JPS6145030B2 - - Google Patents

Info

Publication number
JPS6145030B2
JPS6145030B2 JP4717978A JP4717978A JPS6145030B2 JP S6145030 B2 JPS6145030 B2 JP S6145030B2 JP 4717978 A JP4717978 A JP 4717978A JP 4717978 A JP4717978 A JP 4717978A JP S6145030 B2 JPS6145030 B2 JP S6145030B2
Authority
JP
Japan
Prior art keywords
crane
bottom plate
post
floating roof
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP4717978A
Other languages
Japanese (ja)
Other versions
JPS54140211A (en
Inventor
Takaumi Miura
Munehiro Sakamaki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawasaki Heavy Industries Ltd
Original Assignee
Kawasaki Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Heavy Industries Ltd filed Critical Kawasaki Heavy Industries Ltd
Priority to JP4717978A priority Critical patent/JPS54140211A/en
Publication of JPS54140211A publication Critical patent/JPS54140211A/en
Publication of JPS6145030B2 publication Critical patent/JPS6145030B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)

Description

【発明の詳細な説明】 〈産業上の利用分野〉 この発明は石油貯蔵等に供する地下タンク構築
に於て地盤中に形成したコンクリート躯体内にク
レーンを設置して該クレーンにより各部材を組付
け溶接し、底板、浮屋根等を据付ける方法に関す
る発明であり、特に、側壁コンクリートにレール
材をリング状に固設しておいて、底板コンクリー
トにクレーンポストを設立し、該クレーンポスト
上端と上記レール材との間にクレーンガーダーを
設け、該クレーンガーダーに設置するクレーン台
車と該台車から吊り下げたホイスト等のフツクを
介してタンク構成部材を吊上げ吊下げしてタンク
半径方向に移動し、クレーンガーダーを回動させ
て施工を行うようにした浮屋根タンク据付方法に
係る発明である。
[Detailed Description of the Invention] <Industrial Application Field> This invention involves installing a crane inside a concrete frame formed in the ground and assembling each member using the crane when constructing an underground tank for oil storage, etc. This invention relates to a method of welding and installing a bottom plate, a floating roof, etc., and in particular, a rail material is fixed in a ring shape to a side wall concrete, a crane post is established on the bottom plate concrete, and the upper end of the crane post and the above-mentioned A crane girder is installed between the rail material, and the tank components are lifted and suspended via a crane truck installed on the crane girder and a hook such as a hoist suspended from the truck, and moved in the radial direction of the tank. This invention relates to a floating roof tank installation method in which construction is performed by rotating the girder.

〈従来技術〉 周知の如く、従来より石油等の貯蔵タンクには
種々のものが建造運転されているが、それぞれ一
長一短があり、設計条件に応じて構築されてい
る。
<Prior Art> As is well known, various types of storage tanks for petroleum, etc. have been built and operated in the past, each having advantages and disadvantages, and are constructed according to design conditions.

而して、そのうち浮屋根式タンクはその構造の
簡単さやメンテナンスがし易い等のメリツトのた
め広く用いられている。
Among them, floating roof tanks are widely used because of their simple structure and easy maintenance.

さりながら、一方において浮屋根タンクは浮屋
根の建造に際し、最初底板上にて形成するため、
底板自体の形成は勿論、タンク全体の施工能率の
点で問題があつた。
However, on the other hand, when constructing a floating roof tank, since it is first formed on the bottom plate,
There were problems not only with the formation of the bottom plate itself, but also with the construction efficiency of the tank as a whole.

即ち、第1図に示す様に、地盤1を掘削して構
築された地下タンクのコンクリート躯体2の底板
3の中央にバランスクレーン4を設置し、これを
用いて内側ライニング底板5を据付けたり、その
後底板5上の足場6をセツトしその上に浮屋根7
を組付けたりするようにしていた。
That is, as shown in FIG. 1, a balance crane 4 is installed at the center of the bottom plate 3 of the concrete frame 2 of the underground tank constructed by excavating the ground 1, and using this, the inner lining bottom plate 5 is installed. After that, a scaffold 6 is set on the bottom plate 5, and a floating roof 7 is placed on top of it.
I was trying to assemble it.

〈発明が解決しようとする問題点〉 ところで、該種バランスクレーン設置方式によ
れば、基本的にバランスクレーン4自体のバラン
スの限度のため、底板5や浮屋根7等の部材の重
量ブロツクの組付けに制約がある欠点があり、
又、小、中径タンクの場合はともかくとして大径
の大型タンクになると当然のことながら、底板
5、浮屋根7も大径になり、そのためクレーンの
アーム長が長くなり、それに伴つてバランスウエ
イトも中心から大きく離して設けねばならず、そ
のためクレーン構造が大規模となり、作業の操作
にもバランスウエイトの慣性のため円滑さが無く
なるという不都合さがあつた。
<Problems to be Solved by the Invention> By the way, according to this type of balance crane installation method, basically due to the balance limit of the balance crane 4 itself, it is difficult to assemble the weight blocks of members such as the bottom plate 5 and the floating roof 7. There is a drawback that there are restrictions on attachment,
Furthermore, aside from the case of small and medium diameter tanks, when it comes to large diameter tanks, the bottom plate 5 and floating roof 7 also become larger in diameter, which increases the arm length of the crane and increases the balance weight accordingly. The crane had to be placed far away from the center, resulting in a large-scale crane structure, and there was an inconvenience that the work operation was not smooth due to the inertia of the balance weight.

そして、バランスクレーンに代えて、例えば、
ガイデリツク等をタンク底部基盤上に設置する場
合もあるが、その作動半径に限界があり、センタ
ーポストの控えワイヤ等、ブームの動きを制限す
る要素もあり、特に、ライニング側板のコンクリ
ート巻立工事に支障をきたす等の不都合さもあつ
た。
And instead of a balance crane, for example,
In some cases, guiding devices are installed on the base of the bottom of the tank, but there is a limit to their operating radius, and there are also elements that limit the movement of the boom, such as the center post's retainer wire, and this is especially true when constructing concrete for lining side plates. There were also inconveniences such as interference.

この発明の目的は上述従来技術に基づく浮屋根
タンク施工の際のクレーン作業の問題点を解決す
べき技術的課題とし、タンク底板や屋根の形成が
し易く、しかも、大型タンクでも容易に施工出
来、施工装置のセツト、リセツトもスムースに出
来るようにしてエネルギー産業におけるタンク技
術利用分野に益する優れた浮屋根タンク据付方法
を提供せんとするものである。
The purpose of this invention is to solve the technical problem of crane operation when constructing a floating roof tank based on the above-mentioned conventional technology, and to make it possible to easily form a tank bottom plate and a roof, and to easily construct even large tanks. It is an object of the present invention to provide an excellent floating roof tank installation method that allows smooth setting and resetting of construction equipment and is beneficial to the field of tank technology utilization in the energy industry.

〈問題点を解決するための手段・作用〉 上述目的に沿い先述特許請求の範囲を要旨とす
るこの発明の構成は前述問題点を解決するため
に、地盤中に掘削したタンク部位に打設するコン
クリート躯体の側壁中に予めレール材をリング状
に埋設させ、又、底板にはクレーンポストを設立
し、その上端とレール材との間にクレーンガーダ
ーを設け、クレーンガーダーをクレーンポストを
中心に旋回させると共に、クレーンガーダーに沿
つてクレーン台車を移動させ、クレーン台車に吊
下したホイストのフツクにより部材の組付溶接を
行い、底部でライニング底板を形成、又、底板上
に形成した足場上に浮屋根を形成し、その間側壁
でコンクリートの巻立用の側板を形成し、又、ク
レーンガーダー、クレーンポストは事後解体する
と共に、レール材はライニング側板補強リブとし
て用いるようにした技術的手段を講じたものであ
る。
<Means/effects for solving the problems> In order to solve the above-mentioned problems, the structure of the present invention, which is based on the above-mentioned claims and in accordance with the above-mentioned object, is to install a tank in a tank excavated into the ground. Rail material is buried in a ring shape in the side wall of the concrete frame in advance, a crane post is established on the bottom plate, a crane girder is installed between the upper end of the rail material and the rail material, and the crane girder is rotated around the crane post. At the same time, the crane truck was moved along the crane girder, and the parts were assembled and welded using the hook of the hoist suspended from the crane truck, and a lining bottom plate was formed at the bottom. A roof was formed, and the side walls were used to form side plates for concrete rolling. Also, the crane girder and crane post were dismantled after the fact, and technical measures were taken to use the rail materials as reinforcing ribs for the lining side plates. It is something.

〈実施例〉 次にこの発明の1実施例を第2図以下の図面に
したがつて説明すれば以下の通りである。尚、第
1図と同一態様部分は同一符号を用いて説明する
ものとする。
<Embodiment> Next, an embodiment of the present invention will be described below with reference to FIG. 2 and the following drawings. Note that the same parts as in FIG. 1 will be explained using the same reference numerals.

設定地盤1に掘削した部位にタンク外壁として
のコンクリート躯体2を打設するプロセスにおい
て底板3の打設後側壁3′の打設に際し、全周的
に設定高さ位置にスタツド8を一体的に埋設し、
更に該スタツド8のライナー9にH型鋼のレール
材10を一体的に周方向にリング状に設けてお
く。
In the process of pouring the concrete frame 2 as the outer wall of the tank in a site excavated in the set ground 1, after pouring the bottom plate 3, when pouring the side wall 3', studs 8 are integrally placed at the set height position all around the circumference. buried,
Furthermore, a rail material 10 made of H-shaped steel is integrally provided on the liner 9 of the stud 8 in a ring shape in the circumferential direction.

一方、地表の図示しない重機から吊り込まれた
クレーンポスト11をコンクリート躯体2の底板
3の中心に予め植設したライニング底板用のスタ
ツドを用いて固定設立し、又、併せて同様に重機
にて吊り込んだクレーンガーダー12をしてその
基端を該クレーンポスト11上部に遊装状態で支
持させ、第4図に詳示するクレーンガーダー12
の先端のブラケツト13に枢支したローラ14を
レール材10上に載置する。
On the other hand, a crane post 11 suspended from a heavy machine (not shown) on the ground surface is fixed to the center of the bottom plate 3 of the concrete frame 2 using studs for the lining bottom plate, and A suspended crane girder 12 is supported with its base end on the upper part of the crane post 11 in a loose state, and the crane girder 12 is constructed as shown in FIG. 4 in detail.
A roller 14 pivotally supported by a bracket 13 at the tip of the roller is placed on the rail material 10.

そして、クレーンガーダー12上に予め形成さ
れているレール15上にクレーン台車16を載置
し、適宜にケーブルを配索して準備を完了する。
Then, the crane truck 16 is placed on the rails 15 formed in advance on the crane girder 12, and the cables are appropriately routed to complete the preparation.

上述準備後、同様にして吊り込まれたライニン
グ底板5の部材に対してはクレーン台車16をク
レーンガーダー12のレール15に沿わせて移動
させると共に、クレーンガーダー12の先端に設
置された可逆モータ17を作動させ、スプロケツ
ト18,19、チエン20を介してローラ14を
回動させ、クレーガーダー12をクレーンポスト
11上端を中心にして旋回させ、クレーン台車1
6より吊下したホイストのフツク21を介して各
部材、及び、機材を移動させ、ライニング底板5
の組付、溶接、検査等を行う。
After the preparation described above, the crane truck 16 is moved along the rail 15 of the crane girder 12 with respect to the lining bottom plate 5 that has been similarly suspended, and the reversible motor 17 installed at the tip of the crane girder 12 is moved. is activated, the roller 14 is rotated via the sprockets 18, 19 and the chain 20, the clay girder 12 is rotated around the upper end of the crane post 11, and the crane truck 1 is rotated.
Each member and equipment are moved via the hoist hook 21 suspended from the lining bottom plate 5.
Assembling, welding, inspecting, etc.

而して、ライニング底板5に対する施工を行つ
た後、同様にして吊り込んだ足場部材をクレーン
台車16、ホイストのフツク21、クレーンガー
ダー12を作動させて足場6を組立て、同じく吊
り込んだ浮屋根部材についてライニング底板5の
場合と同様にして浮屋根7を組付、溶接、検査を
行う。
After the construction of the lining bottom plate 5 is completed, the scaffolding members suspended in the same manner are assembled by operating the crane dolly 16, hoist hook 21, and crane girder 12 to assemble the scaffolding 6, which is also suspended from the floating roof. As for the members, the floating roof 7 is assembled, welded, and inspected in the same manner as for the lining bottom plate 5.

そして、当該底板5、足場6、及び、浮屋根7
の組付、溶接、検査等の据付作業は図示する様に
コンクリート躯体2内部で行われるために上部の
施工に支障はない。
Then, the bottom plate 5, the scaffolding 6, and the floating roof 7
Installation work such as assembly, welding, inspection, etc. is carried out inside the concrete frame 2 as shown in the figure, so there is no problem with the construction of the upper part.

したがつて、これらの下部作業と同時に図示し
ないライニング側板の据付作業を行うようにすれ
ばタンク施工能率は著しく促進される。
Therefore, if the installation work of the lining side plate (not shown) is performed simultaneously with these lower part work, the efficiency of tank construction will be greatly improved.

而して、ライニング底板5、足場6、及び、浮
屋根7の据付完了時に併せてライニング側板の上
部据付がレール材10の近傍に来るようにすれ
ば、次段のライニング側板の添接に際してはレー
ル材10をスペーサー、スタツド材等のリブ材と
して利用し、上段への添接を続けることが出来、
又、その間使用済のクレーンガーダー12、クレ
ーンポスト11は前述した設立セツト作業の逆操
作によつて解体して吊り上げ、系外に搬出し次タ
ンクの施工に供するようにする。
Therefore, if the upper part of the lining side plate is installed near the rail material 10 when the installation of the lining bottom plate 5, scaffolding 6, and floating roof 7 is completed, it will be easier to attach the lining side plate in the next stage. The rail material 10 can be used as a rib material such as a spacer or stud material, and can be continued to be attached to the upper stage.
Meanwhile, the used crane girder 12 and crane post 11 are dismantled and lifted up by the reverse operation of the above-mentioned installation and setting work, and carried out of the system to be used for construction of the next tank.

そして、クレーンポスト11、及び、クレーン
ガーダー12の撤去後はクレーンポスト11の跡
はタンク底板の一部になるように溶接、検査を行
うが、その部分はタンク内中央部であるために各
種の作業は比較的容易に行える。
After the crane post 11 and crane girder 12 are removed, the remains of the crane post 11 are welded and inspected so that they become part of the tank bottom plate, but since that part is in the center of the tank, various The work is relatively easy.

尚、この発明における上述実施例は完全地下式
の地下タンクのものであるが、この発明は所謂地
盤に掘削部位が半地下式タンクにも適用可能であ
ることも勿論である。
Although the above-described embodiments of the present invention are for completely underground tanks, it goes without saying that the present invention can also be applied to semi-underground tanks where the portion is excavated into the ground.

〈発明の効果〉 以上、この発明によれば、浮屋根タンクの据付
に際し、コンクリート躯体の側壁内にレール材を
リング状に固設し、底板にクレーンポストを設立
してその上端とレール材との間にクレーンガーダ
ーを設けると共に、クレーンポストを中心に旋回
するようにしてクレーンガーダー上のクレーン台
車をクレーンガーダーに沿つて前後動させて吊り
込んだ部材をして組付、溶接、検査することによ
り、クレーンガーダーが底部を隈なくカバーし、
したがつて、ライニング底板や浮屋根の組立形成
が容易に行え、しかも、1本のクレーンポストと
1本のクレーンガーダーだけで大径のタンク底
板、浮屋根も支障なく形成出来る効果がある。
<Effects of the Invention> As described above, according to the present invention, when installing a floating roof tank, the rail material is fixed in a ring shape within the side wall of the concrete frame, a crane post is established on the bottom plate, and the upper end of the rail material is connected to the rail material. A crane girder is installed between the parts, and the crane cart on the crane girder is moved back and forth along the crane girder so as to rotate around the crane post, and the suspended parts are assembled, welded, and inspected. As a result, the crane girder covers the entire bottom area,
Therefore, it is easy to assemble and form a lining bottom plate and a floating roof, and moreover, a large diameter tank bottom plate and a floating roof can be formed without any trouble using only one crane post and one crane girder.

又、クレーンポストとクレーンガーダーをセツ
トするだけなので、従来のようにバランスクレー
ンやガイデリツクのようにセンタリングやバラン
ス調整をせずに済み、構造も極めて簡単にするこ
とが出来、したがつて、クレーン作業が簡単であ
るため、セツト、リセツト、解体が容易である上
に操作も楽で、製作も低コストで済む利点があ
る。
In addition, since you only need to set the crane post and crane girder, there is no need for centering or balance adjustment like in conventional balance cranes or guide trucks, and the structure is extremely simple, making crane work much easier. Since it is simple, it is easy to set up, reset, and disassemble, and has the advantage of being easy to operate and being manufactured at low cost.

更に、コンクリート躯体の側壁にリング状に固
設したレール材はライニング側壁の補強リブに用
いることが出来るメリツトがある。
Furthermore, the rail material fixed in a ring shape to the side wall of the concrete frame has the advantage that it can be used as a reinforcing rib for the lining side wall.

更に又、クレーンによつてライニング底板や浮
屋根の据付が行え、しかも、クレーンがクレーン
ポストとクレーンガーダーの逆L型枠を形成する
だけなので上方に於けるライニング側板の施工等
が容易に行えるため、タンク構築の能率が著しく
向上する利点がある。
Furthermore, the lining bottom plate and floating roof can be installed using a crane, and since the crane only forms an inverted L-shaped frame of the crane post and crane girder, it is easy to install the lining side plate above. , which has the advantage of significantly improving tank construction efficiency.

そして、クレーンガーダーをコンクリート躯体
の側壁に設けたレール材とクレーンポストとの間
に設けたために、所謂カンチレバー式にせずとも
良く、そのため相当重量の部材の吊り込みも可能
であり、その割にはクレーンポストやクレーンガ
ーダーの構造を軽量にすることが出来、したがつ
て、クレーンポストの吊り込みやクレーンガーダ
ーの設置もし易いという優れた効果が奏される。
In addition, since the crane girder is installed between the rail material installed on the side wall of the concrete frame and the crane post, there is no need to use the so-called cantilever type, and it is therefore possible to suspend quite heavy components. The structure of the crane post and crane girder can be made lightweight, and therefore the crane post can be easily hung and the crane girder can be easily installed, which is an excellent effect.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来技術に基づく浮屋根タンクの据付
工法の概略断面図、第2図はこの発明の1実施例
の全体概略縦断面図、第3図は第2図の平面図、
第4図は第2図部分拡大断面図である。 2……コンクリート躯体、3′……側壁、10
……レール材、11……クレーンポスト、12…
…クレーンガーダー、16……クレーン台車、5
……底板、7……浮屋根。
FIG. 1 is a schematic sectional view of a floating roof tank installation method based on the prior art, FIG. 2 is a general longitudinal sectional view of an embodiment of the present invention, and FIG. 3 is a plan view of FIG. 2.
FIG. 4 is a partially enlarged sectional view of FIG. 2. 2... Concrete frame, 3'... Side wall, 10
...Rail material, 11...Crane post, 12...
... Crane girder, 16 ... Crane trolley, 5
...Bottom plate, 7...Floating roof.

Claims (1)

【特許請求の範囲】[Claims] 1 浮屋根タンクの据付に際しコンクリート躯体
内にクレーンを設置し該クレーンにより部材を組
付け施工する据付方法において、上記躯体の側壁
内面にレール材をリング状に固設しておき、底板
中央にクレーンポストを設け、該クレーンポスト
と上記レール材との間に設けたクレーンガーダー
をして該クレーンポストを中心に旋回させ、該ク
レーンガーダーに設置したクレーン台車により部
材を組付け底板、浮屋根施工等を行うことを特徴
とする浮屋根タンク据付方法。
1. When installing a floating roof tank, in an installation method in which a crane is installed inside the concrete structure and parts are assembled using the crane, a ring-shaped rail material is fixed to the inner surface of the side wall of the structure, and a crane is installed in the center of the bottom plate. A post is provided, a crane girder is provided between the crane post and the above-mentioned rail material, and the crane girder is rotated around the crane post, and members are assembled using a crane dolly installed on the crane girder to construct a bottom plate, floating roof, etc. A floating roof tank installation method characterized by performing the following steps.
JP4717978A 1978-04-22 1978-04-22 Floating roof tank installation procedure Granted JPS54140211A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4717978A JPS54140211A (en) 1978-04-22 1978-04-22 Floating roof tank installation procedure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4717978A JPS54140211A (en) 1978-04-22 1978-04-22 Floating roof tank installation procedure

Publications (2)

Publication Number Publication Date
JPS54140211A JPS54140211A (en) 1979-10-31
JPS6145030B2 true JPS6145030B2 (en) 1986-10-06

Family

ID=12767844

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4717978A Granted JPS54140211A (en) 1978-04-22 1978-04-22 Floating roof tank installation procedure

Country Status (1)

Country Link
JP (1) JPS54140211A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58145951U (en) * 1982-03-27 1983-10-01 石川島播磨重工業株式会社 Equipment for construction and maintenance inspection of tanks in pits
JPS58178761A (en) * 1982-04-13 1983-10-19 川崎重工業株式会社 Construction of flat bottomed cylindrical tank having concrete side wall
JPS61282559A (en) * 1985-06-10 1986-12-12 三井建設株式会社 Crane apparatus for roof construction of tank

Also Published As

Publication number Publication date
JPS54140211A (en) 1979-10-31

Similar Documents

Publication Publication Date Title
CN107299643B (en) Steel lattice column combined type tower crane foundation structure in foundation pit and construction method
CN203271243U (en) Chimney titanium plate steel inner barrel reverse installation construction device of thermal power plant
CN206616184U (en) Coke oven loss flue dust dust gathering arrester supporting construction
CN114575589B (en) Construction method for electric hoist lifting formwork of steel reinforced concrete structural column
CN111675111A (en) Boiler hoisting sling in closed plant area and construction method
JP2008162749A (en) Jib crane
CN108396749B (en) Installation system and installation method of steel support in foundation pit
JPS6145030B2 (en)
CN210737607U (en) A hang braced system for reverse construction method beam slab construction
CN112249876A (en) Mounting platform and mounting method for large-tonnage precast tubular pile
CN110924723A (en) Construction method and hoisting device for earth-covered oil tank and using method
CN100366832C (en) Construction technique for hoisting steel made coal hopper on-site
JPH10195826A (en) Bridge construction method and device thereof
CN107268447A (en) A kind of overall peace is torn open connects high operation platform built in formula radial pattern colyliform steel pile casting
CN201128882Y (en) Lifting and supporting brackets integrated construction device for bridge arch rib
CN207227959U (en) Overall peace is torn open connects high construction platform built in formula radial pattern colyliform steel pile casting
JP2668237B2 (en) Core leading construction method
CN210457249U (en) Electric pole holding structure with self-jacking machine body
CN205990200U (en) 360 ° of luffing independent hoist device
CN216583900U (en) All-directional rotary small crane
JP2942879B2 (en) Temporary house for all-weather construction
JPH09110379A (en) Crane
JP3869962B2 (en) Vertical furnace inner wall refractory dismantling apparatus and dismantling method
CN212024599U (en) Column cantilever crane convenient to transportation
JPH07158300A (en) Method for installing vertical type vessel