JPS63289140A - Construction method for anchoring main bar of reinforced concrete beam - Google Patents

Construction method for anchoring main bar of reinforced concrete beam

Info

Publication number
JPS63289140A
JPS63289140A JP12214687A JP12214687A JPS63289140A JP S63289140 A JPS63289140 A JP S63289140A JP 12214687 A JP12214687 A JP 12214687A JP 12214687 A JP12214687 A JP 12214687A JP S63289140 A JPS63289140 A JP S63289140A
Authority
JP
Japan
Prior art keywords
reinforced concrete
column
main
construction method
concrete beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12214687A
Other languages
Japanese (ja)
Inventor
雅夫 高野
豊 斉藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP12214687A priority Critical patent/JPS63289140A/en
Publication of JPS63289140A publication Critical patent/JPS63289140A/en
Pending legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は鉄筋コンクリート柱に、鉄筋コンクリート梁
の主筋を定着する工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a construction method for fixing the main reinforcement of a reinforced concrete beam to a reinforced concrete column.

〔従来の技術〕[Conventional technology]

高層の鉄筋コンクリート構造の建築物では、柱及び梁の
主筋として大径鉄筋が使用されることが多い。また梁主
筋は鉄筋の端部を下向きに折曲して柱内に定着している
In high-rise buildings with reinforced concrete structures, large-diameter reinforcing bars are often used as the main reinforcement for columns and beams. In addition, the main beam reinforcement is fixed in the column by bending the end of the reinforcing bar downward.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

上記梁主筋の定着工法では、柱、梁の交差部分のパネル
領域に太い鉄筋が集中するため、パネル領域の施工性が
悪く、また鉄筋とコンクリートとの付着力も劣化するな
どの問題を有する。
In the above-described beam main reinforcement anchoring method, thick reinforcing bars are concentrated in the panel area at the intersection of columns and beams, which causes problems such as poor workability in the panel area and deterioration of the adhesion between the reinforcing bars and concrete.

この発明は上記従来の問題点を解決するために考えられ
たものであって、その目的はli筋の定着を従来工法よ
りも容易にでき、またパネル領域鉄筋の密集を避けてコ
ンクリートの付着力を増大させることができる新たな工
法を提供づることにある。
This invention was devised in order to solve the above-mentioned conventional problems, and its purpose is to make it easier to fix the Li-bars than in the conventional construction method, and to avoid the crowding of reinforcing bars in the panel area, thereby increasing the adhesion of concrete. The objective is to provide a new construction method that can increase the

〔問題点を解決するための手段〕[Means for solving problems]

上記目的によるこの発明は、中央部にコンクリート流動
孔を有し、側辺に複数の受は片を平行に突設した鋳造板
を、鉄筋コンクリート社の柱梁接合部に水平に設置し、
上記各受片に梁の主筋を載置して鉄筋コンクリート社に
梁を架設するとともに、受片と梁主筋とを一体に溶接す
ることによって、上記問題点を解決してなる。
This invention for the above purpose installs a cast plate having a concrete flow hole in the center and a plurality of support pieces protruding in parallel on the sides horizontally at the column-beam joint of Reinforced Concrete Co., Ltd.
The above-mentioned problems are solved by placing the main reinforcement of the beam on each of the receiving pieces and erecting the beam at a reinforced concrete company, and by welding the receiving pieces and the main beam reinforcement together.

〔作 用〕[For production]

上記工法では、梁主筋が鋳造板を介して柱主筋に定着さ
れるので、パネル領域に鉄筋が集中せず、また全ての梁
主筋を同一レベルにて定着することができる。
In the above construction method, the beam main reinforcements are fixed to the column main reinforcements through the cast plate, so the reinforcing bars are not concentrated in the panel area, and all the beam main reinforcements can be fixed at the same level.

〔実施例〕〔Example〕

図中1は鉄筋コンクリート柱、2は社主筋、3はプレキ
ャストコンクリートの大梁、4は梁主筋、5は鋳造板で
ある。
In the figure, 1 is a reinforced concrete column, 2 is a main reinforcement, 3 is a precast concrete beam, 4 is a beam main reinforcement, and 5 is a cast plate.

上記鋳造板5は鉄筋コンクリート柱1の横断面内に収ま
る寸法の正方形からなり、四隅面内に柱主筋2を複数本
ずつ挿入することができる挿通孔6.6を有する。また
中央部にコンクリート流動孔7が穿設してあり、板面に
はコンクリートとの付着性を良くするために多数のりブ
8.8が形成しである。
The cast plate 5 has a square shape that fits within the cross section of the reinforced concrete column 1, and has insertion holes 6.6 in its four corner surfaces into which a plurality of column main reinforcements 2 can be inserted. A concrete flow hole 7 is drilled in the center, and a number of ribs 8, 8 are formed on the plate surface to improve adhesion to concrete.

この鋳造板5の西側辺には、所要長さの上向きに弯曲し
た受片9が3片ずつ平行に突設してあり、この各受片9
.9に上記梁主筋4.4が載置され、更に溶接により一
体に接続される。
On the west side of the cast plate 5, three upwardly curved receiving pieces 9 of a required length are protruded in parallel.
.. The beam main reinforcing bars 4.4 are placed on 9 and are further connected together by welding.

第5図に示す鋳造板5は、柱主筋2が配筋し易いように
四隅部をカットしたものからなる。
The cast plate 5 shown in FIG. 5 is made by cutting the four corners so that the main column reinforcements 2 can be easily arranged.

しかして大梁3の架設は、まず鋳造板5を鉄筋コンクリ
ート1の上端に露出した柱主筋2.2に挿通して定むす
る。
Therefore, the erection of the girder 3 is determined by first inserting the cast plate 5 through the column main reinforcing bars 2.2 exposed at the upper end of the reinforced concrete 1.

次に大梁3を吊込んで梁主鉄4.4の端部を各受片9.
9に載置し、更に溶接により梁主鉄4.4と受片9.9
とをそれぞれ溶接して定着を行う。
Next, suspend the girder 3 and attach the ends of the beam main iron 4.4 to each receiving piece 9.
9, and further welded the beam main iron 4.4 and the receiving piece 9.9.
and are respectively welded and fixed.

〔発明の効果〕〔Effect of the invention〕

この発明は上述のように、鉄筋コンクリート柱の柱梁接
合部に水平に鋳造板を設置し、その鋳造板を介して鉄筋
コンクリート梁の主筋を、鉄筋コンクリート柱の主筋に
定着してなることから、パネル領域に鉄筋が集中するこ
とがなく、太径の鉄筋を利用した場合であっても施工性
が悪くなったり、鉄筋とコンクリートの定着性能が劣化
するようなことがない。
As described above, this invention installs a cast plate horizontally at the column-beam joint of a reinforced concrete column, and fixes the main reinforcement of the reinforced concrete beam to the main reinforcement of the reinforced concrete column through the cast plate. There is no concentration of reinforcing bars in the area, and even when using large-diameter reinforcing bars, there is no problem of poor workability or deterioration of the fixing performance of the reinforcing bars and concrete.

また通常工法では交差する二方向の梁の主筋定着に際し
ては、柱梁接合部において、両方の梁の主筋が相互に重
なるため、レベル差を付ける必要があるが、鋳造板を介
しての定着にあっては、全ての梁の主筋を同一レベルに
て定着することができるので、レベル差を付けずに施工
ができ、この結果、大梁の構造性能が一段と向上し、ま
た施工も容易となるなどの特長を有する。
In addition, in normal construction methods, when fixing the main reinforcement of beams in two directions that intersect, it is necessary to make a difference in level because the main reinforcement of both beams overlaps each other at the column-beam joint. In this case, the main reinforcing bars of all beams can be fixed at the same level, so construction can be carried out without making any difference in level. As a result, the structural performance of the girders is further improved, and construction is also easier. It has the following features.

【図面の簡単な説明】[Brief explanation of the drawing]

図面はこの発明に係る鉄筋コンクリート梁主筋定着工法
の1実施例を示すもので、第1図及び第2図は工程説明
図、第3図は第1図の平面図、第4図は第2図の平面図
、第5図は他の実施例の鋳造板の平面図である。 1・・・鉄筋コンクリート柱 2・・・柱主筋 3・・・大梁        4・・・梁主筋5・・・
鋳造板       6・・・挿通孔7・・・コンクリ
ート流動孔 8・・・リブ9・・・受片 第1図   第3図 第2図
The drawings show one embodiment of the reinforced concrete beam main bar anchoring method according to the present invention, and FIGS. 1 and 2 are process explanatory diagrams, FIG. 3 is a plan view of FIG. 1, and FIG. 4 is a diagram of FIG. 2. FIG. 5 is a plan view of a cast plate of another embodiment. 1... Reinforced concrete column 2... Column main reinforcement 3... Beam 4... Beam main reinforcement 5...
Cast plate 6... Insertion hole 7... Concrete flow hole 8... Rib 9... Receiving piece Fig. 1 Fig. 3 Fig. 2

Claims (1)

【特許請求の範囲】[Claims] 中央部にコンクリート流動孔を有し、側辺に複数の受片
を平行に突設した鋳造板を、鉄筋コンクリート柱の柱梁
接合部に水平に設置し、上記各受片に梁の主筋を載置し
て鉄筋コンクリート柱に梁を架設するとともに、受片と
梁主筋とを一体に溶接することを特徴とする鉄筋コンク
リート梁主筋定着工法。
A cast plate with a concrete flow hole in the center and multiple support pieces protruding in parallel on the sides is installed horizontally at the column-beam joint of a reinforced concrete column, and the main reinforcement of the beam is placed on each of the support pieces. A method for anchoring reinforced concrete beam main bars, which is characterized in that the beam is erected on a reinforced concrete column by placing the beam on the ground, and the support pieces and the beam main reinforcement are integrally welded.
JP12214687A 1987-05-19 1987-05-19 Construction method for anchoring main bar of reinforced concrete beam Pending JPS63289140A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12214687A JPS63289140A (en) 1987-05-19 1987-05-19 Construction method for anchoring main bar of reinforced concrete beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12214687A JPS63289140A (en) 1987-05-19 1987-05-19 Construction method for anchoring main bar of reinforced concrete beam

Publications (1)

Publication Number Publication Date
JPS63289140A true JPS63289140A (en) 1988-11-25

Family

ID=14828745

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12214687A Pending JPS63289140A (en) 1987-05-19 1987-05-19 Construction method for anchoring main bar of reinforced concrete beam

Country Status (1)

Country Link
JP (1) JPS63289140A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016035178A (en) * 2014-08-04 2016-03-17 日之出水道機器株式会社 Beam connection panel, column reinforcement connection panel, and reinforcement structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016035178A (en) * 2014-08-04 2016-03-17 日之出水道機器株式会社 Beam connection panel, column reinforcement connection panel, and reinforcement structure

Similar Documents

Publication Publication Date Title
JP2000144896A (en) Construction method of rahmen frame using beam having step difference
JPH0441829A (en) Pillar/beam joint and its execution method
JPS63289140A (en) Construction method for anchoring main bar of reinforced concrete beam
CN210238769U (en) Assembled concrete frame node
KR101193074B1 (en) Method of strengthening foundation where above main structure is reinforced with external load bearing precast concrete wall panel
JP2000291289A (en) Joining structure of earthquake resistant member
CN217538101U (en) Energy consumption node of integrated mild steel damper
CN209025261U (en) A kind of L-type steel wood composite shear wall connecting node
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JPS61229070A (en) Connection of reinforced concrete structure
JP2000034780A (en) Column structure
JPH01137032A (en) Method of lap joint construction of main reinforcement in post and beam joining section
JPS61102939A (en) Connection of precast concrete member
JPH01187237A (en) Method for beam-column joining in precast reinforced concrete structure
JP2562779Y2 (en) Joint structure between column and beam
JPS6375231A (en) Building housing
JPH03217541A (en) Column/slab jointing construction in flat slab structure
JP2674442B2 (en) Structure of column-beam joint of steel reinforced concrete structure
CN117266448A (en) Composite beam, composite beam manufacturing method, and composite beam manufacturing system
CN110258819A (en) A kind of connecting node and its construction method of reinforced column and arch without beam
JPH05321404A (en) Reinforcement for beam through hole
JPH01198950A (en) Shear reinforcing structure around pillar head of flat plate slab
JPS61286429A (en) Connection of pc pillar and beam
JPH03241138A (en) Jointing structure of steel pipe column and slab in flat slab structure
JPH0468419B2 (en)