JP2697807B2 - Reinforcing cage assembly / building equipment - Google Patents

Reinforcing cage assembly / building equipment

Info

Publication number
JP2697807B2
JP2697807B2 JP15342293A JP15342293A JP2697807B2 JP 2697807 B2 JP2697807 B2 JP 2697807B2 JP 15342293 A JP15342293 A JP 15342293A JP 15342293 A JP15342293 A JP 15342293A JP 2697807 B2 JP2697807 B2 JP 2697807B2
Authority
JP
Japan
Prior art keywords
reinforcement
frame
view
cage
reinforcing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP15342293A
Other languages
Japanese (ja)
Other versions
JPH0711771A (en
Inventor
信行 松井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP15342293A priority Critical patent/JP2697807B2/en
Publication of JPH0711771A publication Critical patent/JPH0711771A/en
Application granted granted Critical
Publication of JP2697807B2 publication Critical patent/JP2697807B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)
  • Wire Processing (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、鉄筋コンクリート躯体
構築工における鉄筋篭組立・建込装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for assembling and building a reinforced cage in a reinforced concrete skeleton construction work.

【0002】[0002]

【従来の技術】複数の鉄筋で構成される鉄筋篭を躯体構
築に伴い、順次組立・施工するに際し、構築場所で全て
の鉄筋篭を組立てるには、長期間の工事日数と多数の工
数を要するだけでなく、上下作業等の危険作業となる。
そのため、プレファブ後に構築場所で据付けを行う場合
が多い。その鉄筋筋のプレファブ工法の一例を図19な
いし図39を参照して地下タンク用鉄筋篭を例に説明す
る。
2. Description of the Related Art When assembling and constructing a reinforcing cage composed of a plurality of reinforcing bars sequentially with the construction of a frame, assembling all reinforcing bars at a construction site requires a long construction time and a large number of man-hours. In addition, it is dangerous work such as up and down work.
Therefore, installation is often performed at the construction site after prefabrication. An example of the reinforcing bar prefabrication method will be described with reference to FIGS. 19 to 39 using a reinforcing bar cage for an underground tank as an example.

【0003】図19及び図20において、鉄筋組立架台
1に複数の縦筋2及び円周筋3を配材し、結束して外網
筋4及び内網筋5を製作する。
In FIG. 19 and FIG. 20, a plurality of vertical bars 2 and circumferential bars 3 are provided on a reinforcing bar assembly 1 and tied to form an outer mesh bar 4 and an inner mesh bar 5.

【0004】次いで、図21及び図22に示すように、
鉄筋組立架台1Aに内網筋5をセットし、複数のアング
ル材製の補強フレーム6を取付ける。
Then, as shown in FIGS. 21 and 22,
The inner net reinforcement 5 is set on the reinforcing bar assembly base 1A, and a plurality of reinforcing frames 6 made of angle materials are attached.

【0005】次いで、図23及び図24に示すように、
補強フレーム6、6・・・上に外網筋4をセットしたの
ち、図25ないし図27に示すスターラップ筋7、7A
又は7Bにより、図28に示すように、作業員Mが鉄筋
組立架台1Aの内部に入り、外網筋4及び内網筋5を連
結して鉄筋篭8を組立てる。
Next, as shown in FIGS. 23 and 24,
After the outer reticulation bar 4 is set on the reinforcing frames 6, 6,..., The stirrup bars 7, 7A shown in FIGS.
Alternatively, as shown in FIG. 28, the worker M enters the inside of the reinforcing bar assembling base 1A by 7B, and connects the outer net reinforcing bar 4 and the inner net reinforcing bar 5 to assemble the reinforcing bar cage 8.

【0006】次いで、図29に示すように、複数(図示
の例では3個)のスペーサ9、9aを介して複数(図示
の例では3個)の鉄筋篭8を積重仮置きする。
Next, as shown in FIG. 29, a plurality (three in the illustrated example) of reinforcing bar cages 8 are temporarily stacked through a plurality of (three in the illustrated example) spacers 9 and 9a.

【0007】そこで、図30に示すように、鉄筋篭8を
現場に移動する。
[0007] Then, as shown in FIG. 30, the rebar basket 8 is moved to the site.

【0008】現場においては図31及び図32に示すよ
うに、クローラクレーン10の主巻フック11、吊治具
12、吊ワイヤロープ13及び補巻フック14により鉄
筋篭8を吊り、矢印方向に建起する。この際鉄筋篭8の
縦方向剛性を補強するため、側部に複数のラチス筋15
を取付ける。
At the site, as shown in FIGS. 31 and 32, the reinforced basket 8 is hung by the main winding hook 11, the hanging jig 12, the hanging wire rope 13 and the auxiliary winding hook 14 of the crawler crane 10, and is built in the direction of the arrow. Wake up. At this time, in order to reinforce the longitudinal rigidity of the reinforcing bar 8, a plurality of lattice bars 15
Install.

【0009】次いで、図33及び図34に示すように、
鉄筋篭8の縦筋2の下端を、既設ロットコンクリートC
の頂面からオーバラップ部Lだけ突出している縦筋2a
の部分に建込み、結束する。なお、図中の符号Aはセグ
メント、Bは型枠フレームである。
Next, as shown in FIGS. 33 and 34,
The lower end of the vertical bar 2 of the reinforcing bar 8 is connected to the existing lot concrete C.
Longitudinal stripes 2a protruding from the top surface of the
Erected and united. In addition, the code | symbol A in a figure is a segment, B is a formwork frame.

【0010】次いで、図35に示すように、あらかじめ
既設ロットコンクリートC上に、円周筋3aを配材して
おく。これら円周筋3aは、側方から横移動させてもよ
く、又は、図36に示すように、鉄筋篭8の下部に円周
筋3aをたくし上げて配材しておいてもよい。
Next, as shown in FIG. 35, circumferential bars 3a are previously distributed on the existing lot concrete C. These circumferential bars 3a may be moved laterally from the side, or as shown in FIG. 36, the circumferential bars 3a may be lifted and distributed below the reinforcing bar cage 8.

【0011】次いで、図37に示すように、オーバラッ
プ部Lに円周筋3aを取付ける。
Next, as shown in FIG. 37, the circumferential muscle 3a is attached to the overlap portion L.

【0012】次いで、図38及び図39に示すように、
建込んだ鉄筋篭8の内部に作業員Mが入り、オーバラッ
プ部Lの両側円周筋3a、3aをスターラップ筋7で連
結し、結束する。
Next, as shown in FIGS. 38 and 39,
The worker M enters the built-in reinforcing bar cage 8, and connects the circumferential bars 3a, 3a on both sides of the overlap portion L with the stirrup bar 7, and binds them.

【0013】[0013]

【発明が解決しようとする課題】従来のプレファブ工法
においては、補強フレーム6(図21)は、本設の強度
メンバでなく、埋殺しになるので、無駄でありコスト高
になる。
In the conventional prefabrication method, the reinforcing frame 6 (FIG. 21) is not a permanent member, but is buried, resulting in waste and increased cost.

【0014】また、図28におけるスターラップ筋7に
よる外網筋4及び内網筋5の連結は、スターラップ筋7
の個数が多く、かつ、連結作業が困難で、時間と作業員
を多く必要とし、また、鉄筋組立架台1Aの数も多くな
る。
The connection of the outer reticulum 4 and the inner reticulum 5 by the stirrup muscle 7 in FIG.
And the connection work is difficult, requiring a lot of time and labor, and the number of reinforcing bar assembly bases 1A also increases.

【0015】また、図29における鉄筋篭8の仮置き
は、強度上から3段が限度で、仮置きスペースが広く必
要となる。
The temporary placement of the rebar basket 8 in FIG. 29 is limited to three steps from the viewpoint of strength, and a large temporary placement space is required.

【0016】また、図31における鉄筋篭8を補強する
ラチス筋15の取付けは面倒で、また、埋殺しになるの
で、無駄である。
Further, the attachment of the lattice bars 15 for reinforcing the reinforcing bar cage 8 in FIG. 31 is troublesome and buried, so that it is useless.

【0017】また、図34におけるオーバラップ部Lに
おける縦筋2、2aの結束は、ラチス筋15が邪魔で出
入が不自由であるなどして作業性が悪い。
Further, the binding of the vertical streaks 2 and 2a in the overlap portion L in FIG. 34 is inferior in workability because the lattice streaks 15 are in the way and access is difficult.

【0018】また、図35及び図36における円周筋3
aの配筋は、面倒で、かつ危険である。
The circumferential muscle 3 shown in FIGS.
Arrangement of a is troublesome and dangerous.

【0019】また、図37におけるオーバラップ部Lの
円周筋3aの取付けは、作業員Mが鉄筋篭8の内部に入
って行うため、作業性が悪く、危険である。
Further, the installation of the circumferential streaks 3a of the overlap portion L in FIG. 37 is performed by the worker M entering the inside of the reinforcing bar cage 8, so that the workability is poor and dangerous.

【0020】また、図38及び図39におけるオーバラ
ップ部Lのスターラップ筋7の取付けは、鉄筋篭8の内
部に作業員Mが入って行うため、作業が困難で作業性が
悪く、出来上りの品質が悪い。
Further, since the stirrup 7 of the overlap portion L in FIGS. 38 and 39 is attached by the worker M inside the reinforced cage 8, the work is difficult, the workability is poor, and Poor quality.

【0021】このように従来のプレファブ工法による鉄
筋篭8の組立て及び建込みは、資材の無駄があり、作業
性が悪く危険である。
As described above, assembling and installing the rebar basket 8 by the conventional prefabrication method involves waste of materials, poor workability, and is dangerous.

【0022】本発明は、資材の無駄がなく作業性が良く
安全な鉄筋篭組立・建込装置を提供することを目的とし
ている。
An object of the present invention is to provide a rebar cage assembling / building apparatus which is safe and has good workability without waste of materials.

【0023】[0023]

【課題を解決するための手段】本発明によれば、ベース
フレーム上に立設され外網筋形状に対応する形状の固定
側部フレームと、前記ベースフレーム上に走行自在に設
けられ、内網筋形状に対応する形状の可動側部フレーム
と、該可動側部フレームの前記固定側部フレームに対す
る間隔を調整する間隔調整手段と、前記両側部フレーム
の頂部を間隔調整自在に連結する吊ビーム受桁と、該吊
ビーム受桁に支持され、それぞれ外網筋及び内網筋を吊
設する外網筋吊ビーム及び内網筋吊ビームと、該両吊ビ
ームを連結する吊ビーム連結桁とを設けている。
According to the present invention, a fixed side frame standing on a base frame and having a shape corresponding to the shape of the outer mesh line is provided. A movable side frame having a shape corresponding to the streak shape, an interval adjusting means for adjusting an interval of the movable side frame with respect to the fixed side frame, and a suspension beam receiver for connecting the tops of the both side frames so as to be able to adjust the interval. A girder, an outer mesh reinforcement beam and an inner mesh reinforcement beam that are supported by the suspension beam receiving girder and hang the outer mesh reinforcement and the inner mesh reinforcement, respectively, and a suspension beam connection girder connecting the two suspension beams. Provided.

【0024】上記間隔調整手段は、内網筋側部フレーム
を支持する走行フレームと、この走行フレームとベース
フレームとの間に介装された走行駆動シリンダ等で構成
するのが好ましい。
It is preferable that the distance adjusting means comprises a traveling frame for supporting the inner reticulation side frame, and a traveling drive cylinder interposed between the traveling frame and the base frame.

【0025】また、両側部フレームには、数階の作業床
を設けるのが好ましい。
It is preferable to provide several floors of work floors on both side frames.

【0026】[0026]

【作用】上記のように構成された鉄筋篭組立・建込装置
においては、外網筋吊ビームを吊ビーム受桁に支持して
外網筋をセットし、同様にして内網筋をセットし、外網
筋側部フレーム側からスターラップ筋を挿入し、一端を
外網筋の円周筋に結束したのち、間隔調整手段により両
側部フレームの間隔を拡張してスターラップ筋の他端を
外網筋の円周筋に引掛け結束して鉄筋篭を組立てる。
In the rebar cage assembling / building apparatus constructed as described above, the outer net reinforcement is supported on the suspension beam receiving girder to set the outer net reinforcement, and the inner net reinforcement is similarly set. After inserting the stirrup muscle from the outer reticulum side frame side and binding one end to the circumferential muscle of the outer reticulum muscle, expanding the interval between the two side frames by the interval adjusting means to connect the other end of the stirrup muscle. Assemble the reinforcing bar cage by hooking and tying it to the circumferential muscle of the outer mesh bar.

【0027】次いで、両吊ビームを吊ビーム連結桁で連
結し、該連結桁を介して鉄筋篭を吊込み、移動して所定
位置に建込む。
Next, the two suspension beams are connected by a suspension beam connecting girder, and the reinforcing bar cage is hung through the connecting girder, moved and built at a predetermined position.

【0028】[0028]

【実施例】以下図面を参照して本発明の実施例を説明す
る。
Embodiments of the present invention will be described below with reference to the drawings.

【0029】図1ないし図6において、鉄筋篭組立・建
込装置のベースフレーム20の一側には、例えば地下タ
ンクを構築する外方に凸の円弧状の固定側部フレーム2
1が立設されている。その固定側部フレーム21には、
2階作業床22a〜5階作業床22d及び頂部作業床2
2eが設けられている。そして、ベースフレーム20に
は、固定側部フレーム21に対向する形状の可動側部フ
レーム23が接離方向に走行自在に立設されており、2
階作業床24a〜5階作業床24d及び頂部作業床24
eが設けられている。
In FIGS. 1 to 6, one side of a base frame 20 of the reinforced cage assembly / building device has an arc-shaped fixed side frame 2 which is outwardly convex and forms, for example, an underground tank.
1 is erected. In the fixed side frame 21,
2nd floor work floor 22a to 5th floor work floor 22d and top work floor 2
2e is provided. A movable side frame 23 having a shape facing the fixed side frame 21 is erected on the base frame 20 so as to be freely movable in the contact and separation directions.
Floor work floor 24a to 5th floor work floor 24d and top work floor 24
e is provided.

【0030】この可動側部フレーム23は、2組の走行
フレーム25に立設され、その走行フレーム25の両側
は、ベースフレーム走行ガイド部20aを挟持する前後
一対の走行ローラ26及びフックローラ27で走行ガイ
ド部20aにガイドされ、ベースフレーム20との間に
介装された走行駆動シリンダ28により可動範囲S(例
えば1000mm)の範囲で移動されるようになってお
り、これらの部材25〜28により間隔調整手段が構成
されている。
The movable side frame 23 is erected on two sets of running frames 25. On both sides of the running frame 25, a pair of front and rear running rollers 26 and hook rollers 27 sandwiching the base frame running guide portion 20a. It is guided by the travel guide portion 20a and is moved within a movable range S (for example, 1000 mm) by a travel drive cylinder 28 interposed between the travel guide portion 20a and the base frame 20. An interval adjusting means is configured.

【0031】また、図8に示すように、固定側部フレー
ム21の頂部両側には、吊ビーム受桁29の一端が固設
され、その吊ビーム受桁29の他端には、ローラ29a
を介して可動側部フレーム23の頂部両側が移動自在に
ガイドされている。
As shown in FIG. 8, one end of a suspension beam girder 29 is fixedly provided on both sides of the top of the fixed side frame 21, and the other end of the suspension beam girder 29 is provided with a roller 29a.
Both sides of the top portion of the movable side frame 23 are movably guided via.

【0032】そして、これら一対の吊ビーム受桁29に
は図17に示すように、外網筋吊ビーム30及び内網筋
吊ビーム31が支持され、それら両ビーム30、31
は、一対の吊ビーム連結桁32で連結されている。
As shown in FIG. 17, the pair of suspension beam receiving beams 29 support an outer mesh reinforcement beam 30 and an inner mesh reinforcement beam 31, and both beams 30, 31 are supported.
Are connected by a pair of suspension beam connection girders 32.

【0033】次に、図7ないし図18を参照して鉄筋篭
の組立・建込態様を説明する。
Next, the manner of assembling and installing the reinforcing bar will be described with reference to FIGS.

【0034】(1) 外網筋吊込工程(図7) 走行駆動シリンダ28、28を作動して可動側部フレー
ム23を移動し、固定側部フレーム21との間に、網筋
が挿入し易く、かつ、後記スターラップ筋7の長さより
若干(例えば400mm)狭い例えば800mmの間隔
Dを設ける。そこで、外網筋吊ビーム30と外網筋吊ロ
ープ30a、30aとにより外網筋4を両フレーム2
1、23の間に吊込む。
(1) External Reinforcement Hanging Step (FIG. 7) The traveling drive cylinders 28, 28 are operated to move the movable side frame 23, and the reinforcement is inserted between the movable side frame 23 and the fixed side frame 21. An interval D of, for example, 800 mm, which is easy and slightly (for example, 400 mm) smaller than the length of the stirrup streak 7, which will be described later, is provided. Therefore, the outer net reinforcement 4 is connected to both frames 2 by the outer net reinforcement beam 30 and the outer net reinforcement ropes 30a, 30a.
Hang between 1 and 23.

【0035】(2) 外網筋セット工程(図8) 外網筋吊ビーム30の両端を吊ビーム受桁29、29に
支持し、外網筋4を所定位置にセットする。
(2) Outer net reinforcement setting step (FIG. 8) Both ends of the outer net reinforcement beam 30 are supported by the suspension beam receiving beams 29, 29, and the outer net reinforcement 4 is set at a predetermined position.

【0036】(3) 内網筋吊込工程(図9) 内網筋吊ビーム31と内網筋吊ロープ31a、31aと
により内網筋5を、外網筋4と可動側部フレーム23と
の間に吊込む。
(3) Inner Reinforcement Hanging Step (FIG. 9) The inner reinforcement 5 is formed by the inner reinforcement suspension beam 31 and the inner reinforcement suspension ropes 31a, 31a. Hang it between.

【0037】(4) 内網筋セット工程(図10) 内網筋吊ビーム31の両端を吊ビーム受桁29、29に
支持し、内網筋5を所定位置にセットする。
(4) Inner Reinforcement Setting Step (FIG. 10) The both ends of the inner reinforcement hanging beam 31 are supported by the suspension beam receiving beams 29, 29, and the inner reinforcement 5 is set at a predetermined position.

【0038】(5) スターラップ筋セット工程(図1
1ないし図13) 作業員Mは作業床24a〜24dにおいて、床上に仮置
きしてあるスターラップ筋7を内網筋5側から外網筋4
側に押し込み、手前側の端部7aを外網筋5の円周筋3
に結束する。なお、この際、スターラップ筋7の他側
は、外網筋4の円周筋3上に載置され、端部7bと円周
筋3との間には、間隔D1(例えば400mm)が形成
されている。
(5) Stirrup streaks setting step (FIG. 1)
1 to 13) On the working floors 24a to 24d, the worker M removes the stirrup streaks 7 temporarily placed on the floor from the inner stoma 5 side to the outer stoma 4
Side, and the end 7a on the near side is connected to the circumferential muscle 3
Unite. At this time, the other side of the stirrup streak 7 is placed on the circumferential streak 3 of the outer reticulum 4, and a gap D1 (for example, 400 mm) is provided between the end 7b and the circumferential streak 3. Is formed.

【0039】(6) 網筋間拡張工程(図14ないし図
16) 走行駆動シリンダ28、28を収縮し、可動側部フレー
ム23を距離Dと距離D1との差(例えば400mm)
だけ固定側部フレーム21との間を拡張し、スターラッ
プ筋7の端部7bを外網筋4の円周筋3にひっかけ、結
束する。なお、この工程の当初において、外網筋4及び
内網筋5の底部a、bを、それぞれ両フレーム21、2
3に結束しておく。
(6) Step of Expanding between Reticulated Bars (FIGS. 14 to 16) The traveling drive cylinders 28, 28 are contracted, and the movable side frame 23 is moved to the difference between the distance D and the distance D1 (for example, 400 mm).
Only the space between the fixed side frame 21 and the end portion 7b of the stirrup 7 is hooked on the circumferential muscle 3 of the outer mesh wire 4 and bound. At the beginning of this step, the bottom portions a and b of the outer and inner reticulated muscles 4 and 5 are attached to both frames 21 and 2 respectively.
3

【0040】(7) 鉄筋篭吊込工程(図17及び図1
8) 外網筋吊ビーム30と内網筋吊ビーム31とを、一対の
吊ビーム連結桁32で連結し、これらの吊ビーム連結桁
32、32を介して鉄筋篭33を吊込み、移動して所定
位置に建込む。
(7) Reinforced basket hanging process (FIG. 17 and FIG. 1)
8) The outer rebar suspension beam 30 and the inner rebar suspension beam 31 are connected by a pair of suspension beam connection beams 32, and the reinforcing bar cage 33 is suspended and moved via these suspension beam connection beams 32, 32. To set it in place.

【0041】[0041]

【発明の効果】本発明は、以上説明したように構成され
ているので、以下に記載されるような効果を奏する。
Since the present invention is configured as described above, it has the following effects.

【0042】鉄筋篭を建起こす必要がないように吊込む
際の立てた状態で組立て、従来の建起こし時に保形する
のに必要な補強フレーム、ラチス筋を省き、資材の無駄
をなくすことができる。
It is possible to assemble the squirrel cage in an upright position so that it is not necessary to erect it, to omit the reinforcing frame and lattice bars necessary for retaining the shape at the time of conventional erecting, and to reduce waste of materials. it can.

【0043】また、特に作業性の悪いスターラップ筋の
取付けを、両網筋の間隔を拡張することにより容易に行
い、かつ、組立てのすべての作業を、両網筋外方の作業
床で行い、作業性を向上し、安全を図ることができる。
In addition, the stirrup streak, which is particularly difficult to work, can be easily mounted by extending the distance between the two reticulation bars, and all the assembly work is performed on the work floor outside the two reticulation bars. Thus, workability can be improved and safety can be improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例を示す側面図。FIG. 1 is a side view showing one embodiment of the present invention.

【図2】図1の正面図。FIG. 2 is a front view of FIG. 1;

【図3】図2の上面図。FIG. 3 is a top view of FIG. 2;

【図4】間隔調整手段を示す斜視図。FIG. 4 is a perspective view showing an interval adjusting unit.

【図5】図4の上面図。FIG. 5 is a top view of FIG. 4;

【図6】図4の部分的詳細図。FIG. 6 is a partial detailed view of FIG. 4;

【図7】外網筋吊込工程を説明する斜視図。FIG. 7 is a perspective view illustrating a step of suspending the outer net reinforcement.

【図8】外網筋セット工程を説明する斜視図。FIG. 8 is a perspective view illustrating an outer reticulum setting step.

【図9】内網筋吊込工程を説明する斜視図。FIG. 9 is a perspective view illustrating a step of suspending the inner reticulation.

【図10】内網筋セット工程を説明する斜視図。FIG. 10 is a perspective view illustrating an inner reticulum setting step.

【図11】スターラップ筋セット工程を説明する斜視
図。
FIG. 11 is a perspective view illustrating a stirrup stitch setting step.

【図12】図11の側面図。FIG. 12 is a side view of FIG. 11;

【図13】スターラップ筋の一端を結束した状態を示す
側面図。
FIG. 13 is a side view showing a state where one end of the stirrup stitch is bound.

【図14】網筋間拡張工程を説明する斜視図。FIG. 14 is a perspective view illustrating an interstitial muscle expanding step.

【図15】図14の側面図。FIG. 15 is a side view of FIG. 14;

【図16】スターラップ筋の両端を結束した状態を示す
側面図。
FIG. 16 is a side view showing a state in which both ends of the stirrup are bound.

【図17】外網筋吊ビーム及び内網筋吊ビームを吊ビー
ム連結桁で連結した状態を示す斜視図。
FIG. 17 is a perspective view showing a state in which the outer net reinforcement beam and the inner net reinforcement beam are connected by a suspension beam connecting girder.

【図18】鉄筋篭吊込工程を説明する斜視図。FIG. 18 is a perspective view illustrating a reinforcing cage hanging step.

【図19】従来のプレファブ工法の外網筋及び内網筋組
立工程を説明する斜視図。
FIG. 19 is a perspective view for explaining an outer reinforcement and an inner reinforcement assembling step of the conventional prefabrication method.

【図20】図19で製作された外網筋及び内網筋を示す
斜視図。
FIG. 20 is a perspective view showing the outer and inner reticulated muscles produced in FIG. 19;

【図21】内網筋セット工程を説明する斜視図。FIG. 21 is a perspective view illustrating an inner reticulum setting step.

【図22】図21の側面図。FIG. 22 is a side view of FIG. 21;

【図23】外網筋セット工程を説明する斜視図。FIG. 23 is a perspective view for explaining an outer net reinforcement setting step.

【図24】図23の側面図。FIG. 24 is a side view of FIG. 23.

【図25】スターラップ筋の一例を示す側面図。FIG. 25 is a side view showing an example of the stirrup streaks.

【図26】スターラップ筋の他例を示す側面図。FIG. 26 is a side view showing another example of the stirrup streaks.

【図27】スターラップ筋の他例を示す斜視図。FIG. 27 is a perspective view showing another example of the stirrup streaks.

【図28】鉄筋篭組立工程を説明する側面図。FIG. 28 is a side view illustrating a reinforcing cage assembly process.

【図29】鉄筋篭仮置工程を説明する斜視図。FIG. 29 is a perspective view illustrating a reinforcing cage temporary placement step.

【図30】鉄筋篭移動工程を説明する斜視図。FIG. 30 is a perspective view illustrating a rebar cage moving step.

【図31】鉄筋篭建起工程を説明する側面図。FIG. 31 is a side view for explaining a reinforcing cage building process.

【図32】鉄筋篭の建起こした状態を示す側面図。FIG. 32 is a side view showing a state in which the reinforcing cage is erected.

【図33】鉄筋篭建込工程を説明する側面図。FIG. 33 is a side view for explaining the reinforcing cage building process.

【図34】鉄筋篭固定工程を説明する側面図。FIG. 34 is a side view illustrating a reinforcing cage fixing step.

【図35】円周筋配材の一態様を説明する側面図。FIG. 35 is a side view illustrating one embodiment of a circumferential muscle distribution member.

【図36】円周筋配材の他態様を説明する側面図。FIG. 36 is a side view illustrating another embodiment of the circumferential muscle distribution member.

【図37】円周筋取付工程を説明する側面図。FIG. 37 is a side view for explaining a circumferential streak attaching step.

【図38】スターラップ筋取付工程を説明する側面図。FIG. 38 is a side view illustrating a stirrup streak attaching process.

【図39】スターラップ取付態様を示す斜視図。FIG. 39 is a perspective view showing a stirrup mounting mode.

【符号の説明】[Explanation of symbols]

A・・・セグメント B・・型枠フレーム C・・・既設ロッドコンクリート D、D1・・・両側部フレームの間隔 L・・・オーバラップ部 M・・・作業員 S・・・可動範囲 1、1A・・・鉄筋組立架台 2、2a・・・縦筋 3・・・円周筋 4・・・外網筋 5・・・内網筋 6・・・補強フレーム 7、7A、7B・・・スターラップ筋 7a、7b・・・スターラップ筋の端部 8・・・鉄筋篭 9、9a・・・スペーサ 10・・・クローラクレーン 11・・・主巻フック 12・・・吊治具 13・・・吊ワイヤロープ 14・・・補巻フック 15・・・ラチス筋 20・・・ベースフレーム 20a・・・ベースフレーム走行ガイド 21・・・固定側部フレーム 22a〜22d、24a〜24d・・・作業床 23・・・可動側部フレーム 25・・・走行フレーム 26・・・走行ローラ 27・・・フックローラ 28・・・走行駆動シリンダ 29・・・吊ビーム受桁 29a・・・ローラ 30・・・外網筋吊ビーム 31・・・内網筋吊ビーム 32・・・吊ビーム連結桁 33・・・鉄筋篭 A: Segment B: Formwork frame C: Existing rod concrete D, D1: Spacing between both side frames L: Overlapping part M: Worker S: Movable range 1, 1A ... rebar assembly base 2, 2a ... vertical bar 3 ... circumferential bar 4 ... outer net bar 5 ... inner web bar 6 ... reinforcement frame 7, 7A, 7B ... Stirrup streaks 7a, 7b: End of stirrup streaks 8: Reinforcing bar 9, 9a: Spacer 10: Crawler crane 11: Main winding hook 12: Suspension jig 13. ..Hanging wire ropes 14 ... Hook-up hooks 15 ... Lattice streaks 20 ... Base frame 20a ... Base frame running guide 21 ... Fixed side frames 22a-22d, 24a-24d ... Work floor 23 ・ ・ ・ Movable side frame 25 ・..Running frame 26 ... Running roller 27 ... Hook roller 28 ... Running drive cylinder 29 ... Suspension beam receiving beam 29a ... Roller 30 ... Outer net suspension beam 31 ... Inner Reinforcing beam suspension beam 32 ... suspension beam connecting girder 33 ... steel cage

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 ベースフレーム上に立設され外網筋形状
に対応する形状の固定側部フレームと、前記ベースフレ
ーム上に走行自在に設けられ、内網筋形状に対応する形
状の可動側部フレームと、該可動側部フレームの前記固
定側部フレームに対する間隔を調整する間隔調整手段
と、前記両側部フレームの頂部を間隔調整自在に連結す
る吊ビーム受桁と、該吊ビーム受桁に支持され、それぞ
れ外網筋及び内網筋を吊設する外網筋吊ビーム及び内網
筋吊ビームと、該両吊ビームを連結する吊ビーム連結桁
とを設けたことを特徴とする鉄筋篭組立・建込装置。
1. A fixed side frame which is erected on a base frame and has a shape corresponding to the shape of an outer netting, and a movable side portion which is provided on the base frame so as to run freely and has a shape corresponding to the shape of an inner netting. A frame, an interval adjusting means for adjusting an interval of the movable side frame with respect to the fixed side frame, a suspension beam receiving beam for connecting the tops of the both side frames so as to be adjustable in distance, and supported by the suspension beam receiving beam. And an outer net reinforcement and an inner net reinforcement suspended respectively for suspending the outer reinforcement and the inner reinforcement, and a suspension beam connecting girder connecting the both suspension beams.・ Building equipment.
JP15342293A 1993-06-24 1993-06-24 Reinforcing cage assembly / building equipment Expired - Fee Related JP2697807B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15342293A JP2697807B2 (en) 1993-06-24 1993-06-24 Reinforcing cage assembly / building equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15342293A JP2697807B2 (en) 1993-06-24 1993-06-24 Reinforcing cage assembly / building equipment

Publications (2)

Publication Number Publication Date
JPH0711771A JPH0711771A (en) 1995-01-13
JP2697807B2 true JP2697807B2 (en) 1998-01-14

Family

ID=15562165

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15342293A Expired - Fee Related JP2697807B2 (en) 1993-06-24 1993-06-24 Reinforcing cage assembly / building equipment

Country Status (1)

Country Link
JP (1) JP2697807B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3509444B2 (en) * 1997-01-13 2004-03-22 住友電装株式会社 Insert molding connector
JPH11339881A (en) * 1998-05-27 1999-12-10 Sumitomo Wiring Syst Ltd Connector
JP3997852B2 (en) 2002-06-28 2007-10-24 住友電装株式会社 Insert molded connector

Also Published As

Publication number Publication date
JPH0711771A (en) 1995-01-13

Similar Documents

Publication Publication Date Title
JP2697807B2 (en) Reinforcing cage assembly / building equipment
JP3054736B2 (en) How to assemble the beam concrete reinforced mesh
JP3752934B2 (en) Method for constructing annular concrete frame using slip form device
JP2593621B2 (en) Reinforcing cage assembly / building equipment
JP3538017B2 (en) Precast column unit and column construction method using it
JP3426492B2 (en) Hollow precast concrete precast concrete column unit with column and beam reinforcement and column construction method using this column unit
CN211447283U (en) Connecting beam of main building and skirt house
JP2748964B2 (en) Reinforcing cage assembly / building equipment
JP2000273946A (en) Method for constructing reinforced concrete structure
JP2648937B2 (en) Reinforcing bar for long span beams
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
JP2001081865A (en) Roof structure and construction method therefor
JP3187618B2 (en) How to assemble beam reinforcement
JP4005259B2 (en) How to build columns and beams
JP2733536B2 (en) Beam rebar preassembly method and beam rebar suspension device
JPH0978836A (en) Combined reinforcements for wall and beam and formation method of mold by use thereof
JP2847046B2 (en) Pre-assembly method of reinforced concrete small beam rebar
JPH0988348A (en) Method for constructing foundation beam
JPH05263526A (en) Construction method of rc construction beam
RU1783101C (en) Method of strengthening precast ferroconcrete multi-hollow panel floor
JPH0738516Y2 (en) Reinforcing bar for opening
JPS6114295B2 (en)
KR0135678B1 (en) Method for installing safety nets on steel structure
JPH0643237Y2 (en) Formwork for legal form
JPH0528248Y2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees