JPS6192214A - Method of pulling out pile - Google Patents

Method of pulling out pile

Info

Publication number
JPS6192214A
JPS6192214A JP21168084A JP21168084A JPS6192214A JP S6192214 A JPS6192214 A JP S6192214A JP 21168084 A JP21168084 A JP 21168084A JP 21168084 A JP21168084 A JP 21168084A JP S6192214 A JPS6192214 A JP S6192214A
Authority
JP
Japan
Prior art keywords
pile
auger
casing
casing auger
earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP21168084A
Other languages
Japanese (ja)
Inventor
Kaname Nakayama
要 仲山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanwa Kizai Co Ltd
Original Assignee
Sanwa Kizai Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanwa Kizai Co Ltd filed Critical Sanwa Kizai Co Ltd
Priority to JP21168084A priority Critical patent/JPS6192214A/en
Publication of JPS6192214A publication Critical patent/JPS6192214A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/02Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To easily pull out a pile, by a method wherein, after a pile is edge-cut through excavation of a casing auger having a screw blade, the pile is pulled off together with the auger through reversing of the auger as refiling with soil is effected from the outer side of the auger. CONSTITUTION:With a casing auger 3 being rotated, the auger is lowered by excavation to a level lower than that of the lower end of a pile 2. A wire rope 16 is connected to the pile 2, and the rope 16 is secured to a wire securing tool 13 of the auger 3. With the rotation of the auger 3 being reversed, earth 18, discharged resulting from edge cutting excavation, is guided to the interior of the auger 3 from the outside of the auger 3, and the earth 18 in the hole 17 is consolidated to be raised. Further, when the auger 3 is raised by reversing, the pile 2 connected to the rope 16 is raised together with the auger and pulled out from a ground.

Description

【発明の詳細な説明】 (産業上の利用分野) 、 本発明は基礎杭の引抜き工法にかかり、特にスクリ
ューケーシングを用いた引抜き工法に関する。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a drawing method for foundation piles, and particularly to a drawing method using a screw casing.

〔従来技術とその問題点〕[Prior art and its problems]

一般に建築構造物は、地上の建物と地中の基礎とより構
成され、特に大型の構造物においては、構造物を安定さ
ぜるため、基礎の下にさらに柱状の基礎杭を埋設するこ
とが従来より行なわれている。    □ したがって古くなった建築構造物の解体後の土地に新し
い構造物を建てる場合には、上記のような基礎杭の引抜
きは必須の基礎工事の工程となっている。
Architectural structures generally consist of an above-ground building and an underground foundation, and in particularly large structures, column-shaped foundation piles may be buried beneath the foundation to stabilize the structure. This has been done traditionally. □ Therefore, when building a new structure on land after demolishing an old building structure, pulling out the foundation piles as described above is an essential foundation work process.

しかして従来行なわれている基礎杭の引の抜き工法は、
杭の外周に管状のケーシングを打込み、杭周器の地盤と
の縁切りを行ない、そののち杭を引扱くか、あるいはケ
ーシングと共に杭を引抜くという工法が用いられている
However, the conventional method of pulling out foundation piles,
The construction method used is to drive a tubular casing around the outer circumference of the pile, cut the edge of the pile fence from the ground, and then either handle the pile or pull it out together with the casing.

しかしな”みら杭のみを引抜く工法の場合には、ケーシ
ングと杭との間の土を除去する必要があり、またケーシ
ングと共に杭を引抜く工法の場合には、ケーシングの引
抜き後にケーシングから杭を抜き出す工程が必要となり
、前者後者とも工程に多くの時間と労ノjを必要とする
ものであった。
However, in the case of the method of pulling out only the Mira pile, it is necessary to remove the soil between the casing and the pile, and in the case of the method of pulling out the pile together with the casing, it is necessary to remove the soil from the casing after pulling out the casing. A process for extracting the piles was required, and both the former and the latter processes required a lot of time and labor.

また老化した杭は折れ易く、このため抗引抜き工程にお
いて、杭の下端部が地中に取り残されるという問題があ
り、さらに上記の工法によると、杭引抜き後の孔を埋め
る処理をしなければならず、単に土砂を埋めるだけでは
土が圧密されず、地盤沈下や地盤強度が下がるとすうお
それがあった。
In addition, aged piles are prone to breakage, so there is a problem that the lower end of the pile is left underground during the anti-pulling process.Furthermore, according to the above construction method, it is necessary to fill in the holes after the pile is pulled out. First, simply filling in earth and sand would not consolidate the soil, which could lead to ground subsidence and a decrease in ground strength.

〔発明の目的〕[Purpose of the invention]

本発明はこれに鑑み、スクリュー羽根のついたケーシン
グオーガを使用してオーガの掘進により杭を縁切りした
のち、オーガを逆回転させて杭下部の土圧をあげて杭を
押しあげるようにすることにより、従来の工法よりも工
程が簡単で、杭引抜き作業に時間を要せず、また杭を折
損させることがなく確実に引抜き作業ができ、しかも杭
引抜き作業と同時に孔の埋め戻し処理を行なうようにし
だ杭引抜き工法を提供することを目的としてなされたも
のである。
In view of this, the present invention uses a casing auger with screw blades to cut the edge of a pile by digging the auger, and then rotates the auger in the opposite direction to increase the earth pressure at the bottom of the pile and push the pile up. As a result, the process is simpler than the conventional construction method, it does not take much time to pull out the piles, it can be pulled out reliably without damaging the piles, and the holes can be backfilled at the same time as the piles are pulled out. This was done for the purpose of providing a method for pulling out piles.

〔発明の概要〕[Summary of the invention]

上記目的を達成するため、本発明においては、中空体の
周囲にスクリュー羽根を設けた、ケーシングオーガによ
り、杭とその周辺の地盤を、この抗の全長に亘って縁切
り掘りしたのち、前記杭にワイヤロープを連繋し、この
ワイヤロープを前記ケーシングオーガ上方のワイヤ固定
具により固定し、つぎに前記ケーシングオーガを逆転さ
せて前記縁切り掘りにより排出された土砂をケーシング
オーガの外側より埋め戻しながら、ケーシングオーガと
ともに前記杭を抜くようにした工法に特徴を有するもの
である。
In order to achieve the above object, the present invention uses a casing auger provided with screw blades around the hollow body to edge-cut the pile and the ground around it over the entire length of the pile, and then The wire ropes are connected and fixed by a wire fixture above the casing auger, and then the casing auger is reversed and the earth and sand discharged by the edge cutting is backfilled from the outside of the casing auger. This construction method is characterized by the fact that the piles are pulled out together with the auger.

〔発明の実施例〕[Embodiments of the invention]

以下、本発明を第1図乃至第5図に示す実施例により説
明する。
The present invention will be explained below with reference to embodiments shown in FIGS. 1 to 5.

まず、第1図(a)に示すように地!81に基礎杭とし
て打込まれている既存の杭2の頭部を掘り出し、杭2(
¥よりも大きい内径のケーシングオーガ3を穿孔機に取
付けて杭2の周囲の地?A1.を掘削する。
First, as shown in Figure 1 (a), the ground! Dig out the head of the existing pile 2 that has been driven into 81 as a foundation pile, and install the pile 2 (
Attach a casing auger 3 with an inner diameter larger than ¥ to the drilling machine and dig into the ground around the pile 2? A1. excavate.

ここで穿孔機は第2図に示すよ5うにタワー4をもつ作
業機械5であって、この、タワー4の上部にはトップシ
ーブ6が設けられている。ワイヤ7は前記作業機械5側
の巻上機に一端を固定され、他端は前記トップシーブ6
を介して駆動部8に連結されている。この駆動部8はモ
ー、夕および、減速機などよりなり、下部に設けられた
前記ケーシングオーガ3とは連結具9を介して連結され
ている。
Here, the drilling machine is a working machine 5 having a tower 4 as shown in FIG. 2, and a top sheave 6 is provided at the top of the tower 4. The wire 7 has one end fixed to the hoisting machine on the work machine 5 side, and the other end fixed to the top sheave 6.
It is connected to the drive unit 8 via. This drive section 8 is made up of a motor, a motor, a speed reducer, etc., and is connected to the casing auger 3 provided at the bottom via a connector 9.

第3図はケーシングオーガ3および駆動部8のみを略図
で示したもので、ケーシングオーガ3は所定の長さを有
し外周にはスクリュー羽根10が全長に亘って螺設され
ており、駆動部8であるモータに直結して設けられたギ
ヤ11と、前記ケーシングオーガ3上部の外周に設けら
れたギヤ、12とが噛み1合うことにより正転および逆
転されるようになっている。
FIG. 3 schematically shows only the casing auger 3 and the drive section 8. The casing auger 3 has a predetermined length, and a screw blade 10 is screwed over the entire length on the outer periphery. A gear 11 provided directly connected to the motor 8 and a gear 12 provided on the outer periphery of the upper part of the casing auger 3 mesh with each other to cause forward and reverse rotation.

またワイヤ固定具13は前記駆動部8と同様、ケーシン
グオーガ3の上部に設けられている。
Further, the wire fixture 13 is provided on the upper part of the casing auger 3, similarly to the drive section 8.

さらに、前記ケーシングオーガ3の下端近傍には内側に
も外側の羽根と同じ方向で適宜長さのス・クリユー羽根
14が設けられている。
Further, near the lower end of the casing auger 3, screw blades 14 of an appropriate length are provided on the inner side in the same direction as the outer blades.

ここで15は前記ワイヤ固定具13とケーシングオーガ
3との間の軸受である。
Here, 15 is a bearing between the wire fixture 13 and the casing auger 3.

しかして第1図(a)に示すようにケーシングオーガ3
を回転により掘進させ、杭2の下端よりもある程度深い
位置にオーガ3の先端が下降したときに掘進を止5める
However, as shown in FIG. 1(a), the casing auger 3
The excavation is stopped when the tip of the auger 3 descends to a position somewhat deeper than the lower end of the pile 2.

つぎに第1図(b)に示すように杭2にワイヤロープ1
6を連繋し、そのワイヤローフ16を前記ワイヤ固定具
13に固定する。
Next, wire rope 1 is attached to stake 2 as shown in Figure 1(b).
6 and the wire loaf 16 is fixed to the wire fixture 13.

このときワイヤ口で716の連繋手段は、縁切り掘り後
にワイヤ0−116を棒などにより押し込むか、あるい
はり、ブヤロープ16を予めケーシングす一ガ3内に設
置しておくなど何れの方法りもよい。
At this time, the means for connecting 716 at the wire port may be any method, such as pushing the wires 0-116 with a stick or the like after cutting the edge, or installing the rope 16 in advance in the casing gear 3. .

またワイヤロー116の他端は随時回転を止めることの
できるシーブ等に通すなどして固定J゛る。
The other end of the wire row 116 is fixed by passing it through a sheave or the like that can stop the rotation at any time.

このように杭2をワイヤロー116に連繋させたのら、
第1図(C)に示すようにケーシングオーガ3を逆回転
させると、縁切り掘りにより排出された土砂はケーシン
グオーガ3の外側よりオーガ3内の孔17に導かれて孔
17内の土砂が圧密されて上昇する。
After connecting the stake 2 to the wire row 116 in this way,
When the casing auger 3 is rotated in the opposite direction as shown in FIG. 1 (C), the earth and sand discharged by edge cutting is guided from the outside of the casing auger 3 to the hole 17 in the auger 3, and the earth and sand in the hole 17 is consolidated. be and rise.

ケーシングオーガ3が逆回転により上昇すると、前記ワ
イヤロープ16で連繋された杭2もともに上昇し、地中
から抜けてゆく。
When the casing auger 3 rises due to reverse rotation, the piles 2 connected by the wire rope 16 also rise together and come out of the ground.

この際孔17内の土砂は、前記杭2の下端により圧力を
加えられながら圧密されて徐々に上昇する。
At this time, the earth and sand in the hole 17 is consolidated while being pressurized by the lower end of the pile 2, and gradually rises.

この場合にケーシングオーガ3の外側がらオーガ3内の
孔17に埋め戻す土砂を貧配合のモルタルにして地盤を
強化することもできる。
In this case, it is also possible to strengthen the ground by using soil from the outside of the casing auger 3 to backfill the holes 17 in the auger 3 with mortar with a poor mix.

杭2の用法き後は、ワイヤ固定具13を外し、ケーシン
グオーガ3内がら杭2を取り出すことにより杭用I友き
作業は終了し、第1図(d)に示すようにオーガ3によ
り作られた前記孔17は土砂18により埋めつくされる
After using the pile 2, remove the wire fixture 13 and take out the pile 2 from the inside of the casing auger 3 to complete the pile cutting work, and then use the auger 3 to remove the pile 2 as shown in Figure 1(d). The hole 17 thus formed is completely filled with earth and sand 18.

第5図は他の実施例であって、第1図(a)と異なると
ころは、杭2にワイヤローフ16を連繋して、ケーシン
グオーガ3の作業機械とは別の作業機すなわち、クレー
ン19などで吊下げて徐々に引上げる場合を示ず。
FIG. 5 shows another embodiment, and the difference from FIG. 1(a) is that a wire loaf 16 is connected to the pile 2, and a working machine other than the working machine of the casing auger 3, such as a crane 19, etc. It does not show the case where it is suspended and gradually pulled up.

この場合も上記と全く同じように、まず、ケーシングオ
ーガ3で杭2下端より深く掘削して杭2の側面を縁切り
したのち、ケーシングオーガ3を逆回転して杭2を上昇
させることにより抗2下端を完全に縁切りさせる。
In this case as well, in exactly the same way as above, first, the casing auger 3 is used to excavate deeper than the bottom end of the pile 2 and the side of the pile 2 is edged, and then the casing auger 3 is rotated in the opposite direction to raise the pile 2. Trim the bottom edge completely.

つぎに、杭2にワイヤロープ16を連繋してクレーン1
9に固定し、クレーン19により引き抜く。このとき杭
2を保持しているクレーン19の上昇の駆動源と、ケー
シングオーガ3の上昇の駆動源とは別になっているので
、ケーシングオーガ3の上昇速度を杭2の上昇速度より
も早くすると、ケーシングオーガ3内のスクリュー羽根
14により、オーガ3内の孔17に戻された土砂は杭2
の先端に押しつけられて上昇するのが遅くなり、したが
って土砂は杭2の先端を押し上げるように作用するので
、それだけ圧密されることになる。
Next, the wire rope 16 is connected to the pile 2 and the crane 1
9 and pulled out by crane 19. At this time, the driving source for lifting the crane 19 holding the pile 2 and the driving source for lifting the casing auger 3 are separate, so if the lifting speed of the casing auger 3 is faster than the lifting speed of the pile 2. The earth and sand returned to the hole 17 in the auger 3 by the screw blade 14 in the casing auger 3 is returned to the pile 2.
The soil is pressed against the tip of the pile 2, slowing its rise, and the soil acts to push up the tip of the pile 2, resulting in more compaction.

そして、前記と同様に排出された土砂を孔17゜内に戻
しながらケーシングオーガ3の逆転、により孔17内に
土砂を圧密しケーシングオーガ3を抜くのである。この
場合、クレーンにより杭を先に用法いてしまう手順によ
ってもよい。
Then, while returning the discharged earth and sand to the hole 17° in the same manner as described above, the casing auger 3 is reversed to compact the earth and sand in the hole 17, and the casing auger 3 is removed. In this case, the pile may be used first using a crane.

なお、本発明による杭用法キ工法に使用するケーシング
オーガ3は、ケーシングの外周にスクリュー羽根10の
ついているものであればよく、例えば第3図に示すよう
にケーシングオーガ3の内側に前記のスクリュー羽根1
4のついたもの、あるいは第4図に示すようにケーシン
グオーガ3先端の掘削刃20とスクリュー羽根21が内
側に向いているものであれば、より圧密効果を高めるこ
とができるとともに、内側のスクリュー羽根は正回転す
なわち掘進の場合に杭に上界力を与え、その反力どして
ケーシングオーガの推進力が得られるようになる。  
  ・ 〔発明の効果〕 以上説明したように本発明による杭用法き工法で使用す
るケーシングオーガは正転すれば掘進、逆転で土砂をケ
ーシングオーガ下方に送り、ケーシングオーガ内の孔の
土砂を圧密し、その流動性をもつ土砂を高圧状態にして
杭に上昇力を与える作用をもたせるようにしたから、杭
が最下端より押し上げられるので長い杭でも楽に扱くこ
とができ、折損の危険がなく、杭引抜き後の孔には土砂
、貧配合のモルタル等が填圧されるので地盤強度が低下
せず、また杭引抜き作業と孔埋め処理とが同時に行なわ
れるので作業が簡単になり、作業時間が短縮されるなど
数々の効果を有する。
The casing auger 3 used in the pile method according to the present invention may have screw blades 10 on the outer periphery of the casing. For example, as shown in FIG. Feather 1
4 or in which the excavating blade 20 and screw blade 21 at the tip of the casing auger 3 face inward as shown in Fig. 4, the consolidation effect can be further enhanced, and the inner screw The blades apply an upper limit force to the pile when rotating in the forward direction, that is, when digging, and the reaction force is used to generate the driving force for the casing auger.
- [Effect of the invention] As explained above, the casing auger used in the pile method according to the present invention excavates when it rotates in the forward direction, and sends earth and sand below the casing auger when it rotates in the reverse direction, compacting the earth and sand in the hole in the casing auger. The fluidity of the earth and sand is brought to a high pressure state to give the pile an upward force, so the pile is pushed up from the lowest end, so even long piles can be handled easily, and there is no risk of breakage. After the pile is pulled out, the hole is filled with earth and sand, poorly mixed mortar, etc., so the strength of the ground does not decrease.In addition, the pile pulling and hole filling are done at the same time, making the work easier and reducing the work time. It has many effects such as being shortened.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明にがかる杭用法き工法の作業工程を示し
、(a)は縁切り掘り作業中の断面図、(b)は杭とワ
イヤ固定具にワイヤロープを連繋中の断面図、(C)は
杭とケーシングオーガとを同時に引上げ中の断面図、(
d)は杭引汰き作業後の地盤断面図、第2図は穿孔別の
外観側面図、第3図は本発明工法に使用されるスクリュ
ーオーガ部分の拡大図、第4図はスクリューオーガの他
の実施例で、(a)、(b)は切断面の異なる断面図、
(C)は平面図、第5図は本発明工法の他の実施例の断
面図である。 1・・・地盤、2・・・杭、3・・・ケーシングオーガ
、10・・・スクリュー羽根、13・・・ワイヤ固定具
、16・・・ワイヤロープ、19・・・クレーン。 出願人代理人  猪  股     清b 1 し くG)             (b)(c)   
        (d) 琵 3 圀 54 図 (0)              (b)(C)
Figure 1 shows the working process of the pile method according to the present invention, (a) is a cross-sectional view during edge cutting and digging work, (b) is a cross-sectional view while connecting the wire rope to the pile and wire fixture, ( C) is a cross-sectional view of the pile and casing auger being pulled up simultaneously;
d) is a cross-sectional view of the ground after pile removal work, Figure 2 is an external side view of each hole, Figure 3 is an enlarged view of the screw auger used in the method of the present invention, and Figure 4 is a diagram of the screw auger. In other embodiments, (a) and (b) are different cross-sectional views of the cut plane,
(C) is a plan view, and FIG. 5 is a sectional view of another embodiment of the construction method of the present invention. DESCRIPTION OF SYMBOLS 1... Ground, 2... Pile, 3... Casing auger, 10... Screw blade, 13... Wire fixture, 16... Wire rope, 19... Crane. Applicant's agent Kiyoshi Inomata b 1 Shiku G) (b) (c)
(d) Bi 3 Koku 54 Figure (0) (b) (C)

Claims (1)

【特許請求の範囲】 1、中空体の周囲にスクリュー羽根を設けたケーシング
オーガにより、杭とその周辺の地盤を、この杭の全長以
上に亘って縁切り掘りしたのち、前記杭にワイヤロープ
を連繋し、このワイヤロープを前記ケーシングオーガ上
方のワイヤ固定具により固定し、つぎに前記ケーシング
オーガを逆転させて前記縁切り掘りにより排出された土
砂をケーシングオーガの外側より埋め戻しながら、ケー
シングオーガとともに前記杭を抜くようにしたことを特
徴とする杭引抜き工法。 2、杭の縁切り掘り完了後の引抜き作業において、前記
杭をケーシングオーガとは別に設けた作業機で吊上げ、
前記縁切り掘りにより排出された土砂を、前記ケーシン
グオーガの逆転で孔内に導入して圧密させながら埋め戻
すようにしたことを特徴とする特許請求の範囲第1項記
載の杭引抜き工法。
[Claims] 1. After the pile and the ground around it are edge-trimmed over the entire length of the pile using a casing auger provided with screw blades around the hollow body, a wire rope is connected to the pile. Then, this wire rope is fixed by a wire fixing device above the casing auger, and then the casing auger is reversed and the earth and sand discharged by the edge cutting is backfilled from the outside of the casing auger, and the pile is fixed together with the casing auger. A pile extraction method characterized by the fact that the piles are pulled out. 2. In the pulling operation after completing the edge cutting of the pile, the pile is lifted with a work machine provided separately from the casing auger,
2. The pile extraction method according to claim 1, wherein the earth and sand discharged by the edge cutting is introduced into the hole by reversing the casing auger and is backfilled while being compacted.
JP21168084A 1984-10-09 1984-10-09 Method of pulling out pile Pending JPS6192214A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21168084A JPS6192214A (en) 1984-10-09 1984-10-09 Method of pulling out pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21168084A JPS6192214A (en) 1984-10-09 1984-10-09 Method of pulling out pile

Publications (1)

Publication Number Publication Date
JPS6192214A true JPS6192214A (en) 1986-05-10

Family

ID=16609809

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21168084A Pending JPS6192214A (en) 1984-10-09 1984-10-09 Method of pulling out pile

Country Status (1)

Country Link
JP (1) JPS6192214A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01318615A (en) * 1988-06-16 1989-12-25 Takeshi Koshizuka Method of construction for after treatment temporary work using steel sheet pile
JPH05140934A (en) * 1991-11-21 1993-06-08 Fusao Sakano Existing pipe removing method with heavy machine such as auger machine
NL9201967A (en) * 1992-11-10 1994-06-01 Martens En Van Oord B V Method and device for removing objects from the ground
JP2007138544A (en) * 2005-11-18 2007-06-07 Marui Kiso:Kk Method of pulling out existing pile

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4893106A (en) * 1972-03-10 1973-12-03
JPS5393607A (en) * 1977-01-27 1978-08-16 Shimizu Construction Co Ltd Method of drawing pile out

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4893106A (en) * 1972-03-10 1973-12-03
JPS5393607A (en) * 1977-01-27 1978-08-16 Shimizu Construction Co Ltd Method of drawing pile out

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01318615A (en) * 1988-06-16 1989-12-25 Takeshi Koshizuka Method of construction for after treatment temporary work using steel sheet pile
JPH05140934A (en) * 1991-11-21 1993-06-08 Fusao Sakano Existing pipe removing method with heavy machine such as auger machine
NL9201967A (en) * 1992-11-10 1994-06-01 Martens En Van Oord B V Method and device for removing objects from the ground
JP2007138544A (en) * 2005-11-18 2007-06-07 Marui Kiso:Kk Method of pulling out existing pile

Similar Documents

Publication Publication Date Title
CN206801460U (en) A kind of rectangle friction pile drilling construction device
RO134509A1 (en) Process and device for on-spot making a pile of variable diameter, decreasing in depth
CN108643193A (en) A kind of pattern foundation pit supporting structure prestress anchorage cable Drilling draw out method
CN209958343U (en) Connecting joint for connecting reinforced concrete cast-in-place piles
CN102839915A (en) Hydraulic high frequency rotary vibration construction device applicable to dry pneumatic rock drilling pile machine
CN115478543B (en) Artificial hole digging pile foundation pit supporting structure and construction method
JPS6192214A (en) Method of pulling out pile
CN101338560A (en) Construction method for reinforced concrete pile
US6168350B1 (en) Method and apparatus for forming enlarged pile heads
CN105421398A (en) Trapezoidal inserting device for cross pile and rectangular pile
JP4074198B2 (en) How to remove existing piles
JP4400700B2 (en) Cutting and drawing method and equipment for existing piles
CN203334953U (en) Long rod type hole leading pile machine
GB2270329A (en) Forming a hole in the ground
CN218175956U (en) Trench digging device
JPH05287736A (en) Construction method for high strength cast-in-place concrete pile
JP3896003B2 (en) Connection method and structure of shaft
JPH0699900B2 (en) Ground consolidation method and ground consolidation apparatus used for the method
CN105569012A (en) Trapezoidal splicing equipment for X-shaped piles and rectangular piles
US1593445A (en) Method of installing mushroom piling
JP4057764B2 (en) Cutting device for existing structures
JPH08177365A (en) Soil improvement work for construction and earth auger device therefor
JPH0558085B2 (en)
GB2363152A (en) Method and apparatus for forming enlarged pile heads
JPH0643695B2 (en) Foundation pile construction method