JPS62233789A - Method of building nuclear power plant - Google Patents

Method of building nuclear power plant

Info

Publication number
JPS62233789A
JPS62233789A JP61076465A JP7646586A JPS62233789A JP S62233789 A JPS62233789 A JP S62233789A JP 61076465 A JP61076465 A JP 61076465A JP 7646586 A JP7646586 A JP 7646586A JP S62233789 A JPS62233789 A JP S62233789A
Authority
JP
Japan
Prior art keywords
torus
wall
reactor
containment vessel
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP61076465A
Other languages
Japanese (ja)
Other versions
JPH0471478B2 (en
Inventor
塚田 幸男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP61076465A priority Critical patent/JPS62233789A/en
Publication of JPS62233789A publication Critical patent/JPS62233789A/en
Publication of JPH0471478B2 publication Critical patent/JPH0471478B2/ja
Granted legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)
  • Structure Of Emergency Protection For Nuclear Reactors (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明のし1的〕 (産業上の利用分野) 本発明は、トーラス型圧力抑制室を備えた原子炉格納容
器を持つ沸騰水型原子炉を有する原子力発電所の建設方
法に関する。
[Detailed description of the invention] [First aspect of the invention] (Industrial application field) The present invention is directed to a nuclear power plant having a boiling water reactor having a reactor containment vessel equipped with a torus-shaped pressure suppression chamber. Concerning construction methods.

(従来の技術) 一般に原子炉建屋に対するトーラス型原子炉格納容器の
配設構造は、第3図の縦断面図に示されるように、鋼製
の原子炉格納容器3が、コンクリートを打設した原子炉
建屋マット(1)1.同(II)4にアンカー(図示省
略)で固定され、側面を地下シールドウオール(1)5
.同(II)9.1階シールドウオール12等で囲まれ
た上、底部空間にコンクリート8を充填して設置される
。トーラス2は、同じく原子炉建屋マット(1)1にア
ンカー2Aで固定され、原子炉建屋マット(■)1から
立上ってトーラス2の外方を囲むW6、および壁6と地
下シールドウオール(■)9を繋いでトーラス2の上方
を覆う原子炉建屋1階の床IOにより画成されるトーラ
ス室7内に収納されている。床IOの上方には1階の壁
11.2階の床13が配設される。
(Prior art) In general, the arrangement structure of a torus-type reactor containment vessel in a nuclear reactor building is as shown in the vertical cross-sectional view of Fig. Reactor building mat (1) 1. It is fixed to (II) 4 with an anchor (not shown), and the side surface is attached to underground shield wall (1) 5.
.. (II) 9. The first floor is surrounded by a shield wall 12, etc., and is installed by filling the bottom space with concrete 8. The torus 2 is also fixed to the reactor building mat (1) 1 with an anchor 2A, and W6 rises from the reactor building mat (■) 1 and surrounds the outside of the torus 2, and the wall 6 and the underground shield wall ( (2) It is housed in the torus room 7 defined by the floor IO on the first floor of the reactor building, which connects the torus 2 and covers the upper part of the torus 2. A wall 11 on the first floor and a floor 13 on the second floor are provided above the floor IO.

従来このような構造部の建設は、第4図の工程図に示す
ように、まず原子炉建屋マット(I)1の完成後に、ト
ーラス2のアンカーボルトおよび原子炉格納容器3のア
ンカーボルトの設定を行なう。
Conventionally, in the construction of such a structure, as shown in the process diagram of Figure 4, after the reactor building mat (I) 1 is completed, the anchor bolts of the torus 2 and the anchor bolts of the reactor containment vessel 3 are set. Do the following.

次に原子炉建屋マット(■)4の打設を行ない、地下シ
ールドウオール(1)5を施工し、原子炉格納容器3を
組立てる。一方、並行してトーラス室の壁6の施工を行
ない、地下シールドウオール(1)5と、トーラス室の
壁6が完成したならば、トーラス室7にトーラス2を搬
入し、据付ける。こうして、トーラス2の据付けが完了
したならば、先に組立てが完了している原子炉格納容器
3と合せ。
Next, the reactor building mat (■) 4 is placed, the underground shield wall (1) 5 is constructed, and the reactor containment vessel 3 is assembled. On the other hand, the wall 6 of the torus room is constructed in parallel, and once the underground shield wall (1) 5 and the wall 6 of the torus room are completed, the torus 2 is carried into the torus room 7 and installed. In this way, once the installation of the torus 2 is completed, it is combined with the reactor containment vessel 3, which has been assembled previously.

耐圧試験を行なう。次に、原子炉格納容器3の塗装を行
ない、原子炉格納容器3の下部空間にコンクリート8を
充填し、地下シールドウオール(II)9を施工し、次
に1階の床10を施工する。この後、1階の壁11と1
階のシールドウオール12を施工し。
Perform a pressure test. Next, the reactor containment vessel 3 is painted, the lower space of the reactor containment vessel 3 is filled with concrete 8, the underground shield wall (II) 9 is constructed, and then the first floor floor 10 is constructed. After this, walls 11 and 1 on the first floor
Installed the shield wall 12 on the first floor.

2階の床13を施工していた。Floor 13 on the second floor was being constructed.

(発明が解決しようとする問題点) 上述した建設工程では、トーラス2とトーラス室の壁6
との間隔が狭い為、トーラス室の壁6を施工する際の配
筋作業、型枠取付は及び取外し作業に用いる足場とトー
ラス2が干渉することから、トーラス室のl!4が完成
し1足場を撤去してからでなければトーラス2の搬入・
据付工事ができない。この為、原子炉格納容器3の組立
てが完了していても、トーラス室の壁6が完成しトーラ
ス2の搬入・据付工事が完了しなければ、原子炉格納容
器3の耐圧試験が実施できない、したがって、トーラス
室の壁6の施工からトーラス2の搬入・据付工事までの
作業が建設工事全体のクリティカルパスとなり、原子力
発電所建設工期の長期化を招く要因となっていた。
(Problems to be Solved by the Invention) In the construction process described above, the torus 2 and the wall 6 of the torus room
Because the distance between the torus 2 and the l! Torus 2 must be brought in after Torus 4 is completed and 1 scaffold is removed.
Installation work cannot be done. Therefore, even if the assembly of the reactor containment vessel 3 has been completed, the pressure test of the reactor containment vessel 3 cannot be carried out until the torus chamber wall 6 is completed and the torus 2 is delivered and installed. Therefore, the work from the construction of the wall 6 of the torus room to the carrying-in and installation of the torus 2 constitutes a critical path for the entire construction work, and is a factor that prolongs the construction period of the nuclear power plant.

本発明は、上記の事情を考慮してなされたものであり、
原子力発電所の建設工期を短縮することができるととも
に、建設作業の作業効率を向上させることができる原子
力発電所の建設方法を提供することを目的とする。
The present invention has been made in consideration of the above circumstances,
The purpose of the present invention is to provide a method for constructing a nuclear power plant that can shorten the construction period of a nuclear power plant and improve the efficiency of construction work.

〔発明の構成〕[Structure of the invention]

(問題点を解決するための手段) 本発明は原子炉建屋マット上に設置される原子炉格納容
器の建設と、この原子炉格納容器の下部外周を包囲して
原子炉建屋マット上に設置され、原子炉格納容器の圧力
抑制室を構成するトーラスの建設と、このトーラスの外
周に原子炉建屋マットから立上り設置される鉄筋コンク
リート製の壁の建設とを含む原子力発電所の建設方法で
あって、建設されるべき壁のトーラスとの対向面に一致
する板状部材を原子炉建屋マット上に立設し、板状部材
を壁のトーラスとの対向面造成用型枠兼壁の恒久碍成要
素として用いながら壁を原子炉建屋マット上に立設開始
し、壁の設立完了を待つことなく部分形成されたトーラ
スを原子炉建屋マット上に搬入設置する工程から成る。
(Means for Solving the Problems) The present invention relates to the construction of a reactor containment vessel installed on a reactor building mat, and the construction of a reactor containment vessel that is installed on the reactor building mat surrounding the lower outer periphery of the reactor containment vessel. , a method for constructing a nuclear power plant including constructing a torus constituting a pressure suppression chamber of a reactor containment vessel, and constructing a reinforced concrete wall rising from a reactor building mat around the outer periphery of the torus, A plate member corresponding to the surface facing the torus of the wall to be constructed is erected on the reactor building mat, and the plate member is used as a formwork for creating the surface facing the torus of the wall and as a permanent insulating element for the wall. The process consists of the steps of starting to erect the wall on the reactor building mat while using it as a reactor building mat, and then carrying and installing the partially formed torus on the reactor building mat without waiting for the completion of wall construction.

(作 用) 壁のトーラスとの対向面は、壁の建設中であっても、予
め原子炉建屋マット上に立設された板状部材に何等手を
加えることなく維持されるので、トーラスは、壁の建設
中であっても、何等障害物に阻止されることなく、原子
炉建屋マット上に搬入設置される。
(Function) Even during the construction of the wall, the surface of the wall facing the torus is maintained without any modification to the plate-shaped member installed on the reactor building mat, so the torus remains intact. Even during the construction of the wall, it is carried and installed on the reactor building mat without being blocked by any obstacles.

(実施例) 以下本発明の一実施例を第1図乃至第3図を参照して説
明する。
(Embodiment) An embodiment of the present invention will be described below with reference to FIGS. 1 to 3.

第1図は、本実施例を適用した場合のトーラス室の壁6
の水平断面を拡大して表す一部切欠き断面図であり、図
の右側面が第3図のトーラス室7に対面している。
FIG. 1 shows the wall 6 of the torus chamber when this embodiment is applied.
4 is a partially cutaway sectional view showing an enlarged horizontal cross section of , the right side of the figure facing the torus chamber 7 of FIG. 3. FIG.

第1図において、符号15は第3図の原子炉建屋マット
(I)1に植立されたH型鋼であり、鉄筋コンクリート
製の壁6に埋込まれる鉄筋16が植立されたプレキャス
トコンクリート板14が、隣接するH型鋼15の四部間
に挿入保持されている。符号17はその他の配筋を表す
。なおプレキャストコンクリート板14は鉄板等であっ
てもよい。
In FIG. 1, reference numeral 15 is an H-shaped steel installed in the reactor building mat (I) 1 shown in FIG. is inserted and held between the four adjacent H-shaped steel parts 15. Reference numeral 17 represents other reinforcements. Note that the precast concrete plate 14 may be an iron plate or the like.

本実施例においては、第2図に示す工程図のように、原
子炉建屋マット(I)1の打設の際、壁6の設定予定面
のトーラス室7側に沿って、定められた間隔を保ちなが
ら壁6の予定高さまでH型鋼15を立てこむ。次いでト
ーラス2のアンカーボルトおよび原子炉格納容器3のア
ンカーボルトの設定を行なう。
In this embodiment, as shown in the process diagram shown in FIG. The H-shaped steel 15 is built up to the planned height of the wall 6 while maintaining the height. Next, the anchor bolts of the torus 2 and the anchor bolts of the reactor containment vessel 3 are set.

次に原子炉建屋マット(■)4の工事開始と同時に、ト
ーラス室のul、6の施工を行なう、この際。
Next, at the same time as the construction of the reactor building mat (■) 4 started, the construction of the torus room ul, 6 was carried out.

原子炉建屋マット(I)1の打設時に立てておいたH型
鋼15にプレキャストコンクリート板14を挿入設定し
、トーラス室7の外側に足場を組立てて。
A precast concrete plate 14 is inserted into the H-shaped steel 15 that was erected when the reactor building mat (I) 1 was placed, and a scaffold is assembled outside the torus room 7.

鉄筋16と係合させた配筋17の作業等を行なった後。After working on the reinforcing bars 17 engaged with the reinforcing bars 16.

外側の型枠を設定しコンクリートを打設する。一方、原
子炉建屋マット(■)4の打設終了後、地下シールドウ
オール(I)5を施工する。この後、原子炉格納容器3
の組立てと、トーラス2の搬入・据付工事を並行して行
なう。次に、原子炉格納容器3の耐圧試験を実施し、終
了したならばDI子炉格納容器3の塗装を行なう。塗装
が完了したならば、原子炉格納容器3の下部空間にコン
クリート8を充填し、地下シールドウオール(■)9を
施工する。この後、1階の床1o、1階の壁11.1階
の地下シールドウオール12.2階の床13の順で順次
施工してゆく。
Set the outer formwork and pour concrete. On the other hand, after the reactor building mat (■) 4 has been placed, the underground shield wall (I) 5 is constructed. After this, reactor containment vessel 3
The assembly of the Torus 2 and the transport and installation of Torus 2 will be carried out in parallel. Next, a pressure test is carried out on the reactor containment vessel 3, and upon completion of the pressure test, the DI sub-reactor containment vessel 3 is painted. When the painting is completed, concrete 8 is filled in the lower space of the reactor containment vessel 3, and an underground shield wall (■) 9 is constructed. After this, construction will be carried out in order: floor 1o on the first floor, wall 11 on the first floor, underground shield wall 12 on the first floor, and floor 13 on the second floor.

本実施例によれば、壁6の施工中であっても、トーラス
室7の側に足場等の障害物がないので、トーラス2の搬
入・据付ができる。すなわち第4図に示す従来の工程と
比較しても明らがなように。
According to this embodiment, even when the wall 6 is being constructed, there are no obstacles such as scaffolding on the side of the torus room 7, so the torus 2 can be carried in and installed. That is, it is not obvious even when compared with the conventional process shown in FIG.

壁6の施工とは無関係に、原子炉格納容器3の組立と並
行して、トーラス2の搬入・据付が行なえるので、従来
原子炉格納容器3の組立が終了してもトーラス2の搬入
・据付が終了するまで、原子炉格納容器3の耐圧試験の
開始が遅延して生じた損失時間は消滅した。
Since the torus 2 can be carried in and installed in parallel with the assembly of the reactor containment vessel 3, regardless of the construction of the wall 6, the torus 2 can be carried in and installed even after the assembly of the reactor containment vessel 3 is completed. The time lost due to the delay in starting the pressure test of the reactor containment vessel 3 has disappeared until the installation is completed.

〔発明の効果〕〔Effect of the invention〕

本発明によれば、トーラス室の施工から原子炉格納容器
の耐圧試験までに到る作業工程が改善さることができる
According to the present invention, it is possible to improve the work process from constructing the torus chamber to pressure testing of the reactor containment vessel.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例が適用された一部を表す一部
切欠き断面図、第2図は本発明の一実施例を表す工程図
、第3図はトーラス型原子炉格納容器が収納された原子
炉建屋の要部を表す縦断面図、第4図は従来の工程図で
ある。 1・・・原子炉建屋マット 2・・・トーラス 3・・・原子炉格納容器 6・・・壁 14・・・プレキャストコンクリート板15・・・H型
鋼 16・・・鉄筋 代理人 弁理士  則 近 憲 佑 同           三ヨも  イ!i&   i
/、   f第1図 耐五!入験 第2図
Fig. 1 is a partially cutaway sectional view showing a part to which an embodiment of the present invention is applied, Fig. 2 is a process diagram showing an embodiment of the present invention, and Fig. 3 is a torus-type reactor containment vessel. FIG. 4 is a longitudinal sectional view showing the main parts of the reactor building in which the reactor building is housed, and is a conventional process diagram. 1...Reactor building mat 2...Torus 3...Reactor containment vessel 6...Wall 14...Precast concrete plate 15...H-shaped steel 16...Reinforcement agent Patent attorney Nori Chika Ken Yudo Sanyomo too! i&i
/, f Figure 1 Taigo! Entrance exam diagram 2

Claims (1)

【特許請求の範囲】 1、原子炉建屋マット上に設置される原子炉格納容器の
建設と、この原子炉格納容器の下部外周を包囲して前記
原子炉建屋マット上に設置され前記原子炉格納容器の圧
力抑制室を構成するトーラスの建設と、このトーラスの
外周に前記原子炉建屋マットから立上り設置される鉄筋
コンクリート製の壁の建設とを含む原子力発電所の建設
方法において、 建設されるべき前記壁の前記トーラスとの対向面に一致
する板状部材を前記原子炉建屋マット上に立設し、 前記板状部材を前記壁の前記トーラスとの対向面造成用
型枠兼前記壁の恒久構成要素として用いながら前記壁を
前記原子炉建屋マット上に立設開始し、 前記壁の設立完了を待つことなく部分形成された前記ト
ーラスを前記原子炉建屋マット上に搬入設置する原子力
発電所の建設方法。 2、前記板状部材に前記壁の鉄筋を付設させた特許請求
の範囲第1項記載の原子力発電所の建設方法。
[Scope of Claims] 1. Construction of a reactor containment vessel installed on the reactor building mat, and construction of the reactor containment vessel installed on the reactor building mat surrounding the lower outer periphery of the reactor containment vessel. In a method of constructing a nuclear power plant, the method includes constructing a torus constituting a pressure suppression chamber of a vessel, and constructing a reinforced concrete wall rising from the reactor building mat around the outer periphery of the torus, comprising: A plate-shaped member corresponding to a surface of the wall facing the torus is erected on the reactor building mat, and the plate-shaped member serves as a formwork for creating the surface of the wall facing the torus and as a permanent structure of the wall. Construction of a nuclear power plant, in which the wall is started to be erected on the reactor building mat while being used as an element, and the partially formed torus is carried and installed on the reactor building mat without waiting for the completion of the construction of the wall. Method. 2. The method for constructing a nuclear power plant according to claim 1, wherein reinforcing bars for the wall are attached to the plate member.
JP61076465A 1986-04-04 1986-04-04 Method of building nuclear power plant Granted JPS62233789A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61076465A JPS62233789A (en) 1986-04-04 1986-04-04 Method of building nuclear power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61076465A JPS62233789A (en) 1986-04-04 1986-04-04 Method of building nuclear power plant

Publications (2)

Publication Number Publication Date
JPS62233789A true JPS62233789A (en) 1987-10-14
JPH0471478B2 JPH0471478B2 (en) 1992-11-13

Family

ID=13605912

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61076465A Granted JPS62233789A (en) 1986-04-04 1986-04-04 Method of building nuclear power plant

Country Status (1)

Country Link
JP (1) JPS62233789A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014525033A (en) * 2011-07-02 2014-09-25 ルンプ,ビヨルン・ジイグート Safe reactor plant construction method and corresponding reactor plant

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57165792A (en) * 1981-04-07 1982-10-12 Tokyo Shibaura Electric Co Method of constructing nuclear reactor building
JPS57175290A (en) * 1981-04-21 1982-10-28 Tokyo Shibaura Electric Co Nuclear reactor building
JPS58118987A (en) * 1982-01-06 1983-07-15 株式会社日立製作所 Method of constructing building

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57165792A (en) * 1981-04-07 1982-10-12 Tokyo Shibaura Electric Co Method of constructing nuclear reactor building
JPS57175290A (en) * 1981-04-21 1982-10-28 Tokyo Shibaura Electric Co Nuclear reactor building
JPS58118987A (en) * 1982-01-06 1983-07-15 株式会社日立製作所 Method of constructing building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014525033A (en) * 2011-07-02 2014-09-25 ルンプ,ビヨルン・ジイグート Safe reactor plant construction method and corresponding reactor plant

Also Published As

Publication number Publication date
JPH0471478B2 (en) 1992-11-13

Similar Documents

Publication Publication Date Title
JP3946352B2 (en) Construction method of reactor containment vessel
JPS62233789A (en) Method of building nuclear power plant
JPS5829922A (en) Constructing method for underground outer wall
JP4352071B2 (en) Construction method of reactor containment vessel
JPS63274897A (en) Cask cleaning pit in common use as depot for head of nuclear reactor pressure vessel
JPH0953277A (en) Construction method for atomic power station
JPS63308B2 (en)
JP3110059B2 (en) Containment vessel construction method for nuclear power plants
JPS5926095A (en) Method of constructing reactor building
JP3273668B2 (en) How to construct a containment vessel
JPS62165185A (en) Method of constructing upper structure of container for nuclear reactor
JPS62157591A (en) Construction structure and method of container for nuclear reactor
JPS6367875B2 (en)
JPH10339791A (en) Partition wall structure in spent fuel storage pool and construction method for the partition wall
JPH0759813B2 (en) Underground construction method
JPS6324276B2 (en)
JPH0765313B2 (en) Underground construction method
JPS63312439A (en) Underground construction method
JPS63272690A (en) Construction of lining tank
JPS62159093A (en) Method of construction of housing for nuclear reactor
JPS6291895A (en) Method of constructing housing of nuclear reactor
JPS6331076B2 (en)
JPH0558112B2 (en)
JPH03237391A (en) Storage container constructing method for nuclear power plant
JPS6326211B2 (en)