JPS61102970A - Construction of turbine building - Google Patents

Construction of turbine building

Info

Publication number
JPS61102970A
JPS61102970A JP22419484A JP22419484A JPS61102970A JP S61102970 A JPS61102970 A JP S61102970A JP 22419484 A JP22419484 A JP 22419484A JP 22419484 A JP22419484 A JP 22419484A JP S61102970 A JPS61102970 A JP S61102970A
Authority
JP
Japan
Prior art keywords
turbine
pedestal
construction
turbine pedestal
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP22419484A
Other languages
Japanese (ja)
Inventor
平野 厚志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP22419484A priority Critical patent/JPS61102970A/en
Publication of JPS61102970A publication Critical patent/JPS61102970A/en
Pending legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明は発電所におけるタービン建屋の建設工法に係り
、特に、タービンペデスタルの建設方法を改良したター
ビン建屋の建設工法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a method for constructing a turbine building in a power plant, and particularly to a method for constructing a turbine building that is an improved method for constructing a turbine pedestal.

〔発明の技術的背景とその問題点〕[Technical background of the invention and its problems]

従来のタービン建屋は第3図に示すように構成゛され、
タービン本体1は基礎のマット2上に立設され、タービ
ンペデスタル3により支持されている。ずなわら、ター
ビン本体1の下部外周はタービンペデスタル3の柱部3
aにより囲まれ、タービン本体1の上部はタービンペデ
スタル3の頂部3bにより支持されている。タービンペ
デスタル3の外周には各種機器(図示せず)を収容する
機器室4が複数配設され、タービンペデスタル3の外周
に隣接する機器室4の隣接壁4aとタービンペデスタル
3の外周面には防振のために所要のギャップ5が設定さ
れている。また、タービン本体1の上方にはタービン建
′屋屋根6が横架されてぃる。
A conventional turbine building is constructed as shown in Figure 3.
The turbine body 1 is erected on a foundation mat 2 and supported by a turbine pedestal 3. However, the lower outer periphery of the turbine body 1 is the column part 3 of the turbine pedestal 3.
The upper part of the turbine body 1 is supported by the top part 3b of the turbine pedestal 3. A plurality of equipment chambers 4 for accommodating various types of equipment (not shown) are arranged around the outer periphery of the turbine pedestal 3, and an adjacent wall 4a of the equipment room 4 adjacent to the outer periphery of the turbine pedestal 3 and an outer peripheral surface of the turbine pedestal 3 are provided with A required gap 5 is set for vibration prevention. Further, a turbine building roof 6 is horizontally suspended above the turbine main body 1.

次に、従来のタービン建屋建設工法を第3図に基づいて
説明する。
Next, a conventional turbine building construction method will be explained based on FIG. 3.

まず、タービン建屋基礎部分であるマット2の鉄筋、型
枠、コンクリート打設を行なう。このマット2の工事が
完了した復、タービンペデスタル3の柱部3aの鉄筋、
型枠、コンクリート打設を数分割に分けて行ない、順次
タービンペデスタル3の柱部3aの建て上げを行なう。
First, reinforcing bars, formwork, and concrete for mat 2, which is the foundation of the turbine building, will be placed. After the construction of this mat 2 is completed, the reinforcing bars of the column part 3a of the turbine pedestal 3,
Formwork and concrete pouring are carried out in several parts, and the column parts 3a of the turbine pedestal 3 are erected one after another.

この柱部3aの建て上げにより、その頂部3bが完成し
た後、タービンペデスタル3外周部の足場解体を行なう
After the top 3b of the column 3a is completed, the scaffolding around the outer periphery of the turbine pedestal 3 is dismantled.

このようなタービンペデスタル建設工事が完了した後、
タービンペデスタル3外周のタービン系機器の設置エリ
アとなる機器室4を、鉄筋、型枠、コンクリート打設の
順序で行ないながら、順次下から建て上げて行く。この
機器室4の建設工事が完成後、タービン建屋屋根6の鉄
骨組立および鉄筋コンクリート工事を行ない、タービン
建屋を完成させる。タービン建屋が完成した後、タービ
ン本体1および発電機本体(図示せず)を据付ける。
After such turbine pedestal construction work is completed,
The equipment room 4, which will be the installation area for turbine system equipment around the outer periphery of the turbine pedestal 3, will be built from the bottom up, with reinforcing bars, formwork, and concrete being poured in that order. After the construction work of this equipment room 4 is completed, the steel frame assembly and reinforced concrete work for the turbine building roof 6 are performed to complete the turbine building. After the turbine building is completed, the turbine main body 1 and the generator main body (not shown) are installed.

しかしながら、このような従来のタービン建屋の建設工
法では、タービンペデスタル3と、この・タービンペデ
スタル3の外周に隣接する機器室4の隣接壁4aとの間
には、プラント運転中にタービン本体1の撮動が他の機
器類に影響を与えないようにすると共に、タービン本体
1が他の機器類の振動により、影響を受けないようにす
る等の理由から例えば約5In!R程度のギャップ5を
設けている。このために、タービンペデスタル3の完成
後、所定のギャップ5を有するように機器室4の建設工
事に着手していた。その結果、タービン建屋の建設工期
が長くなり、タービン建屋内の機器類の据付、配管工事
およびタービン本体の据付も遅くなるため発電所建設工
期が長くなるという問題があった。
However, in such a conventional turbine building construction method, there is a gap between the turbine pedestal 3 and the adjacent wall 4a of the equipment room 4 adjacent to the outer periphery of the turbine pedestal 3. For example, about 5 In! to prevent the photographing from affecting other equipment and to prevent the turbine body 1 from being affected by the vibrations of other equipment. A gap 5 of approximately R is provided. For this purpose, after completion of the turbine pedestal 3, construction work for the equipment room 4 was started so as to have a predetermined gap 5. As a result, the construction period for the turbine building becomes longer, and the installation of equipment in the turbine building, piping work, and installation of the turbine itself are also delayed, resulting in a problem that the power plant construction period becomes longer.

(発明の目的) 本発明の目的は、タービン建屋の建設工期を短縮するこ
とにより発電所建設工期の大幅な短縮と建設工事の能率
向上を図ることができるタービン建屋の建設工法を提供
することにある。
(Objective of the Invention) An object of the present invention is to provide a construction method for a turbine building that can significantly shorten the construction period of a power plant and improve the efficiency of construction work by shortening the construction period of the turbine building. be.

(発明の概要) 上述した目的を達成するために本発明は、タービンペデ
スタルと、このタービンペデスタルの外周に隣接する綴
器室の隣接壁とを一体化し、この一体化したタービンペ
デスタルの建設工事と機器室の建設工事とを並行して行
ない、タービンペデスタル建設工事の上部と下部との画
成部には弾性部材を介在させてタービンペデスタル頂部
を建設することを特徴とする。
(Summary of the Invention) In order to achieve the above-mentioned object, the present invention integrates a turbine pedestal and an adjacent wall of an orthopedic chamber adjacent to the outer periphery of the turbine pedestal, and performs construction work of the integrated turbine pedestal. The construction work of the equipment room is carried out in parallel, and the top part of the turbine pedestal is constructed by interposing an elastic member between the upper part and the lower part of the turbine pedestal construction work.

〔発明の実施例〕[Embodiments of the invention]

以下、本発明の一実施例について図面を参照して説明J
る。なお、第1図中、第3図と同一部分には同一符号を
付してその説明を省略する。
Hereinafter, one embodiment of the present invention will be explained with reference to the drawings.
Ru. In FIG. 1, the same parts as in FIG. 3 are designated by the same reference numerals, and their explanations will be omitted.

第1図は本発明の一実施例の全体構成を示す概略縦断面
図であり、タービン本体1はマット2上に立設され、タ
ービンペデスタル1oにより支持されている。すなわち
、タービンペデスタル10の柱部10aによりタービン
本体1の下部外周が囲まれ、タービンペデスタル10の
頂部10bによりタービン本体1の上部が支持されてい
る。上記タービンペデスタル10の柱部10aは、この
柱部10aの外周に隣接する機器室11の隣接壁11a
と一体化され、第3図で示す従来例のように、柱部10
aと隣接壁11aとの間にはギャップ5が設置プられて
いない。一方、タービン本体1の上部を支持するタービ
ンペデスタル10の頂部10bは上部12と下部13と
に上下方向に画成され、その画成部のギャップ10cに
は第2図に示すようにスプリングユニット14が介在さ
れている。このスプリングユニット14の上下両面は粘
着質板15がそれぞれ配設されている。
FIG. 1 is a schematic vertical sectional view showing the overall configuration of an embodiment of the present invention, in which a turbine main body 1 is erected on a mat 2 and supported by a turbine pedestal 1o. That is, the lower outer periphery of the turbine body 1 is surrounded by the pillar portion 10a of the turbine pedestal 10, and the upper part of the turbine body 1 is supported by the top portion 10b of the turbine pedestal 10. The column portion 10a of the turbine pedestal 10 is connected to an adjacent wall 11a of the equipment room 11 adjacent to the outer periphery of the column portion 10a.
As in the conventional example shown in FIG.
No gap 5 is provided between a and the adjacent wall 11a. On the other hand, the top part 10b of the turbine pedestal 10 that supports the upper part of the turbine body 1 is vertically defined by an upper part 12 and a lower part 13, and a spring unit 14 is provided in a gap 10c in the defined part, as shown in FIG. is mediated. Adhesive plates 15 are provided on both upper and lower surfaces of the spring unit 14, respectively.

次に、このように構成されたタービン建屋の建設工法の
一実施例について述べる。
Next, an embodiment of a construction method for a turbine building constructed in this manner will be described.

まず、第1図に示すように建屋基礎部分であるマット2
の鉄筋、型枠、コンクリート打設を行なう。この工程は
従来と同じである。マット2の完成後、タービンペデス
タル10の柱部10aの建設工事と、この柱部10aの
外周に配設される機器室11の建設工事とを並行して行
なう。すなわち、タービンペデスタル10の柱部10a
は、この柱部10aの外周に隣接するm器室11の壁に
形成されるものであり、足場組立、鉄筋、コンクリート
打設を順次行い、この柱部10aを建て上げる。そして
、この柱部10aの構築レベルがタービンペデスタル頂
部10bの下部13に達した時点でタービン本体1の基
礎となるタービンペデスタル頂部10bの上部12の工
事を行なう。すなわち、第2図の部分拡大図に示すよう
に、タービンペデスタル頂部10bの下部13のコンク
リート打設後、コンクリート面のレベル測定を行なう。
First, as shown in Figure 1, the mat 2, which is the foundation of the building,
Reinforcement, formwork, and concrete placement will be carried out. This process is the same as before. After the mat 2 is completed, the construction work of the column part 10a of the turbine pedestal 10 and the construction work of the equipment room 11 arranged around the outer periphery of this column part 10a are carried out in parallel. That is, the pillar portion 10a of the turbine pedestal 10
is formed on the wall of the chamber 11 adjacent to the outer periphery of the column 10a, and the column 10a is erected by sequentially assembling scaffolding, reinforcing bars, and placing concrete. Then, when the construction level of this column 10a reaches the lower part 13 of the turbine pedestal top 10b, the upper part 12 of the turbine pedestal top 10b, which becomes the foundation of the turbine body 1, is constructed. That is, as shown in the partially enlarged view of FIG. 2, after concrete is placed in the lower part 13 of the turbine pedestal top 10b, the level of the concrete surface is measured.

次にコンクリート面に弾力性を有する粘着質板15を載
置し、この粘着質板15上にスプリングユニット14を
セットし、次に、タービンペデスタル頂部10bの上部
12の支保工組立、型枠取付、鉄筋組立、タービン本体
1のアンカボルト据付は等を行なう。このとき、スプリ
ングユニット14上の弾力性を有する粘着質板15およ
びしl    ベル調整用のシムプレート16をセット
する。このような弾力性を有する粘着質板15をセット
することにより、タービンペデスタル頂部10bの上部
12の構築が容易なものとなる。
Next, an elastic adhesive board 15 is placed on the concrete surface, and the spring unit 14 is set on this adhesive board 15. Next, the support assembly for the upper part 12 of the turbine pedestal top 10b and the formwork installation are carried out. , assembling reinforcing bars, installing anchor bolts for the turbine body 1, etc. At this time, the elastic adhesive plate 15 on the spring unit 14 and the shim plate 16 for adjusting the lever are set. By setting the adhesive plate 15 having such elasticity, the construction of the upper part 12 of the turbine pedestal top part 10b becomes easy.

また、スプリングユニット14は、タービン本体1の据
付時の前後にスプリングの調整を行なう。
Further, the spring unit 14 adjusts the spring before and after installing the turbine main body 1.

スプリングユニット14によりタービン本体1の振動や
機器室11の機器類の振動が吸収され、また、地震等の
不測の事態の場合にもタービン本体1の振動、r1重が
吸収されるため、構築物は安定である。タービンペデス
タル頂部10bの上部12のコンクリート打設の準備が
終了後、コンクリート打設を行ない、タービンペデスタ
ル頂部10b全体の工事を完了させる。しかる後に、タ
ービン建屋屋根5の建設工事を行ない、タービン建屋の
工事が完了する。
The spring unit 14 absorbs the vibrations of the turbine body 1 and the vibrations of the equipment in the equipment room 11, and also in the event of an unexpected situation such as an earthquake, the vibrations of the turbine body 1 and the r1 weight are absorbed, so the structure is It is stable. After finishing the preparation for placing concrete on the upper part 12 of the turbine pedestal top 10b, concrete is placed to complete the construction of the entire turbine pedestal top 10b. After that, the construction of the turbine building roof 5 is carried out, and the construction of the turbine building is completed.

〔発明の効果〕〔Effect of the invention〕

以上説明したように本発明は、タービンペデスタルとそ
の外周に設置される機器室を構築するタービン建屋の建
設工法において、上記タービンペデスタルの頂部を上部
と下部とに上下方向に画成すると共に、この下部を含む
タービンペデスタル本体と、このタービンペデスタル本
体外周に隣接する上記機器室の隣接壁とを一体化し、こ
の一体化したタービンペデスタル本体の建設工事と上記
機器室の建設工事とを並行して行ない、上記タービンペ
デスタル頂部の上部と下部との画成部には弾性材を介在
させてタービンペデスタル頂部の上部を構築する。
As explained above, the present invention provides a method for constructing a turbine building in which a turbine pedestal and an equipment room installed around its outer periphery are constructed, in which the top of the turbine pedestal is defined in the vertical direction into an upper part and a lower part. The turbine pedestal main body including the lower part and the adjacent wall of the equipment room adjacent to the outer periphery of the turbine pedestal main body are integrated, and the construction work of the integrated turbine pedestal main body and the construction work of the equipment room are performed in parallel. The upper part of the turbine pedestal is constructed by interposing an elastic material between the upper and lower parts of the turbine pedestal.

したがって、本発明によれば、タービンペデスタル頂部
の完成を待つことなく、タービンへデスタルの建設工事
と並行して機器室の建設工事を行なうことができ、ター
ごン杼屋の建設工程が短縮され、タービン本体の据付、
タービン系機器室の様器据付が早くなり、発電所建設工
期の大幅な短縮と建設工事の能率向上を図ることができ
る。
Therefore, according to the present invention, the construction of the equipment room can be carried out in parallel with the construction of the turbine pedestal without waiting for the completion of the top of the turbine pedestal, and the construction process of the targon shuttle is shortened. , installation of the turbine body,
This will speed up the installation of equipment in the turbine equipment room, significantly shortening the power plant construction period and improving the efficiency of construction work.

また、タービンペデスタル頂部の上部と下部との画成部
に弾性部材を介在させたので、ターごン本体の振動およ
び機器室内の機器類の振動はこの弾性部材にて吸収され
防振効果の向上を図ることができる。
In addition, since an elastic member is interposed between the upper and lower parts of the top of the turbine pedestal, the vibrations of the targon body and the vibrations of the equipment in the equipment room are absorbed by this elastic member, improving the vibration isolation effect. can be achieved.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係る一実施例を説明するためのタービ
ン本体を中心としたタービン建屋の概略縦断面図、第2
図は第1図の要部拡大図、第3図は従来のタービン建屋
のぼ殿方法を説明するためのタービン本体を中心とした
タービン建屋の概略縦断面図である。 1・・・タービン本体、2・・・マット、3.10・・
・タービンペデスタル、3a、10a・・・タービンペ
デスタルの柱部、3b、10b・・・タービンペデスタ
ルの頂部、4・・・機器室、4a・・・隣接壁、5,1
00・・・ギャップ、6・・・ターごン建屋屋根、11
・・・別器室、11a・・・隣接壁、12・・・タービ
ンペデスタル頂部の上部、13・・・タービンペデスタ
ル頂部の下部、14・・・スプリングユニット。 出願人代理人   波 多 野   久第1図 第2図 第3図
FIG. 1 is a schematic vertical cross-sectional view of a turbine building centered on the turbine body for explaining one embodiment of the present invention, and FIG.
The figure is an enlarged view of the main part of FIG. 1, and FIG. 3 is a schematic longitudinal sectional view of the turbine building centered on the turbine body for explaining the conventional method of building the turbine building. 1... Turbine body, 2... Mat, 3.10...
- Turbine pedestal, 3a, 10a... Column part of turbine pedestal, 3b, 10b... Top of turbine pedestal, 4... Equipment room, 4a... Adjacent wall, 5, 1
00... Gap, 6... Targon building roof, 11
... Separate chamber, 11a... Adjacent wall, 12... Upper part of the top of the turbine pedestal, 13... Lower part of the top of the turbine pedestal, 14... Spring unit. Applicant's agent Hisashi Hatano Figure 1 Figure 2 Figure 3

Claims (1)

【特許請求の範囲】 1、タービンペデスタルとその外周に配設される機器室
を構築するタービン建屋の建設工法において、上記ター
ビンペデスタルの頂部を上部と下部とに上下方向に画成
すると共に、この下部を含むタービンペデスタル本体と
、このタービンペデスタル本体外周に隣接する上記機器
室の隣接壁とを一体化し、この一体化したタービンペデ
スタル本体の建設工事と上記機器室の建設工事とを並行
して行ない、上記タービンペデスタル頂部の上部と下部
との画成部には弾性部材を介在させてタービンペデスタ
ル頂部の上部を構築することを特徴とするタービン建屋
の建設工法。 2、弾性部材がスプリングユニットである特許請求の範
囲第1項に記載のタービン建屋の建設工法。
[Claims] 1. In a construction method for a turbine building in which a turbine pedestal and an equipment room arranged around its outer periphery are constructed, the top of the turbine pedestal is vertically defined into an upper part and a lower part, and The turbine pedestal main body including the lower part and the adjacent wall of the equipment room adjacent to the outer periphery of the turbine pedestal main body are integrated, and the construction work of the integrated turbine pedestal main body and the construction work of the equipment room are performed in parallel. A construction method for a turbine building, characterized in that the upper part of the turbine pedestal is constructed by interposing an elastic member between the upper and lower parts of the turbine pedestal. 2. The method for constructing a turbine building according to claim 1, wherein the elastic member is a spring unit.
JP22419484A 1984-10-26 1984-10-26 Construction of turbine building Pending JPS61102970A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22419484A JPS61102970A (en) 1984-10-26 1984-10-26 Construction of turbine building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22419484A JPS61102970A (en) 1984-10-26 1984-10-26 Construction of turbine building

Publications (1)

Publication Number Publication Date
JPS61102970A true JPS61102970A (en) 1986-05-21

Family

ID=16809990

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22419484A Pending JPS61102970A (en) 1984-10-26 1984-10-26 Construction of turbine building

Country Status (1)

Country Link
JP (1) JPS61102970A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008196716A (en) * 2007-02-08 2008-08-28 Toshiba Corp Turbine building integrated with condenser made of steel plate concrete, and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008196716A (en) * 2007-02-08 2008-08-28 Toshiba Corp Turbine building integrated with condenser made of steel plate concrete, and its construction method
JP4643599B2 (en) * 2007-02-08 2011-03-02 株式会社東芝 Steel plate concrete condenser-integrated turbine building and its construction method

Similar Documents

Publication Publication Date Title
JP3803434B2 (en) Installation method of seismic isolation devices in construction of building structures
JPS61102970A (en) Construction of turbine building
JP3004242B2 (en) Building material for vibration control, vibration control structure and construction method
JP2000226952A (en) Attaching structure of hysteresis damping member in concrete building frame structure, attaching method and vibration control concrete building frame structure
CN217711265U (en) Cast-in-place concrete steel wire net rack wallboard
JP2002295203A (en) Foundation pedestal for turbine generator and the construction method
JP2784450B2 (en) Reinforced concrete foundation
JPS63308B2 (en)
JPH03107047A (en) Constructing method for slab
JP2914539B2 (en) Steel beam assembly method for large-scale RC structures
JPH0743490A (en) Constructing method for reactor container
JPH1025922A (en) Base isolation steel flamed construction
JPH019037Y2 (en)
JP2001073713A (en) Machine frame and its construction
JP3110059B2 (en) Containment vessel construction method for nuclear power plants
JP2000120982A (en) Work executing method of frame for weight structure
JPH01306A (en) Steel mount for turbine
JPH01249902A (en) Turbine building
JPH07294682A (en) Reactor containment
JP2557427B2 (en) Reactor building mat construction method
JPS62157591A (en) Construction structure and method of container for nuclear reactor
JPH0820541B2 (en) How to construct a containment vessel
JP2004116281A (en) Construction method for concrete structure
JPH03290528A (en) Fabrication method for equipment rack foundation
JPS6113183A (en) Method of constructing mat for housing of nuclear reactor