JPS61246472A - Wall reinforcing bar assembling method - Google Patents
Wall reinforcing bar assembling methodInfo
- Publication number
- JPS61246472A JPS61246472A JP8463085A JP8463085A JPS61246472A JP S61246472 A JPS61246472 A JP S61246472A JP 8463085 A JP8463085 A JP 8463085A JP 8463085 A JP8463085 A JP 8463085A JP S61246472 A JPS61246472 A JP S61246472A
- Authority
- JP
- Japan
- Prior art keywords
- reinforcing bar
- wall
- bars
- reinforcement
- joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Reinforcement Elements For Buildings (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
(発明の分野と目的)
本発明は、中高層建物の壁用空間に張設する壁鉄筋網を
柱構造体に連結して定着固定する壁鉄筋網の組付は工法
に関する。Detailed Description of the Invention (Field and Object of the Invention) The present invention provides a construction method for assembling a wall reinforcing bar network that connects and fixes a wall reinforcing bar network to a column structure to be stretched in a wall space of a medium-to-high-rise building. Regarding.
集合住宅などの中高層建物の耐震壁面に埋込まれる壁鉄
筋として、縦筋と横筋とを格子状に溶接した鉄筋網を用
いることが多くなっている。BACKGROUND ART As wall reinforcing bars embedded in earthquake-resistant walls of medium-to-high-rise buildings such as apartment complexes, a reinforcing bar network in which vertical and horizontal bars are welded in a lattice pattern is increasingly used.
この壁鉄筋網の柱に隣接する側縁部は、鉄筋又は鉄骨・
鉄′筋からなる柱構造体のフープ筋に囲まれた内部にま
で挿入して定着しなければならず、壁鉄筋網の位置決め
は正確で位置ずれや脱落を生じないようにしなければな
らない。The side edges of this wall reinforcement network adjacent to the columns should be reinforced with reinforcing bars or steel frames.
It must be inserted into the interior of the column structure made of steel bars surrounded by hoop reinforcements, and the wall reinforcement network must be positioned accurately to prevent it from shifting or falling off.
ところが、壁鉄筋網の横筋先端部は、柱の鉄筋構造内に
達するまで差込みにくいので、まず上記横筋先端部を柱
構造体に近接させて轟込んだ後に、一定長さの差し筋を
多数本用意し、その一端が柱の鉄筋構造体内に収まシ他
端が壁鉄筋網の側縁部と重なるよう位置決め支持しつつ
、この差し筋と柱構造体及び壁鉄筋とを結束して、壁鉄
筋網を柱に定着することが多い。However, it is difficult to insert the tips of the transverse bars of the wall reinforcing bar network until they reach the reinforcing structure of the columns, so after first bringing the tips of the transverse bars close to the column structure and inserting them, it is necessary to insert a large number of insert bars of a certain length. While positioning and supporting the reinforcing bars so that one end fits inside the reinforcing bar structure of the column and the other end overlaps with the side edge of the wall reinforcing bar network, this insert bar is tied to the column structure and wall reinforcing bar, and the wall reinforcing bar They often settle in nets on pillars.
しかし、この工法では多数の差し筋を各個別々に正確に
位置合わせして支持しつつ壁鉄筋網の側縁部と柱構造体
とに取付けなければならないから、その作業が繁雑で工
事時間も長くなる。However, with this construction method, a large number of reinforcing bars must be individually aligned and supported while being attached to the side edges of the wall reinforcing bar network and the column structure, making the work complicated and taking a long time. Become.
のみならず、上記差し筋は、各個別々に鉄筋網の横筋及
び柱のフープ筋と結束されるので、コンクリート投入そ
の他の外力によって一部の差し筋が所定位置からずれた
シ離脱したシして不完全な構造体になるおそれがある。In addition, since each of the above-mentioned insert bars is individually tied to the horizontal bars of the reinforcing bar network and the hoop bars of the column, there is a possibility that some of the insert bars may be displaced from their predetermined positions or detached due to concrete pouring or other external forces. This may result in an incomplete structure.
本発明は、上記従来工法の欠点をなくす新規の工法の提
供を目的とする。The present invention aims to provide a new construction method that eliminates the drawbacks of the conventional construction methods described above.
(発明の構成)
本発明にかかる工法の構成は、特許請求の範囲に記載の
とおりであり、これを要するに、その主要な特徴は、従
来の差し筋の多数本に相肖する継手鉄筋部材の複数本を
上下に所要間隔をおいて重畳配列し、その延長部と直交
する通し鉄筋部材とを溶接して一体化した壁筋と柱とを
つなぐ定着用鉄筋構造体を採用し、これを一工程で柱構
造体の鉄筋囲い内に挿入し、これによって、あたかも従
来の差し筋の多数本を順次−々正確に位置決めして位置
ずれ及び離脱不能に倉入シに固着したのと同等以上の効
果を収めるよう、にしたところにある。(Structure of the Invention) The structure of the construction method according to the present invention is as described in the claims, and in short, the main feature is that a joint reinforcing bar member that is compatible with a large number of conventional reinforcing bars is used. A fixing reinforcement structure is adopted that connects the wall reinforcements and columns by arranging multiple reinforcements vertically and overlapping each other at the required intervals, and welding the extended portions and orthogonal through-reinforcing members to the columns. It is inserted into the reinforcing bar enclosure of the column structure during the process, and by doing so, it is equivalent to or better than the conventional method of positioning multiple reinforcing bars one after another accurately and fixing them to the warehouse without being able to move or remove them. It's in a place where it's designed to be effective.
(実施例及び補足説明)
以下本工法の一実施例を図面を引用して説明し、変形例
について補足する。(Example and Supplementary Explanation) An example of the present construction method will be described below with reference to drawings, and modified examples will be supplemented.
まず、その概略を述べると、第1図の鉄骨・鉄筋からな
る柱構造体A、 A’、コンクリート打設ずみ床板B及
びこの上面に継手筋をくし刃状に突出して設けた壁用空
間R側から、第2図に示すとおシ、本工法に用いる壁筋
定着用鉄筋構造体Cを柱の鉄筋囲み内に挿入し、柱構造
体と結束し定着する。そして、@3図に示すとおシ、壁
鉄筋網りの縦筋下端を上記下床板から突出しているくし
刃状継手筋と結束し、かつ、壁鉄筋網りの一側縁を柱に
定着しである上記壁筋定着用鉄筋構造体Cの柱から突き
出した継手鉄筋部材の延長部と結合する。First, to give an overview, there are columnar structures A and A' made of steel frames and reinforcing bars in Fig. 1, a concrete-cast floor plate B, and a wall space R with joint reinforcements protruding from the upper surface in the shape of a wedge. From the side, as shown in FIG. 2, the wall reinforcing bar structure C used for this construction method is inserted into the reinforcing bar enclosure of the column, and is tied and fixed to the column structure. Then, as shown in Figure @3, the lower end of the vertical bar of the wall reinforcing bar network is tied to the comb-shaped joint bar protruding from the subfloor board, and one side edge of the wall reinforcing bar network is fixed to the column. It is coupled to an extension of a joint reinforcing member protruding from a column of the above-mentioned wall reinforcing reinforcing bar structure C.
次いで、第4図に示すとおシ、順次壁鉄筋網D′を重ね
、反対側の柱構造体A′にも壁筋定着用鉄筋構造体C′
を前同様に挿入結束定着し、壁鉄筋網Dllの一側縁を
同D′に重ねて結束し、かつ、他の側縁を壁筋定着用鉄
筋構造体C′と結束して定着する。Next, as shown in FIG. 4, the wall reinforcing bar network D' is stacked one after another, and the reinforcing bar structure C' for anchoring the wall reinforcing bars is also placed on the column structure A' on the opposite side.
are inserted and bound and fixed in the same way as before, one side edge of the wall reinforcing bar network Dll is overlapped and tied to the wall reinforcing bar network D', and the other side edge is tied and fixed to the wall reinforcing bar structure C'.
その後に、この張設された鉄筋網との平面と平行に所要
の間隔すなわち本実施例では10mの間隔をとって前同
様に壁鉄筋網を順次取付け、第5図の平面図に示すよう
なダブル配筋構造とする。After that, wall reinforcing bars are sequentially installed in the same way as before, parallel to the plane of the stretched reinforcing bar net, at the required intervals, that is, in this example, 10 m intervals, as shown in the plan view of Fig. 5. It will have a double reinforcement structure.
この実施例の柱中心間隔は8000 wx 、−階分の
高さは2700mで、床板Bから突出した差し筋又は継
手筋部材は150m+〜200■間隔であるが、この実
施例に用いる立体的な壁筋定着用鉄筋構造体Cとその取
付は法をよシ詳細に述べると次のとおシである。In this example, the column center spacing is 8,000 wx, the height of the -story is 2,700 m, and the insert or joint reinforcement members protruding from the floor plate B are spaced at intervals of 150 m+ to 200 cm. The reinforcing bar structure C for anchoring wall reinforcements and its installation will be described in detail as follows.
壁筋定着用鉄筋構造体Cは、第6図の見取図に示すとお
りで、コ字状に折曲げ形成された先端部1aから100
mの間隔を距てて平行に延びる一対の延長部1b、lb
’を有する継手鉄筋部材1.1、・・・・・・の複数本
を各延長部1b、Ib’が水平方向に延びるよう上下に
150m又は200 vmの間隔をおいて重畳的に襲列
配置し、上記延長部1b、lb’上の折曲げた先端部1
aから反対端の方に220■距たる個所において上下の
各延長部1b、lb・・・・・・及びlb’、lb’・
・・・・・と直交するよう左右各一本の通し鉄筋部材2
.2′を溶接し一体構造としている。The reinforcing bar structure C for anchoring wall reinforcements is as shown in the sketch of FIG.
A pair of extensions 1b, lb extending in parallel with a distance of m.
A plurality of joint reinforcing bars 1.1, . The bent tip portions 1 on the extension portions 1b and lb'
Upper and lower extensions 1b, lb...and lb', lb', at a distance of 220 cm from a to the opposite end.
One through-reinforcing bar member 2 on the left and right so as to be orthogonal to .
.. 2' are welded to form an integral structure.
上記実施例の壁筋定着用鉄筋構造体c、 c’は複数本
の継手筋部材1となるべき多数本の血筋を150露又は
200露間隔で平行に並列し、これに直交する直紡2本
を約450m距てて溶接し一体の格子状構造体にしてか
ら、上記多数本の血筋の中央をコ字状に二つ折)にし補
助筋aを配して立体構造体に成形したものである。In the wall reinforcement reinforcement structures c and c' of the above embodiments, a large number of blood lines to be a plurality of joint reinforcement members 1 are arranged in parallel at an interval of 150 or 200 lines, and a direct spun 2 is perpendicular to the lines. Books were welded at a distance of about 450 m to form an integrated grid-like structure, and then the center of the many blood lines was folded in half into a U-shape) and auxiliary lines a were arranged to form a three-dimensional structure. be.
この壁筋定着用鉄筋構造体Cは、第2図及び第7.8図
に示すとおり、壁用空間R側から柱構造体Aの中心方向
に向って、上記定着用鉄筋構造体Cを構成する継手鉄筋
部材1.1・・・・・・の先端部la、Ia・・・・・
・が柱構造体Aの鉄骨3、王血筋4を囲むフープ筋5よ
シも十分内部に達して壁筋定着用鉄筋構造体Cを構成す
る通し鉄筋部材2が柱構造体Aの7−プ筋5と当接する
まで差込まれ、両者は適轟間隔をおいた複数個所で結束
される。これによって、あたかも従来の多数本の差し筋
が同時−挙に相互位置及び柱に対する位置を正確に規整
されて取付けられたのと同様の状態になる。通し鉄筋部
材2.2′に溶接された各継手鉄筋部材1.1・・・・
・・は以後のコンクリートの投入によって位置ずれや離
脱を生じない。As shown in FIGS. 2 and 7.8, this wall reinforcement reinforcement structure C is constructed from the wall space R side toward the center of the column structure A. The tip portions la, Ia... of the joint reinforcing bar members 1.1...
- The steel frame 3 of the column structure A and the hoop reinforcements 5 surrounding the blood vessels 4 have also reached the inside of the column structure A, so that the through-reinforcing bar members 2 constituting the wall reinforcement reinforcement structure C are connected to the 7-pipe of the column structure A. It is inserted until it comes into contact with the reinforcement 5, and both are tied together at a plurality of locations with appropriate spacing between them. As a result, a state similar to that in which a large number of conventional reinforcing bars are attached at the same time and with their mutual positions and positions relative to the pillars accurately regulated is achieved. Each joint reinforcing bar member 1.1 welded to the through reinforcing bar member 2.2'...
...will not cause displacement or separation due to subsequent concrete injection.
次に第3図及び第7図に示すとお夛、鉄筋径lO■の縦
筋6及び横筋7を溶接した格子間隔150■又は200
mm、高さ2500m、幅3000日程度の壁鉄筋網り
をクレーン作業その他の手段によって浦込み、その側端
縁付近を柱構造体Aに取付けた壁筋定着用鉄筋構造体C
を構成する各継手鉄筋部材1の延長部1bKfi接させ
、壁鉄筋網りの縦筋6及び横筋7と下床面Bから突出し
ているくし刃状継手筋及び上記継手鉄筋部材lの延長部
1bとを各必要個所で接合する。壁鉄筋網りと定着用鉄
筋構造体Cとの接合は、柱の鉄筋構造体外に約400■
突出した継手用鉄筋部材lの延長部1bと壁鉄筋網り中
の側端縁部の縦筋6二本及び横筋7との重畳部における
適宜の個所を結束して行う。Next, as shown in Fig. 3 and Fig. 7, welded vertical bars 6 and horizontal bars 7 with reinforcing bar diameter 10 cm have a lattice spacing of 150 cm or 200 cm.
Reinforcement structure C for anchoring wall reinforcements, in which a network of wall reinforcements approximately 2,500m in height and 3,000mm in width is inserted by crane work or other means, and the vicinity of the side edges are attached to column structure A.
Extension portion 1bKfi of each joint reinforcing bar member 1 constituting the wall reinforcing bar network is in contact with vertical reinforcement 6 and horizontal reinforcement 7 of the wall reinforcing bar network, comb-like joint reinforcement protruding from the subfloor surface B, and extension portion 1b of the joint reinforcing bar member 1. and are joined at each necessary location. The connection between the wall reinforcing bar network and the anchoring reinforcing bar structure C is approximately 400 mm outside the column reinforcing bar structure.
This is done by tying together appropriate points in the overlapping portion of the extended portion 1b of the protruding reinforcing bar member 1 for the joint and the two vertical bars 6 and the horizontal bars 7 at the side edge portions of the wall reinforcing bar network.
次いで、第4rI!Jに示すように、壁鉄筋網D′を通
常の方法で取付け、続いて取付けた壁筋定着用鉄筋構造
体C′又は既設の構造体C′に壁鉄筋網DIlを前同様
に取付ける。Next, the 4th rI! As shown in J, the wall reinforcing bar network D' is attached in the usual manner, and then the wall reinforcing bar network DIl is attached to the attached wall reinforcing bar anchoring structure C' or the existing structure C' in the same manner as before.
以上で二重鉄筋網のうちの一面の張設を終え、次にこれ
と平行する他の面の壁鉄筋網を前同様の工程によシ取付
けて本工法を終了する。This completes the installation of one side of the double reinforcing bar net, and then the wall reinforcing bar net on the other side parallel to this is installed in the same process as before, completing this construction method.
上述の実施例は、上梁ないし上階の床用鉄筋を後組みし
、壁鉄筋網をダブル配筋する例であるが、上梁等を先組
みしたり壁鉄筋をシングル配筋とする場合にも本工法を
採用できることはいうまでもない。The above example is an example in which the upper beams or floor reinforcing bars on the upper floor are assembled later and the wall reinforcing bar network is double reinforced, but when the upper beams etc. are assembled first or the wall reinforcing bars are single reinforced. It goes without saying that this method can also be applied to
すなわち、壁鉄筋網が一重である場合には、先端をL字
状等に折曲げた継手鉄筋部材の複数本を平行配列し通し
鉄筋部材及びこれに平行する補助筋を溶接した定着用構
造体を用い得るが、前述の実施例に示した構造とシシの
構造体を用いることもできる。後者の場合は壁筋定着用
鉄筋構造体の各継手鉄筋部材の平行する一対の延長部の
間に壁鉄筋網の側端縁部を挿入し、両者の相互位置をス
ペーサで規整して固定すればよい。In other words, when the wall reinforcing bar network is a single layer, a fixing structure is constructed by arranging a plurality of joint reinforcing bars whose tips are bent into an L-shape or the like in parallel, and welding through the reinforcing bar members and auxiliary bars parallel to the reinforcing bars. However, it is also possible to use the structure shown in the above embodiment and the structure of Shishi. In the latter case, insert the side edges of the wall reinforcing bar network between a pair of parallel extensions of each joint reinforcing bar member of the reinforcing bar structure for wall reinforcement anchorage, adjust the mutual position of both with spacers, and fix. Bye.
また、ラチス梁を先組みした構造体に本工法を実施する
例についてコンクリート打設までの工程を含めて述べて
おく2次のとシ)である。In addition, we will discuss an example of implementing this construction method on a structure pre-assembled with lattice beams, including the process up to concrete pouring.
すなわち、この場合には第9図に示すとおり、壁鉄筋網
りを一重又は二重に張設し、その縦筋上端のくし刃状突
出部分をアングル材8、平板材9及びラチス筋lOから
力るラチス架空に差込む。That is, in this case, as shown in Fig. 9, the wall reinforcing bar network is stretched in single or double layers, and the comb-like protruding portions at the upper ends of the vertical bars are connected to the angle members 8, the flat plate members 9, and the lattice bars 10. Insert the force lattice into the imaginary.
この状態で上階の床板格子鉄筋11又は上端筋を配設し
、第6図に示した壁筋定着用鉄筋構造体Cで補助筋aを
設けないものをその継手鉄筋部材1の先端部1aが上に
なるように向けてラチス梁の上方から梁中に差込むと、
通し鉄筋部材2が床板格子鉄筋11に当接してとまった
位置で固定する。In this state, the floor plate lattice reinforcement 11 or upper end reinforcement of the upper floor is arranged, and the wall reinforcement reinforcement structure C shown in FIG. Insert it into the beam from above the lattice beam with the side facing up.
The through reinforcing bar member 2 is fixed at the position where it comes into contact with the floor plate lattice reinforcing bar 11.
そうすると、多数本の差し筋を一挙に取付けたのと同じ
構成となシ、−々の差し筋を用いる場合と異なシ、その
一部の位置ずれ離脱などのおそれがなくなる。その後に
柱、床板及び壁のコンクリートを同時打設すると、その
床面上に前記鉄筋構造体Cを構成する継手鉄筋部材1の
延長部1bが先端部1aを上に向は並列露呈して立設さ
れるから、これに上階の壁鉄筋網の縦筋を結束接合し、
前同様に上階について本工法を施工できる。In this case, the structure is the same as that of attaching a large number of reinforcing bars at once, and there is no fear that some of the reinforcing bars may become misaligned or detached, which is different from the case where multiple insert reinforcing bars are used. After that, when concrete is poured for columns, floor plates, and walls at the same time, the extension part 1b of the joint reinforcing bar member 1 constituting the reinforcing bar structure C stands on the floor surface with the tip part 1a exposed upward and in parallel. The vertical bars of the wall reinforcing bar network on the upper floor are bound and connected to this.
As before, this construction method can be applied to the upper floors.
これらの工法に用いる壁筋定着用構造体の具体的構成位
前述の実施例に限定されるものではない。The specific structure of the wall reinforcement anchoring structure used in these construction methods is not limited to the above-mentioned embodiments.
継手鉄筋部材として太径のものと細径のものを併用して
よく、その折曲げ先端部の形状や形成方法も自由であル
、これを延長部の両端に設けることもできる。延長部の
一端のみに折曲げ先端部があるものでは上記先端部を上
下適宜逆向きにしてもよい。延長部は実質的に水平方向
に延びていれば足シ、一部分に傾斜わん曲等があるとと
も差支えない。各継手鉄筋部材間の間隔を壁鉄筋網の横
筋の間隔の整数倍とするとともできる。As the joint reinforcing bar member, one with a large diameter and one with a small diameter may be used in combination, and the shape and formation method of the bent end portion can be freely determined, and these can be provided at both ends of the extension portion. If only one end of the extension has a bent tip, the tip may be oriented vertically in the opposite direction. As long as the extension part extends substantially in the horizontal direction, there is no problem even if the extension part has a sloping curve or the like in a part of the extension part. The spacing between each joint reinforcing bar member may be an integral multiple of the spacing between the horizontal bars of the wall reinforcing bar network.
以上述べ九とおシ、本工法の特徴は、一本の柱に壁鉄筋
網を取付は定着するに轟って、従来工法と異なシ一体構
造の壁筋定着用鉄筋構造体を用い、これを柱に取付ける
ことによって、−挙に多数本の継手鉄筋部材を位置固定
し、それらの延長部に壁鉄筋網の側縁部を取付けるとこ
ろにある。As mentioned above, the feature of this construction method is that the installation of wall reinforcing bars on a single pillar is fixed, and it uses a reinforcing bar structure for anchoring wall bars of an integral structure, which is different from conventional construction methods. By attaching it to the column, a large number of joint reinforcing bars are fixed in position, and the side edges of the wall reinforcing bar network are attached to their extensions.
この工程を各所で同時又は屓次に行うか、この工程に関
与しない壁鉄筋その他の構造部材の取付けをどの段階で
行うかは適宜状況に応じ選択すればよい。なお、通常の
壁鉄筋網をダブル配筋する場合には、従来の順序とは反
対に、まず壁筋定着用鉄筋構造体を柱構造体に取付けて
から、これに壁鉄筋網を取付けることになる。Depending on the situation, it is appropriate to select whether this step is to be carried out at various locations simultaneously or sequentially, or at what stage wall reinforcing bars and other structural members that are not involved in this step are to be installed. In addition, when double reinforcing a normal wall reinforcing bar network, contrary to the conventional order, first attach the wall reinforcing bar structure to the column structure, and then attach the wall reinforcing bar network to this. Become.
(効果)
以上のとおシ、本工法は壁鉄筋網を柱構造体に定着固定
するために、両者の間に一々各個の差し筋を取付けるこ
とによって生ずる現場工事の繁絨化と遅れを解消する。(Effects) As described above, this construction method eliminates the complexity and delay in on-site construction caused by installing individual reinforcing bars between the wall reinforcing bars and the column structure in order to fix them to the column structure. .
すなわち、−個の壁筋定着用鉄筋構造体を柱に取付ける
ことによって、あたかも多数本の差し筋を一挙に挿入す
るのに比敵する工事の迅速化をもたらす。That is, by attaching - number of reinforcing bar structures for anchoring wall bars to columns, the construction work can be completed more quickly than if a large number of reinforcing bars were inserted all at once.
また、上記壁筋定着用鉄筋構造体は所定寸法仕様によっ
て溶接された一体物であるから、継手鉄筋部材相互間の
位置決めが極めて正確でTo)、取付けに当って一々面
倒な柱との位置合わせを要しない。とくに、壁鉄筋網を
二重に張設するときは、継手鉄筋部材の延長部の間隔が
正確なので、それ自体が壁鉄筋網の間隔を保持するスペ
ーサとしての作用をする。In addition, since the above-mentioned reinforcing bar structure for anchoring wall reinforcement is an integral piece welded according to predetermined dimensional specifications, the positioning of the joint reinforcing bar members is extremely accurate (To), and the positioning with the pillars is difficult during installation. does not require In particular, when the wall reinforcing bar network is installed in double tension, the intervals between the extensions of the joint reinforcing bar members are accurate, so that the extensions of the joint reinforcing bar members themselves act as spacers to maintain the spacing between the wall reinforcing bar networks.
しかも、壁筋定着用鉄筋構造体の継手鉄筋部材と通し鉄
筋部材とが一体に溶接されているので、コンクリートの
投入その他の外力によって一部の継手鉄筋部材の位置ず
れや離脱などの現象が生じない。Moreover, since the joint reinforcing bars and the through reinforcing bars of the wall reinforcement reinforcement structure are welded together, some of the joint reinforcing bars may shift or come off due to concrete injection or other external forces. do not have.
なお、本工法によれば、柱間の間隔が広く一面に数枚以
上の壁鉄筋網を張設する場合にも、多くて三種類の寸法
仕様の鉄筋網を用意すれば足シるから、その管理等も容
易になる利点がある。Furthermore, according to this construction method, even when installing several or more wall reinforcing bars on one wall with wide spacing between columns, it is sufficient to prepare reinforcing bars with at most three different dimensional specifications. This has the advantage of making its management easier.
第1〜4図は、本発明にかかる工法の一例の概略順序を
示す建物構造体の正面図、同第5図は第4図に相当する
平面図、第6図は本工法に用いる鉄筋構造体の一例の見
取図、第7.8図は、第3図の一部の詳細正面図と平面
図、第9図は、ラチス梁を先組みした場合の本工法の一
例の説明図である。
A、 A’・・・柱構造体、B・・・下床板、R・・・
壁用空間、C・・・壁筋定着用鉄筋構造体、D% l)
’、 D/l・・・壁鉄筋網、3・・・柱鉄骨、4・・
・柱ミ筋、5・・・7−プ筋、1・・・継手鉄筋部材、
la・・・同先端部、lb・・・同延長部、2・・・通
し鉄筋部材、6・・・壁鉄筋網縦筋、7・・・同横筋、
8・・・アングル材、9・・・平板材、lO・・・2チ
ス筋、11・・・床用格子鉄筋Figures 1 to 4 are front views of building structures showing the general sequence of an example of the construction method according to the present invention, Figure 5 is a plan view corresponding to Figure 4, and Figure 6 is the reinforcing steel structure used in this construction method. FIG. 7.8 is a sketch of an example of the structure, and FIG. 7.8 is a detailed front view and plan view of a part of FIG. A, A'...Column structure, B...Subfloor board, R...
Wall space, C...Reinforced structure for wall reinforcement, D% l)
', D/l...Wall reinforcement network, 3...Column steel frame, 4...
・Column reinforcement, 5...7-pu reinforcement, 1...joint reinforcing bar member,
la... the same tip, lb... the same extension part, 2... the through reinforcing bar member, 6... the wall reinforcing bar network vertical reinforcement, 7... the same horizontal reinforcement,
8... Angle material, 9... Flat plate material, lO... 2-chiss bar, 11... Floor lattice reinforcing bar
Claims (1)
をおいて上下に重畳配列した複数本の継手鉄筋部材とこ
れらの部材の上下に配置した延長部に直交する通し鉄筋
部材を溶接連結して一体化した壁筋定着用鉄筋構造体を
、その継手鉄筋部材の上記先端部が柱の鉄筋又は鉄骨・
鉄筋構造体の壁用空間側鉄筋囲い内部に収まるよう挿入
して定着固定し、かつ、上記定着用鉄筋構造体を構成す
る継手鉄筋部材の延長部と壁用空間に建込まれた壁鉄筋
網の側縁部とを重ね合わせて定着固定することを特徴と
する壁鉄筋組付け工法A plurality of joint reinforcing bars in which extensions extending laterally from the bent tips are stacked vertically at intervals are connected by welding to through reinforcing bars arranged above and below these members and perpendicular to the extensions. The above-mentioned tip of the joint reinforcing bar member is a column reinforcing bar or a steel frame.
A wall reinforcing bar network that is inserted and fixed in such a way that it fits inside the reinforcing bar enclosure on the wall space side of the reinforcing bar structure, and that is built in the extension of the joint reinforcing bar member that constitutes the anchoring reinforcing bar structure and the wall space. A wall reinforcing bar assembly method characterized by overlapping and fixing the side edges of
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8463085A JPS61246472A (en) | 1985-04-22 | 1985-04-22 | Wall reinforcing bar assembling method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8463085A JPS61246472A (en) | 1985-04-22 | 1985-04-22 | Wall reinforcing bar assembling method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS61246472A true JPS61246472A (en) | 1986-11-01 |
JPH0437903B2 JPH0437903B2 (en) | 1992-06-22 |
Family
ID=13836001
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8463085A Granted JPS61246472A (en) | 1985-04-22 | 1985-04-22 | Wall reinforcing bar assembling method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS61246472A (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5998976A (en) * | 1982-11-29 | 1984-06-07 | 株式会社 長谷川工務店 | Anchoring of wall skeletal of scene cast src structure |
-
1985
- 1985-04-22 JP JP8463085A patent/JPS61246472A/en active Granted
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5998976A (en) * | 1982-11-29 | 1984-06-07 | 株式会社 長谷川工務店 | Anchoring of wall skeletal of scene cast src structure |
Also Published As
Publication number | Publication date |
---|---|
JPH0437903B2 (en) | 1992-06-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS61246472A (en) | Wall reinforcing bar assembling method | |
JP2651322B2 (en) | Construction method of wall type rigid frame structure | |
JPH1025840A (en) | Constructing method for building frame with precast anti-seismic wall | |
JPH0452321Y2 (en) | ||
KR102175474B1 (en) | Rebar assembly | |
JPS61207739A (en) | Reinforced concrete construction method and beam cross part hoop clamp tool used therein | |
JPS61169559A (en) | Semi-existing concrete panel using assembled reinforcement | |
JP2651321B2 (en) | Anchoring method of beam in wall type rigid frame structure | |
JPS61246436A (en) | Wall and reinforcing bar assembling construction method | |
JPS62133237A (en) | Precast structural member | |
JPH06306977A (en) | Precast wall form, earthquake-resisting wall using this form and execution method thereof | |
JPS628295Y2 (en) | ||
JPH0967899A (en) | Reinforcement cage and assembling method therefor | |
JPH0463184B2 (en) | ||
JPS61225468A (en) | Reinforcing bar arranging method in reinforced concrete pillar | |
JPS63289140A (en) | Construction method for anchoring main bar of reinforced concrete beam | |
JP2000303552A (en) | Reinforcing cage erecting method | |
JPS62121249A (en) | Construction of pillar/beam connection part | |
JPS6131546A (en) | Construction of floor slab | |
JPS60219347A (en) | Construction of precast concrete floor and precast truss plate used therein | |
JPH01187237A (en) | Method for beam-column joining in precast reinforced concrete structure | |
JPH0427036A (en) | Method for constructing reinforced concrete beam | |
JPS6311768A (en) | Beam reinforcing bar assembling method | |
JPS6213627A (en) | Construction of pc small beam | |
JPH08114003A (en) | Reinforcing structural body for half pc plate |