JPS6187015A - Method of building steel pipe sheet pile underground outer wall - Google Patents

Method of building steel pipe sheet pile underground outer wall

Info

Publication number
JPS6187015A
JPS6187015A JP59207653A JP20765384A JPS6187015A JP S6187015 A JPS6187015 A JP S6187015A JP 59207653 A JP59207653 A JP 59207653A JP 20765384 A JP20765384 A JP 20765384A JP S6187015 A JPS6187015 A JP S6187015A
Authority
JP
Japan
Prior art keywords
steel pipe
pipe sheet
sheet pile
underground
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP59207653A
Other languages
Japanese (ja)
Other versions
JPH025203B2 (en
Inventor
Yuko Ikuta
幾田 悠康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP59207653A priority Critical patent/JPS6187015A/en
Publication of JPS6187015A publication Critical patent/JPS6187015A/en
Publication of JPH025203B2 publication Critical patent/JPH025203B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To improve economical efficiency, by a method wherein, after excava tion for a landslide protection wall by means of steel pipe sheet piles is carried out, the sheet piles are welded to each other to arranged steels and reinforce ment to the inner side of the landslide protection wall, and concrete is placed in a given thickness in the inner side of the landslide protection wall. CONSTITUTION:A ground is excavated at the inside of steel pipe sheet piles 3, and after underground water is pumped up, and a connection between a C-shaped pipe 1 and a T-shaped rail 2 is joined in a direction, extending from a pit excavation bottom toward the upper part, by welding. A doweled stud 4 is welded to the inside of a landslide protection wall employing a sheet piles 3, and after longitudinal and lateral reinforcement 5 is superoposed with the doweled stud 4 for mounting, concrete 6 is a placed in a given thickness. This enables a steel pipe sheet pile landslide protection wall to be utilized as part of a regularily-built underground outer wall, resulting in improvement of econom ical efficiency.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、地盤の掘削工事に際し地盤の崩壊を防ぐた
め施工される鋼管矢板山留め壁を、そ[■本設の地下外
壁(地下構造壁)として構築する方法に係り、さらにい
えば、鋼管矢板と鉄筋、鉄骨及びコンクIJ −トを一
体的に複合化した地下外壁の構築法に関する。
[Detailed Description of the Invention] (Industrial Application Field) This invention provides a steel pipe sheet pile retaining wall constructed to prevent ground collapse during ground excavation work. ), and more specifically, it relates to a method of constructing an underground exterior wall that integrally combines steel pipe sheet piles, reinforcing bars, steel frames, and concrete IJ-concrete.

(従来技術とその問題点など) 地下構造物を構築するに際しては、所要の地下空間を得
るため地盤を掘削し地下水を汲み出す必要がある。この
ため山留め壁を構築し、これに作用する土圧や水圧を切
梁等によって支え、空間を確保しつつ工事を進めている
のが現状である。山留め壁や切梁等には材料や施工法等
により多糧多様あり、鋼管矢板山留め壁もその一つであ
る。
(Prior art and its problems, etc.) When constructing an underground structure, it is necessary to excavate the ground and pump out groundwater in order to obtain the required underground space. For this reason, construction is currently progressing by constructing retaining walls, supporting the earth pressure and water pressure acting on them with struts, etc., and securing space. There are many types of retaining walls, struts, etc., depending on materials and construction methods, and retaining walls made of steel pipe sheet piles are one of them.

ところで、従来の山留め壁に1いずれも仮設構造物とし
てのみ利用され、使用済後はその11残置され何ら利用
されることはなかった0しかし、鋼管矢板は、工場にて
一貫生産された鋼製品(鋼管)であり、他の材の山留め
壁に比べて品質、精度の点で高い位置にある。このよう
に優れた材料を単に仮設材としてのみ利用しその後放置
することは不経済この上ないことといわねばならない。
By the way, all of the conventional mountain retaining walls were used only as temporary structures, and after they were used they were left behind and never used. However, steel pipe sheet piles are steel products that are manufactured in a factory in an integrated manner. (steel pipe), and is in a higher position in terms of quality and precision than retaining walls made of other materials. It must be said that it would be extremely uneconomical to use such an excellent material merely as a temporary construction material and then leave it as is.

しかも、仮設山留め壁の内側にあらためて本設地下外壁
を構築することは、トータルコストが大きくなり、かつ
、敷地の有効利用を阻害することになり、問題である。
Moreover, constructing a permanent underground outer wall inside the temporary retaining wall increases the total cost and impedes the effective use of the site, which is problematic.

(発明の目的) そこで、この発明の目的は、鋼管矢板全本設の地下外壁
(永久構造物)の一部として利用し。
(Object of the invention) Therefore, the object of this invention is to utilize the steel pipe sheet pile as part of an underground outer wall (permanent structure) completely installed.

もってその経済性を高めるところの鋼管矢板地下外壁の
構築法を提供することにある。
The object of the present invention is to provide a method of constructing an underground steel pipe sheet pile exterior wall that improves its economic efficiency.

(発明の構FJi、) 上記目的を達成するために、この発明の鋼管矢板地下外
壁の構築法は、鋼管矢板(但し、鋼矢板その他の類似材
を含む。以下同じ)による山留め掘削後に、鋼管矢板相
互を根切り面内側から溶接する工程と、鋼管矢板山留め
壁の内側に必要とされる鉄骨お工び(又は)鉄筋を所要
の形態で付設する工程と、鋼管矢板山留め壁の内側に所
要厚さのコンクリートを打設する工程とより成るものと
している。
(Structure of the invention FJi) In order to achieve the above object, the method for constructing an underground outer wall of steel pipe sheet piles of the present invention is such that after excavation of piles using steel pipe sheet piles (including steel sheet piles and other similar materials; the same shall apply hereinafter), steel pipes are The process of welding the sheet piles to each other from the inside of the cut surface, the process of attaching the required steel frame (or) reinforcing bars in the required form to the inside of the steel pipe sheet pile retaining wall, and the process of welding the steel pipe piles to the inside of the steel pipe sheet pile retaining wall. The process consists of pouring concrete to a certain thickness.

(作用効果) つ1す、鋼管矢板を本設の地下外壁として利用する上で
のネックは、鋼管矢板自体土庄、水圧等の面外力に対し
ては十分耐える材ではあるものの、継手がルーズで、地
震横力やせん断力等の面内力に対する抵抗が不十分であ
り、即ち構造材料としては一方向材状のため耐震壁、支
持壁としては使い難いという点である。
(Function and effect) First, the problem with using steel pipe sheet piles as permanent underground external walls is that although the steel pipe sheet piles themselves are strong enough to withstand out-of-plane forces such as soil pressure and water pressure, the joints are loose. However, it has insufficient resistance to in-plane forces such as seismic lateral force and shear force, and as a structural material, it is difficult to use as a shear wall or a support wall because it is a unidirectional material.

ところが、この発明では、鋼管矢板を鉄骨、鉄筋と共に
取り込んでコンクリートで一体的に複合化する。このた
め、面外力はもとより、面内の地震横力、せん断力等に
対しても必要十分な強度、剛性を発揮するところとなり
、建物の本設地下外壁として、及び山留め壁、耐震壁、
支持壁として永久的に使用可能である。
However, in this invention, steel pipe sheet piles are taken in together with steel frames and reinforcing bars, and are integrated into a composite structure with concrete. For this reason, it exhibits sufficient strength and rigidity not only against out-of-plane forces, but also against in-plane seismic lateral forces, shear forces, etc., and can be used as permanent underground external walls of buildings, retaining walls, earthquake-resistant walls, etc.
Can be used permanently as a supporting wall.

また、従来問題視された構造地下外壁との結合、あるい
は鉄骨柱、梁との取り合わせに、鉄骨や鉄筋を付設した
結果、その態様如何により解決できる0 かくして、鋼管矢板が地下外壁の一部として利用される
結果、従来単に土中に残置されるだけでしかなかった鋼
管矢板の利用価値、経済性は著るしく高められる。その
上、仮設山留め壁の内側にあらためて本設地下外壁を構
築するところのスペース上の無駄が生じなく、トータル
コストの上昇を抑制して、なおかつ敷地は境界線際の山
留め壁のところまで有効利用できるという優れた経済性
を発揮するのである。
In addition, as a result of attaching steel frames and reinforcing bars to connect the structure with the underground external wall, which was considered a problem in the past, or in combination with steel columns and beams, the problem can be solved depending on the mode. As a result of its use, the utility value and economic efficiency of steel pipe sheet piles, which were previously simply left in the ground, will be significantly increased. Furthermore, there is no waste of space when constructing a permanent underground outer wall inside the temporary retaining wall, which reduces the total cost increase, and makes effective use of the site up to the retaining wall near the boundary line. It demonstrates excellent economic efficiency.

(実施例) 第1図〜第3図に示した鋼管矢板地下外壁は、継手たる
C形パイグ1とT形し−ル2とを連結して打込1れた鋼
管矢板3…による山留め壁を利用して施工されている。
(Example) The underground outer wall of the steel pipe sheet piles shown in Figs. 1 to 3 is a retaining wall made of steel pipe sheet piles 3 driven by connecting a C-shaped pike 1 and a T-shaped pipe 2 as joints. It is constructed using.

即ち、鋼管矢板3の内側において地盤を掘削し、地下水
を汲み出して所要の地下空間を得た後、根切り面内側に
おいて、根切り底面から上方に向って、1ずC形バイグ
1とT形し−ル2との当接部を溶接で接合し、鋼管矢板
3,3…相互を一枚の壁(又は膜)構造としている。従
って、これにより鋼管矢′&3…は面内力に対する抵抗
力を大幅に増強される。
That is, after excavating the ground inside the steel pipe sheet pile 3 and pumping out groundwater to obtain the required underground space, on the inside of the root cut surface, from the bottom of the root cut upwards, 1, C-shaped barge 1 and T-type The contact portion with the steel pipe 2 is joined by welding, and the steel pipe sheet piles 3, 3... have a single wall (or membrane) structure. Therefore, this greatly increases the resistance of the steel pipes '&3' to in-plane forces.

次に、鋼管矢板3…による山留め壁の内側にシャーコネ
クターとしてスタットジペル4…を所要本数、所要の配
置で溶接し、これに縦横鉄筋5を重ねて組付け、所望厚
さのコンクリート6が打設されている。
Next, Statzipel 4... as shear connectors are welded in the required number and in the required arrangement to the inside of the retaining wall made of steel pipe sheet piles 3..., vertical and horizontal reinforcing bars 5 are stacked and assembled, and concrete 6 of the desired thickness is poured. has been done.

従って、鋼管矢板3と鉄筋5及びコンクIJ −トロは
完全一体的に複合化しており、各資材の特性を発揮して
剛強性の高い地下外壁が得られる。よって、本設の構造
地下外壁としての使用に供し得るのである。
Therefore, the steel pipe sheet piles 3, reinforcing bars 5, and concrete IJ-toro are completely integrated into a composite structure, and a highly rigid underground wall can be obtained by exhibiting the characteristics of each material. Therefore, it can be used as a permanent structural underground outer wall.

なお、鋼管矢板地下外壁の構築は、上記工程を順次上方
に向って一定高さづつくり返し、鋼管矢板3の全高にわ
たり施工して完了する。
In addition, the construction of the steel pipe sheet pile underground wall is completed by repeating the above-mentioned steps in sequence upward at a constant height and constructing over the entire height of the steel pipe sheet pile 3.

ところで、鋼管矢板3の継手構造は、従来、第4図に示
した如くC形バイグ1.1同志の連結、又は第5図に示
した如くC形溝鋼材7とT形し−ル2の連結によるもの
などが実施されており、そのいずれでも全く同様に施工
可能である0 また、継手部の溶接だけでは鋼管矢板3…による壁構造
の剛強性に不安があるときは、第1図中に2点鎖線で示
したように、鋼管矢板3…相互間に根切り面内側から組
入れた鉄板8…を溶接し、もっていわゆる鋼フレーム構
造を形成することにより解決する。
By the way, the joint structure of the steel pipe sheet pile 3 has conventionally been the connection of the C-type vigs 1.1 to each other as shown in FIG. Some methods have been used, such as connecting them together, and any of these methods can be constructed in exactly the same way.0 In addition, if there is any concern about the rigidity of the wall structure made of steel pipe sheet piles 3... by simply welding the joints, please refer to Figure 1. As shown by two-dot chain lines, the problem is solved by welding steel plates 8 inserted between the steel pipe sheet piles 3 from the inside of the root cut surface, thereby forming a so-called steel frame structure.

(第2の実施例) 第6図と第7図に示した鋼管矢板地下外壁の場合は、各
鋼管矢板3…の根切り面内側に横−列状の配置で通孔8
…を設け、これに横筋9全通している。縦筋10…は、
各横筋9…のうち鋼管矢板3…の外に露出した部位に数
本づつ配筋シている。コンクリート6は、鋼管矢f3…
の内側部に所要厚さ打設すると共に各鋼管矢板3…の中
空部内にもコンクリートを打設し、もって鋼管矢板3…
の剛強性を高めている。
(Second Embodiment) In the case of the underground outer wall of the steel pipe sheet piles shown in FIGS. 6 and 7, the through holes 8 are arranged in horizontal rows on the inside of the cut surface of each steel pipe sheet pile 3...
... is provided, and all of the horizontal stripes 9 are passed through this. Vertical line 10... is
Of each horizontal reinforcement 9..., several reinforcements are arranged at the parts exposed outside the steel pipe sheet piles 3.... Concrete 6 is steel pipe arrow f3...
Concrete is poured to the required thickness on the inside of each steel pipe sheet pile 3..., and concrete is also poured into the hollow part of each steel pipe sheet pile 3...
The rigidity is increased.

なお、選択的配置の鋼管矢板3′については、これを支
持層11に1で到達させて支持杭となしている。従って
、この地下外壁は支持壁としての効能を有する。
In addition, regarding the selectively arranged steel pipe sheet piles 3', these are made to reach the support layer 11 at 1 and are used as support piles. Therefore, this underground outer wall has an effect as a supporting wall.

(第3の実施例) 第8図は、鋼管矢板地下外壁と鉄骨柱との取り合わせ部
分を示している。
(Third Embodiment) FIG. 8 shows a combination of a steel pipe sheet pile underground wall and a steel column.

即ち、柱位置の鋼管矢板3“は、これを−万のフランジ
部として利用しているのであり、これにTカット鋼材1
21に溶接し、柱鉄筋13を巻いてコンクリート打設を
行ない枕型14が形成されている。
In other words, the steel pipe sheet pile 3" at the column position is used as a flange part of -10,000, and the T-cut steel material 1 is attached to this.
21, and the column reinforcing bars 13 are wrapped around them and concrete is placed to form a pillow shape 14.

従って、この場合、−万の7ランジとして利用する鋼管
矢板3′については、予めその肉厚を鉄骨柱の一部とし
て適合するように調整しておく。また、Tカット鋼材1
2の溶接を良好ならしめるため、ウェブの一部15は、
予め鋼管矢板3′の内側に先付けしておく。
Therefore, in this case, the wall thickness of the steel pipe sheet pile 3' to be used as a lunge is adjusted in advance so that it will fit as part of the steel column. In addition, T-cut steel material 1
2, part 15 of the web is
Attach it to the inside of the steel pipe sheet pile 3' in advance.

念のためには、前記鋼管矢板3#の打込み時に、そのウ
ェブの一部15を鉄板等の箔で覆っておくのがよい。か
くすれば、溶接時にその箔を除去すると、清掃の手間が
かからないからである。
Just to be sure, when driving the steel pipe sheet pile 3#, it is better to cover a portion 15 of the web with a foil such as an iron plate. This is because if the foil is removed at the time of welding, there is no need for cleaning.

柱鉄筋の組立ては、鋼管矢板3“の肉厚を利用するため
、ツー1筋13の両端を鋼管矢板3′′に溶接して行な
っている。もつとも、鋼管矢板3#にスタットジペル等
を設け、これに7−1筋13を溶接する方法で柱鉄筋の
組立てを行なってもよい0 (第4の実施例) 第9図〜第11図1丁、柱位置の鋼管矢板3を直接鉄骨
柱のフランジの一部として利用しない場合、又は地下外
壁をより剛強なものとする手段を示している。
In order to utilize the wall thickness of the steel pipe sheet pile 3'', the column reinforcing bars are assembled by welding both ends of the two 1st reinforcement 13 to the steel pipe sheet pile 3''. Column reinforcing bars may be assembled by welding 7-1 bars 13 to this. (Fourth embodiment) Figure 9 to Figure 11, the steel pipe sheet pile 3 at the column position can be directly attached to the steel column. This shows a case where it is not used as part of a flange, or a means to make the underground outer wall stronger.

即ち、@管矢版3には、その根切I)面内仰の上下方向
に一足のピッチで柱鉄骨のウェブ部分を突出きせるスリ
ット形状の窓孔16…を設けている。
That is, the @pipe pile 3 is provided with slit-shaped window holes 16 that allow the web portion of the column steel frame to protrude at a pitch of one foot in the vertical direction of the root cut I) plane.

他方、柱鉄骨17に、そのウェブ中央部に縦に組長い略
六角形状(但し、形状はこの限りではない。)の開孔1
79…を前記環孔16と略同−ピッチで設け、そのウェ
ブ中央を縦に二分割している。
On the other hand, a vertically elongated approximately hexagonal opening 1 (however, the shape is not limited to this) is formed in the column steel frame 17 at the center of its web.
79... are provided at substantially the same pitch as the annular holes 16, and the center of the web is vertically divided into two.

そして、−万の分割体17、は鋼管矢板3の中空部内に
挿入し、そのウェブ部分を窓孔16…を通じて外方に突
出させる。これに対して他方の分割体171は、鋼管矢
板3の外において、そのウェブを前記管内の分割体17
.のウェブと突き合わせ溶接している。従って、鋼管矢
板3と柱鉄骨17とを完全一体重に複合化したものが得
られる。よって、これを利用することにより剛性の高い
地下構造躯体を構築できる。
Then, the -10,000-piece divided body 17 is inserted into the hollow part of the steel pipe sheet pile 3, and its web portion is made to protrude outward through the window holes 16. On the other hand, the other divided body 171 transfers its web to the divided body 17 inside the pipe outside the steel pipe sheet pile 3.
.. The web is butt welded. Therefore, a composite structure in which the steel pipe sheet pile 3 and the column steel frame 17 are completely integrated is obtained. Therefore, by utilizing this, a highly rigid underground structure framework can be constructed.

(第5の実施例) 第12図は、鋼管矢板地下外壁と梁との取り合い構造を
示している。
(Fifth Embodiment) FIG. 12 shows a joint structure between a steel pipe sheet pile underground wall and a beam.

即ち、鋼管矢板3の中間部分の梁型18に、その梁鉄筋
のうちフープ筋19の両端を鋼管矢板3に溶接して(又
はスタットジペル等のシャーコネクターに重ねて)組立
て、地下外壁と一体にコンクリート打設して形成されて
いる。
That is, both ends of hoop reinforcements 19 of the beam reinforcing bars are welded to the steel pipe sheet pile 3 (or stacked on a shear connector such as Statzipel) and assembled to the beam type 18 in the middle part of the steel pipe sheet pile 3, and integrated with the underground outer wall. It is formed by pouring concrete.

また、鋼管矢板3の頭部には、臥梁20を被せた構成と
し、応力の伝達を確実ならしめている0 (その他) 第7図に示した鋼管矢板30通孔8、及び第10図に示
した鋼管矢板3の窓孔16は、予め孔あけ加工しておく
のがよく、その方法としては予め孔あけ加工した平版を
丸めて溶接し管体に形成する方法を採用することもでき
る。
In addition, the head of the steel pipe sheet pile 3 is covered with a girder 20 to ensure stress transmission. The window holes 16 of the steel pipe sheet pile 3 shown are preferably drilled in advance, and a method of forming the tube body by rolling and welding a flat plate with holes drilled in advance may also be adopted.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第3図はこの発明の第1実施例の方法で構築さ
れつつある鋼管矢板地下外壁を示す平面図と立面図及び
側面図、第4図と第5図は鋼管矢板継手部の異なる構成
の例を示した平面図、第6図と第7図は第2実施例の方
法で構築される鋼管矢板地下外壁を示した平面図と立面
図、第8図は第3実施例を示した平面図、第9図〜第1
1図は鋼管矢板と鉄骨の取ジ合いを示した平面図と正面
図及び断面図、第12図は鋼管矢板地下外壁と梁との取
り合いを示した断面図である。 発明者   幾田悠康
1 to 3 are a plan view, an elevation view, and a side view showing an underground outer wall of a steel pipe sheet pile being constructed by the method of the first embodiment of the present invention, and FIGS. 4 and 5 are a joint section of a steel pipe sheet pile. Fig. 6 and Fig. 7 are plan views and elevation views showing the steel pipe sheet pile underground external wall constructed by the method of the second embodiment, and Fig. 8 is a plan view showing examples of different configurations of the method of the third embodiment. Plan views showing examples, Figures 9 to 1
Figure 1 is a plan view, front view, and cross-sectional view showing the connection between the steel pipe sheet pile and the steel frame, and Figure 12 is a cross-sectional view showing the connection between the steel pipe sheet pile and the underground outer wall and the beam. Inventor Yuyasu Ikuta

Claims (9)

【特許請求の範囲】[Claims] (1)(イ)鋼管矢板(3)…による山留め掘削後、鋼
管矢板相互を根切り面内側から溶接する工程と、(ロ)
鋼管矢板山留め壁の内側に鉄骨(12)、(17)、鉄
筋(5)を付設する工程と、 (ハ)鋼管矢板山留め壁の内側に所要厚さのコンクリー
ト(6)を打設する工程と、より成ることを特徴とする
鋼管矢板地下外壁の構築法。
(1) (A) After excavating the piles using the steel pipe sheet piles (3)..., the process of welding the steel pipe sheet piles together from the inside of the cut surface, and (B)
A step of attaching steel frames (12), (17), and reinforcing bars (5) inside the steel pipe sheet pile retaining wall; (c) A step of pouring concrete (6) of the required thickness inside the steel pipe sheet pile retaining wall. , a construction method for an underground steel pipe sheet pile exterior wall.
(2)特許請求の範囲第1項に記載した鋼管矢板相互の
溶接は、鋼管矢板継手部(1)、(2)の溶接により行
なう鋼管矢板地下外壁の構築法。
(2) A method for constructing an underground outer wall of steel pipe sheet piles, in which the mutual welding of the steel pipe sheet piles described in claim 1 is performed by welding the steel pipe sheet pile joints (1) and (2).
(3)特許請求の範囲第1項に記載した鉄筋(5)の付
設は、鋼管矢板(3)に対してその根切り面内側にスタ
ットジペル(4)等のシャーコネクターを取り付け、こ
れに重ねて鉄筋(5)を組立てることにより行なう鋼管
矢板地下外壁の構築法。
(3) The reinforcing bars (5) described in claim 1 are attached by attaching shear connectors such as Studzipel (4) to the inner side of the cut surface of the steel pipe sheet pile (3), and stacking them on top of this. A construction method for underground steel pipe sheet pile walls by assembling reinforcing bars (5).
(4)特許請求の範囲第1項に記載した鉄骨(12)の
付設は、鋼管矢板(3)に予めウェブの一部(15)を
先付けしておき、これに鉄骨(12)のウェブを溶接す
ることにより行なう鋼管矢板地下外壁の構築法。
(4) The attachment of the steel frame (12) described in claim 1 is achieved by attaching a part of the web (15) to the steel pipe sheet pile (3) in advance, and then attaching the web of the steel frame (12) to this. A construction method for underground steel pipe sheet pile walls by welding.
(5)特許請求の範囲第1項に記載した鉄筋(9)、(
10)の付設は、鋼管矢板(3)の根切り面内側に通孔
(8)…を設けてこれに横筋(9)を貫通せしめ、この
横筋(9)に対して縦筋(10)を配筋することにより
行なう鋼管矢板地下外壁の構築法。
(5) Reinforcing bars (9), (
10) is achieved by providing a through hole (8) on the inside of the cut surface of the steel pipe sheet pile (3), passing the horizontal reinforcement (9) through it, and attaching the vertical reinforcement (10) to the horizontal reinforcement (9). A construction method for underground steel pipe sheet pile walls using reinforcement.
(6)特許請求の範囲第1項に記載した梁鉄筋(19)
又は柱鉄筋(13)の付設は、そのフープ筋両端を鋼管
矢板(3)に溶接することにより行なう鋼管矢板地下外
壁の構築法。
(6) Beam reinforcing bars (19) described in claim 1
Alternatively, the column reinforcing bars (13) are installed by welding both ends of the hoop bars to the steel pipe sheet piles (3).
(7)特許請求の範囲第1項に記載した鉄骨(17)の
付設は、鉄骨のウェブを二分割してその一方の分割体(
17_1)を鋼管矢板(3)の中空部内に挿入し、同鋼
管矢板(3)の根切り面内側に設けた窓孔(16)を通
じてウェブを一部突出させ、他方の分割体(17_2)
は鋼管矢板(3)の外からそのウェブを前記分割体(1
7_1)のウェブと当接させ溶接により一体化すること
により行なう鋼管矢板地下外壁の構築法。
(7) The attachment of the steel frame (17) described in claim 1 is achieved by dividing the steel frame web into two parts (
17_1) into the hollow part of the steel pipe sheet pile (3), a part of the web protrudes through the window hole (16) provided inside the cut surface of the steel pipe sheet pile (3), and the other divided body (17_2)
The web is inserted into the divided body (1) from outside the steel pipe sheet pile (3).
7_1) A method of constructing an underground steel pipe sheet pile underground wall by bringing it into contact with the web and integrating it by welding.
(8)特許請求の範囲第1項に記載したコンクリート(
6)の打設は、鋼管矢板(3)の中空部内にも行なう鋼
管矢板地下外壁の構築法。
(8) Concrete (
6) is a construction method for underground external walls of steel pipe sheet piles in which the driving is also carried out inside the hollow part of the steel pipe sheet piles (3).
(9)特許請求の範囲第5項に記載した通孔(8)又は
特許請求の範囲第7項に記載した窓孔(16)は、予め
孔あけ加工した平板を丸めて管体とする方法等により予
め鋼管矢板(3)に設けておく鋼管矢板地下外壁の構築
法。
(9) The through hole (8) described in claim 5 or the window hole (16) described in claim 7 is a method of forming a tube by rolling a flat plate that has been previously drilled. A method of constructing a steel pipe sheet pile underground external wall that is installed in advance on the steel pipe sheet pile (3) by etc.
JP59207653A 1984-10-03 1984-10-03 Method of building steel pipe sheet pile underground outer wall Granted JPS6187015A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP59207653A JPS6187015A (en) 1984-10-03 1984-10-03 Method of building steel pipe sheet pile underground outer wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP59207653A JPS6187015A (en) 1984-10-03 1984-10-03 Method of building steel pipe sheet pile underground outer wall

Publications (2)

Publication Number Publication Date
JPS6187015A true JPS6187015A (en) 1986-05-02
JPH025203B2 JPH025203B2 (en) 1990-02-01

Family

ID=16543334

Family Applications (1)

Application Number Title Priority Date Filing Date
JP59207653A Granted JPS6187015A (en) 1984-10-03 1984-10-03 Method of building steel pipe sheet pile underground outer wall

Country Status (1)

Country Link
JP (1) JPS6187015A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010073538A1 (en) * 2008-12-25 2010-07-01 新日本製鐵株式会社 Steel sheet pile wall and method for constructing same

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4811607B1 (en) * 1969-09-30 1973-04-14
JPS574772B2 (en) * 1977-12-03 1982-01-27
JPS5829922A (en) * 1981-08-14 1983-02-22 Takenaka Komuten Co Ltd Constructing method for underground outer wall

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS574772A (en) * 1980-06-11 1982-01-11 Noda Plywood Mfg Co Ltd Decorative board and its manufacture

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4811607B1 (en) * 1969-09-30 1973-04-14
JPS574772B2 (en) * 1977-12-03 1982-01-27
JPS5829922A (en) * 1981-08-14 1983-02-22 Takenaka Komuten Co Ltd Constructing method for underground outer wall

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010073538A1 (en) * 2008-12-25 2010-07-01 新日本製鐵株式会社 Steel sheet pile wall and method for constructing same
JP4757959B2 (en) * 2008-12-25 2011-08-24 新日本製鐵株式会社 Steel sheet pile wall and its construction method

Also Published As

Publication number Publication date
JPH025203B2 (en) 1990-02-01

Similar Documents

Publication Publication Date Title
KR100634726B1 (en) Form system for construction of underground slab and method for constructing underground slab and breast wall using the same
KR20090094971A (en) Under ground top-down method
KR101278687B1 (en) Box-type thrust tube structure, and method of building underground structure using the box-type thrust tube structure
KR101631447B1 (en) Top-Down method of underground structure using the CFT and the Composite Beam
KR101083762B1 (en) Connection Structure of Concrete Filled Steel Tube Column and Flat Plate Slab
KR102362257B1 (en) Top-down construction method
KR100631363B1 (en) Panel zone system of y shape tied column reinforced with high tension bolts
JPH09268583A (en) Structural steel embedded half precast concrete member and construction method of underground structure using the same member
CN212801651U (en) Ground is wall and horizontal beam connected node even based on reverse construction method
JPS6187015A (en) Method of building steel pipe sheet pile underground outer wall
JPS5829922A (en) Constructing method for underground outer wall
JP3244614B2 (en) Deck plate steel orthogonal sandwich structure
KR20220065461A (en) WIRE STRUCTURE FOR STAGGERED LAPPING IN SLURRY WALL, SLURRY WALL and CONSTRUCTION METHOD FOR THE SAME
JPH08109631A (en) Underground wall
CN110792103A (en) Underground pipeline with integrated supporting piles and pipeline wall and construction method
CN218148285U (en) PC construction method pile convenient to lengthen
JPH06137065A (en) Conjunction of new precast material members and new concrete wall member
JPS63280153A (en) Underground inverted lining method
JP2987371B2 (en) Underground diaphragm wall
JP4483095B2 (en) Joint structure of H-shaped steel column and RC shear wall
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
JPH01315520A (en) Underground outer wall constructing method for superstructure
CN216920292U (en) Precast tubular pile and supporting construction thereof
JP2004124554A (en) Basement structure
JPH05263404A (en) Column base structural body and construction method thereof