JPS6135331B2 - - Google Patents
Info
- Publication number
- JPS6135331B2 JPS6135331B2 JP60074870A JP7487085A JPS6135331B2 JP S6135331 B2 JPS6135331 B2 JP S6135331B2 JP 60074870 A JP60074870 A JP 60074870A JP 7487085 A JP7487085 A JP 7487085A JP S6135331 B2 JPS6135331 B2 JP S6135331B2
- Authority
- JP
- Japan
- Prior art keywords
- formwork
- shoring
- hanging
- earth retaining
- constructed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000009415 formwork Methods 0.000 claims description 51
- 238000010276 construction Methods 0.000 claims description 12
- 238000000034 method Methods 0.000 claims description 10
- 229910000831 Steel Inorganic materials 0.000 description 20
- 239000010959 steel Substances 0.000 description 20
- 239000000463 material Substances 0.000 description 13
- 238000009412 basement excavation Methods 0.000 description 7
- 239000000725 suspension Substances 0.000 description 5
- 230000014759 maintenance of location Effects 0.000 description 4
- 239000011120 plywood Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000005096 rolling process Methods 0.000 description 1
- 238000007493 shaping process Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【発明の詳細な説明】
本発明は、堅坑やシヤフト等の地下構築物を地
中深くに築造する場合のコンクリート土留支保工
の施工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for concrete earth retaining shoring when underground structures such as shafts and shafts are constructed deep underground.
例えば、連続地中壁等でかかる堅坑やシヤフト
等の躯体壁を先行して施工し、この中を順次掘削
しながら該躯体壁の内側に沿つて土留支保工とな
るRC構築物を複数段構築していく場合、従来地
盤をもつて型枠支保工としていた。 For example, a continuous underground wall, etc., is constructed in advance to construct the main body wall of a shaft or shaft, and while excavating the inside of this structure one after another, multiple stages of RC structures are constructed to serve as earth retention shoring along the inside of the main body wall. In the past, the ground was used as formwork support.
すなわち、前記RC構築物の下端予定線まで地
山を掘削し、整形した後にその地盤上に型枠を組
むものである。 That is, the ground is excavated to the planned lower end line of the RC structure, and after shaping, a formwork is constructed on the ground.
従つて各段の掘削下端で、床付掘削、整地、均
しコンクリート(あるいは捨型枠)等の作業が必
要となり、また、地盤上の型枠内にコンクリート
を打設し、これが所定の強度に達するまでの養生
期間を経なければ次の掘削工程に移行することが
できず、その間作業が休止し非常に能率の悪いも
のであつた。これに対し、逆巻工法では順次上か
らコンクリートを打設するようにして型枠も上か
ら吊るタイプのものがある(特開昭57−19420
号)。これによればコンクリート打設後、養生期
間をまたずに型枠の下部をすぐに掘削でき、上記
不都合を解消できる。しかし、これは上下に一体
連続する躯体の上方にその支持を求めるものであ
〓〓〓〓
るから、上から一連に吊下げるもので、躯体の進
行にともなつて吊下部材が長くなり、その結果工
事が進行するにしたがい部材が多くなり取扱いが
面倒になるという不都合がある。 Therefore, at the bottom of each level of excavation, work such as floor excavation, land leveling, leveling concrete (or dumping formwork), etc. is required, and concrete is poured into formwork above the ground to achieve the specified strength. It is not possible to move on to the next excavation process until a curing period has passed, and during this period the work is suspended, resulting in extremely low efficiency. On the other hand, there is a type of reverse-rolling method in which concrete is poured sequentially from above and the formwork is also suspended from above (Japanese Patent Application Laid-Open No. 57-19420
issue). According to this, the lower part of the formwork can be excavated immediately after concrete is poured without passing through the curing period, and the above-mentioned inconvenience can be solved. However, this requires support from above the frame, which is continuous vertically.
Therefore, the hanging members are suspended from above in a series, and as the construction progresses, the length of the hanging members increases.As a result, as the construction progresses, the number of members increases, making handling difficult.
本発明の目的は、上記従来例の不都合を解消
し、作業工程を簡略化できるとともに、次工程へ
の移行に休止期間を置かずにすむのみならず、型
枠の吊下位置を順次下方へと盛り替えることで吊
下部材も必要最少限のもので足り取扱いも容易で
作業能率を上げることができる。地下構築物にお
けるコンクリート土留支保工の施工法及び装置を
提供することにある。 The purpose of the present invention is to eliminate the above-mentioned disadvantages of the conventional example, simplify the work process, eliminate the need for a pause period when moving to the next process, and also move the hanging position of the formwork downward in sequence. By changing the structure, the number of hanging members can be kept to a minimum, and handling is easy and work efficiency can be increased. An object of the present invention is to provide a method and device for constructing concrete earth retaining shoring for underground structures.
しかして、この目的は本発明によれば、先に施
工済みの上位コンクリート土留支保工から底及び
側壁部分の型枠を吊り下げ、該型枠を用いて下位
のコンクリート土留支保工を施工し、このように
順次型枠の吊り下げ位置を下位のコンクリート土
留支保工に盛り替えて、更に下位のコンクリート
土留支保工を施工することにより達成される。 According to the present invention, this purpose is to suspend the formwork of the bottom and side wall portions from the upper concrete earth retaining shoring that has already been constructed, and to construct the lower concrete earth retaining shoring using the formwork. This is achieved by sequentially changing the hanging position of the formwork to the lower concrete earth retaining shoring and then constructing the lower concrete earth retaining shoring.
以下、図面について本発明の実施例を詳細に説
明する。 Embodiments of the present invention will be described in detail below with reference to the drawings.
第1図は本発明の第1実施例を示す一部切欠い
た平面図、第2図は同上縦断側面図で、まず本発
明方法で用いる装置から説明する。 FIG. 1 is a partially cutaway plan view showing a first embodiment of the present invention, and FIG. 2 is a longitudinal sectional side view of the same. First, the apparatus used in the method of the present invention will be explained.
図中1はネジ鋼材からなる吊鋼材で、該吊鋼材
の上端に昇降及び掛止手段としてのナツト2を螺
合し、下端は吊支材3の下面にナツト4で固定す
る。 In the figure, reference numeral 1 denotes a hanging steel member made of threaded steel. A nut 2 serving as lifting and hanging means is screwed into the upper end of the hanging steel member, and the lower end is fixed to the lower surface of the hanging support member 3 with a nut 4.
吊支材3の上部にチヤンネル材からなる荷重受
け材6を介して鋼製の底型枠7をボルト絞め又は
溶接等で固定して載置し、さらにこの底型枠7の
一側端に側型枠8の下端をピン等で多少回動自在
に結合する。 A steel bottom form 7 is placed on the top of the suspension support 3 via a load receiving material 6 made of channel material, fixed by bolting or welding, and furthermore, one side end of this bottom form 7 is placed. The lower end of the side formwork 8 is connected with a pin or the like so that it can rotate to some extent.
これらは吊支材3、底型枠7及び側型枠8の全
体平面形状は、当然施工すべきコンクリート土留
支保工の平面形状に合致すべきものであり、図面
の例では躯体壁13が八角形、該支保工の内側面
を円形としたので吊支材3及び底型枠7は外側八
角形で内側円形に、側型枠8は円形に形成した。 The overall planar shape of the hanging supports 3, bottom formwork 7, and side formwork 8 should naturally match the planar shape of the concrete earth retaining structure to be constructed, and in the example of the drawing, the frame wall 13 is octagonal. Since the inner surface of the support was circular, the hanging support 3 and the bottom form 7 were octagonal on the outside and circular on the inside, and the side form 8 was formed in a circle.
なお、これらはすべて適宜数の分割体の集合で
構成される。 Note that all of these are composed of a set of an appropriate number of division bodies.
また、側型枠8の上部内側面にこの側型枠8を
垂直に立設した状態に固定するたが材であるセン
トル櫛形9を配設する。 Further, a center comb shape 9, which is a hoop material, is provided on the inner surface of the upper part of the side formwork 8 to fix the side formwork 8 in a vertically erected state.
一方、吊支材3と一体に矩形の吊枠10を設
け、該吊枠10に形成した吊穴10aを側型枠8
よりも内側に突設する。 On the other hand, a rectangular hanging frame 10 is provided integrally with the hanging support 3, and the hanging holes 10a formed in the hanging frame 10 are inserted into the side formwork 8.
protrudes inward from the
その他、吊鋼材1に被覆するスリーブ管11や
必要に応じてナツト2,4に併用する座金等を準
備し、また底型枠7の外側に補助型枠12を接続
する。 In addition, a sleeve pipe 11 to cover the hanging steel material 1 and washers to be used together with the nuts 2 and 4 as necessary are prepared, and an auxiliary formwork 12 is connected to the outside of the bottom formwork 7.
次に、前記装置を用いて行なう本発明方法につ
いて説明する。 Next, the method of the present invention performed using the above-mentioned apparatus will be explained.
例えば連続地中壁等の施工法で土留壁としての
躯体壁13が先行して築造され、この躯体壁13
の内側に沿つてコンクリート土留支保工14,1
5がすでに形成されており、支保工15の下方に
支保工16を形成しようとする。 For example, by a construction method such as a continuous underground wall, the frame wall 13 as an earth retaining wall is constructed in advance, and this frame wall 13
Concrete earth shoring along the inside of 14,1
5 has already been formed, and a shoring 16 is to be formed below the shoring 15.
まず、支保工15の直下から支保工16の直下
まで躯体壁13内の地盤18を掘削する。 First, the ground 18 within the frame wall 13 is excavated from directly below the support 15 to directly below the support 16.
支保工14,15に埋設したスリーブ管11で
形成する貫通孔を介して吊鋼材1を垂下し、支保
工14の上面に突出する吊鋼材1の上端にナツト
2を螺合して掛止する。 The hanging steel 1 is suspended through the through hole formed by the sleeve pipe 11 buried in the shoring 14, 15, and the nut 2 is screwed onto the upper end of the hanging steel 1 protruding from the upper surface of the shoring 14 to hang it. .
吊鋼材1の下端には前記吊支材3、底型枠7、
側型枠8、補助型枠12等をナツト4を介して吊
り下げ、型枠内に鉄筋を組立てコンクリートを打
設して支保工16を築造する。その際吊鋼材1の
周囲にスリーブ管11をセツトしておく。 At the lower end of the hanging steel material 1, the hanging support material 3, the bottom formwork 7,
The side formwork 8, auxiliary formwork 12, etc. are suspended via nuts 4, reinforcing bars are assembled inside the formwork, and concrete is poured to construct the shoring 16. At this time, a sleeve pipe 11 is set around the hanging steel member 1.
なお、補助型枠12は躯体壁13と底型枠7と
の隙間を埋めればよく、合板ベニア等の簡便な材
料を用いて一側を底型枠7に止めておく。 The auxiliary formwork 12 only needs to fill the gap between the frame wall 13 and the bottom formwork 7, and is fixed to the bottom formwork 7 on one side using a simple material such as plywood veneer.
このように支保工16を築造したならば、次い
で第3図に示すように、次に施工すべき支保工1
7の直下まで地盤18を掘り下げる。この掘削作
業は、支保工16のコンクリート養生期間を待た
ずにすぐ行なうことができる。 After constructing the shoring 16 in this way, as shown in Fig. 3, the next shoring 1 to be constructed is
Dig the ground 18 to just below point 7. This excavation work can be performed immediately without waiting for the concrete curing period of the shoring 16.
該養生期間経過後、セントル櫛形9をゆるめて
側型枠8を内側に多少傾斜させ、支保工14上の
ナツト2をゆるめてゆくと、吊鋼材1は下降し底
型枠7及び側型枠8は支保工16から脱型され
る。 After the curing period has passed, the center comb 9 is loosened to make the side formwork 8 incline a little inward, and the nuts 2 on the shoring 14 are loosened, the hanging steel 1 is lowered and the bottom formwork 7 and the side formwork are loosened. 8 is demolded from the shoring 16.
一方、別途クレーン等で吊枠10の吊穴10a
をワイヤー吊りして脱型した型枠を中空で保持
し、ナツト2を吊鋼材1から外し、次の支保工1
7の施工位置まで型枠を下げる。 On the other hand, using a crane or the like, the hanging hole 10a of the hanging frame 10 is
Hold the demolded formwork in the air by suspending it with a wire, remove the nuts 2 from the hanging steel 1, and install the next shoring 1.
Lower the formwork to the construction position in step 7.
この状態では、吊鋼材1の上端は支保工14を
抜け出て支保工15の上面まで下がるので、これ
〓〓〓〓
にナツト2を螺合し、かつ吊枠10のワイヤー吊
りを解除すれば、吊支材3上の底型枠7、側型枠
8は、今度は支保工15で吊持されることにな
る。 In this state, the upper end of the hanging steel member 1 passes through the support 14 and descends to the top surface of the support 15, so this
If the nuts 2 are screwed together and the wire suspension of the hanging frame 10 is released, the bottom form 7 and side form 8 on the hanging support 3 will now be suspended by the support 15. .
以後、同様にして順次下位の支保工を施工して
ゆく。なお、型枠を直上の支保工で吊らずに、少
なくとも2段上位の支保工で吊持させたのは、コ
ンクリート打設後の養生による手持ちを防ぐため
であるが、必ずしもこれに限定されるものではな
い。 Thereafter, lower-level shoring will be constructed in the same manner. Note that the reason why the formwork was not suspended from the support directly above it, but from support at least two levels above, was to prevent the formwork from being held up due to curing after concrete was poured, but this is not necessarily the case. It's not a thing.
第4図は、本発明の第2実施例を示す縦断側面
図で、図示の例は直上の支保工で型枠を吊り下げ
る場合を示す。この場合、スリーブ管11は少な
くともナツト2よりも太径とし、また吊鋼材1の
中間には中間部固定ナツト2′を螺合しておき、
更にナツト2,2′には第5図に示すように切欠
き19aを有し吊鋼材1の側部からセツト可能な
アンカー座金19を使用する。 FIG. 4 is a longitudinal sectional side view showing a second embodiment of the present invention, and the illustrated example shows the case where the formwork is suspended from the shoring directly above. In this case, the sleeve pipe 11 has at least a larger diameter than the nut 2, and an intermediate fixing nut 2' is screwed into the middle of the hanging steel member 1.
Furthermore, an anchor washer 19 having a notch 19a and which can be set from the side of the hanging steel member 1 as shown in FIG. 5 is used for the nuts 2, 2'.
本実施例においては、セントル櫛形9及び側型
枠8をゆるめた後に、予め吊鋼材1にセツトして
おいた中間固定ナツト2′を支保工16の天端ま
で下げ、この支保工16の天端とナツト2′の間
に前記アンカー座金19を挿入する。支保工15
上のナツト2をゆるめてアンカー座金19を外せ
ば吊鋼材1の吊支点は支保工15から16へ移り
変わる。 In this embodiment, after loosening the center comb 9 and the side formwork 8, the intermediate fixing nuts 2', which had been set in advance on the hanging steel 1, are lowered to the top of the shoring 16. Insert the anchor washer 19 between the end and the nut 2'. Shoring 15
When the upper nut 2 is loosened and the anchor washer 19 is removed, the suspension fulcrum of the hanging steel member 1 is shifted from the support 15 to the support 16.
次いでナツト2′をゆるめ、漸次吊支材3、底
型枠7、側型枠8等を下げてゆき、型枠全体が適
切な所まで下げられたら、吊枠10を用いて一時
中間吊りしナツト2′をスリーブ管11内に挿入
する。 Next, loosen the nuts 2' and gradually lower the suspension supports 3, bottom formwork 7, side formwork 8, etc. Once the entire formwork has been lowered to an appropriate position, temporarily suspend it using the hanging frame 10. Insert the nut 2' into the sleeve tube 11.
同時に、上部のナツト2をこの位置まで下げて
きて支保工16の天端に固定する。更に該ナツト
2を回動して型枠全体を次位の支保工17の築造
位置にセツトする。他の方法は前記第2図、第3
図で示した第1実施例と同じである。 At the same time, lower the upper nut 2 to this position and fix it to the top of the shoring 16. Further, the nut 2 is rotated to set the entire formwork to the construction position of the next supporting structure 17. Other methods are shown in Figures 2 and 3 above.
This is the same as the first embodiment shown in the figure.
この第2実施例を用いた場合、第1実施例と比
べて吊枠10を用いて中間吊り期間は短かくな
り、また吊鋼材1の盛り変え作業も楽に行なうこ
とができる。 When this second embodiment is used, compared to the first embodiment, the intermediate hanging period is shortened by using the hanging frame 10, and the work of changing the hanging steel material 1 can be carried out easily.
さらに、型枠全体が大型で重量があり吊枠10
を用いて中間吊りができない場合も考えられる。 Furthermore, the entire formwork is large and heavy, and the hanging frame 10
There may be cases where it is not possible to carry out intermediate suspension using .
この場合は、吊鋼材1の中間部にカツプラーを
設けこの部分で一時吊鋼材1を切りここに前記第
2実施例での中間ナツト2′を挿入して盛り変え
てゆくようにすればよい。 In this case, a coupler may be provided in the middle of the hanging steel material 1, and the hanging steel material 1 may be temporarily cut at this portion and the intermediate nut 2' of the second embodiment may be inserted therein to reposition it.
以上述べたように本発明は、躯体壁を先行して
施工し、この躯体壁内を順次掘削しながらコンク
リート土留支保工を複数段築造してゆく地下構築
物施工法において、先に施工済みの上位コンクリ
ート土留支保工から底及び側壁部分の型枠を吊り
下げ、該型枠を用いて下位のコンクリート土留支
保工を施工し、このように順次型枠の吊り下げ位
置を下位のコンクリート土留支保工に盛り替えて
更に下位のコンクリート土留支保工を施工するこ
ととしたので、従来のごとく地盤を直接型枠支保
工として利用する場合と異なり、当該コンクリー
ト土留支保工を施工後コンクリート養生期間を待
たずにすぐ掘削を行なうことができ効率的に作業
を進めることができるのみならず、吊下部材も短
いもので足り、しかもその長さは土留支保工の施
工位置が順次下位に移行しても長くなることはな
いから、取扱いが簡単で施工能率を上げることが
できる。 As described above, the present invention is an underground structure construction method in which a frame wall is constructed first, and concrete earth retaining shoring is constructed in multiple stages while sequentially excavating the inside of the frame wall. Hang the formwork for the bottom and side walls from the concrete earth retention shoring, use the formwork to construct the lower concrete earth retention shoring, and in this way, sequentially change the hanging position of the formwork to the lower concrete earth retention shoring. Since we decided to relocate the concrete earth retaining shoring and construct the lower level concrete earth retaining shoring, unlike the conventional case where the ground is directly used as formwork shoring, the concrete earth retaining shoring can be installed without waiting for the concrete curing period after construction. Not only can excavation be carried out immediately and work can be carried out efficiently, but only short hanging members are required, and the length will remain long even if the construction position of the earth retaining shoring is moved to a lower level. Since there is no problem, handling is easy and construction efficiency can be increased.
また、コンクリート土留支保工各段の掘削下端
での床付掘削、敷地、均しコンクリートあるいは
捨型枠等の作業が不要となり少ない工程数で簡単
に施工することができるものである。 In addition, the work such as floor excavation, site leveling, leveling concrete, or waste form work at the lower end of the excavation of each stage of concrete earth retaining shoring is unnecessary, and construction can be easily performed with a small number of steps.
第1図は本発明の実施例を示す一部切欠いた平
面図、第2図は同上縦断側面図、第3図は第2図
の次工程を示す縦断側面図、第4図は本発明の第
2実施例を示す縦断側面図、第5図はナツト部分
の平面図である。
1……吊鋼材、2,2′,4……ナツト、3…
…吊支材、6……荷重受け材、7……底型枠、8
……側型枠、9……セントル櫛形、10……吊
枠、10a……吊穴、11……スリーブ管、12
……補助型枠、13……躯体壁、14,15,1
6,17……コンクリート土留支保工、19……
アンカー座金、19a……切欠き。
〓〓〓〓
Fig. 1 is a partially cutaway plan view showing an embodiment of the present invention, Fig. 2 is a longitudinal sectional side view of the same, Fig. 3 is a longitudinal sectional side view showing the next step after Fig. 2, and Fig. 4 is a partially cutaway plan view showing an embodiment of the present invention. A vertical side view showing the second embodiment, and FIG. 5 is a plan view of the nut portion. 1... Hanging steel material, 2, 2', 4... Nut, 3...
... Hanging support material, 6 ... Load receiving material, 7 ... Bottom formwork, 8
... Side formwork, 9 ... Center comb shape, 10 ... Hanging frame, 10a ... Hanging hole, 11 ... Sleeve pipe, 12
...Auxiliary formwork, 13...Structure wall, 14, 15, 1
6,17... Concrete earth retaining shoring, 19...
Anchor washer, 19a...notch. 〓〓〓〓
Claims (1)
次掘削しながらコンクリート土留支保工を複数段
築造してゆく地下構築物施工法において、先に施
工済みの上位コンクリート土留支保工から底及び
側壁部分の型枠を吊り下げ、該型枠を用いて下位
のコンクリート土留支保工を施工し、このように
順次型枠の吊り下げ位置を下位のコンクリート土
留支保工に盛り替えて更に下位のコンクリート土
留支保工を施工することを特徴とする地下構築物
におけるコンクリート土留支保工の施工法。 2 型枠吊り下げを行なう土留支保工は施工すべ
き土留支保工の少なくとも2段上位の支保工であ
る特許請求の範囲第1項記載の地下構築物におけ
るコンクリート土留支保工の施工法。[Claims] 1. In an underground structure construction method in which a frame wall is constructed first, and multiple stages of concrete earth retaining are constructed while excavating the inside of the frame wall one after another, the upper concrete earth retaining which has already been constructed is The formwork for the bottom and side walls is suspended from the shoring, and the lower concrete earth retaining shoring is constructed using the formwork, and in this way, the hanging position of the formwork is sequentially transferred to the lower concrete earth retaining shoring. A method for constructing concrete earth retaining shoring in an underground structure, characterized by constructing a lower level concrete earth retaining shoring. 2. The method for constructing concrete earth retaining shoring in an underground structure according to claim 1, wherein the earth retaining shoring for suspending the formwork is at least two steps higher than the earth retaining shoring to be constructed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60074870A JPS60226918A (en) | 1985-04-08 | 1985-04-08 | Construction of timbering for concrete of underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60074870A JPS60226918A (en) | 1985-04-08 | 1985-04-08 | Construction of timbering for concrete of underground structure |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP57104791A Division JPS58222218A (en) | 1982-06-18 | 1982-06-18 | Method and apparatus for concrete sheathing and timbering work in underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS60226918A JPS60226918A (en) | 1985-11-12 |
JPS6135331B2 true JPS6135331B2 (en) | 1986-08-12 |
Family
ID=13559794
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP60074870A Granted JPS60226918A (en) | 1985-04-08 | 1985-04-08 | Construction of timbering for concrete of underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS60226918A (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4964032B2 (en) * | 2007-06-14 | 2012-06-27 | 鹿島建設株式会社 | Side wall and method for constructing side wall |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS555359A (en) * | 1978-06-27 | 1980-01-16 | Kawasaki Heavy Ind Ltd | Fabricating of side wall of underground tank |
JPS5719420A (en) * | 1980-07-05 | 1982-02-01 | Shimizu Constr Co Ltd | Installing process of timbering in counter lining process |
-
1985
- 1985-04-08 JP JP60074870A patent/JPS60226918A/en active Granted
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS555359A (en) * | 1978-06-27 | 1980-01-16 | Kawasaki Heavy Ind Ltd | Fabricating of side wall of underground tank |
JPS5719420A (en) * | 1980-07-05 | 1982-02-01 | Shimizu Constr Co Ltd | Installing process of timbering in counter lining process |
Also Published As
Publication number | Publication date |
---|---|
JPS60226918A (en) | 1985-11-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS6135331B2 (en) | ||
JPS6134533B2 (en) | ||
US6748717B2 (en) | Method and system for emplacing prefabricated buildings | |
JP2001241287A (en) | Construction method of shaft, assembly method of structural body used for construction method, and assembly device used for assembly method | |
JPH0140178B2 (en) | ||
JP3809618B2 (en) | Foundation pile and construction method of foundation pile | |
JPH01131723A (en) | Method of holding sidewall of deep excaveted hole | |
JPS63277341A (en) | Reverse execution of underground story | |
JP2996113B2 (en) | How to build a shaft | |
SU977176A1 (en) | Apparatus for installing underground reinforced concrete vessels | |
JP2772397B2 (en) | Underground building construction method | |
JPS63312437A (en) | Construction of underground structure | |
JPH116147A (en) | Constructing method for pile group, structure of pile group and pile holding device | |
JPS5911015B2 (en) | How to install shoring in the reverse winding method | |
JPH0762898A (en) | Reinforcing method for existing tank | |
JPH0343520A (en) | Method of setting bottom die frame in reverse winding process | |
KR960002379B1 (en) | A form-less style working method and a structure apparatus for underground constructions | |
JPH0460018A (en) | Retaining wall and constructing method thereof | |
JP2024017251A (en) | Method for erecting reinforcing bar cage | |
JPS5921831A (en) | Reverse placement work | |
JPH03132521A (en) | Strut construction method of basement floor excavation work | |
JPH07122272B2 (en) | Construction method for walls and retaining walls | |
JPS6121277A (en) | Building of underground tank | |
JPH09310442A (en) | Roof structure | |
JP2001248171A (en) | Caisson method for constructing basement and level adjusting device |