JPS6156403B2 - - Google Patents

Info

Publication number
JPS6156403B2
JPS6156403B2 JP15073679A JP15073679A JPS6156403B2 JP S6156403 B2 JPS6156403 B2 JP S6156403B2 JP 15073679 A JP15073679 A JP 15073679A JP 15073679 A JP15073679 A JP 15073679A JP S6156403 B2 JPS6156403 B2 JP S6156403B2
Authority
JP
Japan
Prior art keywords
turbine building
circulating water
construction
concrete
water piping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP15073679A
Other languages
Japanese (ja)
Other versions
JPS5675912A (en
Inventor
Michio Shibuya
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Tokyo Shibaura Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Shibaura Electric Co Ltd filed Critical Tokyo Shibaura Electric Co Ltd
Priority to JP15073679A priority Critical patent/JPS5675912A/en
Publication of JPS5675912A publication Critical patent/JPS5675912A/en
Publication of JPS6156403B2 publication Critical patent/JPS6156403B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 本発明は、復水器を有する発電所建設における
タービン建屋マツト下に埋設される蒸気凝縮用の
冷却水配管(以下循環水配管と称する)の施工方
法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for constructing cooling water piping (hereinafter referred to as circulating water piping) for steam condensation to be buried under a mat of a turbine building in the construction of a power plant having a condenser.

本発明は明確に示すため、従来の実施例につい
て説明する。第1図は、タービン建屋マツト下に
埋設される循環水配管の配置を示す断面図であ
る。第2図は、循環水配管施工、タービン建屋マ
ツト施工を示す断面図である。
In order to clearly illustrate the present invention, conventional embodiments will be described. FIG. 1 is a sectional view showing the arrangement of circulating water piping buried under a turbine building mat. FIG. 2 is a sectional view showing circulating water piping construction and turbine building mat construction.

タービン建屋エリアの掘削が完了すると、循環
水配管固定用のアンカー材1を設定し、コンクリ
ート2を打設する。コンクリート2養生後、復水
器12に付属する水室13に接続する循環水配管
3,4用の架台5を据付、循環水配管3,4の搬
入、芯出、仮付溶接を行なう。循環水配管3,4
の配列が完了すると、本溶接、溶接検査、を行な
い、循環水配管3,4の管内外面の塗装を行な
う。塗装検査完了後、コンクリート11をタービ
ン建屋マツト下レベルまで打設する。コンクリー
ト11養生後、補強材10を組立て、タービン建
屋マツトコンクリート9を打設する。
When the excavation of the turbine building area is completed, anchor materials 1 for fixing circulating water piping are set and concrete 2 is poured. After the concrete 2 has cured, a frame 5 for the circulating water pipes 3 and 4 connected to the water chamber 13 attached to the condenser 12 is installed, and the circulating water pipes 3 and 4 are brought in, centered, and temporarily welded. Circulating water piping 3, 4
When the arrangement is completed, main welding and welding inspection are performed, and the inner and outer surfaces of the circulating water pipes 3 and 4 are painted. After the coating inspection is completed, concrete 11 is poured to the level below the turbine building pine. After the concrete 11 is cured, the reinforcing material 10 is assembled and the turbine building mat concrete 9 is poured.

なお、14はタービンペデスタル、15はター
ビン、20はタービン運転床である。
Note that 14 is a turbine pedestal, 15 is a turbine, and 20 is a turbine operating bed.

従来のタービン建屋マツト下に埋設される循環
水配管の施工方法は、上述のようであつたが、こ
のような施工方法では、次のような重大な欠点が
あつた。
The conventional construction method for circulating water piping buried under the pine of a turbine building was as described above, but such construction method had the following serious drawbacks.

すなわち、このような従来の施工方法では、循
環水配管3,4の施工が完了し、コンクリート1
1が打設され、コンクリート11の養生後でない
と、タービン建屋マツト9の工事が施工できな
い。しかも、このエリアのタービン建屋マツト工
事が、他のエリアのマツト工事よりも遅れ、施工
上及び安全上からも問題がある。
That is, in such a conventional construction method, the construction of the circulating water pipes 3 and 4 is completed, and the concrete 1
The turbine building mat 9 cannot be constructed until after the concrete 11 has been poured and the concrete 11 has cured. Moreover, the turbine building mating work in this area is delayed compared to the mating work in other areas, which poses problems from a construction and safety perspective.

この結果、タービンペデスタル14部の躯体工
事がタービン建屋全体の躯体工事のクリテイカル
パスとなり、発電所全体の建設工期が長期に及ぶ
最大の原因となつている。
As a result, the construction of the 14th section of the turbine pedestal becomes a critical path for the construction of the entire turbine building, and is the biggest reason for the long construction period of the entire power plant.

本発明は、以上の事情に鑑みなされたものであ
り、(イ)タービン建屋マツト下に埋設される循環水
配管の施工をタービン建屋マツト工事施工と並行
作業とし、タービン建屋全体の躯体工事のクリテ
イカルパスからはずすこと、(ロ)タービン建屋全体
の躯体施工工期の大巾短縮をはかること、(ハ)ター
ビン建屋躯体工事の施工性の向上と、安全性の向
上をはかることを目的としている。
The present invention has been made in view of the above-mentioned circumstances.(a) The construction of the circulating water piping buried under the turbine building mat is carried out in parallel with the turbine building mat construction, and the structure work of the entire turbine building can be completed. (b) To significantly shorten the construction period for the entire turbine building frame, and (c) To improve the workability and safety of the turbine building frame work.

すなわち、以上の目的が達成できるタービン建
屋マツト下に埋設される循環水配管の施工方法を
得ることにある。
That is, the object is to obtain a construction method for circulating water piping buried under the pine of a turbine building that can achieve the above objects.

以下、図面を参照して本発明の一実施例を説明
する。第3図に示すように、掘削完了後、アンカ
ー材1を設定しコンクリート2を打設する。コン
クリート2養生後、金網(リブラス)6及びター
ビン建屋マツト補強材10を受ける受け梁鋼材7
の支持用鋼材8をアンカー材1より据付る。この
時点で、埋設される循環水配管4を搬入し仮置す
る。次に金網(リブラス)及びタービン建屋マツ
ト補強材10を受ける受け梁鋼材7を据付、この
受け梁鋼材7を利用して復水器12に付属する水
室13に接続され、タービン建屋マツト9に直接
埋設される循環水管の垂直部3を設定し同時に金
網(リブラス)6を据付る。この金網(リブラ
ス)6で、タービン建屋マツト部9と循環水配管
3,4の施工エリア11を分離することができ、
各々の工事施工が並行して可能となる。つまり、
循環水配管3,4の施工を続けながらタービン建
屋マツト9の工事が開始することできる。循環水
配管施工は引続き水平部4の配列、溶接、溶接検
査、更に、塗装及び塗装検査を行なう。
Hereinafter, one embodiment of the present invention will be described with reference to the drawings. As shown in FIG. 3, after completion of excavation, anchor materials 1 are set and concrete 2 is poured. After the concrete 2 has cured, the support beam steel 7 receives the wire mesh (ribrass) 6 and the turbine building pine reinforcing material 10
The supporting steel material 8 is installed from the anchor material 1. At this point, the circulating water piping 4 to be buried is brought in and temporarily placed. Next, a steel support beam 7 for receiving the wire mesh (ribrass) and the turbine building mat reinforcement material 10 is installed, and using this support beam steel material 7, it is connected to the water chamber 13 attached to the condenser 12, and is connected to the turbine building mat 9. The vertical part 3 of the circulating water pipe to be directly buried is set up, and at the same time, the wire mesh (ribrass) 6 is installed. This wire mesh (ribrass) 6 can separate the turbine building mat section 9 from the construction area 11 of the circulating water pipes 3 and 4.
Each construction project can be carried out in parallel. In other words,
Construction of the turbine building mat 9 can be started while continuing construction of the circulating water pipes 3 and 4. The construction of the circulating water piping will continue with alignment of the horizontal section 4, welding, welding inspection, and painting and painting inspection.

タービン建屋マツト9工事は第4図に示すよう
に金網(リブラス)据付後、補強材10を組立て
る。循環水配管3,4埋設、コンクリート11の
打設とタービン建屋マツトコンクリート9の打設
は時期を同じくして打設する。ここで、タービン
建屋マツト下に埋設される循環水配管工事及びタ
ービン建屋マツト工事が完了し、引続きタービン
建屋躯体工事を行なう。
In the turbine building mat 9 construction, as shown in Figure 4, after installing the wire mesh (ribrass), the reinforcing material 10 is assembled. The circulating water pipes 3 and 4 are buried, the concrete 11 is placed, and the turbine building mat concrete 9 is placed at the same time. At this point, the circulating water piping work to be buried under the turbine building mat and the turbine building mat work have been completed, and work on the turbine building frame will continue.

かくして、タービン建屋マツト下に埋設される
循環水配管の施工をタービン建屋全体の躯体工事
のクリテイカルパスからはずすことが可能とな
り、タービン建屋全体の躯体施工工期が大巾に短
縮できる。又、循環水配管エリアとタービン建屋
マツト部とを金網(リブラス)で仕切つてあるた
め、循環水配管埋設コンクリートと、タービン建
屋マツトコンクリートが同時に打設でき、循環水
配管埋設コンクリート打設後のコンクリート収縮
の影響が排除できる。
In this way, it becomes possible to remove the construction of the circulating water piping buried under the turbine building pine from the critical path of the framework construction of the entire turbine building, and the construction period for the framework of the entire turbine building can be significantly shortened. In addition, since the circulating water piping area and the turbine building pine area are separated by a wire mesh (ribrass), the circulating water piping buried concrete and the turbine building pine concrete can be poured at the same time, and the concrete after the circulating water piping buried concrete is placed. The effect of shrinkage can be eliminated.

更に、タービン建屋躯体工事の施工性と安全性
が著しく改善できる。
Furthermore, the workability and safety of turbine building frame work can be significantly improved.

以上、本発明をその具体例について説明した
が、本発明は、これら特定の実施例に限定される
ものでなく、本発明の精神を逸脱しないで幾多の
変化変形がなし得ることは勿論である。
Although the present invention has been described above with reference to specific examples, the present invention is not limited to these specific examples, and it goes without saying that many changes and modifications can be made without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図Aは循環水配管付近の機器配置を示す縦
断面図、第1図Bは第1図AをB−B線で切断し
矢視方向に見た図、第2図は従来のタービン建屋
の建築施工方法を説明するための図、第3図Aは
本発明によるマツト下工事を説明するための図、
第3図Bは第3図AをB−B線で切断し矢視方向
に見た図、第4図は本発明の工事方法を説明する
ための縦断面図である。 1……アンカー材、3……循環水配管、4……
循環水配管、2……コンクリート、6……金網
(リブラス)、7……梁鋼材、9……マツト、10
……補強材、12……復水器、13……水室、1
1……コンクリート。
Figure 1A is a longitudinal cross-sectional view showing the equipment arrangement near the circulating water piping, Figure 1B is a view of Figure 1A taken along line B-B and viewed in the direction of the arrows, and Figure 2 is a conventional turbine. A diagram for explaining the building construction method, FIG. 3A is a diagram for explaining the pine underlayment construction according to the present invention,
FIG. 3B is a diagram of FIG. 3A cut along line BB and viewed in the direction of the arrows, and FIG. 4 is a longitudinal sectional view for explaining the construction method of the present invention. 1... Anchor material, 3... Circulating water piping, 4...
Circulating water piping, 2... Concrete, 6... Wire mesh (librass), 7... Beam steel, 9... Matsut, 10
... Reinforcement material, 12 ... Condenser, 13 ... Water chamber, 1
1...Concrete.

Claims (1)

【特許請求の範囲】[Claims] 1 タービン建屋建設工事において、マツト下に
埋設される蒸気凝縮用の冷却水配管エリアとマツ
トとを金網で分離して、前記冷却水配管エリアの
コンクリート工事とマツトコンクリート工事を同
時に施工することを特徴とするタービン建屋建設
工事方法。
1. In the turbine building construction work, the cooling water piping area for steam condensation buried under the pine and the pine are separated by a wire mesh, and the concrete work for the cooling water piping area and the pine concrete work are performed at the same time. Turbine building construction method.
JP15073679A 1979-11-22 1979-11-22 Construction of turbine building Granted JPS5675912A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15073679A JPS5675912A (en) 1979-11-22 1979-11-22 Construction of turbine building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15073679A JPS5675912A (en) 1979-11-22 1979-11-22 Construction of turbine building

Publications (2)

Publication Number Publication Date
JPS5675912A JPS5675912A (en) 1981-06-23
JPS6156403B2 true JPS6156403B2 (en) 1986-12-02

Family

ID=15503282

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15073679A Granted JPS5675912A (en) 1979-11-22 1979-11-22 Construction of turbine building

Country Status (1)

Country Link
JP (1) JPS5675912A (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3639560B2 (en) 2002-02-28 2005-04-20 オリンパス株式会社 Endoscope hood
JP2006276689A (en) * 2005-03-30 2006-10-12 Olympus Corp Objective lens unit, living body observation device and adaptor
JP2008206559A (en) * 2007-02-23 2008-09-11 Hoya Corp Tip part of endoscope
JP4825997B2 (en) * 2007-04-27 2011-11-30 株式会社トップ Endoscope adapter
EP2203106A1 (en) * 2007-10-22 2010-07-07 Wilson-Cook Medical Inc. Endoscope cap with aperture for passing guidewire

Also Published As

Publication number Publication date
JPS5675912A (en) 1981-06-23

Similar Documents

Publication Publication Date Title
US1380324A (en) Concrete construction
JPS6156403B2 (en)
JPH06272267A (en) Method for utilizing soil cement post lined wall to built composite underground skeleton
CN209523198U (en) A kind of underpinning structure supporting lattice column
JPS6244636B2 (en)
US2620651A (en) Prefabricated building structure
KR100379740B1 (en) Framework
JPH0364015B2 (en)
KR101700950B1 (en) the hybrid steel joint construction between column and beam
KR101665622B1 (en) the construction method of steel-concrete hybrid precast concrete structure
KR101766805B1 (en) the hybrid joint construction between column plate and column
JP3873629B2 (en) Curtain wall support member and mounting method thereof
JPS63308B2 (en)
Vittorini et al. The use of ‘structural prefabrication’in the Flaminio Stadium by Pier Luigi and Antonio Nervi. A technical-constructive study aimed at formulating guidelines for a future conservation plan
JP3742598B2 (en) Steel wall structure
JP2709140B2 (en) Power plant and steam turbine support
SU962413A1 (en) Butt joint of ribbed girders of unsplit bridge span structures
KR101665628B1 (en) the construction method of hybrid precast concrete structure
SU1196473A1 (en) Reinforcement post for structures
JP2716919B2 (en) Turbine building construction method
JPS6336105Y2 (en)
JPS6062335A (en) Wooden column base-buried foundation
JP2531045B2 (en) Construction method for reinforced concrete structure
JPS6367875B2 (en)
SE451275B (en) System for concrete coating of pipes