JPS60151193A - Strength testing method of lng spherical tank - Google Patents
Strength testing method of lng spherical tankInfo
- Publication number
- JPS60151193A JPS60151193A JP579584A JP579584A JPS60151193A JP S60151193 A JPS60151193 A JP S60151193A JP 579584 A JP579584 A JP 579584A JP 579584 A JP579584 A JP 579584A JP S60151193 A JPS60151193 A JP S60151193A
- Authority
- JP
- Japan
- Prior art keywords
- hull
- lng
- tank
- dock
- lng spherical
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Filling Or Discharging Of Gas Storage Vessels (AREA)
Abstract
Description
【発明の詳細な説明】
〔発明の技術分野〕
本発明はLNG運搬船に積込まれるLNG球形タンクの
強度テスト方法に係るものである。DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a method for testing the strength of LNG spherical tanks loaded onto LNG carriers.
この種のL N G運搬船に積込まれるLNG球形タン
クは、建造後にLNG球形タンク1内に真水を張ると共
に、所定圧力を負荷する強度テストが必要である。After construction of the LNG spherical tank to be loaded onto this type of LNG carrier, it is necessary to fill the LNG spherical tank 1 with fresh water and to conduct a strength test by applying a predetermined pressure.
この強度テストを実施するにば、第1図に示す従来法1
のように、予め陸地の工場で製作されたLNG球形タン
ク1を、陸地2に設けたテスI〜施設3によりテストン
た後、船体に積込まれるようになっている。To carry out this strength test, the conventional method 1 shown in Fig.
As shown in the figure, an LNG spherical tank 1 manufactured in advance at a factory on land is tested at a test I to facility 3 installed on land 2, and then loaded onto a ship.
しかし、この従来法Iでは、強度テストに必要なLNG
球形タンク1内に給水する真水4重■が一基当り13o
oo TONとなるため、テスト施設3を含む地盤が沈
下しないための地盤強度を得るためのテスト施設3を建
造することが、場所および;Jスト的に非常に大変であ
るという問題点がある。However, in this conventional method I, the LNG required for the strength test
Four layers of fresh water supplied into the spherical tank 1 is 13o per unit.
oo TON, there is a problem in that it is very difficult to construct the test facility 3 in order to obtain the ground strength to prevent the ground containing the test facility 3 from sinking, in terms of space and construction.
この問題点を解消するために、第2図に示す従来法2の
ように、進水した船体5に複数のL N G球形タンク
1を積込むようになし、このllj 6に厚」二する船
体5上を利用することにより、地盤沈十の問題は解消す
るようにして、L、NG球形タンク1の強度テストを行
うようにする方法もあるか、テストに必要な真水が非常
に多量であるので、−目に使用する水量が給水制限によ
り制限されているため、−基のL N G球形タンク1
内に給水するのに2週間程度を必要とし、例えば第2図
に示すように5基のL N G球形タンク1の強度テス
トおよびテスト後のタンク内の洗浄・乾燥等を含む完了
までに約3ケ月要するため、進水後における引渡前の船
体貼装期間が非常に長期間を要するという問題点があっ
た。In order to solve this problem, as in the conventional method 2 shown in FIG. Is there a way to solve the problem of ground subsidence by using the top of the hull 5 to perform the strength test of the L and NG spherical tanks 1? Since the amount of water used for - is limited by water supply restrictions, - group L N G spherical tank 1
For example, as shown in Figure 2, it takes about two weeks to supply water to the interior of the tank, and for example, as shown in Figure 2, it takes about two weeks to complete the test, including the strength test of the five LNG spherical tanks 1 and the cleaning and drying of the tank interior after the test. Since it takes three months, there was a problem in that the period for applying the stickers to the ship's hull after launch and before delivery was extremely long.
本発明は上述した従来の実情に鑑み、それらの問題点を
解消すべく創案されたものであって、渠内で建造中途の
船体を利用してL N G球形タンクの強度テストを行
うようになし、進水前に1、NG球形タンクの強度テス
トを完了することができるL N G球形タンクの強度
デスト方法を提供することを目的とするものである。The present invention has been devised to solve these problems in view of the above-mentioned conventional situation, and is designed to conduct a strength test of an LNG spherical tank using a half-built hull in a ditch. 1. The purpose of the present invention is to provide a strength test method for LNG spherical tanks that can complete the strength test of NG spherical tanks before launching.
上記目的を達成する本発明のLNG球形タンクの強度テ
スト方法は、複数基のL N G rik形タンクを渠
内で建造中の船体に積込むようになし、このLNG球形
タンク内に給水される真水のff1ffiを、渠内に導
入した海水により浮上する建造中の船体浮力により相殺
させてL N G球形タンクの強度テストを行うことを
特徴とするものである。The strength test method of the LNG spherical tank of the present invention which achieves the above object is to load a plurality of LNG rik type tanks onto a ship being constructed in a conduit, and to carry out water supply into the LNG spherical tank. This test is characterized by performing a strength test of an LNG spherical tank by offsetting the ff1ffi of fresh water by the buoyancy of a ship under construction that is floated by seawater introduced into a conduit.
第3図〜第4図は本発明の一実施例を示すものであって
、本発明にあっては、第3図〜第4図に示すように、複
数基のLNG球形タンク1を渠7内で建造中途の船体8
に積込ようになし、この複数のI、N G球形タンク1
内に給水される真水4の重量を、渠7内に導入した海水
9により浮上する建造中の船体8の浮力により相殺させ
てL N G球形タンク1の強度テスI・を行うように
なっている。FIGS. 3 and 4 show an embodiment of the present invention. In the present invention, as shown in FIGS. Hull 8 currently under construction
These multiple I, N G spherical tanks 1
The strength test I of the LNG spherical tank 1 is now conducted by canceling out the weight of the fresh water 4 supplied into the tank by the buoyancy of the hull 8 under construction, which is floated by the seawater 9 introduced into the conduit 7. There is.
つまり、この建造中の船体8の浮力を、渠7内に導入し
たljσ水9の水深I」と、船体8のバラスI・タンク
11に供給するハラスI・水12との調節により、渠7
内で建造中途の船体8を支える盤木10に加算されるL
NG球形タンク1内の真水4の1Tifflを相殺させ
るようになし、この真水重量の相殺によつ−C,渠7底
の地盤沈下を防止すると共に、盤木10に負荷する重1
ikの安全係数を確保した上、給水制限があるLNG球
形タンク1の強度テストのための真水4の給水を、渠7
内において長期間を要する船体8の建造と並行して行)
ことができる。In other words, the buoyancy of the hull 8 under construction can be adjusted by adjusting the water depth I of ljσ water 9 introduced into the ditch 7 and the ballast I and water 12 supplied to the ballast I and tank 11 of the hull 8.
L added to the board 10 that supports the hull 8 that is currently under construction.
The weight of the fresh water 4 in the NG spherical tank 1 is offset by 1 Tiffl, and by offsetting the weight of the fresh water, -C, the ground subsidence at the bottom of the ditch 7 is prevented, and the weight 1 loaded on the board 10 is
In addition to ensuring the safety factor of ik, fresh water 4 for the strength test of LNG spherical tank 1, which has limited water supply, is supplied to conduit 7.
(conducted in parallel with the construction of hull 8, which requires a long period of time)
be able to.
このため、船体1進水前に複数基のLNG球形タンク1
の強度テストを完了することができる。For this reason, multiple LNG spherical tanks 1 were installed before launching the hull 1.
The strength test can be completed.
また、強度テストの実施にあたっては、給水制限がある
ため、複数基のLNG球形球形タンク1時には真水4の
給水ができないが、この種のLNG球形タンク1を禎込
む船体8には、各L N G球形タンク1毎に独立した
バラストタンク11がそれぞれに設けであるので、真水
4が給水される位置のL N G球形タンク1に対応す
る位置のバラストタンク11内にバラス1へ水12を注
水することにより、渠7内の海水9による建造中途の船
体8浮力を、L N G球形タンク1内の真水4の重量
のみに相殺させながら、船体8の前後および左右の平衡
バランスを確保するようにする。In addition, in carrying out the strength test, due to water supply restrictions, fresh water 4 cannot be supplied at the time of multiple LNG spherical tanks 1, but the hull 8 that houses this type of LNG spherical tanks 1 must be equipped with water for each LNG tank. Since each G spherical tank 1 is provided with an independent ballast tank 11, water 12 is injected into the ballast tank 11 at a position corresponding to the LNG spherical tank 1 at the position where fresh water 4 is supplied. By doing so, the buoyancy of the hull 8 during construction due to the seawater 9 in the conduit 7 is offset only by the weight of the fresh water 4 in the LNG spherical tank 1, and the balance between the front and back and left and right sides of the hull 8 is ensured. Make it.
船体8に積込んだLNG球形タンク1の強度テストは、
船体8の船首および船尾のバルクヘッド13および14
が建造され船体8全体が箱型となった建造中途から開始
することができるため、さらに船体8に船首および船尾
が接続建造される以前に複数個のT、、 N G球形タ
ンク1の強度テストを終了するようにすることにより、
船体8の建造とLNG球形タンクlの強度テストとを並
行して進行さ−Uることができるようになる。The strength test of the LNG spherical tank 1 loaded into the hull 8 was as follows:
Bow and stern bulkheads 13 and 14 of hull 8
Since the construction can be started from the middle of construction when the hull 8 has been constructed and the entire hull 8 has become box-shaped, strength tests of multiple T, N, and G spherical tanks 1 can be performed before the bow and stern are connected to the hull 8 and constructed. By making it terminate,
It becomes possible to proceed with the construction of the hull 8 and the strength test of the LNG spherical tank l in parallel.
したがって、船体8の進水時までには、給水制限のため
に長期間を要するLNG球形タンク10)強度テストを
終了することができるため、進水後におりる引渡前の船
体貼装期間を短縮することができる。Therefore, by the time the hull 8 is launched, the LNG spherical tank 10) strength test, which requires a long period of time due to water supply restrictions, can be completed, thereby shortening the period for attaching the hull after launch and before delivery. can do.
これを要するに本発明によるL N G球形タンクの強
度テスト方法は、複数基のLNG球形タンクを渠内で建
造中の船体に積込むようになし、このL N G l[
Jξ形タンク内に給水される真水の重量を、渠内に導入
した海水により浮上する建造中の船体浮力により相殺さ
せてり、NG球形タンクの強度テスト沿行うようにした
から、建造中の船体の浮力により、渠内で建造中途の船
体を支える盤木に加算される1、NG球形タンク内の真
水の重量を相殺させ、ごの真水重量の相殺によって、渠
内の地盤沈下を防止すると共に盤木に負荷する重量の安
全係数を確保した上、給水制限があるLNG球形タンク
の強度テストのための真水の給水を、渠内において長期
間を要する船体の建造と並行して行うことができる。In summary, the strength testing method for LNG spherical tanks according to the present invention involves loading a plurality of LNG spherical tanks onto a ship being constructed in a ditch, and
The weight of fresh water supplied into the Jξ-shaped tank is offset by the buoyancy of the hull under construction, which floats due to the seawater introduced into the ditch, and the strength test of the NG spherical tank is carried out. The buoyancy of the buoyant force offsets the weight of the fresh water in the NG spherical tank, which is added to the board that supports the hull of the ship in the middle of construction in the culvert. In addition to ensuring a safety factor for the weight loaded on the board, it is possible to supply fresh water for strength testing of LNG spherical tanks, which have limited water supply, in parallel with the long-term construction of the ship's hull in the conduit. .
したがって、船体の進水前にLNG球形タンクの強度テ
ス1を完了することかできるため、進水後における引渡
前の船体1y装期間を短縮することができる。Therefore, it is possible to complete the strength test 1 of the LNG spherical tank before launching the ship, so that the period for installing the ship after launching and before delivery can be shortened.
第1図〜第2図番J従来例を示すもので、第1図は陸地
におりる従来の強度う−ストを示ず横lJi面図、第2
図は海上におLJる従来の強度テストを示ず側面図、第
3図〜第・1図は本発明の一実施例を示すものであって
、第3図は渠内における強度う−ストを示ず側面図、第
4図は第3図の斜視図である。
1・・・LNG球形タンク、4・・・具水、7・・・渠
、8・・・船体、9・・・海水。Figures 1 to 2 show conventional examples.
The figure shows a side view of a conventional strength test conducted on an LJ at sea, Figures 3 to 1 show an embodiment of the present invention, and Figure 3 shows a strength test in a ditch. FIG. 4 is a perspective view of FIG. 3. 1...LNG spherical tank, 4...Water, 7...Drainage, 8...Hull, 9...Seawater.
Claims (1)
積込むようになし、このLNG球形タンク内に給水され
る真水の重量を、渠内に導入した海水により浮上する建
造中の船体浮力により相殺させてLNG球形タンクの強
度テストを行うLNG球形タンクの強度テスト方法。Multiple LNG spherical tanks are loaded onto the hull of a ship under construction in a culvert, and the weight of fresh water supplied into the LNG spherical tanks is used to float the hull under construction using seawater introduced into the culvert. A strength test method for LNG spherical tanks that tests the strength of LNG spherical tanks by offsetting buoyancy.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP579584A JPS60151193A (en) | 1984-01-18 | 1984-01-18 | Strength testing method of lng spherical tank |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP579584A JPS60151193A (en) | 1984-01-18 | 1984-01-18 | Strength testing method of lng spherical tank |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS60151193A true JPS60151193A (en) | 1985-08-09 |
Family
ID=11621011
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP579584A Pending JPS60151193A (en) | 1984-01-18 | 1984-01-18 | Strength testing method of lng spherical tank |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS60151193A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109991094A (en) * | 2019-05-07 | 2019-07-09 | 张化机(苏州)重装有限公司 | A kind of horizontal hydraulic test method of large pressurized vessel |
-
1984
- 1984-01-18 JP JP579584A patent/JPS60151193A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109991094A (en) * | 2019-05-07 | 2019-07-09 | 张化机(苏州)重装有限公司 | A kind of horizontal hydraulic test method of large pressurized vessel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100513252C (en) | Method for loading and unloading cargo from a twin-hull sea-going ship | |
KR100796410B1 (en) | Inundation method using tandem construction method | |
CN101850834A (en) | Semi-submersible type multifunctional jetty | |
CN114787031B (en) | Ship construction process suitable for dry dock non-floating type serial connection process | |
US3837310A (en) | Underwater oil storage | |
GB1218272A (en) | Method and apparatus for constructing a ship | |
GB2187680A (en) | Ocean launching apparatus for space rockets | |
CN110371270A (en) | A kind of product safety that launches a ship plays the method that emersion is refuted | |
CN112078746A (en) | Method for carrying out strength test on ballast tank in dock | |
US3736898A (en) | Device for controlling list and level of pontoon | |
US2406084A (en) | Ship or vessel | |
JPS60151193A (en) | Strength testing method of lng spherical tank | |
US3776167A (en) | Semi-submersible tender | |
US3675606A (en) | Method of constructing marine float structures | |
US3765359A (en) | Apparatus and method of constructing marine float structures | |
US5090346A (en) | Multi-part ship construction system | |
JPH11140893A (en) | Manufacture and launching method for sinking box | |
US3220372A (en) | Submersible mining, lifting and towing barge | |
JPS61155509A (en) | Installation of large-size marine structure | |
JPS59156887A (en) | Method of installing tank in ship body | |
KR100953487B1 (en) | Inundation method using lashing in tandem construction method | |
US2369265A (en) | Sectional ship | |
JPH0514076B2 (en) | ||
US1788824A (en) | Method of determining the center of gravity of ships | |
JPS5813393B2 (en) | Barge for offshore storage tanks |