 (en)
US20240018771A1 (en) Building system
JP2515227B2 (en) Installation method of cast-in-place concrete foundation and precast concrete wall slab
JPS6335923A (en) Basement and its construction
GB2385071A (en) Building foundation with insulating members
KR20100018183A (en) Varied depth independent footing method formed by tapering excavation
JPH073813A (en) Construction of building foundation
JPH07279184A (en) Floating underground beam foundation for building
JPH0540110Y2 (en)
JPS5833156Y2 (en) Pile head structure
JP2776620B2 (en) Basic structure of building
AU727660B2 (en) Slab construction method
JP3000511B2 (en) Retaining wall
JPH10317487A (en) Support structure of floor slab in building structure utilizing pile for column, and execution method of the support structure
JPH0156215B2 (en)
JPS594011B2 (en) Concrete foundation method
JPS62276119A (en) Composite piling work