JPS605906A - Installation work of penstock by jack-up process - Google Patents
Installation work of penstock by jack-up processInfo
- Publication number
- JPS605906A JPS605906A JP58113901A JP11390183A JPS605906A JP S605906 A JPS605906 A JP S605906A JP 58113901 A JP58113901 A JP 58113901A JP 11390183 A JP11390183 A JP 11390183A JP S605906 A JPS605906 A JP S605906A
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- tapered
- pipes
- jack
- inclined shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B9/00—Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
- E02B9/02—Water-ways
- E02B9/06—Pressure galleries or pressure conduits; Galleries specially adapted to house pressure conduits; Means specially adapted for use therewith, e.g. housings, valves, gates
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Abstract
Description
【発明の詳細な説明】
本発明は、ジヤツキアップによる水圧鉄管の据付工法に
関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for installing a penstock by jacking up.
従来、比較的小口径の水圧鉄管を長い斜坑内へ据付ける
方法としては、第1図に示すように据付ける鉄管より相
当大きい内径の斜坑(1)を掘削し、その中へレール(
2)を敷設し、斜坑(1)上部に連なる坑道の水平部に
設けた搬入口(3)から据付ける単管(43)を搬入す
ると共に搬入台車(5)に載せ、次に上部坑内の水平部
に設置した搬入用ウィンチi6)により搬入台車(5)
とと単管(43)を据付位置へ運び、搬入台車(5)を
引上げ、既据付管(42)へ手溶接により接合していた
。このような作業を繰り返していたので、単管、(44
,42,43・・・)の接合作業場所は、据付作業の進
行とともに変化するものである。また、据付ける鉄管(
4)と斜坑(1)内面との間をある程度大きくしないと
、斜坑(1)内で管の接合作業ができないため、斜坑(
1)の内径は大きなものとなり、掘削費用が高くなる欠
点があった。さらに裾付ける鉄管(4)の内径がある程
度より小さな場合、管内作業が困難であったり、斜坑(
1)が畏い場合、作業者が作業場所へ行くのに不便であ
ったり、作業場所が作業の進行とともに変化するので、
いつも一定の足場が確保できず、作業性に問題があるな
ど、多くの欠点があり、その改善が望まれていた。Conventionally, as shown in Figure 1, the method of installing a relatively small-diameter penstock pipe into a long inclined shaft is to excavate a inclined shaft (1) with a considerably larger inner diameter than the iron pipe to be installed, and then insert the rail (
2), the single pipe (43) to be installed is carried in from the entrance (3) provided in the horizontal part of the tunnel that connects to the upper part of the inclined shaft (1), and placed on the delivery cart (5), and then The loading truck (5) is moved by the loading winch (i6) installed on the horizontal section.
The single pipe (43) was carried to the installation position, the carrying cart (5) was pulled up, and it was joined to the already installed pipe (42) by hand welding. As I was repeating this kind of work, I decided to use a single tube (44
, 42, 43...) will change as the installation progresses. In addition, the iron pipe to be installed (
4) and the inner surface of the inclined shaft (1), the pipes cannot be joined inside the inclined shaft (1).
The disadvantage of 1) is that the inner diameter is large, which increases excavation costs. Furthermore, if the inner diameter of the hemming iron pipe (4) is smaller than a certain level, it may be difficult to work inside the pipe, or the inclined shaft (
If 1) is a concern, it may be inconvenient for workers to get to the work location, or the work location may change as the work progresses.
It had many shortcomings, such as not being able to secure a constant foothold at all times and problems with workability, and improvements were desired.
そこで本発明はかかる欠点を解消するジヤツキアップに
よる水圧鉄管据付工法を提供するものであって、その特
徴とするところは、斜坑の下端に作業室を形成し、該作
業室内にジャツギアップ設備を配設し、下部坑道から作
業室内に上端頭部が下端よシ大径のテーパ管を搬入し、
該テーパ管をジヤツキアップ設備により押上げ、下部坑
道から作業室内に第1単管を搬入すると共にその上端を
テーパ管の下端に接合し、次にジヤツキアップ設備によ
り第1単管を押上げてテーパ管を斜坑内に挿入し、テー
パ管と斜坑内面との7間にコンクリートを打設し、次に
作業室内に第2単管を搬入すると共にその上端を第1単
管の下端に接合し、次にジヤツキアップ設備により第2
単管を押上げ、テーパ管と斜坑内面との間にコンクリー
トを打設し同様にして第3以下の各単管を順次作業室内
に搬入すると共に単管どうしを接合かつジヤツキアップ
設備により押上げて斜坑内に水圧鉄管を配設し、その水
圧鉄管と既設コンクリートとの間にモルタルを充填する
ことにある。Therefore, the present invention provides a method for installing hydraulic iron pipes by jacking up that eliminates such drawbacks, and its characteristics are that a working chamber is formed at the lower end of the inclined shaft, and jacking up equipment is arranged in the working chamber. A tapered pipe whose upper head is larger in diameter than the lower end is carried into the work chamber from the lower tunnel.
The tapered pipe is pushed up by jack-up equipment, the first single pipe is carried into the work chamber from the lower tunnel, and its upper end is joined to the lower end of the tapered pipe, and then the first single pipe is pushed up by the jack-up equipment, and the tapered pipe is is inserted into the inclined shaft, concrete is poured between the tapered pipe and the inner surface of the inclined shaft, and then the second single pipe is carried into the working chamber and its upper end is joined to the lower end of the first single pipe. In the second stage, the jack-up equipment
The single pipes were pushed up, concrete was poured between the tapered pipe and the inner surface of the inclined shaft, and in the same way, each of the third and subsequent single pipes was carried into the work room one after another, and the single pipes were joined together and pushed up using jack-up equipment. The purpose of this method is to install a penstock in the inclined shaft and fill the space between the penstock and the existing concrete with mortar.
かかる工法によれば次の効果を得ることができる。According to this construction method, the following effects can be obtained.
げ) 単管を既に押し上げたテーパ管または単管の下端
へ接合する作業と並行して、斜坑内でコンクリートを打
設することができるため、作業能率がよい。(G) Concrete can be placed in the inclined shaft in parallel with the work of joining the single pipe to the lower end of the tapered pipe or single pipe that has already been pushed up, improving work efficiency.
(1′) いつも同じ作業室でテーパ管および単管の接
合ができるので、作業室に自動溶接機を設置しても、そ
の取扱いが極めて容易となり、溶接品質の向上を期待で
きる。(1') Since tapered pipes and single pipes can always be joined in the same work room, even if an automatic welding machine is installed in the work room, it is extremely easy to handle, and welding quality can be expected to improve.
(つ) 作業室の作業空間を十分確保でき、足場も安定
しており、作条者が墜落することもなく、安全性が向上
する。(1) Sufficient work space can be secured in the work room, and the footing is stable, preventing workers from falling, improving safety.
に)斜坑の内径を据付けるテーパ管および単管の外径よ
り少し大きくするだけで足りるので、斜坑掘削の費用も
少なくてすむ。(b) Since it is sufficient to make the inner diameter of the inclined shaft slightly larger than the outer diameter of the tapered pipe or single pipe to be installed, the cost of excavating the inclined shaft can be reduced.
(3) 作業者が作業室へ行くのに容易である。(3) It is easy for workers to get to the work room.
(力) 作業室への機材や資材の搬入が容易である。(Power) It is easy to bring equipment and materials into the work room.
(噌 作業室の換気も、場所が一定であるため容易であ
る。したがって環境衛生上も好ましい。(Sou) Ventilation of the work room is also easy because the location is fixed. Therefore, it is also favorable from the standpoint of environmental hygiene.
すなわち本発明の工法を実施すると、従来の工法に比べ
、作業能率、溶接品質、安全性、作業環境、経済性とも
に向上する効果がある。That is, when the construction method of the present invention is implemented, it has the effect of improving work efficiency, welding quality, safety, work environment, and economic efficiency compared to conventional construction methods.
以下本発明の一実施例を第2図以下の図に基づいて説明
する。αOは斜坑(1)の下端に形成された作業室、α
υは該作業室叫に連通ずる下部坑道であって、底面には
搬入台車(6)用のレールα]を敷設しである。Q41
は上端頭部が下端より大径のテーパ管、σ9は斜坑(1
)内に適当間隔ごとに配設された支持杆(IGの上端に
回転自在に配設されたテーパ管α4および単管(4,,
42,43・・・)のガイドローラである。07)は作
業室(IQの上部に配設された防護壁であって、中央に
テーパ管04)および単管(4,,4,45・・・)の
通過穴α印を形成しである。q俤は作業室(l(1の四
隅に配設婆れると共に両端が防護壁αηと作業室ooの
傾斜端面(IOA)とにそれぞれ固着された支柱であっ
て、互いに平行する2本のコの竿杆(19A)と、フの
竿杆(19A)どうしをつなぐ連結板(19B)とから
構成されている。An embodiment of the present invention will be described below with reference to FIG. 2 and the following figures. αO is the working chamber formed at the lower end of the inclined shaft (1), α
υ is a lower tunnel that communicates with the working room, and a rail α for the loading cart (6) is laid on the bottom surface. Q41
is a tapered pipe whose upper end head is larger in diameter than the lower end, and σ9 is an inclined shaft (1
) are arranged at appropriate intervals in the support rods (the tapered pipe α4 and the single pipe (4, ,
42, 43...) guide rollers. 07) is a protective wall installed in the upper part of the working chamber (IQ), which has a tapered pipe 04 in the center and a passage hole α mark for the single pipe (4, 4, 45...). . q is a column installed in the four corners of the work chamber (1), and both ends are fixed to the protective wall αη and the inclined end face (IOA) of the work chamber oo, and the two columns are parallel to each other. It consists of a rod rod (19A) and a connecting plate (19B) that connects the rod rods (19A).
また各コの竿杆(19A)にはその長手方向に沿って一
定間隔ごとにピン穴翰を形成しである。、、 WUは作
業室uo内に矢印(A)Q3)方向移動自在に配設され
た押上枠であって、その四隅には各支柱叫のコの字杆(
19A)内に嵌入する突出部(21A)を設けである。Further, pin holes are formed in the rod rod (19A) of each rod at regular intervals along its longitudinal direction. ,, WU is a push-up frame that is disposed in the work room uo so that it can move freely in the direction of arrow (A) Q3), and at its four corners there are U-shaped bars (
19A) is provided with a protrusion (21A) that fits into the inside.
(イ)は押上枠?pの中央に形成されたテーパ管(14
)および単管C41*42.45・・・)の通過穴に固
着されたリングであって、この実施例では90°おきに
切欠口@を形成しである。(財)は各切欠口@に対向し
てリング翰の外周面に固着されたコの字枠、(ハ)は該
コの字枠(ハ)内に矢印(C) (DJ方向移動自在に
配設された押えブロックであって、そのリング(イ)内
対向面は円弧面とされ、その円弧面には、テーパ管α→
および単管(4,。Is (a) an push-up frame? A tapered tube (14
) and a single tube C41*42.45...) are fixed to the passage holes, and in this embodiment, notches are formed at every 90°. (C) is a U-shaped frame fixed to the outer circumferential surface of the ring pen facing each notch opening @, (C) is an arrow (C) inside the U-shaped frame (C) (moveable in the DJ direction). The presser block is arranged so that the opposing surface inside the ring (A) is an arcuate surface, and the arcuate surface has a tapered pipe α→
and monotube (4,.
42.43・・・)の外周面下部に90’おきに固着さ
れた突条(イ)に嵌合する溝翰を形成しである。(ハ)
は各コの字#■の中央に形成したねじ穴に螺合すると共
に先端が各押えブロック(イ)に回転自在に連結された
へンドル翰付きねじ捧、輪は各支柱α呻のコの竿杆(1
’lA)内に配設された油圧シリンダであって、本体下
面に固着したピース(31)は押上枠&1)の各突出部
(21A)のブラケット(ハ)にピン連結されている。42, 43...) are formed with grooves that fit into the protrusions (A) fixed every 90' on the lower part of the outer peripheral surface. (c)
is screwed into the screw hole formed in the center of each U-shape #■, and the tip is rotatably connected to each presser block (A).The ring is attached to each support α. Pole rod (1
The piece (31), which is a hydraulic cylinder disposed in the 'lA) and fixed to the lower surface of the main body, is connected with a pin to the bracket (c) of each protrusion (21A) of the push-up frame &1).
(33)(2)は各支柱α呻のコの竿杆(1弧)のピン
穴(イ)に挿通されるピンであって、その上方ピン關に
は上記油圧シリンダーのピストンロッド先端の貫通穴間
が外嵌し、下方ピン(財)には上記突出部(21A)の
貫通穴間が外嵌している。(3′7)は作業室αQの傾
斜端面(10A)に配設された高さ調整ジヤツキ、(ハ
)は作業室0Qの傾斜側面(IOB)に配設された調心
ジヤツキである。なお作業室αQには自動溶接装置(図
示せず)を配設しである。第10図において唾は各単管
(41−42+45・・・)に形成されたモルタル充填
ノズル、顛は該ノズル(至)に接続されたモルタル供給
パイプである。(33) (2) is a pin that is inserted into the pin hole (A) of the rod rod (1 arc) of each support column α, and the upper pin hole is inserted through the tip of the piston rod of the hydraulic cylinder. The holes are externally fitted, and the through holes of the protrusion (21A) are externally fitted onto the lower pin. (3'7) is a height adjustment jack disposed on the inclined end surface (10A) of the working chamber αQ, and (c) is an alignment jack disposed on the inclined side surface (IOB) of the working chamber 0Q. Note that an automatic welding device (not shown) is installed in the work room αQ. In FIG. 10, the spit is a mortar filling nozzle formed in each single pipe (41-42+45...), and the tile is a mortar supply pipe connected to the nozzle (to).
上記構成に基づいて鉄管(4)の据付手順を説明する。The installation procedure of the iron pipe (4) will be explained based on the above configuration.
まずテーパ管α力を載せた搬入台車(2)を下部坑道α
υを通って作業室Q(l前までもたらし、次に第11図
に示すととくチェンブロック(41)でテーパ管(1功
を吊上げ、第12図に示すごとくそのテーパ管(14)
をジヤツキ(3η(381に受け渡す。次に下方ピン(
34)を抜取り、油圧シリンダ(至)のピストンロッド
を伸長させ、押上枠c21)を矢印(2)方向へ移動さ
せる。次に下方ピン04]をピン穴(ホ)および貫通穴
(刻に挿入して押上枠+21)を支柱o傷に固定し、次
に上方ピン(33)を抜いて油圧シリンダ(7)のピス
トンロッドを縮小させ、次KJx方ピン關をピン穴(イ
)および貫通穴□□□に挿入してピストンロッドを支柱
o1に連結する。かかる運動をくシ返すことにより、押
上枠&1)をいわゆる尺取虫のようにして矢印開方向へ
移動させ、第13図のように押上枠c2])を突条翰に
対向させる。次にハンドル(イ)を回して各押えブロッ
クに)を矢印(D)方向へ移動させてテーパ管αaに押
付けると共に溝(イ)を突条(ハ)に嵌合させる。次に
前記と逆の動作により押上枠Rを矢印色)方向へ移動さ
せる。次に前記と同じようにして下方坑道Ql)から作
業室aQ内に第1単管(4,)を入れ、ジヤツキ(3η
(至)に受け渡す。次に第14図に示すととく調心ジヤ
ツキ酩を作動させて第1単管(4,)をテーパ管α4に
対し同心状にし、高さ調整ジヤツキe171により第1
単管(41)を持上げてその上端をテーパ管α→の下端
に当接させる。次に自動溶接装置によりテーパ管0→と
第1単管(4,)との当接部を溶接する。次にへンドル
翰を逆口伝させて各ブロック′に)をテーパ管α力から
離間させる。次に押上枠eηを矢印開方向へ移動させ、
各ブロック(ハ)を第1車管(4,)に当接させると共
に溝(転)を突条(ホ)に嵌合させる。次に押上枠C2
1)を矢印(B1方向へ移動させて第15図に示すごと
くテーパ管α力を斜坑(1)内に挿入し、該斜坑(1)
の下端とテーパ管α→との間の空間142を仕切板旧に
より仕切り、上記空間(ハ)内に作業室αQまたは斜坑
(1)の上部からのばしたコンクリート打設管(441
よりコンクリート(蛾を打設する。First, the transport cart (2) carrying the tapered pipe α force is transported to the lower tunnel α.
υ to the front of the working chamber Q (1), then lift the tapered pipe (1) with the special chain block (41) shown in Fig. 11, and lift the tapered pipe (14) as shown in Fig. 12.
Pass it to Jyatsuki (3η (381). Next, press the lower pin (
34), the piston rod of the hydraulic cylinder (to) is extended, and the push-up frame c21) is moved in the direction of arrow (2). Next, fix the lower pin 04] in the pin hole (E) and the through hole (push-up frame +21 by inserting it into the slot), then remove the upper pin (33) and fix the piston of the hydraulic cylinder (7). Reduce the rod, and then insert the KJx pin into the pin hole (a) and the through hole □□□ to connect the piston rod to the support column o1. By reversing this movement, the push-up frame &1) is moved in the direction of the arrow opening like a so-called inchworm, and the push-up frame c2]) is opposed to the protrusion as shown in FIG. Next, turn the handle (A) to move each presser block in the direction of the arrow (D) to press it against the tapered pipe αa, and to fit the groove (A) into the protrusion (C). Next, the push-up frame R is moved in the direction of the arrow (color) by an operation opposite to that described above. Next, in the same manner as above, put the first single pipe (4,) from the lower tunnel Ql) into the working chamber aQ, and jack it (3η
(to) hand over. Next, as shown in FIG. 14, the alignment jack is operated to make the first single pipe (4,) concentric with the tapered pipe α4, and the height adjustment jack e171 is used to make the first single pipe (4,) concentric with the tapered pipe α4.
Lift the single pipe (41) and bring its upper end into contact with the lower end of the tapered pipe α→. Next, an automatic welding device welds the contact portion between the tapered pipe 0→ and the first single pipe (4,). Next, the Hendl wire is passed backwards to each block') to separate it from the tapered tube α force. Next, move the push-up frame eη in the arrow opening direction,
Each block (C) is brought into contact with the first wheel pipe (4,), and the groove (roller) is fitted into the protrusion (E). Next, push up frame C2
1) in the direction of arrow B1 and insert the tapered tube α force into the inclined shaft (1) as shown in FIG.
A space 142 between the lower end of the pipe and the tapered pipe α→ is partitioned by a partition plate old, and a concrete pouring pipe (441
More concrete (place concrete).
次に第2単管(42)を上記と同じようにして第1単管
(4,)に溶接し、テーパ管α4および第1、第2の単
管(4,)(4□)を押上げ、空間t42内にコンクリ
ート(4(へ)を打設する。以上の動作をくり返すこと
により斜坑(1)内に鉄管(4)を配設し、次にコンク
リート(4均と鉄管性)との間の間隙ケ6)内に各ノズ
ル139)からモルタルを充填すれば据付作業が完了す
る。なおテーパ管a4の作用により各単管(4,’42
.45・・・)とコンクIJ −) (載との間に間隙
側が生じるから、押上げの際の摩擦抵抗をきわめて小さ
くすることができるものである。Next, weld the second single pipe (42) to the first single pipe (4,) in the same manner as above, and press the tapered pipe α4 and the first and second single pipes (4,) (4□). concrete (4) in the space t42. By repeating the above operations, the iron pipe (4) is placed in the inclined shaft (1), and then the concrete (4 uniform and iron pipe) is placed in the inclined shaft (1). The installation work is completed by filling mortar into the gap 6) from each nozzle 139). In addition, due to the action of tapered pipe a4, each single pipe (4, '42
.. 45...) and the concrete IJ-) (Since a gap is created between the conc.
以上述べたごとく本発明によれば次のような効果を得る
ことができる。As described above, according to the present invention, the following effects can be obtained.
(力 単管を既に押し上げたテーパ管または単管の下端
へ接合する作業と並行して、斜坑内でコンクリートを打
設することができるため、作業能率がよい。(Power) Concrete can be placed in the inclined shaft in parallel with the work of joining the single pipe to the lower end of the tapered pipe or single pipe that has already been pushed up, improving work efficiency.
(イ) いつも同じ作業室でテーパ管および単管の接合
ができるので、作業室に自動溶接機を設置しても、その
取扱いが極めて容易となり、溶接品質の向上を期待でき
る。(b) Since tapered pipes and single pipes can always be joined in the same work room, even if an automatic welding machine is installed in the work room, it will be extremely easy to handle, and we can expect an improvement in welding quality.
(つ) 作業室の作業空間を十分俯保でき、足場も安定
しており、作業者が墜落することもなく、安全性が向上
する。(1) The work space in the work room can be sufficiently overlooked, the footing is stable, and workers will not fall, improving safety.
に) 下部坑道の内径を据付けるテーパ管および−単管
の外径より少し大きくするだけで尼りるので、坑道掘削
の費用も少なくてすむ。(b) Since the inner diameter of the lower shaft only needs to be made slightly larger than the outer diameter of the tapered pipe and single pipe to be installed, the cost of tunnel excavation can be reduced.
(3) 作業者が作業室へ行くのに容易である。(3) It is easy for workers to get to the work room.
(力) 作、業室への機材や資材の搬入が容易である。(Power) It is easy to work and transport equipment and materials to the work room.
(ギ 作業室の換気も、場所が一定であるため容易でお
る。したがって環境衛生上も好ましい。(G) Ventilation of the work room is also easy because the location is fixed. Therefore, it is also favorable from the viewpoint of environmental hygiene.
すなわち本発明の工法を実施すると、従来の工法に比べ
、作業能率、溶接品質、安全性、作業環境、経済性とも
に向上する効果がある。That is, when the construction method of the present invention is implemented, it has the effect of improving work efficiency, welding quality, safety, work environment, and economic efficiency compared to conventional construction methods.
第1図は従来例を示す縦断面図、第2図以下の図は本発
明の一実施例を示すものであって、第2図は縦断面図、
第3図は作業室の縦断面図、第4図は要部の縦断面図、
第5図は第3図のv−■矢視図、第6図は第3図の■−
VI矢視図、第7図は第6図のvト■矢視図、第8図は
テーパ管部分の縦断面図、第9図は第2図のIK4矢視
図、第10図はモルタル充填ノズル部分の縦断面図、第
11図〜第15図は鉄管据付手順を示す縦断面図でおる
。
(1)・・・斜坑、(4)・・・鉄管、(44,42,
4,・・・)・・・単管、αQ・・・作業室、圓・−・
テーパ管、四・・・支柱、φB・・・押上枠(ジヤツキ
アップ設備)、翰・・・押えプロ・ツク、…・・・油圧
シリンダ、m311341・・・ピン、おη・・・高さ
68整ジヤツキ、歪・・・調心ジヤツキ、(徹・・・コ
ンクリート代理人 森 本 義 弘
第3図
第1θ図
4t、4z、43−FIG. 1 is a longitudinal cross-sectional view showing a conventional example, FIG. 2 and the following figures show an embodiment of the present invention.
Figure 3 is a longitudinal sectional view of the working room, Figure 4 is a longitudinal sectional view of the main parts,
Figure 5 is a view from the v-■ arrow in Figure 3, and Figure 6 is a view from ■- in Figure 3.
VI arrow view, Fig. 7 is a view from V to ■ arrow in Fig. 6, Fig. 8 is a vertical sectional view of the tapered pipe portion, Fig. 9 is a view from IK4 arrow in Fig. 2, and Fig. 10 is a mortar view. The longitudinal sectional views of the filling nozzle portion, and FIGS. 11 to 15, are longitudinal sectional views showing the iron pipe installation procedure. (1)... Inclined shaft, (4)... Iron pipe, (44, 42,
4,...)...Single tube, αQ...Working chamber, Round...
Tapered pipe, 4... Support, φB... Push-up frame (jack-up equipment), Han... Presser foot pro-tsuku,... Hydraulic cylinder, m311341... Pin, η... Height 68 Adjustment jack, distortion... Alignment jack, (Toru...Concrete agent Yoshihiro Morimoto Fig. 3 Fig. 1θ Fig. 4t, 4z, 43-
Claims (1)
ツキアップ設備を配設し、下部坑道から作業室内に上端
頭部が下端より大径のテーパ管を搬入し、該テーパ管を
ジヤツキアップ設備により押上げ、下部坑道から作業室
内に第1単管を搬入すると共にその上端をテーパ管の下
端に接合し、次にジヤツキアップ設備により第1単管を
押上げてテーパ管を斜坑内に挿入し、テーパ管と斜坑内
面との間にコンクリートを打設し、次に作業室内に第2
単管を搬入すると共にその上端を第1単管の下端に接合
し、次にジヤツキアップ設備によ9第2単管を押上げ、
テーパ管と斜坑内面との間にコンクリートを打設し、同
様にして第3以下の各単管を順次作業室内に搬入すると
共に単管どうしを接合かつジヤツキアップ設備により押
上げて斜坑内に水圧鉄管を配設し、その水圧鉄管と既設
コンクリートとの間にモルタルを充填することを特徴と
するジヤツキアップによる水圧鉄管据付工法。1. Form a working chamber at the lower end of the inclined shaft, install jacking equipment in the working chamber, bring a tapered pipe whose upper head has a larger diameter than the lower end from the lower tunnel into the working chamber, and jack up the tapered pipe. The first single pipe is pushed up by equipment and carried into the work chamber from the lower tunnel, and its upper end is joined to the lower end of the tapered pipe. Next, the first single pipe is pushed up by jack-up equipment and the tapered pipe is inserted into the inclined shaft. Then, concrete was poured between the tapered pipe and the inner surface of the inclined shaft, and then a second
The single pipe is brought in, its upper end is joined to the lower end of the first single pipe, and then the jack-up equipment is used to push up the second single pipe,
Concrete is placed between the tapered pipe and the inner surface of the inclined shaft, and in the same manner, each of the third and subsequent single pipes is sequentially carried into the work room, and the single pipes are joined together and pushed up using jack-up equipment to form the penstock into the inclined shaft. A penstock installation method using jack-up, which is characterized by installing a penstock and filling mortar between the penstock and the existing concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP58113901A JPS605906A (en) | 1983-06-23 | 1983-06-23 | Installation work of penstock by jack-up process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP58113901A JPS605906A (en) | 1983-06-23 | 1983-06-23 | Installation work of penstock by jack-up process |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS605906A true JPS605906A (en) | 1985-01-12 |
JPS6328170B2 JPS6328170B2 (en) | 1988-06-07 |
Family
ID=14623994
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP58113901A Granted JPS605906A (en) | 1983-06-23 | 1983-06-23 | Installation work of penstock by jack-up process |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS605906A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160097279A1 (en) * | 2013-05-14 | 2016-04-07 | Minrail Inc. | Mining site having a shallow angle extraction shaft, shallow angle mining method and method for constructing a penstock |
-
1983
- 1983-06-23 JP JP58113901A patent/JPS605906A/en active Granted
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160097279A1 (en) * | 2013-05-14 | 2016-04-07 | Minrail Inc. | Mining site having a shallow angle extraction shaft, shallow angle mining method and method for constructing a penstock |
US10196072B2 (en) * | 2013-05-14 | 2019-02-05 | Minrail Inc. | Mining site having a shallow angle extraction shaft, shallow angle mining method and method for constructing a penstock |
US10486717B2 (en) * | 2013-05-14 | 2019-11-26 | Minrail Inc. | Hydro-electric site and method for constructing a penstock |
Also Published As
Publication number | Publication date |
---|---|
JPS6328170B2 (en) | 1988-06-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113323011B (en) | Novel underpinning construction method for steel pipe under existing building foundation | |
JP4317322B2 (en) | Arch support structure | |
JPS605906A (en) | Installation work of penstock by jack-up process | |
CN209923941U (en) | Building foundation pit supporting device | |
CN204960309U (en) | Fixed adjustable cast -in -place stair template is propped up to establish and is used cushion braced system | |
JP2013130001A (en) | Pipe body support device | |
JP4113007B2 (en) | Widening method of existing tunnel | |
KR101335796B1 (en) | Apparatus for supporting form of underground building and method of constructing the underground building using the same | |
JP6387778B2 (en) | Suspension jig used when building the core material of the underground continuous wall, the method of building the core material of the underground continuous wall, and the system for building the core material of the underground continuous wall | |
CN214695638U (en) | Novel water-washed pore-forming shaped steel underground structure supporting device | |
KR101662096B1 (en) | The Construction Method of Non-excavation tunnel what press in extruding Steel pipe by Arch type Precast Upperslab | |
US4050255A (en) | Methods of shifting heavy and/or loaded structures | |
CN211472401U (en) | Dam panel pours with trolley-bus slipform structure | |
CN210369047U (en) | Portable movable template support | |
CN215211038U (en) | Plain type concrete dado pours auxiliary device | |
JPS605907A (en) | Installation work of penstock by jack-up process | |
CN211817901U (en) | Overhanging type scaffold fixing device | |
CN111979991A (en) | Special large-gradient sliding form device with arc lining bottom plate and construction method | |
CN213297036U (en) | Construction mechanism with foldable vertical rail type putty scraping function | |
CN220979545U (en) | Auxiliary centering and grouting device for anchor rod | |
CN210086776U (en) | Telescopic movable scaffold | |
CN220433662U (en) | Operating device with pile head overspray mould | |
CN218027820U (en) | Be used for deep basal pit reverse construction method construction structures | |
CN216342129U (en) | Connecting channel pipe jacking construction system | |
CN209923735U (en) | Quick strutting arrangement of concrete road side mould |