CN114787031B - Ship construction process suitable for dry dock non-floating type serial connection process - Google Patents

Ship construction process suitable for dry dock non-floating type serial connection process Download PDF

Info

Publication number
CN114787031B
CN114787031B CN202080085969.7A CN202080085969A CN114787031B CN 114787031 B CN114787031 B CN 114787031B CN 202080085969 A CN202080085969 A CN 202080085969A CN 114787031 B CN114787031 B CN 114787031B
Authority
CN
China
Prior art keywords
ship
launch
vessel
dock
seawater
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202080085969.7A
Other languages
Chinese (zh)
Other versions
CN114787031A (en
Inventor
朴江浩
赵成源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hanhua Ocean Co ltd
Original Assignee
Hanhua Ocean Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hanhua Ocean Co ltd filed Critical Hanhua Ocean Co ltd
Publication of CN114787031A publication Critical patent/CN114787031A/en
Application granted granted Critical
Publication of CN114787031B publication Critical patent/CN114787031B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63CLAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
    • B63C1/00Dry-docking of vessels or flying-boats
    • B63C1/08Graving docks

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Ship Loading And Unloading (AREA)
  • Cleaning Or Clearing Of The Surface Of Open Water (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Output Control And Ontrol Of Special Type Engine (AREA)
  • Earth Drilling (AREA)

Abstract

The invention provides a ship building process suitable for a dry dock non-floating type serial process, which comprises the following steps: respectively constructing a plurality of ship segments of the same type or different types in one or two rows in the same dry dock, performing a part of ship hull engineering of the launch ship in a dock adjacent area, and performing a part of ship hull engineering of the launch ship in a dock adjacent area; a step of forcibly injecting water into the part of the launch ship by a pump; a step of causing seawater to flow in by opening a dock gate of the dry dock so that the launch vessel is floated and the part of the launch vessel is not floated; a step of moving the floating launch vessel to the external bank wall of the dock gate; a step of discharging seawater from the dry dock by closing the dock gate; and performing engineering of the remaining hull portion of the partially launched vessel at the same location.

Description

Ship construction process suitable for dry dock non-floating type serial connection process
Technical Field
The present invention relates to a ship construction process for a dry dock non-floating tandem process, which is suitable for constructing a ship of the same type or different types in the same dry dock, and which can not only simultaneously construct a launch ship and a part of the launch ship, but also stably ensure that the launch ship does not float while maintaining the equilibrium of the part of the launch ship when the launch ship is carried out, and which can prevent the launch of the launch ship from being affected by performing forced water injection to different degrees according to the construction steps of the part of the launch ship.
Background
It is known to construct a ship in a dry dock manner in order to construct a large ship efficiently, a ship segment may be constructed in the dry dock and the ship is floated by introducing seawater into the dry dock, thereby being carried out after being lifted to a shore wall.
In addition, a tandem process for simultaneously constructing a launch vessel and a portion of the launch vessel using the available space in the dry dock may be applied.
For example, in the case of a tandem process of a part of a launch vessel to which an oversized container vessel and an oversized crude oil transport Vessel (VLCC) are applied, when seawater is introduced into the interior of a dry dock, it may be unevenly inclined and floated to the stern end side due to buoyancy of a cargo area in which a bulkhead is formed in the part of the launch vessel, so that when the launch vessel is lifted by a tug, it may cause dumping of a support supporting the part of the launch vessel due to rotation of a propeller of the tug and further cause dumping of the part of the launch vessel, thus having a problem that the launch vessel and the part of the launch vessel of the oversized container vessel cannot be simultaneously built.
As a prior art for solving the problems as described above, korean registered patent publication No. 10-0796410 is disclosed as a dipping process applicable to a conventional tandem construction process, including: a step of constructing a ship segment in a dock through a tandem construction process; a step of installing main carrying objects such as a main engine, a tail shaft, an intermediate shaft, a stern section, a binding bridge or a hatch cover and the like in a ship to be immersed; a step of immersing the ship in water to the same position by naturally introducing water into the cargo ballast tanks and a part of the double bottom tanks of the immersed ship when the ship is floating; and a step of constructing a submerged ship after pulling the launch ship; the construction can be completed at the same location without moving the hull by immersing the hull after all the cargo is loaded.
However, in a state where the main cargo is mounted on a part of the launch vessel, the water which flows in to float the launch vessel naturally flows into the cargo ballast tanks and a part of the double bottom tanks, and thus the launch vessel can be launched only after all the main cargo is mounted on the part of the launch vessel, as shown in fig. 1, and therefore, even in a state where the construction of the launch vessel is completed, the lifting time of the launch vessel may be delayed according to the construction steps of the part of the launch vessel, and the water which naturally flows into the dock, that is, the seawater may cause the sinking of the part of the launch vessel, and thus the hull may corrode due to salt and chlorine, and therefore, a pre-engineering or a post-engineering for preventing the hull corrosion may be required to be performed and finally the construction period may be delayed to a problem.
For this reason, there is a need for an improved in-line process that can hoist a launch vessel independently of the construction steps of a portion of the launch vessel, thereby minimizing construction delays and minimizing hull corrosion caused by the flooding of a portion of the launch vessel.
Disclosure of Invention
The technical problem to be achieved by the concept of the invention is to provide a ship construction process applicable to a dry dock non-floating tandem process, which can hoist a launch ship irrespective of the construction steps of a part of the launch ship, thereby minimizing a delay in construction period and minimizing corrosion of the hull caused by the soaking of the part of the launch ship.
To achieve the above object, the present invention provides a ship construction process adapted to a dry dock non-floating tandem process, comprising: respectively constructing a plurality of ship segments of the same type or different types in one or two rows in the same dry dock, performing a part of ship hull engineering of the launch ship in a dock adjacent area, and performing a part of ship hull engineering of the launch ship in a dock adjacent area; a step of forcibly injecting water into the part of the launch ship by a pump; a step of causing seawater to flow in by opening a dock gate of the dry dock so that the launch vessel is floated and the part of the launch vessel is not floated; a step of moving the floating launch vessel to the external bank wall of the dock gate; a step of discharging seawater from the dry dock by closing the dock gate; and performing engineering of the remaining hull portion of the partially launched vessel at the same location.
Wherein fresh water or seawater may be forcibly injected into the interior of the cargo hold formed with the bulkhead in the partial launch vessel by the pump in order to offset the buoyancy of the partial launch vessel and maintain equilibrium with the center of gravity (COG).
In this case, when the deck house and the nacelle cover of the partially launched vessel are mounted, water may be forcibly injected into a pair of left and right Side Crude Oil (SCO) tanks adjacent to the nacelle cover, respectively, and when the deck house and the nacelle cover of the partially launched vessel are not mounted, a large amount of water may be forcibly injected into a pair of left and right Side Crude Oil (SCO) tanks adjacent to the nacelle cover, respectively, and the remaining water may be forcibly injected into a pair of left and right oil-water tanks, respectively.
In addition, fresh water or seawater may be forcibly injected into the Side Crude Oil (SCO) tank and the oily water tank.
In addition, when the seawater is forcibly injected, the seawater may be injected after the salt and chlorine are removed by the seawater desalination plant.
Furthermore, it may further include: and executing the hull part engineering of the subsequent ship at the launch position.
In the present invention, it is possible to minimize corrosion of a ship hull while preventing a part of a launch vessel from floating by forcibly injecting fresh water or seawater alone, and when constructing vessels of the same type or different types in the same dry dock, it is possible to construct not only a launch vessel and a part of a launch vessel at the same time, but also stably secure a part of a launch vessel from floating while maintaining an equilibrium state thereof when the launch vessel is carried out, and it is possible to prevent an influence on the launch of a launch vessel by forcibly injecting water to different extents according to a construction step of a part of a launch vessel, thereby continuously constructing a large-scale construction vessel while shortening a construction period by a serial process.
Drawings
Fig. 1 illustrates a flooding process suitable for use in a tandem construction process based on the prior art.
Fig. 2 illustrates a sequence diagram of a ship construction process for a dry dock non-floating tandem process, to which embodiments of the present invention are applied.
Fig. 3 schematically illustrates a dry dock implementing the ship building process of fig. 2 for which the dry dock non-floating tandem process is applicable.
Fig. 4 illustrates a stern cross-sectional structure of a portion of the launch vessel of fig. 2 for a vessel construction process employing a dry dock non-floating tandem process.
Fig. 5 illustrates an engineering flow diagram of the non-floating tandem process in the dry dock of fig. 3, respectively.
Detailed Description
Embodiments of the present invention will be described in detail below with reference to the accompanying drawings so that those having ordinary skill in the art to which the present invention pertains can easily practice the present invention. The present invention may be realized in many different forms and is not limited to the embodiments described herein.
Referring to fig. 2, the ship construction process according to the embodiment of the present invention, which is applicable to the dry dock non-floating tandem process, generally includes a hull engineering and hull part engineering performing step S110, a forced water injection step S120, a seawater inflow step S130, a launch ship carrying-out step S140, a seawater draining step S150, a remaining hull part engineering performing step S160, and a subsequent ship hull part engineering performing step S170, and is characterized in that continuous tandem construction of a ship can be achieved.
Next, a ship construction process applicable to a dry dock non-floating tandem process according to an embodiment of the present invention will be described in detail with reference to fig. 2 to 5.
First, in the hull engineering and hull part engineering execution step S110, as shown in fig. 3 and 5 (a), a plurality of ship segments of the same type of ship or different types of ships are respectively built in one or two columns in the same dry dock, a hull engineering of a part of the launch ship is executed in a dock (dock head) adjacent area, and a hull part engineering of the launch ship is executed in a dock gate (dock) adjacent area.
The launch vessel or a part of the launch vessels are not particularly limited, and may be, for example, a very large crude oil carrier (VLCC; very Large Crude oil Carrier), a very large container vessel, a Liquefied Natural Gas (LNG) carrier, a Liquefied Natural Gas (LNG) power vessel, or a large construction vessel of a chemical product carrier, etc., and the launch vessels having a total length (LOA; length Of Overall) of about 400m and a part of the launch vessels having a total length of about 120m may be constructed simultaneously in one or two lines in the same dry dock having a length of 500m or more.
For reference, the interval between the dock and a part of the launch vessel and the distance between the dock gate and the launch vessel need to be maintained at an interval of about 5m, and the interval between a part of the launch vessel and the launch vessel needs to be maintained at an interval of about 10 m.
Next, in the forced water injection step S120, as shown in fig. 3, water can be injected into the interior of the partially launched vessel by the pump P, thereby ensuring that the bow of the partially launched vessel, i.e., the partially launched vessel, does not float due to its own buoyancy when seawater flows into the interior of the dock.
That is, in order to offset buoyancy of a part of the launch vessel under the density of seawater varying according to water temperature and salinity as well as water pressure and maintain equilibrium with a center of gravity (COG), fresh water or seawater is forcibly injected into the interior of a tank (cargo tank) formed with a bulkhead of the part of the launch vessel by a pump P, thereby ensuring that the part of the launch vessel remains in place and is prevented from floating from a support (support) for preventing the section of the vessel from being toppled.
Further, referring to fig. 4, in the case of carrying a deckhouse (D/H) a and a cabin shed (engine House) B of a part of a launch vessel at the time of forced water injection, water is forcibly injected into a pair of left and right Side Crude Oil (SCO) cabins (SCO TK (P), (S)) adjacent to a bow part of the launch vessel, that is, the cabin shed B, respectively, and, for example, a very large crude oil carrier (VLCC), it is possible to prevent the bow part of the launch vessel from floating up by injecting water of about 8000 tons, while maintaining the balance with the gravity Center (COG) in which the center of gravity tends to the rear end of the stern, thereby avoiding the phenomenon of partial floating up due to unbalanced inclination of the front and rear parts of the stern. For example, 8000 tons of No.5SCO TK (P) may be injected and 7,950 tons of No.5SCO TK (S) may be injected, thereby adding up to 15,950 tons.
Alternatively, in the case of the deck house a and the cabin shed B of the launch vessel without the loading portion, the gravity Center (COG) tends to be at a lower level than the stern rear end when loaded, and therefore, most of the water is forcibly injected into the pair of left and right crude oil (SCO) tanks adjacent to the cabin shed B, and the surplus water is forcibly injected into the pair of left and right oil-water tanks (chop TK (P), (S)), respectively, and the phenomenon of partial floating due to unbalanced inclination of the front and rear portions of the stern is avoided by injecting the pair of left and right SCO tanks with about 7000 tons, respectively, and about 800 tons, respectively, for example, to the oversized crude oil carrier (VLCC), while preventing the stern from floating. For example, 7100 tons of water can be injected into No.5SCO TK (P, S) and 860 tons of water can be injected into SLOP TK (P), and 750 tons of water can be injected into SLOP TK (S), so as to add 15810 tons in total.
Wherein fresh water or seawater can be forcibly injected into a Side Crude Oil (SCO) tank and a dirty oil water tank by a pump P, and water can be injected after salt and chlorine are removed by a seawater desalination device in order to minimize corrosion of a hull due to salt and chlorine when the seawater is forcibly injected.
For this reason, it is possible to forcibly inject fresh water or seawater in various ways according to the construction steps of the partial launch vessel, thereby stably ensuring that the partial launch vessel does not float in a state where equilibrium thereof is maintained, and minimizing a construction period delay because it does not affect the launch of the launch vessel.
For reference, although the case where the pump P is mounted in a dry dock is illustrated, water may be forcibly injected by a part of a water-launched vessel, and the oil-and-sewage tank is a tank for storing an oily mixture of oil and seawater formed after washing various tanks or waste oil flowing out from an engine compartment, and is disposed in order to prevent marine pollution due to oil stains and reduce loss of cargo.
Further, in the seawater inflow step S130, as shown in (b) of fig. 5, the seawater can be flowed in by opening the dock gate of the dry dock and the launch vessel is floated, and a part of the launch vessel is maintained in a non-floating state at the original position.
Further, in the launch ship carrying-out step S140, as shown in fig. 3 and (c) in fig. 5, the floating launch ship is hoisted to the external wall of the dock gate by a tug.
Further, in the sea water draining step S150, sea water is drained from the dry dock by closing the dock gate.
Further, in the remaining hull part engineering execution step S160, as shown in (d) of fig. 5, fresh water or seawater forcibly injected into a part of the launch vessel is discharged, and the remaining hull part engineering of the part of the launch vessel is executed at the same position where the water is immersed, thereby completing the construction of the launch vessel.
Further, in the subsequent ship hull part engineering execution step S170, as shown in fig. 5 (d), the subsequent ship hull part engineering is executed at the carry-out position of the launch ship.
By this, with the construction of the ship construction process to which the dry dock non-floating tandem process is applied as described above, compared with the prior art in which the part of the launch ship carrying the main carrying object is submerged by natural inflow of seawater in order to float the launch ship by the submerged process, the part of the launch ship can be prevented from floating while minimizing corrosion of the hull by forcibly injecting fresh water or seawater alone, and when the same type or different types of ships are constructed in the same dry dock, not only the launch ship and the part of the launch ship can be constructed simultaneously, but also the launch ship can be stably ensured not to float in a state where the equilibrium of the part of the launch ship is maintained when the launch ship is carried out, and the effect on the launch of the launch ship can be prevented by forcibly injecting water to a different degree according to the construction steps of the part of the launch ship, and further, the large-scale construction ship can be constructed continuously while shortening the construction period by the tandem process.
In the foregoing, the invention is described in detail with reference to the accompanying drawings. However, the present invention is not limited thereto, and those having ordinary skill in the art to which the present invention pertains may implement various modifications and embodiments within the scope equivalent to the present invention. Accordingly, the true scope of the invention should be defined by the following claims.

Claims (5)

1. A ship building process adapted for a dry dock non-floating tandem process, comprising:
respectively constructing a plurality of ship segments of the same type or different types in one or two rows in the same dry dock, performing a part of ship hull engineering of the launch ship in a dock adjacent area, and performing a part of ship hull engineering of the launch ship in a dock adjacent area;
a step of forcibly injecting water into the partially launched vessel by a pump before the dock gate of the dry dock is opened to allow seawater to flow in;
a step of causing seawater to flow in by opening a dock gate of the dry dock so that the launch vessel is floated and the part of the launch vessel is not floated;
a step of moving the floating launch vessel to the external bank wall of the dock gate;
a step of discharging seawater from the dry dock by closing the dock gate; the method comprises the steps of,
the step of engineering the remaining hull part of the partially launched vessel is performed at the same location,
wherein in the step of forcibly filling water into the interior of the partially launched vessel by means of a pump,
in order to offset buoyancy of the partial launch vessel and maintain equilibrium with the center of gravity, fresh water or seawater is forcibly injected into the interior of the cargo space in which the bulkhead is formed in the partial launch vessel by the pump, and the cargo space and the water injection amount to be forcibly injected with fresh water or seawater are variously determined according to the construction steps of the partial launch vessel.
2. The ship building process adapted for a dry dock non-floating tandem process according to claim 1, wherein:
when the deck house and the cabin shed of the part of the launch ship are mounted, fresh water or seawater is forcibly injected into a pair of left and right crude oil tanks adjacent to the cabin shed.
3. The ship building process adapted for a dry dock non-floating tandem process according to claim 1, wherein:
when the deck house and the cabin shed of the part of the launch ship are not mounted, most fresh water or seawater is forcibly injected into a pair of left and right crude oil tanks adjacent to the cabin shed, and the rest fresh water or seawater is forcibly injected into a pair of left and right oil sewage tanks.
4. A ship building process adapted for a dry dock non-floating tandem process according to claim 2 or claim 3, wherein:
when the seawater is forcibly injected, the seawater is injected after the salt and chlorine are removed by the seawater desalination device.
5. The ship building process for a dry dock non-floating tandem process according to claim 1, further comprising:
and executing the hull part engineering of the subsequent ship at the launch position.
CN202080085969.7A 2019-12-26 2020-09-02 Ship construction process suitable for dry dock non-floating type serial connection process Active CN114787031B (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
KR1020190174629A KR102157346B1 (en) 2019-12-26 2019-12-26 Method for shipbuilding by adapting non-floating tandem in dry dock
KR10-2019-0174629 2019-12-26
PCT/KR2020/011740 WO2021132840A1 (en) 2019-12-26 2020-09-02 Shipbuilding method employing non-floating tandem method in dry dock

Publications (2)

Publication Number Publication Date
CN114787031A CN114787031A (en) 2022-07-22
CN114787031B true CN114787031B (en) 2024-03-22

Family

ID=72670304

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202080085969.7A Active CN114787031B (en) 2019-12-26 2020-09-02 Ship construction process suitable for dry dock non-floating type serial connection process

Country Status (4)

Country Link
JP (1) JP7341627B2 (en)
KR (1) KR102157346B1 (en)
CN (1) CN114787031B (en)
WO (1) WO2021132840A1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115611367A (en) * 2021-02-22 2023-01-17 中印恒盛(北京)贸易有限公司 Cell type ship bearing circulating water treatment unit
CN113186956B (en) * 2021-04-01 2022-11-29 中交第四航务工程局有限公司 Construction method for floating installation of dock gate and construction method for floating deposition of dock gate
CN114435554B (en) * 2022-03-17 2022-11-08 广船国际有限公司 Semi-ship floating method
CN114753297B (en) * 2022-04-11 2024-02-02 中国铁建港航局集团有限公司 Novel dock wall connecting structure and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3955523A (en) * 1974-03-20 1976-05-11 Nippon Kokan Kabushiki Kaisha Method of continuously building ships
KR100796410B1 (en) * 2006-12-29 2008-01-21 현대중공업 주식회사 Inundation method using tandem construction method
CN101357673A (en) * 2008-04-30 2009-02-04 大连船舶重工集团有限公司 Dock non-dry type multi-boat construction method
KR20100008086A (en) * 2008-07-15 2010-01-25 삼성중공업 주식회사 Tandem construction method for a liquid cargo carrier using compulsion inundation
KR20100062131A (en) * 2008-12-01 2010-06-10 삼성중공업 주식회사 Ballast water supplying apparatus and ship wiht the same
CN101920766A (en) * 2010-05-14 2010-12-22 蓬莱中柏京鲁船业有限公司 Shipbuilding method
CN103754323A (en) * 2014-02-14 2014-04-30 南通中远川崎船舶工程有限公司 Mid-series building method of large ship
KR20150036222A (en) * 2012-07-19 2015-04-07 재팬 마린 유나이티드 코포레이션 Ship
CN208630806U (en) * 2018-07-26 2019-03-22 江苏扬子鑫福造船有限公司 Quick integral shift falls pier two and half and floats ship structure

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008143281A (en) * 2006-12-07 2008-06-26 Minami Nippon Zosen Kk Construction system of ship or the like
JP4759620B2 (en) 2006-12-29 2011-08-31 ヒュンダイ ヘビー インダストリーズ カンパニー リミテッド Inundation method applied to tandem construction method
SE0700759L (en) 2007-03-26 2008-09-27 Wallenius Marine Ab Method for having a ship's hull manufactured, and a ship's hull thus manufactured
KR20120107587A (en) 2011-03-22 2012-10-04 현대중공업 주식회사 The specialized method for making shorten the quay working time

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3955523A (en) * 1974-03-20 1976-05-11 Nippon Kokan Kabushiki Kaisha Method of continuously building ships
KR100796410B1 (en) * 2006-12-29 2008-01-21 현대중공업 주식회사 Inundation method using tandem construction method
CN101356091A (en) * 2006-12-29 2009-01-28 现代重工业株式会社 Inundation method used in tandem shipbuilding process
CN101357673A (en) * 2008-04-30 2009-02-04 大连船舶重工集团有限公司 Dock non-dry type multi-boat construction method
KR20100008086A (en) * 2008-07-15 2010-01-25 삼성중공업 주식회사 Tandem construction method for a liquid cargo carrier using compulsion inundation
KR20100062131A (en) * 2008-12-01 2010-06-10 삼성중공업 주식회사 Ballast water supplying apparatus and ship wiht the same
CN101920766A (en) * 2010-05-14 2010-12-22 蓬莱中柏京鲁船业有限公司 Shipbuilding method
KR20150036222A (en) * 2012-07-19 2015-04-07 재팬 마린 유나이티드 코포레이션 Ship
CN103754323A (en) * 2014-02-14 2014-04-30 南通中远川崎船舶工程有限公司 Mid-series building method of large ship
CN208630806U (en) * 2018-07-26 2019-03-22 江苏扬子鑫福造船有限公司 Quick integral shift falls pier two and half and floats ship structure

Also Published As

Publication number Publication date
KR102157346B1 (en) 2020-09-18
WO2021132840A1 (en) 2021-07-01
JP7341627B2 (en) 2023-09-11
CN114787031A (en) 2022-07-22
JP2023504152A (en) 2023-02-01

Similar Documents

Publication Publication Date Title
CN114787031B (en) Ship construction process suitable for dry dock non-floating type serial connection process
KR100796410B1 (en) Inundation method using tandem construction method
KR100552939B1 (en) Automatic ballast system using tubes and method for operating the same
SE7707627L (en) VESSELS FOR THE TRANSPORT OF PRAMS, BARRIERS OR SIMILAR MOVABLE LOADS
CN103228531B (en) The method of loading boats and ships and this loading boats and ships of loading and unloading
KR100914350B1 (en) Tank hydro test method a period of dock stage using buoyancy of half diving state
KR102627020B1 (en) How to control trim on a transport vessel without seawater ballast
US20050163572A1 (en) Floating semi-submersible oil production and storage arrangement
CN105015705A (en) Ballast-water-free ship and operating method thereof
KR101302037B1 (en) Floating dock
JP2005324120A (en) Ballast water treatment method and apparatus, and float structure having ballast water treatment function
KR100923405B1 (en) System scaffolding construct method for LNG carrier hold on dry dock
CN202244010U (en) Ship structure without ballast water
KR20100082979A (en) The method of building two ships on a floating dock
US5301625A (en) Marine construction
JP6992942B2 (en) Bulk carrier
KR20210124837A (en) Method on tandem of launching ship in dry-dock by using buoyancy structure-combined keel block having added buoyancy
KR20150049808A (en) Sea structure launching method to use barge
CN102372075B (en) Unballast water ship structure and operation method thereof
KR20210002004U (en) A vessel equipped with ballast tanks of pipe structure
KR101024553B1 (en) Method for constructing ship
CN213620178U (en) Floating dock with transportation function
KR20100008086A (en) Tandem construction method for a liquid cargo carrier using compulsion inundation
KR101251917B1 (en) Barge ship of marine fishing ground
KR101807600B1 (en) Construction method for fpu on floating facility

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: Geoje, Gyeongsangnam-do, South Korea

Applicant after: Hanhua Ocean Co.,Ltd.

Address before: Geoje, Gyeongsangnam-do, South Korea

Applicant before: DAEWOO SHIPBUILDING & MARINE ENGINEERING Co.,Ltd.

GR01 Patent grant
GR01 Patent grant