JPS60126410A - Delivery type ocean bridge construction method - Google Patents

Delivery type ocean bridge construction method

Info

Publication number
JPS60126410A
JPS60126410A JP23528383A JP23528383A JPS60126410A JP S60126410 A JPS60126410 A JP S60126410A JP 23528383 A JP23528383 A JP 23528383A JP 23528383 A JP23528383 A JP 23528383A JP S60126410 A JPS60126410 A JP S60126410A
Authority
JP
Japan
Prior art keywords
bridge girder
bridge
movable
permanent
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP23528383A
Other languages
Japanese (ja)
Other versions
JPH0336082B2 (en
Inventor
太田 統士
高橋 秀吉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TOMOEGUMI IRON WORKS
TOMOEGUMI TEKKOSHO KK
Original Assignee
TOMOEGUMI IRON WORKS
TOMOEGUMI TEKKOSHO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TOMOEGUMI IRON WORKS, TOMOEGUMI TEKKOSHO KK filed Critical TOMOEGUMI IRON WORKS
Priority to JP23528383A priority Critical patent/JPS60126410A/en
Publication of JPS60126410A publication Critical patent/JPS60126410A/en
Publication of JPH0336082B2 publication Critical patent/JPH0336082B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、海上に構築するシーバースと陸岸の工場・
倉庫等との間に架設する荷役運搬用連絡橋等の施工方法
である繰出し式海上ブリッジ工法に関する。
[Detailed Description of the Invention] (Industrial Application Field) This invention is applicable to sea berths built on the sea and factories/factories on land.
This article relates to the rolling-out marine bridge construction method, which is a construction method for connecting bridges for cargo handling and transportation constructed between warehouses, etc.

(従来技術) 従来、海上に構築したシーバースと陸岸とをつなぐ荷役
運搬用の連絡橋の施工は、菫す海底地盤上lこ杭を打設
して下部工を構築した後、手延ベニ法、押出し工法等に
より橋桁を架設して行っていた。
(Prior art) Conventionally, the construction of a connecting bridge for cargo handling and transportation connecting a sea berth built on the sea and the shore was done by driving piles on the seabed ground to build the substructure, and then using hand-rolled plywood. Bridge girders were erected using methods such as method and extrusion method.

しかし、いずれの工法も上部工の施工を行う前に、菫ず
海上用杭打機等により下部工を施工しなければならない
。このため海上用杭打機等の設備が必要であり%菫た下
部工施工に必要な資材を海上運搬しなければならず施工
が面倒であるほか、工期が長く、建設経費もかさんでし
葦うという欠点があった。
However, with either construction method, the substructure must be constructed using a Sumire offshore pile driver, etc. before the superstructure is constructed. For this reason, equipment such as a marine pile driver is required, and the materials necessary for the construction of the substructure, which requires a lot of effort, have to be transported by sea, which makes construction cumbersome, and the construction period is long and construction costs are high. It had the drawback of being reedy.

(発明の目的) この発明は、以上の問題点に鑑み案出されたもので、施
工に必要な設備を最小限のものとし、作業が容易であっ
て、工期の大幅な短縮化および建設経費の低減化を達成
し得る繰出し式海上ブリッジ工法を提供することを目的
とする。
(Purpose of the Invention) This invention was devised in view of the above-mentioned problems, and it minimizes the equipment necessary for construction, makes the work easy, and significantly shortens the construction period and construction costs. The purpose of the present invention is to provide a rolling-out offshore bridge construction method that can reduce the

(発明の構成) この発明の繰出し式海上ブリッジ工法は、少なくとも2
径間にわたる作業用可動橋桁を設け、その移動方向端部
に垂直方向上下動自在の仮設柱をMすると共に該可動橋
桁上に杭打機を載置し、反対側端部にすでに架設した本
設橋桁上に移動自在に載置された本設用橋桁の端部を連
結し、既設の本設杭に沿ってその可動橋桁 を所定長さ
送り出し、仮設柱を支持地盤上に当接させて可動橋桁の
先端部を支持した後、該端部近傍に前H上杭打機を移動
させ本設杭を打設して橋脚部を設け、送り出した可動橋
桁と既設の本設橋桁との間に前記載置された本設橋桁を
吊り降ろして連結固定し、以下順次同様の作業を繰返し
て構築し、最後は繰出した可動橋桁をそのま丈固定して
本設橋桁として用いることを特徴と(5) している。
(Structure of the Invention) The retractable offshore bridge construction method of this invention comprises at least two
A movable bridge girder for work spanning a span is provided, a temporary column that can move up and down in the vertical direction is installed at the end of the movable bridge girder, and a pile driver is placed on the movable bridge girder, and the pile driver that has already been erected is installed at the opposite end. The ends of the permanent bridge girder placed movably on the construction bridge girder are connected, the movable bridge girder is sent out a predetermined length along the existing permanent pile, and the temporary pillar is brought into contact with the supporting ground. After supporting the tip of the movable bridge girder, move the front H upper pile driver to the vicinity of the end and drive the permanent pile to establish the bridge pier, and then install the bridge between the sent-out movable bridge girder and the existing permanent bridge girder. The main bridge girders placed above are lowered and connected and fixed, and the same work is repeated sequentially to construct the bridge.Finally, the movable bridge girder that has been extended is fixed to the same length and used as the permanent bridge girder. (5) Yes.

以上の構成において、本設杭打設作業と本設用橋桁の架
設・連結固定作業とは一連の作業であるので、どちらを
先に行ってもかまわない。
In the above configuration, the permanent pile driving work and the erection and connection fixing work of the permanent bridge girder are a series of works, so it does not matter which one is performed first.

菫た、可動橋桁上に載置する杭打機は、可動橋桁上を移
動自在なものでも、可動橋桁移動方向端部に固定したも
のでもよい。
The pile driver placed on the movable bridge girder may be movable on the movable bridge girder or may be fixed at the end of the movable bridge girder in the moving direction.

(実 施 例) 以下、この発明を図面に示す実施例に基いて説明する。(Example) The present invention will be explained below based on embodiments shown in the drawings.

図面第1図はこの発明の実施例の側面図であり、可動橋
桁1の移動中の状態を示したものである。
FIG. 1 is a side view of an embodiment of the present invention, showing the movable bridge girder 1 in a moving state.

トラスで組菫れた可動橋桁1は5箇所の橋脚2で支持さ
れる2径間橋であって、両端部は橋脚2より張出してお
り片持ち支持されている。
A movable bridge girder 1 assembled with trusses is a two-span bridge supported by five piers 2, and both ends protrude from the piers 2 and are supported in a cantilevered manner.

橋脚2は複数の本設杭5(図においては4本)と支持梁
4と連結パネル21とから構築されており、第8図に示
すように複数のローラー5により橋軸方向移動自在に可
動橋桁1を支持して(4) いる。
The pier 2 is constructed from a plurality of permanent piles 5 (four in the figure), a support beam 4, and a connecting panel 21, and is movable in the bridge axis direction by a plurality of rollers 5 as shown in FIG. It supports bridge girder 1 (4).

可動橋桁1の移動方向端部およびその近傍位置には垂直
方向上下動自在の仮設柱6,7が設けられている。菫た
可動橋桁1上には移動自在な杭打機8が載置されており
、本設杭5を打設できるようになっている。
Temporary pillars 6 and 7 are provided at the ends of the movable bridge girder 1 in the direction of movement and in the vicinity thereof, which are vertically movable up and down. A movable pile driver 8 is placed on the rounded movable bridge girder 1, and is capable of driving permanent piles 5.

さらにこの可動橋桁1の両端部を橋脚2で支持固定すれ
ば本設橋桁9として使用することもできる。
Furthermore, if both ends of the movable bridge girder 1 are supported and fixed by the piers 2, it can also be used as a permanent bridge girder 9.

以下、この発明の繰出し式海上ブリッジ工法の一行程を
施工順序に従って説明する。
Hereinafter, one step of the retractable offshore bridge construction method of the present invention will be explained according to the construction order.

(1) 第1図に示すように、仮設柱6,7を有し杭打
機8を載置した可動橋桁1の反対側端部に2本設吊橋桁
9aの端部を連結する。本設用橋桁9aは架設した本設
橋桁9上に載置されており5本設橋桁側端部をローラー
で支持され橋軸方向へ移動自在である。
(1) As shown in FIG. 1, the end of the two-piece suspension bridge girder 9a is connected to the opposite end of the movable bridge girder 1, which has the temporary columns 6 and 7 and on which the pile driver 8 is mounted. The permanent bridge girder 9a is placed on the constructed permanent bridge girder 9, and its five-piece bridge girder side end is supported by rollers and is movable in the bridge axis direction.

(2) 次に#!2図に示すように、本設用橋桁9aを
連結した可動橋桁1を、既設の本設杭5に沿って所定長
さ送り出し、仮設柱6,7を下方へおろして支持地盤上
に当接させて可動橋桁1の端部を支持する。
(2) Next #! As shown in Fig. 2, the movable bridge girder 1 connected to the permanent bridge girder 9a is sent out a predetermined length along the existing permanent piles 5, and the temporary columns 6 and 7 are lowered to come into contact with the supporting ground. to support the end of the movable bridge girder 1.

(5) そして第5図に示すように可動橋桁1の端部近
傍に前記杭打機8を移動させ1本設杭3をj願人打設し
く図においては4本)、さらに連結パネル21を固定し
て橋脚部2を設ける。
(5) Then, as shown in FIG. 5, the pile driver 8 is moved to the vicinity of the end of the movable bridge girder 1, and one pile 3 is driven (four in the figure), and the connecting panel 21 is driven. A bridge pier part 2 is provided by fixing.

(4)最後に送り出した可動橋桁1と既設の本設橋桁9
との間に前記載置された本設用橋桁9aをクレーン等で
吊り降ろし、連結固定した後、上部に新たな本設用橋桁
を載置する。
(4) The last sent out movable bridge girder 1 and the existing permanent bridge girder 9
After lifting and lowering the permanent bridge girder 9a placed above with a crane or the like and connecting and fixing it, a new permanent bridge girder is placed on top.

なお、既設の本設用橋桁9a上にはプレストレスト・コ
ンクリート、プレキャスト・コンクリート等で床版10
を構築する。
In addition, the deck slab 10 is made of prestressed concrete, precast concrete, etc. on the existing permanent bridge girder 9a.
Build.

ところで、可動橋桁1に取付けた仮設柱6゜7は鋼管等
から形成されており、第5図に示すように側方にはみぞ
形影状のロッキングレール11が1対付設されていて、
所定間隔をおいてピン嵌入用の長穴12が穿設されてい
る。そして仮設柱6は桁張出しs15と支持枠14とで
By the way, the temporary columns 6.7 attached to the movable bridge girder 1 are made of steel pipes, etc., and as shown in FIG. 5, a pair of groove-shaped rocking rails 11 are attached to the sides.
Elongated holes 12 for pin insertion are bored at predetermined intervals. The temporary pillar 6 is made up of a girder overhang s15 and a support frame 14.

仮設柱7は可動橋桁1内側部と支持枠14とでそれぞれ
支持されている。
The temporary pillar 7 is supported by the inner side of the movable bridge girder 1 and the support frame 14, respectively.

図面第6図は可動橋桁1の移動方向端部に取付けた仮設
柱6の一実施例を示す側面図であり。
FIG. 6 is a side view showing an embodiment of the temporary pillar 6 attached to the end of the movable bridge girder 1 in the moving direction.

第7図はそのI−1線断面図である。桁張出し部15の
上部には油圧ステイ15が、支持桁14対向部にはロッ
キング部材22がそれぞれ設けられており、仮設柱6の
上下動および任意位置での保持を自在に行うことができ
るようになっている。なお、実施例において油圧ステイ
15は、支持リング16%ロッキングピン17、油圧シ
リンダ18.ロッキングシリンダ19、硬質ゴム緩衝材
20で構成されている。
FIG. 7 is a sectional view taken along line I-1. A hydraulic stay 15 is provided on the upper part of the girder overhang 15, and a locking member 22 is provided on the opposite part of the support girder 14, so that the temporary column 6 can be freely moved up and down and held at any position. It has become. In addition, in the embodiment, the hydraulic stay 15 includes a support ring 16%, a locking pin 17, a hydraulic cylinder 18. It is composed of a locking cylinder 19 and a hard rubber cushioning material 20.

なお、仮設柱6,7および本設杭Sを海底地盤に打設す
る場合は、必要によりサイドポンプまたはオーガー等で
予め杭穴を掘削して打設作業を行う。
In addition, when driving the temporary columns 6, 7 and permanent piles S into the seabed ground, if necessary, pile holes are excavated in advance using a side pump or an auger, etc., and the driving work is performed.

図面第6図は橋脚部2における可動橋桁1の横断面図で
ある。本設杭5.5および支持梁4には前述したように
ローラー5が4つ取付けられており、該ローラー5を介
して橋軸方向移動(7) 自在に可動橋桁1が取付けられている。
FIG. 6 is a cross-sectional view of the movable bridge girder 1 at the bridge pier 2. As mentioned above, four rollers 5 are attached to the permanent piles 5.5 and the support beams 4, and the movable bridge girder 1 is attached via the rollers 5 so as to be freely movable (7) in the bridge axis direction.

図面第9図は同じく橋脚部2における横断面図であって
5本設橋桁9を架設した状態を示しており、第10図は
その側面図であり、杭5と杭3の間は、予め工場で製作
された水平剛性を高める連結パネル21で固定されてい
る。図示したように必要により床版10上を覆うコルゲ
ートチューブ23を設ければ、運搬される荷役への波・
風等の外力の影響を最少限に抑えることができる。前記
構築した本設橋桁上にコルゲートチューブ25を順次設
けていくことはいう才でもない。
Figure 9 of the drawing is a cross-sectional view of the bridge pier 2, showing a state in which five bridge girders 9 have been erected, and Figure 10 is a side view thereof. It is fixed with a connecting panel 21 manufactured at the factory to increase horizontal rigidity. As shown in the figure, if a corrugated tube 23 is provided to cover the floor slab 10 if necessary, waves and
The influence of external forces such as wind can be minimized. It is no secret to sequentially install the corrugated tubes 25 on the constructed permanent bridge girder.

(発明の効果) この発明は以上の構成からなり1次のような効果を得る
ことができる。
(Effects of the Invention) The present invention has the above configuration and can obtain the following effects.

できるので、海上用杭打機等が不要であり、資材を海上
運搬する必要もない。
Therefore, there is no need for a marine pile driver, etc., and there is no need to transport materials by sea.

■ 可動橋桁を送り出す際、同時に本設用橋桁(8) を繰出して施工を行うので、作業の効率がよい口 ■ 可動橋桁は本設橋桁として使用することもできる。■ When sending out the movable bridge girder, at the same time, the permanent bridge girder (8) Since construction is carried out by drawing out a ■ Movable bridge girders can also be used as permanent bridge girders.

■ 上述した理由により、施工を容易に行うことができ
、同時に工期の大幅な短縮化、建設経費の低減化を達成
できる。
■ For the reasons mentioned above, construction can be carried out easily, and at the same time, the construction period can be significantly shortened and construction costs can be reduced.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第5図はこの発明の実施例を示す側面図、#!
4図は#!5図の平面図、第5図は仮設柱の斜視図、第
6図は可動橋桁に取付けた仮設柱の側面図、第7図は第
6図の1−1線断面図、第8図は橋脚部における可動橋
桁の横断WJ図。 #I9図は同じく橋脚部における本設橋桁の横断面図、
@10図は第9図の側面図である。 1・・可動橋桁、2・・橋脚部、3・・本設杭、4・・
支持梁、5・・ローラー、6.7・・仮設柱、8・・杭
打機、9・・本設橋桁、10壷・床版、11・・ロッキ
ングレール、12噂・長穴、1i・・張出し部、14・
・支持枠。 15・・油圧スティ、16・・支持リング。 17・・ロッキングピン、18・・油圧シリンダ、19
・・ロッキングシリンダ、20・・緩衝材、21・・連
結パネル、22・・ロッキング部材、25・・コルゲー
トチューブ。
FIGS. 1 to 5 are side views showing an embodiment of the present invention, #!
Figure 4 is #! Figure 5 is a plan view, Figure 5 is a perspective view of the temporary pillar, Figure 6 is a side view of the temporary pillar attached to the movable bridge girder, Figure 7 is a sectional view taken along the line 1-1 in Figure 6, and Figure 8 is a Cross-sectional WJ diagram of the movable bridge girder at the bridge pier. Figure #I9 is a cross-sectional view of the permanent bridge girder at the pier,
@Figure 10 is a side view of Figure 9. 1. Movable bridge girder, 2. Pier, 3. Permanent pile, 4.
Support beam, 5...roller, 6.7...temporary column, 8...pile driver, 9...permanent bridge girder, 10 pot/slab, 11...rocking rail, 12 rumor/elongated hole, 1i...・Overhanging part, 14・
・Support frame. 15...Hydraulic stay, 16...Support ring. 17... Locking pin, 18... Hydraulic cylinder, 19
... Locking cylinder, 20.. Cushioning material, 21.. Connection panel, 22.. Locking member, 25.. Corrugate tube.

Claims (1)

【特許請求の範囲】[Claims] (1)少なくとも2径間にわたる作業用可動橋桁を設け
、その移動方向端部に画直方向上下動自在の仮設柱を有
すると共に該可動橋桁上に杭打機を載置し、反対側端部
にすでに架設した本設橋桁上に移動自在に載置された本
設用橋桁の端部を連結し、既設の本設杭に沿ってその可
動橋桁 を所定長さ送り出し、仮設柱を支持地盤上に尚
接させて可動橋桁の先端部を支持した後、該端部近傍に
前1已杭打機を移動させ本設杭を打設して橋脚部を設け
、送り出した可動橋桁と既設の本設橋桁との間に前記載
置された本設橋桁を吊り降ろして連結固定し、以下順次
同様の作業を繰返して構築していくことを特徴とする繰
出し式海上ブリッジ工法。
(1) Provide a movable bridge girder for work over at least two spans, have a temporary column at the end of the moving direction that can move up and down in the vertical direction, and place a pile driver on the movable bridge girder, and at the opposite end The ends of the permanent bridge girders that are movably placed on the permanent bridge girders that have already been erected are connected, the movable bridge girder is sent out a predetermined length along the existing permanent piles, and the temporary columns are placed on the supporting ground. After supporting the tip of the movable bridge girder in contact with the bridge, the pile driver was moved one foot in front of the end and the permanent pile was driven to form the bridge pier, and the movable bridge girder and the existing main A floating offshore bridge construction method characterized by suspending and connecting and fixing the main bridge girder placed between the bridge girder and the bridge girder, and building the bridge by repeating the same steps in sequence.
JP23528383A 1983-12-14 1983-12-14 Delivery type ocean bridge construction method Granted JPS60126410A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23528383A JPS60126410A (en) 1983-12-14 1983-12-14 Delivery type ocean bridge construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23528383A JPS60126410A (en) 1983-12-14 1983-12-14 Delivery type ocean bridge construction method

Publications (2)

Publication Number Publication Date
JPS60126410A true JPS60126410A (en) 1985-07-05
JPH0336082B2 JPH0336082B2 (en) 1991-05-30

Family

ID=16983803

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23528383A Granted JPS60126410A (en) 1983-12-14 1983-12-14 Delivery type ocean bridge construction method

Country Status (1)

Country Link
JP (1) JPS60126410A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100449498B1 (en) * 2002-05-07 2004-09-22 주식회사 한진중공업 Heavy truss building method
JP6034531B1 (en) * 2016-08-03 2016-11-30 ヒロセ株式会社 Construction method of simple temporary bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100449498B1 (en) * 2002-05-07 2004-09-22 주식회사 한진중공업 Heavy truss building method
JP6034531B1 (en) * 2016-08-03 2016-11-30 ヒロセ株式会社 Construction method of simple temporary bridge

Also Published As

Publication number Publication date
JPH0336082B2 (en) 1991-05-30

Similar Documents

Publication Publication Date Title
CN108729354B (en) Downstream bridge movable formwork and construction method thereof
CN111851313A (en) Pile-driving bridge erecting construction all-in-one machine and construction method thereof
CN112695696A (en) Integrated construction equipment for superstructure of high-pile wharf and construction method thereof
CN101324054B (en) Incremental launching positioning construction method of bridge subsection girder temporary pier
CN114457668A (en) Large-span spatial special-shaped arch rib flying-swallow type basket steel box arch bridge and rapid construction method
US4080916A (en) Maritime platform assemblies
CN112342915B (en) Construction method for gantry hoisting beam of overhead track
CN103806374B (en) The overall track erection supplying system of assembly type steel bridge on highway and erection push technique
US4662019A (en) Method of erecting a cable stayed bridge
CN110820519A (en) Tunnel arch bridge convenient for rapid construction and construction method thereof
CN217078829U (en) Position structure of bridge pile foundation and subway tunnel
JPS60126410A (en) Delivery type ocean bridge construction method
US3511057A (en) Erection and construction of multispan bridges and piers
CN215329670U (en) Integrated construction equipment for superstructure of high-pile wharf
CN115961549A (en) Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge
CN212612030U (en) Pile bridge erection construction all-in-one
CN111945572B (en) Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method
CN210086301U (en) Full-composite assembly type subway station prefabricated part mechanized transportation system
CN111926714A (en) Installation method of steel truss girder bridge
JPH0711620A (en) Construction method of artificial ground
CN216891927U (en) Large-span double-layer combined construction steel truss arch bridge
CN220746602U (en) A handle station that is used for mountain area high pier beam slab to erect
CN216512506U (en) Gantry crane system
CN220468517U (en) Overlap joint type continuous overhead beam
CN211395375U (en) Small-interval equal-span support platform longitudinally-transversely-moving quick-beam-outlet upper bridge deck structure