JPS60219397A - Blade shield drilling machine - Google Patents
Blade shield drilling machineInfo
- Publication number
- JPS60219397A JPS60219397A JP59075785A JP7578584A JPS60219397A JP S60219397 A JPS60219397 A JP S60219397A JP 59075785 A JP59075785 A JP 59075785A JP 7578584 A JP7578584 A JP 7578584A JP S60219397 A JPS60219397 A JP S60219397A
- Authority
- JP
- Japan
- Prior art keywords
- blade
- formwork
- concrete
- blade shield
- jack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000005553 drilling Methods 0.000 title 1
- 238000009415 formwork Methods 0.000 claims description 46
- 230000005641 tunneling Effects 0.000 claims description 4
- 238000009412 basement excavation Methods 0.000 description 11
- 238000010276 construction Methods 0.000 description 7
- 238000000034 method Methods 0.000 description 5
- 239000000463 material Substances 0.000 description 3
- 239000002689 soil Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- NMFHJNAPXOMSRX-PUPDPRJKSA-N [(1r)-3-(3,4-dimethoxyphenyl)-1-[3-(2-morpholin-4-ylethoxy)phenyl]propyl] (2s)-1-[(2s)-2-(3,4,5-trimethoxyphenyl)butanoyl]piperidine-2-carboxylate Chemical compound C([C@@H](OC(=O)[C@@H]1CCCCN1C(=O)[C@@H](CC)C=1C=C(OC)C(OC)=C(OC)C=1)C=1C=C(OCCN2CCOCC2)C=CC=1)CC1=CC=C(OC)C(OC)=C1 NMFHJNAPXOMSRX-PUPDPRJKSA-N 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000009413 insulation Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】 本発明はブレードシールド掘進機に関するものである。[Detailed description of the invention] The present invention relates to a blade shield tunneling machine.
トンネル施工法の一種でメツセル工法とシールド工法の
両者の特徴を兼備えたブレードシールド工法が存在する
。There is a blade shield method, which is a type of tunnel construction method and has the characteristics of both the Metsu cell method and the shield method.
すなわちこの工法はブレードと言う矢板をトンネルの外
周に配置し、このブレードを支えるサポーテイングフレ
ームとブレードを前進させる油圧ジヤツキとから成り、
前進の推力を後方のセグメント、あるいは鋼製支保工に
とるシールド掘進機と異なり、掘進機の周辺の地山とブ
レードとの摩擦力を利用して自走するブレードシールド
掘進機が使用されている。In other words, this method consists of placing sheet piles called blades around the outer circumference of the tunnel, a supporting frame that supports the blades, and a hydraulic jack that moves the blades forward.
Unlike a shield excavator, which uses the forward thrust from the rear segment or steel shoring, a blade shield excavator is used, which uses the frictional force between the blade and the ground around the excavator to propel itself. .
ところで上記従来のブレードシールド掘進機を使用する
と、掘削後、コンクリートを打設するために掘進作業か
ら独立して型枠の組み立て、脱型、そして掘進に合せて
型枠を移動しなければならない。By the way, when the conventional blade shield excavator is used, after excavation, the formwork must be assembled and demolded independently of the excavation work in order to place concrete, and the formwork must be moved in conjunction with the excavation.
これらの資材は掘進機に装備されてはおらず、公知の資
材を使用して行なわれていた。These materials were not equipped on the excavator, and the work was carried out using publicly known materials.
従ってコンクリート覆工に多くの手数を要し全体の施工
効率が低いという問題があった。Therefore, there was a problem that the concrete lining required a lot of work and the overall construction efficiency was low.
本発明はこのような問題を解決するためになされたもの
で、型枠の着脱および移動をスムーズに行ってコンクリ
ートの打設効率が向上し、かつ、掘進と同時にコンクリ
ートの打設覆工が可能なブレードシールド掘進機を提供
する事を目的とする。The present invention was developed to solve these problems, and it improves concrete placement efficiency by smoothly attaching and detaching formwork and moving it, and also enables concrete placement and lining at the same time as excavation. The purpose is to provide a blade shield excavator that is suitable for
次に本発明の実施例を図面に基すき説明する。Next, embodiments of the present invention will be explained based on the drawings.
[イコ全体の構成
第1図において1はオープン式のブレードシールドであ
り、U字形のサポーテイングフレーム3の側面にはフロ
ントブレード2とテールブレード21に二分割してブレ
ード間をビンでジヨイントした側壁側のブレードを配置
し、フロント部の底面にはボトムブレード22を配置す
る。[Overall structure of Iko In Fig. 1, 1 is an open type blade shield, and on the side of the U-shaped supporting frame 3 there is a side wall that is divided into two parts, a front blade 2 and a tail blade 21, and a joint between the blades with a pin. The side blades are arranged, and the bottom blade 22 is arranged on the bottom surface of the front part.
さらに各フロントブレード2およびボトムブレード22
は油圧ジヤツキを介してサポーテイングフレーム3に接
続して進退自在に構成する。Furthermore, each front blade 2 and bottom blade 22
is connected to the supporting frame 3 via a hydraulic jack so that it can move forward and backward.
テールブレード21内にはボトムブレードは存在せず、
コンクリートを打設するための型枠装置5を装備する。There is no bottom blade in the tail blade 21,
It is equipped with a formwork device 5 for pouring concrete.
10]ブレード
ブレードは十分な断面係数を有する薄い板体を使用する
。10] Blade The blade uses a thin plate with a sufficient section modulus.
各ブレードには遠隔において選択的な進退操作が可能な
よう、フロントブレード2にはフロントジヤツキ23を
接続し、ボトムブレード22にはボトムジヤツキ24を
それぞれ接続し、各ジヤツキ23.24の自由端をサポ
ーテイングフレーム3に接続する。A front jack 23 is connected to the front blade 2, a bottom jack 24 is connected to the bottom blade 22, and the free end of each jack 23. Connect to supporting frame 3.
各ブレードは、土圧を支えながら選択的な推進力によっ
て土中に貫入して推進できるよう構成する。Each blade is configured to penetrate and propel itself into the soil with selective propulsion force while supporting earth pressure.
またテールブレード21はコンクリート打設時の外枠と
しての目的も併有する。The tail blade 21 also has the purpose of serving as an outer frame during concrete pouring.
フロントブレード2の内部には掘削機や廃土搬出装置、
運転室等(図示せず)を設ける。Inside the front blade 2, there is an excavator, waste soil removal device,
A driver's cab etc. (not shown) will be provided.
[ハ]型枠装置
テールブレード21内には第1図に示すように掘削溝の
横断方向にベース51を配置する。[C] A base 51 is placed in the tail blade 21 of the formwork device in the transverse direction of the excavated groove, as shown in FIG.
ベース51の両端部には溝方向に連通した空間を有する
係合部52を形成する。At both ends of the base 51, engaging portions 52 having spaces communicating in the groove direction are formed.
係合部52の空間内には第3図に示すように上大部およ
び下底部にそれぞれローラー53を取り付け、これらの
ローラー53を介してど一ム4を摺動自在に貫挿する。As shown in FIG. 3, rollers 53 are attached to the upper part and the lower bottom part of the space of the engaging part 52, respectively, and the sleeve 4 is slidably inserted through these rollers 53.
ビーム4は掘進機の進行方向に並行に配置し、その全長
は後述するように型枠6を前進させる関係から、型枠6
の溝方向の幅より長く形成し、さらに1スパン分だけの
スライドに制限するためビーム4の周面にストッパー4
1を突設する。The beam 4 is arranged parallel to the advancing direction of the excavator, and its total length is determined by the relationship between the formwork 6 and the formwork 6, which will be described later.
A stopper 4 is installed on the circumferential surface of the beam 4 to limit the slide to one span.
1 is installed protrudingly.
係合部52とブレードとの間には公知の素材からなる型
枠6を配置し、型枠6の下方を係合部52の下端にビン
等で軸支して取り付ける。A formwork 6 made of a known material is placed between the engagement part 52 and the blade, and the lower part of the formwork 6 is attached to the lower end of the engagement part 52 by supporting it pivotally with a pin or the like.
さらに型枠6の背面には、一端を係合部52に固定した
複数の型枠用ジヤツキ54の自由端を接続し、各型枠用
ジヤツキ54を同一方向に伸縮することによって型枠6
とブレード21との間隔を調整できるよう構成する。Further, the free ends of a plurality of formwork jacks 54, one end of which is fixed to the engaging portion 52, are connected to the back side of the formwork 6, and each formwork jack 54 is expanded and contracted in the same direction, so that the formwork
The configuration is such that the distance between the blade 21 and the blade 21 can be adjusted.
すなわち型枠用ジヤツキ54の伸縮によって軸支点を中
心として型枠6に開閉運動を行わせて型枠6のセットお
よびnG2型を行えるよう構成する。That is, the structure is such that the formwork 6 can be opened and closed about the pivot point by expanding and contracting the formwork jack 54, and the formwork 6 can be set and the nG2 mold can be formed.
型枠6はテールブレード21が外枠を形成するのに対し
て、内枠を形成する事を目的とする。The purpose of the formwork 6 is to form an inner frame while the tail blade 21 forms an outer frame.
ビーム4の両端には下方向に向けてサイドジヤツキ42
を取り付ける。At both ends of the beam 4, there are side jacks 42 facing downward.
Attach.
その結果すべてのサイドジヤツキ42を伸長すると型枠
装置5は四点で支持される事となる。As a result, when all the side jacks 42 are extended, the formwork device 5 will be supported at four points.
次に施工方法について説明する。Next, the construction method will be explained.
[イ]掘進
ブレードシールド1を溝内に設置した後、いずれかのジ
ヤツキ23を伸長すると伸長したフロントジヤツキ23
に接続するブレードが、伸長しない全てのブレードの摩
擦抵抗にょる反力を得て前方に押し出され、ブレード2
の先端が地山に貫入する。[A] After installing the digging blade shield 1 in the groove, when either jack 23 is extended, the extended front jack 23
The blade connected to blade 2 receives a reaction force due to the frictional resistance of all the blades that do not extend, and is pushed forward.
The tip penetrates into the ground.
ボトムブレード22も同様に地山に圧入し、掘削機で掘
削する。The bottom blade 22 is similarly press-fitted into the ground and excavated with an excavator.
このようにして全てのブレードを前進させた後、−各ブ
レードに接続する油圧ジヤツキを同時に収縮すると、す
べてのブレードの摩擦抵抗によってサポーテイングフレ
ーム3が切羽側にスライドする。After all the blades have been advanced in this manner, when the hydraulic jacks connected to each blade are simultaneously retracted, the supporting frame 3 slides toward the face side due to the frictional resistance of all the blades.
以上は従来の掘進方法と同様である。The above is the same as the conventional excavation method.
[ロコ型粋のセット(第4図)
まずビーム4の両端に設けICサイドジヤツキ42を伸
長して定位置に固定する。[Loco-style set (Figure 4) First, extend the IC side jacks 42 provided at both ends of the beam 4 and fix them in place.
このどき後方のジヤツキ42は硬化したコンクリートC
1上に、前方のジヤツキ42は掘進機上にセットする。Nowadays, the jack 42 in the back is hardened concrete C.
1, the front jack 42 is set on the excavator.
そして、収縮させた状態の型枠6を1スパンの4〕離だ
けビーム4上を滑動させて前進させる。Then, the formwork 6 in the contracted state is advanced by sliding on the beam 4 by a distance of 4] of one span.
型枠装置5はビーム4上に摺動自在に搭載しであるので
機械的な力によらなくとも人力で簡単に前進させる事が
できる。Since the formwork device 5 is slidably mounted on the beam 4, it can be easily moved forward by human power without using mechanical force.
型枠装置5を前進させたら、型枠用ジヤツキ54を伸長
して型枠6をコンクリート打設可能な状態にセットする
。When the formwork device 5 is advanced, the formwork jacks 54 are extended to set the formwork 6 in a state in which concrete can be poured.
「ハココンクリ−1〜の打設
型枠6をセットした後、ブレード21と型枠6の間の空
間前方に妻板61をセットし、ベースは検査窓より、側
壁は上部開口部よりコンクリートを打設する。After setting the pouring forms 6 for box concrete 1 to 1, set the gable board 61 in front of the space between the blade 21 and the formwork 6, and pour concrete for the base through the inspection window and for the side walls through the upper opening. do.
また、別途設けた注入口からコンクリートを打設する事
も可能である。It is also possible to pour concrete from a separately provided injection port.
[ニコ外型枠の脱型、掘進
コンクリートが十分な強度を得る以前に、型枠6はその
ままで、前記掘進と同様に順次フロントジヤツキ23を
伸長してフロントブレード2を前進させ、コンフート覆
工壁と外型枠との絶縁を図る。[Removal of the outer formwork and excavation Before the concrete has sufficient strength, the formwork 6 is left as it is, and the front jack 23 is sequentially extended and the front blade 2 is advanced in the same way as in the excavation described above, and the concrete is covered with concrete. Aim for insulation between the construction wall and the outer formwork.
ただし内型枠は十分な強度が得られるまで型枠6によっ
て支持し養生する。However, the inner formwork is supported and cured by the formwork 6 until sufficient strength is obtained.
こうしてコンクリートの養生期間中にも、工事を中断せ
ずに次の掘削の為に機体を前進させる事ができる。In this way, even during the concrete curing period, the machine can be moved forward for the next excavation without interrupting construction work.
そのときにはど−ム4のジヤツキ42は短縮して全重量
を球部分のコンクリートに加えておけば、ビーム4は機
体前進の障害とならない。At that time, if the jack 42 of the beam 4 is shortened and its entire weight is added to the concrete of the sphere, the beam 4 will not become an obstacle to the forward movement of the aircraft.
[ホ]ビーム、内型枠の前進(第5図)型枠6で支持す
るコンクリートが硬化したら型枠用ジヤツキ54を収縮
して型枠6をコンクリートC2から脱型する。[E] Advancement of the beam and inner formwork (Fig. 5) When the concrete supported by the formwork 6 hardens, the formwork jacks 54 are contracted to remove the formwork 6 from the concrete C2.
次に両端のジヤツキ42を短縮したビーム4を人力で掘
進方向に1スパンだけ前進させる。Next, the beam 4 with the jacks 42 at both ends shortened is manually advanced by one span in the excavation direction.
そしてジヤツキ42を伸長し、ビーム4に係合させて内
型枠である型枠6を前進させる。Then, the jack 42 is extended and engaged with the beam 4 to move the formwork 6, which is the inner formwork, forward.
[へ]その他の実施例
前記実施例はオープン式のブレードシールドの場合につ
いて説明したが、トンネル等を構築する場合は全周面に
スライド可能なブレードを配置し、かつ、その内部に前
記実施例と同様な収縮する型枠装置を内装してなるブレ
ードシールド掘進機を採用することができる。[F] Other Examples The above example describes the case of an open type blade shield, but when constructing a tunnel etc., a slidable blade is arranged on the entire circumference, and the above example is used inside the blade. A blade shield excavator equipped with a contracting formwork device similar to the above can be adopted.
従って、躯体の断面形状は本件の開梁に止どまらず画形
、馬蹄形、円形、アーチカルバート等自由に選択するこ
とが可能である。Therefore, the cross-sectional shape of the frame is not limited to the open beam of the present invention, but can be freely selected such as a picture shape, a horseshoe shape, a circle, an arch culvert, etc.
本発明は以上説明したようになるから次のような効果を
期待づる事ができる。Since the present invention is as explained above, the following effects can be expected.
くイ〉テールブレードが外枠として、型枠装置に装着す
る型枠が内枠として型枠が形成されるので、地山との接
触を避りてブレード内で直にコンクリートを打設できる
。Since the formwork is formed using the tail blade as the outer frame and the formwork attached to the formwork device as the inner frame, concrete can be placed directly within the blade avoiding contact with the ground.
従って従来のようなセグメントまたは支保工工事等の一
次覆■を不要とし、経済性に優れている。Therefore, there is no need for primary covering such as conventional segment or shoring work, making it highly economical.
〈口〉ブレード内に型枠装置を配置した。<Mouth> A formwork device was placed inside the blade.
従って開削と型枠の着脱およびコンクリート覆工の各作
業を1サイクルとして、何サイクルでも連続して行える
ので作業効率が向上する。Therefore, the work of excavation, attachment/detachment of formwork, and concrete lining can be performed as one cycle, and can be performed continuously for any number of cycles, thereby improving work efficiency.
〈ハ〉ジヤツキによって開削方向を横断する方向に開閉
するよう型枠を構成した型枠装置をブレード内に配置し
た。<C> A formwork device with a formwork configured to open and close in a direction transverse to the excavation direction by jacking was placed inside the blade.
そのため型枠のセットおよび脱型を容易に行うことがで
きる。Therefore, the mold can be easily set and demolded.
〈二〉機械操作は全て油圧式のワンマンコントロールが
可能である。(2) All mechanical operations can be controlled by one-man hydraulics.
〈ホ〉開削孔に応じて例えば円形、馬蹄形、方形等型枠
の断面形状を自由に選択できる。<E> The cross-sectional shape of the formwork can be freely selected, for example, circular, horseshoe-shaped, rectangular, etc., depending on the drilled hole.
くへ〉覆工コンクリ−1−と地山のボイドが少ないので
地山への影響も少ない。Kuhe〉There are few voids between the lining concrete and the ground, so there is little impact on the ground.
第1N:本発明の一実施例の説明図
第2図ニブレードシールド掘進機の側面図第3図:第1
図における■−■の断面同第4〜5図=iM工状態の説
明図
1ニブレードシールド 2:フロントブレード3:サポ
ーテイングフレーム 4:ビーム6:型枠 21:テー
ルブレード
出願人 トーメン建機販売株式会社No. 1N: Explanatory diagram of one embodiment of the present invention Fig. 2 Side view of Niblade shield tunneling machine Fig. 3: Fig. 1
Cross section of ■-■ in the figure Figures 4 and 5 = Explanation of iM construction status 1 Ni-blade shield 2: Front blade 3: Supporting frame 4: Beam 6: Formwork 21: Tail blade Applicant Tomen Construction Machinery Sales Co., Ltd.
Claims (1)
ドシールド掘進機において、 進行方向と並行にシールド掘進機内にビームを設置し、 ビーム両端には垂直ジヤツキを取り付け、断面形状を拡
大縮小できる型枠をビームに対して相互に滑動自在に係
合させた事を特徴とする、ブレードシールド掘進機。[Scope of Claims] In a blade shield tunneling machine that moves forward using frictional resistance from surrounding ground as a reaction force, a beam is installed inside the shield tunneling machine parallel to the direction of movement, vertical jacks are attached to both ends of the beam, and a cross-sectional A blade shield excavator characterized in that a formwork whose shape can be enlarged or reduced is slidably engaged with a beam.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP59075785A JPS60219397A (en) | 1984-04-17 | 1984-04-17 | Blade shield drilling machine |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP59075785A JPS60219397A (en) | 1984-04-17 | 1984-04-17 | Blade shield drilling machine |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS60219397A true JPS60219397A (en) | 1985-11-02 |
| JPH0332658B2 JPH0332658B2 (en) | 1991-05-14 |
Family
ID=13586211
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP59075785A Granted JPS60219397A (en) | 1984-04-17 | 1984-04-17 | Blade shield drilling machine |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS60219397A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH01268993A (en) * | 1988-04-19 | 1989-10-26 | Toomen Kenki Kk | Blade shield excavator |
-
1984
- 1984-04-17 JP JP59075785A patent/JPS60219397A/en active Granted
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH01268993A (en) * | 1988-04-19 | 1989-10-26 | Toomen Kenki Kk | Blade shield excavator |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH0332658B2 (en) | 1991-05-14 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPS60219397A (en) | Blade shield drilling machine | |
| KR20180070079A (en) | excavator using propulsion of assembled front tip | |
| JPS6137411B2 (en) | ||
| JPH0237480B2 (en) | ||
| US4875807A (en) | Method and means for basement construction | |
| JPH0574677B2 (en) | ||
| JPH0762436B2 (en) | Open shield method | |
| JPH11280373A (en) | Starting device and method for portal | |
| JPH0868293A (en) | Underground tunnel connection method and segment | |
| JPS60141995A (en) | Next excavation method in shield excavation and excavator for it | |
| JPH0357248B2 (en) | ||
| JP2002188392A (en) | Method of starting open shield machine | |
| JP2759416B2 (en) | Open shield machine | |
| JP2819224B2 (en) | Reaction force support structure for shaft excavator | |
| JPS60109497A (en) | Grips in tunnel boring machines | |
| JPS6145037B2 (en) | ||
| JPH07269275A (en) | How to build an underground space | |
| JP2573881B2 (en) | Tunnel construction method and its excavation equipment | |
| JP4374517B2 (en) | Tunnel construction method | |
| JPS5914512Y2 (en) | Temporary earth retention device | |
| JPH0535196Y2 (en) | ||
| JPS6338313Y2 (en) | ||
| JPH0988479A (en) | Open shield method | |
| JPS639612Y2 (en) | ||
| JPS61165494A (en) | Open-shielding excavator |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| EXPY | Cancellation because of completion of term |