JPS6042121Y2 - Piles for constructing underwater structures - Google Patents

Piles for constructing underwater structures

Info

Publication number
JPS6042121Y2
JPS6042121Y2 JP12543682U JP12543682U JPS6042121Y2 JP S6042121 Y2 JPS6042121 Y2 JP S6042121Y2 JP 12543682 U JP12543682 U JP 12543682U JP 12543682 U JP12543682 U JP 12543682U JP S6042121 Y2 JPS6042121 Y2 JP S6042121Y2
Authority
JP
Japan
Prior art keywords
pile
bottom plate
piles
steel
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP12543682U
Other languages
Japanese (ja)
Other versions
JPS5931648U (en
Inventor
建治 石倉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP12543682U priority Critical patent/JPS6042121Y2/en
Publication of JPS5931648U publication Critical patent/JPS5931648U/en
Application granted granted Critical
Publication of JPS6042121Y2 publication Critical patent/JPS6042121Y2/en
Expired legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

【考案の詳細な説明】 河川、港湾等の水中構造物構築用杭に関する。[Detailed explanation of the idea] Concerning piles for constructing underwater structures such as rivers and ports.

構造用H鋼杭は幾多の利点を有しながら水中構造物の構
築用材として使用される場合は、H鋼杭の表面積が大き
いために腐食損耗を大きく、これを十分に防止する方策
をとらなければ使用不能となる場合もある。
Although structural H-steel piles have many advantages, when they are used as construction materials for underwater structures, the large surface area of H-steel piles causes significant corrosion and wear, and measures must be taken to sufficiently prevent this. In some cases, it may become unusable.

これに対し電気防食等の防食法もあるが、直接外海に面
するような波浪の荒いところでは効率が低下し、高価で
ある。
Corrosion prevention methods such as cathodic protection are available, but they are less efficient and expensive in areas with rough waves, such as those directly facing the open sea.

本考案は以上の欠点を簡単に除去するもので、これを実
施例によって説明する。
The present invention simply eliminates the above drawbacks and will be explained by way of examples.

第1図は本考案の杭を上からみた平面図で、第2図は第
1図の側面図である。
FIG. 1 is a top plan view of the pile of the present invention, and FIG. 2 is a side view of FIG. 1.

1はH鋼杭、2はH鋼杭のフランジと腹板によって形威
されるコ部に丁度嵌合するように平鉄を溶接した底板で
、底板の一部には小孔3を設けである。
1 is an H steel pile, 2 is a bottom plate made of flat iron welded to fit exactly into the shape formed by the flange and belly plate of the H steel pile, and a small hole 3 is provided in a part of the bottom plate. .

4は底板の端部とH鋼のフランジ端部に溶接した平鉄で
側板である。
4 is a side plate made of flat iron welded to the end of the bottom plate and the flange end of the H steel.

かくてH鋼杭の1のフランジ、腹板、および底板2、側
板4によって筒形の囲い(以下単に1筒ヨと称する)5
が形威される。
Thus, a cylindrical enclosure (hereinafter simply referred to as a cylindrical enclosure) 5 is formed by the flange 1, belly plate, bottom plate 2, and side plates 4 of the H steel pile.
is expressed.

本考案の杭1を水底地盤上に設立したとき、第2図のよ
うに底板2は満潮時には水中にあり、従って筒5の内部
には水が入っている。
When the pile 1 of the present invention is installed on underwater ground, the bottom plate 2 is underwater at high tide, as shown in FIG. 2, and therefore the inside of the tube 5 is filled with water.

しかし本考案では底板2の一部に小孔3を設けであるか
ら、筒5の中にコンクリートを静かに流し込めば、筒5
の中の水は小孔3から流出し、コンクリートの充填の進
行とともに小孔3は自然に閉塞してしまう。
However, in the present invention, since the small hole 3 is provided in a part of the bottom plate 2, if concrete is poured into the cylinder 5 gently, the cylinder 5
The water inside flows out from the small hole 3, and the small hole 3 naturally closes as filling with concrete progresses.

小孔3がなければ干潮時に底板2が水上に出ても筒5の
中には水が入ったままでコンクリートの充填に支障をき
たす。
Without the small holes 3, even if the bottom plate 2 rises above the water at low tide, water will remain in the tube 5, which will hinder the filling of concrete.

本考案では小孔3があるために、干潮時に底板2が水上
に出る場合は筒5の中の水は自然に流出する。
In the present invention, since there is a small hole 3, when the bottom plate 2 comes out on the water at low tide, the water in the tube 5 naturally flows out.

このように底板2が水上にあるときは勿論、水中にある
ときでも筒5の中の水は容易に外に排出されるから、筒
5の中にはコンクリートを容易に充填できる。
In this way, the water in the tube 5 can be easily drained out not only when the bottom plate 2 is above water but also when it is underwater, so that the tube 5 can be easily filled with concrete.

従ってH鋼杭1は水底地盤上に設立されたときに最も腐
食のはげしい乾湿を繰返す部分のH鋼杭の内側の表面を
完全にコンクリートで被覆することができる。
Therefore, when the H-steel pile 1 is installed on underwater ground, the inner surface of the H-steel pile, which is exposed to repeated wet and dry conditions where corrosion is most severe, can be completely covered with concrete.

第3図は通常のH鋼杭を使用して構築された防波構造物
の一実施例の断面図である。
FIG. 3 is a cross-sectional view of one embodiment of a wave-break structure constructed using ordinary H-steel piles.

通常のH鋼杭1′を適当な間隔をもって水底地盤上に設
立し、杭の頭部を複数の横桟6をもって連結して角筒状
の囲いを形威し、その囲いの内部に上記各杭の間隙から
脱出しない程度の大きさの石またはコンクリートブロッ
ク等の消波材7を充填し、杭の頭部を場所打コンクリー
ト8をもって強固に連結してなるものである。
Ordinary H-steel piles 1' are installed on the underwater ground at appropriate intervals, and the heads of the piles are connected with a plurality of horizontal bars 6 to form a rectangular cylindrical enclosure. A wave-dampening material 7 such as a stone or a concrete block is filled with a size that does not escape from the gap between the piles, and the head of the pile is firmly connected with cast-in-place concrete 8.

この際、杭の頭部には最も大きなモーメントが発生する
が、満潮面10附近以上の干潟を繰返す部分は腐食も一
番大きく、港湾等の設計基準によれば、腐食率は満潮面
以上を0.3m/年、満潮面と干潮面の間を0.1mm
/年としている。
At this time, the largest moment is generated at the head of the pile, but the corrosion is greatest in the part that repeats tidal flats above the high tide level.According to the design standards for ports, etc., the corrosion rate is higher than the high tide level. 0.3m/year, 0.1mm between high tide and low tide
/ year.

それゆえ満潮面以上では例えば3咋間では約911rI
IL1満潮面と干潮面の間でも約31rrIILも腐食
により損耗することとなる。
Therefore, above the high tide level, for example, for a distance of 3 cm, it is approximately 911 rI.
Approximately 31rr of IL1 will be lost due to corrosion between the high tide and low tide levels of IL1.

従って満潮面以上ではH鋼杭は構造上膜も重要なフラン
ジが両側から97rrIItづつ計18rIrIItも
損耗し、原形の残るところがほんの僅かとなり、杭頭部
のモーメントに耐えることができない。
Therefore, above the high tide level, the flanges of H-steel piles, which are structurally important, wear out 97rrIIt on each side, a total of 18rIrIIt, leaving only a small portion of the original shape, unable to withstand the moment of the pile head.

そこで第3図のように満潮面10附近、または満潮面1
0と干潮面9の間の適当な位置から上のH鋼杭をコンク
リート8で被覆する必要があった。
Therefore, as shown in Figure 3, the area is around high tide level 10 or high tide level 1.
It was necessary to cover the upper H steel pile with concrete 8 from an appropriate position between 0 and low tide level 9.

これは構造上欠くことのできない絶対条件であった。This was an absolute structural requirement.

ところがH鋼杭を被覆するためには、まづH鋼杭の周辺
に底板をとりつけなければならず、そのとりつけか所が
波浪の影響を受は易いところであるために作業が極めて
困難であった。
However, in order to cover the H-steel pile, it was first necessary to attach a bottom plate around the H-steel pile, and this work was extremely difficult because the installation location was easily affected by waves. .

また干潮差の大きいところでは場所打コンクリート8の
下面以下の干潟を繰返す部分ではH鋼杭は全面に亘って
0.1mm/年づつ腐食が進行するのでH鋼杭の全断面
ではその損耗は非常に大きい。
In addition, in areas with large tidal differences, corrosion of H steel piles progresses over the entire surface at a rate of 0.1 mm/year in areas that repeat tidal flats below the bottom surface of cast-in-place concrete 8, so the wear and tear on the entire cross section of H steel piles is extremely high. big.

なお場所打コンクリート8はその作業が極めて困難であ
るのも拘らず、H鋼杭の腐食上できるだけ下にさける必
要があり、そうすると場所打コンクリート8の高さaが
大きくなり、波力はaに全面的に作用するから、外力の
影響が非常に大きくなる。
Although the cast-in-place concrete 8 is extremely difficult to work with, it is necessary to avoid it as low as possible due to the corrosion of the H-steel piles, so the height a of the cast-in-place concrete 8 increases, and the wave force increases to a. Since it acts on the entire surface, the influence of external forces becomes very large.

従って応力が大きくなって、杭の断面も大きくしなけれ
ばならないという欠点があった。
Therefore, there was a drawback that the stress increased and the cross section of the pile also had to be made larger.

これに対し、第4図は本考案のH鋼杭による防波構造物
の一実施例であるが、筒5の底板2は干潮面以下とし、
筒5内のコンクリートは水中コンクリートとしているが
この場合はH鋼杭の損耗が腹板については皆無であり、
フランジについても片面だけであるから、第3図のよう
な従来のものに比し腐食損耗は172以下に減じ、全体
としてH鋼杭の損耗は非常に小さくなる。
On the other hand, FIG. 4 shows an example of a wave-break structure using H steel piles of the present invention, in which the bottom plate 2 of the cylinder 5 is below the low tide level,
The concrete inside tube 5 is underwater concrete, but in this case there is no wear on the H steel piles and no damage to the bottom plate.
Since the flange is also only on one side, the corrosion wear is reduced to 172 or less compared to the conventional one as shown in Fig. 3, and the wear of the H steel pile as a whole is extremely small.

そのため杭頭部の場所打コンクリート8は満潮面附近よ
り上の位置からでも十分である。
Therefore, it is sufficient to cast in place concrete 8 at the pile head from a position above the high tide level.

それゆえ場所打コンクリート8の高さbは第3図の従来
の構造によるaに比し小さくなるから波力の作用する面
が少なくなり、応力上非常に有利になるばかりでなく、
場所打コンクリート打設そのものが容易で、コンクリー
ト量も少なく、全体として施工が容易で工費が大いに軽
減できるようになった。
Therefore, the height b of the cast-in-place concrete 8 is smaller than the height a of the conventional structure shown in FIG.
Cast-in-place concrete placement itself is easy, the amount of concrete is small, and overall construction is easy and construction costs can be greatly reduced.

【図面の簡単な説明】[Brief explanation of drawings]

第1図・・・・・・H鋼杭の平面図、第2図・・・・・
・側面図、第3図・・・・・・従来の防波構造物の断面
図、第4図・・・・・・本考案のH鋼杭を使用した防波
構造物の断面図。 1.1′・・・・・・杭、2・・・・・・底板、3・・
・・・・小孔、4・・・・・・側板、5・・・・・・筒
形の囲い、6・・・・・・横桟、7・・・・・・消波材
、訃・・・・・場所打コンクリート。
Figure 1... Plan view of H steel pile, Figure 2...
・Side view, Fig. 3...A sectional view of a conventional wave-break structure, Fig. 4...A sectional view of a wave-break structure using the H steel pile of the present invention. 1.1'...Pile, 2...Bottom plate, 3...
... Small hole, 4 ... Side plate, 5 ... Cylindrical enclosure, 6 ... Horizontal bar, 7 ... Wave-dissipating material, tail ...Cast-in-place concrete.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 水底地盤上に設立されるH鋼杭の設立後における該杭の
乾湿を繰返す水面附近のH鋼杭のコ部に平鉄を溶接して
底板2とし、かつ底板の一部に小孔を設け、さらに底板
とH鋼杭のフランジ端部に平鉄を溶接して筒状の囲いを
形威し、この囲いの内部にコンクリートを充填してなる
水中構造物構築用杭。
A flat iron is welded to the bottom plate 2 of the H steel pile near the water surface where the pile is repeatedly dried and moistened after it is installed on the underwater ground, and a small hole is provided in a part of the bottom plate. A pile for constructing an underwater structure is made by welding flat iron to the bottom plate and the flange end of the H steel pile to form a cylindrical enclosure, and filling the inside of this enclosure with concrete.
JP12543682U 1982-08-19 1982-08-19 Piles for constructing underwater structures Expired JPS6042121Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12543682U JPS6042121Y2 (en) 1982-08-19 1982-08-19 Piles for constructing underwater structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12543682U JPS6042121Y2 (en) 1982-08-19 1982-08-19 Piles for constructing underwater structures

Publications (2)

Publication Number Publication Date
JPS5931648U JPS5931648U (en) 1984-02-27
JPS6042121Y2 true JPS6042121Y2 (en) 1985-12-23

Family

ID=30285582

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12543682U Expired JPS6042121Y2 (en) 1982-08-19 1982-08-19 Piles for constructing underwater structures

Country Status (1)

Country Link
JP (1) JPS6042121Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0791002B2 (en) * 1988-07-23 1995-10-04 株式会社日立ビルシステムサービス High speed elevator governor test equipment

Also Published As

Publication number Publication date
JPS5931648U (en) 1984-02-27

Similar Documents

Publication Publication Date Title
US4856935A (en) Beachfront wave energy dissipation structure
US20040076477A1 (en) Underwater building unit and methods of installation and application thereof
US2662378A (en) Art of shore protection
JPS6042121Y2 (en) Piles for constructing underwater structures
US952645A (en) Reinforced-concrete sectional sea-wall.
JPS6138977Y2 (en)
JPS5925944Y2 (en) floating wave bank
JP3619951B2 (en) Wave-dissipating structure with composite main pile for wave-dissipating structure
SU433272A1 (en) ISLAND ICE-RESISTANT KNIFE FOR DRILLING ON THE SEAS
JP2002302924A (en) Assembly type revetment structural body
RU2040632C1 (en) Enclosure
JPH0526094Y2 (en)
JPS6130093B2 (en)
JPS605075Y2 (en) Ship mooring bridge
JPS62233318A (en) Concrete sink frame
SU1687709A1 (en) Sea dike, assy
JPH076175B2 (en) Breakwater structure
JPH0724412Y2 (en) Floating body of a breakwater
JPS6268926A (en) Construction for underwater reinforced concrete
JPH0234248Y2 (en)
JP3808552B2 (en) Form for constructing underwater caisson, underwater caisson and construction method thereof
JPS5850205A (en) Curtain wall type brakewater
JPH01275805A (en) Connection caisson
CA1277842C (en) Beachfront wave energy dissipation structure
SU943374A1 (en) Shore-protecting structure