JPS6119764B2 - - Google Patents

Info

Publication number
JPS6119764B2
JPS6119764B2 JP57022814A JP2281482A JPS6119764B2 JP S6119764 B2 JPS6119764 B2 JP S6119764B2 JP 57022814 A JP57022814 A JP 57022814A JP 2281482 A JP2281482 A JP 2281482A JP S6119764 B2 JPS6119764 B2 JP S6119764B2
Authority
JP
Japan
Prior art keywords
caisson
support pile
pile
piles
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP57022814A
Other languages
Japanese (ja)
Other versions
JPS58143023A (en
Inventor
Masutoshi Yudasaka
Yoshihiro Manabe
Takao Tanogami
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2281482A priority Critical patent/JPS58143023A/en
Publication of JPS58143023A publication Critical patent/JPS58143023A/en
Publication of JPS6119764B2 publication Critical patent/JPS6119764B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/20Caisson foundations combined with pile foundations

Description

【発明の詳細な説明】 現今、海洋環境を保全しつつ大水深で海象、土
質条件の悪い地点での港湾技術の開発が要望され
ている。特にヘドロ等の堆積した軟弱地盤におい
ては、ヘドロ除去の環境問題、地盤改良等の経済
性の問題等が大きな課題となつている。現に重力
式の安定によつて防波堤構造物を施工すると、地
盤改良、マウンド造成等に多大のコストと工期と
を必要としている。
[Detailed Description of the Invention] Currently, there is a demand for the development of port technology that can be used at deep water locations with poor sea and soil conditions while preserving the marine environment. In particular, in soft ground where sludge and the like have accumulated, environmental problems in removing sludge and economic problems in ground improvement, etc., have become major issues. In fact, when a breakwater structure is constructed using gravity stabilization, a large amount of cost and construction time is required for ground improvement, mound creation, etc.

本発明はこのような欠点を除去するために提案
されたもので、四隅に昇降把持装置を介してスパ
ツドが昇降自在に嵌挿され、底版には支持杭貫入
孔が配設されてなり、ケーソン設置後は前記スパ
ツドが杭として使用されるように構成されたこと
を特徴とする杭支持式防波堤用ケーソンに係るも
のである。
The present invention has been proposed in order to eliminate these drawbacks, and consists of a spud that is inserted into the four corners of the caisson so that it can be raised and lowered via lifting and lowering gripping devices, and a support pile penetration hole is provided in the bottom plate. The present invention relates to a pile-supported breakwater caisson, characterized in that the spuds are configured to be used as piles after installation.

本発明に係るケーソンは前記したように構成さ
れているので、所定位置まで曳航したのち、前記
昇降把持装置によつてケーソンに昇降自在に嵌挿
されたスパツドを降下して着底せしめたのち、ケ
ーソン内に注水すると同時に、前記昇降把持装置
を作動してケーソンを所定位置まで沈降させるこ
とによつて施工中のケーソン部分の固定を確実な
らしめ、この状態で前記底版に配設された支持杭
貫入孔より支持杭を所定の支持層まで貫入し、同
支持杭によつてケーソンを支持するものであり、
この際前記スパツドをも支持杭として利用するも
のである。
Since the caisson according to the present invention is constructed as described above, after being towed to a predetermined position, the spud, which is fitted into the caisson so that it can be raised and lowered, is lowered by the lift gripping device and landed on the bottom. At the same time as water is poured into the caisson, the elevating and lowering gripping device is operated to lower the caisson to a predetermined position, thereby ensuring the fixation of the caisson part under construction. A support pile is inserted through the penetration hole to a specified support layer, and the caisson is supported by the support pile.
At this time, the spuds are also used as support piles.

本発明によればこのように、所定位置まで曳航
されたケーソンを、同ケーソンに貫挿されたスパ
ツド及び支持杭を介して海底支持層上に支持する
ようにしたので、地盤改良を施すことなく、軟弱
地盤上に防波構造物を構築しうるものであり、支
持杭をケーソン底版の支持杭貫入孔を利用してケ
ーソン内に建込んだ状態で所定位置まで曳航し、
直ちに支持杭に打設を行なうことができるので、
施工期間を短縮しうるものである。
According to the present invention, the caisson that has been towed to a predetermined position is supported on the seabed support layer via the spuds and support piles inserted into the caisson, so there is no need to perform ground improvement. , it is possible to construct a wave-break structure on soft ground, and the support pile is built inside the caisson using the support pile penetration hole of the caisson bottom slab and then towed to the specified position.
Support piles can be driven immediately, so
This can shorten the construction period.

また水中のケーソン底版附近において支持杭の
回転を拘束するため、その自由突出長を短かくで
き、更に直杭のみならず斜杭の施工も可能であつ
て外力作用時の変形を小さくでき、前記スパツド
をして杭を兼用せしめることと相俟つて経済的な
基礎杭を施工しうるものである。
In addition, since the rotation of the support pile is restrained near the submerged caisson bottom plate, its free protrusion length can be shortened, and not only straight piles but also oblique piles can be constructed, and deformation when external forces are applied can be reduced. In combination with the use of spuds to double as piles, it is possible to construct foundation piles economically.

また本発明によれば、陸上で製作したケーソン
が構造物の外郭体となるので、大型構造物を急速
施工することができ、現地の施工期間を短縮しう
るものである。
Further, according to the present invention, since the caissons manufactured on land serve as the outer shell of the structure, large structures can be rapidly constructed, and the on-site construction period can be shortened.

なお本発明のケーソンを透過型とすることによ
つて海水の流動を防げずに消波できるので環境保
全に有利であり、また前面壁または背面壁に防舷
材を設けることによつて繋船岸を兼ねた防波構造
物とすることができ、更に前面面壁にスリツト
孔、ケーソン内部に遊水部を設けることによつて
波の反射率を著しく低減することができ、附近の
船舶航行及び漁業操業に対して障害を招来しな
い。
By making the caisson of the present invention a transparent type, it is possible to dissipate waves without preventing the flow of seawater, which is advantageous for environmental conservation.Also, by providing fenders on the front or rear wall, it is possible to dissipate waves without preventing the flow of seawater. Furthermore, by providing slit holes in the front wall and a retarding section inside the caisson, wave reflectivity can be significantly reduced, making it difficult for nearby ship navigation and fishing operations. Do not cause any problems.

本発明はまた前記ケーソンにおいて、底版に配
設された支持杭貫入孔が、水圧に対してのみ耐
え、柱の落下によつて打抜かれる仮蓋で閉塞され
たことを特徴とし、前記貫入孔をケーソン曳航時
の水圧に耐えるようにしてケーソンに浮力を賦与
し、所定位置までのケーソンの曳航が円滑に遂行
されるようにするとともに、前記貫入孔より支障
なく支持杭の貫入作業が遂行されるようにするも
のである。
The present invention is also characterized in that in the caisson, the support pile penetration hole provided in the bottom slab is closed with a temporary cover that withstands only water pressure and is punched out when the column falls, and the penetration hole is buoyancy is imparted to the caisson by making it withstand water pressure when the caisson is towed, so that the caisson can be towed smoothly to a predetermined position, and the work of penetrating the support pile through the penetration hole can be carried out without any hindrance. The purpose is to ensure that

以下本発明を図示の実施例について説明する。 The present invention will be described below with reference to the illustrated embodiments.

Aはコンクリート製ケーソンで、それ自体完成
構造物の躯体を構成するものであり、その四隅部
にはスパツド1が配設され、公知の昇降把持機構
Bを介して昇降自在に支持されている。
A is a concrete caisson which itself constitutes the frame of the completed structure, with spuds 1 disposed at its four corners and supported so as to be able to rise and fall via a known elevating and lowering gripping mechanism B.

ケーソンAの底版2には支持杭貫入孔3が穿設
されていて、支持杭を建込んだまま曳航する場合
には前記貫入孔3の延長上にケーシングパイプ4
を取付けてこれによつて例えば鋼管杭より構成さ
れた支持杭5を仮支持する。また前記貫入孔3
は、浮遊曳航の場合、曳航時の水圧に耐えるよう
に、底版2下面においてボルトによつて仮支持さ
れた仮蓋6によつて封塞される。
A support pile penetration hole 3 is bored in the bottom slab 2 of the caisson A, and when towing with the support pile installed, a casing pipe 4 is drilled on the extension of the penetration hole 3.
This temporarily supports the support pile 5 made of, for example, a steel pipe pile. In addition, the penetration hole 3
In the case of floating towing, the bottom plate 2 is sealed by a temporary cover 6 temporarily supported by bolts on the lower surface of the bottom plate 2 so as to withstand water pressure during towing.

なお消波型ケーソンとする場合には、ケーソン
Aの前面壁に必要条件に応じた開口率を有する縦
スリツト孔7が設けられ、落し鉄板8が嵌装され
ている。また透明型の消波体とする場合には、前
面壁、背面壁共に縦スリツトを設け、現地完成後
必要に応じて内部に応じて栗石、砕石等を中詰す
る。
In the case of a wave-dissipating type caisson, a vertical slit hole 7 having an aperture ratio according to necessary conditions is provided in the front wall of the caisson A, and a drop iron plate 8 is fitted therein. In the case of a transparent wave absorber, vertical slits will be provided in both the front and rear walls, and the interior will be filled with chestnut stone, crushed stone, etc. as necessary after construction is completed on site.

(第1図及び第2図参照) 而してケーソンAにおけるスパツド1を配設し
た区劃のみ上下両面開放してスパツド1の昇降を
自由ならしめておき、前面壁または背面壁にスリ
ツト部を有する場合には、前記のように落し鉄板
8またはゴム板を嵌装して水の浸入を防止する。
(See Figures 1 and 2) Only the section of the caisson A where the spud 1 is installed is left open on both the top and bottom to allow the spud 1 to move up and down freely, and has a slit section on the front or back wall. In such a case, a drop iron plate 8 or a rubber plate is fitted as described above to prevent water from entering.

浮遊曳航の場合には底版2の支持杭貫入孔3に
仮蓋6を設け、スパツド1及び支持杭5を建込ん
だ状態で所定位置までケーソンAを曳航する。ま
た圧気曳航の場合には底版、上床版共に支持杭貫
入孔を設け、上床版に仮蓋をして曳航するか、底
版にのみ前記貫入孔を設けておいて圧気蓋をして
ケーソンを所定位置まで曳航する。なお図中Cは
曳船である。(第3図参照) かくしてケーソンAを所定位置まで曳航したの
ち、同ケーソンAを曳船、アンカーワイヤーによ
つて位置決めを行ない。次いでスパツド1を昇降
把持機構Bによつて下降させ、着底せしめる。ス
パツド1の着底後、ケーソンA内に注水すると同
時に前記昇降把持装置Bを作動してケーソンAを
所定位置まで沈降させる。なお地盤が洗掘される
可能性のある場合、アスフアルトマツト等によつ
て洗掘防止施工を行う。(第4図参照) 次いで仮支持していた支持杭5のケーシングパ
イプ4と同支持杭5との支点を外すことによつ
て、支持杭5が落下して前記貫入孔2の仮蓋6を
外し、同支持杭5の自由沈下後、オフシヨンハン
マーまたはバイブロハンマーを使用して所定の支
持層まで支持杭5を打設する。図中Dは杭打船で
ある。
In the case of floating towing, a temporary cover 6 is provided over the support pile penetration hole 3 of the bottom slab 2, and the caisson A is towed to a predetermined position with the spud 1 and support pile 5 erected. In the case of pneumatic towing, support pile penetration holes are provided in both the bottom slab and the top slab, and the top slab is temporarily covered for towing, or the penetration holes are provided only in the bottom slab and a pneumatic cap is provided to secure the caisson in place. Towed to location. Note that C in the figure is a tugboat. (See Figure 3) After caisson A was towed to a predetermined position, caisson A was positioned using the towboat and anchor wire. Next, the spud 1 is lowered by the elevating and lowering gripping mechanism B, and is brought to the bottom. After the spud 1 reaches the bottom, water is poured into the caisson A and at the same time the elevating and lowering gripping device B is operated to lower the caisson A to a predetermined position. If there is a possibility that the ground will be scoured, construction will be carried out to prevent scouring using asphalt mats, etc. (See Figure 4) Next, by removing the fulcrum between the casing pipe 4 of the temporarily supported support pile 5 and the support pile 5, the support pile 5 will fall and cover the temporary cover 6 of the penetration hole 2. After removing the support pile 5 and allowing the support pile 5 to sink freely, use an offset hammer or a vibrohammer to drive the support pile 5 to a predetermined support layer. D in the figure is a pile driving ship.

支持杭5の打設後、ケーシングパイプ4と支持
杭5とをシヤーコネクター、ライナープレートで
仮結構し、杭列に頂部コンクリートを打設して上
部ストラツトを設ける。杭頭部を水中に設ける場
合はヤツトコ打ちにて支持杭5を水中の所要位置
まで打ち下げる。(第5図参照) 支持杭5の打設が完了し、杭列の頂部コンクリ
ートストラツトが所要強度に達すると、潜水夫に
よつて底版2と支持杭5との間隙を支持杭5に緊
締された止水バンド9で封塞して、(第7図及び
第8図参照)水中コンクリート10を打設する。
ケーソンAの内部は必要に応じて遊水状態とする
か、栗石等を中詰する。
After driving the support piles 5, the casing pipe 4 and the support piles 5 are temporarily assembled using a shear connector and a liner plate, and top concrete is placed in the row of piles to provide an upper strut. When the pile head is installed underwater, the support pile 5 is driven down to the required position in the water by hammer driving. (See Figure 5) When the driving of the support pile 5 is completed and the top concrete strut of the pile row reaches the required strength, the gap between the bottom slab 2 and the support pile 5 is tightened to the support pile 5 by a diver. The concrete is sealed with a waterproof band 9 (see FIGS. 7 and 8), and underwater concrete 10 is placed.
The inside of caisson A should be kept in a water-retentive state or filled with chestnut stone, etc., as necessary.

消波ケーソン、消波型透過ケーソンの場合、前
面壁または背面壁のスリツト孔に嵌装された鉄板
またはゴム状を引上げ、頂部スラブE、パラペツ
ト等のコンクリートを打設して構造物を完成す
る。(第6図参照) 第9図乃至第12図は本発明のケーソンを使用
した各種構造物を示し、第9図は直立消波透過
堤、第10図は消波堤、第11図は大型消波堤、
第12図は低波力台形透過型消波堤を示し、図中
前記実施例と均等部分には同一符号が附されてい
る。
In the case of a wave-dissipating caisson or a wave-dissipating transmission caisson, the steel plate or rubber plate fitted into the slot in the front or rear wall is pulled up, and concrete is poured for the top slab E, parapet, etc. to complete the structure. . (See Fig. 6) Figs. 9 to 12 show various structures using the caisson of the present invention, Fig. 9 shows an upright wave-dissipating and transmitting dam, Fig. 10 shows a wave-dissipating dam, and Fig. 11 shows a large-scale structure. wave-dissipating dyke,
FIG. 12 shows a low wave force trapezoidal transmission type wave breakwater, and in the figure, parts equivalent to those of the above embodiment are given the same reference numerals.

以上本発明を実施例について説明したが、本発
明は勿論このような実施例にだけ局限されるもの
ではなく、本発明の精神を逸脱しない範囲内で
種々の設計の改変を施しうるものである。
Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various ways without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係るケーソンの一実施例を示
す平面図、第2図はその縦断面図、第3図乃至第
6図は前記ケーソンを使用した構造物の施工々程
を示す縦断面図、第7図は支持杭止水部分の縦断
面図、第8図はその平面図、第9図乃至第12図
は夫々本発明のケーソンを使用した構造物の各実
施例を示す斜面図である。 A……ケーソン、B……スパツドの昇降把持装
置、1……スパツド、2……底版、3……支持貫
入孔、5……支持杭、6……仮蓋。
Fig. 1 is a plan view showing an embodiment of a caisson according to the present invention, Fig. 2 is a longitudinal sectional view thereof, and Figs. 3 to 6 are longitudinal sectional views showing construction steps of a structure using the caisson. 7 is a vertical cross-sectional view of the water stop portion of the support pile, FIG. 8 is a plan view thereof, and FIGS. 9 to 12 are slope views showing each example of a structure using the caisson of the present invention. It is. A...Caisson, B...Spud lifting/lowering gripping device, 1...Spud, 2...Bottom plate, 3...Support penetration hole, 5...Support pile, 6...Temporary cover.

Claims (1)

【特許請求の範囲】[Claims] 1 四隅に昇降把持装置を介してスパツドが昇降
自在に嵌挿され、底版には支持杭貫入孔が配設さ
れるとともに、同貫入孔は水圧に対してのみ耐
え、杭の落下によつて打抜かれる仮蓋で閉塞され
てなり、ケーソン設置後は前記スパツドが杭とし
て使用されるように構成されたことを特徴とする
杭支持式防波堤用ケーソン。
1 Spuds are inserted into the four corners so that they can be raised and lowered via lift gripping devices, and support pile penetration holes are provided in the bottom slab, and the penetration holes can only withstand water pressure and cannot be driven by falling piles. A pile-supported caisson for a breakwater, characterized in that the spud is closed with a temporary cover that can be removed, and the spuds are used as piles after the caisson is installed.
JP2281482A 1982-02-17 1982-02-17 Caisson for pile supporting type breakwater Granted JPS58143023A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2281482A JPS58143023A (en) 1982-02-17 1982-02-17 Caisson for pile supporting type breakwater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2281482A JPS58143023A (en) 1982-02-17 1982-02-17 Caisson for pile supporting type breakwater

Publications (2)

Publication Number Publication Date
JPS58143023A JPS58143023A (en) 1983-08-25
JPS6119764B2 true JPS6119764B2 (en) 1986-05-19

Family

ID=12093153

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2281482A Granted JPS58143023A (en) 1982-02-17 1982-02-17 Caisson for pile supporting type breakwater

Country Status (1)

Country Link
JP (1) JPS58143023A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH054631B2 (en) * 1986-10-06 1993-01-20 Iatron Lab

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0258631A (en) * 1988-08-24 1990-02-27 Toa Harbor Works Co Ltd Execution of caisson
JP2009228268A (en) * 2008-03-21 2009-10-08 Nishimatsu Constr Co Ltd Leg type offshore breakwater
JP5669189B2 (en) * 2010-11-09 2015-02-12 五洋建設株式会社 Construction method of transmission type sea area control structure
JP2012117353A (en) * 2010-11-09 2012-06-21 Penta Ocean Construction Co Ltd Construction method for permeable sea area control structure
JP5646978B2 (en) * 2010-12-15 2014-12-24 五洋建設株式会社 Construction method of transmission type sea area control structure
US8714881B2 (en) * 2012-04-17 2014-05-06 Richard J. Gagliano Multiple pile foundation locking systems
CN103306300B (en) * 2013-06-27 2015-07-01 陈振新 Assembled caisson for marine construction
JP6616959B2 (en) * 2015-04-16 2019-12-04 鹿島建設株式会社 Laying anti-scouring material

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5647216U (en) * 1979-09-20 1981-04-27

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5647216U (en) * 1979-09-20 1981-04-27

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH054631B2 (en) * 1986-10-06 1993-01-20 Iatron Lab

Also Published As

Publication number Publication date
JPS58143023A (en) 1983-08-25

Similar Documents

Publication Publication Date Title
US3896628A (en) Marine structures
US3528254A (en) Offshore platform structure and construction method
US4063426A (en) Three column tower
US2756021A (en) Submersible oil rig for drilling on bottom
US3624702A (en) Offshore platform support
JPS6119764B2 (en)
JP4409357B2 (en) Construction method for underwater foundation
CA1243494A (en) Gravity type oceanic structure and its stable installation
US2612024A (en) Submarine foundation and method of erecting
US3857247A (en) Offshore tower erection technique
US3740956A (en) Portable retaining structure
US3115013A (en) Artificial island and method of constructing the same
JPH06146305A (en) Underwater foundation and installation method thereof
JP3463604B2 (en) Dolphin construction method
JP3075179B2 (en) Bridge pier foundation structure and its construction method
JP2718241B2 (en) Foundation construction method on soft submarine ground
JPS6143493B2 (en)
JP2815492B2 (en) How to build an underwater foundation
US3965688A (en) Underwater structures, in particular for underwater drilling operations
JPS60215924A (en) Settlement of steel skeleton for underwater foundation structure
JPS6340024A (en) Pile-type caisson work
JP2953823B2 (en) Construction method of offshore substructure
JPH0323689B2 (en)
JP3132846B2 (en) Construction method of pile type offshore structure
JPH0213098B2 (en)