JPS6114295B2 - - Google Patents

Info

Publication number
JPS6114295B2
JPS6114295B2 JP11341281A JP11341281A JPS6114295B2 JP S6114295 B2 JPS6114295 B2 JP S6114295B2 JP 11341281 A JP11341281 A JP 11341281A JP 11341281 A JP11341281 A JP 11341281A JP S6114295 B2 JPS6114295 B2 JP S6114295B2
Authority
JP
Japan
Prior art keywords
reinforcement
muscle
shaped
mesh
reinforcements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP11341281A
Other languages
Japanese (ja)
Other versions
JPS5813833A (en
Inventor
Hiroshi Suwa
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP11341281A priority Critical patent/JPS5813833A/en
Publication of JPS5813833A publication Critical patent/JPS5813833A/en
Publication of JPS6114295B2 publication Critical patent/JPS6114295B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations

Description

【発明の詳細な説明】 この発明は特に梁成の高い地中梁の鉄筋組みに
対して特に有効且つ全く新規な工法に関するもの
であります。
[Detailed Description of the Invention] This invention relates to a completely new construction method that is particularly effective for constructing reinforcing bars for underground beams with high beam thickness.

従来殊に隣接して土留め等のある場合は地中梁
配筋の支え筋を土留側より取付けたり、高価な形
鋼、鋼管等により主筋の受け枠をつくり受け枠の
上の所定の位置に主筋を並べ次いで肋筋で主筋を
囲う様に配列して組立てる方法で上部主筋、肋筋
を狭い足場の上で然も高所での危険が多い作業を
行つている現状です。
Traditionally, especially when there is an earth retaining structure adjacent to the earth, the support bars for underground beam reinforcements are installed from the earth retaining side, or a receiving frame for the main reinforcement is made of expensive shaped steel, steel pipes, etc., and then placed at a predetermined position above the receiving frame. Currently, the upper main reinforcement and cost reinforcement are assembled on narrow scaffolding by arranging the main reinforcement and then surrounding the main reinforcement with cost reinforcement, which involves dangerous work at high places.

又足場はコンクリート打設の時には再び解体除
去しなければならず更に主筋受け枠はそのまゝコ
ンクリート内に埋め込んでしまうことゝなり何れ
も無用な費用と手間を掛けています。
In addition, the scaffolding must be dismantled and removed again when concrete is poured, and the main reinforcement frame is embedded directly into the concrete, all of which add unnecessary cost and effort.

このため建設現場の人力による手作業が極めて
多くなり作業の進行もおくれ能率も悪く、特に鉄
筋組みのためのみに必要な足場を組んだり鉄筋あ
づけの仮設資材が必要となり工数も多く、現場環
境も悪く、難作業となり工期が長くなり、コスト
高をまねく等欠点が数多くある現状です。
As a result, there is an extremely large amount of manual labor at the construction site, slowing down the progress of the work and reducing efficiency.In particular, scaffolding and temporary materials for attaching the reinforcing bars are required, which requires a large amount of man-hours, and the site environment is Currently, there are many drawbacks such as difficult work, long construction times, and high costs.

本発明は上記の点にかんがみなされたもので、
殊に梁の高さが2mをこえるような地中梁の鉄筋
組みではこれらの欠点を解消し大巾な効果を発揮
する新規な工法です。
The present invention has been made in view of the above points,
This is a new construction method that eliminates these drawbacks and is highly effective, especially for reinforcing underground beams where the height of the beam exceeds 2m.

その要旨とするところは、予め作成したメツシ
ユ状筋の剛性を利用してそのまゝ自立させて組立
てるもので鉄筋組みのための仮設材や足場を必要
とせず組立て作業は、分割したメツシユ状筋の設
置と接続及び主筋を取付けるだけで良くなり、鉄
筋一本一本の手結束による手組みとは比較になら
ないほどの高能率で組み立てられその結果本発明
は次のような数多くの利点を有する。
The gist of this is that the rigidity of the mesh-shaped bars created in advance is used to assemble the mesh bars in a self-supporting manner, and there is no need for temporary materials or scaffolding for assembling the reinforcing bars. It is only necessary to install and connect the reinforcing bars and attach the main reinforcing bars, and it is assembled with a high efficiency that is incomparable to manual assembly by manually tying each reinforcing bar one by one.As a result, the present invention has many advantages as follows. .

1 組立てが手作業からメツシユ状筋、籠状筋と
したことにより労動力が大巾に減少できる。
1 Labor force can be greatly reduced by changing the assembly from manual work to mesh-shaped and cage-shaped bars.

2 籠状筋、メツシユ状筋は寸法・直角等が完全
で剛性もあるため、素人でも容易に組立てが出
来る。
2. Cage-shaped muscles and mesh-shaped muscles have perfect dimensions, right angles, etc., and are rigid, so even an amateur can easily assemble them.

3 メツシユ状筋には自立性があるため高価な主
筋受け枠、足場等の仮設資材を全く必要とせ
ず、従つて施工費用を大きく省くことができ
る。
3. Because the mesh-shaped reinforcement has self-supporting properties, there is no need for expensive main reinforcement support frames, scaffolding, or other temporary construction materials, and construction costs can therefore be significantly reduced.

4 配筋が完全であり、組立てられた鉄筋寸法の
精度が高く関連する雑配筋・型枠・設備・コン
クリート打設作業が楽となり、作業もはかど
る。
4. Reinforcement arrangement is perfect, and the assembled rebar dimensions are highly accurate, making related miscellaneous reinforcement, formwork, equipment, and concrete placement work easier and faster.

5 かぶりが適確に維持出来配筋が所定の位置に
乱れることなく納まるので構造体としての品
質・強度の向上が期待できる。
5. Since the cover can be maintained accurately and the reinforcing bars are placed in the specified positions without disturbance, it is expected that the quality and strength of the structure will improve.

6 工期を大巾に短縮することができる。6. Construction period can be drastically shortened.

7 メツシユ状筋の剛性により従来の巾止め筋は
最少限で良く材料・手間の大巾減となる。
7. Due to the rigidity of mesh-like bars, the number of conventional stop bars can be kept to a minimum, resulting in a significant reduction in materials and labor.

以下、この発明の詳細を実施例にもとずいて説
明する。
The details of this invention will be explained below based on examples.

本発明に使用するL字形籠状筋1は第1図に示
すように肋筋の側部2とその下部3並びに他方の
側部下端4からなるL字形筋に腹筋5,5′を溶
着又は手結束したものである。
As shown in FIG. 1, the L-shaped cage muscle 1 used in the present invention is made by welding or welding the abdominal muscles 5, 5' to the L-shaped muscle consisting of the side part 2 of the costal muscle, its lower part 3, and the lower end 4 of the other side. It is hand tied.

次いでこのL字形籠状筋1を第2図に示すよう
に地中梁を構築する所定の場所に設着し、下部主
筋9をL字形籠状筋1に収めセツトする。このL
字形籠状筋1を地中梁長手方向の側面からみると
第5図に示すようである。1つのL字形籠状筋1
で梁長に達しない場合は複数個を継ぎ足してゆ
く。
Next, this L-shaped cage reinforcement 1 is installed at a predetermined location where an underground beam will be constructed, as shown in FIG. 2, and the lower main reinforcement 9 is placed in the L-shaped cage reinforcement 1 and set. This L
Figure 5 shows the shape of the cage bar 1 when viewed from the side in the longitudinal direction of the underground beam. 1 L-shaped cage muscle 1
If the beam length is not reached, add multiple pieces.

地中梁の巾が広い場合は中子筋6を複数本並列
し腹筋7によつて溶着した籠状筋8を第2図に示
すようにL字形籠状筋1の下部に取付ける。
When the width of the underground beam is wide, a plurality of core reinforcements 6 are arranged in parallel and a cage reinforcement 8 welded by abdominal reinforcement 7 is attached to the lower part of the L-shaped cage reinforcement 1 as shown in FIG.

第3図に示すように中子筋10に腹筋11を、
第4図に示すように肋筋14に腹筋15をそれぞ
れ溶着してメツシユ状としたもの12及び16を
その剛性を利用して自立させL字形籠状筋の側部
下端4にはメツシユ状筋16を籠状筋8にはメツ
シユ状筋12をそれぞれ結束13をもつて取付け
る。中子筋のメツシユ状筋を支えるには篭状筋に
類するL形状筋を用いても良い。
As shown in FIG. 3, the abdominal muscles 11 are attached to the core muscles 10,
As shown in FIG. 4, the abdominal muscles 15 are welded to the costal muscles 14 to form mesh-like structures 12 and 16 that are self-supporting by utilizing their rigidity. 16 is attached to the cage-shaped reinforcement 8 with mesh-shaped reinforcements 12, respectively, with ties 13. To support the mesh-like muscle of the takata muscle, an L-shaped muscle similar to the cage-like muscle may be used.

メツシユ状筋12,16及びL字形籠状筋1の
側部2の間隔を正確に保つためには第6図に示す
ように巾止め筋19を適当間隔に取り付けること
によつて達成される。中子筋を必要としない時は
L字形籠状筋の下部端部にメツシユ状筋16を取
り付けて成し得る。
In order to accurately maintain the spacing between the mesh bars 12, 16 and the side portion 2 of the L-shaped cage bar 1, it is achieved by attaching the stop bars 19 at appropriate intervals as shown in FIG. When a core muscle is not required, a mesh-like muscle 16 can be attached to the lower end of the L-shaped cage muscle.

次いで第7図に示すように上部主筋21が納め
セツトされるのである。この場合カンザシ筋20
を端部上部主筋21′に先行してセツトするとか
んざし筋20とフツク22との間の空間が小さく
なり端部上部主筋21′の取付けが不可能となる
ので端部上部主筋21′をかんざし筋に先行して
フツク22の中に定置させることが必要である。
Next, as shown in FIG. 7, the upper main reinforcement 21 is placed and set. In this case, Kanzaki muscle 20
If set before the end upper main reinforcement 21', the space between the hairpins 20 and the hook 22 will become smaller, making it impossible to install the end upper main reinforcement 21'. It is necessary to place it in the hook 22 prior to the installation.

その後中央部の上部主筋21を順次配筋すれば
よい。但しスラブに連結する梁の場合のようにフ
ツクが90゜又はフツク不要の場合空間に余裕があ
るのでかんざし筋を先行してセツトしその上に上
部主筋21を並べればよい。尚上部主筋が複数段
とする場合には最下段のものからセツトする。
After that, the upper main reinforcing bars 21 in the central part may be sequentially arranged. However, if the hook is 90 degrees or no hook is needed, as in the case of a beam connected to a slab, there is sufficient space, so it is sufficient to set the hairpins in advance and arrange the upper main reinforcements 21 on top of them. If the upper main reinforcing bars have multiple levels, set them starting from the lowest level.

次いで第8図に示す如くキヤツプタイ25は腹
筋24と溶着して成るメツシユ状筋を用いるが、
又手組みによりキヤツプタイ1本毎結束26等で
連結取り付けても良い。このようにすれば梁成が
2mをこえる高い地中梁の鉄筋組立も大巾に合理
化され既述する種々の諸効果が得られるのであり
ます。
Next, as shown in FIG. 8, the cap tie 25 uses a mesh-shaped muscle welded to the abdominal muscle 24.
Alternatively, each cap tie may be connected and attached using a bundle 26 or the like by hand assembly. In this way, the assembly of reinforcing bars for high underground beams exceeding 2 meters in width can be greatly streamlined, and the various effects mentioned above can be obtained.

以上の作用は地中梁の構築される場所で行つて
もよいし、他の場所でユニツト化し出来たものを
揚重機等で吊上げ所定の場所へ運び組立ててもよ
いものであります。
The above actions may be performed at the location where the underground beam is constructed, or it may be assembled into a unit at another location, lifted up by a lifting machine, etc., and transported to the designated location.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明工法の実施例を示したもので第1
図〜第4図は鉄筋の組立て手順を示したものであ
ります。第5図は底部L字形籠状筋の側面図、第
6図は底部L字形筋にメツシユ状筋を取付けた正
面図、第7図は肋筋上部と上部主筋との関係図、
第8図はキヤツプタイを取付けた関係図でありま
す。 1……L字形籠状筋、5,5′,11,15,
24……腹筋、8……中子筋の籠状筋、9……下
部主筋、12……中子筋のメツシユ状筋、16…
…肋筋側部のメツシユ状筋、21,21′……上
部主筋、25……キヤツプタイの籠状筋。
The drawings show an example of the construction method of the present invention.
Figures 4 to 4 show the reinforcing bar assembly procedure. Figure 5 is a side view of the bottom L-shaped cage muscle, Figure 6 is a front view of the bottom L-shaped cage muscle attached to the mesh muscle, Figure 7 is a diagram of the relationship between the upper ribs and the upper main reinforcement.
Figure 8 is a diagram showing the relationship with the cap tie installed. 1...L-shaped cage muscle, 5, 5', 11, 15,
24...abdominal muscle, 8...basketoid muscle of takata muscle, 9...lower main muscle, 12...mesh-form muscle of takata muscle, 16...
... mesh-like muscle on the side of the costal muscle, 21, 21'... upper main muscle, 25... cage-like muscle of the cap tie.

Claims (1)

【特許請求の範囲】 1 助筋の片面側部と下部とを一体化したL字形
篭状筋1を基盤上に敷設し、その下部内に下部主
筋9を配筋し地中梁の反面側部となるメツシユ状
筋16をL字形篭状筋の短い方の立上り筋を利用
して自立させ、自立させたメツシユ状筋の剛性を
生かして上部腹筋にかんざし筋20を通し、上に
上部主筋21を配筋し主筋をかんざし筋で支持さ
せキヤツプタイ25をメツシユ状筋にかぶさるよ
うに取付けることにより仮設資材を使用せず組立
てをすることを特徴とする地中梁の鉄筋組み工
法。 2 助筋の片面側部と下部とを一体したL字形篭
状筋1を基盤上に敷設しL字形篭状筋の下部内側
に更に小さい下部中子筋8を設け、その中に下部
主筋9を配筋し地中梁の反面側部となるメツシユ
状筋16と地中梁中子筋の配筋となるメツシユ状
筋12をL字形篭状筋の短かい方と下部中子筋の
立上り筋を利用して自立させ、自立させたメツシ
ユ状筋の剛性を生かして上部腹筋にかんざし筋2
0を通し、上に上部主筋21を配筋し主筋をかん
ざし筋で支持させキヤツプタイ25をメツシユ状
筋にかぶさるように取付けることにより仮設資材
を使用せず組立てをすることを特徴とする地中梁
の鉄筋組み工法。 3 L字形篭状筋の下部内に下部中子筋が篭状筋
(状)である特許請求の範囲第2項の地中梁の
鉄筋組み工法。 4 L字形篭状筋の下部内に下部中子筋がL形状
である特許請求の範囲第2項の地中梁の鉄筋組み
工法。
[Claims] 1. An L-shaped cage reinforcement 1 that integrates one side and a lower part of the auxiliary reinforcement is laid on the base, and the lower main reinforcement 9 is arranged in the lower part, and the other side of the underground beam is laid. The mesh-form muscle 16, which is the main part of the body, is made independent by using the shorter rising muscle of the L-shaped basket-like muscle, and the stiffness of the mesh-form muscle that has been made free-standing is utilized to pass the kanzashi muscle 20 through the upper abdominal muscle, and the upper main muscle is placed above it. This method of assembling reinforcing bars for underground beams is characterized by assembling without using temporary materials by arranging reinforcements 21, supporting the main reinforcements with pintail reinforcements, and installing cap ties 25 so as to cover the mesh reinforcements. 2 An L-shaped cage reinforcement 1 that integrates one side and a lower part of the auxiliary reinforcement is laid on the base, an even smaller lower core reinforcement 8 is provided inside the lower part of the L-shaped cage reinforcement, and a lower main reinforcement 9 is installed inside it. The mesh-shaped reinforcement 16 which becomes the opposite side of the underground beam, the mesh-shaped reinforcement 12 which becomes the reinforcement of the underground beam core reinforcement, the shorter one of the L-shaped cage reinforcement and the rising reinforcement of the lower core reinforcement. By utilizing the rigidity of the mesh-formed muscle, which has been made independent, the upper abdominal muscles are
This underground beam is characterized in that it can be assembled without using temporary materials by passing through 0, placing upper main reinforcements 21 on top, supporting the main reinforcements with hairpin reinforcements, and installing cap ties 25 so as to cover the mesh reinforcements. Reinforced construction method. 3. The reinforcing reinforcement construction method for an underground beam according to claim 2, wherein the lower core reinforcement is a cage reinforcement (shaped) in the lower part of the L-shaped cage reinforcement. 4. The reinforcing reinforcement construction method for an underground beam according to claim 2, wherein the lower core reinforcement is L-shaped in the lower part of the L-shaped cage reinforcement.
JP11341281A 1981-07-20 1981-07-20 Assembling work for underground beam of large span Granted JPS5813833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11341281A JPS5813833A (en) 1981-07-20 1981-07-20 Assembling work for underground beam of large span

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11341281A JPS5813833A (en) 1981-07-20 1981-07-20 Assembling work for underground beam of large span

Publications (2)

Publication Number Publication Date
JPS5813833A JPS5813833A (en) 1983-01-26
JPS6114295B2 true JPS6114295B2 (en) 1986-04-18

Family

ID=14611606

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11341281A Granted JPS5813833A (en) 1981-07-20 1981-07-20 Assembling work for underground beam of large span

Country Status (1)

Country Link
JP (1) JPS5813833A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59228568A (en) * 1983-06-09 1984-12-21 伊藤鉄筋株式会社 Wire arrangement of beam
JPS61146969A (en) * 1984-12-17 1986-07-04 株式会社竹中工務店 Assembling of reinforcement of beam

Also Published As

Publication number Publication date
JPS5813833A (en) 1983-01-26

Similar Documents

Publication Publication Date Title
JPH07506643A (en) Modular reinforcing cage for ductile concrete frame members and method of manufacturing and erection thereof
US10017942B2 (en) Rebar wall set-up bar
KR101519086B1 (en) Bridg using t-girder with pile supporting apparatus and bridge continuous construction method using the same
CA2791840A1 (en) Reinforcement system for concrete structures and a method for reinforcing an elongate concrete structure
WO2016020932A2 (en) Deployable pre-fabricated reinforcement cage system
JPS6114295B2 (en)
JP2020026634A (en) Seismic isolation upper foundation structure and method for manufacturing the same, footing structure, and method for constructing seismic isolation foundation
JPS6114294B2 (en)
JPH0332586Y2 (en)
JPH08319695A (en) Underground beam reinforcement assembly and underground beam construction method
JP2697807B2 (en) Reinforcing cage assembly / building equipment
KR20060024169A (en) Construction method of underground structures comprising composite reinforced concrete girders and beams using frp
JP2538528B2 (en) Slope stabilization method
JP2654597B2 (en) Reinforcement method of wall type rigid frame structure
KR100579543B1 (en) System for constructing composite reinforced concrete girders and beams using FRP
JP2001220858A (en) Concrete reinforced body and its assembly method
JPH11131692A (en) Unit joint bar
JP2005163330A (en) Tool for constructing impact receiving slab, wall surface material for constructing impact receiving slab, and construction method for protective dam body
JP2545129B2 (en) Underground beam construction method
JP3138874B2 (en) How to build underground structures
JPH0816331B2 (en) Underground construction wall foundation method
JPH11107423A (en) Void block metal fitting, simple swell-preventive metal fitting, and simple execution of void slab thereby
CN117127713A (en) Single-plate concrete structure and construction method thereof
JPS5923135Y2 (en) wall beam structure
JPH05106228A (en) Underground girder and execution method thereof and form used for the method