JPH025852B2 - - Google Patents
Info
- Publication number
- JPH025852B2 JPH025852B2 JP57089870A JP8987082A JPH025852B2 JP H025852 B2 JPH025852 B2 JP H025852B2 JP 57089870 A JP57089870 A JP 57089870A JP 8987082 A JP8987082 A JP 8987082A JP H025852 B2 JPH025852 B2 JP H025852B2
- Authority
- JP
- Japan
- Prior art keywords
- floater
- pontoon
- sheet pile
- steel sheet
- pile cell
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【発明の詳細な説明】
本発明はプレハブ鋼矢板セル組立装置、特にフ
ローターポンツーンを用いたプレハブ鋼矢板セル
組立方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a prefabricated steel sheet pile cell assembly apparatus, and particularly to a prefabricated steel sheet pile cell assembly method using a floater pontoon.
従来のプレハブ鋼矢板セル工法ではセルを陸上
のヤードもしくは海上の海象条件のよい場所で組
んで現地にクレーン船で吊りあげて運搬して打込
んでいる。しかし陸上で組立てる場合は、あとで
これを吊りあげるためクレーン船が近寄る事の出
来るような水際線をもつたヤードが必要なため、
この様な場所を得ることはなかなか難しい。 In the conventional prefabricated steel sheet pile cell construction method, the cells are assembled in a yard on land or at a location at sea with favorable sea conditions, then hoisted to the site by a crane ship, transported, and driven into place. However, when assembling on land, you need a yard with a waterline where a crane ship can approach to lift it later.
It is difficult to find a place like this.
そこで一般には、専用台船を用いて組立てる方
法と前記海中に組立用導枠を造つて、ここで組立
てる方法の二種類が用いられている。 Therefore, two methods are generally used: a method of assembling using a special barge, and a method of building an assembly guiding frame underwater and assembling it there.
然しながらこの従来の方法には下記に示すよう
な欠点がある。 However, this conventional method has drawbacks as shown below.
(a) プレハブセル組立専用台船による方法
専用台船上でセルを組立てて打設する方法で
あるが、大型設備の割に回転率が悪く、工事が
永続的であれば工事費も安くなる可能性がある
がスポツト的な工事の発注では専用台船の稼働
率が悪く、組立工事費も割高である。(a) Method using a dedicated barge for prefabricated cell assembly This method involves assembling and pouring the cells on a dedicated barge, but the turnover rate is low considering the large equipment, and if the construction is permanent, the construction cost may be lower. However, when ordering spot work, the utilization rate of dedicated barges is low and the assembly costs are relatively high.
(b) 海上に導枠を設置する方法
適当な水深の海底に杭を打ち、これを基礎に
してこの上に導枠を組んで矢板をさしこんでセ
ル形成する工法であるが
工事現場の近くに静かな水面を有する適当
な広さと水深をもつた水域が必要であり、工
事現場から遠く離れた場所で組立てた場合に
はプレハブセルをクレーン船で吊つて運搬す
る必要があり安定性や経済性、工期等で問題
が生じる。(b) Method of installing guide frames on the sea This is a construction method in which piles are driven on the seabed at an appropriate depth, and using this as a foundation, guide frames are built on top of this and sheet piles are inserted to form cells. A calm body of water of appropriate size and depth is required nearby, and if the prefabricated cell is assembled far from the construction site, it will be necessary to transport the prefabricated cell by hoisting it on a crane ship, which may cause stability problems. Problems arise in economic efficiency, construction period, etc.
プレハブセルを組立てた後、これを移動す
るには導枠を越える高さにクレーン船によつ
て吊下する必要があり、これがクレーン船の
大きさを決める要素となる。即ち吊り荷重よ
りも吊り上げ高さやリーチに左右されてクレ
ーン船が大型になり、それだけ工事費が高く
なる。 After a prefabricated cell is assembled, in order to move it, it must be suspended by a crane ship to a height that exceeds the guide frame, and this is a factor that determines the size of the crane ship. In other words, the size of the crane ship depends more on the lifting height and reach than on the lifting load, and the construction cost increases accordingly.
杭打工事、導枠取付工事等すべてが海上工
事であると同時に現地工事であるため工期が
比較的長くなる。 All of the work, including pile driving and installation of guide frames, will be carried out both offshore and on-site, so the construction period will be relatively long.
打込み装置を取付ける時の仮設足場が十分
でない。 There is not enough temporary scaffolding when installing the driving device.
本発明のプレハブ鋼矢板セル組立方法は、この
ような欠点を除くようにしたものであつて、その
浮力を調節自在ならしめたフローターポンツーン
に重錘を吊下しこのフローターポンツーンを幾分
海面下に沈下せしめた状態とする工程と、前記フ
ローターポンツーンの側面にプレハブ鋼矢板セル
組立用ガイド枠を設ける工程と、このガイド枠を
利用して鋼矢板セルを組み立てる工程と、前記フ
ローターポンツーンの浮力を調節してこれを海底
に沈めた状態とする工程と、前記鋼矢板セルを吊
り上げ運搬する工程とより成ることを特徴とす
る。 The method of assembling a prefabricated steel sheet pile cell according to the present invention is designed to eliminate these drawbacks, and involves suspending a weight from a floater pontoon whose buoyancy can be freely adjusted. a step of providing a guide frame for assembling a prefabricated steel sheet pile cell on the side surface of the floater pontoon, a step of assembling the steel sheet pile cell using this guide frame, and a step of reducing the buoyancy of the floater pontoon. The method is characterized by comprising a step of adjusting the steel sheet pile cell so that it is submerged on the seabed, and a step of lifting and transporting the steel sheet pile cell.
本発明プレハブ鋼矢板セル組立方法の第2の発
明はその浮力を調節自在ならしめたフローターポ
ンツーンに重錘を吊下しこのフローターポンツー
ンを幾分海面下に沈下せしめた状態とする工程
と、前記フローターポンツーンの側面にプレハブ
鋼矢板セル組立用ガイド枠を設ける工程と、この
ガイド枠を利用して鋼矢板セルを組み立てる工程
と、前記鋼矢板セルとフローターポンツーンを連
結し、前記重錘を除去する工程と、前記連結され
た鋼矢板セルとフローターポンツーンを運搬する
工程とより成ることを特徴とする。 The second aspect of the prefabricated steel sheet pile cell assembly method of the present invention is the step of suspending a weight from a floater pontoon whose buoyancy can be adjusted so that the floater pontoon is slightly submerged below the sea surface; A step of providing a guide frame for assembling a prefabricated steel sheet pile cell on the side of a floater pontoon, a step of assembling a steel sheet pile cell using this guide frame, a step of connecting the steel sheet pile cell and the floater pontoon, and removing the weight. and a step of transporting the connected steel sheet pile cell and floater pontoon.
以下図面によつて本発明の実施例を説明する。 Embodiments of the present invention will be described below with reference to the drawings.
本発明においては注水することによつてその浮
力を調節自在ならしめたフローターポンツーン1
の下面にワイヤ2を介して重錘3を吊下し、前記
フローターポンツーン1をその浮力に抗して幾分
海面下に沈下せしめた状態で保持すると共に前記
フローターポンツーン1の外周には支持具4を介
してプレハブ鋼矢板セル組立用の円筒状のガイド
枠5を取り付け、このガイド枠5を利用して鋼矢
板セル6を組立てるようにする。 In the present invention, a floater pontoon 1 whose buoyancy can be freely adjusted by injecting water.
A weight 3 is suspended from the lower surface of the floater pontoon 1 via a wire 2, and the floater pontoon 1 is held in a state in which it is sunk somewhat below the sea surface against the buoyancy of the floater pontoon. A cylindrical guide frame 5 for assembling the prefabricated steel sheet pile cell is attached via the guide frame 5, and the steel sheet pile cell 6 is assembled using this guide frame 5.
本発明組立方法は上記のとおりであるから潮位
の変動によつてもフローターポンツーン1の位置
は殆んど変化せず、即ち干潮状態は第1図、満潮
状態は第3図に示すようになり、海底からのフロ
ーターポンツーン1の高さは殆んど変化せず鋼矢
板セル6の組立てが極めて容易になし得る。 Since the assembly method of the present invention is as described above, the position of the floater pontoon 1 hardly changes even when the tide level fluctuates, that is, the position of the floater pontoon 1 is as shown in Fig. 1 at low tide and as shown in Fig. 3 at high tide. The height of the floater pontoon 1 from the seabed hardly changes, and the steel sheet pile cells 6 can be assembled very easily.
鋼矢板セル6の組立後は第4図に示すようにフ
ローターポンツーン1に注水してこれを海底に沈
めた状態とし、次いでクレーンによつて鋼矢板セ
ル6を吊り上げて運搬するようにすれば鋼矢板セ
ル6の吊上高さを極めて低くでき従つてクレーン
も小型で良い大きな利益がある。 After assembling the steel sheet pile cell 6, as shown in FIG. There is a great advantage that the lifting height of the sheet pile cell 6 can be made extremely low, and the crane can also be made smaller.
本発明方法の他の実施例においては第5図に示
すようにフローターポンツーン1をその内部に海
水バラスト7を入れた状態でフローターポンツー
ン1が浮くようにしこの状態で鋼矢板セル6を組
立て、その後第6図に示すようにフローターポン
ツーン1と鋼矢板セル6を連結部8によつて連結
し、フローターポンツーン1より海水バラスト7
を排水してフローターポンツーン1を鋼矢板セル
6と共に浮上せしめ、第7図に示すようにこの両
者をワイヤ2を切断した後曳船9によつて所定の
設置場所に曵航せしめるようにする。 In another embodiment of the method of the present invention, as shown in FIG. 5, the floater pontoon 1 is floated with a seawater ballast 7 inside it, and the steel sheet pile cell 6 is assembled in this state, and then As shown in FIG. 6, the floater pontoon 1 and the steel sheet pile cell 6 are connected by a connecting part 8, and the seawater ballast 7 is connected from the floater pontoon 1 to the steel sheet pile cell 6.
The floater pontoon 1 is floated together with the steel sheet pile cell 6 by draining water, and as shown in FIG. 7, both of them are towed to a predetermined installation location by a tugboat 9 after cutting the wire 2.
上記のように本発明組立方法を用いれば従来の
欠点を一掃でき、極めて簡単な手段で鋼矢板セル
を容易に組立てることができる大きな利益があ
る。 As described above, by using the assembly method of the present invention, the drawbacks of the conventional method can be eliminated, and there is a great advantage that steel sheet pile cells can be easily assembled using extremely simple means.
第1図は本発明組立方法の説明用正面図、第2
図はその平面図、第3図、第4図はその作動説明
図、第5図〜第7図は本発明の他の使用例説明図
である。
1……フローターポンツーン、2……ワイヤ、
3……重錘、4……支持具、5……ガイド枠、6
……鋼矢板セル、7……海水バラスト、8……連
結部、9……曵船。
Figure 1 is a front view for explaining the assembly method of the present invention;
The figure is a plan view, FIGS. 3 and 4 are explanatory diagrams of its operation, and FIGS. 5 to 7 are explanatory diagrams of other usage examples of the present invention. 1...Floater pontoon, 2...Wire,
3... Weight, 4... Support, 5... Guide frame, 6
... steel sheet pile cell, 7 ... seawater ballast, 8 ... connection section, 9 ... tugboat.
Claims (1)
ンツーンに重錘を吊下しこのフローターポンツー
ンを幾分海面下に沈下せしめた状態とする工程
と、前記フローターポンツーンの側面にプレハブ
鋼矢板セル組立用ガイド枠を設ける工程と、この
ガイド枠を利用して鋼矢板セルを組み立てる工程
と、前記フローターポンツーンの浮力を調節して
これを海底に沈めた状態とする工程と、前記鋼矢
板セルを吊り上げ運搬する工程とより成ることを
特徴とするプレハブ鋼矢板セル組立方法。 2 その浮力を調節自在ならしめたフローターポ
ンツーンに重錘を吊下しこのフローターポンツー
ンを幾分海面下に沈下せしめた状態とする工程
と、前記フローターポンツーンの側面にプレハブ
鋼矢板セル組立用ガイド枠を設ける工程と、この
ガイド枠を利用して鋼矢板セルを組み立てる工程
と、前記鋼矢板セルとフローターポンツーンを連
結し、前記重錘を除去する工程と、前記連結され
た鋼矢板セルとフローターポンツーンを運搬する
工程とより成ることを特徴とするプレハブ鋼矢板
セル組立方法。[Scope of Claims] 1. A step of suspending a weight on a floater pontoon whose buoyancy can be adjusted so that the floater pontoon is slightly submerged below the sea surface, and installing prefabricated steel on the side of the floater pontoon. a step of providing a guide frame for assembling a sheet pile cell, a step of assembling a steel sheet pile cell using this guide frame, a step of adjusting the buoyancy of the floater pontoon so that it is submerged on the seabed, and a step of assembling the steel sheet pile cell using the guide frame; A prefabricated steel sheet pile cell assembly method comprising the steps of lifting and transporting the cells. 2. A step in which a weight is suspended from a floater pontoon whose buoyancy can be adjusted to allow the floater pontoon to sink somewhat below the sea surface, and a guide frame for assembling a prefabricated steel sheet pile cell is attached to the side of the floater pontoon. a step of assembling a steel sheet pile cell using this guide frame, a step of connecting the steel sheet pile cell and the floater pontoon and removing the weight, and a step of assembling the steel sheet pile cell and the floater pontoon after the connected steel sheet pile cell and the floater pontoon. A prefabricated steel sheet pile cell assembly method comprising the steps of:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8987082A JPS58207410A (en) | 1982-05-28 | 1982-05-28 | Assembler for prefabricated steel sheet pile cell |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8987082A JPS58207410A (en) | 1982-05-28 | 1982-05-28 | Assembler for prefabricated steel sheet pile cell |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS58207410A JPS58207410A (en) | 1983-12-02 |
JPH025852B2 true JPH025852B2 (en) | 1990-02-06 |
Family
ID=13982798
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8987082A Granted JPS58207410A (en) | 1982-05-28 | 1982-05-28 | Assembler for prefabricated steel sheet pile cell |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS58207410A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0498237U (en) * | 1991-01-18 | 1992-08-25 | ||
JPH04102540U (en) * | 1991-02-08 | 1992-09-03 | 日本電気株式会社 | electromagnetic relay |
JPH05120973A (en) * | 1991-10-25 | 1993-05-18 | Nec Corp | Coil sealing body for electromagnetic relay |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5462606A (en) * | 1977-10-26 | 1979-05-19 | Ishikawajima Harima Heavy Ind | Device for constructing caisson or like |
-
1982
- 1982-05-28 JP JP8987082A patent/JPS58207410A/en active Granted
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5462606A (en) * | 1977-10-26 | 1979-05-19 | Ishikawajima Harima Heavy Ind | Device for constructing caisson or like |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0498237U (en) * | 1991-01-18 | 1992-08-25 | ||
JPH04102540U (en) * | 1991-02-08 | 1992-09-03 | 日本電気株式会社 | electromagnetic relay |
JPH05120973A (en) * | 1991-10-25 | 1993-05-18 | Nec Corp | Coil sealing body for electromagnetic relay |
Also Published As
Publication number | Publication date |
---|---|
JPS58207410A (en) | 1983-12-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS6315381Y2 (en) | ||
CN101837929B (en) | Operation method for lifting fan for barge in shoal area | |
JP2004001750A (en) | Construction of special work boats and offshore structures | |
EP3276086A1 (en) | Gravity foundation for the installation of offshore wind turbines | |
CN112726548B (en) | Construction method for split jacket foundation of deep-open sea converter station | |
JPS62215711A (en) | Ocean structure and method for anchoring the same | |
CN218506092U (en) | C-shaped assembly type floating transportation structure for split floating transportation of offshore substation | |
JP6735050B1 (en) | Stand lifting device for ships | |
CN115704209A (en) | Shallow water area offshore platform installation method | |
JPH025852B2 (en) | ||
EP0908382A2 (en) | Methods of assembling floating offshore structures | |
KR102062204B1 (en) | Method for All-in-one Installation and Transportation of Offshore Wind Turbine | |
JPH1096241A (en) | Jacket structure | |
JP2606799B2 (en) | Installation method of marine platform | |
GB2580103A (en) | Underwater pedestal synchronous sinking and posture fixing and solid release control device and method thereof | |
JPS59145688A (en) | Launching/grounding system for vessel and ocean structure | |
JPS58218521A (en) | Construction, launching and installation of caisson | |
CN222541467U (en) | A positioning device for offshore wind power four-pile pipe frame foundation | |
JP2001081790A (en) | Jacket structural body and construction method of the structure | |
RU67111U1 (en) | MARINE PLATFORM FOR THE WIND POWER GENERATOR | |
JP2001003332A (en) | Immersion method for caisson and floater for immersing the caisson | |
EP2918729B1 (en) | Foundation base | |
JPS60208512A (en) | How to install tower-shaped offshore structures | |
JPS6335766B2 (en) | ||
US5136960A (en) | Method and apparatus for reducing the draft and increasing the load bearing area and stability of marine drilling barges |