JPS6118586A - Construction of ocean structure - Google Patents
Construction of ocean structureInfo
- Publication number
- JPS6118586A JPS6118586A JP13932484A JP13932484A JPS6118586A JP S6118586 A JPS6118586 A JP S6118586A JP 13932484 A JP13932484 A JP 13932484A JP 13932484 A JP13932484 A JP 13932484A JP S6118586 A JPS6118586 A JP S6118586A
- Authority
- JP
- Japan
- Prior art keywords
- crane
- ocean
- base section
- foundation
- land
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、大型の海洋構造物の建造方法に関するもので
ある。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of constructing a large marine structure.
海洋構造物の型式には、浮揚させて使用するもの、沈設
して使用するもの等がおるが、いずれの型式のものも出
来るだけ設備条件の整ったところで建造し、浮上させた
まま現地まで曳航またはパージに乗せて′運搬するのが
一般的である。There are two types of offshore structures: those that are used floating and those that are submerged. All types of structures are constructed where the facilities are as ready as possible and then towed to the site while floating. Alternatively, it is common to transport it on a purge.
このような海洋構造物の従来の建造方法を第4図ないし
第11図について説明する。A conventional method of constructing such a marine structure will be explained with reference to FIGS. 4 to 11.
第4図は既在のドッグ等でブロック(α)、(b)をそ
れぞれ建造し、海上にてブロック(a) 、 (b)’
t 一体に結合する建造方法であるが、水中部の信頼で
きる接合技術が未開発であシ、波浪による動揺のため、
ブロック(α)、(b)相互の固定に膨大な設備を必要
とする欠点があった。Figure 4 shows blocks (α) and (b) constructed using existing dogs, etc., and blocks (a) and (b)'
t This is a construction method that connects them in one piece, but reliable joining technology for the underwater part has not yet been developed, and due to turbulence caused by waves,
Blocks (α) and (b) had the disadvantage of requiring a huge amount of equipment to fix them together.
第5図は、陸上固定台(c)上で海洋構造物(d)を一
体建造し、これを進水させる建造方法であるが、ドッグ
で建造する場合よりもクレーンのリフトが高くなって効
率が悪く、水中固定台(g)が水深によっては可成シ沖
合まで延長する必要があって、作業が難しくなる欠点が
あった。Figure 5 shows a construction method in which a marine structure (d) is built integrally on a fixed platform (c) on land and launched into the water, but the crane lift is higher and more efficient than when building with a dog. However, depending on the water depth, the underwater fixed platform (g) had to be extended far offshore depending on the water depth, making the work difficult.
第6図は、予め海岸近くの陸地に露天掘シの仮設ドッグ
(f)を作シ、仕切扉(g)で仕切った状態で海洋構造
物(d)を一体建造する方法であるが、海洋構造物が完
成した場合かなりの吃水となるので、海洋構造物(d3
の浮上曳出しのためには仮設ドッグ<fI内はもとよシ
、前面海底の掘削量が多く不経済な欠点がある。そこで
第7図に示すように仮設ドッグ(A内で海洋構造物の基
礎部分(h)のみを作シ、これを海上にて浮上させたま
ま上部構体を引続き建造する方法が行なわれている。こ
の方法は仮設ドッグ(Aの掘削量は少なくてすむが、上
部構体の建造は海上で行なうため、能率が悪い欠点があ
る。Figure 6 shows a method in which a temporary open-pit dog (f) is built on land near the coast in advance, and an offshore structure (d) is built integrally with the structure separated by a partition door (g). If the structure is completed, there will be considerable swamping, so marine structures (d3
In order to float and pull out a temporary dog <fI, it requires a large amount of excavation of the seabed in front, which is uneconomical. Therefore, as shown in Fig. 7, a method is being used in which only the foundation part (h) of the marine structure is constructed in a temporary dog (A), and the upper structure is continued to be constructed while it is floating on the sea. Although this method requires less excavation of the temporary dog (A), it has the disadvantage of being inefficient because the construction of the upper structure is carried out at sea.
次に海洋構造物を建造するときに使用する揚重機につい
て述べると、一般に門型クレーンを使用する場合、同じ
吊上げ荷重でもスパンが大きくなるほど、門型クレーン
は重構造となって不経済になるOで、第8図、第9図に
示すように、仮設ドッグも含めたドッグ(()等で海洋
構造物(d)を建造する場合には、タワークレーン(j
)を走行させて構築資材を移動させることになるが、こ
の場合、海洋構造物(d)全体をカイ(−するには、タ
ワークレーン(j)の到達距離の関係から最低2台のタ
ワークレーン(j)が必要となるばかりでなく、もし海
洋構造物(d)の中心まで到達距離がなかったり、おる
いは揚重能力が不足の場合には、海洋構造物上に別の基
型クライミングクレーン等の設備が必要であり、またク
レーンの台数に応じて資材供給ルート(k)も増えるの
で、資材運搬の手間も不経済になる欠点がある。Next, regarding the lifting equipment used when constructing offshore structures, when using a gantry crane, the larger the span, the heavier the structure and the less economical the gantry crane becomes. As shown in Figures 8 and 9, when constructing an offshore structure (d) using a dog (), including a temporary dog, a tower crane (j
) to move construction materials, but in this case, in order to move the entire offshore structure (d), at least two tower cranes are required due to the reachable distance of the tower crane (j). (j) is not only required, but if the center of the offshore structure (d) is not reachable or the lifting capacity is insufficient, another base climbing system on the offshore structure may be required. Since equipment such as a crane is required, and the number of material supply routes (k) increases depending on the number of cranes, there is a disadvantage that the labor involved in transporting materials becomes uneconomical.
また第10図、第11図に示すように、海洋構造物(d
)を海上で建造する場合には、70−ティングクレーン
(j)によらざるを得ないが、フローティングクレーン
(1)は陸上のクレーンよりは動作が鈍く、さらに資材
を安定供給するには資材運搬用の随伴台船や、陸上から
の運搬パージ等が必要となシ、非能率な海上輸送を行な
わなければならない。In addition, as shown in Figures 10 and 11, marine structures (d
) to be constructed on the sea, a 70-ton crane (j) must be used, but the floating crane (1) operates more slowly than a land-based crane, and in order to provide a stable supply of materials, it is difficult to transport the materials. This requires an accompanying barge and transportation purge from land, resulting in inefficient sea transportation.
本発明は、最低の台数の陸上クレーンを使用し、高い能
率で海洋構造物を建造しようとするものである。The present invention aims to construct offshore structures with high efficiency using the minimum number of land cranes.
本発明は、基礎部分を組立てた後、この基礎部分を浮上
させて回動し、陸上のクレー・ンによって基礎部分の上
に上部構体を組立てる海洋構造物の建造方法としたもの
である。The present invention is a method of constructing an offshore structure in which a foundation is assembled, the foundation is floated and rotated, and an upper structure is assembled on the foundation by a crane on land.
以下、本発明の一実施例を図面を参照して説明する。 Hereinafter, one embodiment of the present invention will be described with reference to the drawings.
第1図において(1)は海洋構造物の基礎部分であって
、ドッグ等で組立てた後、浮上させて岸壁(2)に引出
して係留したものである。岸壁(2)にはクレーン(3
)が設置してあって、そのブームは海上(4)に向って
延びている。In Fig. 1, (1) is the foundation of the marine structure, which is assembled using a dog or the like, floated, pulled out to a quay (2), and moored. There is a crane (3) on the quay (2).
) is installed, and its boom extends toward the sea (4).
クレーン(3)のブームの下に係留した基礎部分(1)
は、浮上させたまま回動し、クレーン(3)を使用して
基礎部分(1)の上に海洋構造物の上部構体を組立てて
いく。基礎部分(1)の回動け、陸上のウィンチ(5)
と海上(4)の曳船(6)等で互いに引き合ったシ、あ
るいは基礎部分(1)上に数台の仮設ウィンチを据え、
陸上や海底にアンカーを設けてワイヤーを引くようにし
てもよい。基礎部分(1)の回動に要する力としては、
基礎部分(1)は浮上しているので自重は零と考えてよ
く、また回動に伴って生じる造波抵抗は安全上からも超
微速で行なうので殆んど問題にならず、僅かに水の動粘
性抵抗に打ち勝つだけの力があればよく、従って基礎部
分(1)の水中部の水との接触面積や、形状による差異
はあるが、極めて小さい力ですむことになる。Foundation part (1) moored under the boom of crane (3)
rotates while floating, and uses a crane (3) to assemble the upper structure of the offshore structure on the foundation (1). Rotating base part (1), land winch (5)
and several temporary winches are installed on the foundation (1), pulled together by a tugboat (6) on the sea (4), etc.
An anchor may be installed on land or on the ocean floor to pull a wire. The force required to rotate the base part (1) is:
Since the foundation part (1) is floating, it can be considered that its own weight is zero, and the wave-making resistance that occurs due to the rotation is hardly a problem because it is carried out at extremely slow speed for safety reasons, and there is only a slight It is sufficient to have enough force to overcome the kinematic and viscous resistance of the water, and therefore an extremely small force is required, although this varies depending on the contact area with the water in the underwater part of the base portion (1) and the shape.
基礎部分(1)を回動することによって、クレーン(3
)は固定状態のままか、あるいは最少限の距離を走行す
るだけで、基礎部分(1)の上面は順次クレーン(3)
の到達範囲に入るので、資材供給ルー ) (7)は集
中することが可能となり、クレーン(3)の資材供給作
業も基礎部分(1)の大きさに関係なく最短の搬送距離
で効率の良い作業ができ、海上クレーンを使用する必要
もない。クレーン(3)による上部構体の資材供給は片
側からになるが、基礎部分(1)の平面積が大きいので
、基礎部分(1)の傾斜は極めて僅かで、1、上部構体
の組立に支障を生ずることはない。By rotating the foundation part (1), the crane (3
) remains fixed or travels only a minimum distance, and the upper surface of the foundation (1) is sequentially moved by a crane (3).
Since the material supply route (7) is within the reach of The work can be done without the need for a marine crane. Materials for the upper structure are supplied by the crane (3) from one side, but since the planar area of the foundation part (1) is large, the slope of the foundation part (1) is extremely slight, and 1. It is difficult to assemble the upper structure. It will never occur.
第2図の実施例は、予め組立てた基礎部分(1)を岸壁
(2)のコーナーの海上(4)で回動し、2台のクレー
ン(3)を使用する場合である。The embodiment shown in FIG. 2 is a case where a pre-assembled foundation part (1) is rotated on the sea (4) at the corner of a quay (2) and two cranes (3) are used.
第3図は海洋構造物専用の建造ドッグ(8)を使用する
場合の実施例で、建造ドッグ(8)を排水した状態で基
礎部分を組立てだ後、建造ドッグ(8)内に注水して基
礎部分(1)を浮上させ、ウィンチ(5)で基礎部分(
1)を回動しながら、クレーン(3)によって上部構体
を組立てる。Figure 3 shows an example of using a construction dog (8) exclusively for offshore structures.After the foundation is assembled with the construction dog (8) drained, water is poured into the construction dog (8). Float the foundation part (1) and use the winch (5) to lift the foundation part (
1), assemble the upper structure using the crane (3).
本発明は海洋構造物の建造にあたって、能率の低いフロ
ーティングクレーンを使用する必要がなく、陸上のクレ
ーンのみを効率よく使用することができ、資材供給ルー
トも集約して能率を上げることが可能となシ、露天掘仮
設ドッグ等の掘削量も低減することができる。When constructing offshore structures, the present invention eliminates the need to use inefficient floating cranes, makes it possible to efficiently use only land-based cranes, and improves efficiency by consolidating material supply routes. It is also possible to reduce the amount of excavation for temporary open pit dogs.
第1図ないし第3図はそれぞれ本発明の実施例を示す平
面図、第4図ないし第7図は従来の建造方法の側面図、
第8図は従来の他の方法の平面図、第9図は第8図のI
X−IX線の断面図、第10図は従来のさらに他の方法
の平面図、第11図は第10図のXI−XI線の断面図
である。
図中、(1)は基礎部分、(2)は岸壁、(3)はクレ
ーン、(8)は建造ドッグを示す。Figures 1 to 3 are plan views showing embodiments of the present invention, Figures 4 to 7 are side views of the conventional construction method,
Figure 8 is a plan view of another conventional method, and Figure 9 is the I of Figure 8.
10 is a plan view of still another conventional method, and FIG. 11 is a sectional view taken along the line XI-XI in FIG. 10. In the figure, (1) shows the foundation, (2) the quay, (3) the crane, and (8) the construction dog.
Claims (1)
せて回動し、陸上のクレーンによって基礎部分の上に上
部構体を組立てることを特徴とする海洋構造物の建造方
法。1) A method for constructing an offshore structure, which comprises assembling a foundation, floating the foundation in water, rotating it, and assembling an upper structure on top of the foundation using a crane on land.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13932484A JPS6118586A (en) | 1984-07-05 | 1984-07-05 | Construction of ocean structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP13932484A JPS6118586A (en) | 1984-07-05 | 1984-07-05 | Construction of ocean structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6118586A true JPS6118586A (en) | 1986-01-27 |
Family
ID=15242655
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP13932484A Pending JPS6118586A (en) | 1984-07-05 | 1984-07-05 | Construction of ocean structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6118586A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008112672A (en) * | 2006-10-31 | 2008-05-15 | Hirose Electric Co Ltd | Coaxial electrical connector |
-
1984
- 1984-07-05 JP JP13932484A patent/JPS6118586A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2008112672A (en) * | 2006-10-31 | 2008-05-15 | Hirose Electric Co Ltd | Coaxial electrical connector |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH05503124A (en) | Method and apparatus for constructing artificial islands and islands thus obtained | |
US6565286B2 (en) | Method for fabricating and assembling a floating offshore structure | |
US3922868A (en) | Deep water platform construction | |
JPS6118586A (en) | Construction of ocean structure | |
JP2000297411A (en) | Erection method for structure, erection device and erection method for bridge | |
JPH0213684B2 (en) | ||
CN112609585A (en) | Cable construction method suitable for positioning overwater large-sized steel open caisson | |
EP0137625B1 (en) | Transport of prefabricated offshore structures | |
JPS61222892A (en) | Semisubmersible type floating structure and construction method thereof | |
JPS60208512A (en) | Installation of tower type marine structure | |
JPH025852B2 (en) | ||
GB2196675A (en) | Offshore platform system | |
JPS60208513A (en) | Installation of tower type marine structure | |
JPH0227095A (en) | Sinking and burying method | |
GB2143269A (en) | Bridges for traversing waterways | |
JPS5973389A (en) | Process of launching concrete structure | |
JPH04258494A (en) | Construction of horizontal long structure | |
Werenskiold | Paper 10: Maritime operations relative to construction of large concrete offshore structures | |
JPS60208511A (en) | Installation of legs for tower type marine structure | |
JPS5847392B2 (en) | Construction and transport method of large structures | |
JPH0835221A (en) | Construction of large scale floating structure | |
JPH01247293A (en) | Method for erecting large-sized semisubmersible rig | |
JPS61135891A (en) | Ship for transporting structure on sea | |
Morgan | New Cape Size Berth for North Pulau Laut Coal Terminal Indonesia | |
JPS5936054B2 (en) | How to assemble a landing lift type offshore work platform |