JPS6131510A - Construction of cable of suspension bridge - Google Patents

Construction of cable of suspension bridge

Info

Publication number
JPS6131510A
JPS6131510A JP15212684A JP15212684A JPS6131510A JP S6131510 A JPS6131510 A JP S6131510A JP 15212684 A JP15212684 A JP 15212684A JP 15212684 A JP15212684 A JP 15212684A JP S6131510 A JPS6131510 A JP S6131510A
Authority
JP
Japan
Prior art keywords
strand
small diameter
suspension bridge
pull
strands
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15212684A
Other languages
Japanese (ja)
Inventor
良文 坂本
俵矢 与文
武野 優
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Nippon Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Steel Corp filed Critical Nippon Steel Corp
Priority to JP15212684A priority Critical patent/JPS6131510A/en
Publication of JPS6131510A publication Critical patent/JPS6131510A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、吊橋ケーブルの架設方法に関するものである
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method for constructing suspension bridge cables.

〔従来技術〕[Prior art]

従来、吊橋ケーブル架設方法としては、工場で約100
本の素線を集束すると共に端部にソケットに取付けて所
定長さのストランドを構成し、これを専用リールに巻取
って現場捷で輸送した後、アンリーラ−にセットしてリ
ールから巻戻しながらストランド金吊足場の床上のロー
ラー上に引出すP−W−8(パラレル・ワイヤ・ストラ
ンド)工法と、現場に素線コイルを運、搬し、この索引
をスピニングホイールと呼ぶ直径約1mの移動するホイ
ールに架け、このスピニングホイールでケーブルを定着
する両岸のアンカーの一万側から他方側に素線を移動さ
せて運び、この作業を繰り返すことによって約500本
の素線を架設し、これを束ねて、太径ストランドを形成
するA−8(エアー・スピニング)工法とが知られてい
る。
Conventionally, the suspension bridge cable construction method was about 100
The main wires are bundled together and attached to sockets at the ends to form a strand of a predetermined length, which is then wound onto a special reel and transported to the site, then set on an unreeler and unwound from the reel. The P-W-8 (parallel wire strand) method involves pulling out strands onto rollers on the floor of the scaffolding, and transporting the bare wire coils to the site using a spinning wheel with a diameter of approximately 1 m. The cables are hung on wheels, and the spinning wheels are used to move the wires from one side of the anchors on both banks to the other, and by repeating this process, approximately 500 wires are erected. The A-8 (air spinning) method is known, in which strands are bundled to form large diameter strands.

しかしながら、上述の従来工法には、それぞれ次の欠点
がある。
However, each of the above-mentioned conventional construction methods has the following drawbacks.

p −w −S工法では、ストランドの引出し完了後に
、ストランド1本毎に仮引、移設作業を行ない、各サド
ル部で四角形に整形するため、吊橋の長さが4000m
にも及ぶ超長大吊橋では、仮引。
In the p-w-S method, after the strands are pulled out, each strand is temporarily pulled and relocated, and each saddle is shaped into a square shape, so the length of the suspension bridge is 4000 m.
The extremely long suspension bridge is temporarily closed.

移設時のフリーハング張カ、仮引ストロークが太きくな
り、さらにサドル溝長さも長くなるためストランド整形
作業時間が長くなる。このためストランド1本毎りの仮
引、移設、整形に要する作業時間が約4時間にもなり、
1日の稼動時間を8日時間とすると半日もこれらの作業
に費されてしまいp−w、S工法の大きなりリティヵル
作業となる。
The free-hang tension and temporary pulling stroke during relocation become thicker, and the length of the saddle groove also becomes longer, resulting in longer strand shaping work. For this reason, the work time required for temporary pulling, relocation, and shaping of each strand was approximately 4 hours.
If the operating time per day is 8 days, half a day will be spent on these tasks, resulting in a large amount of critical work for the PW and S construction methods.

したがってストランド引出し時間の短縮すなわち引出し
速度の向上がサイクルタイム、工程の短縮化にはつなが
らないといつ長尺ストランド架設の場合に顕著な工期上
の欠点がある。
Therefore, unless shortening the strand drawing time, that is, improving the drawing speed, does not lead to shortening the cycle time and process, there will be a noticeable drawback in terms of construction period when constructing long strands.

一方、品質面では、ストランド長さが4000mにも及
ぶとリールに巻取る時、リールから巻戻す時に生ずるス
トランドのたるみ、うねり、サドル部近傍でのバードケ
ージ等による品質の低下が起りうる。
On the other hand, in terms of quality, if the strand length is as long as 4000 m, the quality may deteriorate due to sag, waviness, and birdcage in the vicinity of the saddle that occur when the strand is wound onto a reel or unwound from the reel.

さらに、引出し方法がトラムウェイ式であり、ホーリン
グロープ、キャリアーは吊足場の床上を約4mの高い位
置で走行するので、ホーリングロープの振動、緩みなど
にょる脱索、キャリアーの風に対する不安定さなどの危
険性がある。
Furthermore, the pulling out method is a tramway type, and the hauling rope and carrier run at a height of approximately 4 m above the floor of the suspended scaffold, so there is a risk of the hauling rope coming off due to vibration or loosening, and instability of the carrier due to wind. There are risks such as

次に、A 、 S工法では、スピニングホイールの走行
速度を最大約240 m7分にすることができ、p 、
 w 、 S工法の約6〜8倍の高速化が可能であるに
もかかわらず、素線単位で架設するために単位ンステム
尚りの施工速度が遅く、風による稼動率の低下も大きく
、さらに安全性も低下する。
Next, in the A, S construction method, the running speed of the spinning wheel can be increased to a maximum of approximately 240 m7 minutes, and the p,
Although it is possible to speed up the construction by approximately 6 to 8 times using the S construction method, the construction speed per unit of stem is slow because the construction is carried out in units of strands, and the operating rate is greatly reduced by wind. Safety also decreases.

〔発明の目的、構成〕[Purpose and structure of the invention]

本発明は上述の従来工法の欠点を完全に克服する工法で
あって、大巾な工期短縮、ストランド品質の向上、高い
安全性などを目的とするものでおり、この発明の要旨と
するところは、吊橋を架設すべき両岸のアンカレッジ1
間に吊足場2を架設し、ストランド引出移設装置6を前
記吊足場2の床上に設置した軌条4によりガイドして駆
動装置等により往復走行させながら、両岸のアンカレッ
ジ1の後方に設置した素線集束装置5により多数本の素
線を現場集束すると共にシージングしなから細径ストラ
ンドを形成し、前記ストランド引出移設装置乙により、
一方の岸から細径ストランドを吊足場上の引出しローラ
6上に引出すと同時に、他方の岸から既に引出されてい
る細径ストランドをケーブルフオーマー7内に自動的に
移設する工程を必要匠数繰り返し、次に移設完了した各
細径ストランドを束ねて太径ストランド8を形成したの
ち、その太径ストランド8の両端にソケット9を取付け
て引込み定着を行なうことを特徴とする吊橋ケーブルの
架設方法にある。
The present invention is a construction method that completely overcomes the drawbacks of the conventional construction method described above, and aims to significantly shorten the construction period, improve strand quality, and provide high safety.The gist of this invention is , Anchorage 1 on both banks where suspension bridges should be constructed
A suspended scaffold 2 was erected in between, and a strand pull-out relocation device 6 was guided by a rail 4 installed on the floor of the suspended scaffold 2 and moved back and forth by a drive device, etc., and was installed behind the anchorage 1 on both banks. A large number of strands are gathered on-site by the strand concentrator 5 and are sheathed to form a small-diameter strand, and the strand pull-out transfer device B
The number of required steps is to pull out a small diameter strand from one bank onto the pull-out roller 6 on the suspended scaffold, and at the same time automatically transfer the small diameter strand that has already been pulled out from the other bank into the cable former 7. This method of constructing a suspension bridge cable is characterized by repeatedly bundling the small diameter strands that have been transferred to form a large diameter strand 8, and then attaching sockets 9 to both ends of the large diameter strand 8 to pull in and fix it. It is in.

〔実施例〕〔Example〕

次にこの発明全図示の例によって詳細に説明する。 Next, the invention will be explained in detail using fully illustrated examples.

第1図ないし第6図にこの発明を1本の吊橋ケーブルの
架設に実施した例を示すものであって、この発明ケ実施
して吊橋ケーブルを架設する場合ば、まず1本当りのケ
ーブルについてP−w・S工法におけるコストランド当
りの素線数の約半分程の個数のヌイ71−10を両岸の
アンカレッジ1の後部に設置したのち、そのスイットの
数と同数の素線コイルを両岸でスイット1oにセットし
、かつ両岸のスイット1oの前方において素線集束装置
5およびシージング装置11を設置する。
Figures 1 to 6 show examples in which the present invention is applied to the construction of a single suspension bridge cable. After installing Nui 71-10, which is about half the number of strands per cost land in the P-w S construction method, at the rear of Anchorage 1 on both banks, the same number of strand coils as the number of switches are installed. The wire convergence device 5 and the sheathing device 11 are set in the switches 1o on both banks, and in front of the switches 1o on both banks.

次に両岸においてスイット1oがら繰り出される素線1
2を素線集束装置5により現場集束して細径ストランド
1ろを構成し、次いでその細径ストランド16を7−ジ
ンク装置11により所要ピッチでシージングする。
Next, the wire 1 is let out from the switch 1o on both banks.
The thin strands 16 are sheathed at a required pitch using the 7-zinc device 11.

次に前記細径ストランド16の先端を、引出し作業と移
動作業とを同時に行なえる装置である引出移設装置(ラ
ソセラー)3(・て接続し、その引出移設装置6を吊足
場2の床上に取付けた軌条4によりガイドしながら走行
させると共に、その走行に追従して、前記現場集束、シ
ー/フグを行ないながら、細径ストランド16を吊足場
2.の床上に設置されている引出しローラ6上に所要張
力で引出していく。
Next, the tip of the small diameter strand 16 is connected to a drawer relocation device (rasoceller) 3 (a device that can perform drawer work and moving work at the same time), and the drawer relocation device 6 is attached to the floor of the suspended scaffold 2. The small-diameter strand 16 is moved onto the pull-out roller 6 installed on the floor of the suspended scaffold 2. Pull it out with the required tension.

最初の細径ストランドを、片岸から上述の一連作業によ
り対岸まで引出し終了した後、この細径ストランドの先
端を引出移設装置6から外すと共に、第2の細径ストラ
ンドの先端を引出移設装置6に接続し、その引出移設装
置6を逆方向に走行させることにより、現場集束、ンー
ジングを行ないながら、この第2の細径ストランドを吊
足場2の床上の引出しローラ6上に所要張力で引出して
いくと同時に、既に引出し完了済みの最初の細径ストラ
ンドを、引出移設装置乙における複数の傾斜ガイドンー
プ14,15によりガイドして、引出しローラ6からケ
ーブルフォーマ−7内に自動的に移設していく。ここで
、引出移設装置6における複数の傾斜ガイドシーブ14
.15は走行方向によシ傾斜力向およびガイドする方向
を変えることができる。傾斜ガイドシーブ14.15の
傾斜力向およびガイド方向を変更する手段としては、着
は換えによる手段を採用してもよく、あるいは傾斜ガイ
ドンープ14,15を保持部材に取付け、その保持部材
を引出移設装置のフレームに対し傾斜方向変換およびガ
イド方向変換自在に取付けると共に、前記保持部材を前
記フレームに固定するための固定装置を設けてもよい。
After the first small-diameter strand has been pulled out from one bank to the opposite bank through the series of operations described above, the tip of this small-diameter strand is removed from the drawer transfer device 6, and the tip of the second small-diameter strand is attached to the drawer transfer device 6. By connecting and running the pull-out relocation device 6 in the opposite direction, this second small-diameter strand is pulled out with the required tension onto the pull-out roller 6 on the floor of the suspended scaffold 2 while performing on-site focusing and cleaning. At the same time, the first small diameter strand, which has already been drawn out, is automatically transferred from the drawing roller 6 into the cable former 7 by being guided by the plurality of inclined guide loops 14 and 15 in the drawing transfer device B. Here, the plurality of inclined guide sheaves 14 in the drawer relocation device 6
.. 15 can change the tilting force direction and the guiding direction depending on the running direction. As a means for changing the direction of the tilting force and the guide direction of the tilting guide sheave 14, 15, a means of changing the mounting may be adopted, or a method of attaching the tilting guide loops 14, 15 to a holding member and pulling out and relocating the holding member. The holding member may be attached to the frame of the apparatus so as to be able to change the tilting direction and the guiding direction, and a fixing device may be provided for fixing the holding member to the frame.

前述のように引出移設装置6が、最初のストランドの引
出し側の岸に到着すると、引出し終了した第2の細径ス
トランドの先端を引出移設装置6から外すと共に、第6
の細径ストランドの先端を引出移設装置乙に接続し、対
岸に向って、第2の細径ストランドを自動的に移設しな
がら、第6の細径ストランドを引出していく。第6図お
よび第4図において符号16はケーブルフォーマ−7内
に移設された細径ストランドを示している。
As described above, when the drawer transfer device 6 arrives at the bank on the drawer side of the first strand, it removes the tip of the second small diameter strand that has been drawn out from the drawer transfer device 6, and then
The tip of the thin strand is connected to the drawer relocation device B, and the sixth thin strand is pulled out toward the opposite bank while automatically transferring the second thin strand. In FIGS. 6 and 4, reference numeral 16 indicates a small diameter strand that has been moved into the cable former 7.

前述のような引出移設工程を必要回数繰り返して行なっ
たのち、ケーブルフォーマ−7内に移設された細径スト
ランド群を束ねて、A−8工法と同程度の、あるいはそ
れ以上の太径ストランド8を構成する。その後、この太
径ストランド8の両端に現場でソケット9を取付けて、
太径ストランド8の両端をアンカレッジ1に引込定着す
る。
After repeating the drawer relocation process as described above a necessary number of times, the group of small diameter strands relocated in the cable former 7 is bundled to form a large diameter strand 8 that is equivalent to or larger than that of the A-8 construction method. Configure. After that, sockets 9 are attached to both ends of this large diameter strand 8 on site.
Both ends of the large diameter strand 8 are drawn into the anchorage 1 and fixed.

なお第1図および第2図において、17は主塔である。In addition, in FIG. 1 and FIG. 2, 17 is the main tower.

第7図ないし第10図はこの発明を2本の吊橋ケーブル
の同時架設に実施した例を示すものであって、スイフl
−10、素線集束装置5.ンーゾング装置11.引出し
ローラ6、ケーブルフォーマ−7の列が平行して2列設
けられ、かつ左右両側に傾斜ガイドシーブ14.15を
備えている共通の引出移設装置6により左右両側の細径
ストランドの引出移設が同時に行なわれるように構成さ
れているが、架設順序は第1図ないし第6図の場合と同
様である。
Figures 7 to 10 show an example in which the present invention is applied to the simultaneous erection of two suspension bridge cables.
-10, Element wire focusing device 5. Nzongu device 11. A common drawer relocation device 6, which has two parallel rows of drawer rollers 6 and cable formers 7 and is equipped with inclined guide sheaves 14 and 15 on both the left and right sides, can transfer the small diameter strands on both the left and right sides. The erection order is the same as in FIGS. 1 to 6, although they are configured to be done simultaneously.

次に引出移設装置3を往復移動させる駆動方式としては
、両岸に設置した駆動ウィンチ18によりホーリングロ
ープ19を介して往復移動させる方式全採用してもよく
、あるいは引出移設装置6自体に取付けた駆動装置等に
より引出移設装置6を吊足場2の床上に敷設固定した軌
条4の上で往復自走行できる方式全採用してもよい。
Next, as a drive method for reciprocating the drawer relocation device 3, a method may be adopted in which the drive winch 18 installed on both banks reciprocates via the hauling rope 19, or a drive winch installed on the drawer relocation device 6 itself may be adopted. All methods may be adopted in which the drawer relocation device 6 can be moved back and forth on the rail 4 laid and fixed on the floor of the suspended scaffolding 2 using a drive device or the like.

駆動方式は、従来のトラムウェイ方式のように、吊足場
2の床から約4mの高さに位置せず、吊足場2の床から
約1mの高さに設置させておけば、ホーリングロープ振
動や緩み等にょる脱索が発生することはなく、1だ高所
である場合に生じる風に対する不安定さが全くないので
、安全性も犬きく向上する。
The drive system is not located at a height of about 4 m from the floor of the suspended scaffold 2 like the conventional tramway system, but if it is installed at a height of about 1 m from the floor of the suspended scaffold 2, the vibration of the hauling rope can be reduced. Safety is also greatly improved because there is no chance of the rope coming off due to loosening or loosening, and there is no instability due to the wind that occurs when the rope is at a higher elevation.

〔発明の効果〕〔Effect of the invention〕

この発明は前述のように構成されているので、P−W、
S工法における前述のクリティカル作業をなくすること
ができ、そのためサイクルタイムを大巾に短縮すること
かでき、かつ引出移設装置乙の片道走行時に細径ストラ
ンドの引出しと、1サイクル前の引出し済みストランド
の移設を同時に行なうので、サイクルタイムをさらに短
縮することができ、しかもこの発明の架設方法における
クリティカル作業は、引出し、移設作業そのものである
ため、速度の向上が直接サイクルタイムの短縮につなが
り、したがって工期を著しく短縮することができ、また
品質面では、素線をスイット10から直接引出したのち
細径ストランドにして引出すため、P、、W、S工法で
生じる可能性のあるストランドのうねり、たるみ、バー
ドケージ。
Since this invention is configured as described above, P-W,
It is possible to eliminate the above-mentioned critical work in the S method, and therefore the cycle time can be greatly shortened, and when the drawer relocation device B runs one way, it is possible to pull out small diameter strands and to remove the strands that have already been pulled out one cycle before. Since the relocation and relocation are performed at the same time, the cycle time can be further shortened.Moreover, the critical work in the erection method of this invention is the pulling out and relocation work itself, so the improvement in speed directly leads to a reduction in the cycle time. The construction period can be significantly shortened, and in terms of quality, since the strands are drawn directly from the switch 10 and then made into small diameter strands, there is no waviness or sag in the strands that may occur with the P, W, or S methods. , Birdcage.

捩れ等による品質低下が少なくなる効果がある。This has the effect of reducing quality deterioration due to twisting, etc.

さらに、1)、W、S工法で必要なストランド運搬用の
大型リール、特殊運搬設備等が不要である。
Furthermore, 1) there is no need for large reels for transporting the strands, special transport equipment, etc., which are required in the W and S methods.

また本工法ではストランド長さを現場にて合せるため、
p、w、s工法で必要なゲージワイヤが不要であり、p
 、w、s工法のストランド長さを現場にて調整するシ
ム板を少なくできる。さらに捷だ、ストランドの太径化
が行ない易いため、アンカレンジ’1A−8工法なみに
、あるいは、それ以上に小さくできる。各サドル内部に
おいては、スペーサーを少なくできる等、多くの効果が
あり、また特に超長大吊橋ケーブルの場合には、その効
果が極めて大きくなる。
In addition, in this construction method, the strand length is adjusted on site, so
Gauge wire required in p, w, s method is not required, and p
The number of shim plates used to adjust the strand length of the , w, and s construction methods on site can be reduced. Furthermore, since it is easy to increase the diameter of the strand, it can be made as small as the Anchorage '1A-8 construction method or even smaller. Inside each saddle, there are many effects such as reducing the number of spacers, and especially in the case of ultra-long suspension bridge cables, the effects are extremely large.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第6図はこの発明を1本の吊橋ケーブルの
架設に実施した例を示すものであって、第1図は全体を
示す概略側面図、第2図は第1図の左側を拡大して示す
側面図、第6図は第1図におけるアンカレッジおよび主
塔を省略して示す概略平面図、第4図は第3図の左側を
拡大して示す平面図、第5図は引出移設装置による移設
状況を示す斜視図、第6図はその概略正面図である。 第7図ないし第10図はこの発明を2本の吊橋ケーブル
の同時架設に実施した例を示すものであって、第7図は
概略平面図、第8図は第7図の左側を拡大して示す平面
図、第9図は引出移設装置による移設状況を示す斜視図
、第10図はその概略正面図である。 図において、1t/′iアyカレツジ、2は吊足場、6
はストランド引出移設装置、4は軌条、5は素線集束装
置、6は引出しローラー、7はケーブルフォーマ−18
は太径ストランド、9はソケット、10はスイット、1
1はシージング装置、12は素線、16は細径ストラン
ド、14および15は傾斜ガイドシーブ、18は駆動ウ
ィンチである。
Figures 1 to 6 show an example in which the present invention is applied to the construction of one suspension bridge cable. Figure 1 is a schematic side view showing the whole, and Figure 2 is a left side view of Figure 1. FIG. 6 is a schematic plan view with the anchorage and main tower omitted in FIG. 1, FIG. 4 is an enlarged plan view of the left side of FIG. 3, and FIG. FIG. 6 is a perspective view showing a relocation situation using the drawer relocation device, and a schematic front view thereof. Figures 7 to 10 show an example in which the present invention is applied to the simultaneous erection of two suspension bridge cables, with Figure 7 being a schematic plan view and Figure 8 being an enlarged view of the left side of Figure 7. FIG. 9 is a perspective view showing the relocation situation by the drawer relocation device, and FIG. 10 is a schematic front view thereof. In the figure, 1t/'i eye college, 2 is suspended scaffolding, 6
1 is a strand drawing transfer device, 4 is a rail, 5 is a wire concentrator, 6 is a drawing roller, 7 is a cable former 18
is a thick diameter strand, 9 is a socket, 10 is a switch, 1
1 is a sheathing device, 12 is a wire, 16 is a thin diameter strand, 14 and 15 are inclined guide sheaves, and 18 is a driving winch.

Claims (1)

【特許請求の範囲】[Claims] 吊橋を架設すべき両岸のアンカレツジ1間に吊足場2を
架設し、ストランド引出移設装置3を前記吊足場2の床
上に設置した軌条4によりガイドして駆動装置等により
往復走行させながら、両岸のアンカレツジ1の後方に設
置した素線集束装置5により多数本の素線を現場集束す
ると共にシージングしながら細径ストランドを形成し、
前記ストランド引出移設装置3により、一方の岸から細
径ストランドを吊足場上の引出しローラ6上に引出すと
同時に、他方の岸から既に引出されている細径ストラン
ドをケーブルフオーマー7内に自動的に移設する工程を
必要回数繰り返し、次に移設完了した各細径ストランド
を束ねて太径ストランド8を形成したのち、その太径ス
トランド8の両端にソケット9を取付けて引込み定着を
行なうことを特徴とする吊橋ケーブルの架設方法。
A suspended scaffold 2 is erected between the anchorages 1 on both banks where a suspension bridge is to be constructed, and a strand pull-out transfer device 3 is guided by a rail 4 installed on the floor of the suspended scaffold 2 and moved back and forth by a drive device, etc. A large number of strands are gathered on site using a strand converging device 5 installed behind the anchorage 1 on the shore, and a small diameter strand is formed while sheathing.
The strand pull-out transfer device 3 pulls out a small diameter strand from one bank onto the pull-out roller 6 on the suspended scaffold, and at the same time automatically transfers the small diameter strand already pulled out from the other bank into the cable former 7. The transfer process is repeated as many times as necessary, and then each small diameter strand that has been transferred is bundled to form a large diameter strand 8, after which sockets 9 are attached to both ends of the large diameter strand 8 and the sockets 9 are pulled in and fixed. A method for constructing suspension bridge cables.
JP15212684A 1984-07-24 1984-07-24 Construction of cable of suspension bridge Pending JPS6131510A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15212684A JPS6131510A (en) 1984-07-24 1984-07-24 Construction of cable of suspension bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15212684A JPS6131510A (en) 1984-07-24 1984-07-24 Construction of cable of suspension bridge

Publications (1)

Publication Number Publication Date
JPS6131510A true JPS6131510A (en) 1986-02-14

Family

ID=15533628

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15212684A Pending JPS6131510A (en) 1984-07-24 1984-07-24 Construction of cable of suspension bridge

Country Status (1)

Country Link
JP (1) JPS6131510A (en)

Similar Documents

Publication Publication Date Title
CN104278637B (en) A kind of main rope of suspension bridge strand is without the cableway erection method in cat road
JP5812325B2 (en) Electric wire tension reduction device and electric wire tension reduction method
CN104631329B (en) A kind of suspension bridge continuous way cat road integral linear method of adjustment
CN113756201B (en) T-structure continuous beam prestressed steel strand pulling method and pulling device thereof
CN111907378A (en) Passenger-cargo collinear carrier cable and contact line synchronous replacement construction process
CN212025936U (en) Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge
CN212670303U (en) Stay cable beam end mounting structure
CN101459321B (en) Long distance bundling paying-out method and apparatus for slope tower over hanging power transmission line
CN210236765U (en) Pay-off rack for construction of prestressed steel strand finished product bundle
CN110172919A (en) A kind of low-pylon cable-stayed bridge is reeved method and system
CN211142840U (en) Suspension bridge main push-towing rope erects system
JPS6131510A (en) Construction of cable of suspension bridge
CN111409511A (en) Positioning and mounting structure for existing railway line contact net
CN210827120U (en) Tensioning operation platform supported by temporary anchoring platform based on prefabricated section box girder
CN214396490U (en) Novel cable laying device for ring network between metro sections
SU939626A1 (en) Method and apparatus for mounting the ropes of guys of guy bridge
JP4276731B2 (en) Cable wiring method and wiring device
CN220789433U (en) Circulation traction system suitable for two-bank tunnel anchor suspension bridge main cable erection
CN212148525U (en) Positioning and mounting structure for existing railway line contact net
KR20100076142A (en) A pair of spinning wheels and installing method of mono calble of suspension bridge using that spinning wheels
JPH05215923A (en) Method for laying wiring cable and traction jig to be used therein
CN117684477A (en) Main cable erection method of self-anchored suspension bridge with space cable structure
CN118145433A (en) Method for doubling and coiling rotary main cable strand and method for erecting main cable strand
JPS6429504A (en) Holing rope support method for erecting suspension bridge cable
JPS5810522B2 (en) How to erect long objects in the air