JPS62111050A - Construction of slab - Google Patents
Construction of slabInfo
- Publication number
- JPS62111050A JPS62111050A JP24847185A JP24847185A JPS62111050A JP S62111050 A JPS62111050 A JP S62111050A JP 24847185 A JP24847185 A JP 24847185A JP 24847185 A JP24847185 A JP 24847185A JP S62111050 A JPS62111050 A JP S62111050A
- Authority
- JP
- Japan
- Prior art keywords
- slab
- assembly module
- floor assembly
- constructing
- opening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
r産業上の利用分野」
本発明は、スラブの構築方法に係わり、特に、スパンの
長いスラブを形成する際に用いて好適な構築方法に関す
るものである。DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a method of constructing a slab, and particularly to a method of constructing a slab suitable for use in forming a long span slab.
「従来の技術」
一般に、スラブを構築する場合、例えば上部に開口を有
する先行躯体上に、その開口を覆って型枠を組上げ、該
型枠内に鉄筋あるいはデツキプレート等を組み付けたの
らにコンクリートを打設する、いわゆるRC構造を用い
る方法が採用されている。``Prior Art'' Generally, when constructing a slab, for example, a formwork is assembled on a preceding frame having an opening at the top, covering the opening, and reinforcing bars, deck plates, etc. are assembled within the formwork. A method using so-called RC structure, in which concrete is poured, is adopted.
[発明が解決しようとする問題点]
本発明は、前)ホした従来の技術における次のような問
題点を解決せんとするものである。[Problems to be Solved by the Invention] The present invention aims to solve the following problems in the conventional technology mentioned above.
すなわら、前述したMI!築方決方法っては、RC構造
自体の強度に限度があるため、先行躯体の開口のスパン
の大型化すなわちスラブの大型化が制限されてしまうと
いった問題点である。そして、このような問題点は、ス
ラブの細分化を余儀なくするために、工期の短縮化を図
る上において障害の一つとなっている。In other words, the aforementioned MI! The problem with the construction method is that there is a limit to the strength of the RC structure itself, which limits the ability to increase the span of the opening in the preceding frame, that is, to increase the size of the slab. Such a problem is one of the obstacles to shortening the construction period because it necessitates subdividing the slab.
一方、このような問題点を解消するための一手段として
、先行一体の開口部に仮設鉄骨を掛は渡しておき、該仮
設鉄骨上に前記型枠を載置することにより、スラブの強
度を高めてその大型化を図ることが考えられている。On the other hand, as a means to solve such problems, a temporary steel frame is hung over the opening of the preceding integral part, and the formwork is placed on the temporary steel frame to increase the strength of the slab. It is being considered to increase the height and increase the size.
しかしながら、このような方法によっても、前述した先
行躯体の開口部のスパンの長尺化に伴い、多数の仮設鉄
骨を設置しなければならないこと、また、設計上RC構
造に仮設鉄骨を併設するもので、これらの取り合いが煩
雑化すること等から、有効な解決手段とはなり1qでい
ない。However, even with this method, a large number of temporary steel frames must be installed due to the longer span of the opening in the preceding structure, and it is also difficult to install temporary steel frames along with the RC structure due to the design. However, since these negotiations become complicated, 1q is not an effective solution.
さらに、前jホした構築方法であると、スラブを構築し
たのらに、該スラブの上下の付帯工事(特に、先行躯体
内の付帯工事)、例えば、配管工事やダクトあるいは諸
機器の設置工事等を別個に行なわなければならないから
、スラブの大型化を行なったとしても、工1!!1の大
幅な短縮にはつながらないといった問題点が残されてい
る。Furthermore, with the construction method mentioned above, after constructing the slab, incidental work above and below the slab (especially incidental work within the preceding structure), such as piping work, duct work, or installation work of various equipment, is carried out. etc. must be done separately, so even if the slab is made larger, it will only take 1 minute! ! The problem remains that it will not lead to a significant reduction in 1.
[問題点を解決するための手段」
本発明は、前述した従来の諸問題点を有効に解決し1q
るスラブの構築方法を提供せんとづ°るもので、複数の
鉄骨梁および鉄筋を枠組みしたのちに、これらを覆って
デツキプレートを取り付けることによりスラブ構成体を
形成し、該スラブ構成体の上部あるいは下部に配管等の
諸機器を取りイ」りて床組モジュールを形成し、該床組
モジュールを吊り上げて先行躯体の上部に載置してその
開口を閉塞したのちに、前記床組モジュールを覆ってコ
ンクリートを打設することを特徴とする。[Means for Solving the Problems] The present invention effectively solves the above-mentioned conventional problems and achieves 1q.
This method provides a method for constructing a slab, in which a plurality of steel beams and reinforcing bars are framed, a deck plate is attached over these to form a slab structure, and the upper part of the slab structure is Alternatively, a floor assembly module is formed by removing various equipment such as piping from the lower part, and the floor assembly module is lifted and placed on the upper part of the preceding structure to close the opening, and then the floor assembly module is removed. It is characterized by covering it and pouring concrete.
「作用」
本発明は、前述した構成とすることにより、スラブをS
RC構造として、その剛性を高めて大型化を可能にし、
また、スラブ構築後の現場にお(ブる諸作業を極力少な
くするとともに、スラブのコンクリート打設作業と先行
躯体内の作業との同時進行を可能にするものである。"Function" The present invention has the above-mentioned configuration, so that the slab can be
As an RC structure, its rigidity is increased and it can be made larger.
In addition, it minimizes the amount of work that must be done on-site after the slab is constructed, and allows concrete work for the slab to be carried out simultaneously with work inside the preceding structure.
「実施例」
以下、本発明を第1図〜第4図に示す好適な一実施例に
基づき詳細に説明する。"Embodiment" The present invention will be described in detail below based on a preferred embodiment shown in FIGS. 1 to 4.
まず、第1図に示すように、複数の鉄骨梁1や鉄筋2を
ほぼ格子状に枠組みしたのちに、これらの間に形成され
た空間部を波型鋼板からなるデツキプレート3によって
覆ってスラブ構成体4を形成する。First, as shown in Fig. 1, a plurality of steel beams 1 and reinforcing bars 2 are framed almost in a lattice shape, and then the spaces formed between them are covered with deck plates 3 made of corrugated steel plates to form a slab. A structure 4 is formed.
次いで、第2図に示すように、前記スラブ構成体4をク
レーンC等によって吊り上げたのちに、その上部および
下部あるいは上下に貫通させで、配管5やその他の諸機
器(例えば、ダクトや照明器具であってその何れも図示
略)をサポート6や吊り具(図示略)を介して一体に取
り付けて床組モジュール7を形成する。Next, as shown in FIG. 2, after the slab structure 4 is lifted by a crane C or the like, pipes 5 and other equipment (for example, ducts and lighting equipment) are inserted through the upper and lower parts or the upper and lower parts of the slab structure 4. (all of which are not shown) are integrally attached via supports 6 and hangers (not shown) to form a floor assembly module 7.
このようにして形成した床組モジュール7を、予め形成
された、上部に開口8aを有する先行躯体8の上方へ搬
送し、該床組モジュール7を先行躯体8の開口8aに位
置合わせしたのらに徐々に下降させて、ぞの下部に取り
付けられている配管5等を先行躯体8内へ挿入するとと
もに、第3図に示すように、スラブ構成体4の下部周縁
部を先行躯体8の上方周縁部上に載置する。The floor assembly module 7 thus formed is transported above the preceding body 8 which has been formed in advance and has an opening 8a in the upper part, and the floor assembly module 7 is aligned with the opening 8a of the preceding body 8. and insert the piping 5 etc. attached to the lower part of the slab structure into the preceding structure 8, and as shown in FIG. Place it on the periphery.
次いで、床組モジュール7を吊り上げているクレーンC
を取り外したのちに、第4図に示すJ:うに、前記床組
モジュール7を覆ってコンクリート9を打設することに
より、床組モジュール7を先行躯体8へ一体化する。Next, crane C is lifting the floor assembly module 7.
After removing the floor assembly module 7, the floor assembly module 7 is integrated with the preceding frame 8 by pouring concrete 9 to cover the floor assembly module 7 as shown in FIG.
しかるのらに、床組モジュール7の上部および下部の仕
上げ作業を行なってスラブの構築を完了する。Thereafter, finishing work is carried out on the upper and lower parts of the floor assembly module 7 to complete the construction of the slab.
しかして、このような方法によってスラブを構築すると
、スラブの主たる強度部材をyN骨梁1や鉄筋2とによ
って構成しであるので、その強度を十分に高めて大スパ
ンの先行躯体8への適用範囲を大幅に拡大することがで
きる。一方、スラブ構成体4に予め配管5等の諸機器等
を設置しであること、また、床組モジュール7を先行躯
体8に設置したのらにあっては、εの上部へのコンクリ
ート打設作業と先行躯体8内の諸作業とを同時に進行さ
せることができることから工期を著しく短縮することが
できる。However, when constructing a slab using such a method, the main strength members of the slab are composed of the yN trabecular beams 1 and the reinforcing bars 2, so the strength can be sufficiently increased to apply it to the large-span preceding frame 8. The range can be expanded significantly. On the other hand, if various equipment such as piping 5 is installed in the slab structure 4 in advance, and if the floor assembly module 7 is installed in the preceding frame 8, it is necessary to place concrete on the upper part of ε. Since the work and various works in the preceding frame 8 can be carried out simultaneously, the construction period can be significantly shortened.
なお、前記実施例において示した工程は一例を示1もの
であって、他の工程を追加したりすることもできるもの
である。また、各構成部材の諸形状や寸法等は一例であ
って設計要求等に基づき種々変更可能である。Note that the steps shown in the above embodiments are just one example, and other steps may be added. Further, the shapes and dimensions of each component are merely examples, and can be changed in various ways based on design requirements and the like.
「発明の効果J
以上説明したように、本発明に係わるスラブの構築方法
によれば、構築すべきスラブの主たる強1衰部材である
スラブ構成体を鉄骨梁と鉄筋とによって構成したから、
その剛性を高めて先行躯体の大スパン化への適用範囲を
大幅に拡大することができる。また、該スラブ構成体に
配管等の諸機器を取り付けて形成した床組モジュールを
先行躯体へ載置したのちに、該床組モジュールを覆って
コンクリートを打設してスラブを構築するものであるか
ら、コンクリート打設作業と先行躯体内の諸作業とを同
時に進行させることができ、もって、スラブ構築のため
の工期を著しく短縮することができる等温れた効果を奏
する。"Effects of the Invention J As explained above, according to the method for constructing a slab according to the present invention, since the slab structure, which is the main strength-decay member of the slab to be constructed, is composed of steel beams and reinforcing bars,
By increasing its rigidity, it is possible to greatly expand the scope of application to larger spans of preceding structures. Furthermore, after a floor assembly module formed by attaching piping and other equipment to the slab structure is placed on the preceding frame, concrete is poured to cover the floor assembly module to construct a slab. Therefore, the concrete pouring work and the various works inside the preceding structure can proceed at the same time, thereby producing an isothermal effect that can significantly shorten the construction period for slab construction.
図面は本発明の一実施例を示すもので、第1図はスラブ
構成体を形成した状態を示す縦断面図、第2図は床組モ
ジュールを形成した状態を示す縦断面図、第3図は床組
モジュールを先行側体へ載置した状態を示す縦断面図、
第4図は床組モジュールを覆ってコンクリートを打設し
た状態を示す縦断面図である。
1・・・・・・鉄骨梁、 2・・・・・・鉄筋
、3・・・・・・デツキプレート、 4・・・・・・ス
ラブ構成体5・・・・・・配管、 6・・・
・・・サポート、7・・・・・・床組モジュール、 8
・・・・・・先行躯体、8a・・・・・・開口部、
9・・・・・・コンクリート。The drawings show one embodiment of the present invention, and FIG. 1 is a longitudinal cross-sectional view showing a state in which a slab structure is formed, FIG. 2 is a longitudinal cross-sectional view showing a state in which a floor assembly module is formed, and FIG. is a longitudinal sectional view showing the floor assembly module placed on the leading side body;
FIG. 4 is a longitudinal cross-sectional view showing a state in which concrete has been poured to cover the floor assembly module. 1... Steel beam, 2... Rebar, 3... Deck plate, 4... Slab structure 5... Piping, 6.・・・
...Support, 7...Floor assembly module, 8
・・・・・・Advanced frame, 8a・・・Opening,
9... Concrete.
Claims (1)
築方法であって、複数の鉄骨梁および鉄筋を枠組みした
のちに、これらを覆ってデッキプレートを取り付けるこ
とによりスラブ構成体を形成し、該スラブ構成体の上部
あるいは下部に配管等の諸機器を取り付けて床組モジュ
ールを形成し、該床組モジュールを吊り上げて先行躯体
の上部に載置してその開口を閉塞したのちに、前記床組
モジュールを覆ってコンクリートを打設することを特徴
とするスラブの構築方法。 2)前記配管等の諸機器は、スラブ構成体を上下に貫通
して設けられていることを特徴とする特許請求の範囲第
1項記載のスラブの構築方法。[Claims] 1) A method for constructing a slab provided to cover the upper opening of a preceding building frame, in which a plurality of steel beams and reinforcing bars are framed, and then a deck plate is attached to cover these to construct the slab. A floor assembly module was formed by attaching piping and other equipment to the upper or lower part of the slab structure, and the floor assembly module was lifted and placed on top of the preceding framework to close the opening. A method for constructing a slab, the method comprising subsequently pouring concrete to cover the floor assembly module. 2) The method of constructing a slab according to claim 1, wherein the various equipment such as the piping are provided vertically penetrating the slab structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24847185A JPS62111050A (en) | 1985-11-06 | 1985-11-06 | Construction of slab |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24847185A JPS62111050A (en) | 1985-11-06 | 1985-11-06 | Construction of slab |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS62111050A true JPS62111050A (en) | 1987-05-22 |
Family
ID=17178638
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP24847185A Pending JPS62111050A (en) | 1985-11-06 | 1985-11-06 | Construction of slab |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS62111050A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62273347A (en) * | 1986-05-22 | 1987-11-27 | 株式会社東芝 | Construction of building of atomic power plant |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57127049A (en) * | 1981-01-27 | 1982-08-07 | Kajima Corp | Post-striking non-support slab structure |
JPS5949999A (en) * | 1982-09-16 | 1984-03-22 | ウア−コ・インコ−ポレ−テツド | Continuous office paper for automatic mail |
-
1985
- 1985-11-06 JP JP24847185A patent/JPS62111050A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57127049A (en) * | 1981-01-27 | 1982-08-07 | Kajima Corp | Post-striking non-support slab structure |
JPS5949999A (en) * | 1982-09-16 | 1984-03-22 | ウア−コ・インコ−ポレ−テツド | Continuous office paper for automatic mail |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62273347A (en) * | 1986-05-22 | 1987-11-27 | 株式会社東芝 | Construction of building of atomic power plant |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7219474B2 (en) | Load bearing building panel | |
JP2001164757A (en) | Work method for building | |
JPS62111050A (en) | Construction of slab | |
JP3128627B2 (en) | Hollow PCa pillar | |
JPS62141242A (en) | Construction of concrete floor panel | |
JPH0657710A (en) | Construction of concrete main tower | |
JPH0334967Y2 (en) | ||
JPS6268946A (en) | Beam construction method | |
JP4445366B2 (en) | Reinforcement method for tower crane mount | |
JP2928002B2 (en) | Column formwork structure | |
JP2888913B2 (en) | External wall panel mounting method | |
JPH0642184A (en) | Construction of skeleton using half precast floor board | |
JP2518568Y2 (en) | Connection structure of steel beams to concrete columns | |
JPH01121425A (en) | Post and beam joint structure of multistoried building | |
JP2005171548A (en) | Reinforcing structure and reinforcing method for flat plate frame | |
JPS6033959A (en) | Reinforcing struc ture of room unit by wall type construction method | |
JPH09256457A (en) | Building assembly method | |
JPS6360326A (en) | Construction of underground beam | |
JPS62170640A (en) | Outer wall structure of building | |
JPS634146A (en) | Slab execution method | |
JPS63261037A (en) | Execution of waffle slab and lower constitution body of waffle slab | |
JPH042147B2 (en) | ||
JPS62233358A (en) | Construction of concrete floor panel | |
JPS61246470A (en) | Building method | |
JPH0417262B2 (en) |