JPS6127524B2 - - Google Patents

Info

Publication number
JPS6127524B2
JPS6127524B2 JP56166436A JP16643681A JPS6127524B2 JP S6127524 B2 JPS6127524 B2 JP S6127524B2 JP 56166436 A JP56166436 A JP 56166436A JP 16643681 A JP16643681 A JP 16643681A JP S6127524 B2 JPS6127524 B2 JP S6127524B2
Authority
JP
Japan
Prior art keywords
injection
pipe
injected
stratum
face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP56166436A
Other languages
Japanese (ja)
Other versions
JPS5869921A (en
Inventor
Susumu Nishida
Masao Kamyama
Hiromichi Hata
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP16643681A priority Critical patent/JPS5869921A/en
Publication of JPS5869921A publication Critical patent/JPS5869921A/en
Publication of JPS6127524B2 publication Critical patent/JPS6127524B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Description

【発明の詳細な説明】 本発明は薬液注入工法に関するものである。[Detailed description of the invention] The present invention relates to a chemical injection method.

一般の薬液注入工法は、トンネルなどの掘削を
行う以前に掘削予定部分に注入して止水処理を施
し、その後に湧水に妨害されることなく掘削しよ
うとするものである。
In the general chemical injection method, before excavating a tunnel or the like, the chemical is injected into the area to be excavated to stop water, and then excavation is attempted without being hindered by spring water.

従つて第1図に示すように切羽Sから掘削予定
部Pに出来るだけ広く注入しておくことが望まし
い。
Therefore, as shown in FIG. 1, it is desirable to inject as widely as possible from the face S into the planned excavation area P.

しかし例えば第2図に示すように切羽Sのすぐ
内側の地層Qには薬液を注入する必要がなく、一
方それより奥の部分P′には注入する必要があり、
その注入は切羽が奥の部分P′に達する以前に止水
処理を施こしておかねばならない場合がある。
However, as shown in Figure 2, for example, there is no need to inject the chemical into the stratum Q immediately inside the face S, while it is necessary to inject into the deeper part P'.
In some cases, it may be necessary to perform water stop treatment before the injection face reaches the inner part P'.

また切羽Sのすぐ内側の地層Qと奥の地層P′の
透水係数が大きく異なるため、他の部分とは別に
奥の地層P′のみに薬液を注入する必要が生じる場
合もある。あるいは切羽周辺が強度のない地層で
あり、一方奥の湧水の圧力が高い場合は、奥の地
層P′には高圧注入が必要でありかつ注入液が口元
や切羽周辺に漏出しやすいが、そのような場合に
も奥の地層P′のみに注入することができればきわ
めて好都合である。
Furthermore, since the hydraulic conductivity of the stratum Q immediately inside the face S and the deep stratum P' are significantly different, it may be necessary to inject the chemical only into the deep stratum P' separately from other parts. Alternatively, if the area around the face is a weak stratum and the pressure of the spring water in the back is high, high-pressure injection is required into the deep stratum P′, and the injected liquid is likely to leak around the mouth or around the face. Even in such a case, it would be extremely convenient if it could be injected only into the deep stratum P'.

本発明はこのような状況に応じてなされたもの
であり、切羽や地層などの地山露出部のすぐ内側
部分には注入を行なうことなく、より奥部分のみ
に注入を行うことのできる工法を提供することを
目的とする。
The present invention was developed in response to this situation, and provides a construction method that allows injection only to the deeper parts of the exposed parts of the earth, such as faces and strata, without injecting directly inside the exposed parts. The purpose is to provide.

また本発明は切羽へのリークを生じることなく
目的とする奥の部分に注入を行うことのできる工
法を提供することを目的とする。
Another object of the present invention is to provide a construction method that can perform injection into the target deep part without causing leakage to the face.

次に実施例について説明する。 Next, an example will be described.

<1> 保護パイプの設置(第3図) トンネルにおける場合を説明すると切羽1に
保護パイプ2を設置する。
<1> Installation of a protection pipe (Fig. 3) To explain the case in a tunnel, a protection pipe 2 is installed at the face 1.

切羽1の状態が悪い時にはコンクリート壁3
を打設して切羽1の崩壊を防止することもあ
る。
If face 1 is in poor condition, concrete wall 3
The collapse of face 1 may be prevented by pouring.

保護パイプ2は比較的大径の削孔機で削孔し
た孔に圧入した強度を有するパイプであるが、
長い区間に設置する必要はなく、切羽1から浅
い区間に設ける。
The protective pipe 2 is a strong pipe that is press-fitted into a hole drilled with a relatively large-diameter drilling machine.
There is no need to install it in a long section, but in a shallow section from face 1.

<2> 削孔(第3図) 保護パイプ2以深を小径の削岩機4で長い区
間深部まで小径孔5を削孔する。
<2> Drilling holes (Fig. 3) Drill small-diameter holes 5 deeper than the protection pipe 2 in a long section using a small-diameter rock drill 4.

ここでいう小径とは保護パイプ2部分の大径
孔に比較して小径であるという意味であり、一
般に注入孔より特に小径であるという意味では
ない。
The small diameter here means that the diameter is smaller than the large diameter hole of the protection pipe 2 portion, and does not generally mean that the diameter is particularly smaller than the injection hole.

<3> 非金属パイプの挿入(第4図) 削孔後の小径孔5内に例えば硬質塩化ビニー
ル管、ポリエチレン管、などの非金属製のパイ
プ6を挿入する。
<3> Insertion of a non-metallic pipe (Fig. 4) A non-metallic pipe 6, such as a hard vinyl chloride pipe or a polyethylene pipe, is inserted into the small-diameter hole 5 after drilling.

このパイプ6は後述するように容易に破壊す
るものであれば良く、注入時の内圧に対してパ
イプ自体で耐えられる必要はない。
This pipe 6 only needs to be easily destroyed as will be described later, and it is not necessary that the pipe itself can withstand the internal pressure during injection.

非金属パイプ6の先端は小径孔5の最先端、
すなわち第2図で言えば奥の地層P′内に位置さ
せる。
The tip of the non-metallic pipe 6 is the leading edge of the small diameter hole 5,
In other words, in Fig. 2, it is located in the deep stratum P'.

<4> T型パイプの取り付け(第5図) 保護パイプ2の外部にT型パイプ7の一端を
固着する。
<4> Attaching the T-shaped pipe (FIG. 5) One end of the T-shaped pipe 7 is fixed to the outside of the protective pipe 2.

そして非金属パイプ6の一層をT型パイプ7
から露出させ非金属パイプ6端に注入材用バル
ブ8を、直交する側の出口には仮充填材用バル
ブ9を、各々取り付ける。
Then, one layer of the non-metallic pipe 6 is connected to the T-shaped pipe 7.
An injection material valve 8 is attached to the exposed end of the nonmetallic pipe 6, and a temporary filling material valve 9 is attached to the outlet on the orthogonal side.

ここに注入材とは奥の地層P′のクラツクに高
圧で注入して止水を行うための材料であり、こ
の止水が注入工事本来の目的である。
The injection material here is a material that is injected at high pressure into the crack in the deep stratum P' to stop water, and stopping water is the original purpose of the injection work.

一方仮充填材とは非金属パイプ6等の周囲の
空隔を仮に充填するための材料であり、本来の
注入工事を完全に行うためのものに過ぎない。
On the other hand, the temporary filling material is a material for temporarily filling the space around the non-metallic pipe 6, etc., and is only used to completely perform the original injection work.

<5> 仮充填材の注入 仮充填材用バルブ9を通して充填材、例えば
高濃度の懸濁型水ガラス系注入材LWなどの高
強度でゲルタイムの短かい注入材を低圧で注入
する。
<5> Injection of temporary filler A filler, for example, a high-strength, short-gelling-time injection material such as a high concentration suspension type water glass injection material LW, is injected at low pressure through the temporary filling material valve 9.

この仮充填材10は保護パイプ2内および非
金属パイプ6外周に沿つて小径孔5の深部に向
かつて充填されるが、流量を管理することによ
つて非金属パイプ6の先端周辺に到達する前に
充填を終了する。
This temporary filling material 10 is filled into the protective pipe 2 and along the outer periphery of the nonmetallic pipe 6 towards the deep part of the small diameter hole 5, but by controlling the flow rate, it reaches around the tip of the nonmetallic pipe 6. before finishing filling.

小径孔5深の湧水は非金属パイプ6および開
口した注入材用バルブ8を通してトンネル内に
排水する。
The spring water deep in the small diameter hole 5 is drained into the tunnel through a non-metallic pipe 6 and an open injection material valve 8.

<6> 注入材の注入 仮充填材10によつて周囲を強固に固められ
た非金属パイプ6によつて地山注入材11を注
入する。
<6> Injection of injection material The earth injection material 11 is injected through the non-metallic pipe 6 whose periphery is firmly solidified with the temporary filler 10.

この注入材11は小径孔5の先端の地層P′の
クラツクには充分に注入されるが孔内は仮充填
材10が充填してあるから小径孔5に沿つて戻
つたり、切羽からリークすることはない。
This injection material 11 is sufficiently injected into the crack in the stratum P' at the tip of the small diameter hole 5, but since the hole is filled with the temporary filler 10, it may return along the small diameter hole 5 or leak from the face. There's nothing to do.

<1> 掘削 注入材11で処理した後トンネルの掘削を行
うが、地中の残つている注入パイプは簡単に破
壊できる非金属製のパイプ6だけであるから掘
削作業の障害となることはない。
<1> Excavation A tunnel will be excavated after treatment with the injection material 11, but the only injection pipe remaining underground is the non-metallic pipe 6, which can be easily destroyed, so it will not interfere with the excavation work. .

<8> 他の実施例(第6図) 以上は仮充填材10の充填の後に注入材11
を注入する方法について述べたが、例えば水平
注入、下向き注入のように仮充填材10が小径
孔5の孔底に先行してしまうような場合があ
る。
<8> Other embodiments (Fig. 6) In the above, the injection material 11 was filled after the temporary filling material 10 was filled.
Although the method of injecting has been described, there are cases where the temporary filler 10 precedes the bottom of the small diameter hole 5, such as horizontal injection or downward injection.

その時は長いゲルタイムの地山注入材11を
低速度(5〜10/分)で注入して非金属製パ
イプ6先端を閉塞を防いだ状態で仮充填材10
をバランスを取りながら充填すればよい。
At that time, the ground injection material 11 with a long gel time is injected at a low speed (5 to 10/min) to prevent the tip of the non-metallic pipe 6 from clogging, and the temporary filling material 10 is
Just fill it while keeping the balance.

本発明は上記したようになるから次のような効
果を期待することができる。
Since the present invention is as described above, the following effects can be expected.

<イ> 注入孔を充填する充填材と、目的とする
地中に注入する本来の地山注入材とを使い分け
る工法である。
<B> This is a construction method that uses the filling material that fills the injection hole and the original ground injection material that is injected into the target ground.

従つて地山への高圧注入を行つても注入材が
抵抗の少ない切羽方向へ戻つて切羽からリーク
するといつた従来の欠点を完全に防止すること
ができる。
Therefore, even if high-pressure injection into the ground is performed, the conventional drawbacks such as leakage from the face due to the injection material returning to the direction of the face where there is less resistance can be completely prevented.

<ロ> 地山注入材を目的の位置だけに注入し、
それより手前には注入しないという処理を行う
ことができる。
<B> Inject the ground injection material only into the desired location,
It is possible to perform processing such that injection is not performed before this point.

従つて手前の地層が不透水性で(止水処理が
不要の地層)胞弱であつてそれより奥の地層が
高圧湧水を持つ透水性の地層(止水処理を要す
る地層)であるような場合に、深部の地層への
みの注入を行うことができる。
Therefore, the stratum in the foreground is impermeable (a stratum that does not require water-stopping treatment) and is weak, and the stratum further back is a permeable stratum that has high-pressure spring water (a stratum that requires water-stopping treatment). In certain cases, injection can be carried out only into deep geological formations.

<ハ> 注入管は非金属製パイプであつてもその
周囲を充填材で固めた後に使用するから注入の
最中に破壊することがない。
<C> Even if the injection pipe is a non-metallic pipe, the surrounding area is hardened with filler before use, so it will not break during injection.

<ニ> 非金属製パイプは安価で破壊しやすいた
め使い捨てにして回収する必要がなく、かつ処
理後の地山掘削時に掘削の障害とならない。
<D> Non-metallic pipes are cheap and easy to destroy, so there is no need to throw them away and collect them, and they do not become an obstacle when excavating the ground after treatment.

<ホ> 注入管は使い捨てなので注入の最後に注
入管の回収ができなくなるような充分の圧力を
かけ、流量も最少にして理想的な注入を行うこ
とができる。
<e> Since the injection tube is disposable, ideal injection can be performed by applying sufficient pressure so that the injection tube cannot be recovered at the end of injection and minimizing the flow rate.

従来の方法では注入管の回収を考慮して最終
段階での注入を充分に行うことができなかつ
た。
In the conventional method, it was not possible to perform the final injection sufficiently in consideration of recovery of the injection tube.

<ヘ> 単管ロツド工法に準じた簡単な工法であ
るから施工が複雑ではなく施工機器も特別なも
のは必要としない。
<F> Since it is a simple construction method similar to the single pipe rod construction method, construction is not complicated and no special construction equipment is required.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図:一般の薬液注入の状態の説明図、第2
図:本工法の目的とする注入方法の一例の説明
図、第3〜5図:本工法の施工方法の順序の説明
図、第6図:他の実施例の説明図、 P′:奥の地層、2:保護パイプ、6:非金属パ
イプ、10:仮充填材、11:注入材。
Figure 1: Explanatory diagram of general drug injection conditions, Figure 2
Figure: An explanatory diagram of an example of the injection method intended for this method, Figures 3 to 5: An explanatory diagram of the order of the construction method of this construction method, Figure 6: An explanatory diagram of another example, P': In the back Geological stratum, 2: protection pipe, 6: nonmetallic pipe, 10: temporary filling material, 11: injection material.

Claims (1)

【特許請求の範囲】 1 薬液を深部の地層のみへ注入を行い、 それより浅い部分への注入を阻止する工法であ
つて、 注入を行う深部まで削孔した孔内に、その先端
まで非金属製パイプを挿入し、 パイプ先端部を残して非注入部分の孔内とパイ
プとの間隙を充填材で充填し、 固化した後に非金属製パイプの先端から深部の
地層の地山へ向けて注入材を注入することを特徴
とする、 薬液注入工法。
[Scope of Claims] 1. A construction method in which a chemical solution is injected only into the deep strata and prevented from being injected into shallower layers, in which a non-metallic material is injected into a hole drilled to the depth where the injection is to be performed, up to the tip of the hole. A non-metallic pipe is inserted, and the gap between the hole and the pipe is filled with filler material, leaving the tip of the pipe in place. After solidification, the filler is injected from the tip of the non-metallic pipe into the ground in the deep strata. A chemical injection method characterized by injecting materials.
JP16643681A 1981-10-20 1981-10-20 Grout injection work Granted JPS5869921A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16643681A JPS5869921A (en) 1981-10-20 1981-10-20 Grout injection work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16643681A JPS5869921A (en) 1981-10-20 1981-10-20 Grout injection work

Publications (2)

Publication Number Publication Date
JPS5869921A JPS5869921A (en) 1983-04-26
JPS6127524B2 true JPS6127524B2 (en) 1986-06-26

Family

ID=15831370

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16643681A Granted JPS5869921A (en) 1981-10-20 1981-10-20 Grout injection work

Country Status (1)

Country Link
JP (1) JPS5869921A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0696862B2 (en) * 1986-06-06 1994-11-30 東急建設株式会社 Water-stopping material and water-stopping method using the same
JP4679966B2 (en) * 2005-05-20 2011-05-11 関西電力株式会社 Boring hole closing method and equipment
JP4679967B2 (en) * 2005-05-20 2011-05-11 関西電力株式会社 Boring hole closing device and construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4828208A (en) * 1971-08-13 1973-04-14

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4828208A (en) * 1971-08-13 1973-04-14

Also Published As

Publication number Publication date
JPS5869921A (en) 1983-04-26

Similar Documents

Publication Publication Date Title
AU2020101047A4 (en) Method for filling underground cavity in bedrock by grouting and hydraulic filling device
CN106320354B (en) The Seepage method on solution cavity development stratum under coating
CN106014201B (en) A kind of outer release hole safe construction technique of tunnel grouting curtain
CN105200978B (en) A kind of protrusive localization two-liquid grouting device and construction method
JP5182922B2 (en) Water stop grout method and system under high water pressure
CN107605498A (en) Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN105909265A (en) Heaving-prevention retrusive deep-hole grouting system and method for passing through existing shield tunnel
US4065927A (en) Method for blocking gas flow in a coal seam
JPS6127524B2 (en)
JP2008045352A (en) Landslide prevention construction method of valley-filling banking
JP4252070B2 (en) Ground stabilization method
CN109914390A (en) It is a kind of to construct the slip casting structure and construction method of cold seam for biting connecions campshed
JP2867204B2 (en) Construction method of outer pipe for injection under pressurized water
CN201129178Y (en) Drilling subsection advanced type grouting water-shutoff apparatus
JP2979360B2 (en) Groundwater draining method
JPH0814105B2 (en) Horizontal sleeve injection method
JPH0476110A (en) Installation method for medical fluid injection strainer pipe and strainer pipe therefor
CN103615011A (en) Construction method for anchoring support in high-water-pressure soil layer
JP3488887B2 (en) Well drilling method
JP2000310094A (en) Prelining reinforcing construction technique for natural ground
JPH0433926B2 (en)
JP4133898B2 (en) How to reach the excavator
JP2007162265A (en) Tunnel construction method
JP3686006B2 (en) Water stoppage method in pipe propulsion method