Prior art keywords
presser
reinforcing bar
frame
metal fitting
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP18397881U
Other languages
Japanese (ja)
Other versions
JPS5890230U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP18397881U priority Critical patent/JPS5890230U/en
Publication of JPS5890230U publication Critical patent/JPS5890230U/en
Application granted granted Critical
Publication of JPS6231460Y2 publication Critical patent/JPS6231460Y2/ja
Granted legal-status Critical Current

Links

Description

【考案の詳細な説明】 この考案は連続地中壁工事において使用する鉄
筋篭の浮上り防止装置に関するものである。
[Detailed description of the invention] This invention relates to a device for preventing floating of reinforcing bar cages used in continuous underground wall construction.

連続地中壁工事においては各パネルの削溝終了
後に鉄筋篭を建込み、トレミー管により水中コン
クリートを打設する。このとき第1図に示すよう
に鉄筋篭に回り込むコンクリート圧によつて鉄筋
篭を浮上がらせるような力が作用する。従つてコ
ンクリート打設時には予めこの鉄筋篭の浮上りを
防止するような処置が必要とされる。
In continuous underground wall construction, a reinforcing cage is erected after each panel has been cut, and underwater concrete is poured using tremie pipes. At this time, as shown in FIG. 1, the concrete pressure that wraps around the reinforcing bar cage acts on the reinforcing bar cage to cause it to float. Therefore, when concrete is poured, measures must be taken in advance to prevent the reinforcing bar cage from floating up.

この考案の連続地中壁用鉄筋篭の浮上り防止装
置は上述のような鉄筋篭の浮上りを防止する必要
から、下記の条件を満足することを目的として考
案されたものである。
The device for preventing floating of reinforcing bar cages for continuous underground walls of this invention was devised for the purpose of satisfying the following conditions in view of the need to prevent floating of reinforcing bar cages as described above.

鉄筋篭の浮上りを防止するのに十分な強度を
有すること。
Must have sufficient strength to prevent the reinforcing bar cage from floating.

装置の取付けが容易であること。 The equipment should be easy to install.

装置の取りはずし、転用が可能であること。 The device must be able to be removed and repurposed.

以下この考案を図示した実施例(第2図〜第8
図)に基づいて説明する。
Examples illustrating this invention (Figs. 2 to 8) are as follows.
The explanation will be based on Figure).

この浮上り防止装置は連続地中壁まわりのガイ
ドウオール1にアンカー筋2を設け、これを後述
するような治具により鉄筋篭3と連結し、浮上り
を防止するものである。
This floating prevention device provides anchor bars 2 on a guide wall 1 around a continuous underground wall, and connects them to a reinforcing bar cage 3 using a jig as described later to prevent floating.

アンカー筋2は施工する連続地中壁に沿つて両
側のガイドウオール1の上面に所定間隔をおいて
あるいは適当な間隔で突設されている。この実施
例ではシヤツクル7を係止させるため突出部は逆
U字状としてガイドウオール1に埋め込まれてい
る。
The anchor reinforcements 2 are protruded from the upper surfaces of the guide walls 1 on both sides at predetermined or appropriate intervals along the continuous underground wall to be constructed. In this embodiment, in order to lock the shackle 7, the protrusion is embedded in the guide wall 1 in the shape of an inverted U.

図中4は鉄筋篭3の受架台で、H形鋼が使用さ
れている。そしてこの受架台4上に溝形鋼などの
押え架台5を架け渡し、受架台4を押え付けるこ
とにより鉄筋篭3の浮上りを防止する。この押え
架台5の上には押え金具6が跨設されており押え
架台5上をスライドさせることができる。そして
アンカー筋2の位置へスライドさせ、シヤツクル
7等の連結材でアンカー筋2に連結する。図の実
施例では押え金具6は一方が短かく、他方が長い
二枚の垂下片8,9とこれらを連結する二枚の連
結片10および連結片10下端の水平片11から
なりスライド用の凹部を形成している。そして長
い方の垂下片8にはシヤツクル7のボルトを挿通
するための穴が設けられ、アンカー筋2との連結
に利用される。また前記水平片11にはほぼ中央
にねじ穴が形成され、これに締付調整ボルト12
を螺合してある。締付調整ボルト12の先端は押
え架台5の上面に当接するようになつており、従
つてアンカー筋2と押え金具6をシヤツクル7で
連結した状態で締付調整ボルト12を回転させ押
し込むことによりアンカー筋2と押え架台5が緊
結される。この結果鉄筋篭3の受架台4が押え架
台5によつて押え付けられるので、鉄筋篭3の浮
上りが防止される。
4 in the figure is a receiving frame for the reinforcing bar cage 3, and H-shaped steel is used. A holding frame 5 made of channel steel or the like is placed over this receiving frame 4 to press down the receiving frame 4 to prevent the reinforcing bar basket 3 from floating up. A presser metal fitting 6 is provided over the presser frame 5 and can be slid on the presser frame 5. Then, it is slid to the position of the anchor bar 2 and connected to the anchor bar 2 using a connecting member such as a shaft 7. In the illustrated embodiment, the presser metal fitting 6 consists of two hanging pieces 8 and 9, one of which is short and the other long, two connecting pieces 10 that connect these pieces, and a horizontal piece 11 at the lower end of the connecting piece 10. A recess is formed. The longer hanging piece 8 is provided with a hole through which a bolt of the shaft 7 is inserted, and is used for connection with the anchor bar 2. Further, a screw hole is formed in the horizontal piece 11 approximately in the center, and a tightening adjustment bolt 12 is inserted into the screw hole.
are screwed together. The tip of the tightening adjustment bolt 12 is designed to come into contact with the upper surface of the presser frame 5, and therefore, by rotating and pushing the tightening adjustment bolt 12 while the anchor bar 2 and the presser metal fitting 6 are connected by the shackle 7. The anchor bar 2 and the presser frame 5 are tightly connected. As a result, the receiving frame 4 of the reinforcing bar cage 3 is held down by the holding frame 5, so that floating of the reinforcing bar cage 3 is prevented.

施工手順は、第6図〜第8図に示すように、ま
ず受架台4上に押え架台5を載置する。なお押え
架台5はプレハブ化した一体のものとすることに
より施工の簡略化が図れる。次に押え架台5に押
え金具6を載せアンカー筋2の位置までスライド
させる。シヤツクル7でアンカー筋2と押え金具
6を連結し、次いで押え金具6の締付調整ボルト
を締めて、アンカー筋2と押え架台5を緊結す
る。この後水中コンクリートの打設を行ない、一
連の連続地中壁工事を行なう。
In the construction procedure, as shown in FIGS. 6 to 8, first, the presser pedestal 5 is placed on the receiving pedestal 4. Note that construction can be simplified by making the presser frame 5 a prefabricated integral piece. Next, the presser metal fitting 6 is placed on the presser frame 5 and slid to the position of the anchor bar 2. The anchor bar 2 and the presser metal fitting 6 are connected by the shaft 7, and then the tightening adjustment bolt of the presser metal fitting 6 is tightened to tightly connect the anchor bar 2 and the presser frame 5. After this, underwater concrete will be placed and a series of continuous underground wall works will be carried out.

この考案は以上の構成からなり、前述した目的
を達成するほか、アンカー筋の位置が不規則であ
つても取付けに支障をきたさない、アンカー筋と
鉄筋篭とを緊結できるといつた利点を有する。
This invention consists of the above-mentioned structure, and in addition to achieving the above-mentioned purpose, it has the advantage that even if the position of the anchor bar is irregular, there is no problem in installation, and the anchor bar and the reinforcing bar cage can be tightly tied together. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は鉄筋篭の浮上りを説明するための縦断
面図、第2図はこの考案の実施例における平面
図、第3図は左側面図、第4図は正面図、第5図
は右側面図、第6図〜第8図は施工手順を示した
もので第6図は地中壁と垂直方向の縦断面図、第
7図は斜視図、第8図は側面図である。 1・・ガイドウオール、2・・アンカー筋、
3・・鉄筋篭、4・・受架台、5・・押え架台、
6・・押え金具、7・・シヤツクル、8,9・・
垂下片、10・・連結片、11・・水平片、1
2・・締付調整ボルト、13・・トレミー管、1
4・・コンクリート。
Fig. 1 is a longitudinal sectional view for explaining the floating of the reinforcing bar cage, Fig. 2 is a plan view of an embodiment of this invention, Fig. 3 is a left side view, Fig. 4 is a front view, and Fig. 5 is a The right side view and FIGS. 6 to 8 show the construction procedure. FIG. 6 is a vertical cross-sectional view in a direction perpendicular to the underground wall, FIG. 7 is a perspective view, and FIG. 8 is a side view. 1. Guide wall, 2. Anchor wire,
3. Reinforced cage, 4. Support stand, 5. Holder stand,
6... Presser metal fitting, 7... Shackle, 8, 9...
Hanging piece, 10... Connecting piece, 11... Horizontal piece, 1
2. Tightening adjustment bolt, 13. Tremy tube, 1
4. Concrete.

Claims (1)

【実用新案登録請求の範囲】 (1) ガイドウオール上面に突出させたアンカー筋
と、鉄筋篭受架台上に架け渡した押え架台と、
押え架台に跨設され押え架台上をスライドする
押え金具と、前記アンカー筋と押え金具を連結
する連結材とからなり、前記押え金具には先端
部を押え架台上面に当接させた締付調整ボルト
が螺合されていることを特徴とする連続地中壁
用鉄筋篭の浮上り防止装置。 (2) 連結材はシヤツクルである実用新案登録請求
の範囲第1項記載の連続地中壁用鉄筋篭の浮上
り防止装置。
[Scope of Claim for Utility Model Registration] (1) Anchor bars protruding from the upper surface of the guide wall, a presser frame suspended over the reinforcing bar cage receiving frame,
It consists of a presser metal fitting that straddles the presser frame and slides on the presser frame, and a connecting member that connects the anchor bar and the presser metal fitting. A device for preventing floating of a reinforcing bar cage for continuous underground walls, characterized by screwing together bolts. (2) The device for preventing floating of a reinforcing bar cage for a continuous underground wall according to claim 1 of the utility model registration claim, wherein the connecting member is a shackle.
JP18397881U 1981-12-10 1981-12-10 Floating prevention device for reinforcing bar cages for continuous underground walls Granted JPS5890230U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18397881U JPS5890230U (en) 1981-12-10 1981-12-10 Floating prevention device for reinforcing bar cages for continuous underground walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18397881U JPS5890230U (en) 1981-12-10 1981-12-10 Floating prevention device for reinforcing bar cages for continuous underground walls

Publications (2)

Publication Number Publication Date
JPS5890230U JPS5890230U (en) 1983-06-18
JPS6231460Y2 true JPS6231460Y2 (en) 1987-08-12

Family

ID=29983724

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18397881U Granted JPS5890230U (en) 1981-12-10 1981-12-10 Floating prevention device for reinforcing bar cages for continuous underground walls

Country Status (1)

Country Link
JP (1) JPS5890230U (en)

Also Published As

Publication number Publication date
JPS5890230U (en) 1983-06-18

Similar Documents

Publication Publication Date Title
US4130977A (en) Concrete insert
US1729935A (en) Wall anchor
US4182092A (en) Building panel chord tie and method of tieing together precast concrete building panels
JPS6231460Y2 (en)
EP0127359A1 (en) Slotted insert and nut assembly
CN216041972U (en) Installation assembly in steel wire mesh combined heat-insulation plate cast-in-place concrete wall
US5283999A (en) Prefabricated panel for building construction
KR102175989B1 (en) Anchor bolt fixture
JPS6122088B2 (en)
CN211775201U (en) Embedded pipeline bracket
JPH0115774Y2 (en)
JPS5814733Y2 (en) ALC panel with embedded metal fittings
CN204326495U (en) A kind of structure of tool-type anchored end of Overhanging Outside Scaffold section steel beam
CN213234237U (en) Fair-faced concrete outer wall scaffold wall connecting piece
CN212957239U (en) Assembled building board
JPS639733Y2 (en)
CN113152921B (en) Ground ring beam reinforcing structure and construction method
JP2001098684A (en) Structure for fixing form
CN211948996U (en) Connect reliable prefabricated assembled shear force wall
CN211775200U (en) Overhanging type pipeline bracket
JPS5820866A (en) Reinforcing wire arranging and connecting method of vertical and horizontal reinforcing wires for wall of construction
JPS5953416B2 (en) How to install anti-corrosion formwork for steel sheet pile structures
KR970005544Y1 (en) Device for tying forms
JPS6013951Y2 (en) Handrail mounting structure
KR200162948Y1 (en) Device for supporting wall forms